SlideShare a Scribd company logo
1 of 75
Download to read offline
What Does Wind Really Cost?What Does Wind Really Cost?
Modeling Wind Resources in AURORAModeling Wind Resources in AURORA
presented by
Ray Bliven
Power Rates Manager
Bonneville Power Administration
The views presented in this presentation are those of those of the presenter and
do not necessarily represent the position of BPA on any of these issues.
Last TimeLast Time
Building a Cogeneration ResourceBuilding a Cogeneration Resource
Modeling cogeneration in AURORAModeling cogeneration in AURORA
Combined Cycle Cogeneration
High Pressure Steam to Process
High Pressure Steam
to Turbine
Low Pressure Steam Return
Low Pressure Steam
for NOx Reduction
Low Pressure Steam to Process
Process
Steam
Use
Heat Recovery
Steam Generator
(HRSG)
Gas Turbine
Exhaust Heat
Recovery
DuctBurners
HPBoiler
SCR
Economizer
Preheater
StackAmmonia
for NOx
Reduction
BFW Pump
Pump
Water
Treatment
Water
Source
MakeupWater
Deaerator
Transformer
Generator
Transformer
Generator
Natural
Gas
Supply
Compressor
Outside
Air
Cumbustors
Cumbustion
Turbine
Gas Turbine Generator
High Pressure Steam
to Turbine
Low Pressure Steam
for NOx Reduction
Water Vapor
Pump
Steam
Condensate
Condensator
Cool
Water
Cooling Tower
Warm Water
Steam
Turbine
Last TimeLast Time
Building a Cogeneration ResourceBuilding a Cogeneration Resource
Modeling cogeneration in AURORAModeling cogeneration in AURORA
This time:This time:
Building a Wind ResourceBuilding a Wind Resource
Modeling wind generation in AURORAModeling wind generation in AURORA
Examining issues related to wind generationExamining issues related to wind generation
Turbine Parts Arrive by ShipTurbine Parts Arrive by Ship
Site Preparation BeginsSite Preparation Begins
Foundation Bolts InstalledFoundation Bolts Installed
Foundation PouredFoundation Poured
Foundation FinishedFoundation Finished
Tower Section Trucked to SiteTower Section Trucked to Site
Nacelle Trucked to SiteNacelle Trucked to Site
Rotor Blade Trucked to SiteRotor Blade Trucked to Site
Parts Arrive at SiteParts Arrive at Site
Tower InstalledTower Installed
Rotor Hub Attached to NacelleRotor Hub Attached to Nacelle
Nacelle InstalledNacelle Installed
Rotor Blade InstalledRotor Blade Installed
Completed TurbineCompleted Turbine
Electrical Connection ProceedsElectrical Connection Proceeds
Project CompleteProject Complete
83 turbines at 1.8 MW each = 150 MW
Located on 165 acres in Eastern Washington
Produces 50 average megawatts
Site prep began March 2005
First turbine construction began August 2005
Project complete December 2005
Phases in Building a Wind ResourcePhases in Building a Wind Resource
Find a SiteFind a Site
Build the MachineBuild the Machine
Integrate onto the GridIntegrate onto the Grid
Find a SiteFind a Site
Location, Location, LocationLocation, Location, Location
Site StudiesSite Studies ---- Wind Speed DataWind Speed Data
Permits and LeasesPermits and Leases
Windy Sites are Best, ButWindy Sites are Best, But ……
Ridgelines are Usually GoodRidgelines are Usually Good
Consistently Windy Areas Work GreatConsistently Windy Areas Work Great
Wind AtlasWind Atlas –– Winter PotentialWinter Potential
Wind AtlasWind Atlas –– Spring PotentialSpring Potential
Wind AtlasWind Atlas –– Summer PotentialSummer Potential
Wind AtlasWind Atlas –– Autumn PotentialAutumn Potential
Build the MachineBuild the Machine
Decide Which Machine and How BigDecide Which Machine and How Big
–– old technologyold technology –– 600 to 660 kW600 to 660 kW
–– new technologynew technology –– 2 to 3 MW2 to 3 MW
–– developing technologydeveloping technology –– 5 MW5 MW
Get In LineGet In Line
–– everyone seems to want wind generatorseveryone seems to want wind generators
–– current order backlogscurrent order backlogs
–– secondary markets developingsecondary markets developing
Costs of a Wind GeneratorCosts of a Wind Generator
Site and Site PreparationSite and Site Preparation
HardwareHardware
Integration and TransmissionIntegration and Transmission
Current estimatesCurrent estimates
–– EIAEIA –– 1,200 per kW1,200 per kW
–– NPCCNPCC –– 1,175 per kW1,175 per kW
Environmental ConsiderationsEnvironmental Considerations
BirdsBirds
VisualVisual
NoiseNoise
Emissions??Emissions??
Wind Generation in the WestWind Generation in the West
19901990 –– 1,650 MW in California1,650 MW in California
19991999 –– 1,975 MW in California + 117 MW1,975 MW in California + 117 MW
20022002 –– 3,000 MW3,000 MW
20042004 –– 4,000 MW4,000 MW
20062006 –– 5,000 MW5,000 MW
20072007 –– 8,000 MW ??8,000 MW ??
20112011 –– 14,000 MW !!!???14,000 MW !!!???
Modeling Wind Generation in AURORAModeling Wind Generation in AURORA
Obtain hourly generation or wind speedsObtain hourly generation or wind speeds
