SlideShare a Scribd company logo
1 of 58
What will you gain from this
presentation?
• Gain insight into the construction process activities for a structural steel
frame of a case study office building. Slides are presented from a
construction management point of view.
• Develop an understanding of the duration and sequence of activities that
are part of the structural steel construction process of the case study.
• Learn about how this office building was sequenced.
• Observe how the structural steel frame was erected through photographs
and animations.
• Get acquainted with equipment used for this project.
Introduction
This presentation was developed as a teaching aid with the support of the
American Institute of Steel Construction. Its objective is to introduce the user
to the construction process of the structural steel frame for a common
building type, a four story office building.
The presentation documents the construction of the steel frame for a case
study building. Photographs were taken throughout the construction process
of the structural steel frame including detailing, fabrication and erection. Data
from the project was also compiled including plans, schedules, specifications
and other details. This information was brought together to create the
following presentation.
This slide show is presented from a construction management perspective.
In this sense, it contains information on material procurement, sequencing,
site logistics, schedules, and equipment, as well as technical aspects of the
project.
Case Study Project
Description of the structural steel frame:
• Office building use
• 4 Stories
• 80,000 square feet of building
construction area
• Approximately 400 tons of structural
steel or 10 pounds per square foot
• Approximate fabrication and erection
cost 9 dollars per square foot
• Standard bay size of 30ft by 30ft
• 3 by 7 bays
• 964 pieces of structural steel
• Built in 2003
Structural Steel Construction Phase
Schedule
As seen on the schedule, material procurement occurs early in the process, even
before shop drawings are generated. This is done so that a steel mill has enough
time to produce the required steel. Material procurement includes: quantity
surveying, placing the mill order, delivery of steel from the mill and storage of the
steel in the fabrication shop. Detailing includes the creation of shop drawings of
each piece in the structural frame. Shop drawings are submitted to the contractor
and structural engineer to ensure that they comply with the engineer’s design.
Upon approval of shop drawings and arrival of steel from the mill, steel pieces are
precisely fabricated. Once structural steel members are fabricated they are taken
to the yard, loaded on trucks and transported to the job site for erection.
Detailing Process
During the detailing process, the detailer develops shop drawings for each
structural steel member in the structure. Each member is assigned a unique piece
mark for identification and tracking. The detailer also prepares a list with a
description of the structural steel members.
Shop Drawings
These are shop drawings of columns 3C1 and 3C2 for the case study
project. Shop drawings convey precise information to the fabricator, and
other project parties about how each steel member in the structure is to be
fabricated.
Materials
Raw steel used to fabricate structural steel members can be purchased from
a steel mill or steel service center. Material purchased from a steel service
center is usually more expensive, but may be quicker to obtain and can be
ordered in smaller quantities. The material for the case study project was
ordered directly from a mill and delivered in two batches approximately 4 and
5 weeks after the mill order was placed. Once the material arrived at the
fabricator’s shop it was organized and stored in the yard.
Fabrication
Structural steel members are fabricated by precisely cutting, shearing,
punching, drilling, fitting and welding in order to produce the
configurations detailed in the shop drawings. Each member is labeled
with a piece mark, length, and job number for identification.
Piece Mark
Once fabricated, each finished structural steel member is labeled. In this case
the fabricator labeled each steel member with its piece mark, sequence
number, and the last two digits of the job number. Specific labeling practices
may vary by fabricator. Notice that this time the label color is yellow to
differentiate it from previous labels. Labeling of the steel pieces is crucial
because it will help identify members on the job site.
Storage
After fabrication, finished structural steel members are stored in the
fabricator’s storage yard. The more organized the yard, the easier it will be
to transport steel to the site. In this case structural steel was stored
according to erection sequence. Sequences define areas of the frame and
are used to organize their delivery and erection. The practice of planning
and storing by sequence improves the efficiency of loading, delivery,
offloading and erection.
Anchor Rod Plan
One of the first drawings prepared by the detailer is the anchor rod plan.
This plan guides the foundation subcontractor in the placement of anchor
rods. It contains horizontal and vertical information for placement of
anchor rods, as well as dimensions and elevations of leveling plates (if
used).
Anchor Rod Details
The anchor rod detail on the left depicts how anchor rods and leveling plates were
placed for the case study project. A leveling plate is a steel plate fixed on top of a
foundation on which a structural column can be placed. The leveling plate is
leveled and grouted prior to installation of the column. Although this is one method
for setting columns, practices may vary with other erectors. On the right is a
photograph of the anchor rods and leveling plates in place for the case study
project.
Anchor Rod Survey
Before the erection process started, anchor rods and leveling plates were
surveyed by the erector’s surveyor to check if they were correctly positioned. If
anchor rods are improperly located, they must be corrected by the foundation
subcontractor before the erection process may start. The surveyor used a total
station to determine the horizontal and vertical location of each leveling plate
and anchor rod.
Hoisting Sequences
During detailing, the steel frame was divided into 6 sequences illustrated on the
erection drawings. Sequences represent the order in which a zone or section of the
frame will be erected. They are designed to improve efficiency of the erection
process. Planning the sequences allowed for parallel construction operations to take
place. For example, while the erection crew erected sequence 2, the decking crew
