IOSR Journal of Engineering (IOSRJEN) www.iosrjen.org
ISSN (e): 2250-3021, ISSN (p): 2278-8719
Vol. 04, Issue 07 (July. 2014), ||V1|| PP 42-45
International organization of Scientific Research 42 | P a g e
Practical Approach for Detection Of Failure Of Distribution
Transformers And Their Remidies.
B.Suresh Kumar
Asst.Professor-CBIT-Hyderabad
I. INTRODUCTION
Power is generated at lower voltage like 11KV and 13.8 KV in generating stations which are far away
from the load centre. The power is transmitted to the load centers at extra high voltages like 132KV, 220KV and
400KV to reduce the losses and to improve the system efficiency. The power of these higher voltages is stepped
down at various E.H.T., 33/11KV and 11KV/400V Sub-stations to attain the requirements of the consumers of
different categories.
As the demand for electrical power is increasing day by day, the distribution system plays an important role in
catering the needs of consumers. For reliability in maintaining un-interrupted power supply one must have an
efficient distribution system. The major components in the distribution system are 11KV feeders, Distribution
transformers and LT 3 phase 4 wire line.
One of the most vital component of the above, the heart of the system is distribution transformer.
Hence the failure of a distribution transformer leads to break down in power supply to all the LT consumers.
Therefore the reliability in power supply mainly depends on the reliable functioning of distribution transformer.
At present about 28204 distribution transformers of various capacities rating from 10 KVA to 500KVA
are installed in Medak district. The failure rate is about 14.5% of total installed transformers which accounts for
higher side.
In the present project work it is proposed to investigate the practical and technical causes for failure of
distribution transformers and suggested suitable remedial measures to minimize the failure and to study the
testing procedures which are being adopted in APCPDCL. For this purpose the No. of distribution transformers
existing in Sangareddy, Jogipet, Medak, Toopran, Siddipet have been considered for cause study.
1.2 ORGANISATION OF PROJECT WORK
The project report is organized in 6 (six) chapters excluding the introductory chapter it has 5 chapters. The
Chapter-II deals with the failure of the distribution transformers, the general causes for failure and maintenance
schedule recommended/adopted by APCPDCL
1.3 STATEMENT OF THE PROBLEM:
An attempt has been made to analyze the practical causes contributing to the failure of distribution transformers.
2.DISTRIBUTION TRANSFORMER GENERAL CAUSES FOR FAILURES AND MAINTENANCE
SCHEDULE
2.1 INTRODUCTION
In this chapter an attempt is made to explain the essential features involved in construction, operation,
maintenance and the reasons for failure of transformers. Specific emphasis is made on what is likely to happen
if a particular item of maintenance is not done in-time.
The power that is generated at various power stations is stepped up and transmitted at extra high voltages viz.,
132 KV, 220 KV and 400 KV for reducing the transmission line losses. The voltage stepped down to service
voltages at various receiving stations depending upon the requirement of the prospective consumers. The higher
voltage is stepped down to 11KV/400V and is made available at L.T. consumers installations. It is roughly
estimated that the power that is generated is transformed 3 or 4 times before it reaches the consumers
installations. Thus the distribution transformer is an essential device in the distribution network which step
down the voltage
2.2. THE DISTRIBUTION TRANSFORMER COMPRISES OF THE FOLLOWING FEATURES.
1. Magnetic Circuits : Comprising of limbs, yoke and clamp Structures.
2. Electric Circuits :The primary and secondary windings, insulation and bracing devices.
3. Terminals: Tappings, tap switch, insulators i.e. bushings and leads.
4.Others: Tank, Oils, Radiators, conservator,Breather and auxiliary apparatus.
2.3 FUNCTIONS OF A DISTRIBUTION TRANSFORMER:
Practical Approach For Detection Of Failure Of Distribution Transformers And Their Remidies.
International organization of Scientific Research 43 | P a g e
The Distribution Transformer is static equipment and is used to either step down or step up the voltage
as the case may be. The capacity of the transformers is the extent of power in KVA that can be handled by the
transformer while it does the voltage transformation at the pre-determined ratio. The number of turns in H.V.
and L.V. windings determine the voltage ratio.
Suppose the primary winding has N.P. number of turns and secondary winding has N.S. number of
turns and the primary and secondary voltages are VP and VS respectively, the voltage ratio of the Distribution
Transformer will be equivalent to
VP/VS = NP/NS
Therefore the number of turns on HV and LV Windings also decide the voltage ratio and the size of the
winding wire decide the capacity of the transformer.
2.4 CAUSES OF FAILURE OF DISTRIBUTION TRANSFORMERS:
From a study on the various causes of failure of a transformer it is easy to know what is to be done to prevent
them. The various causes for failure of distribution transformers are listed below.
2.4.1 FAILURES DUE TO MECHANICAL DAMAGES
These are generally (1) oil leakages (2) flash over of bushings.
1. The welding of the main tank may be defective and also the fillings are not leak proof. This causes oil to leak
reducing the oil level in the transformer causing heating of winding and leading to a certain break-down of the
equipment. Rough handling during transport may also contribute to leak.
