SlideShare a Scribd company logo
1 of 40
Signalling Internship
23 December 2015
Sharing Segments
1. Legacy Signalling System
2. Thales Signalling System
3. General Learning Experiences
Legacy Signalling System
Automatic Sub-Systems
Automatic Train
Operation (ATO)
Automatic Train
Protection (ATP)
Automatic Train
Supervision (ATS)
Westinghouse Signalling
System
Interlocking
OCC
Legacy System Visits
1. Night Work with YCK SMO
2. Signal Equipment Rooms
3. OCC ATS
Night Work (PM/CM)
YCK Signal Maintenance Office (SMO)
(4/12/15)
Dynamic Nature Of Plans
• Maintenance plans are never cast in stone.
Can change at eleventh hour.
• CM supersedes PM.
SBW Point
PM
WDL Track
Circuit Fault
AMK ATO
Tripping
AMK ATO Tripping
1 December 2015
(1630)
• Could restart in CM
1 December 2015
(1704)
• Failed several times to
restart in CM
• Had to RM to AMK SB
Approach
Check Relay
Room
Check Track
Circuit Wiring
Check ATP Loop
Feed Cable/DB
Check Relay Room
• Used the Track Circuit Monitoring Unit
(TCMU) to check carrier frequency of track
circuit.
• Checked relays.
• Pull out then replace speed code pins.
No anomalies
Check Track Circuit Wiring
• Checked for any loose
connections between tuning
unit and rails.
No anomalies
Check ATP Loop Feed Cable/DB
• Only applicable to N700 SRTC
• Codes are send through LFU
instead of the track circuit
itself.
• Checked LFU and DB
connections
No anomalies
Inconclusive Outcome
• No leads to find the true reason for ATO trip.
• Problem could now lie in train-borne
equipment (antenna? Processors?)
• Typical experiences for maintenance crew.
• Justifies the difficulty of their job.
Signal Equipment Rooms
AMK, MSL, RDH, CT, East Relay Room
Platform-ATO Communicator
Dwell Time At Station
Platform ATO
Communicator
(PAC)
Train Sends
• Positive Train
Identification (PTI)
• Train Door Status
PAC Sends
• Detailed track profile
for next 2 interstation
runs
• Door Close command
• PSD Status
OCC
Victoria St
Environment
Legacy ATS System
Schedule
Compiler
LPU
OCC
Allocation
Table
IL/S
LPU LPU
I/S
IL/S IL/S
I/S I/S I/S I/S I/S
IL/S – Interlocking Station
I/S – Intermediate Station
Legacy Schedule Compiler
• Compiles Weekday, Weekend
and Special Schedules.
• Must define track layout and
station stopping positions.
• Conflicts must be resolved
manually.
• Revisions are done as and
when needed.
• Demand-driven schedule
formulation
Dwell Time Problems
Real Life Problems with ATS and
ATO
Dwell Time Problems
• PSDs cannot close properly.
• Train-borne ATO or PAC may not be
communicating door status properly to the
train.
Dwell Time Problems
https://youtu.be/Bg1LYEQF4TU
Consequences
• Train timings deviates from schedule.
• Peak hour schedules that barely passed
schedule feasibility checks will now be
unfeasible.
• Increase likelihood of schedule conflicts due
to delayed trains.
Potential Solutions
• PSD Health Monitoring System
• Monitoring times when PAC didn’t receive or
send the Door Open/Close signal properly.
Thales CBTC System
Automatic Sub-Systems
ATO
Automatic Train
Supervision (ATS)
Thales
CBTC System
Interlocking
OCC
Train-Borne
PMI MAU
Zone Controller
ATP
ATO
ATP
VOBC
Thales CBTC System Visits
1. QUE WRU PICO
2. CBTC Train Testing
Installation Procedures
Signal Light
1. Prelim
2. PICO DB
3. Install/Cut-In
4. PICO everything
5. SAT
Other Equipment
1. Install
2. PICO
3. Cut-In
4. SAT
QUE WRU PICO
WB Trackside
QUE WRU PICO
• Check out the conditions
of the wayside WRUs.
Casing and circuitry.
• Check earthing of
equipment
• Used Cable Tester (VSWR)
(AP broadcasting) and
Spectral Analyser (power
supply)
Overall Experience
• Working in imminent rain conditions.
• Extreme care towards WRU setup.
• WRU ponding issue due to condensation.
• Breather valve.
Static and Dynamic Testing
KHI 097/098
Static Test
• Check if the correct
outcomes happen when
controls are set in a certain
way.
• Copy and paste the
command code into
computer which connects
to VOBC.
Dynamic Test
• Test the train’s performance
in various driving modes.
• Test the 2 VOBCs ability to
control train in DTO.
• Test the stopping accuracy.
Overall Experience
• First time experiencing the new ATO system.
• It is teamwork to test trains.
General Learning Experiences
First Internship
Learning Experiences
• System Management and Maintenance
• Keeping records of the day’s proceedings
• Better picture of my future role in rail
industry.
Internship Experience
• Insightful and fulfilling
• Free and easy exploring nature.
Thank You