placed metal deck at the previously placed sequence 1. In this way the deck placed
at sequence 1 formed a work platform and reduced the potential fall distance when
the steel contractor erected sequence 3 which was above sequence 1.
Structural Steel Erection Schedule
This is a detailed schedule of the erection process of the structural steel frame. In this
project an average of 40 pieces of steel were hoisted per day. Hoisting, bolt up, detail
work, decking and stud activities are performed by sequence. Hoisting consists of
lifting and placing steel members into their appropriate position and temporarily
fastening them using several bolts and/or welds. Plumbing up refers to the vertical
alignment of the frame. Final bolt up refers to tightening the bolts which connect the
components of the structure.
STRUCTURAL STEEL ERECTION BY
SEQUENCE
The following is an animation of the structural steel erection process by
sequence. The six sequences will slowly appear along with the working day in
which hoisting of each sequence was completed. The last images to appear
are of the masonry stair and elevator shafts. They were built after the frame
was erected. The steel frame was connected to the vertical shafts to provide
permanent lateral stability of the frame.
Erection Crew
Seven people formed the erection crew used for this project. The crew
consisted of one foreman, two ironworkers hooking steel (upper left), two
ironworkers connecting steel (upper right), a crane operator (lower left), and
an oiler (lower right).
Crane Mobilization and Set Up
Crane mobilization and set up took place before structural steel members
were delivered to the site. An additional crane was utilized to unload and set
up the crane. Crane mobilization and setup for the project took
approximately one day.
Crane
The crane used for the project was a 100 ton crawler mounted crane with a 160
foot boom and a 40 foot jib. The boom (upper right) is the main projecting structure
of the crane and the jib (lower right) is the smaller structure attached to the boom.
There are many configurations and sizes of cranes available. Cranes are selected
on the basis of cost, availability, speed, reach and capacity.
Crane Locations
Two crane locations were used for this project. Location 1 was used to
erect sequences 1, 3, and 5. Location 2 was used to erect sequences 2, 4,
and 6. The crane was moved to the appropriate location for each sequence.
Crane locations were approximately 45 feet from the face of the building.
Transportation
Once the on-site crane was fully set up, the fabricator loaded the steel
members for sequence 1 onto trucks and transported them to the job site.
Structural steel was delivered by sequence throughout the erection process. It
took a total of 29 truckloads to deliver all of the structural steel for the project.
Unloading and Shakeout
Upon delivery to the job site, fabricated
steel was unloaded and placed on wood or
steel blocking. The blocking allowed for
chokers to be attached to each member for
subsequent hoisting and erection. Shakeout
of structural steel took place after
unloading. Shakeout is the process of
sorting the steel pieces on the site so that
they can be efficiently erected (lower left),
and involves organizing and spacing each
structural steel piece.
Erection Drawings
This is the erection drawing (e-drawing or e-sheet) of the first floor framing for the
project. The numbers one and two inside the red hexagons on each side of the red
line indicate the sequence number for each part of the structure. The piece marks
on the drawing match those on the beams, girders and columns and are used to
locate and orient each member during erection.
Erection Order
The erection crew foreman used the erection drawings to determine the exact
order in which structural steel members were to be erected. The first pieces
hoisted during this project were the columns in sequence 1 (right sheet), then
girders and beams (left and center sheets).
Access
When planning for construction operations, the building contractor decided
to pour a portion of the foundation at a later date to facilitate the access of
people, materials and equipment to the lower level during construction.
First Column
This is the first column being hoisted into position. Using ladders,
ironworkers temporarily bolted the column. Prior to erection, the erector
must consider column stability in accordance with safety standards and the
AISC Code of Standard Practice.
Sequence 1 Columns
The first structural steel members hoisted were the columns. This is a
view of sequence 1 after the columns were set. Notice that all columns
have a splice on the top.
Chokers
A choker is a rigging assembly used to attach a load to a hoisting device. It
is usually made of wire rope or synthetic fiber. Chokers are used to hoist
beams into position. They are positioned at the center of gravity of the
beam so that the beam remains level when hoisted.
Multiple Lift Rigging
Multiple lift rigging is a process used to hoist several pieces of steel
simultaneously. This is accomplished by utilizing a rigging assembly that
facilitates the attachment of up to five independent loads to the hoist
rigging of a crane. In this project up to four beams were hoisted at a time.
Multiple lift rigging speeds the lifting process by reducing the total number
of lifts required for the frame.
Preliminary Bolting
The connector uses pins to align the holes between structural steel members
being connected. Then he places several bolts and temporarily tightens them
with his spud wrench. At least two bolts per connection are used to
temporarily fasten each connection.
Hand Signals
Teamwork and communication are important when erecting steel.
Ironworkers use hand signals to communicate with the crane operator (left).
The photograph in the right presents a situation in which the crane operator
could not see the member being connected. In this case, an ironworker was
located where he could be seen by both the crane operator and the other
ironworkers. This ironworker was able to guide the crane operator using
standard hand signals.
Beams
Main girders are hoisted after the columns. Beams are then hoisted
and connected to the girders. On the left is a photograph of the first
bay to be hoisted. On the right is a photograph of the first three bays
in place.
Sequence 1 Sequence 2
This is a view of the completed hoisting activity for sequences 1 (left)
and 2 (right). It took approximately 5 days to hoist the 166 pieces of
steel that are part of the two sequences.
Erection Schedule
The activities in yellow were completed by the time sequence 2 was hoisted.
Notice how deck and studs for sequence 1 starts before hoisting sequence 3 to
