First Oil Tie-in's Status First Oil Tie-in's Status First Oil Tie-in's Status
M007-SOQ-STR-DWG-UCSTEDU-F1-00623_REV1.0
1. CB 04
10000
SB 09
SB 06
SB05SB04SB02
SB03
SB 07
SB07
SB 08 SB 10 CB 01 CB 02 CB 03 CB 05
SB01
Masterflex W4 Waterstop
at Vertical Construction Joint
Masterflex W4 Waterstop
at Horizontal Construction Joint
Masterflex W4 Waterstop
at Horizontal Construction Joint
Masterflex W4 Waterstop
at Vertical Construction Joint
STAGE -1
TEMPORARY SHUTTER FIXING
STAGE -2
MASTERFLEX W4 WATERSTOP INSTALLING
ONTO TEMPORARY SHUTTER
STAGE -3
BASF INJECTION FLANGES INSTALLING
ONTO TEMPORARY SHUTTER
STAGE -4
BASF INJECTION FLANGES HOSE & RE-INJECTABLE HOSE
INSTALLING INTO WALL OUTSIDE JUNCTION BOX
INJECTION FLANGES HOSE
STAGE -5
RETAINING WALL CASTING
STAGE -6
FINAL STAGE TEMPORARY SHUTTER
REMOVE AND APPLIED PVC WATERPROOFING SYSTEM
VARIES
Geotextile 350gm
5mm Polypropylene Protection Board
Masterpren BG 2mm
PVC Waterproofing Membrane
Geotextile 140gm
FixingDistance<1.5M
BASF PVC Roundelle, Dia. approx. 80mm
fixed with nail and washer
Masterpren BG 2mm
PVC Waterproofing Membrane
hot air welded to PVC Roundelle
FixingDistance<1.5M
BASF Injection Flanges
Injection Flanges Hose
Junction Box
Retaining Wall
BASF Injection Flanges
Existing Masterflex W4
Waterstop (Through the Raft Slab)
Existing Masterflex W4 Waterstop
(Through the Raft Slab)
Masterflex W4 Waterstop
200mm extended for new
welding Masterflex w4
New Masterflex W4 Waterstop welded
onto Vertical Masterflex W4 Waterstop
Masterflex W4 Waterstop (Horizontal cj.)
Re-injectable Hose (Horizontal)
Re-injectable Hose (Horizontal)
Existing Masterflex W4
Waterstop through to Raft Slab
(Horizontal cj.)
RE-INJECTABEL HOSE
VARIES
cj.
cj.
Masterflex W4 Waterstop
at Vertical Construction Joint
Masterflex W4 Waterstop
at Horizontal Construction Joint
BASF Injection Flange
BASF Injection Flange
Masterflex W4 Waterstop
at Horizontal Construction Joint
JUNCTION BOX
Injection Flanges Hose
RE-INJECTABEL HOSE
BASF Injection Flange
BASF Injection
Flange
INJECTION FLANGES HOSE
RE-INJECTABEL HOSE
Masterflex W4 Waterstop
at Horizontal Construction Joint
JUNCTION BOX
Injection Flanges Hose
RE-INJECTABEL HOSE
BASF Injection Flange
BASF Injection
Flange
RETAINING WALL
RETAINING WALL
RE-INJECTABEL HOSE
NOTE:-
1) EVERY INJECTION FLANGES FIXED 1.5 METER
DISTANCE FROM THE WALL EDGES OR SLAB EDGES.
WBF - Wall Base Flange
WTF - Wall Top Flange
1. ALL DIMENSIONS ARE IN MM. OTHERWISE MENTIONED.
1.0 11-12-2014 HAM ISSUED FOR CONSTRUCTION SW SUJ
BRIDGES,VIADUCTS,RAMPS & STATIONS
Drawing Number :
Designed
Drawn
Dwg check
Rev
Title :
Discipline :
Project :
Client :
Consultant Endorsement :
DVE Endorsement :
STATUS PURPOSE OF ISSUE
Rev Date Drawn Description Chkd. App.
Reference Documents :
Notes :
Legends :
Design check
Eng check
Approved
Qatar Integrated Railway Project
Doha Metro : Major Stations
RTC/042/2012
Qatar Railways Company
P.O.Box 29988
Doha - Qatar
SAMSUNG - OHL - QBC Joint Venture
Key Plan :
AS SHOWN
Scale :Sheet Size
A1
HAM
HAM
S.S.T.
H.W. Kim
S.W.Nam
S.U.Ji
11-12-2014
11-12-2014
11-12-2014
11-12-2014
11-12-2014
11-12-2014
1.0
M007-SOQ-STR-DWG-UCSTEDU-F1-00623
-
-
08
INJECTION FLANGES TYPICAL
INSTALLATION DETAIL AT WALL
2. THE MASTERPREN BG ALONG WITH MASTERPREN PZ WILL BE
TEMPORARILY
LAYED ABOVE THE MASS CONCRETE PROTECTED BY SCREED AND IT
WILL BE FLIPPED OVER THE RAFT AFTER CASTING. SEE SECTION E
This drawing and any information or descriptive matter set out hereon is licensed
to the Qatar Railways Company and is confidential and subject to copyright.
It must not be disclosed, loaned, copied or used for manufacturing, tendering or
ISSUED FOR CONSTRUCTION
EDUCATION CITY STATION
Approved By Design Manager
DATE :
FOR CONSTRUCTION
11/12/2014
M007-SOQ-STR-DWG-UCSTEDU-F1-00623_REV1.0,11-12-201409:25:22