More Related Content

What's hot

FEAS_Poster_2016_WNCS_Tina
FEAS_Poster_2016_WNCS_TinaFEAS_Poster_2016_WNCS_Tina
FEAS_Poster_2016_WNCS_Tina
Tina Mirfakhraie
 
1.08 European Traffic Management Approaches-Ello Weits-Emmanuel Houriez NR
1.08 European Traffic Management Approaches-Ello Weits-Emmanuel Houriez NR1.08 European Traffic Management Approaches-Ello Weits-Emmanuel Houriez NR
1.08 European Traffic Management Approaches-Ello Weits-Emmanuel Houriez NR
Ello Weits
 

What's hot (20)

ETCS
ETCSETCS
ETCS
 
India railway and green infra smart move 2018
India railway and green infra smart move 2018India railway and green infra smart move 2018
India railway and green infra smart move 2018
 
Strategic analysis of communications based train control systems in the weste...
Strategic analysis of communications based train control systems in the weste...Strategic analysis of communications based train control systems in the weste...
Strategic analysis of communications based train control systems in the weste...
 
Train sense
Train senseTrain sense
Train sense
 
FEAS_Poster_2016_WNCS_Tina
FEAS_Poster_2016_WNCS_TinaFEAS_Poster_2016_WNCS_Tina
FEAS_Poster_2016_WNCS_Tina
 
RTD FasTracks - INCOSE Colorado Front Range Chapter Presentation - Dec, 2014
RTD FasTracks - INCOSE Colorado Front Range Chapter Presentation - Dec, 2014RTD FasTracks - INCOSE Colorado Front Range Chapter Presentation - Dec, 2014
RTD FasTracks - INCOSE Colorado Front Range Chapter Presentation - Dec, 2014
 
Need for platform-to-track intrusion detection systems in automated metro lines
Need for platform-to-track intrusion detection systems in automated metro linesNeed for platform-to-track intrusion detection systems in automated metro lines
Need for platform-to-track intrusion detection systems in automated metro lines
 
CBTC fitting strategies and challenges for maintenance vehicles
CBTC fitting strategies and challenges for maintenance vehiclesCBTC fitting strategies and challenges for maintenance vehicles
CBTC fitting strategies and challenges for maintenance vehicles
 
Dubai metro paper in ASPECT Conference
Dubai metro paper in ASPECT Conference Dubai metro paper in ASPECT Conference
Dubai metro paper in ASPECT Conference
 
ERTMS and Brexit
ERTMS and BrexitERTMS and Brexit
ERTMS and Brexit
 
THE FINAL
THE FINALTHE FINAL
THE FINAL
 
Towards railway virtual coupling
Towards railway virtual couplingTowards railway virtual coupling
Towards railway virtual coupling
 
Automated railway level crossing protection system-track circuit
Automated railway level crossing protection system-track circuitAutomated railway level crossing protection system-track circuit
Automated railway level crossing protection system-track circuit
 
1.08 European Traffic Management Approaches-Ello Weits-Emmanuel Houriez NR
1.08 European Traffic Management Approaches-Ello Weits-Emmanuel Houriez NR1.08 European Traffic Management Approaches-Ello Weits-Emmanuel Houriez NR
1.08 European Traffic Management Approaches-Ello Weits-Emmanuel Houriez NR
 
Sro Project Brief
Sro Project BriefSro Project Brief
Sro Project Brief
 
CONCEPT AND WORKING OF WILD (Wheel Impact Load Detector)
CONCEPT AND WORKING OF WILD (Wheel Impact Load Detector)CONCEPT AND WORKING OF WILD (Wheel Impact Load Detector)
CONCEPT AND WORKING OF WILD (Wheel Impact Load Detector)
 
RDSO Training ppt
RDSO Training pptRDSO Training ppt
RDSO Training ppt
 
Ieeepro techno solutions 2013 ieee embedded project - adaptive traffic sig...
Ieeepro techno solutions   2013 ieee embedded project  - adaptive traffic sig...Ieeepro techno solutions   2013 ieee embedded project  - adaptive traffic sig...
Ieeepro techno solutions 2013 ieee embedded project - adaptive traffic sig...
 