–– Wind speeds for Washington & OregonWind speeds for Washington & Oregon
–– wwwwww--k12.atmos.washington.edu/k12/grayskies/nw_weather.htmlk12.atmos.washington.edu/k12/grayskies/nw_weather.html
Adjust for tower heightAdjust for tower height
–– Speed increases by a factor of 1/7th with heightSpeed increases by a factor of 1/7th with height
Apply power curveApply power curve
–– Power increases by a cube function with wind speedPower increases by a cube function with wind speed
Normalize to average outputNormalize to average output
–– Wind speed readings arenWind speed readings aren’’t always at the wind sitet always at the wind site
Tower Height AdjustmentTower Height Adjustment
www.rpc.com.au/products/windturbines/wind_faq.htmlwww.rpc.com.au/products/windturbines/wind_faq.html
Power CurvePower Curve
www.windpower.org/en/tour/wres/pwr.htmwww.windpower.org/en/tour/wres/pwr.htm
Modeling Wind Generation in AURORAModeling Wind Generation in AURORA
Choose a representative week for each monthChoose a representative week for each month
Convert each hourConvert each hour’’s generation into a forceds generation into a forced
outage factor for each of the 168 hours of weekoutage factor for each of the 168 hours of week
Result is 168 hours for 12 months per siteResult is 168 hours for 12 months per site
Use monthly time series vector to refer toUse monthly time series vector to refer to
appropriate weekly time series vectorappropriate weekly time series vector
For each wind resource, point to the monthly timeFor each wind resource, point to the monthly time
series with that resourceseries with that resource’’s forced outage values forced outage value
ExamplesExamples
Wind speed =Wind speed = mphmph 11 55 1010 1515 2020
Height adjust =Height adjust = mphmph 22 77 1515 2222 3030
Power curve =Power curve = kWkW 00 1010 8080 270270 640640
Forced outage =Forced outage = %% 100100 9999 9292 7373 3636
Wind speed =Wind speed = mphmph 2525 3030 3535 4040
Height adjust =Height adjust = mphmph 3737 4545 5252 6060
Power curve =Power curve = kWkW 10001000 10001000 10001000 00
Forced outage =Forced outage = %% 00 00 00 100100
AURORA setupAURORA setup –– Weekly VectorsWeekly Vectors
AURORA setupAURORA setup –– Monthly VectorsMonthly Vectors
AURORA setupAURORA setup –– ResourcesResources
AURORA setupAURORA setup –– FuelFuel
set to zero
AURORA setupAURORA setup –– AnnualAnnual
actual VOM minus Production Tax Credit
Results of Wind ShapingResults of Wind Shaping
Shaped WindShaped Wind v.v. Flat WindFlat Wind OutputOutput
January 2007 – Existing Wind Resources – 5,500 MW capacity
Results of Wind ShapingResults of Wind Shaping
Shaped WindShaped Wind v.v. Flat WindFlat Wind OutputOutput
Year 2007 – Existing Wind Resources – 5,500 MW capacity
Results of Wind ShapingResults of Wind Shaping
Shaped WindShaped Wind v.v. Flat WindFlat Wind OutputOutput
January 2007 – Future Wind Resources – 14,000 MW capacity
Results of Wind ShapingResults of Wind Shaping
Shaped WindShaped Wind v.v. Flat WindFlat Wind OutputOutput
Year 2007 – Future Wind Resources – 14,000 MW capacity
Results of Wind ShapingResults of Wind Shaping
Shaped WindShaped Wind v.v. Flat WindFlat Wind PricesPrices
Avg = 78.89; Stdev = 10.2 Avg = 78.18; Stdev = 9.4
January 2007 – Existing Wind Resources – Mid-C Prices
Results of Wind ShapingResults of Wind Shaping
Shaped WindShaped Wind v.v. Flat WindFlat Wind PricesPrices
Avg = 73.30; Stdev = 9.5Avg = 70.36; Stdev = 16.7
January 2007 – Future Wind Resources – Mid-C Prices
Results of Wind ShapingResults of Wind Shaping
Shaped WindShaped Wind v.v. Flat WindFlat Wind PricesPrices
Avg = 80.04; Stdev = 17.4 Avg = 80.04; Stdev = 17.1
Year 2007 – Existing Wind Resources – Mid-C Prices
Results of Wind ShapingResults of Wind Shaping
Shaped WindShaped Wind v.v. Flat WindFlat Wind PricesPrices
Avg = 75.96; Stdev = 17.1Avg = 75.33; Stdev = 18.5
Year 2007 – Future Wind Resources – Mid-C Prices
Geographic ConcentrationGeographic Concentration
Wind generation in Washington and OregonWind generation in Washington and Oregon
may grow to about 4,500 MW within fivemay grow to about 4,500 MW within five
yearsyears
Almost 3,000 MW is targeted to the easternAlmost 3,000 MW is targeted to the eastern
Columbia River gorge and another 1,000Columbia River gorge and another 1,000
MW 50 miles east of the gorgeMW 50 miles east of the gorge
How will this concentration affect the systemHow will this concentration affect the system
operations and market clearing pricesoperations and market clearing prices
Expected Geographic ConcentrationExpected Geographic Concentration
about 200 MW each
Test Geographic DispersionTest Geographic Dispersion
about 200 MW each
Results of Wind DispersionResults of Wind Dispersion
Concentrated WindConcentrated Wind v.v. Dispersed WindDispersed Wind ProductionProduction