2. The LT terminals connected through cables to LT take off lines. If these cables are not properly wired
through wooden cleats they cause some loading on LT Bush rods and finally results to burnt out.
3. Deposits of coal dust, saline or chemicals on the bushing may cause a flash over, as the bushings will loose
their insulating properties.
4. Sufficient place around a transformer to dissipate heat must be provided. If two transformers are kept close
the surfaces may get clogged and oil temperature increases endangering to coil insulation.
5. Vapours at the top of an oil cooled transformers, may be explosive. Bringing naked lamps at the places may
cause damage.
2.4.2 FAILURE IN DI-ELECTRIC CIRCUITS:
1. Moisture entering the tank by breathing action of transformer reduces the di-electric strength of oil .The
results in break down from coils or terminal leads to tank or core structures. The greatest damages is however
the inter turns short in the coils.
2. Deterioration of oil may occur due to prolonged over loading of the transformer. This action is aggravated by
the presence of copper and lead. When oil temperature increases formation of sludge, water and acids are
accelerated.
3. Certain amount of oil is lost due to evaporation and oxidation while the transformer is in service. Periodical
topping up of oil level with fresh tested oil is necessary, leads to unit gets over heated.
4. Narrow oil ducts and improper ventilation reduce the useful life of a transformer. Oil insulation turns brittle
and may get punctured on account of this.
5. Some times the clearance, provided between phases is insufficient. Also insertion of press board barriers may
aggravate as they may up set the di-electric stress to throw too much stress across the coil spaces and across the
barriers.
6. Wooden ducts provided for taking the terminal leads over them should be properly dried. These may cause
short circuit between tapping leads.
7. Presence of foreign particles in oil reduces the di-electric strength of the insulating oil and may cause a flash
over resulting in serious break down of the transformer.
8. When the acidity value of the oil increases, it will promote oxidation of the metal parts and results in a break-
down.
SAFE VALUES FOR OIL
Di-electric strength: 30 KV for 1 minute between gap of 2.5mm 40 KV instant.
Acidity: Upto 0.7m.grs/KCH per gram of oil satisfactory.
2.4.3. FAILURE IN ELECTRIC CIRCUITS:
1. When moisture manages to ingress through the fabric insulation of the coils it causes short circuit between
turns sooner or later. Impregnation of coils by applying varnish so that it penetrates deep enough to the inner
layers of the coils is to be ensured. Failures from this cause are most common.
Practical Approach For Detection Of Failure Of Distribution Transformers And Their Remidies.
International organization of Scientific Research 44 | P a g e
2. Presence of sharp edges on the copper conductors may cause a short circuit between adjacent turns when the
transformer vibrates on load or when the windings are subjected to repeated electromagnets stresses cause
adjacent turns coming into contact.
3. One or more turns in a coil may get dis-lodged and a short circuit between them may result, when heavy
external short circuit occurs and if the same is not cleared by fuses intime. Break down may not immediately
occur but when the transformer vibrates on load dislodged coils may take place causing a break down.
4. Improper drying out and applying full voltage with poor I.R.values will result in failure of insulation between
adjacent layers. The I.R. values for a 11kv/440v distribution transformers are given below:
The I.R. values in mega ohms are to be taken with a 1000v megger.
-----------------------------------------------------------------------------------------------------
Temperature 11kv/440v distribution Transformer
HT to LT HT to E LT to E
------------------------------------------------------------------------------------------------------
60 C 65 50 25
50C 130 100 50
40C 260 200 100
30C above above above
250 200 100
------------------------------------------------------------------------------------------------------
Whenever readings are taken at ambient temperature, the temperature also is to be noted.
5. Sudden changes in load cause sudden expansion and contraction of copper and is likely to damage the
insulation fabric.
6. Where individual H.V. coils are designed to have too great a radial depth, compared to its height, hot spots
may develop in the interior of the coils due to in adequate oil passage allowed. The insulation becomes brittle
and short circuit between turns may result.
7. Over heat on load occurs badly soldered joints and oil gets carbonized locally. The heat at the joints will be
conducted to a certain length in the copper coil and the insulation may get carbonized to a little extent resulting
in a short circuit between turns.
8. When external short circuit occurs, the coils get displaced violently as a result of the internal imbalance in
electromagnetic conditions.
9. Sustained heavy over loads produce high temperature throughout the transformer. The coil insulation
becomes brittle and in the course of time flakes off the conductors at places resulting in short circuit between
turns. Transformers with a high ratio of copper losses to iron losses are less able to withstand over load and are
therefore more liable to fail on account of sustained over loading.
10. The tap adjusting leads should be carefully handled to ensure that wrong leads are not joined otherwise part
