SlideShare a Scribd company logo
1 of 18
Download to read offline
MMAE557 Personal Consulting Project
Analysis of Ball Bearing Manufacturing
Li He A20358122
Xingye Dai A20365915
Instructor: John Cesarone
Apr.30, 2016
Section.1 Client Description
Our client is Weili bearing factory in China which we have ever visited. It’s a company located in
Hebei province and produces many models of bearings. It’s a private company so the factory
has not a large scale of manufacturing and their economic situation does not allow them to hire
a large amounts of workers. In that case, to improve their efficiency of manufacturing system
becomes essential.
In this factory, one of the production workshop was investigated. Totally three lines of work
stations are applied to the manufacturing process of bearings. The first line includes 4 steps
(Turning, heat treatment, grinding and testing) of manufacturing the inner and outer rings. The
second line includes 5 steps (shearing & heading, forging, heating treatment, lapping, testing)
of manufacturing the bearing balls. The third line includes 3 steps (blanking & punching,
forming and testing) of manufacturing the cages. All the machining processes are finished by
corresponding machining equipment and the heat treatments are processing in furnace. The
products are annealed at high temperature and quenched in oil for hardening. The inspections
are done by workers and operators. Each line has two operators, one for testing and the other
one for loading and unloading. The inspection for size and surface finish of balls is carried out
on a sample basis by means of microscopes and other precision equipment. The balls are then
cleaned and packed ready for bearing assembly operations. For inspections of cages, blanking,
punching, forming rivet holes and visual inspection is carried for any deformity. For inner and
outer rings, the diameters are measured. The finished parts of bearings are then manually
transport to assembling station after a batch of parts are produced. Then the assembling
station assembles the parts into bearings automatically. The finally products are then tested by
2 inspectors at next station. For each line, because all the steps are continuous and the
transport time between stations is accounted in load and unload time. the products are
transport so the multiple station cells are not applied to the manufacturing system. Two types
of products are recorded for the entire process and their average time for each procedure were
calculated and listed in following tables.
The classifications of manufacturing system of this factory belongs to ‘’Type II-A B. Type II-A
means it works on multiple automated stations and B means that the cell produces bearing
parts in batch production system.
Section 2: Client analysis
This factory is capable of manufacturing of large amount of bearings depends on the demands
and orders. In our investigation, processing times of two products are recorded and their cycle
time and production rates are calculated in following steps.
Line 1: Inner/Outer Ring Manufacturing Process and Step Time
Turning (s) Heat Treatment (S) Grinding (s) Testing (s) Load & Unload (s)
Product A 3 2 4 2 2.5
Product B 4 2.5 5 2 2.5
Note: The time of Heat Treatment is the average time of each ring.
Line 2: Ball Manufacturing Process and Step Time
Shearing & Heading
(s)
Forging
(s)
Heat Treatment
(s)
Lapping
(s)
Testing
(s)
Load & Unload
(s)
Product A 0.1 0.1 0.05 0.3 0.3 0.3
Product B 0.1 0.1 0.05 0.3 0.3 0.3
Note: Each of Product A needs 8 balls; Each of Product B needs 10 balls.
Line 3: Cage Manufacturing Process and Step Time
Blanking & Punching (s) Forming (s) Testing (s) Load & Unload (s)
Product A 0.5 2 1 1.5
Product B 0.8 3 1 1.5
Assembly:
Note: the Assembly & Testing time (Cycle Time) of Product A is 10s, the Assembly & Testing time (Cycle
Time) of Product B is 12s.
Plant Layout:
Cage
Rivet
Outer Ring
Inner Ring
Balls
Assembling
(Pillow Wrapping Machine) Testing
Cycle Time and Production Rate
Line 1:
2 operators: one for Testing, one for loading & unloading
Turning Heating Grinding Testing
Breakdown Probability 0.005 0.003 0.008 0.007
Down Time (min) 5 10 6 3
𝑇𝐶 = 𝑇 𝑀 + 𝑇𝑆
A: Tc1=3+2+4+2+2.5=13.5S
B: TC1=4+2.5+5+2+2.5=16S
𝑇𝑃 = 𝑇𝐶 + 𝐹 ∗ 𝑇𝑑
F*Td=0.005×5+0.003×10+0.008×6+0.007×3=0.124min=7.44s
A: Tp1=13.5+7.44=20.94s
B: Tp1=16+7.44=23.44s
𝑅 𝑃 =
3600
𝑇 𝑃
(Parts/hr)
A: Rp1=
3600
20.94
=171.92 Parts/hr.
B: Rp1=
3600
23.44
=153.58 Parts/hr.
Line 1 Line 2 Line 3
Assembly
Testing
Line 2:
2 operators: one for Testing, one for loading & unloading
Shearing & Heading Forging Heat Treatment Lapping Testing
Breakdown Probability 0.0008 0.0003 0.0003 0.0005 0.0007
Down Time (min) 3 5 10 5 3
𝑇𝐶 = 𝑇 𝑀 + 𝑇𝑆
Ball: Tc=0.1+0.1+0.05+0.2+0.3+0.3=1.05s
𝑇𝑃 = 𝑇𝐶 + 𝐹 ∗ 𝑇𝑑
F*Td=0.0008×3+0.0003×5+0.0003×10+0.0005×5+0.0007×3=0.0115min=0.69s
Ball: Tp=1.05+0.69=1.74s
𝑅 𝑃 =
3600
𝑇 𝑃
(Parts/hr)
Ball: Rp=
3600
20.91.744
=2068.97 Parts/hr.
Tc
A: Tc2=8*Tc=8×1.05=8.4s
B: TC2=10* Tc=10×1.05=10.5s