January 2007 – Washington/Oregon Wind Resources
Results of Wind DispersionResults of Wind Dispersion
Concentrated WindConcentrated Wind v.v. Dispersed WindDispersed Wind ProductionProduction
January 2007 – Washington/Oregon Wind Resources
Results of Wind DispersionResults of Wind Dispersion
Concentrated WindConcentrated Wind v.v. Dispersed WindDispersed Wind ProductionProduction
Year 2007 – Washington/Oregon Wind Resources
Results of Wind DispersionResults of Wind Dispersion
Concentrated WindConcentrated Wind v.v. Dispersed WindDispersed Wind ProductionProduction
Year 2007 – Washington/Oregon Wind Resources
How Does Wind Produce Emissions?How Does Wind Produce Emissions?
The Overlooked Environmental Cost of a WindThe Overlooked Environmental Cost of a Wind
Generation Portfolio to Serve the Need for PowerGeneration Portfolio to Serve the Need for Power
–– draft paper by Lincolndraft paper by Lincoln WolvertonWolverton (attached)(attached)
Premise of the paperPremise of the paper
–– In a closed system, wind generation may not change theIn a closed system, wind generation may not change the
amount of fossil fuel burnedamount of fossil fuel burned
–– In an open system, the addition of wind generation willIn an open system, the addition of wind generation will
change the system operations from base load plants tochange the system operations from base load plants to
cycling plantscycling plants
Testing the Premise with AURORATesting the Premise with AURORA
First, test the closed system premiseFirst, test the closed system premise
–– Use AURORAUse AURORA’’s closed system dispatch features closed system dispatch feature
to examine two portfoliosto examine two portfolios
One portfolio has a 100 MW wind generator and aOne portfolio has a 100 MW wind generator and a
100 MW single cycle combustion turbine100 MW single cycle combustion turbine
–– Heat rate = 9500Heat rate = 9500
Other portfolio has a 100 MW combined cycleOther portfolio has a 100 MW combined cycle
combustion turbinecombustion turbine
–– Heat rate = 7300Heat rate = 7300
Testing the Premise with AURORATesting the Premise with AURORA
Results:Results:
–– Fossil fuel usage increases from wind case toFossil fuel usage increases from wind case to
CCCT case by 6.6%CCCT case by 6.6%
–– GHG production increases by 8.8%GHG production increases by 8.8%
–– NONOxx production decreases by 73%production decreases by 73%
–– SOSO22 production decreases by 33%production decreases by 33%
Testing the Premise with AURORATesting the Premise with AURORA
Next, test the open system premiseNext, test the open system premise
–– Examine two casesExamine two cases
First, compare the future system with windFirst, compare the future system with wind
generation presentgeneration present
Second, replace the future system wind with anSecond, replace the future system wind with an
equivalent amount of energy production fromequivalent amount of energy production from
combined cycle combustion turbinescombined cycle combustion turbines
14,000 MW of wind producing 4,13514,000 MW of wind producing 4,135 aMWaMW ofof
energy replaced with combustion turbines inenergy replaced with combustion turbines in
each area with wind plantseach area with wind plants
Testing the Premise with AURORATesting the Premise with AURORA
Results:Results:
–– Fossil fuel usage increases from wind case to CCCTFossil fuel usage increases from wind case to CCCT
case by 5.7% across all of WECCcase by 5.7% across all of WECC
–– GHG production increases by 4.0%GHG production increases by 4.0%
18.7% increase in CCCT GHG offset by18.7% increase in CCCT GHG offset by peakerpeaker reductionsreductions
–– NONOxx production increases by 0.8%production increases by 0.8%
18.2% increase in CCCT NO18.2% increase in CCCT NOxx offset byoffset by peakerpeaker reductionsreductions
–– SOSO22 production increases by 0.1%production increases by 0.1%
19.5% increase in CCCT SO19.5% increase in CCCT SO22 offset byoffset by peakerpeaker reductionsreductions
Testing the Premise with AURORATesting the Premise with AURORA
Conclusions:Conclusions:
–– Wind generation in the WECC is now of suchWind generation in the WECC is now of such
size that hourly modeling is an important factorsize that hourly modeling is an important factor
in predicting market clearing pricesin predicting market clearing prices
–– Geographic concentration of wind generation isGeographic concentration of wind generation is
more expensive tomore expensive to MCPsMCPs than diverse locationsthan diverse locations
–– Emissions savings from wind generation areEmissions savings from wind generation are
minimized if SCCT operation increases tominimized if SCCT operation increases to
regulate wind output to meet loadregulate wind output to meet load