provide fall protection for the ironworkers connecting steel.
Metal Decking
This is the metal decking used in the project. The erector had the
responsibility of unloading and hoisting metal decking to pre-
established positions on the frame.
Hoisting Metal Decking
On the left is a plan specifying where
bundles of decking were to be placed by
the erector. Considerations for
placement locations included both the
productivity of the deck installers and
construction loading. Each bundle was
identified with a number and placed at
its preplanned location.
Metal Decking
Metal deck was placed and attached with a series of welds. Controlled deck zones
were used during installation. A controlled deck zone is an area in which initial
installation and placement of metal decking may take place without the use of
guardrail systems, personal fall arrest systems, fall restraint systems, or safety net
systems and where access to the zone is controlled.
Metal Decking
This is a view (lower left)
of the welding used to
fasten metal deck to the
structure.
Perimeter Safety Cables
On multi-story structures, perimeter safety
cables are installed at the interior and exterior
perimeters of floors and openings as soon as
the metal decking has been installed.
Shear Studs
These are shear studs. The white rings are ceramic ferrules. The ceramic
ferrule constrains the molten metal into which the stud is thrust automatically
and a high quality fusion weld is accomplished where the weld is stronger
than the stud itself.
Welding Shear Studs
Snow was removed from the locations where shear
studs were to be placed (upper left). Using a stud-
welding gun (an automatic welding device) the shear
studs were then welded to the structural members
below the metal decking. Shear studs are used to
ensure a composite action between the concrete slab
and structural steel beams (upper right). Whether shear
studs are used is a function of the structural engineer’s
design.
Shear Studs
This is a view of the welded studs. Shear studs were tested to ensure that they
were correctly welded to the structural steel members in compliance with the bend
test of the AWS D 1.1 Structural Welding Code.
Sequence 3 Sequence 4
This is a view of the completed hoisting activity for sequences 3 and 4.
Hoisting these two sequences took approximately 9 days in contrast
with the five days it took to hoist sequences 1 and 2, because
sequences 3 and 4 consisted of two floors (365 pieces of steel) and
sequences 1 and 2 consisted of one floor (166 pieces of steel).
Erection Schedule
The activities in yellow are the ones completed by the time sequence 4 was hoisted.
Notice that deck and studs for sequence 3 were started before hoisting sequence 5 in
order to provide fall protection for the ironworkers connecting steel. Plumbing up and
final bolt up for sequences 1 through 4 were performed after sequence 4 was hoisted.
Temporary Bracing
Temporary bracing was placed before
plumbing up the structural frame.
Temporary bracing is used to provide
temporary lateral stability to the structure
and to plumb up the frame. The temporary
bracing was removed by the erector once
the structural steel frame was secured to
the vertical masonry elevator and stair
shafts, which were installed after
completion of the steel frame.
Plumbing Up
Plumbing up refers to the vertical alignment of the structure in
accordance with the AISC Code of Standard Practice. A theodolite
was used to verify the alignment of columns in the perimeter of the
building. The foreman directed ironworkers on the structure to shift
the frame using the temporary bracing.
Plumbing Up
Turnbuckles (lower left) are a common part of
the bracing system. A turnbuckle is a device
that usually consists of a link with screw
threads at both ends that is turned to bring
the ends closer together. Using several
turnbuckles connected to the temporary
bracing, the steel frame was shifted until it
was vertically aligned.
Final Bolt-up
After a section of the structural frame was assembled and vertically
aligned, ironworkers permanently fastened the structural steel members
with additional bolts and welds. Tension controlled bolts (F1852) were
used. Final bolt-up was performed using a torque wrench. The wrench
stops automatically when the bolt shears at a tension control groove
indicating that the required tension is reached.
Sequence 5 Sequence 6
This is a view of the completed hoisting activity for sequences 5 (left) and
6 (right). It took approximately 9 days to hoist both sequences, similar to
sequences 3 and 4.
Erection Schedule
The activities in yellow are the ones completed by the time sequence 6 was hoisted.
Plumbing up and final bolt up for sequences 5 through 6 was performed after
sequence 6 was hoisted. Hoisting sequence 6 was the last activity that required the
use of the crane. After hoisting sequence 6 the crane was demobilized.
Lateral Stability
Masonry elevator and stair shafts were installed after the steel frame
was erected. The steel frame was secured to the shafts of the building
at each floor providing lateral stability for the frame.
Slabs
Floor slabs were poured (upper right)
after the structural steel frame was
secured to the vertical masonry shafts.
After reinforcing steel (upper left) and
concrete were placed, the slab was
leveled and finished (lower left).
Slabs
This is a view of the finished slab. At this point the structural
frame of the building is complete.
Inspection
The structural steel frame was inspected upon completion by the local
jurisdiction and work could proceed accordingly. Depending on frame
complexity, additional periodic inspection and testing may also be required
by the local jurisdiction. The design engineer also conducts contract
administration and field observation activities which help ensure quality.
Fireproofing
Structural steel has to be protected from fire. Steel will not burn, but it
may become soft and weak when exposed to intense heat. Building
codes regulate the need for fire protection and its required locations.
There are several methods for fire protection. The method utilized for
this project was spray-on fire protection. Spray-on material may be
portland cement or a gypsum-based product and can be applied
directly to structural steel members.
Finished Building
This is how the building will look after it is completed. The structural steel frame is
one of the most important parts of the building. Building with steel has several
advantages over other building materials. Steel can be erected year round. It is
light yet strong when compared with other structural frame materials. Steel can
also be adapted to almost any imaginable shape. One of the biggest advantages
is that it can be erected very fast.

