SlideShare a Scribd company logo
1 of 24
ABC WATERS PROJECT AT
PANG SUA POND AND
TOA PAYOH LORONG 8
2nd Progress Update
DATE : 1 December 2014
Agenda of Meeting
 Organization Chart (updated)
 Site Progress Update
(Master Programme and Photos)
 PQP Checklist
 Status of clearances from Agencies/Authorities
Organization Chart (Updated)
Site Progress Update – Master Programme
Work Programme @Pang Sua Pond
Hoarding
Fortnightly Schedule:
1. Erection of hoarding. (close the lower deck)
2. Installation of hoarding artwork.
3. Demolition and RC works.
Site Progress Update – Photos
(Pang Sua Pond)
Site Progress Update – Photos
(Pang Sua Pond)
Site Progress Update – Photos
(Pang Sua Pond)
Site Progress Update – Photos
(Pang Sua Pond)
Site Progress Update – Photos
(Pang Sua Pond)
Site Progress Update – Photos
Before
After
Site Progress Update – Photos
(Toa Payoh Lorong 8)
Site Progress Update – Photos
(Toa Payoh)
Before
Site Progress Update – Photos
(Toa Payoh)
Site Progress Update – Photos
(Toa Payoh)
Site Progress Update – Photos
(Toa Payoh)
PQP Checklist –
(Pang Sua Pond and Lorong 8 Toa Payoh)
No. Description Actioned
By
Submitted
On
Re-Submitted
On
Approved
On
Status
1 CONTRACT REQUIREMENT
1.1 Performance Bond Elaine Done
1.2 Insurances incl WMC PUB Done
2 PROJECT QUALITY PLAN (PQP)
2.1 Site Organisational Chart Gereld 30/06/2014 06/11/2014 07/11/2014 Done
2.2 Site Facilities Plan
a Site Office & Site Access Esther 30/07/2014 23/09/2014 23/09/2014 Done
b Project Signboards Esther 29/07/2014 17/09/2014 25/09/2014 Done
c Hoarding Artwork Esther 29/07/2014 15/09/2014 22/09/2014 Done
d Sanitary Esther 30/07/2014 23/09/2014 23/09/2014 Done
2.3 Master Construction Programme Gereld 01/09/2014 to re-submit
2.4 Statutory Licenses/Approvals
a Factory License Sally 17/06/2014 25/06/2014 Done
b Access to Site (PUB) Esther 22/09/2014 06/10/2014 Done
c Tree felling (Nparks/HDB/Town Council) Esther 01/09/2014 02/09/2014 Done
d Demolition (BCA, URA, HDB) Esther NA NA NA
e Earthworks (Powergrid, telecom etc) Esther in progress
f ECM (PUB) Gereld 09/10/2014 20/10/2014 Done
c Cable Detection report Esther 31/10/2014 Done
Approved
PQP Checklist –
(Pang Sua Pond and Lorong 8 Toa Payoh)
2.5 Quality Control Plan
a Pre-Condition survey Esther
18/9/2014,
9/10/2014 Done
b Setting out/ As built Survey Gereld pre-comp done
2.6 Workplace safety and Health Plan
a RA David 13/10/2014 In progress
b Safe Work Procedures David 13/10/2014 In progress
c Permit-to-work (PTW) David
d Authorised operators David
e List of Manpower & machinery Gereld
f Public engagement Plan David
2.7 Suppliers and Subcontractors
a Registered surveyors Gereld on board
b Pre-condition surveyor Gereld on board
c Licensed Cable Detector (LCDW) Gereld on board
d Piler Phua 29/09/2014
e Steel fabricator Phua 29/09/2014
f Ready Mix Esther 29/09/2014
g Rebar and WSF Esther 29/09/2014
h RC works Esther 29/09/2014
i Composite timber Gereld 29/09/2014
j Wetland materials Gereld
k Plumber Gereld
l Electrical Subcon/ LEW Gereld
m Accredited laboratory Gereld
PQP Checklist –
(Pang Sua Pond and Lorong 8 Toa Payoh)
2.8 Shopdrawings
a Hoarding design Esther 26/09/2014 02/10/2014 Done
b Pile setting out plan Gereld
c Steel structures Gereld 18/11/2014
d Floating wetland design Gereld
e Instream Wetland design Gereld 28/10/2014 11/11/2014
f Timber deck Gereld
g Railing details Gereld/Sally 14/11/2014 (galv. Railing for TPY)
2.9 Material/ System Quality Plan
a Fitness equipment Esther 10/11/2014
b EPDM Esther 21/11/2014
c Composite timber Esther
d Green Roof Esther
e Env swale Esther
f Floating wetland Esther
g Instream wetland Esther
h Lightings Esther
i Aerators Esther
j Pump Esther
k Railings Esther
l Membrane roof Esther
2.10 Method Statement
Hoarding Esther 26/09/2014 02/10/2014 Done
Piling & Steel Structure Gereld 14/11/2014 for piling work
Timber boardwalk Gereld
Wetlands Gereld 13/11/2014 for instream wetland
Membrane Structures Gereld
RC Structures Gereld
Agencies / Authorities Clearance Update
S/No. Agencies Submission/ Resubmission Date Reply/ Approval Date Remarks
1 URA
1st Subm – 04 Feb 2014
2nd Subm – 19 May 2014
3rd Subm – 09 Jul 2014
1st Reply – 11 Feb 2014
2nd Reply – 16 Jun 2014
3rd Reply – 21 Jul 2014
PP and WP approved
2 BCA
ST01 (RC Seating Works)
1st Subm – 20 Aug 2014
2nd Subm – 19 May 2014
ST02 (Piling and Pilecap Works)
ST03 (Steel Structures Works)
ST01 (RC Seating Works)
1st Reply – 01 Sep 2014
1st Reply – 01 Sep 2014
ST02 (Piling and Pilecap Works)
ST03 (Steel Structures Works)
ST01 Approved
ST02 (Already amended base on AC
comments, to submit to BCA)
ST03 (In Progress)
Permit to start works - Approved
3 NParks 1st Subm – 24 Oct 2014 1st Reply – 03 Nov 2014
Approved
(To fell trees at site storage and barge
berthing area)
(Pang Sua Pond)
(Lorong 8 Toa Payoh)
S/No. Agencies Submission/ Resubmission Date Reply/ Approval Date Remarks
1 URA 1st Subm – 05 Feb 2014 1st Reply – 26 Feb 2014 PP approved
2 BCA
In Progress Green Roof Pavilion In Progress
(To proceed with rain garden and railing
mock-up first)
Method for Piling Works
For Steel Pipe Pile
Method for Piling Works
Piling Machine for RC Pile
THANK YOU