More Related Content

What's hot

Re-Energizing Our Cities: From District to Specific - Integral Group
Re-Energizing Our Cities:  From District to Specific - Integral GroupRe-Energizing Our Cities:  From District to Specific - Integral Group
Re-Energizing Our Cities: From District to Specific - Integral GroupToronto 2030 District
 
Energy resolution of several scintillating crystals using different readout ...
 Energy resolution of several scintillating crystals using different readout ... Energy resolution of several scintillating crystals using different readout ...
Energy resolution of several scintillating crystals using different readout ...Martin Gascon
 
ARX models for Building Energy Performance Assessment Based on In-situ Measur...
ARX models for Building Energy Performance Assessment Based on In-situ Measur...ARX models for Building Energy Performance Assessment Based on In-situ Measur...
ARX models for Building Energy Performance Assessment Based on In-situ Measur...Christoffer Rasmussen
 
CCS cost estimation methods in the coal, oil and gas sectors - David Butler, ...
CCS cost estimation methods in the coal, oil and gas sectors - David Butler, ...CCS cost estimation methods in the coal, oil and gas sectors - David Butler, ...
CCS cost estimation methods in the coal, oil and gas sectors - David Butler, ...Global CCS Institute
 
Bicycle sharing demand analysis using R
Bicycle sharing demand analysis using RBicycle sharing demand analysis using R
Bicycle sharing demand analysis using REvelyn Zoubi
 
Consumption and demand comparisons of HVAC systems
Consumption and demand comparisons of HVAC systemsConsumption and demand comparisons of HVAC systems
Consumption and demand comparisons of HVAC systemsGaren Ewbank
 
EDEN - Acumentrics Comparison Chart
EDEN - Acumentrics Comparison ChartEDEN - Acumentrics Comparison Chart
EDEN - Acumentrics Comparison Charth2portugal
 
Haitao Hu - NORWEGIAN UNIVERSITY OF SCIENCE AND TECHNOLOGY - POMPE DI CALORE ...
Haitao Hu - NORWEGIAN UNIVERSITY OF SCIENCE AND TECHNOLOGY - POMPE DI CALORE ...Haitao Hu - NORWEGIAN UNIVERSITY OF SCIENCE AND TECHNOLOGY - POMPE DI CALORE ...
Haitao Hu - NORWEGIAN UNIVERSITY OF SCIENCE AND TECHNOLOGY - POMPE DI CALORE ...Centro Studi Galileo
 
Gas turbine advisors review of a 9 e.03 ccgt power plant
Gas turbine advisors review of a 9 e.03 ccgt power plant Gas turbine advisors review of a 9 e.03 ccgt power plant
Gas turbine advisors review of a 9 e.03 ccgt power plant Gasturbineconsultants
 

What's hot (12)

Re-Energizing Our Cities: From District to Specific - Integral Group
Re-Energizing Our Cities:  From District to Specific - Integral GroupRe-Energizing Our Cities:  From District to Specific - Integral Group
Re-Energizing Our Cities: From District to Specific - Integral Group
 
Energy resolution of several scintillating crystals using different readout ...
 Energy resolution of several scintillating crystals using different readout ... Energy resolution of several scintillating crystals using different readout ...
Energy resolution of several scintillating crystals using different readout ...
 
ARX models for Building Energy Performance Assessment Based on In-situ Measur...
ARX models for Building Energy Performance Assessment Based on In-situ Measur...ARX models for Building Energy Performance Assessment Based on In-situ Measur...
ARX models for Building Energy Performance Assessment Based on In-situ Measur...
 
CCS cost estimation methods in the coal, oil and gas sectors - David Butler, ...
CCS cost estimation methods in the coal, oil and gas sectors - David Butler, ...CCS cost estimation methods in the coal, oil and gas sectors - David Butler, ...
CCS cost estimation methods in the coal, oil and gas sectors - David Butler, ...
 
Bicycle sharing demand analysis using R
Bicycle sharing demand analysis using RBicycle sharing demand analysis using R
Bicycle sharing demand analysis using R
 
Consumption and demand comparisons of HVAC systems
Consumption and demand comparisons of HVAC systemsConsumption and demand comparisons of HVAC systems
Consumption and demand comparisons of HVAC systems
 
EDEN - Acumentrics Comparison Chart
EDEN - Acumentrics Comparison ChartEDEN - Acumentrics Comparison Chart
EDEN - Acumentrics Comparison Chart
 
Haitao Hu - NORWEGIAN UNIVERSITY OF SCIENCE AND TECHNOLOGY - POMPE DI CALORE ...
Haitao Hu - NORWEGIAN UNIVERSITY OF SCIENCE AND TECHNOLOGY - POMPE DI CALORE ...Haitao Hu - NORWEGIAN UNIVERSITY OF SCIENCE AND TECHNOLOGY - POMPE DI CALORE ...
Haitao Hu - NORWEGIAN UNIVERSITY OF SCIENCE AND TECHNOLOGY - POMPE DI CALORE ...
 
Gas turbine advisors review of a 9 e.03 ccgt power plant
Gas turbine advisors review of a 9 e.03 ccgt power plant Gas turbine advisors review of a 9 e.03 ccgt power plant
Gas turbine advisors review of a 9 e.03 ccgt power plant
 
Coal to electricity
Coal to electricityCoal to electricity
Coal to electricity
 
ERU CEP.pptx
ERU CEP.pptxERU CEP.pptx
ERU CEP.pptx
 
IMEC Poster
IMEC PosterIMEC Poster
IMEC Poster
 

Viewers also liked

Marley Island
Marley IslandMarley Island
Marley Islandmmartin2
 
Rock Island Cesar
Rock Island CesarRock Island Cesar
Rock Island CesarMS.SANCHA
 
2 q14 slides final
2 q14 slides final2 q14 slides final
2 q14 slides finalDupontInv
 
Work Samples
Work SamplesWork Samples
Work Samplesjcrew_ku
 
Proyecto de etica 02
Proyecto de etica 02Proyecto de etica 02
Proyecto de etica 02Said Sosa
 
Que dice la biblia acerca de las cuatro lunas de sangre
Que dice la biblia acerca de las cuatro lunas de sangreQue dice la biblia acerca de las cuatro lunas de sangre
Que dice la biblia acerca de las cuatro lunas de sangreJosias Espinoza
 
Seguridad industrial harold
Seguridad industrial haroldSeguridad industrial harold
Seguridad industrial haroldHarold Aranguren
 
Walking Festival Kingston upon Thames 2016 Programme
Walking Festival Kingston upon Thames 2016 ProgrammeWalking Festival Kingston upon Thames 2016 Programme
Walking Festival Kingston upon Thames 2016 ProgrammeKingstonVA
 