of winding may get short circuited and heavy currents circulate in the short circuited windings which would
produce a fault between turns.
11. It is to be ensured that bolted joints and all connection are tightly screwed and locked lest they may become
loose in service due to vibrations produced and such joints get heated up rapidly.
12. When a transformer is switched off the magnetizing current and thus the magnetic flux tends to collapse
instantaneously. Due to various reasons this some time does at a much more rapid date than corresponding
normal cyclic rate of change and as a result high voltage rises may occur.
13. Short circuit between turns, break-down of windings to earth and puncture of insulation may take place due
to following phenomenon:-
(a) Lightening surges reaching the transformer, usually for the damage in the surge impedance and coils get
damaged as they take the burnt of the shock.
(b) Excessive voltage set-up by surges may be accent rated at open ended tappings, at any point of change of
surge impedance like at termination of conductor reinforcement where employed, spare between series coils, at
the neutral or midpoint. Extra insulation is to be provided at these points.
2.4.4. FAILURES IN MAGNETIC CIRCUITS
1. The laminations are clamped together by inserting bolts through core and yoke. The bolts are provided with
insulation around them which may give way. This total amount to a short in lamination causing local eddy
currents. When this trouble occurs, in due two bolts simultaneously they form a short circuit turn through which
magnetic flux passes. If one of the bolts situated at the ends of the limb fail simultaneously they form a short
circuit turn through which magnetic flux passes. If one of the bolts situated at the ends of the limb fail
simultaneously with an adjacent bolt-in-the yokes. The patch between the two bolts is threaded by almost the
entire value of the magnetic flux when passing from the core to the yoke. The heat generated is so severe to
Practical Approach For Detection Of Failure Of Distribution Transformers And Their Remidies.
International organization of Scientific Research 45 | P a g e
cause a distortion of the whole core also causing charring of the insulation and a resultant short circuit between
turns of adjacent windings.
2. Failure may occur of insulation between lamination and insulation between yoke clamping bolts fails. This
registers an increase in the iron losses of the transformer.
3. Core clamping bolts should be securely tightened and locked lest vibration will set up causing damage of core
insulation and produce failures.
4. Care should be taken to ensure that the edges of the core and yoke lamination do not develop burns which
produce local short circuit in the lamination.
5. No metallic fillings should be allowed to be present in between lamination in finished transformers which
causes short circuit.
2.5. GENERAL REMARKS:
1. Almost all the parts in a transformer liable to failure on opening a failed transformer it is often very difficult
to say definitely the reason for the failure as all evidence is eliminated by the very nature of the break down.
Consequently the cause of failure is only a matter of guess.
At best: A close idea of the real cause may be obtained by a careful study of the transformer and the operating
conditions obtaining at the time of failure of transformers and also the weather conditions.
2. Careful design and construction on the part of the manufacturer, without sub-ordinating quality to competition
in market is necessary, on the part of purchasers also the economic behind the purchase should not be arrive at
by cost alone but by performance guarantee.
3. Timely preventive maintenance is the back bone for safe and efficient operation of any electrical equipment
the maintenance scheduled as well as the construction standards drown up by the APCPDCL are exhaustive
enough to detect and prevent a possible failure ahead. If these are adhering it may be possible to reduce the
failures to a large extent.
2.6 PRE –COMMISSIONING TESTS
The following tests are to be done before commissioning a distribution transformer. These are termed as pre-
commissioning tests.
1. Megger Test: - This test is to be done with a 1000v megger. At normal ambient temperature the I.R.Values
should not be less than the following.
H.T. to Body - 150 MegaOhms
L.T. to Body - 100 Mega Ohms
H.T. to L.T. - 150 Mega Ohms
b) Whenever possible and alternate L.T. Supply is available L.T. Supply may be given to the H.V. Terminals
and the voltages on L.V. side measured between phase and phase and phase and neutral. This not only confirms
the correctness of tap operation and healthiness of transformers but also gives scope to identify the neutral
bushing.
2.7. TESTS BEFORE DECLARING THE TRANSFORMER SICK
Instances are not remote when section officers have handed over healthy transformer as a sick-unit. They
appear to have been mislead by repeated blowing off the H.G. Fuses presembly due to placing lower gauge
fuses or due to reasons other than faults in the transformers. Replacing of H.G. Fuses is to be properly done.
Usage of under size fuses result in frequent blowing off H.G. fuses and switching surges decreases the useful
life of a transformer.
They are advised to do the following tests at site of L.T. Supply is available or at their section office before
declaring it sick.
(a) Megger test H.V. to body and L.V. to body and see if satisfactory I.R. values or obtained. If not it can be
declared sick straight away.
(b)If I.R. values are o.k., conduct ratio test, if unequal voltages are obtained the transformer is sick.