Rp
A: Rp2=2068.97×
1
8
=258.62 Parts/hr.
B: Rp2=2068.97×
1
10
=106.90 Parts/hr.
Line 3:
2 operators: one for Testing, one for loading & unloading
Blanking & Punching Forming Testing
Breakdown Probability 0.005 0.003 0.004
Down Time (min) 5 8 3
𝑇𝐶 = 𝑇 𝑀 + 𝑇𝑆
A: Tc3=0.5+2+1+1.5=5s
B: TC3=0.8+3+1+1.5=6.3s
𝑇𝑃 = 𝑇𝐶 + 𝐹 ∗ 𝑇𝑑
F*Td=0.005×5+0.003×8+0.004×3=0.061min=3.66s
A: Tp3=5+3.66=8.66s
B: Tp3=6.3+3.66=9.96s
𝑅 𝑃 =
3600
𝑇 𝑃
(Parts/hr)
A: Rp3=
3600
8.66
=415.70 Parts/hr.
B: Rp3=
3600
9.96
=361.45 Parts/hr.
Assembly:
Breakdown Probability: 0.008; Down Time: 8min.
A: TPA=10+0.008×8×60=13.84s
B: TPA=12+0.008×8×60=15.84s
Ball Bearing:
Tc= max{Tc1, TC2, TC3}+TCA
A: TC=TC1+TCA=13.5+10=23.5s
B: TC=TC1+TCA=16+12=28s
Tp= max{TP1, Tp2, TP3}+TPA
A: Tp=TP1+TPA=20.94+13.84=34.78s
B: Tp=TP1+TPA=23.44+15.84=39.28s
RP=
3600
𝑇 𝑃
(Parts/hr)
A: RP=
3600
34.78
=103.51 Bearing/hr.
B: RP=
3600
39.28
=91.65 Bearing/hr.
Sections 3: optimize the system
Notice that the original system is not perfect efficient based on current process of
manufacturing, some improvement changes could be applied into the system like the number
of workstations and workers.
3.1 Optimum Number of Workstation—Assembling Workstation
Product A Product B
Annual Goal (Q) 800000 600000
Cycle Time without testing (TC) 8s 10s
Scrap Time (µ) 2%
Worker Efficiency (Ew) 95%
Machine Running Reliability (RM) 98%
Machine Setup Reliability (RS) 99.5%
Setup Time (TSP) 20min
Batch Size (N) 5000
Original Factory Operation Hours: 8 Hours/day; 5 Days/week; 50 Weeks/year.
Workload:
𝑊𝐿 =
𝑄 ∗ 𝑇𝐶
1 − µ
A: WL(A)=
800000×8
1−2%
=6530612s=1814.06hr.
B: WL(B)=
600000×10
1−2%
=6122449s=1700.68hr.
No. of setup changes:
No.=
𝑄(𝐴)+𝑄(𝐵)
𝑁
=
800000+600000
5000
=280
Setup: WL(SP)=No. ×TSP=280×20=5600min=93.33hr.
Available Time:
AT=8×5×50=2000hr/yr.
Optimum number of workstations:
𝑁𝑜. =
𝑊𝐿(𝐴) + 𝑊𝐿(𝐵)
𝐴𝑇 ∗ 𝐸 𝑊 ∗ 𝑅 𝑀
+
𝑊𝐿(𝑆𝑃)
𝐴𝑇 ∗ 𝑅 𝑆
𝑁𝑜. =
1814.06+1700.68
2000×0.95×0.98
+
93.33
2000×0.995
=1.93452
So, 1 workstation  2 workstations OR double the operation hours.
Considering the high price of assembling machines, we choose doubling the operation hours as the
solution.
Then, the cycle time of assembling (with testing) changes from 8+2 to 4+2 for product A; 10+2 to 5+2 for
product B.
Ball Bearing:
Cycle Time:
A: TC=TC1+TCA=13.5+6=19.5s
B: TC=TC1+TCA=16+7=23s
Production Time:
A: TP=TP1+TPA=20.94+(6+0.008×8×60)=30.78s
B: TP=TP1+TPA=23.44+(7+0.008×8×60)=34.28s
Production Rate:
A: RP=
3600
30.78
=116.96 Bearing/hr.
B: RP=
3600
34.28
=105.02 Bearing/hr.
3.2 Machine Cluster Analysis (Determine the number of workers)
Line 1 Line 2 Line 3 Line 4
A (s) B (s) A (s) B (s) A (s) B (s) A (s) B (s)
Machine Time (TM) 6 7 0.5 0.625 1.5 2 6 7.5
Worker Service Time (Ts) 5 5 0.3 0.3 1.5 1.5 4 4.5
Repositioning Time (Tr) 5 5.5 0.15 0.1875 2.3 3.5 5 6
The number of machines could be operated by one person (N): 𝑁 =
𝑇 𝑀+𝑇 𝑆
𝑇 𝑆+𝑇𝑟
Line 1:
A: 𝑁 =
6+5
5+5
= 1.1 one worker could operate 1.1 line 1. So, in line 1, employee 1 worker.
B: 𝑁 =
7+5
6+5.5
= 1.14 1 worker
Line 2:
A: 𝑁 =
0.5+0.3
0.3+0.15
= 1.78 1 worker
B: 𝑁 =
0.625+0.3
0.3+0.1875
= 1.90 1 worker
Line 3:
A: 𝑁 =
1.5+1.5
1.5+2.3
= 0.79 2 workers
B: 𝑁 =
2+1.5
1.5+3.5
= 0.7 2 workers
Assembly:
A: 𝑁 =
6+4
4+5
= 1.11 1 worker
B: 𝑁 =
7.5+4.5
4.5+6
= 1.14 1 worker
Conclusion: Theoretically, set 1 worker in Line 1; 1 worker in Line 2; 2 workers in Line 3; 1 worker in
Assembly.
However, as to practice, some of the stuff could not be lifted by one worker, and there are a lot of
emergency situations which could cause the stop of whole factory if there is only one worker in a line,
such as sickness or vacation.
As to Line 2, one worker almost could operate 2 lines. The company could try to train the other guys,
and ask them to do both line 1 & line2, or both line 2 & line 3. Another method, the company could try
to buy standard Balls from other companies, just like buying Rivets.
Cost Analysis (Machine never idle):
Labor Cost ( CL): $2.5/hr. Machine/Line Cost (CM): $20/hr.
Cost/part=(
𝐶 𝐿
𝑛
+ 𝐶 𝑀) ∗ (𝑇 𝑀 + 𝑇𝑆)
Original:
Line 1, Labor 2:
A: $=(2.5×2+20) ×13.5÷3600=0.09375
B: $=(2.5×2+20) ×16÷3600=0.1111
Line 2, Labor 2:
A: $=(2.5×2+20) ×8.4÷3600=0.0583
B: $=(2.5×2+20) ×10.5÷3600=0.0729
Line 3, Labor 2:
A: $=(2.5×2+20) ×5÷3600=0.0347
B: $=(2.5×2+20) ×6.3÷3600=0.0438
Assembly, Labor 2:
In order to meet the annual goal, we choose double the operator hours. And the Labor Cost at night is
$3/hr, which means the average Labor Cost is $2.75/hr.
A: $=(2.75×2+20) ×10÷3600=0.0708
B: $=(2.75×2+20) ×12÷3600=0.085
Total:
A: ∑$=0.09375+0.0583+0.0347+0.0708=0.25755 $/bearing
B: ∑$=0.1111+0.0729+0.0438+0.085=0.3128 $/bearing
Optimization (theoretically)
Line 1, Labor 2:
A: $=(2.5+20) ×13.5÷3600=0.0844
B: $=(2.5+20) ×16÷3600=0.1000
Line 2, Labor 2:
A: $=(2.5+20) ×8.4÷3600=0.0525
B: $=(2.5+20) ×10.5÷3600=0.0656
Line 3, Labor 2:
A: $=(2.5×2+20) ×5÷3600=0.0347
B: $=(2.5×2+20) ×6.3÷3600=0.0438
Assembly, Labor 2:
A: $=(2.75+20) ×10÷3600=0.0632
B: $=(2.75+20) ×12÷3600=0.0758
Total:
A: ∑$=0.0844+0.0525+0.0347+0.0632=0.2348 $/bearing
B: ∑$=0.1000+0.0656+0.0438+0.0758=0.2852 $/bearing
Conclusion: After optimizing the number of workers, the cost per product A reduces from $0.25755 to
$0.2348, the cost per product B reduces from $0.3128 to $0.2852.
Section 4 Automate the system
Notice that the original layout of the system has different transportation time for each lines whereas
only the maximum Tr could be applied in to the calculation of calculation time. Then we assumed a new
lay out of the system and all the transportation will be carried out by conveyor belt automatically.
Original:
Tr=max{1, 1.5, 1, 1.5}=1.5s
Optimum:
0.5s
1s
1s
Ring Ball Cage
Assembly
Testing
Rivet
Same distance between each line to assembly workstation.
Tr=max{1.25, 1.25, 1.25, 1.25}=1.25s
Then optimized layout could save repositioning time from 1.5s to 1.25s
New Tc and Rp
Tc:
A: Tc=19.5-0.25=19.25s
B: Tc=23-0.25=22.75s
Rp:
Due to the Tp of line 1 which is the maximum can save 0.25s, the whole Tp could save 0.25s too.
A: Rp=
3600
30.53
=117.92 Bearing/hr.
B: Rp=
3600
34.03
=105.79 Bearing/hr.
1.25s
1.25s
Ring
Assembly
Ball
Rivet Cage
Testing
1.25s
Half Circle Layout
Section 5 Quality assurance
For any factory, quality is the most important specification for their reputations. Therefore, the
inspection procedure becomes essential. The statistical process and quality analysis is given by
the control charts. The mean and range charts are also plotted.
5.1 Product A
Y
direction
Radius Testing Data AVG(x) Range
Y1
r 2.0032 2.0018 1.9958 1.9972 2.0081 2.0026 2.00145 0.0123
R 2.5092 2.5039 2.4909 2.4992 2.5041 2.4955 2.500467 0.0183
Y2
r 2.0071 2.0062 2.0021 1.9988 1.9943 2.0011 2.0016 0.0128
R 2.4989 2.509 2.5021 2.4991 2.4982 2.5033 2.501767 0.0108
Y3
r 1.9978 1.9954 1.9942 1.9933 1.9961 2.0006 1.996233 0.0073
R 2.5032 2.4929 2.4932 2.5077 2.4954 2.5031 2.49925 0.0148
Y4
r 1.9963 2.0085 1.9909 1.9959 2.0085 2.0044 2.00075 0.0176
R 2.5019 2.5055 2.5042 2.4959 2.5044 2.4951 2.501167 0.0104
Y5
r 2.0088 2.0105 2.0049 2.0088 2.0038 1.9992 2.006 0.0113
R 2.4982 2.4966 2.504 2.4921 2.5089 2.4906 2.4984 0.0183
1.988
1.99
1.992
1.994
1.996
1.998
2
2.002
2.004
2.006
2.008
2.01
1 2 3 4 5
DemensionofInnerCircle(inch)
Sample Number,s
Chart of r
UCL
Center
LCL
r
Chart Range Chart
CL UCL LCL CL UCL LCL
2.00120667 2.0071282 1.995285 0.01226 0.024569 0
0
0.005
0.01
0.015
0.02
0.025
0.03
1 2 3 4 5
Range
Sample Number, s
Range Chart of r
Center
2.485
2.49
2.495
2.5
2.505
2.51
1 2 3 4 5
DemensionofOuterCircle(inch)
Sample Number, s
Chart of R
UCL
Center
LCL
𝑋
5.2 Product B
Y
direction
Radius Testing Data AVG(x) Range
Y1
r 3.0098 3.0044 3.0051 3.0026 2.9964 2.9956 3.002317 0.0142
R 3.9976 3.9985 4.0021 4.0016 4.0032 3.9925 3.99925 0.0107
Y2
r 2.9984 2.9973 3.0024 3.0036 2.9979 3.0035 3.000517 0.0063
R 4.0035 3.9946 3.9959 4.0031 3.9916 4.0035 3.9987 0.0119
Y3
r 3.0019 3.0026 2.9959 2.9967 3.0016 3.0025 3.0002 0.0067
R 4.0038 3.9958 3.9986 4.0025 4.0016 4.0035 4.000967 0.008
Y4
r 3.0026 3.0053 2.9935 2.9979 3.0019 3.0014 3.000433 0.0118
R 4.0009 3.9959 4.0016 3.9953 3.9929 4.0031 3.998283 0.0102
Y5
r 3.0049 3.0053 2.9959 2.9975 3.0041 3.0029 3.001767 0.0094
R 3.9989 4.0011 4.0021 4.0013 3.9989 4.0019 4.0007 0.0032
0
0.005
0.01
0.015
0.02
0.025
0.03
0.035
1 2 3 4 5
Range
Sample Number,s
Range Chart of R
UCL
Center
LCL
R
Chart Range Chart
CL UCL LCL CL UCL LCL
2.50021 2.5072232 2.493197 0.01452 0.029098 0
r
Chart Range Chart
CL UCL LCL CL UCL LCL
3.00104667 3.0057221 2.996371 0.00968 0.019399 0
2.99
2.992
2.994
2.996
2.998
3
3.002
3.004
3.006
3.008
1 2 3 4 5
DemensionofInnerCircle(inch)
Sample Number,s
Chart of r
UCL
Center
LCL
0
0.005
0.01
0.015
0.02
0.025
1 2 3 4 5
Range
Sample Number, s
Range Chart of r
Center
R
Chart Range Chart
CL UCL LCL CL UCL LCL
3.99958 4.0038304 3.99533 0.0088 0.017635 0
The charts show us the quality is quite well controlled during the process. While consider that the
company are using some low quality machining equipment. The way to make their defect rate better is
to purchase some new equipment with higher capability of controlling the precision and qualities, which
would also reduce the cost significantly. Assume the defect rate reduces from 5% to 3% after using the
new equipment, the quantity of required bearings to meet every 1 million will reduces from 1,052,632
3.99
3.992
3.994
3.996
3.998
4
4.002
4.004
4.006
1 2 3 4 5
DemensionofOuterCircle(inch)
Sample Number, s
Chart of R
UCL
Center
LCL
𝑋
0
0.002
0.004
0.006
0.008
0.01
0.012
0.014
0.016
0.018
0.02
1 2 3 4 5
Range
Sample Number,s
Range Chart of R
UCL
Center
LCL
to 1,030,928. Cost saved per million is $5,096.14 for A and $6,190.03 for B. Calculated as the following
steps.
Defect Rate=5%:
𝑁 =
1,000,000
1 − 5%
= 1,052,631.58 = 1,052,632
Defect Rate=3%:
𝑁 =
1,000,000
1 − 3%
= 1,030,927.84 = 1,030,928
Cost Saved (Price per Bearing is $0.2348 for A, $0.2852 for B):
CA=0.2348×(1,052,632-1,030,928)=$5,096.14/million
CB=0.2852×(1,052,632-1,030,928)=$6,190.03/million