More Related Content

Similar to ConstructionManagement.ppt

Steel building construction
Steel building constructionSteel building construction
Steel building constructionprices89b
 
Industrialised Building System
Industrialised Building SystemIndustrialised Building System
Industrialised Building Systemjisunfoo
 
Practical design and_detailing_of_steel_column_base_...
Practical design and_detailing_of_steel_column_base_...Practical design and_detailing_of_steel_column_base_...
Practical design and_detailing_of_steel_column_base_...suchit03
 
ADVANCING CONSTRUCTION EXCELLENCE.pptx
ADVANCING CONSTRUCTION EXCELLENCE.pptxADVANCING CONSTRUCTION EXCELLENCE.pptx
ADVANCING CONSTRUCTION EXCELLENCE.pptxGroneSolutionsWholes
 
Multi storey structural steel structures
Multi storey structural steel structuresMulti storey structural steel structures
Multi storey structural steel structuresThomas Britto
 
6 processes of casting production
6 processes of casting production6 processes of casting production
6 processes of casting productionTurbo Cast
 
Comparative Study on the Economy between Pre-Engineered and Conventional Stee...
Comparative Study on the Economy between Pre-Engineered and Conventional Stee...Comparative Study on the Economy between Pre-Engineered and Conventional Stee...
Comparative Study on the Economy between Pre-Engineered and Conventional Stee...IRJET Journal
 
Steelplacementhandbook
SteelplacementhandbookSteelplacementhandbook
Steelplacementhandbookdefrimk
 
Steel framed building Shrilkant
Steel framed building  ShrilkantSteel framed building  Shrilkant
Steel framed building ShrilkantShriKant49
 
Unit 1 Class Notes-2019 pat..pptx
Unit 1 Class Notes-2019 pat..pptxUnit 1 Class Notes-2019 pat..pptx
Unit 1 Class Notes-2019 pat..pptxRESHMAFEGADE
 
IRJET - Analysis and Design of Steel Box Girder Bridge using Tekla Structures
IRJET - Analysis and Design of Steel Box Girder Bridge using Tekla StructuresIRJET - Analysis and Design of Steel Box Girder Bridge using Tekla Structures
IRJET - Analysis and Design of Steel Box Girder Bridge using Tekla StructuresIRJET Journal
 
Importance of Steel Detailing for Steel Fabricators and Structural Engineers
Importance of Steel Detailing for Steel Fabricators and Structural EngineersImportance of Steel Detailing for Steel Fabricators and Structural Engineers
Importance of Steel Detailing for Steel Fabricators and Structural Engineersmetzens
 
Iii design-of-steel-structures-unit-1
Iii design-of-steel-structures-unit-1Iii design-of-steel-structures-unit-1
Iii design-of-steel-structures-unit-1saibabu48
 
Lectures Note 1. Civil Construction.pptx
Lectures Note 1. Civil Construction.pptxLectures Note 1. Civil Construction.pptx
Lectures Note 1. Civil Construction.pptx2020CEB005POTNURUSAI
 
Miscellaneous Steel Detailing-services of Silicon Valley Infomedia
Miscellaneous Steel Detailing-services of Silicon Valley InfomediaMiscellaneous Steel Detailing-services of Silicon Valley Infomedia
Miscellaneous Steel Detailing-services of Silicon Valley InfomediaSilicon Valley Infomedia Pvt Ltd
 
Construction process''column,beam,slab''
Construction process''column,beam,slab''Construction process''column,beam,slab''
Construction process''column,beam,slab''Nabeel Rajpoot
 
design drawing steel structures
design drawing steel structuresdesign drawing steel structures
design drawing steel structuresSurya Swaroop
 

Similar to ConstructionManagement.ppt (20)

Steel building construction
Steel building constructionSteel building construction
Steel building construction
 
Industrialised Building System
Industrialised Building SystemIndustrialised Building System
Industrialised Building System
 
Structural Steel Fabrication Process
 Structural Steel Fabrication Process Structural Steel Fabrication Process
Structural Steel Fabrication Process
 
Practical design and_detailing_of_steel_column_base_...
Practical design and_detailing_of_steel_column_base_...Practical design and_detailing_of_steel_column_base_...
Practical design and_detailing_of_steel_column_base_...
 