More Related Content

What's hot

UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTREUNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTREPremanandDesai
 
mechanical design of power system
mechanical design of power systemmechanical design of power system
mechanical design of power systemBisnu Parida
 
Mechanical Design of Overhead Lines
Mechanical Design of Overhead LinesMechanical Design of Overhead Lines
Mechanical Design of Overhead LinesRanjeet Kumar
 
Edwin Newsletter on transformer failures on 13 October 2015
Edwin Newsletter on transformer failures on 13 October 2015Edwin Newsletter on transformer failures on 13 October 2015
Edwin Newsletter on transformer failures on 13 October 2015Edwin Low
 
Presentation of Manufacturing Of Distribution Transformer (Prodip)
Presentation of Manufacturing Of Distribution Transformer (Prodip)Presentation of Manufacturing Of Distribution Transformer (Prodip)
Presentation of Manufacturing Of Distribution Transformer (Prodip)Prodip Das Durjoy
 
Equipments of power transmission
Equipments of power transmissionEquipments of power transmission
Equipments of power transmissionRasika Ghongade
 
Metal enclosed busduct
Metal enclosed busductMetal enclosed busduct
Metal enclosed busductAmit Agrawal
 
Transfomer diagnostics/sanjeet-1308143
Transfomer diagnostics/sanjeet-1308143Transfomer diagnostics/sanjeet-1308143
Transfomer diagnostics/sanjeet-1308143sanjeet kumar
 
Transmission line insulators
Transmission line insulatorsTransmission line insulators
Transmission line insulatorsPrashant Sharma
 
UNIT - 02 SERVICE MAIN
UNIT - 02 SERVICE MAINUNIT - 02 SERVICE MAIN
UNIT - 02 SERVICE MAINPremanandDesai
 
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKER
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKERDIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKER
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKERRitesh Kumawat
 
Conductor size considerations_for_station_class_arresters
Conductor size considerations_for_station_class_arrestersConductor size considerations_for_station_class_arresters
Conductor size considerations_for_station_class_arrestersGilberto Mejía
 
BEAMA Best Practice Guide to Cable Ladder & Cable Tray Systems
BEAMA Best Practice Guide to Cable Ladder & Cable Tray SystemsBEAMA Best Practice Guide to Cable Ladder & Cable Tray Systems
BEAMA Best Practice Guide to Cable Ladder & Cable Tray SystemsThorne & Derrick International
 

What's hot (20)

UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTREUNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
 
Dps 02 rev02
Dps 02 rev02Dps 02 rev02
Dps 02 rev02
 
IJET-V3I2P1
IJET-V3I2P1IJET-V3I2P1
IJET-V3I2P1
 
mechanical design of power system
mechanical design of power systemmechanical design of power system
mechanical design of power system
 
Mechanical Design of Overhead Lines
Mechanical Design of Overhead LinesMechanical Design of Overhead Lines
Mechanical Design of Overhead Lines
 
Edwin Newsletter on transformer failures on 13 October 2015
Edwin Newsletter on transformer failures on 13 October 2015Edwin Newsletter on transformer failures on 13 October 2015
Edwin Newsletter on transformer failures on 13 October 2015
 
Design of transformer
Design of transformerDesign of transformer
Design of transformer
 
Presentation of Manufacturing Of Distribution Transformer (Prodip)
Presentation of Manufacturing Of Distribution Transformer (Prodip)Presentation of Manufacturing Of Distribution Transformer (Prodip)
Presentation of Manufacturing Of Distribution Transformer (Prodip)
 
Equipments of power transmission
Equipments of power transmissionEquipments of power transmission
Equipments of power transmission
 
Metal enclosed busduct
Metal enclosed busductMetal enclosed busduct
Metal enclosed busduct
 
Distribution transformer
Distribution transformerDistribution transformer
Distribution transformer
 
Metalclad switchgear
Metalclad switchgearMetalclad switchgear
Metalclad switchgear
 
Transfomer diagnostics/sanjeet-1308143
Transfomer diagnostics/sanjeet-1308143Transfomer diagnostics/sanjeet-1308143
Transfomer diagnostics/sanjeet-1308143
 
Transmission line insulators
Transmission line insulatorsTransmission line insulators
Transmission line insulators
 
UNIT - 02 SERVICE MAIN
UNIT - 02 SERVICE MAINUNIT - 02 SERVICE MAIN
UNIT - 02 SERVICE MAIN
 
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKER
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKERDIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKER
DIGITAL TESTING OF HIGH VOLTAGE CIRCUIT BREAKER
 
Conductor size considerations_for_station_class_arresters
Conductor size considerations_for_station_class_arrestersConductor size considerations_for_station_class_arresters
Conductor size considerations_for_station_class_arresters
 
Supports of overhead line
Supports of overhead lineSupports of overhead line
Supports of overhead line
 
BEAMA Best Practice Guide to Cable Ladder & Cable Tray Systems
BEAMA Best Practice Guide to Cable Ladder & Cable Tray SystemsBEAMA Best Practice Guide to Cable Ladder & Cable Tray Systems
BEAMA Best Practice Guide to Cable Ladder & Cable Tray Systems
 
L44086268
L44086268L44086268
L44086268
 

Similar to G04714245

Seminar report theory
Seminar report theorySeminar report theory
Seminar report theoryRanjan kumar
 
Why transformers fail_final
Why transformers fail_finalWhy transformers fail_final
Why transformers fail_finalSnehangshu Ghosh
 
BUCHHOLZ RELAY TESTING KIT
BUCHHOLZ RELAY TESTING KITBUCHHOLZ RELAY TESTING KIT
BUCHHOLZ RELAY TESTING KITIRJET Journal
 
Circuit Breaker: Part 2
Circuit Breaker: Part 2Circuit Breaker: Part 2
Circuit Breaker: Part 2Dr. Rohit Babu
 