More Related Content

What's hot

INDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaM
INDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaMINDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaM
INDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaMshridharthecyberdude
 
Implementing 5 s methodology as tool for improving efficiency
Implementing 5 s methodology as tool for improving efficiencyImplementing 5 s methodology as tool for improving efficiency
Implementing 5 s methodology as tool for improving efficiencyLaukik Raut
 
Product processlayout[1]
Product processlayout[1]Product processlayout[1]
Product processlayout[1]Aditya Suiwal
 
Engineering fundamentals
Engineering fundamentalsEngineering fundamentals
Engineering fundamentalsmkpq pasha
 
Dtk group of industries 2013
Dtk group of industries 2013Dtk group of industries 2013
Dtk group of industries 2013Aamer Pathan
 
Windsor machines industrial report
Windsor machines industrial reportWindsor machines industrial report
Windsor machines industrial reportaman1312
 
Design and Fabrication of Paper Bailing Machine
Design and Fabrication of Paper Bailing MachineDesign and Fabrication of Paper Bailing Machine
Design and Fabrication of Paper Bailing MachineIRJET Journal
 
MANUFACTURING OF CNC MACHINES- TRAINING REPORT AT JYOTI CNC
MANUFACTURING OF CNC MACHINES- TRAINING REPORT AT JYOTI CNCMANUFACTURING OF CNC MACHINES- TRAINING REPORT AT JYOTI CNC
MANUFACTURING OF CNC MACHINES- TRAINING REPORT AT JYOTI CNCBhaumik Sheth
 
Dawlance internship report
Dawlance internship reportDawlance internship report
Dawlance internship reportMohammad Younus
 
VOCATIONAL TRAINING REPORT OF SIMPLE CASTING LIMITED
VOCATIONAL TRAINING REPORT OF SIMPLE CASTING LIMITEDVOCATIONAL TRAINING REPORT OF SIMPLE CASTING LIMITED
VOCATIONAL TRAINING REPORT OF SIMPLE CASTING LIMITEDSurendra Kumar Dewangan
 
Windsor machines training repport
Windsor machines training repportWindsor machines training repport
Windsor machines training repportaman1312
 
Internship Report (MEchanical Engg) by kalpesh pawar
Internship Report (MEchanical Engg) by kalpesh pawarInternship Report (MEchanical Engg) by kalpesh pawar
Internship Report (MEchanical Engg) by kalpesh pawarKalpesh Pawar
 
IRJET- Use of Casting Simulation for Yield Improvement.
IRJET- Use of Casting Simulation for Yield Improvement.IRJET- Use of Casting Simulation for Yield Improvement.
IRJET- Use of Casting Simulation for Yield Improvement.IRJET Journal
 
Report on Industrial attachment with HBL
Report on Industrial attachment with HBLReport on Industrial attachment with HBL
Report on Industrial attachment with HBLMd Rahamat Ullah
 
Micro Project - Design of Can Manufacturing Facility
Micro Project - Design of Can Manufacturing FacilityMicro Project - Design of Can Manufacturing Facility
Micro Project - Design of Can Manufacturing FacilityAmr El-Ganainy
 
Ashirvad Techno Equipments Gujarat India
Ashirvad Techno Equipments Gujarat IndiaAshirvad Techno Equipments Gujarat India
Ashirvad Techno Equipments Gujarat IndiaExportersIndia
 
INDUSTRIAL TRAINING REPORT AT PRABHULINGESHWAR SUGARS
INDUSTRIAL TRAINING REPORT AT PRABHULINGESHWAR SUGARSINDUSTRIAL TRAINING REPORT AT PRABHULINGESHWAR SUGARS
INDUSTRIAL TRAINING REPORT AT PRABHULINGESHWAR SUGARSbkshivkumar012
 

What's hot (20)

INDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaM
INDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaMINDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaM
INDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaM
 
Implementing 5 s methodology as tool for improving efficiency
Implementing 5 s methodology as tool for improving efficiencyImplementing 5 s methodology as tool for improving efficiency
Implementing 5 s methodology as tool for improving efficiency
 
Product processlayout[1]
Product processlayout[1]Product processlayout[1]
Product processlayout[1]
 
STP REPORT (final)
STP REPORT (final)STP REPORT (final)
STP REPORT (final)
 
Engineering fundamentals
Engineering fundamentalsEngineering fundamentals
Engineering fundamentals
 
Dtk group of industries 2013
Dtk group of industries 2013Dtk group of industries 2013
Dtk group of industries 2013
 
report
reportreport
report
 
Windsor machines industrial report
Windsor machines industrial reportWindsor machines industrial report
Windsor machines industrial report
 
Design and Fabrication of Paper Bailing Machine
Design and Fabrication of Paper Bailing MachineDesign and Fabrication of Paper Bailing Machine
Design and Fabrication of Paper Bailing Machine
 
MANUFACTURING OF CNC MACHINES- TRAINING REPORT AT JYOTI CNC
MANUFACTURING OF CNC MACHINES- TRAINING REPORT AT JYOTI CNCMANUFACTURING OF CNC MACHINES- TRAINING REPORT AT JYOTI CNC
MANUFACTURING OF CNC MACHINES- TRAINING REPORT AT JYOTI CNC
 
Dawlance internship report
Dawlance internship reportDawlance internship report
Dawlance internship report
 
VOCATIONAL TRAINING REPORT OF SIMPLE CASTING LIMITED
VOCATIONAL TRAINING REPORT OF SIMPLE CASTING LIMITEDVOCATIONAL TRAINING REPORT OF SIMPLE CASTING LIMITED
VOCATIONAL TRAINING REPORT OF SIMPLE CASTING LIMITED
 
Windsor machines training repport
Windsor machines training repportWindsor machines training repport
Windsor machines training repport
 
Internship Report (MEchanical Engg) by kalpesh pawar
Internship Report (MEchanical Engg) by kalpesh pawarInternship Report (MEchanical Engg) by kalpesh pawar
Internship Report (MEchanical Engg) by kalpesh pawar
 
IRJET- Use of Casting Simulation for Yield Improvement.
IRJET- Use of Casting Simulation for Yield Improvement.IRJET- Use of Casting Simulation for Yield Improvement.
IRJET- Use of Casting Simulation for Yield Improvement.
 
Report on Industrial attachment with HBL
Report on Industrial attachment with HBLReport on Industrial attachment with HBL
Report on Industrial attachment with HBL
 
Micro Project - Design of Can Manufacturing Facility
Micro Project - Design of Can Manufacturing FacilityMicro Project - Design of Can Manufacturing Facility
Micro Project - Design of Can Manufacturing Facility
 
3rd stage ppt black book
3rd stage ppt   black book3rd stage ppt   black book
3rd stage ppt black book
 
Ashirvad Techno Equipments Gujarat India
Ashirvad Techno Equipments Gujarat IndiaAshirvad Techno Equipments Gujarat India
Ashirvad Techno Equipments Gujarat India
 
INDUSTRIAL TRAINING REPORT AT PRABHULINGESHWAR SUGARS
INDUSTRIAL TRAINING REPORT AT PRABHULINGESHWAR SUGARSINDUSTRIAL TRAINING REPORT AT PRABHULINGESHWAR SUGARS
INDUSTRIAL TRAINING REPORT AT PRABHULINGESHWAR SUGARS
 

Viewers also liked

MMAE554 Term Paper
MMAE554 Term PaperMMAE554 Term Paper
MMAE554 Term PaperLI HE
 
2013 CHINA
2013 CHINA2013 CHINA
2013 CHINALI HE
 
2014 Central China Area
2014 Central China Area2014 Central China Area
2014 Central China AreaLI HE
 
Calculation and FE analysis for sustainability of seal for ball bearing
Calculation and FE analysis for sustainability of seal for ball bearingCalculation and FE analysis for sustainability of seal for ball bearing
Calculation and FE analysis for sustainability of seal for ball bearingNBC Bearings
 
MMAE545-Final Report-Analysis of Aircraft Wing
MMAE545-Final Report-Analysis of Aircraft WingMMAE545-Final Report-Analysis of Aircraft Wing
MMAE545-Final Report-Analysis of Aircraft WingLI HE
 
