FORMWORK
by Er. Ankaj Kumar
Formwork
(Shuttering)
What is Formwork?
• Formwork is a mould including all supporting
structures, used to shape and support the
concrete until it attains sufficient strength to
carry its own weight.
• It should be capable of carrying all imposed
dead and live loads apart from its own weight.
Formwork is commonly made of
• Steel andTimber
TIMBER FORMWORK
STEEL FORMWORK
• Formwork has been in use since the beginning
of concrete construction.
• New materials such as steel, plastics and
fibreglass are used in formwork.
• Greater attention is being given to the design,
fabrication, erection and dismantling of
formwork
• Formwork is designed according to The ACI
document SP-4.
Qualities of Formwork
• It should be water tight.
• It should be strong.
• It can be reusable.
• Its contact surface should be uniform.
• It should be according to the size of member.
In order to successfully carry out its function, formwork
must achieve a balance of following requirements:
• Containment
• Strength
• Resistance To Leakage
• Accuracy
• Ease Of Handling
• Finish And Reuse Potential
• Access For Concrete
• Economy
• Containment: formwork must be capable of
shaping and supporting the fluid concrete
until it cures.
• Strength: formwork must be capable of safely
withstanding without distortion or danger the
dead weight of the fluid concrete is placed on
it, labour weight, equipment weight and any
environmental loadings.
• Ease of Handling: form panels and units
should be designed so that their maximum
size does not exceed that which can be easily
handled by hand or mechanical means. – In
addition all formwork must also be designed
and constructed to include facilities for
adjustments, levelling, easing and striking
without damage to the form work or concrete
• Economy: All the formwork is very expensive. On
average about 35% of the total cost of any
finished concrete unit or element can be
attributed to its formwork; of this just over 40%
can be taken for material for formwork and 60%
for labour. – The formwork designer must
therefore not only consider the maximum
number of times that any form can be reused,
but also produce a design that will minimize the
time taken for erection and striking
Major objectives considered in
formwork:
➢ Quality
➢ Safety
➢ Economy
• Quality: Forms must be designed and built
with sufficient stiffness and accuracy so that
the size, shape, position, and finish of the cast
concrete are maintained. so that they have
• Safety: Forms must be built sufficient strength
and factor of safety the capable of all
supporting loads.
• Economy: Forms must be built efficiently,
minimizing time and cost.
Requirements of formwork:
• Material should be cheap and re usable,
• It should be practically water proof, so that it should
not absorb water from concrete,
• Swelling and shrinkage should be minimum,
• Strong enough to with stand all external loads,
• Deflection should be minimum,
• Surface should be smooth, and afford easy striping,
• Light in weight, so that easy to transfer,
• Joints should be stiff, so that lateral deformation and
leak is minimum .
Three stages in the process :
a) Assembly and erection
b) Concrete placement.
c) Stripping and dismantling.
Formwork detail for different
structural members
• In concrete construction formwork is commonly
provided for the following structural members.
• Wall
• Column
• Slabs & Beams
• Stairs o Chimneys
• Water tanks
• Cooling Towers
Formwork for Wall
It consists of
Timber sheeting
• Vertical posts
• Horizontal members
• Rackers
• Stakes
• Wedges
➢ After completing one
side of formwork
reinforcement is provided
at the place then the
second side formwork is
provided.
Formwork for Column
It consists of the
following – Side & End
Planks – Yoke – Nut &
Bolts
• Two end & two side
planks are joined by the
yokes and bolts.
Formwork for columns
Formwork for Slabs & beams
It consistsof
– Sole plates
– Wedges
– Props
– Head tree
– Planks
– Batten
– Ledgers
• Beam formworkrests on
headtree
• Slab form work restson battens
andjoists
• If prop height aremore than 8’
provide horizontalbraces.
Lintel or Beam Formwork
FORMWORK FOR SLAB
FORMWORK FOR STAIRS
It consists of
– Vertical & inclined
posts
– Inclined members
-- Wooden Planks or
sheeting
– Stringer
– Riser Planks
FORMWORK FOR STAIRS
FORMWORK FOR SPIRAL STAIRS
FORMWORK FOR CHIMNEYS
For tall chimneys two
types of forms
techniques are in
generally use in our
country
a) Jump form
b) Slip form
Removal of formwork
• Time of formwork removal depends on the following factors:
Type of Cement
Rapid hardening cements require lesser time as compared to OPC
(Ordinary Portland Cement)
Ratio of concrete mix
Rich ratio concrete gain strength earlier as compared to weak
ratio concrete.
Weather condition
Hydration process accelerates in hot weather conditions as
compared to cold and humid weather conditions
Time of Removal of formwork
Comparison between Steel and
Timber Formwork
• Steel forms are stronger, durable, and have a longer life
than timber formwork and their reuses are more in
number.
• Steel forms can be installed and dismantled with greater
ease and speed.
• The quality of exposed concrete surface by using steel
forms is good and such surfaces need no further
treatment.
• Steel formwork does not absorb moisture from concrete.
• Steel formwork does not shrink or warp.
Cantilever slab
First free end's support
should be removed.
• And then from right to
left it
should be proceed.
• If we are removing
from the
mid span then it will act
as a
prop cantilever.
Simply supported slab
In simply supported
we have to remove
the support from the
mid span to the
ends.
• To meet the design
behavior.
Maintenance of formwork
• Due to continuous use wooden planks & steel
plates surfaces become uneven and require
maintenance.
• For wooden formwork use cardboard or plastic
fiber board. Bolt hole places must also be
repaired.
• For steel formwork plates must be leveled by
mallet and loose corners must be welded.
Cost of formwork
• For normal works cost of formwork is about 30%-
40% of the concrete cost.
➢ For special works cost of formwork is about
50%-60% of the concrete cost.
➢ Formwork cost is controlled by the following
factors
• Formwork Material cost
• Formwork erecting cost
• Formwork removal cost
• Formwork jointing cost (Nails and Cables)
• Labor charges
Advantages of steel form work
• It can be used for a no. of times.
â–Ş It is non absorbent.
â–Ş Smooth finish surface obtained.
â–Ş No shrinkage of formwork occurs.
â–Ş Easy to use.
â–Ş Its volume is less
â–Ş Its strength is more
LOADS ON FORMWORK
Dead load
â–Ş Self weight of formwork
â–Ş Pressure and loads from fresh concrete
â–Ş Reinforcement
• Imposed load
â–Ş Construction workers
â–Ş Stacking of materials
• Horizontal loads
• Environmental loads
â–Ş Accidental loads
â–Ş Wind loads
References
• R.C.C Design by B.C.Punmia
• R.C.C Design by H.J.Shah
• Formwork Design Section 1500
• Doka Formwork Design
• Design of safe timber structures by Eva and
Tomi Torrati
THANK YOU