ADVANCING CONSTRUCTION EXCELLENCE.pptx
ADVANCING CONSTRUCTION EXCELLENCE.pptxADVANCING CONSTRUCTION EXCELLENCE.pptx
ADVANCING CONSTRUCTION EXCELLENCE.pptx
 
Multi storey structural steel structures
Multi storey structural steel structuresMulti storey structural steel structures
Multi storey structural steel structures
 
6 processes of casting production
6 processes of casting production6 processes of casting production
6 processes of casting production
 
Comparative Study on the Economy between Pre-Engineered and Conventional Stee...
Comparative Study on the Economy between Pre-Engineered and Conventional Stee...Comparative Study on the Economy between Pre-Engineered and Conventional Stee...
Comparative Study on the Economy between Pre-Engineered and Conventional Stee...
 
Steelplacementhandbook
SteelplacementhandbookSteelplacementhandbook
Steelplacementhandbook
 
211 ce2236
211 ce2236211 ce2236
211 ce2236
 
Steel framed building Shrilkant
Steel framed building  ShrilkantSteel framed building  Shrilkant
Steel framed building Shrilkant
 
Unit 1 Class Notes-2019 pat..pptx
Unit 1 Class Notes-2019 pat..pptxUnit 1 Class Notes-2019 pat..pptx
Unit 1 Class Notes-2019 pat..pptx
 
IRJET - Analysis and Design of Steel Box Girder Bridge using Tekla Structures
IRJET - Analysis and Design of Steel Box Girder Bridge using Tekla StructuresIRJET - Analysis and Design of Steel Box Girder Bridge using Tekla Structures
IRJET - Analysis and Design of Steel Box Girder Bridge using Tekla Structures
 
Importance of Steel Detailing for Steel Fabricators and Structural Engineers
Importance of Steel Detailing for Steel Fabricators and Structural EngineersImportance of Steel Detailing for Steel Fabricators and Structural Engineers
Importance of Steel Detailing for Steel Fabricators and Structural Engineers
 
Iii design-of-steel-structures-unit-1
Iii design-of-steel-structures-unit-1Iii design-of-steel-structures-unit-1
Iii design-of-steel-structures-unit-1
 
Lectures Note 1. Civil Construction.pptx
Lectures Note 1. Civil Construction.pptxLectures Note 1. Civil Construction.pptx
Lectures Note 1. Civil Construction.pptx
 
Miscellaneous Steel Detailing-services of Silicon Valley Infomedia
Miscellaneous Steel Detailing-services of Silicon Valley InfomediaMiscellaneous Steel Detailing-services of Silicon Valley Infomedia
Miscellaneous Steel Detailing-services of Silicon Valley Infomedia
 
Steel buildings
Steel buildings  Steel buildings
Steel buildings
 
Construction process''column,beam,slab''
Construction process''column,beam,slab''Construction process''column,beam,slab''
Construction process''column,beam,slab''
 
design drawing steel structures
design drawing steel structuresdesign drawing steel structures
design drawing steel structures
 

Recently uploaded

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 

Recently uploaded (20)