パブリッククラウドにおけるL2TPv3を用いたサーバ高可用性の評価
パブリッククラウドにおけるL2TPv3を用いたサーバ高可用性の評価パブリッククラウドにおけるL2TPv3を用いたサーバ高可用性の評価
パブリッククラウドにおけるL2TPv3を用いたサーバ高可用性の評価Naoto MATSUMOTO
 
summary - explaining reward inequality
summary - explaining reward inequalitysummary - explaining reward inequality
summary - explaining reward inequalityut san antonio
 
Day-Ahead LMP Forecasting with AURORAxmp
Day-Ahead LMP Forecasting with AURORAxmpDay-Ahead LMP Forecasting with AURORAxmp
Day-Ahead LMP Forecasting with AURORAxmpEPIS Inc
 
DuPont India Innovation Center: Inclusive Innovation in Action
DuPont India Innovation Center: Inclusive Innovation in ActionDuPont India Innovation Center: Inclusive Innovation in Action
DuPont India Innovation Center: Inclusive Innovation in ActionDuPont
 
Nodal Insights for Generation Owners and Modeling with AURORAxmp
Nodal Insights for Generation Owners and Modeling with AURORAxmpNodal Insights for Generation Owners and Modeling with AURORAxmp
Nodal Insights for Generation Owners and Modeling with AURORAxmpEPIS Inc
 
カンファレンスネットワークの作り方
カンファレンスネットワークの作り方カンファレンスネットワークの作り方
カンファレンスネットワークの作り方KOIWA hidekazu
 

Viewers also liked (15)

Marley Island
Marley IslandMarley Island
Marley Island
 
Rock Island Cesar
Rock Island CesarRock Island Cesar
Rock Island Cesar
 
2 q14 slides final
2 q14 slides final2 q14 slides final
2 q14 slides final
 
Work Samples
Work SamplesWork Samples
Work Samples
 
Design Trends
Design TrendsDesign Trends
Design Trends
 
Proyecto de etica 02
Proyecto de etica 02Proyecto de etica 02
Proyecto de etica 02
 
Que dice la biblia acerca de las cuatro lunas de sangre
Que dice la biblia acerca de las cuatro lunas de sangreQue dice la biblia acerca de las cuatro lunas de sangre
Que dice la biblia acerca de las cuatro lunas de sangre
 
Seguridad industrial harold
Seguridad industrial haroldSeguridad industrial harold
Seguridad industrial harold
 
Walking Festival Kingston upon Thames 2016 Programme
Walking Festival Kingston upon Thames 2016 ProgrammeWalking Festival Kingston upon Thames 2016 Programme
Walking Festival Kingston upon Thames 2016 Programme
 
パブリッククラウドにおけるL2TPv3を用いたサーバ高可用性の評価
パブリッククラウドにおけるL2TPv3を用いたサーバ高可用性の評価パブリッククラウドにおけるL2TPv3を用いたサーバ高可用性の評価
パブリッククラウドにおけるL2TPv3を用いたサーバ高可用性の評価
 
summary - explaining reward inequality
summary - explaining reward inequalitysummary - explaining reward inequality
summary - explaining reward inequality
 
Day-Ahead LMP Forecasting with AURORAxmp
Day-Ahead LMP Forecasting with AURORAxmpDay-Ahead LMP Forecasting with AURORAxmp
Day-Ahead LMP Forecasting with AURORAxmp
 
DuPont India Innovation Center: Inclusive Innovation in Action
DuPont India Innovation Center: Inclusive Innovation in ActionDuPont India Innovation Center: Inclusive Innovation in Action
DuPont India Innovation Center: Inclusive Innovation in Action
 
Nodal Insights for Generation Owners and Modeling with AURORAxmp
Nodal Insights for Generation Owners and Modeling with AURORAxmpNodal Insights for Generation Owners and Modeling with AURORAxmp
Nodal Insights for Generation Owners and Modeling with AURORAxmp
 
カンファレンスネットワークの作り方
カンファレンスネットワークの作り方カンファレンスネットワークの作り方
カンファレンスネットワークの作り方
 

Similar to What does wind really cost? Modeling Wind Resources In AURORAxmp.

Appendix A3_Presentation of Energy Performance
Appendix A3_Presentation of Energy PerformanceAppendix A3_Presentation of Energy Performance
Appendix A3_Presentation of Energy PerformanceRichard D. Ochotorena
 
Wind Resource Assessment
Wind Resource AssessmentWind Resource Assessment
Wind Resource Assessmentmtingle
 
Appendix A5_Summary of Analysis for Okhta Tower Facade Energy Performance
Appendix A5_Summary of Analysis for Okhta Tower Facade Energy PerformanceAppendix A5_Summary of Analysis for Okhta Tower Facade Energy Performance
Appendix A5_Summary of Analysis for Okhta Tower Facade Energy PerformanceRichard D. Ochotorena
 
Value engineered wind turbine
Value engineered wind turbineValue engineered wind turbine
Value engineered wind turbineKim Christensen
 
Design Construction, Simulation and Testing of A 300W Wind-Powered Battery Ch...
Design Construction, Simulation and Testing of A 300W Wind-Powered Battery Ch...Design Construction, Simulation and Testing of A 300W Wind-Powered Battery Ch...
Design Construction, Simulation and Testing of A 300W Wind-Powered Battery Ch...theijes
 
IRJET- Power Generation with the Application of Vortex Wind Turbine
IRJET- Power Generation with the Application of Vortex Wind TurbineIRJET- Power Generation with the Application of Vortex Wind Turbine
IRJET- Power Generation with the Application of Vortex Wind TurbineIRJET Journal
 
