This document provides a 2nd progress update for the ABC Waters project at Pang Sua Pond and Toa Payoh Lorong 8. It includes an updated organization chart, site progress updates with a master programme and photos from both sites. It also includes a Project Quality Plan checklist covering requirements, plans, licenses, and submissions to various agencies. Clearances from authorities like URA, BCA and NParks are outlined. Construction methods for hoarding, piling works, and steel structures are briefly described.
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
ABC WATERS PROJECT 2nd PROGRESS UPDATE
1. ABC WATERS PROJECT AT
PANG SUA POND AND
TOA PAYOH LORONG 8
2nd Progress Update
DATE : 1 December 2014
2. Agenda of Meeting
Organization Chart (updated)
Site Progress Update
(Master Programme and Photos)
PQP Checklist
Status of clearances from Agencies/Authorities
18. PQP Checklist –
(Pang Sua Pond and Lorong 8 Toa Payoh)
No. Description Actioned
By
Submitted
On
Re-Submitted
On
Approved
On
Status
1 CONTRACT REQUIREMENT
1.1 Performance Bond Elaine Done
1.2 Insurances incl WMC PUB Done
2 PROJECT QUALITY PLAN (PQP)
2.1 Site Organisational Chart Gereld 30/06/2014 06/11/2014 07/11/2014 Done
2.2 Site Facilities Plan
a Site Office & Site Access Esther 30/07/2014 23/09/2014 23/09/2014 Done
b Project Signboards Esther 29/07/2014 17/09/2014 25/09/2014 Done
c Hoarding Artwork Esther 29/07/2014 15/09/2014 22/09/2014 Done
d Sanitary Esther 30/07/2014 23/09/2014 23/09/2014 Done
2.3 Master Construction Programme Gereld 01/09/2014 to re-submit
2.4 Statutory Licenses/Approvals
a Factory License Sally 17/06/2014 25/06/2014 Done
b Access to Site (PUB) Esther 22/09/2014 06/10/2014 Done
c Tree felling (Nparks/HDB/Town Council) Esther 01/09/2014 02/09/2014 Done
d Demolition (BCA, URA, HDB) Esther NA NA NA
e Earthworks (Powergrid, telecom etc) Esther in progress
f ECM (PUB) Gereld 09/10/2014 20/10/2014 Done
c Cable Detection report Esther 31/10/2014 Done
Approved
19. PQP Checklist –
(Pang Sua Pond and Lorong 8 Toa Payoh)
2.5 Quality Control Plan
a Pre-Condition survey Esther
18/9/2014,
9/10/2014 Done
b Setting out/ As built Survey Gereld pre-comp done
2.6 Workplace safety and Health Plan
a RA David 13/10/2014 In progress
b Safe Work Procedures David 13/10/2014 In progress
c Permit-to-work (PTW) David
d Authorised operators David
e List of Manpower & machinery Gereld
f Public engagement Plan David
2.7 Suppliers and Subcontractors
a Registered surveyors Gereld on board
b Pre-condition surveyor Gereld on board
c Licensed Cable Detector (LCDW) Gereld on board
d Piler Phua 29/09/2014
e Steel fabricator Phua 29/09/2014
f Ready Mix Esther 29/09/2014
g Rebar and WSF Esther 29/09/2014
h RC works Esther 29/09/2014
i Composite timber Gereld 29/09/2014
j Wetland materials Gereld
k Plumber Gereld
l Electrical Subcon/ LEW Gereld
m Accredited laboratory Gereld
20. PQP Checklist –
(Pang Sua Pond and Lorong 8 Toa Payoh)
2.8 Shopdrawings
a Hoarding design Esther 26/09/2014 02/10/2014 Done
b Pile setting out plan Gereld
c Steel structures Gereld 18/11/2014
d Floating wetland design Gereld
e Instream Wetland design Gereld 28/10/2014 11/11/2014
f Timber deck Gereld
g Railing details Gereld/Sally 14/11/2014 (galv. Railing for TPY)
2.9 Material/ System Quality Plan
a Fitness equipment Esther 10/11/2014
b EPDM Esther 21/11/2014
c Composite timber Esther
d Green Roof Esther
e Env swale Esther
f Floating wetland Esther
g Instream wetland Esther
h Lightings Esther
i Aerators Esther
j Pump Esther
k Railings Esther
l Membrane roof Esther
2.10 Method Statement
Hoarding Esther 26/09/2014 02/10/2014 Done
Piling & Steel Structure Gereld 14/11/2014 for piling work
Timber boardwalk Gereld
Wetlands Gereld 13/11/2014 for instream wetland
Membrane Structures Gereld
RC Structures Gereld
21. Agencies / Authorities Clearance Update
S/No. Agencies Submission/ Resubmission Date Reply/ Approval Date Remarks
1 URA
1st Subm – 04 Feb 2014
2nd Subm – 19 May 2014
3rd Subm – 09 Jul 2014
1st Reply – 11 Feb 2014
2nd Reply – 16 Jun 2014
3rd Reply – 21 Jul 2014
PP and WP approved
2 BCA
ST01 (RC Seating Works)
1st Subm – 20 Aug 2014
2nd Subm – 19 May 2014
ST02 (Piling and Pilecap Works)
ST03 (Steel Structures Works)
ST01 (RC Seating Works)
1st Reply – 01 Sep 2014
1st Reply – 01 Sep 2014
ST02 (Piling and Pilecap Works)
ST03 (Steel Structures Works)
ST01 Approved
ST02 (Already amended base on AC
comments, to submit to BCA)
ST03 (In Progress)
Permit to start works - Approved
3 NParks 1st Subm – 24 Oct 2014 1st Reply – 03 Nov 2014
Approved
(To fell trees at site storage and barge
berthing area)
(Pang Sua Pond)
(Lorong 8 Toa Payoh)
S/No. Agencies Submission/ Resubmission Date Reply/ Approval Date Remarks
1 URA 1st Subm – 05 Feb 2014 1st Reply – 26 Feb 2014 PP approved
2 BCA
In Progress Green Roof Pavilion In Progress
(To proceed with rain garden and railing
mock-up first)