More Related Content

What's hot (20)

Formwork
FormworkFormwork
Formwork
 
Ground and upper floor
Ground and upper floorGround and upper floor
Ground and upper floor
 
Roof
RoofRoof
Roof
 
Formwork
FormworkFormwork
Formwork
 
7. building components
7. building components7. building components
7. building components
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shuttering
 
Walls
WallsWalls
Walls
 
blockwork
 blockwork blockwork
blockwork
 
Roof and roof covering
Roof and roof coveringRoof and roof covering
Roof and roof covering
 
Masonry work
Masonry workMasonry work
Masonry work
 
Roofing materials
Roofing materialsRoofing materials
Roofing materials
 
types of Foundations with animated sketches
types of Foundations with animated sketchestypes of Foundations with animated sketches
types of Foundations with animated sketches
 
Roof covering
Roof coveringRoof covering
Roof covering
 
Floors
FloorsFloors
Floors
 
Roof and roof coverings
Roof and roof coveringsRoof and roof coverings
Roof and roof coverings
 
Reinforced Cement Concrete (RCC)
Reinforced Cement Concrete (RCC) Reinforced Cement Concrete (RCC)
Reinforced Cement Concrete (RCC)
 
Floor
FloorFloor
Floor
 
Formwork
FormworkFormwork
Formwork
 
Form-work in construction
Form-work in construction Form-work in construction
Form-work in construction
 
Structural Steel Work
 Structural Steel  Work Structural Steel  Work
Structural Steel Work
 