2014 USA
2014 USA2014 USA
2014 USALI HE
 
30 Bearings& Lubrication Fope
30 Bearings& Lubrication Fope30 Bearings& Lubrication Fope
30 Bearings& Lubrication Fopejubin
 
Bearing Description about basic, types, failure causes
Bearing Description about basic, types, failure causesBearing Description about basic, types, failure causes
Bearing Description about basic, types, failure causesPankaj
 

Viewers also liked (10)

Ball bearing manufacturing process
Ball bearing manufacturing processBall bearing manufacturing process
Ball bearing manufacturing process
 
MMAE554 Term Paper
MMAE554 Term PaperMMAE554 Term Paper
MMAE554 Term Paper
 
2013 CHINA
2013 CHINA2013 CHINA
2013 CHINA
 
2014 Central China Area
2014 Central China Area2014 Central China Area
2014 Central China Area
 
Calculation and FE analysis for sustainability of seal for ball bearing
Calculation and FE analysis for sustainability of seal for ball bearingCalculation and FE analysis for sustainability of seal for ball bearing
Calculation and FE analysis for sustainability of seal for ball bearing
 
Ball beaing
Ball beaingBall beaing
Ball beaing
 
MMAE545-Final Report-Analysis of Aircraft Wing
MMAE545-Final Report-Analysis of Aircraft WingMMAE545-Final Report-Analysis of Aircraft Wing
MMAE545-Final Report-Analysis of Aircraft Wing
 
2014 USA
2014 USA2014 USA
2014 USA
 
30 Bearings& Lubrication Fope
30 Bearings& Lubrication Fope30 Bearings& Lubrication Fope
30 Bearings& Lubrication Fope
 
Bearing Description about basic, types, failure causes
Bearing Description about basic, types, failure causesBearing Description about basic, types, failure causes
Bearing Description about basic, types, failure causes
 

Similar to MMAE557 Consulting Project-Li He(A20358122),Xingye Dai(A20365915)

CIM report - final
CIM report - finalCIM report - final
CIM report - finalPraveen S R
 
Work Process Analysis of 4-170 Pizoelectric accelerometer at CECVP Project W...
Work Process Analysis of  4-170 Pizoelectric accelerometer at CECVP Project W...Work Process Analysis of  4-170 Pizoelectric accelerometer at CECVP Project W...
Work Process Analysis of 4-170 Pizoelectric accelerometer at CECVP Project W...Joseph Uken
 
Simulation of production systems- final report
Simulation of production systems- final reportSimulation of production systems- final report
Simulation of production systems- final reportSatheesh Kumar Chandran
 
4AD15ME042.pptx
4AD15ME042.pptx4AD15ME042.pptx
4AD15ME042.pptxMrHAD
 
Medium artillery ammunition(MAA) Factory (1)
Medium artillery ammunition(MAA) Factory (1)Medium artillery ammunition(MAA) Factory (1)
Medium artillery ammunition(MAA) Factory (1)Malik Raheel
 
Summer Training Report - Gaurab Pant(1)
Summer Training Report - Gaurab Pant(1)Summer Training Report - Gaurab Pant(1)
Summer Training Report - Gaurab Pant(1)Gaurab Pant
 
flexible-manufacturing-systems
 flexible-manufacturing-systems flexible-manufacturing-systems
flexible-manufacturing-systemssabry said
 
6_2 Flexible MFG Performance.ppt
6_2 Flexible MFG Performance.ppt6_2 Flexible MFG Performance.ppt
6_2 Flexible MFG Performance.pptSabrySYoussef1
 
Preliminary Study of an Assembling Plant
Preliminary Study of an Assembling Plant Preliminary Study of an Assembling Plant
Preliminary Study of an Assembling Plant MustafaElAkkad
 
Enigma of 'six sigma' for foundry sm es in india
Enigma of 'six sigma' for foundry sm es in indiaEnigma of 'six sigma' for foundry sm es in india
Enigma of 'six sigma' for foundry sm es in indiaDr. Bikram Jit Singh
 
IRJET - Design Procedure and Impact of Fixed Type Automation for Billet Loading
IRJET - Design Procedure and Impact of Fixed Type Automation for Billet LoadingIRJET - Design Procedure and Impact of Fixed Type Automation for Billet Loading
IRJET - Design Procedure and Impact of Fixed Type Automation for Billet LoadingIRJET Journal
 
Industrial plants and safety project
Industrial plants and safety projectIndustrial plants and safety project
Industrial plants and safety projectNikoZurabishvili
 
IRJET- Preventive Maintenance and Root Cause Analysis of Sealed Quench Furnac...
IRJET- Preventive Maintenance and Root Cause Analysis of Sealed Quench Furnac...IRJET- Preventive Maintenance and Root Cause Analysis of Sealed Quench Furnac...
IRJET- Preventive Maintenance and Root Cause Analysis of Sealed Quench Furnac...IRJET Journal
 
OPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGE
OPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGEOPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGE
OPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGEyosefhadiwibowo
 

Similar to MMAE557 Consulting Project-Li He(A20358122),Xingye Dai(A20365915) (20)

CIM report - final
CIM report - finalCIM report - final
CIM report - final
 
CIM report - final
CIM report - finalCIM report - final
CIM report - final
 
CIM Report
CIM ReportCIM Report
CIM Report
 
Work Process Analysis of 4-170 Pizoelectric accelerometer at CECVP Project W...
Work Process Analysis of  4-170 Pizoelectric accelerometer at CECVP Project W...Work Process Analysis of  4-170 Pizoelectric accelerometer at CECVP Project W...
Work Process Analysis of 4-170 Pizoelectric accelerometer at CECVP Project W...
 
Simulation of production systems- final report
Simulation of production systems- final reportSimulation of production systems- final report
Simulation of production systems- final report
 
Line Balancing In Garments Industry
Line Balancing In Garments IndustryLine Balancing In Garments Industry
Line Balancing In Garments Industry
 
4AD15ME042.pptx
4AD15ME042.pptx4AD15ME042.pptx
4AD15ME042.pptx
 
Medium artillery ammunition(MAA) Factory (1)
Medium artillery ammunition(MAA) Factory (1)Medium artillery ammunition(MAA) Factory (1)
Medium artillery ammunition(MAA) Factory (1)
 
Summer Training Report - Gaurab Pant(1)
Summer Training Report - Gaurab Pant(1)Summer Training Report - Gaurab Pant(1)
Summer Training Report - Gaurab Pant(1)
 
flexible-manufacturing-systems
 flexible-manufacturing-systems flexible-manufacturing-systems
flexible-manufacturing-systems
 
6_2 Flexible MFG Performance.ppt
6_2 Flexible MFG Performance.ppt6_2 Flexible MFG Performance.ppt
6_2 Flexible MFG Performance.ppt
 
Preliminary Study of an Assembling Plant
Preliminary Study of an Assembling Plant Preliminary Study of an Assembling Plant
Preliminary Study of an Assembling Plant
 
Enigma of 'six sigma' for foundry sm es in india
Enigma of 'six sigma' for foundry sm es in indiaEnigma of 'six sigma' for foundry sm es in india
Enigma of 'six sigma' for foundry sm es in india
 