AJAY CHAUHAN ppt
AJAY CHAUHAN pptAJAY CHAUHAN ppt
AJAY CHAUHAN ppt
 
3 gpp lte-pdcp
3 gpp lte-pdcp3 gpp lte-pdcp
3 gpp lte-pdcp
 

Viewers also liked

JoannaBergerMScDissertation
JoannaBergerMScDissertationJoannaBergerMScDissertation
JoannaBergerMScDissertation
Joanna Berger
 
Pd fbuoi7 8--tongquanseo-mastercode.vn
Pd fbuoi7 8--tongquanseo-mastercode.vnPd fbuoi7 8--tongquanseo-mastercode.vn
Pd fbuoi7 8--tongquanseo-mastercode.vn
MasterCode.vn
 
Blending with deltav
Blending with deltavBlending with deltav
Blending with deltav
Luis Atencio
 
Summit72_extremedreams
Summit72_extremedreamsSummit72_extremedreams
Summit72_extremedreams
Ash Fusiarski
 

Viewers also liked (17)

FDA Internship Review
FDA Internship ReviewFDA Internship Review
FDA Internship Review
 
goodreadppt
goodreadpptgoodreadppt
goodreadppt
 
KUFRE'S CV 1
KUFRE'S CV 1KUFRE'S CV 1
KUFRE'S CV 1
 
ResumeDec2015
ResumeDec2015ResumeDec2015
ResumeDec2015
 
Ppt0000003
Ppt0000003Ppt0000003
Ppt0000003
 
JoannaBergerMScDissertation
JoannaBergerMScDissertationJoannaBergerMScDissertation
JoannaBergerMScDissertation
 
Eastern Bloc vehicles
Eastern Bloc vehiclesEastern Bloc vehicles
Eastern Bloc vehicles
 
Rolling stock by manufacturer CSR rolling stock corporation limited china
Rolling stock by manufacturer CSR rolling stock corporation limited chinaRolling stock by manufacturer CSR rolling stock corporation limited china
Rolling stock by manufacturer CSR rolling stock corporation limited china
 
Atagg 2015 Test automation and effective continuous integration
Atagg 2015 Test automation and effective continuous integrationAtagg 2015 Test automation and effective continuous integration
Atagg 2015 Test automation and effective continuous integration
 
Pdf buoi1 2-on-page-tran-ngoc-chinh-mastercode.vn
Pdf buoi1 2-on-page-tran-ngoc-chinh-mastercode.vnPdf buoi1 2-on-page-tran-ngoc-chinh-mastercode.vn
Pdf buoi1 2-on-page-tran-ngoc-chinh-mastercode.vn
 
Smart Lock for Password @ Game DevFest Bangkok 2015
Smart Lock for Password @ Game DevFest Bangkok 2015Smart Lock for Password @ Game DevFest Bangkok 2015
Smart Lock for Password @ Game DevFest Bangkok 2015
 
Pokemon GO 101@Nextzy
Pokemon GO 101@NextzyPokemon GO 101@Nextzy
Pokemon GO 101@Nextzy
 
Pd fbuoi7 8--tongquanseo-mastercode.vn
Pd fbuoi7 8--tongquanseo-mastercode.vnPd fbuoi7 8--tongquanseo-mastercode.vn
Pd fbuoi7 8--tongquanseo-mastercode.vn
 
online hotel management system
online hotel management system online hotel management system
online hotel management system
 
Blending with deltav
Blending with deltavBlending with deltav
Blending with deltav
 
Summit72_extremedreams
Summit72_extremedreamsSummit72_extremedreams
Summit72_extremedreams
 
US9314934B2
US9314934B2US9314934B2
US9314934B2
 

Similar to SMRT Internship Sharing_V2

ENIF - A Supplier's View_Antonio Bravo - IRSE
ENIF - A Supplier's View_Antonio Bravo - IRSEENIF - A Supplier's View_Antonio Bravo - IRSE
ENIF - A Supplier's View_Antonio Bravo - IRSE
Antonio Bravo Vera
 
railway gate using servo and arduino uno
railway gate using servo and arduino unorailway gate using servo and arduino uno
railway gate using servo and arduino uno
Hamed Raza
 
railway gate using arduino uno and servo motors
railway gate using arduino uno and servo motorsrailway gate using arduino uno and servo motors
railway gate using arduino uno and servo motors
Hamed Raza
 