Similar to FORMWORK.pptx

Formwork
FormworkFormwork
Formworksnehakaira
 
Formwork, by prof. sagar raut
Formwork, by prof. sagar rautFormwork, by prof. sagar raut
Formwork, by prof. sagar rautSAGAR RAUT
 
formwork Bco (1) final.pdf
formwork Bco (1) final.pdfformwork Bco (1) final.pdf
formwork Bco (1) final.pdfFaizanSolanki
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formworkKHUSHBU SHAH
 
All you need to know about Construction Formwork
All you need to know about Construction FormworkAll you need to know about Construction Formwork
All you need to know about Construction FormworkAnkit Singhai
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structuresRithika Ravishankar
 
Introduction and types of Form Work in civil engineering
Introduction and types of Form Work in civil engineeringIntroduction and types of Form Work in civil engineering
Introduction and types of Form Work in civil engineeringUjasPandya2
 
Formwork 151220193813
Formwork 151220193813Formwork 151220193813
Formwork 151220193813Anoop Banshiwal
 
types of formwork.pdf
types of formwork.pdftypes of formwork.pdf
types of formwork.pdfReigerRoyal
 
Types of formwork
Types of formworkTypes of formwork
Types of formworkAglaia Connect
 
6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTUVATSAL PATEL
 

Similar to FORMWORK.pptx (20)

Formwork
FormworkFormwork
Formwork
 
Formwork
FormworkFormwork
Formwork
 
Formwork
FormworkFormwork
Formwork
 
Formwork, by prof. sagar raut
Formwork, by prof. sagar rautFormwork, by prof. sagar raut
Formwork, by prof. sagar raut
 
Formwork
FormworkFormwork
Formwork
 
formwork Bco (1) final.pdf
formwork Bco (1) final.pdfformwork Bco (1) final.pdf
formwork Bco (1) final.pdf
 
FormWork
FormWork FormWork
FormWork
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
All you need to know about Construction Formwork
All you need to know about Construction FormworkAll you need to know about Construction Formwork
All you need to know about Construction Formwork
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structures
 
Introduction and types of Form Work in civil engineering
Introduction and types of Form Work in civil engineeringIntroduction and types of Form Work in civil engineering
Introduction and types of Form Work in civil engineering
 
CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)
 
Formwork
FormworkFormwork
Formwork
 
Formwork 151220193813
Formwork 151220193813Formwork 151220193813
Formwork 151220193813
 
types of formwork.pdf
types of formwork.pdftypes of formwork.pdf
types of formwork.pdf
 
Types of formwork
Types of formworkTypes of formwork
Types of formwork
 
Gurme santoshkumar
Gurme santoshkumarGurme santoshkumar
Gurme santoshkumar
 
Form Work
Form Work Form Work
Form Work
 
Steel formwork
Steel formworkSteel formwork
Steel formwork
 
6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU
 

More from ErankajKumar

Construction Materials.pptx
Construction Materials.pptxConstruction Materials.pptx
Construction Materials.pptxErankajKumar
 
WATERPROOFING.pptx
WATERPROOFING.pptxWATERPROOFING.pptx
WATERPROOFING.pptxErankajKumar
 
Bricks_MCQ_SSC_JE_2007-18
Bricks_MCQ_SSC_JE_2007-18Bricks_MCQ_SSC_JE_2007-18
Bricks_MCQ_SSC_JE_2007-18ErankajKumar
 
Cement & Lime_SSC JE_MCQ_SOLVED_2007-2018
Cement & Lime_SSC JE_MCQ_SOLVED_2007-2018Cement & Lime_SSC JE_MCQ_SOLVED_2007-2018
Cement & Lime_SSC JE_MCQ_SOLVED_2007-2018ErankajKumar
 
TILES, MANUFACTURE,TYPES, CHARACTERISTICS OF GOOD TILES
TILES, MANUFACTURE,TYPES, CHARACTERISTICS OF GOOD TILESTILES, MANUFACTURE,TYPES, CHARACTERISTICS OF GOOD TILES
TILES, MANUFACTURE,TYPES, CHARACTERISTICS OF GOOD TILESErankajKumar
 
construction tools & equipments.pptx
construction tools & equipments.pptxconstruction tools & equipments.pptx
construction tools & equipments.pptxErankajKumar
 
construction tools.pptx
construction tools.pptxconstruction tools.pptx
construction tools.pptxErankajKumar
 