Assignment 1 rev1
Assignment 1 rev1Assignment 1 rev1
Assignment 1 rev1
 
Ct6
Ct6Ct6
Ct6
 
Line balancing
Line balancingLine balancing
Line balancing
 
IRJET - Design Procedure and Impact of Fixed Type Automation for Billet Loading
IRJET - Design Procedure and Impact of Fixed Type Automation for Billet LoadingIRJET - Design Procedure and Impact of Fixed Type Automation for Billet Loading
IRJET - Design Procedure and Impact of Fixed Type Automation for Billet Loading
 
Industrial plants and safety project
Industrial plants and safety projectIndustrial plants and safety project
Industrial plants and safety project
 
IRJET- Preventive Maintenance and Root Cause Analysis of Sealed Quench Furnac...
IRJET- Preventive Maintenance and Root Cause Analysis of Sealed Quench Furnac...IRJET- Preventive Maintenance and Root Cause Analysis of Sealed Quench Furnac...
IRJET- Preventive Maintenance and Root Cause Analysis of Sealed Quench Furnac...
 
OPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGE
OPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGEOPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGE
OPERATIONS MANAGEMENT FOR COMPETITIVE ADVANTAGE
 

MMAE557 Consulting Project-Li He(A20358122),Xingye Dai(A20365915)