Power Generation through the Wind Energy Using Convergent Nozzle
Power Generation through the Wind Energy Using Convergent NozzlePower Generation through the Wind Energy Using Convergent Nozzle
Power Generation through the Wind Energy Using Convergent Nozzletheijes
 
Comparative Analysis of Mechanical Efficiency of Domestic Hawt without Nos...
Comparative  Analysis  of Mechanical  Efficiency of Domestic Hawt without Nos...Comparative  Analysis  of Mechanical  Efficiency of Domestic Hawt without Nos...
Comparative Analysis of Mechanical Efficiency of Domestic Hawt without Nos...IRJET Journal
 
IRJET- A Revieiw of Wind Energy Potential in Kano State, Nigeria for the ...
IRJET-  	  A Revieiw of Wind Energy Potential in Kano State, Nigeria for the ...IRJET-  	  A Revieiw of Wind Energy Potential in Kano State, Nigeria for the ...
IRJET- A Revieiw of Wind Energy Potential in Kano State, Nigeria for the ...IRJET Journal
 
IRJET- Manufacturing System of Hybrid Vertical Axis Wind Turbine
IRJET- Manufacturing System of Hybrid Vertical Axis Wind TurbineIRJET- Manufacturing System of Hybrid Vertical Axis Wind Turbine
IRJET- Manufacturing System of Hybrid Vertical Axis Wind TurbineIRJET Journal
 
Study About Wind turbines
Study About Wind turbinesStudy About Wind turbines
Study About Wind turbinesElia Tohmé
 
Presentation (group)
Presentation (group)Presentation (group)
Presentation (group)Ankit Grover
 
Nwtc turb sim workshop september 22 24, 2008- boundary layer dynamics and wi...
Nwtc turb sim workshop september 22 24, 2008-  boundary layer dynamics and wi...Nwtc turb sim workshop september 22 24, 2008-  boundary layer dynamics and wi...
Nwtc turb sim workshop september 22 24, 2008- boundary layer dynamics and wi...ndkelley
 
Power conversion system design for tidal stream generator by Oceanflow
Power conversion system design for tidal stream generator by OceanflowPower conversion system design for tidal stream generator by Oceanflow
Power conversion system design for tidal stream generator by OceanflowOptima Control Solutions
 
Wind energy applications, ams short course, august 1, 2010, keystone, co
Wind energy applications, ams short course, august 1, 2010, keystone, coWind energy applications, ams short course, august 1, 2010, keystone, co
Wind energy applications, ams short course, august 1, 2010, keystone, condkelley
 
How Idaho Power Company uses AURORAxmp
How Idaho Power Company uses AURORAxmpHow Idaho Power Company uses AURORAxmp
How Idaho Power Company uses AURORAxmpEPIS Inc
 
Siting and Planning Design of Wind Turbines
Siting and Planning Design of Wind TurbinesSiting and Planning Design of Wind Turbines
Siting and Planning Design of Wind TurbinesHimanshu Paghdal
 
Excipio Energy offshore renewables 2016
Excipio Energy offshore renewables 2016Excipio Energy offshore renewables 2016
Excipio Energy offshore renewables 2016Roy Robinson
 

Similar to What does wind really cost? Modeling Wind Resources In AURORAxmp. (20)

Appendix A3_Presentation of Energy Performance
Appendix A3_Presentation of Energy PerformanceAppendix A3_Presentation of Energy Performance
Appendix A3_Presentation of Energy Performance
 
Wind Resource Assessment
Wind Resource AssessmentWind Resource Assessment
Wind Resource Assessment
 
Appendix A5_Summary of Analysis for Okhta Tower Facade Energy Performance
Appendix A5_Summary of Analysis for Okhta Tower Facade Energy PerformanceAppendix A5_Summary of Analysis for Okhta Tower Facade Energy Performance
Appendix A5_Summary of Analysis for Okhta Tower Facade Energy Performance
 
Value engineered wind turbine
Value engineered wind turbineValue engineered wind turbine
Value engineered wind turbine
 
Presentation-for-teachers.pptx
Presentation-for-teachers.pptxPresentation-for-teachers.pptx
Presentation-for-teachers.pptx
 
Design Construction, Simulation and Testing of A 300W Wind-Powered Battery Ch...
Design Construction, Simulation and Testing of A 300W Wind-Powered Battery Ch...Design Construction, Simulation and Testing of A 300W Wind-Powered Battery Ch...
Design Construction, Simulation and Testing of A 300W Wind-Powered Battery Ch...
 
IRJET- Power Generation with the Application of Vortex Wind Turbine
IRJET- Power Generation with the Application of Vortex Wind TurbineIRJET- Power Generation with the Application of Vortex Wind Turbine
IRJET- Power Generation with the Application of Vortex Wind Turbine
 
Power Generation through the Wind Energy Using Convergent Nozzle
Power Generation through the Wind Energy Using Convergent NozzlePower Generation through the Wind Energy Using Convergent Nozzle
Power Generation through the Wind Energy Using Convergent Nozzle
 
Comparative Analysis of Mechanical Efficiency of Domestic Hawt without Nos...
Comparative  Analysis  of Mechanical  Efficiency of Domestic Hawt without Nos...Comparative  Analysis  of Mechanical  Efficiency of Domestic Hawt without Nos...
Comparative Analysis of Mechanical Efficiency of Domestic Hawt without Nos...
 