PLASTER.pptx
PLASTER.pptxPLASTER.pptx
PLASTER.pptxErankajKumar
 
BRICK MASONRY.pptx
BRICK MASONRY.pptxBRICK MASONRY.pptx
BRICK MASONRY.pptxErankajKumar
 
EXPERIMENTAL INVESTIGATION ON M25 & M30 CONCRETE WITH CONSTRUCTION & DEMOLITI...
EXPERIMENTAL INVESTIGATION ON M25 & M30 CONCRETE WITH CONSTRUCTION & DEMOLITI...EXPERIMENTAL INVESTIGATION ON M25 & M30 CONCRETE WITH CONSTRUCTION & DEMOLITI...
EXPERIMENTAL INVESTIGATION ON M25 & M30 CONCRETE WITH CONSTRUCTION & DEMOLITI...ErankajKumar
 
FOUNDATION.pptx
FOUNDATION.pptxFOUNDATION.pptx
FOUNDATION.pptxErankajKumar
 
Foundation Engineering Lab Manual
Foundation Engineering Lab ManualFoundation Engineering Lab Manual
Foundation Engineering Lab ManualErankajKumar
 
Module on fibre reinforced and foam concrete
 Module on fibre reinforced and foam concrete Module on fibre reinforced and foam concrete
Module on fibre reinforced and foam concreteErankajKumar
 
Module on Special and high performance concrete
Module on Special and high performance concreteModule on Special and high performance concrete
Module on Special and high performance concreteErankajKumar
 
Module on pozzolanic materials and fly ash
Module on pozzolanic materials and fly ash Module on pozzolanic materials and fly ash
Module on pozzolanic materials and fly ash ErankajKumar
 
Module on admixture , polymer and exposy resins
Module on admixture , polymer and exposy resinsModule on admixture , polymer and exposy resins
Module on admixture , polymer and exposy resinsErankajKumar
 
Module on light and heavy weight concrete
Module on light and heavy weight concreteModule on light and heavy weight concrete
Module on light and heavy weight concreteErankajKumar
 
special concrete and high performance concrete
special concrete and high performance concretespecial concrete and high performance concrete
special concrete and high performance concreteErankajKumar
 
pozzolanic and flyash
pozzolanic and flyashpozzolanic and flyash
pozzolanic and flyashErankajKumar
 
lightweight and heavy weight concrete
lightweight and heavy weight concretelightweight and heavy weight concrete
lightweight and heavy weight concreteErankajKumar
 

More from ErankajKumar (20)

Construction Materials.pptx
Construction Materials.pptxConstruction Materials.pptx
Construction Materials.pptx
 
WATERPROOFING.pptx
WATERPROOFING.pptxWATERPROOFING.pptx
WATERPROOFING.pptx
 
Bricks_MCQ_SSC_JE_2007-18
Bricks_MCQ_SSC_JE_2007-18Bricks_MCQ_SSC_JE_2007-18
Bricks_MCQ_SSC_JE_2007-18
 
Cement & Lime_SSC JE_MCQ_SOLVED_2007-2018
Cement & Lime_SSC JE_MCQ_SOLVED_2007-2018Cement & Lime_SSC JE_MCQ_SOLVED_2007-2018
Cement & Lime_SSC JE_MCQ_SOLVED_2007-2018
 
TILES, MANUFACTURE,TYPES, CHARACTERISTICS OF GOOD TILES
TILES, MANUFACTURE,TYPES, CHARACTERISTICS OF GOOD TILESTILES, MANUFACTURE,TYPES, CHARACTERISTICS OF GOOD TILES
TILES, MANUFACTURE,TYPES, CHARACTERISTICS OF GOOD TILES
 
construction tools & equipments.pptx
construction tools & equipments.pptxconstruction tools & equipments.pptx
construction tools & equipments.pptx
 
construction tools.pptx
construction tools.pptxconstruction tools.pptx
construction tools.pptx
 
PLASTER.pptx
PLASTER.pptxPLASTER.pptx
PLASTER.pptx
 
BRICK MASONRY.pptx
BRICK MASONRY.pptxBRICK MASONRY.pptx
BRICK MASONRY.pptx
 
EXPERIMENTAL INVESTIGATION ON M25 & M30 CONCRETE WITH CONSTRUCTION & DEMOLITI...
EXPERIMENTAL INVESTIGATION ON M25 & M30 CONCRETE WITH CONSTRUCTION & DEMOLITI...EXPERIMENTAL INVESTIGATION ON M25 & M30 CONCRETE WITH CONSTRUCTION & DEMOLITI...
EXPERIMENTAL INVESTIGATION ON M25 & M30 CONCRETE WITH CONSTRUCTION & DEMOLITI...
 