More Related Content

Similar to ABC WATERS PROJECT 2nd PROGRESS UPDATE

61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 2014112961T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129James Zhang (Chi, Zhang)
 
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...yang lu
 
Barry Moran ROV - Plough Log Book.
Barry Moran ROV - Plough Log Book.Barry Moran ROV - Plough Log Book.
Barry Moran ROV - Plough Log Book.bazza323
 
TonyCV updated5dec16

TonyCV updated5dec16
TonyCV updated5dec16

TonyCV updated5dec16
Tony Newlands
 
Chris Irvine Resume 27.09.2013
Chris Irvine Resume 27.09.2013Chris Irvine Resume 27.09.2013
Chris Irvine Resume 27.09.2013Chris Irvine
 
Update - CV[2 e] - --AIS
Update - CV[2 e] - --AISUpdate - CV[2 e] - --AIS
Update - CV[2 e] - --AISFelix Doghudje
 
ALVIN'S CURRICULUM VITAE 2017
ALVIN'S CURRICULUM VITAE 2017ALVIN'S CURRICULUM VITAE 2017
ALVIN'S CURRICULUM VITAE 2017Alvin Chen
 
DOSH PTI Presentation for FPSO BERTAM LMBV (1)
DOSH PTI Presentation for FPSO BERTAM LMBV (1)DOSH PTI Presentation for FPSO BERTAM LMBV (1)
DOSH PTI Presentation for FPSO BERTAM LMBV (1)Mohd Zaini Baharum
 
Philip Harrison Personal Resume 2017
Philip Harrison Personal Resume 2017Philip Harrison Personal Resume 2017
Philip Harrison Personal Resume 2017Philip Harrison
 
Morritt andrew cv 2017 ref
Morritt andrew cv 2017 refMorritt andrew cv 2017 ref
Morritt andrew cv 2017 refAndy Morritt
 
MORRITT Andrew CV 2017 Ref
MORRITT Andrew CV 2017 RefMORRITT Andrew CV 2017 Ref
MORRITT Andrew CV 2017 RefAndy Morritt
 
Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2Nicholas Naing
 
Presentation
PresentationPresentation
PresentationKrm Chari
 
RDS as at 160527
RDS as at 160527RDS as at 160527
RDS as at 160527Rob Smith
 

Similar to ABC WATERS PROJECT 2nd PROGRESS UPDATE (20)

61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 2014112961T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
 
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
 
10. Overall Implementation Programme
10. Overall Implementation Programme10. Overall Implementation Programme
10. Overall Implementation Programme
 
Barry Moran ROV - Plough Log Book.
Barry Moran ROV - Plough Log Book.Barry Moran ROV - Plough Log Book.
Barry Moran ROV - Plough Log Book.
 
TonyCV updated5dec16

TonyCV updated5dec16
TonyCV updated5dec16

TonyCV updated5dec16

 
Chris Irvine Resume 27.09.2013
Chris Irvine Resume 27.09.2013Chris Irvine Resume 27.09.2013
Chris Irvine Resume 27.09.2013
 
CV.2016
CV.2016CV.2016
CV.2016
 
Update - CV[2 e] - --AIS
Update - CV[2 e] - --AISUpdate - CV[2 e] - --AIS
Update - CV[2 e] - --AIS
 
ALVIN'S CURRICULUM VITAE 2017
ALVIN'S CURRICULUM VITAE 2017ALVIN'S CURRICULUM VITAE 2017
ALVIN'S CURRICULUM VITAE 2017
 
CV Herwandi
CV HerwandiCV Herwandi
CV Herwandi
 
Merrit CV
Merrit CVMerrit CV
Merrit CV
 
DOSH PTI Presentation for FPSO BERTAM LMBV (1)
DOSH PTI Presentation for FPSO BERTAM LMBV (1)DOSH PTI Presentation for FPSO BERTAM LMBV (1)
DOSH PTI Presentation for FPSO BERTAM LMBV (1)
 
Philip Harrison Personal Resume 2017
Philip Harrison Personal Resume 2017Philip Harrison Personal Resume 2017
Philip Harrison Personal Resume 2017
 
Tin's cv
Tin's cvTin's cv
Tin's cv
 
Morritt andrew cv 2017 ref
Morritt andrew cv 2017 refMorritt andrew cv 2017 ref
Morritt andrew cv 2017 ref
 
MORRITT Andrew CV 2017 Ref
MORRITT Andrew CV 2017 RefMORRITT Andrew CV 2017 Ref
MORRITT Andrew CV 2017 Ref
 
Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2
 
CV.FAHRUDIN ASMAN
CV.FAHRUDIN ASMANCV.FAHRUDIN ASMAN
CV.FAHRUDIN ASMAN
 
Presentation
PresentationPresentation
Presentation
 
RDS as at 160527
RDS as at 160527RDS as at 160527
RDS as at 160527
 

Recently uploaded

OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...NETWAYS
 
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...henrik385807
 
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...Pooja Nehwal
 
NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)
NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)
NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)Basil Achie
 
LANDMARKS AND MONUMENTS IN NIGERIA.pptx
LANDMARKS  AND MONUMENTS IN NIGERIA.pptxLANDMARKS  AND MONUMENTS IN NIGERIA.pptx
LANDMARKS AND MONUMENTS IN NIGERIA.pptxBasil Achie
 
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝soniya singh
 
Simulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with AerialistSimulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with AerialistSebastiano Panichella
 
call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@vikas rana
 
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...NETWAYS
 
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...NETWAYS
 
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfCTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfhenrik385807
 
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
Genesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptxGenesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptxFamilyWorshipCenterD
 
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls KolkataRussian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkataanamikaraghav4
 
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Krijn Poppe
 
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...NETWAYS
 
SBFT Tool Competition 2024 -- Python Test Case Generation Track
SBFT Tool Competition 2024 -- Python Test Case Generation TrackSBFT Tool Competition 2024 -- Python Test Case Generation Track
SBFT Tool Competition 2024 -- Python Test Case Generation TrackSebastiano Panichella
 
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...NETWAYS
 
Microsoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AIMicrosoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AITatiana Gurgel
 
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdfOpen Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdfhenrik385807
 

Recently uploaded (20)

OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
OSCamp Kubernetes 2024 | Zero-Touch OS-Infrastruktur für Container und Kubern...
 