IRJET- A Revieiw of Wind Energy Potential in Kano State, Nigeria for the ...
IRJET-  	  A Revieiw of Wind Energy Potential in Kano State, Nigeria for the ...IRJET-  	  A Revieiw of Wind Energy Potential in Kano State, Nigeria for the ...
IRJET- A Revieiw of Wind Energy Potential in Kano State, Nigeria for the ...
 
IRJET- Manufacturing System of Hybrid Vertical Axis Wind Turbine
IRJET- Manufacturing System of Hybrid Vertical Axis Wind TurbineIRJET- Manufacturing System of Hybrid Vertical Axis Wind Turbine
IRJET- Manufacturing System of Hybrid Vertical Axis Wind Turbine
 
Study About Wind turbines
Study About Wind turbinesStudy About Wind turbines
Study About Wind turbines
 
Presentation (group)
Presentation (group)Presentation (group)
Presentation (group)
 
Nwtc turb sim workshop september 22 24, 2008- boundary layer dynamics and wi...
Nwtc turb sim workshop september 22 24, 2008-  boundary layer dynamics and wi...Nwtc turb sim workshop september 22 24, 2008-  boundary layer dynamics and wi...
Nwtc turb sim workshop september 22 24, 2008- boundary layer dynamics and wi...
 
Innovations :Technology unfolding
Innovations :Technology unfolding Innovations :Technology unfolding
Innovations :Technology unfolding
 
Power conversion system design for tidal stream generator by Oceanflow
Power conversion system design for tidal stream generator by OceanflowPower conversion system design for tidal stream generator by Oceanflow
Power conversion system design for tidal stream generator by Oceanflow
 
Wind energy applications, ams short course, august 1, 2010, keystone, co
Wind energy applications, ams short course, august 1, 2010, keystone, coWind energy applications, ams short course, august 1, 2010, keystone, co
Wind energy applications, ams short course, august 1, 2010, keystone, co
 
How Idaho Power Company uses AURORAxmp
How Idaho Power Company uses AURORAxmpHow Idaho Power Company uses AURORAxmp
How Idaho Power Company uses AURORAxmp
 
Siting and Planning Design of Wind Turbines
Siting and Planning Design of Wind TurbinesSiting and Planning Design of Wind Turbines
Siting and Planning Design of Wind Turbines
 
Excipio Energy offshore renewables 2016
Excipio Energy offshore renewables 2016Excipio Energy offshore renewables 2016
Excipio Energy offshore renewables 2016
 

More from EPIS Inc

Final Seasonal Assessment of Resource Adequacy for the ERCOT Region, Summer 2...
Final Seasonal Assessment of Resource Adequacy for the ERCOT Region, Summer 2...Final Seasonal Assessment of Resource Adequacy for the ERCOT Region, Summer 2...
Final Seasonal Assessment of Resource Adequacy for the ERCOT Region, Summer 2...EPIS Inc
 
Preliminary Seasonal Assessment of Resource Adequacy for the ERCOT Region, Su...
Preliminary Seasonal Assessment of Resource Adequacy for the ERCOT Region, Su...Preliminary Seasonal Assessment of Resource Adequacy for the ERCOT Region, Su...
Preliminary Seasonal Assessment of Resource Adequacy for the ERCOT Region, Su...EPIS Inc
 
2015 Long-Term Reliability Assessment by NERC
2015 Long-Term Reliability Assessment by NERC2015 Long-Term Reliability Assessment by NERC
2015 Long-Term Reliability Assessment by NERCEPIS Inc
 
2015 Summer Reliability Assessment by NERC
2015 Summer Reliability Assessment by NERC2015 Summer Reliability Assessment by NERC
2015 Summer Reliability Assessment by NERCEPIS Inc
 
Using Historical Data To Fine-Tune AURORAxmp Predictive Capabilities
Using Historical Data To Fine-Tune  AURORAxmp Predictive CapabilitiesUsing Historical Data To Fine-Tune  AURORAxmp Predictive Capabilities
Using Historical Data To Fine-Tune AURORAxmp Predictive CapabilitiesEPIS Inc
 
Southern Company History and Usage of AURORAxmp
Southern Company History and Usage of AURORAxmpSouthern Company History and Usage of AURORAxmp
Southern Company History and Usage of AURORAxmpEPIS Inc
 
Modeling and Valuing Cogeneration with AURORAxmp
Modeling and Valuing Cogeneration with AURORAxmpModeling and Valuing Cogeneration with AURORAxmp
Modeling and Valuing Cogeneration with AURORAxmpEPIS Inc
 

More from EPIS Inc (7)

Final Seasonal Assessment of Resource Adequacy for the ERCOT Region, Summer 2...
Final Seasonal Assessment of Resource Adequacy for the ERCOT Region, Summer 2...Final Seasonal Assessment of Resource Adequacy for the ERCOT Region, Summer 2...
Final Seasonal Assessment of Resource Adequacy for the ERCOT Region, Summer 2...
 
Preliminary Seasonal Assessment of Resource Adequacy for the ERCOT Region, Su...
Preliminary Seasonal Assessment of Resource Adequacy for the ERCOT Region, Su...Preliminary Seasonal Assessment of Resource Adequacy for the ERCOT Region, Su...
Preliminary Seasonal Assessment of Resource Adequacy for the ERCOT Region, Su...
 
