Budiselich time series
- 2. 09/12/11 - Start of Implementation, looking upstream, vegetation has been cleared
- 4. Weirs 1 and 7 (upper- and lower-most) complete, work begins on weirs 2 and 6
- 5. Weirs 1, 2, 5, 6 & 7 complete, placing engineered streambed before completing weirs 3 & 4
- 6. 10/1/11 – Project complete, test flows to begin soon & fish attraction flows will begin 10/27/11