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
 
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
 
NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)
NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)
NATIONAL ANTHEMS OF AFRICA (National Anthems of Africa)
 
LANDMARKS AND MONUMENTS IN NIGERIA.pptx
LANDMARKS  AND MONUMENTS IN NIGERIA.pptxLANDMARKS  AND MONUMENTS IN NIGERIA.pptx
LANDMARKS AND MONUMENTS IN NIGERIA.pptx
 
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
Call Girls in Sarojini Nagar Market Delhi 💯 Call Us 🔝8264348440🔝
 
Simulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with AerialistSimulation-based Testing of Unmanned Aerial Vehicles with Aerialist
Simulation-based Testing of Unmanned Aerial Vehicles with Aerialist
 
call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@call girls in delhi malviya nagar @9811711561@
call girls in delhi malviya nagar @9811711561@
 
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
Open Source Camp Kubernetes 2024 | Monitoring Kubernetes With Icinga by Eric ...
 
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
Open Source Camp Kubernetes 2024 | Running WebAssembly on Kubernetes by Alex ...
 
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfCTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
 
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Rohini Delhi 💯Call Us 🔝8264348440🔝
 
Genesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptxGenesis part 2 Isaiah Scudder 04-24-2024.pptx
Genesis part 2 Isaiah Scudder 04-24-2024.pptx
 
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls KolkataRussian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
 
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
Presentation for the Strategic Dialogue on the Future of Agriculture, Brussel...
 
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
 
SBFT Tool Competition 2024 -- Python Test Case Generation Track
SBFT Tool Competition 2024 -- Python Test Case Generation TrackSBFT Tool Competition 2024 -- Python Test Case Generation Track
SBFT Tool Competition 2024 -- Python Test Case Generation Track
 
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
OSCamp Kubernetes 2024 | SRE Challenges in Monolith to Microservices Shift at...
 
Microsoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AIMicrosoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AI
 
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdfOpen Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
Open Source Strategy in Logistics 2015_Henrik Hankedvz-d-nl-log-conference.pdf
 