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 

ConstructionManagement.ppt

  • 1.
  • 2. What will you gain from this presentation? • Gain insight into the construction process activities for a structural steel frame of a case study office building. Slides are presented from a construction management point of view. • Develop an understanding of the duration and sequence of activities that are part of the structural steel construction process of the case study. • Learn about how this office building was sequenced. • Observe how the structural steel frame was erected through photographs and animations. • Get acquainted with equipment used for this project.
  • 3. Introduction This presentation was developed as a teaching aid with the support of the American Institute of Steel Construction. Its objective is to introduce the user to the construction process of the structural steel frame for a common building type, a four story office building. The presentation documents the construction of the steel frame for a case study building. Photographs were taken throughout the construction process of the structural steel frame including detailing, fabrication and erection. Data from the project was also compiled including plans, schedules, specifications and other details. This information was brought together to create the following presentation. This slide show is presented from a construction management perspective. In this sense, it contains information on material procurement, sequencing, site logistics, schedules, and equipment, as well as technical aspects of the project.
  • 4. Case Study Project Description of the structural steel frame: • Office building use • 4 Stories • 80,000 square feet of building construction area • Approximately 400 tons of structural steel or 10 pounds per square foot • Approximate fabrication and erection cost 9 dollars per square foot • Standard bay size of 30ft by 30ft • 3 by 7 bays • 964 pieces of structural steel • Built in 2003
  • 5. Structural Steel Construction Phase Schedule As seen on the schedule, material procurement occurs early in the process, even before shop drawings are generated. This is done so that a steel mill has enough time to produce the required steel. Material procurement includes: quantity surveying, placing the mill order, delivery of steel from the mill and storage of the steel in the fabrication shop. Detailing includes the creation of shop drawings of each piece in the structural frame. Shop drawings are submitted to the contractor and structural engineer to ensure that they comply with the engineer’s design. Upon approval of shop drawings and arrival of steel from the mill, steel pieces are precisely fabricated. Once structural steel members are fabricated they are taken to the yard, loaded on trucks and transported to the job site for erection.
  • 6. Detailing Process During the detailing process, the detailer develops shop drawings for each structural steel member in the structure. Each member is assigned a unique piece mark for identification and tracking. The detailer also prepares a list with a description of the structural steel members.
  • 7. Shop Drawings These are shop drawings of columns 3C1 and 3C2 for the case study project. Shop drawings convey precise information to the fabricator, and other project parties about how each steel member in the structure is to be fabricated.
  • 8. Materials Raw steel used to fabricate structural steel members can be purchased from a steel mill or steel service center. Material purchased from a steel service center is usually more expensive, but may be quicker to obtain and can be ordered in smaller quantities. The material for the case study project was ordered directly from a mill and delivered in two batches approximately 4 and 5 weeks after the mill order was placed. Once the material arrived at the fabricator’s shop it was organized and stored in the yard.
  • 9. Fabrication Structural steel members are fabricated by precisely cutting, shearing, punching, drilling, fitting and welding in order to produce the configurations detailed in the shop drawings. Each member is labeled with a piece mark, length, and job number for identification.
  • 10. Piece Mark Once fabricated, each finished structural steel member is labeled. In this case the fabricator labeled each steel member with its piece mark, sequence number, and the last two digits of the job number. Specific labeling practices may vary by fabricator. Notice that this time the label color is yellow to differentiate it from previous labels. Labeling of the steel pieces is crucial because it will help identify members on the job site.
  • 11. Storage After fabrication, finished structural steel members are stored in the fabricator’s storage yard. The more organized the yard, the easier it will be to transport steel to the site. In this case structural steel was stored according to erection sequence. Sequences define areas of the frame and are used to organize their delivery and erection. The practice of planning and storing by sequence improves the efficiency of loading, delivery, offloading and erection.
  • 12. Anchor Rod Plan One of the first drawings prepared by the detailer is the anchor rod plan. This plan guides the foundation subcontractor in the placement of anchor rods. It contains horizontal and vertical information for placement of anchor rods, as well as dimensions and elevations of leveling plates (if used).
  • 13. Anchor Rod Details The anchor rod detail on the left depicts how anchor rods and leveling plates were placed for the case study project. A leveling plate is a steel plate fixed on top of a foundation on which a structural column can be placed. The leveling plate is leveled and grouted prior to installation of the column. Although this is one method for setting columns, practices may vary with other erectors. On the right is a photograph of the anchor rods and leveling plates in place for the case study project.
  • 14. Anchor Rod Survey Before the erection process started, anchor rods and leveling plates were surveyed by the erector’s surveyor to check if they were correctly positioned. If anchor rods are improperly located, they must be corrected by the foundation subcontractor before the erection process may start. The surveyor used a total station to determine the horizontal and vertical location of each leveling plate and anchor rod.
  • 15. Hoisting Sequences During detailing, the steel frame was divided into 6 sequences illustrated on the erection drawings. Sequences represent the order in which a zone or section of the frame will be erected. They are designed to improve efficiency of the erection process. Planning the sequences allowed for parallel construction operations to take place. For example, while the erection crew erected sequence 2, the decking crew placed metal deck at the previously placed sequence 1. In this way the deck placed at sequence 1 formed a work platform and reduced the potential fall distance when the steel contractor erected sequence 3 which was above sequence 1.