  • 1. MMAE557 Personal Consulting Project Analysis of Ball Bearing Manufacturing Li He A20358122 Xingye Dai A20365915 Instructor: John Cesarone Apr.30, 2016
  • 2. Section.1 Client Description Our client is Weili bearing factory in China which we have ever visited. It’s a company located in Hebei province and produces many models of bearings. It’s a private company so the factory has not a large scale of manufacturing and their economic situation does not allow them to hire a large amounts of workers. In that case, to improve their efficiency of manufacturing system becomes essential. In this factory, one of the production workshop was investigated. Totally three lines of work stations are applied to the manufacturing process of bearings. The first line includes 4 steps (Turning, heat treatment, grinding and testing) of manufacturing the inner and outer rings. The second line includes 5 steps (shearing & heading, forging, heating treatment, lapping, testing) of manufacturing the bearing balls. The third line includes 3 steps (blanking & punching, forming and testing) of manufacturing the cages. All the machining processes are finished by corresponding machining equipment and the heat treatments are processing in furnace. The products are annealed at high temperature and quenched in oil for hardening. The inspections are done by workers and operators. Each line has two operators, one for testing and the other one for loading and unloading. The inspection for size and surface finish of balls is carried out on a sample basis by means of microscopes and other precision equipment. The balls are then cleaned and packed ready for bearing assembly operations. For inspections of cages, blanking, punching, forming rivet holes and visual inspection is carried for any deformity. For inner and outer rings, the diameters are measured. The finished parts of bearings are then manually transport to assembling station after a batch of parts are produced. Then the assembling station assembles the parts into bearings automatically. The finally products are then tested by 2 inspectors at next station. For each line, because all the steps are continuous and the transport time between stations is accounted in load and unload time. the products are transport so the multiple station cells are not applied to the manufacturing system. Two types of products are recorded for the entire process and their average time for each procedure were calculated and listed in following tables. The classifications of manufacturing system of this factory belongs to ‘’Type II-A B. Type II-A means it works on multiple automated stations and B means that the cell produces bearing parts in batch production system.
  • 3. Section 2: Client analysis This factory is capable of manufacturing of large amount of bearings depends on the demands and orders. In our investigation, processing times of two products are recorded and their cycle time and production rates are calculated in following steps. Line 1: Inner/Outer Ring Manufacturing Process and Step Time Turning (s) Heat Treatment (S) Grinding (s) Testing (s) Load & Unload (s) Product A 3 2 4 2 2.5 Product B 4 2.5 5 2 2.5 Note: The time of Heat Treatment is the average time of each ring. Line 2: Ball Manufacturing Process and Step Time Shearing & Heading (s) Forging (s) Heat Treatment (s) Lapping (s) Testing (s) Load & Unload (s) Product A 0.1 0.1 0.05 0.3 0.3 0.3 Product B 0.1 0.1 0.05 0.3 0.3 0.3 Note: Each of Product A needs 8 balls; Each of Product B needs 10 balls. Line 3: Cage Manufacturing Process and Step Time Blanking & Punching (s) Forming (s) Testing (s) Load & Unload (s) Product A 0.5 2 1 1.5 Product B 0.8 3 1 1.5 Assembly: Note: the Assembly & Testing time (Cycle Time) of Product A is 10s, the Assembly & Testing time (Cycle Time) of Product B is 12s. Plant Layout: Cage Rivet Outer Ring Inner Ring Balls Assembling (Pillow Wrapping Machine) Testing
  • 4. Cycle Time and Production Rate Line 1: 2 operators: one for Testing, one for loading & unloading Turning Heating Grinding Testing Breakdown Probability 0.005 0.003 0.008 0.007 Down Time (min) 5 10 6 3 𝑇𝐶 = 𝑇 𝑀 + 𝑇𝑆 A: Tc1=3+2+4+2+2.5=13.5S B: TC1=4+2.5+5+2+2.5=16S 𝑇𝑃 = 𝑇𝐶 + 𝐹 ∗ 𝑇𝑑 F*Td=0.005×5+0.003×10+0.008×6+0.007×3=0.124min=7.44s A: Tp1=13.5+7.44=20.94s B: Tp1=16+7.44=23.44s 𝑅 𝑃 = 3600 𝑇 𝑃 (Parts/hr) A: Rp1= 3600 20.94 =171.92 Parts/hr. B: Rp1= 3600 23.44 =153.58 Parts/hr. Line 1 Line 2 Line 3 Assembly Testing
  • 5. Line 2: 2 operators: one for Testing, one for loading & unloading Shearing & Heading Forging Heat Treatment Lapping Testing Breakdown Probability 0.0008 0.0003 0.0003 0.0005 0.0007 Down Time (min) 3 5 10 5 3 𝑇𝐶 = 𝑇 𝑀 + 𝑇𝑆 Ball: Tc=0.1+0.1+0.05+0.2+0.3+0.3=1.05s 𝑇𝑃 = 𝑇𝐶 + 𝐹 ∗ 𝑇𝑑 F*Td=0.0008×3+0.0003×5+0.0003×10+0.0005×5+0.0007×3=0.0115min=0.69s Ball: Tp=1.05+0.69=1.74s 𝑅 𝑃 = 3600 𝑇 𝑃 (Parts/hr) Ball: Rp= 3600 20.91.744 =2068.97 Parts/hr. Tc A: Tc2=8*Tc=8×1.05=8.4s B: TC2=10* Tc=10×1.05=10.5s Rp A: Rp2=2068.97× 1 8 =258.62 Parts/hr. B: Rp2=2068.97× 1 10 =106.90 Parts/hr. Line 3: 2 operators: one for Testing, one for loading & unloading Blanking & Punching Forming Testing Breakdown Probability 0.005 0.003 0.004 Down Time (min) 5 8 3 𝑇𝐶 = 𝑇 𝑀 + 𝑇𝑆 A: Tc3=0.5+2+1+1.5=5s B: TC3=0.8+3+1+1.5=6.3s
  • 6. 𝑇𝑃 = 𝑇𝐶 + 𝐹 ∗ 𝑇𝑑 F*Td=0.005×5+0.003×8+0.004×3=0.061min=3.66s A: Tp3=5+3.66=8.66s B: Tp3=6.3+3.66=9.96s 𝑅 𝑃 = 3600 𝑇 𝑃 (Parts/hr) A: Rp3= 3600 8.66 =415.70 Parts/hr. B: Rp3= 3600 9.96 =361.45 Parts/hr. Assembly: Breakdown Probability: 0.008; Down Time: 8min. A: TPA=10+0.008×8×60=13.84s B: TPA=12+0.008×8×60=15.84s Ball Bearing: Tc= max{Tc1, TC2, TC3}+TCA A: TC=TC1+TCA=13.5+10=23.5s B: TC=TC1+TCA=16+12=28s Tp= max{TP1, Tp2, TP3}+TPA A: Tp=TP1+TPA=20.94+13.84=34.78s B: Tp=TP1+TPA=23.44+15.84=39.28s RP= 3600 𝑇 𝑃 (Parts/hr) A: RP= 3600 34.78 =103.51 Bearing/hr. B: RP= 3600 39.28 =91.65 Bearing/hr.
  • 7. Sections 3: optimize the system Notice that the original system is not perfect efficient based on current process of manufacturing, some improvement changes could be applied into the system like the number of workstations and workers. 3.1 Optimum Number of Workstation—Assembling Workstation Product A Product B Annual Goal (Q) 800000 600000 Cycle Time without testing (TC) 8s 10s Scrap Time (µ) 2% Worker Efficiency (Ew) 95% Machine Running Reliability (RM) 98% Machine Setup Reliability (RS) 99.5% Setup Time (TSP) 20min Batch Size (N) 5000 Original Factory Operation Hours: 8 Hours/day; 5 Days/week; 50 Weeks/year. Workload: 𝑊𝐿 = 𝑄 ∗ 𝑇𝐶 1 − µ A: WL(A)= 800000×8 1−2% =6530612s=1814.06hr. B: WL(B)= 600000×10 1−2% =6122449s=1700.68hr. No. of setup changes: No.= 𝑄(𝐴)+𝑄(𝐵) 𝑁 = 800000+600000 5000 =280 Setup: WL(SP)=No. ×TSP=280×20=5600min=93.33hr. Available Time: AT=8×5×50=2000hr/yr.
  • 8. Optimum number of workstations: 𝑁𝑜. = 𝑊𝐿(𝐴) + 𝑊𝐿(𝐵) 𝐴𝑇 ∗ 𝐸 𝑊 ∗ 𝑅 𝑀 + 𝑊𝐿(𝑆𝑃) 𝐴𝑇 ∗ 𝑅 𝑆 𝑁𝑜. = 1814.06+1700.68 2000×0.95×0.98 + 93.33 2000×0.995 =1.93452 So, 1 workstation  2 workstations OR double the operation hours. Considering the high price of assembling machines, we choose doubling the operation hours as the solution. Then, the cycle time of assembling (with testing) changes from 8+2 to 4+2 for product A; 10+2 to 5+2 for product B. Ball Bearing: Cycle Time: A: TC=TC1+TCA=13.5+6=19.5s B: TC=TC1+TCA=16+7=23s Production Time: A: TP=TP1+TPA=20.94+(6+0.008×8×60)=30.78s B: TP=TP1+TPA=23.44+(7+0.008×8×60)=34.28s Production Rate: A: RP= 3600 30.78 =116.96 Bearing/hr. B: RP= 3600 34.28 =105.02 Bearing/hr. 3.2 Machine Cluster Analysis (Determine the number of workers) Line 1 Line 2 Line 3 Line 4 A (s) B (s) A (s) B (s) A (s) B (s) A (s) B (s) Machine Time (TM) 6 7 0.5 0.625 1.5 2 6 7.5 Worker Service Time (Ts) 5 5 0.3 0.3 1.5 1.5 4 4.5 Repositioning Time (Tr) 5 5.5 0.15 0.1875 2.3 3.5 5 6