FOUNDATION.pptx
FOUNDATION.pptxFOUNDATION.pptx
FOUNDATION.pptx
 
Foundation Engineering Lab Manual
Foundation Engineering Lab ManualFoundation Engineering Lab Manual
Foundation Engineering Lab Manual
 
Module on fibre reinforced and foam concrete
 Module on fibre reinforced and foam concrete Module on fibre reinforced and foam concrete
Module on fibre reinforced and foam concrete
 
Module on Special and high performance concrete
Module on Special and high performance concreteModule on Special and high performance concrete
Module on Special and high performance concrete
 
Module on pozzolanic materials and fly ash
Module on pozzolanic materials and fly ash Module on pozzolanic materials and fly ash
Module on pozzolanic materials and fly ash
 
Module on admixture , polymer and exposy resins
Module on admixture , polymer and exposy resinsModule on admixture , polymer and exposy resins
Module on admixture , polymer and exposy resins
 
Module on light and heavy weight concrete
Module on light and heavy weight concreteModule on light and heavy weight concrete
Module on light and heavy weight concrete
 
special concrete and high performance concrete
special concrete and high performance concretespecial concrete and high performance concrete
special concrete and high performance concrete
 
pozzolanic and flyash
pozzolanic and flyashpozzolanic and flyash
pozzolanic and flyash
 
lightweight and heavy weight concrete
lightweight and heavy weight concretelightweight and heavy weight concrete
lightweight and heavy weight concrete
 

Recently uploaded

VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoĂŁo Esperancinha
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 

Recently uploaded (20)