  • 16. Structural Steel Erection Schedule This is a detailed schedule of the erection process of the structural steel frame. In this project an average of 40 pieces of steel were hoisted per day. Hoisting, bolt up, detail work, decking and stud activities are performed by sequence. Hoisting consists of lifting and placing steel members into their appropriate position and temporarily fastening them using several bolts and/or welds. Plumbing up refers to the vertical alignment of the frame. Final bolt up refers to tightening the bolts which connect the components of the structure.
  • 17. STRUCTURAL STEEL ERECTION BY SEQUENCE The following is an animation of the structural steel erection process by sequence. The six sequences will slowly appear along with the working day in which hoisting of each sequence was completed. The last images to appear are of the masonry stair and elevator shafts. They were built after the frame was erected. The steel frame was connected to the vertical shafts to provide permanent lateral stability of the frame.
  • 18.
  • 19. Erection Crew Seven people formed the erection crew used for this project. The crew consisted of one foreman, two ironworkers hooking steel (upper left), two ironworkers connecting steel (upper right), a crane operator (lower left), and an oiler (lower right).
  • 20. Crane Mobilization and Set Up Crane mobilization and set up took place before structural steel members were delivered to the site. An additional crane was utilized to unload and set up the crane. Crane mobilization and setup for the project took approximately one day.
  • 21. Crane The crane used for the project was a 100 ton crawler mounted crane with a 160 foot boom and a 40 foot jib. The boom (upper right) is the main projecting structure of the crane and the jib (lower right) is the smaller structure attached to the boom. There are many configurations and sizes of cranes available. Cranes are selected on the basis of cost, availability, speed, reach and capacity.
  • 22. Crane Locations Two crane locations were used for this project. Location 1 was used to erect sequences 1, 3, and 5. Location 2 was used to erect sequences 2, 4, and 6. The crane was moved to the appropriate location for each sequence. Crane locations were approximately 45 feet from the face of the building.
  • 23. Transportation Once the on-site crane was fully set up, the fabricator loaded the steel members for sequence 1 onto trucks and transported them to the job site. Structural steel was delivered by sequence throughout the erection process. It took a total of 29 truckloads to deliver all of the structural steel for the project.
  • 24. Unloading and Shakeout Upon delivery to the job site, fabricated steel was unloaded and placed on wood or steel blocking. The blocking allowed for chokers to be attached to each member for subsequent hoisting and erection. Shakeout of structural steel took place after unloading. Shakeout is the process of sorting the steel pieces on the site so that they can be efficiently erected (lower left), and involves organizing and spacing each structural steel piece.
  • 25. Erection Drawings This is the erection drawing (e-drawing or e-sheet) of the first floor framing for the project. The numbers one and two inside the red hexagons on each side of the red line indicate the sequence number for each part of the structure. The piece marks on the drawing match those on the beams, girders and columns and are used to locate and orient each member during erection.
  • 26. Erection Order The erection crew foreman used the erection drawings to determine the exact order in which structural steel members were to be erected. The first pieces hoisted during this project were the columns in sequence 1 (right sheet), then girders and beams (left and center sheets).
  • 27. Access When planning for construction operations, the building contractor decided to pour a portion of the foundation at a later date to facilitate the access of people, materials and equipment to the lower level during construction.
  • 28. First Column This is the first column being hoisted into position. Using ladders, ironworkers temporarily bolted the column. Prior to erection, the erector must consider column stability in accordance with safety standards and the AISC Code of Standard Practice.
  • 29. Sequence 1 Columns The first structural steel members hoisted were the columns. This is a view of sequence 1 after the columns were set. Notice that all columns have a splice on the top.
  • 30. Chokers A choker is a rigging assembly used to attach a load to a hoisting device. It is usually made of wire rope or synthetic fiber. Chokers are used to hoist beams into position. They are positioned at the center of gravity of the beam so that the beam remains level when hoisted.
  • 31. Multiple Lift Rigging Multiple lift rigging is a process used to hoist several pieces of steel simultaneously. This is accomplished by utilizing a rigging assembly that facilitates the attachment of up to five independent loads to the hoist rigging of a crane. In this project up to four beams were hoisted at a time. Multiple lift rigging speeds the lifting process by reducing the total number of lifts required for the frame.
  • 32. Preliminary Bolting The connector uses pins to align the holes between structural steel members being connected. Then he places several bolts and temporarily tightens them with his spud wrench. At least two bolts per connection are used to temporarily fasten each connection.
  • 33. Hand Signals Teamwork and communication are important when erecting steel. Ironworkers use hand signals to communicate with the crane operator (left). The photograph in the right presents a situation in which the crane operator could not see the member being connected. In this case, an ironworker was located where he could be seen by both the crane operator and the other ironworkers. This ironworker was able to guide the crane operator using standard hand signals.
  • 34. Beams Main girders are hoisted after the columns. Beams are then hoisted and connected to the girders. On the left is a photograph of the first bay to be hoisted. On the right is a photograph of the first three bays in place.
  • 35. Sequence 1 Sequence 2 This is a view of the completed hoisting activity for sequences 1 (left) and 2 (right). It took approximately 5 days to hoist the 166 pieces of steel that are part of the two sequences.
  • 36. Erection Schedule The activities in yellow were completed by the time sequence 2 was hoisted. Notice how deck and studs for sequence 1 starts before hoisting sequence 3 to provide fall protection for the ironworkers connecting steel.