How to reduced transformer losses report
How to reduced transformer losses reportHow to reduced transformer losses report
How to reduced transformer losses reportkamal soni
 
Generator and Transformer Protection (PART 2)
Generator and Transformer Protection (PART 2)Generator and Transformer Protection (PART 2)
Generator and Transformer Protection (PART 2)Dr. Rohit Babu
 
Vaccum Circuit Breaker
Vaccum Circuit BreakerVaccum Circuit Breaker
Vaccum Circuit BreakerRAHUL-GOPU
 
Unit 04 Protection of generators and transformers
Unit  04 Protection of generators and transformers Unit  04 Protection of generators and transformers
Unit 04 Protection of generators and transformers PremanandDesai
 
REPORT ON 33/11KV SUBSTATION
REPORT ON 33/11KV SUBSTATION REPORT ON 33/11KV SUBSTATION
REPORT ON 33/11KV SUBSTATION Ravi Phadtare
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear johny renoald
 
IRJET- Current Limiting Transformer
IRJET-  	  Current Limiting TransformerIRJET-  	  Current Limiting Transformer
IRJET- Current Limiting TransformerIRJET Journal
 
U.C: SERVICE IGNITION SYSTEM
U.C: SERVICE IGNITION SYSTEM U.C: SERVICE IGNITION SYSTEM
U.C: SERVICE IGNITION SYSTEM Montefolka Ruel
 
Power Transformer Protection
Power Transformer ProtectionPower Transformer Protection
Power Transformer ProtectionAng Sovann
 
Electrical Installation.pptx
Electrical Installation.pptxElectrical Installation.pptx
Electrical Installation.pptxbharath364108
 
Training report trw
Training report trwTraining report trw
Training report trwChandan Garg
 
Switchgear and protection engineering Lecture 03.pptx
Switchgear and protection engineering Lecture 03.pptxSwitchgear and protection engineering Lecture 03.pptx
Switchgear and protection engineering Lecture 03.pptxLoitaFredy
 

Similar to G04714245 (20)

Seminar report theory
Seminar report theorySeminar report theory
Seminar report theory
 
Why transformers fail_final
Why transformers fail_finalWhy transformers fail_final
Why transformers fail_final
 
BUCHHOLZ RELAY TESTING KIT
BUCHHOLZ RELAY TESTING KITBUCHHOLZ RELAY TESTING KIT
BUCHHOLZ RELAY TESTING KIT
 
Circuit breaker
Circuit breakerCircuit breaker
Circuit breaker
 
Circuit Breaker: Part 2
Circuit Breaker: Part 2Circuit Breaker: Part 2
Circuit Breaker: Part 2
 
How to reduced transformer losses report
How to reduced transformer losses reportHow to reduced transformer losses report
How to reduced transformer losses report
 
Generator and Transformer Protection (PART 2)
Generator and Transformer Protection (PART 2)Generator and Transformer Protection (PART 2)
Generator and Transformer Protection (PART 2)
 
Vaccum Circuit Breaker
Vaccum Circuit BreakerVaccum Circuit Breaker
Vaccum Circuit Breaker
 
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, AllahabadSummer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
 
Unit 04 Protection of generators and transformers
Unit  04 Protection of generators and transformers Unit  04 Protection of generators and transformers
Unit 04 Protection of generators and transformers
 
REPORT ON 33/11KV SUBSTATION
REPORT ON 33/11KV SUBSTATION REPORT ON 33/11KV SUBSTATION
REPORT ON 33/11KV SUBSTATION
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
 
IRJET- Current Limiting Transformer
IRJET-  	  Current Limiting TransformerIRJET-  	  Current Limiting Transformer
IRJET- Current Limiting Transformer
 
Transformer ppt
Transformer pptTransformer ppt
Transformer ppt
 
U.C: SERVICE IGNITION SYSTEM
U.C: SERVICE IGNITION SYSTEM U.C: SERVICE IGNITION SYSTEM
U.C: SERVICE IGNITION SYSTEM
 
Power Transformer Protection
Power Transformer ProtectionPower Transformer Protection
Power Transformer Protection
 
Electrical Installation.pptx
Electrical Installation.pptxElectrical Installation.pptx
Electrical Installation.pptx
 
Training report trw
Training report trwTraining report trw
Training report trw
 
Executive summary
Executive summaryExecutive summary
Executive summary
 
Switchgear and protection engineering Lecture 03.pptx
Switchgear and protection engineering Lecture 03.pptxSwitchgear and protection engineering Lecture 03.pptx
Switchgear and protection engineering Lecture 03.pptx
 

More from IOSR-JEN

More from IOSR-JEN (20)