Computer modeling-simulation&examples1
Computer modeling-simulation&examples1Computer modeling-simulation&examples1
Computer modeling-simulation&examples1
Jian Shen
 
Marine Automation 20151107c
Marine Automation 20151107cMarine Automation 20151107c
Marine Automation 20151107c
Stephen Wright
 
TSE SCADA Design presentation new
TSE SCADA Design presentation newTSE SCADA Design presentation new
TSE SCADA Design presentation new
Mohamed ElSirsy
 
Oscilloscopes and Scan Tools
Oscilloscopes and Scan ToolsOscilloscopes and Scan Tools
Oscilloscopes and Scan Tools
Praneel Chand
 

Similar to SMRT Internship Sharing_V2 (20)

How to perform trouble shooting based on counters
How to perform trouble shooting based on countersHow to perform trouble shooting based on counters
How to perform trouble shooting based on counters
 
Carrier_Protn_08_01_16 - Copy.pdf
Carrier_Protn_08_01_16 - Copy.pdfCarrier_Protn_08_01_16 - Copy.pdf
Carrier_Protn_08_01_16 - Copy.pdf
 
Carrier_Protn_08_01_16.pdf
Carrier_Protn_08_01_16.pdfCarrier_Protn_08_01_16.pdf
Carrier_Protn_08_01_16.pdf
 
Thesis Presentation on Renewal theory based 802.15.6 latest.pptx
Thesis Presentation on Renewal theory based 802.15.6 latest.pptxThesis Presentation on Renewal theory based 802.15.6 latest.pptx
Thesis Presentation on Renewal theory based 802.15.6 latest.pptx
 
ENIF - A Supplier's View_Antonio Bravo - IRSE
ENIF - A Supplier's View_Antonio Bravo - IRSEENIF - A Supplier's View_Antonio Bravo - IRSE
ENIF - A Supplier's View_Antonio Bravo - IRSE
 
railway gate using servo and arduino uno
railway gate using servo and arduino unorailway gate using servo and arduino uno
railway gate using servo and arduino uno
 
railway gate using arduino uno and servo motors
railway gate using arduino uno and servo motorsrailway gate using arduino uno and servo motors
railway gate using arduino uno and servo motors
 
eTPU to GTM Migration Presentation
eTPU to GTM Migration PresentationeTPU to GTM Migration Presentation
eTPU to GTM Migration Presentation
 
Computer modeling-simulation&examples1
Computer modeling-simulation&examples1Computer modeling-simulation&examples1
Computer modeling-simulation&examples1
 
Caged Quadrotor Drone for Inspection of HVAC Ducts
Caged Quadrotor Drone for Inspection of HVAC DuctsCaged Quadrotor Drone for Inspection of HVAC Ducts
Caged Quadrotor Drone for Inspection of HVAC Ducts
 
Adaptive Traffic Control Systems Overview
Adaptive Traffic Control Systems OverviewAdaptive Traffic Control Systems Overview
Adaptive Traffic Control Systems Overview
 
Marine Automation 20151107c
Marine Automation 20151107cMarine Automation 20151107c
Marine Automation 20151107c
 
TSE SCADA Design presentation new
TSE SCADA Design presentation newTSE SCADA Design presentation new
TSE SCADA Design presentation new
 
ac ac control system problems.pptx
ac ac control system problems.pptxac ac control system problems.pptx
ac ac control system problems.pptx
 
Oscilloscopes and Scan Tools
Oscilloscopes and Scan ToolsOscilloscopes and Scan Tools
Oscilloscopes and Scan Tools
 
Major project iii 3
Major project  iii  3Major project  iii  3
Major project iii 3
 
Signaling system principle
Signaling system principleSignaling system principle
Signaling system principle
 
Static_Time_Analysis.pptx
Static_Time_Analysis.pptxStatic_Time_Analysis.pptx
Static_Time_Analysis.pptx
 
2.3b access control random access methods - part 3 - csma ca
2.3b access control   random access methods - part 3 - csma ca2.3b access control   random access methods - part 3 - csma ca
2.3b access control random access methods - part 3 - csma ca
 
S&T Presentation.pptx
S&T Presentation.pptxS&T Presentation.pptx
S&T Presentation.pptx
 

SMRT Internship Sharing_V2