  • 9. The number of machines could be operated by one person (N): 𝑁 = 𝑇 𝑀+𝑇 𝑆 𝑇 𝑆+𝑇𝑟 Line 1: A: 𝑁 = 6+5 5+5 = 1.1 one worker could operate 1.1 line 1. So, in line 1, employee 1 worker. B: 𝑁 = 7+5 6+5.5 = 1.14 1 worker Line 2: A: 𝑁 = 0.5+0.3 0.3+0.15 = 1.78 1 worker B: 𝑁 = 0.625+0.3 0.3+0.1875 = 1.90 1 worker Line 3: A: 𝑁 = 1.5+1.5 1.5+2.3 = 0.79 2 workers B: 𝑁 = 2+1.5 1.5+3.5 = 0.7 2 workers Assembly: A: 𝑁 = 6+4 4+5 = 1.11 1 worker B: 𝑁 = 7.5+4.5 4.5+6 = 1.14 1 worker Conclusion: Theoretically, set 1 worker in Line 1; 1 worker in Line 2; 2 workers in Line 3; 1 worker in Assembly. However, as to practice, some of the stuff could not be lifted by one worker, and there are a lot of emergency situations which could cause the stop of whole factory if there is only one worker in a line, such as sickness or vacation. As to Line 2, one worker almost could operate 2 lines. The company could try to train the other guys, and ask them to do both line 1 & line2, or both line 2 & line 3. Another method, the company could try to buy standard Balls from other companies, just like buying Rivets. Cost Analysis (Machine never idle): Labor Cost ( CL): $2.5/hr. Machine/Line Cost (CM): $20/hr. Cost/part=( 𝐶 𝐿 𝑛 + 𝐶 𝑀) ∗ (𝑇 𝑀 + 𝑇𝑆) Original: Line 1, Labor 2:
  • 10. A: $=(2.5×2+20) ×13.5÷3600=0.09375 B: $=(2.5×2+20) ×16÷3600=0.1111 Line 2, Labor 2: A: $=(2.5×2+20) ×8.4÷3600=0.0583 B: $=(2.5×2+20) ×10.5÷3600=0.0729 Line 3, Labor 2: A: $=(2.5×2+20) ×5÷3600=0.0347 B: $=(2.5×2+20) ×6.3÷3600=0.0438 Assembly, Labor 2: In order to meet the annual goal, we choose double the operator hours. And the Labor Cost at night is $3/hr, which means the average Labor Cost is $2.75/hr. A: $=(2.75×2+20) ×10÷3600=0.0708 B: $=(2.75×2+20) ×12÷3600=0.085 Total: A: ∑$=0.09375+0.0583+0.0347+0.0708=0.25755 $/bearing B: ∑$=0.1111+0.0729+0.0438+0.085=0.3128 $/bearing Optimization (theoretically) Line 1, Labor 2: A: $=(2.5+20) ×13.5÷3600=0.0844 B: $=(2.5+20) ×16÷3600=0.1000 Line 2, Labor 2: A: $=(2.5+20) ×8.4÷3600=0.0525 B: $=(2.5+20) ×10.5÷3600=0.0656 Line 3, Labor 2: A: $=(2.5×2+20) ×5÷3600=0.0347 B: $=(2.5×2+20) ×6.3÷3600=0.0438 Assembly, Labor 2: A: $=(2.75+20) ×10÷3600=0.0632
  • 11. B: $=(2.75+20) ×12÷3600=0.0758 Total: A: ∑$=0.0844+0.0525+0.0347+0.0632=0.2348 $/bearing B: ∑$=0.1000+0.0656+0.0438+0.0758=0.2852 $/bearing Conclusion: After optimizing the number of workers, the cost per product A reduces from $0.25755 to $0.2348, the cost per product B reduces from $0.3128 to $0.2852. Section 4 Automate the system Notice that the original layout of the system has different transportation time for each lines whereas only the maximum Tr could be applied in to the calculation of calculation time. Then we assumed a new lay out of the system and all the transportation will be carried out by conveyor belt automatically. Original: Tr=max{1, 1.5, 1, 1.5}=1.5s Optimum: 0.5s 1s 1s Ring Ball Cage Assembly Testing Rivet
  • 12. Same distance between each line to assembly workstation. Tr=max{1.25, 1.25, 1.25, 1.25}=1.25s Then optimized layout could save repositioning time from 1.5s to 1.25s New Tc and Rp Tc: A: Tc=19.5-0.25=19.25s B: Tc=23-0.25=22.75s Rp: Due to the Tp of line 1 which is the maximum can save 0.25s, the whole Tp could save 0.25s too. A: Rp= 3600 30.53 =117.92 Bearing/hr. B: Rp= 3600 34.03 =105.79 Bearing/hr. 1.25s 1.25s Ring Assembly Ball Rivet Cage Testing 1.25s Half Circle Layout
  • 13. Section 5 Quality assurance For any factory, quality is the most important specification for their reputations. Therefore, the inspection procedure becomes essential. The statistical process and quality analysis is given by the control charts. The mean and range charts are also plotted. 5.1 Product A Y direction Radius Testing Data AVG(x) Range Y1 r 2.0032 2.0018 1.9958 1.9972 2.0081 2.0026 2.00145 0.0123 R 2.5092 2.5039 2.4909 2.4992 2.5041 2.4955 2.500467 0.0183 Y2 r 2.0071 2.0062 2.0021 1.9988 1.9943 2.0011 2.0016 0.0128 R 2.4989 2.509 2.5021 2.4991 2.4982 2.5033 2.501767 0.0108 Y3 r 1.9978 1.9954 1.9942 1.9933 1.9961 2.0006 1.996233 0.0073 R 2.5032 2.4929 2.4932 2.5077 2.4954 2.5031 2.49925 0.0148 Y4 r 1.9963 2.0085 1.9909 1.9959 2.0085 2.0044 2.00075 0.0176 R 2.5019 2.5055 2.5042 2.4959 2.5044 2.4951 2.501167 0.0104 Y5 r 2.0088 2.0105 2.0049 2.0088 2.0038 1.9992 2.006 0.0113 R 2.4982 2.4966 2.504 2.4921 2.5089 2.4906 2.4984 0.0183 1.988 1.99 1.992 1.994 1.996 1.998 2 2.002 2.004 2.006 2.008 2.01 1 2 3 4 5 DemensionofInnerCircle(inch) Sample Number,s Chart of r UCL Center LCL
  • 14. r Chart Range Chart CL UCL LCL CL UCL LCL 2.00120667 2.0071282 1.995285 0.01226 0.024569 0 0 0.005 0.01 0.015 0.02 0.025 0.03 1 2 3 4 5 Range Sample Number, s Range Chart of r Center 2.485 2.49 2.495 2.5 2.505 2.51 1 2 3 4 5 DemensionofOuterCircle(inch) Sample Number, s Chart of R UCL Center LCL 𝑋
  • 15. 5.2 Product B Y direction Radius Testing Data AVG(x) Range Y1 r 3.0098 3.0044 3.0051 3.0026 2.9964 2.9956 3.002317 0.0142 R 3.9976 3.9985 4.0021 4.0016 4.0032 3.9925 3.99925 0.0107 Y2 r 2.9984 2.9973 3.0024 3.0036 2.9979 3.0035 3.000517 0.0063 R 4.0035 3.9946 3.9959 4.0031 3.9916 4.0035 3.9987 0.0119 Y3 r 3.0019 3.0026 2.9959 2.9967 3.0016 3.0025 3.0002 0.0067 R 4.0038 3.9958 3.9986 4.0025 4.0016 4.0035 4.000967 0.008 Y4 r 3.0026 3.0053 2.9935 2.9979 3.0019 3.0014 3.000433 0.0118 R 4.0009 3.9959 4.0016 3.9953 3.9929 4.0031 3.998283 0.0102 Y5 r 3.0049 3.0053 2.9959 2.9975 3.0041 3.0029 3.001767 0.0094 R 3.9989 4.0011 4.0021 4.0013 3.9989 4.0019 4.0007 0.0032 0 0.005 0.01 0.015 0.02 0.025 0.03 0.035 1 2 3 4 5 Range Sample Number,s Range Chart of R UCL Center LCL R Chart Range Chart CL UCL LCL CL UCL LCL 2.50021 2.5072232 2.493197 0.01452 0.029098 0
  • 16. r Chart Range Chart CL UCL LCL CL UCL LCL 3.00104667 3.0057221 2.996371 0.00968 0.019399 0 2.99 2.992 2.994 2.996 2.998 3 3.002 3.004 3.006 3.008 1 2 3 4 5 DemensionofInnerCircle(inch) Sample Number,s Chart of r UCL Center LCL 0 0.005 0.01 0.015 0.02 0.025 1 2 3 4 5 Range Sample Number, s Range Chart of r Center
  • 17. R Chart Range Chart CL UCL LCL CL UCL LCL 3.99958 4.0038304 3.99533 0.0088 0.017635 0 The charts show us the quality is quite well controlled during the process. While consider that the company are using some low quality machining equipment. The way to make their defect rate better is to purchase some new equipment with higher capability of controlling the precision and qualities, which would also reduce the cost significantly. Assume the defect rate reduces from 5% to 3% after using the new equipment, the quantity of required bearings to meet every 1 million will reduces from 1,052,632 3.99 3.992 3.994 3.996 3.998 4 4.002 4.004 4.006 1 2 3 4 5 DemensionofOuterCircle(inch) Sample Number, s Chart of R UCL Center LCL 𝑋 0 0.002 0.004 0.006 0.008 0.01 0.012 0.014 0.016 0.018 0.02 1 2 3 4 5 Range Sample Number,s Range Chart of R UCL Center LCL
  • 18. to 1,030,928. Cost saved per million is $5,096.14 for A and $6,190.03 for B. Calculated as the following steps. Defect Rate=5%: 𝑁 = 1,000,000 1 − 5% = 1,052,631.58 = 1,052,632 Defect Rate=3%: 𝑁 = 1,000,000 1 − 3% = 1,030,927.84 = 1,030,928 Cost Saved (Price per Bearing is $0.2348 for A, $0.2852 for B): CA=0.2348×(1,052,632-1,030,928)=$5,096.14/million CB=0.2852×(1,052,632-1,030,928)=$6,190.03/million