C05921721
C05921721C05921721
C05921721
 
B05921016
B05921016B05921016
B05921016
 
A05920109
A05920109A05920109
A05920109
 
J05915457
J05915457J05915457
J05915457
 
I05914153
I05914153I05914153
I05914153
 
H05913540
H05913540H05913540
H05913540
 
G05913234
G05913234G05913234
G05913234
 
F05912731
F05912731F05912731
F05912731
 
E05912226
E05912226E05912226
E05912226
 
D05911621
D05911621D05911621
D05911621
 
C05911315
C05911315C05911315
C05911315
 
B05910712
B05910712B05910712
B05910712
 
A05910106
A05910106A05910106
A05910106
 
B05840510
B05840510B05840510
B05840510
 
I05844759
I05844759I05844759
I05844759
 
H05844346
H05844346H05844346
H05844346
 
G05843942
G05843942G05843942
G05843942
 
F05843238
F05843238F05843238
F05843238
 
E05842831
E05842831E05842831
E05842831
 
D05842227
D05842227D05842227
D05842227
 

Recently uploaded

FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhisoniya singh
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slidevu2urc
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxMalak Abu Hammad
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure servicePooja Nehwal
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 3652toLead Limited
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024Results
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024Scott Keck-Warren
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slidespraypatel2
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfEnterprise Knowledge
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Paola De la Torre
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...shyamraj55
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 

Recently uploaded (20)

FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 

G04714245

  • 1. IOSR Journal of Engineering (IOSRJEN) www.iosrjen.org ISSN (e): 2250-3021, ISSN (p): 2278-8719 Vol. 04, Issue 07 (July. 2014), ||V1|| PP 42-45 International organization of Scientific Research 42 | P a g e Practical Approach for Detection Of Failure Of Distribution Transformers And Their Remidies. B.Suresh Kumar Asst.Professor-CBIT-Hyderabad I. INTRODUCTION Power is generated at lower voltage like 11KV and 13.8 KV in generating stations which are far away from the load centre. The power is transmitted to the load centers at extra high voltages like 132KV, 220KV and 400KV to reduce the losses and to improve the system efficiency. The power of these higher voltages is stepped down at various E.H.T., 33/11KV and 11KV/400V Sub-stations to attain the requirements of the consumers of different categories. As the demand for electrical power is increasing day by day, the distribution system plays an important role in catering the needs of consumers. For reliability in maintaining un-interrupted power supply one must have an efficient distribution system. The major components in the distribution system are 11KV feeders, Distribution transformers and LT 3 phase 4 wire line. One of the most vital component of the above, the heart of the system is distribution transformer. Hence the failure of a distribution transformer leads to break down in power supply to all the LT consumers. Therefore the reliability in power supply mainly depends on the reliable functioning of distribution transformer. At present about 28204 distribution transformers of various capacities rating from 10 KVA to 500KVA are installed in Medak district. The failure rate is about 14.5% of total installed transformers which accounts for higher side. In the present project work it is proposed to investigate the practical and technical causes for failure of distribution transformers and suggested suitable remedial measures to minimize the failure and to study the testing procedures which are being adopted in APCPDCL. For this purpose the No. of distribution transformers existing in Sangareddy, Jogipet, Medak, Toopran, Siddipet have been considered for cause study. 1.2 ORGANISATION OF PROJECT WORK The project report is organized in 6 (six) chapters excluding the introductory chapter it has 5 chapters. The Chapter-II deals with the failure of the distribution transformers, the general causes for failure and maintenance schedule recommended/adopted by APCPDCL 1.3 STATEMENT OF THE PROBLEM: An attempt has been made to analyze the practical causes contributing to the failure of distribution transformers. 2.DISTRIBUTION TRANSFORMER GENERAL CAUSES FOR FAILURES AND MAINTENANCE SCHEDULE 2.1 INTRODUCTION In this chapter an attempt is made to explain the essential features involved in construction, operation, maintenance and the reasons for failure of transformers. Specific emphasis is made on what is likely to happen if a particular item of maintenance is not done in-time. The power that is generated at various power stations is stepped up and transmitted at extra high voltages viz., 132 KV, 220 KV and 400 KV for reducing the transmission line losses. The voltage stepped down to service voltages at various receiving stations depending upon the requirement of the prospective consumers. The higher voltage is stepped down to 11KV/400V and is made available at L.T. consumers installations. It is roughly estimated that the power that is generated is transformed 3 or 4 times before it reaches the consumers installations. Thus the distribution transformer is an essential device in the distribution network which step down the voltage 2.2. THE DISTRIBUTION TRANSFORMER COMPRISES OF THE FOLLOWING FEATURES. 1. Magnetic Circuits : Comprising of limbs, yoke and clamp Structures. 2. Electric Circuits :The primary and secondary windings, insulation and bracing devices. 3. Terminals: Tappings, tap switch, insulators i.e. bushings and leads. 4.Others: Tank, Oils, Radiators, conservator,Breather and auxiliary apparatus. 2.3 FUNCTIONS OF A DISTRIBUTION TRANSFORMER:
  • 2. Practical Approach For Detection Of Failure Of Distribution Transformers And Their Remidies. International organization of Scientific Research 43 | P a g e The Distribution Transformer is static equipment and is used to either step down or step up the voltage as the case may be. The capacity of the transformers is the extent of power in KVA that can be handled by the transformer while it does the voltage transformation at the pre-determined ratio. The number of turns in H.V. and L.V. windings determine the voltage ratio. Suppose the primary winding has N.P. number of turns and secondary winding has N.S. number of turns and the primary and secondary voltages are VP and VS respectively, the voltage ratio of the Distribution Transformer will be equivalent to VP/VS = NP/NS Therefore the number of turns on HV and LV Windings also decide the voltage ratio and the size of the winding wire decide the capacity of the transformer. 2.4 CAUSES OF FAILURE OF DISTRIBUTION TRANSFORMERS: From a study on the various causes of failure of a transformer it is easy to know what is to be done to prevent them. The various causes for failure of distribution transformers are listed below. 2.4.1 FAILURES DUE TO MECHANICAL DAMAGES These are generally (1) oil leakages (2) flash over of bushings. 1. The welding of the main tank may be defective and also the fillings are not leak proof. This causes oil to leak reducing the oil level in the transformer causing heating of winding and leading to a certain break-down of the equipment. Rough handling during transport may also contribute to leak. 2. The LT terminals connected through cables to LT take off lines. If these cables are not properly wired through wooden cleats they cause some loading on LT Bush rods and finally results to burnt out. 3. Deposits of coal dust, saline or chemicals on the bushing may cause a flash over, as the bushings will loose their insulating properties. 4. Sufficient place around a transformer to dissipate heat must be provided. If two transformers are kept close the surfaces may get clogged and oil temperature increases endangering to coil insulation. 5. Vapours at the top of an oil cooled transformers, may be explosive. Bringing naked lamps at the places may cause damage. 2.4.2 FAILURE IN DI-ELECTRIC CIRCUITS: 1. Moisture entering the tank by breathing action of transformer reduces the di-electric strength of oil .The results in break down from coils or terminal leads to tank or core structures. The greatest damages is however the inter turns short in the coils. 2. Deterioration of oil may occur due to prolonged over loading of the transformer. This action is aggravated by the presence of copper and lead. When oil temperature increases formation of sludge, water and acids are accelerated. 3. Certain amount of oil is lost due to evaporation and oxidation while the transformer is in service. Periodical topping up of oil level with fresh tested oil is necessary, leads to unit gets over heated. 4. Narrow oil ducts and improper ventilation reduce the useful life of a transformer. Oil insulation turns brittle and may get punctured on account of this. 5. Some times the clearance, provided between phases is insufficient. Also insertion of press board barriers may aggravate as they may up set the di-electric stress to throw too much stress across the coil spaces and across the barriers. 6. Wooden ducts provided for taking the terminal leads over them should be properly dried. These may cause short circuit between tapping leads. 7. Presence of foreign particles in oil reduces the di-electric strength of the insulating oil and may cause a flash over resulting in serious break down of the transformer. 8. When the acidity value of the oil increases, it will promote oxidation of the metal parts and results in a break- down. SAFE VALUES FOR OIL Di-electric strength: 30 KV for 1 minute between gap of 2.5mm 40 KV instant. Acidity: Upto 0.7m.grs/KCH per gram of oil satisfactory. 2.4.3. FAILURE IN ELECTRIC CIRCUITS: 1. When moisture manages to ingress through the fabric insulation of the coils it causes short circuit between turns sooner or later. Impregnation of coils by applying varnish so that it penetrates deep enough to the inner layers of the coils is to be ensured. Failures from this cause are most common.
