1. FCC GANTRY FOR
DETECTOR
LOWERING STUDY
Potential designs and Contractors
Julia Collins
Thursday 25th of August 2016
Thanks to John Osborne (SMB-SE-FAS), Hubert Gerwig (EP-CMX-EI) , Raul Fernandez Ortega (SMB-SE-DOP)
2. Problem
presentation
In-situ (underground) assembly of
detectors impractical
CMS heaviest component: 2000
tons
FCC (current) heaviest component
estimate: approx. 6000 tons
Design a static gantry crane
capable of lowering 6000 tons
down 200m
16. Further issues to look into
■ Class 3 cross section will require stiffeners
■ Foundations
– Need to be far enough away from shaft
– This increases the lever arm and greatly increases the moment
generated
– Larger cross section needed
17. Conclusion
■ Based on calculations the crane itself seems feasible
■ Similar capacity cranes have been built before
■ The concrete plug is not expected to be a problem
■ Investigate further the hydraulic jacks for concrete plug and the column foundations
■ DLT manufactures appropriate stand-jackers