young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 

FORMWORK.pptx

  • 3. What is Formwork? • Formwork is a mould including all supporting structures, used to shape and support the concrete until it attains sufficient strength to carry its own weight. • It should be capable of carrying all imposed dead and live loads apart from its own weight. Formwork is commonly made of • Steel andTimber
  • 6. • Formwork has been in use since the beginning of concrete construction. • New materials such as steel, plastics and fibreglass are used in formwork. • Greater attention is being given to the design, fabrication, erection and dismantling of formwork • Formwork is designed according to The ACI document SP-4.
  • 7. Qualities of Formwork • It should be water tight. • It should be strong. • It can be reusable. • Its contact surface should be uniform. • It should be according to the size of member.
  • 8. In order to successfully carry out its function, formwork must achieve a balance of following requirements: • Containment • Strength • Resistance To Leakage • Accuracy • Ease Of Handling • Finish And Reuse Potential • Access For Concrete • Economy
  • 9. • Containment: formwork must be capable of shaping and supporting the fluid concrete until it cures. • Strength: formwork must be capable of safely withstanding without distortion or danger the dead weight of the fluid concrete is placed on it, labour weight, equipment weight and any environmental loadings.
  • 10. • Ease of Handling: form panels and units should be designed so that their maximum size does not exceed that which can be easily handled by hand or mechanical means. – In addition all formwork must also be designed and constructed to include facilities for adjustments, levelling, easing and striking without damage to the form work or concrete
  • 11. • Economy: All the formwork is very expensive. On average about 35% of the total cost of any finished concrete unit or element can be attributed to its formwork; of this just over 40% can be taken for material for formwork and 60% for labour. – The formwork designer must therefore not only consider the maximum number of times that any form can be reused, but also produce a design that will minimize the time taken for erection and striking
  • 12. Major objectives considered in formwork: ➢ Quality ➢ Safety ➢ Economy
  • 13. • Quality: Forms must be designed and built with sufficient stiffness and accuracy so that the size, shape, position, and finish of the cast concrete are maintained. so that they have • Safety: Forms must be built sufficient strength and factor of safety the capable of all supporting loads. • Economy: Forms must be built efficiently, minimizing time and cost.
  • 14. Requirements of formwork: • Material should be cheap and re usable, • It should be practically water proof, so that it should not absorb water from concrete, • Swelling and shrinkage should be minimum, • Strong enough to with stand all external loads, • Deflection should be minimum, • Surface should be smooth, and afford easy striping, • Light in weight, so that easy to transfer, • Joints should be stiff, so that lateral deformation and leak is minimum .
  • 15. Three stages in the process : a) Assembly and erection b) Concrete placement. c) Stripping and dismantling.
  • 16. Formwork detail for different structural members • In concrete construction formwork is commonly provided for the following structural members. • Wall • Column • Slabs & Beams • Stairs o Chimneys • Water tanks • Cooling Towers
  • 17. Formwork for Wall It consists of Timber sheeting • Vertical posts • Horizontal members • Rackers • Stakes • Wedges ➢ After completing one side of formwork reinforcement is provided at the place then the second side formwork is provided.
  • 18. Formwork for Column It consists of the following – Side & End Planks – Yoke – Nut & Bolts • Two end & two side planks are joined by the yokes and bolts.
  • 20. Formwork for Slabs & beams It consistsof – Sole plates – Wedges – Props – Head tree – Planks – Batten – Ledgers • Beam formworkrests on headtree • Slab form work restson battens andjoists • If prop height aremore than 8’ provide horizontalbraces.
  • 21. Lintel or Beam Formwork
  • 23. FORMWORK FOR STAIRS It consists of – Vertical & inclined posts – Inclined members -- Wooden Planks or sheeting – Stringer – Riser Planks
  • 26. FORMWORK FOR CHIMNEYS For tall chimneys two types of forms techniques are in generally use in our country a) Jump form b) Slip form
  • 27. Removal of formwork • Time of formwork removal depends on the following factors: Type of Cement Rapid hardening cements require lesser time as compared to OPC (Ordinary Portland Cement) Ratio of concrete mix Rich ratio concrete gain strength earlier as compared to weak ratio concrete. Weather condition Hydration process accelerates in hot weather conditions as compared to cold and humid weather conditions
  • 28. Time of Removal of formwork
  • 29. Comparison between Steel and Timber Formwork • Steel forms are stronger, durable, and have a longer life than timber formwork and their reuses are more in number. • Steel forms can be installed and dismantled with greater ease and speed. • The quality of exposed concrete surface by using steel forms is good and such surfaces need no further treatment. • Steel formwork does not absorb moisture from concrete. • Steel formwork does not shrink or warp.
  • 30. Cantilever slab First free end's support should be removed. • And then from right to left it should be proceed. • If we are removing from the mid span then it will act as a prop cantilever.
  • 31. Simply supported slab In simply supported we have to remove the support from the mid span to the ends. • To meet the design behavior.
  • 32. Maintenance of formwork • Due to continuous use wooden planks & steel plates surfaces become uneven and require maintenance. • For wooden formwork use cardboard or plastic fiber board. Bolt hole places must also be repaired. • For steel formwork plates must be leveled by mallet and loose corners must be welded.
  • 33. Cost of formwork • For normal works cost of formwork is about 30%- 40% of the concrete cost. ➢ For special works cost of formwork is about 50%-60% of the concrete cost. ➢ Formwork cost is controlled by the following factors • Formwork Material cost • Formwork erecting cost • Formwork removal cost • Formwork jointing cost (Nails and Cables) • Labor charges
  • 34. Advantages of steel form work • It can be used for a no. of times. â–Ş It is non absorbent. â–Ş Smooth finish surface obtained. â–Ş No shrinkage of formwork occurs. â–Ş Easy to use. â–Ş Its volume is less â–Ş Its strength is more
  • 35. LOADS ON FORMWORK Dead load â–Ş Self weight of formwork â–Ş Pressure and loads from fresh concrete â–Ş Reinforcement • Imposed load â–Ş Construction workers â–Ş Stacking of materials • Horizontal loads • Environmental loads â–Ş Accidental loads â–Ş Wind loads
  • 36. References • R.C.C Design by B.C.Punmia • R.C.C Design by H.J.Shah • Formwork Design Section 1500 • Doka Formwork Design • Design of safe timber structures by Eva and Tomi Torrati