  • 3. Practical Approach For Detection Of Failure Of Distribution Transformers And Their Remidies. International organization of Scientific Research 44 | P a g e 2. Presence of sharp edges on the copper conductors may cause a short circuit between adjacent turns when the transformer vibrates on load or when the windings are subjected to repeated electromagnets stresses cause adjacent turns coming into contact. 3. One or more turns in a coil may get dis-lodged and a short circuit between them may result, when heavy external short circuit occurs and if the same is not cleared by fuses intime. Break down may not immediately occur but when the transformer vibrates on load dislodged coils may take place causing a break down. 4. Improper drying out and applying full voltage with poor I.R.values will result in failure of insulation between adjacent layers. The I.R. values for a 11kv/440v distribution transformers are given below: The I.R. values in mega ohms are to be taken with a 1000v megger. ----------------------------------------------------------------------------------------------------- Temperature 11kv/440v distribution Transformer HT to LT HT to E LT to E ------------------------------------------------------------------------------------------------------ 60 C 65 50 25 50C 130 100 50 40C 260 200 100 30C above above above 250 200 100 ------------------------------------------------------------------------------------------------------ Whenever readings are taken at ambient temperature, the temperature also is to be noted. 5. Sudden changes in load cause sudden expansion and contraction of copper and is likely to damage the insulation fabric. 6. Where individual H.V. coils are designed to have too great a radial depth, compared to its height, hot spots may develop in the interior of the coils due to in adequate oil passage allowed. The insulation becomes brittle and short circuit between turns may result. 7. Over heat on load occurs badly soldered joints and oil gets carbonized locally. The heat at the joints will be conducted to a certain length in the copper coil and the insulation may get carbonized to a little extent resulting in a short circuit between turns. 8. When external short circuit occurs, the coils get displaced violently as a result of the internal imbalance in electromagnetic conditions. 9. Sustained heavy over loads produce high temperature throughout the transformer. The coil insulation becomes brittle and in the course of time flakes off the conductors at places resulting in short circuit between turns. Transformers with a high ratio of copper losses to iron losses are less able to withstand over load and are therefore more liable to fail on account of sustained over loading. 10. The tap adjusting leads should be carefully handled to ensure that wrong leads are not joined otherwise part of winding may get short circuited and heavy currents circulate in the short circuited windings which would produce a fault between turns. 11. It is to be ensured that bolted joints and all connection are tightly screwed and locked lest they may become loose in service due to vibrations produced and such joints get heated up rapidly. 12. When a transformer is switched off the magnetizing current and thus the magnetic flux tends to collapse instantaneously. Due to various reasons this some time does at a much more rapid date than corresponding normal cyclic rate of change and as a result high voltage rises may occur. 13. Short circuit between turns, break-down of windings to earth and puncture of insulation may take place due to following phenomenon:- (a) Lightening surges reaching the transformer, usually for the damage in the surge impedance and coils get damaged as they take the burnt of the shock. (b) Excessive voltage set-up by surges may be accent rated at open ended tappings, at any point of change of surge impedance like at termination of conductor reinforcement where employed, spare between series coils, at the neutral or midpoint. Extra insulation is to be provided at these points. 2.4.4. FAILURES IN MAGNETIC CIRCUITS 1. The laminations are clamped together by inserting bolts through core and yoke. The bolts are provided with insulation around them which may give way. This total amount to a short in lamination causing local eddy currents. When this trouble occurs, in due two bolts simultaneously they form a short circuit turn through which magnetic flux passes. If one of the bolts situated at the ends of the limb fail simultaneously they form a short circuit turn through which magnetic flux passes. If one of the bolts situated at the ends of the limb fail simultaneously with an adjacent bolt-in-the yokes. The patch between the two bolts is threaded by almost the entire value of the magnetic flux when passing from the core to the yoke. The heat generated is so severe to
  • 4. Practical Approach For Detection Of Failure Of Distribution Transformers And Their Remidies. International organization of Scientific Research 45 | P a g e cause a distortion of the whole core also causing charring of the insulation and a resultant short circuit between turns of adjacent windings. 2. Failure may occur of insulation between lamination and insulation between yoke clamping bolts fails. This registers an increase in the iron losses of the transformer. 3. Core clamping bolts should be securely tightened and locked lest vibration will set up causing damage of core insulation and produce failures. 4. Care should be taken to ensure that the edges of the core and yoke lamination do not develop burns which produce local short circuit in the lamination. 5. No metallic fillings should be allowed to be present in between lamination in finished transformers which causes short circuit. 2.5. GENERAL REMARKS: 1. Almost all the parts in a transformer liable to failure on opening a failed transformer it is often very difficult to say definitely the reason for the failure as all evidence is eliminated by the very nature of the break down. Consequently the cause of failure is only a matter of guess. At best: A close idea of the real cause may be obtained by a careful study of the transformer and the operating conditions obtaining at the time of failure of transformers and also the weather conditions. 2. Careful design and construction on the part of the manufacturer, without sub-ordinating quality to competition in market is necessary, on the part of purchasers also the economic behind the purchase should not be arrive at by cost alone but by performance guarantee. 3. Timely preventive maintenance is the back bone for safe and efficient operation of any electrical equipment the maintenance scheduled as well as the construction standards drown up by the APCPDCL are exhaustive enough to detect and prevent a possible failure ahead. If these are adhering it may be possible to reduce the failures to a large extent. 2.6 PRE –COMMISSIONING TESTS The following tests are to be done before commissioning a distribution transformer. These are termed as pre- commissioning tests. 1. Megger Test: - This test is to be done with a 1000v megger. At normal ambient temperature the I.R.Values should not be less than the following. H.T. to Body - 150 MegaOhms L.T. to Body - 100 Mega Ohms H.T. to L.T. - 150 Mega Ohms b) Whenever possible and alternate L.T. Supply is available L.T. Supply may be given to the H.V. Terminals and the voltages on L.V. side measured between phase and phase and phase and neutral. This not only confirms the correctness of tap operation and healthiness of transformers but also gives scope to identify the neutral bushing. 2.7. TESTS BEFORE DECLARING THE TRANSFORMER SICK Instances are not remote when section officers have handed over healthy transformer as a sick-unit. They appear to have been mislead by repeated blowing off the H.G. Fuses presembly due to placing lower gauge fuses or due to reasons other than faults in the transformers. Replacing of H.G. Fuses is to be properly done. Usage of under size fuses result in frequent blowing off H.G. fuses and switching surges decreases the useful life of a transformer. They are advised to do the following tests at site of L.T. Supply is available or at their section office before declaring it sick. (a) Megger test H.V. to body and L.V. to body and see if satisfactory I.R. values or obtained. If not it can be declared sick straight away. (b)If I.R. values are o.k., conduct ratio test, if unequal voltages are obtained the transformer is sick.