  • 37. Metal Decking This is the metal decking used in the project. The erector had the responsibility of unloading and hoisting metal decking to pre- established positions on the frame.
  • 38. Hoisting Metal Decking On the left is a plan specifying where bundles of decking were to be placed by the erector. Considerations for placement locations included both the productivity of the deck installers and construction loading. Each bundle was identified with a number and placed at its preplanned location.
  • 39. Metal Decking Metal deck was placed and attached with a series of welds. Controlled deck zones were used during installation. A controlled deck zone is an area in which initial installation and placement of metal decking may take place without the use of guardrail systems, personal fall arrest systems, fall restraint systems, or safety net systems and where access to the zone is controlled.
  • 40. Metal Decking This is a view (lower left) of the welding used to fasten metal deck to the structure.
  • 41. Perimeter Safety Cables On multi-story structures, perimeter safety cables are installed at the interior and exterior perimeters of floors and openings as soon as the metal decking has been installed.
  • 42. Shear Studs These are shear studs. The white rings are ceramic ferrules. The ceramic ferrule constrains the molten metal into which the stud is thrust automatically and a high quality fusion weld is accomplished where the weld is stronger than the stud itself.
  • 43. Welding Shear Studs Snow was removed from the locations where shear studs were to be placed (upper left). Using a stud- welding gun (an automatic welding device) the shear studs were then welded to the structural members below the metal decking. Shear studs are used to ensure a composite action between the concrete slab and structural steel beams (upper right). Whether shear studs are used is a function of the structural engineer’s design.
  • 44. Shear Studs This is a view of the welded studs. Shear studs were tested to ensure that they were correctly welded to the structural steel members in compliance with the bend test of the AWS D 1.1 Structural Welding Code.
  • 45. Sequence 3 Sequence 4 This is a view of the completed hoisting activity for sequences 3 and 4. Hoisting these two sequences took approximately 9 days in contrast with the five days it took to hoist sequences 1 and 2, because sequences 3 and 4 consisted of two floors (365 pieces of steel) and sequences 1 and 2 consisted of one floor (166 pieces of steel).
  • 46. Erection Schedule The activities in yellow are the ones completed by the time sequence 4 was hoisted. Notice that deck and studs for sequence 3 were started before hoisting sequence 5 in order to provide fall protection for the ironworkers connecting steel. Plumbing up and final bolt up for sequences 1 through 4 were performed after sequence 4 was hoisted.
  • 47. Temporary Bracing Temporary bracing was placed before plumbing up the structural frame. Temporary bracing is used to provide temporary lateral stability to the structure and to plumb up the frame. The temporary bracing was removed by the erector once the structural steel frame was secured to the vertical masonry elevator and stair shafts, which were installed after completion of the steel frame.
  • 48. Plumbing Up Plumbing up refers to the vertical alignment of the structure in accordance with the AISC Code of Standard Practice. A theodolite was used to verify the alignment of columns in the perimeter of the building. The foreman directed ironworkers on the structure to shift the frame using the temporary bracing.
  • 49. Plumbing Up Turnbuckles (lower left) are a common part of the bracing system. A turnbuckle is a device that usually consists of a link with screw threads at both ends that is turned to bring the ends closer together. Using several turnbuckles connected to the temporary bracing, the steel frame was shifted until it was vertically aligned.
  • 50. Final Bolt-up After a section of the structural frame was assembled and vertically aligned, ironworkers permanently fastened the structural steel members with additional bolts and welds. Tension controlled bolts (F1852) were used. Final bolt-up was performed using a torque wrench. The wrench stops automatically when the bolt shears at a tension control groove indicating that the required tension is reached.
  • 51. Sequence 5 Sequence 6 This is a view of the completed hoisting activity for sequences 5 (left) and 6 (right). It took approximately 9 days to hoist both sequences, similar to sequences 3 and 4.
  • 52. Erection Schedule The activities in yellow are the ones completed by the time sequence 6 was hoisted. Plumbing up and final bolt up for sequences 5 through 6 was performed after sequence 6 was hoisted. Hoisting sequence 6 was the last activity that required the use of the crane. After hoisting sequence 6 the crane was demobilized.
  • 53. Lateral Stability Masonry elevator and stair shafts were installed after the steel frame was erected. The steel frame was secured to the shafts of the building at each floor providing lateral stability for the frame.
  • 54. Slabs Floor slabs were poured (upper right) after the structural steel frame was secured to the vertical masonry shafts. After reinforcing steel (upper left) and concrete were placed, the slab was leveled and finished (lower left).
  • 55. Slabs This is a view of the finished slab. At this point the structural frame of the building is complete.
  • 56. Inspection The structural steel frame was inspected upon completion by the local jurisdiction and work could proceed accordingly. Depending on frame complexity, additional periodic inspection and testing may also be required by the local jurisdiction. The design engineer also conducts contract administration and field observation activities which help ensure quality.
  • 57. Fireproofing Structural steel has to be protected from fire. Steel will not burn, but it may become soft and weak when exposed to intense heat. Building codes regulate the need for fire protection and its required locations. There are several methods for fire protection. The method utilized for this project was spray-on fire protection. Spray-on material may be portland cement or a gypsum-based product and can be applied directly to structural steel members.
  • 58. Finished Building This is how the building will look after it is completed. The structural steel frame is one of the most important parts of the building. Building with steel has several advantages over other building materials. Steel can be erected year round. It is light yet strong when compared with other structural frame materials. Steel can also be adapted to almost any imaginable shape. One of the biggest advantages is that it can be erected very fast.