ABC WATERS PROJECT 2nd PROGRESS UPDATE

  • 1. ABC WATERS PROJECT AT PANG SUA POND AND TOA PAYOH LORONG 8 2nd Progress Update DATE : 1 December 2014
  • 2. Agenda of Meeting  Organization Chart (updated)  Site Progress Update (Master Programme and Photos)  PQP Checklist  Status of clearances from Agencies/Authorities
  • 4. Site Progress Update – Master Programme
  • 6. Hoarding Fortnightly Schedule: 1. Erection of hoarding. (close the lower deck) 2. Installation of hoarding artwork. 3. Demolition and RC works.
  • 7. Site Progress Update – Photos (Pang Sua Pond)
  • 8. Site Progress Update – Photos (Pang Sua Pond)
  • 9. Site Progress Update – Photos (Pang Sua Pond)
  • 10. Site Progress Update – Photos (Pang Sua Pond)
  • 11. Site Progress Update – Photos (Pang Sua Pond)
  • 12. Site Progress Update – Photos Before After
  • 13. Site Progress Update – Photos (Toa Payoh Lorong 8)
  • 14. Site Progress Update – Photos (Toa Payoh) Before
  • 15. Site Progress Update – Photos (Toa Payoh)
  • 16. Site Progress Update – Photos (Toa Payoh)
  • 17. Site Progress Update – Photos (Toa Payoh)
  • 18. PQP Checklist – (Pang Sua Pond and Lorong 8 Toa Payoh) No. Description Actioned By Submitted On Re-Submitted On Approved On Status 1 CONTRACT REQUIREMENT 1.1 Performance Bond Elaine Done 1.2 Insurances incl WMC PUB Done 2 PROJECT QUALITY PLAN (PQP) 2.1 Site Organisational Chart Gereld 30/06/2014 06/11/2014 07/11/2014 Done 2.2 Site Facilities Plan a Site Office & Site Access Esther 30/07/2014 23/09/2014 23/09/2014 Done b Project Signboards Esther 29/07/2014 17/09/2014 25/09/2014 Done c Hoarding Artwork Esther 29/07/2014 15/09/2014 22/09/2014 Done d Sanitary Esther 30/07/2014 23/09/2014 23/09/2014 Done 2.3 Master Construction Programme Gereld 01/09/2014 to re-submit 2.4 Statutory Licenses/Approvals a Factory License Sally 17/06/2014 25/06/2014 Done b Access to Site (PUB) Esther 22/09/2014 06/10/2014 Done c Tree felling (Nparks/HDB/Town Council) Esther 01/09/2014 02/09/2014 Done d Demolition (BCA, URA, HDB) Esther NA NA NA e Earthworks (Powergrid, telecom etc) Esther in progress f ECM (PUB) Gereld 09/10/2014 20/10/2014 Done c Cable Detection report Esther 31/10/2014 Done Approved
  • 19. PQP Checklist – (Pang Sua Pond and Lorong 8 Toa Payoh) 2.5 Quality Control Plan a Pre-Condition survey Esther 18/9/2014, 9/10/2014 Done b Setting out/ As built Survey Gereld pre-comp done 2.6 Workplace safety and Health Plan a RA David 13/10/2014 In progress b Safe Work Procedures David 13/10/2014 In progress c Permit-to-work (PTW) David d Authorised operators David e List of Manpower & machinery Gereld f Public engagement Plan David 2.7 Suppliers and Subcontractors a Registered surveyors Gereld on board b Pre-condition surveyor Gereld on board c Licensed Cable Detector (LCDW) Gereld on board d Piler Phua 29/09/2014 e Steel fabricator Phua 29/09/2014 f Ready Mix Esther 29/09/2014 g Rebar and WSF Esther 29/09/2014 h RC works Esther 29/09/2014 i Composite timber Gereld 29/09/2014 j Wetland materials Gereld k Plumber Gereld l Electrical Subcon/ LEW Gereld m Accredited laboratory Gereld
  • 20. PQP Checklist – (Pang Sua Pond and Lorong 8 Toa Payoh) 2.8 Shopdrawings a Hoarding design Esther 26/09/2014 02/10/2014 Done b Pile setting out plan Gereld c Steel structures Gereld 18/11/2014 d Floating wetland design Gereld e Instream Wetland design Gereld 28/10/2014 11/11/2014 f Timber deck Gereld g Railing details Gereld/Sally 14/11/2014 (galv. Railing for TPY) 2.9 Material/ System Quality Plan a Fitness equipment Esther 10/11/2014 b EPDM Esther 21/11/2014 c Composite timber Esther d Green Roof Esther e Env swale Esther f Floating wetland Esther g Instream wetland Esther h Lightings Esther i Aerators Esther j Pump Esther k Railings Esther l Membrane roof Esther 2.10 Method Statement Hoarding Esther 26/09/2014 02/10/2014 Done Piling & Steel Structure Gereld 14/11/2014 for piling work Timber boardwalk Gereld Wetlands Gereld 13/11/2014 for instream wetland Membrane Structures Gereld RC Structures Gereld
  • 21. Agencies / Authorities Clearance Update S/No. Agencies Submission/ Resubmission Date Reply/ Approval Date Remarks 1 URA 1st Subm – 04 Feb 2014 2nd Subm – 19 May 2014 3rd Subm – 09 Jul 2014 1st Reply – 11 Feb 2014 2nd Reply – 16 Jun 2014 3rd Reply – 21 Jul 2014 PP and WP approved 2 BCA ST01 (RC Seating Works) 1st Subm – 20 Aug 2014 2nd Subm – 19 May 2014 ST02 (Piling and Pilecap Works) ST03 (Steel Structures Works) ST01 (RC Seating Works) 1st Reply – 01 Sep 2014 1st Reply – 01 Sep 2014 ST02 (Piling and Pilecap Works) ST03 (Steel Structures Works) ST01 Approved ST02 (Already amended base on AC comments, to submit to BCA) ST03 (In Progress) Permit to start works - Approved 3 NParks 1st Subm – 24 Oct 2014 1st Reply – 03 Nov 2014 Approved (To fell trees at site storage and barge berthing area) (Pang Sua Pond) (Lorong 8 Toa Payoh) S/No. Agencies Submission/ Resubmission Date Reply/ Approval Date Remarks 1 URA 1st Subm – 05 Feb 2014 1st Reply – 26 Feb 2014 PP approved 2 BCA In Progress Green Roof Pavilion In Progress (To proceed with rain garden and railing mock-up first)
  • 22. Method for Piling Works For Steel Pipe Pile
  • 23. Method for Piling Works Piling Machine for RC Pile