2015 Long-Term Reliability Assessment by NERC
2015 Long-Term Reliability Assessment by NERC2015 Long-Term Reliability Assessment by NERC
2015 Long-Term Reliability Assessment by NERC
 
2015 Summer Reliability Assessment by NERC
2015 Summer Reliability Assessment by NERC2015 Summer Reliability Assessment by NERC
2015 Summer Reliability Assessment by NERC
 
Using Historical Data To Fine-Tune AURORAxmp Predictive Capabilities
Using Historical Data To Fine-Tune  AURORAxmp Predictive CapabilitiesUsing Historical Data To Fine-Tune  AURORAxmp Predictive Capabilities
Using Historical Data To Fine-Tune AURORAxmp Predictive Capabilities
 
Southern Company History and Usage of AURORAxmp
Southern Company History and Usage of AURORAxmpSouthern Company History and Usage of AURORAxmp
Southern Company History and Usage of AURORAxmp
 
Modeling and Valuing Cogeneration with AURORAxmp
Modeling and Valuing Cogeneration with AURORAxmpModeling and Valuing Cogeneration with AURORAxmp
Modeling and Valuing Cogeneration with AURORAxmp
 

Recently uploaded

Pigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping ElbowsPigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping ElbowsPigging Solutions
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitecturePixlogix Infotech
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxKatpro Technologies
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 3652toLead Limited
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...HostedbyConfluent
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Alan Dix
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersThousandEyes
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksSoftradix Technologies
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 

Recently uploaded (20)

Pigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping ElbowsPigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping Elbows
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC Architecture
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food Manufacturing
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other Frameworks
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 

What does wind really cost? Modeling Wind Resources In AURORAxmp.

  • 1. What Does Wind Really Cost?What Does Wind Really Cost? Modeling Wind Resources in AURORAModeling Wind Resources in AURORA presented by Ray Bliven Power Rates Manager Bonneville Power Administration The views presented in this presentation are those of those of the presenter and do not necessarily represent the position of BPA on any of these issues.
  • 2. Last TimeLast Time Building a Cogeneration ResourceBuilding a Cogeneration Resource Modeling cogeneration in AURORAModeling cogeneration in AURORA
  • 3. Combined Cycle Cogeneration High Pressure Steam to Process High Pressure Steam to Turbine Low Pressure Steam Return Low Pressure Steam for NOx Reduction Low Pressure Steam to Process Process Steam Use Heat Recovery Steam Generator (HRSG) Gas Turbine Exhaust Heat Recovery DuctBurners HPBoiler SCR Economizer Preheater StackAmmonia for NOx Reduction BFW Pump Pump Water Treatment Water Source MakeupWater Deaerator Transformer Generator Transformer Generator Natural Gas Supply Compressor Outside Air Cumbustors Cumbustion Turbine Gas Turbine Generator High Pressure Steam to Turbine Low Pressure Steam for NOx Reduction Water Vapor Pump Steam Condensate Condensator Cool Water Cooling Tower Warm Water Steam Turbine
  • 4. Last TimeLast Time Building a Cogeneration ResourceBuilding a Cogeneration Resource Modeling cogeneration in AURORAModeling cogeneration in AURORA This time:This time: Building a Wind ResourceBuilding a Wind Resource Modeling wind generation in AURORAModeling wind generation in AURORA Examining issues related to wind generationExamining issues related to wind generation
  • 5. Turbine Parts Arrive by ShipTurbine Parts Arrive by Ship
  • 6. Site Preparation BeginsSite Preparation Begins
  • 10. Tower Section Trucked to SiteTower Section Trucked to Site
  • 11. Nacelle Trucked to SiteNacelle Trucked to Site
  • 12. Rotor Blade Trucked to SiteRotor Blade Trucked to Site
  • 13. Parts Arrive at SiteParts Arrive at Site
  • 15. Rotor Hub Attached to NacelleRotor Hub Attached to Nacelle
  • 17. Rotor Blade InstalledRotor Blade Installed
  • 20. Project CompleteProject Complete 83 turbines at 1.8 MW each = 150 MW Located on 165 acres in Eastern Washington Produces 50 average megawatts Site prep began March 2005 First turbine construction began August 2005 Project complete December 2005
  • 21.
  • 22. Phases in Building a Wind ResourcePhases in Building a Wind Resource Find a SiteFind a Site Build the MachineBuild the Machine Integrate onto the GridIntegrate onto the Grid
  • 23. Find a SiteFind a Site Location, Location, LocationLocation, Location, Location Site StudiesSite Studies ---- Wind Speed DataWind Speed Data Permits and LeasesPermits and Leases
  • 24. Windy Sites are Best, ButWindy Sites are Best, But ……
  • 25. Ridgelines are Usually GoodRidgelines are Usually Good
  • 26. Consistently Windy Areas Work GreatConsistently Windy Areas Work Great
  • 27. Wind AtlasWind Atlas –– Winter PotentialWinter Potential
  • 28. Wind AtlasWind Atlas –– Spring PotentialSpring Potential
  • 29. Wind AtlasWind Atlas –– Summer PotentialSummer Potential
  • 30. Wind AtlasWind Atlas –– Autumn PotentialAutumn Potential
  • 31. Build the MachineBuild the Machine Decide Which Machine and How BigDecide Which Machine and How Big –– old technologyold technology –– 600 to 660 kW600 to 660 kW –– new technologynew technology –– 2 to 3 MW2 to 3 MW –– developing technologydeveloping technology –– 5 MW5 MW Get In LineGet In Line –– everyone seems to want wind generatorseveryone seems to want wind generators –– current order backlogscurrent order backlogs –– secondary markets developingsecondary markets developing
  • 32. Costs of a Wind GeneratorCosts of a Wind Generator Site and Site PreparationSite and Site Preparation HardwareHardware Integration and TransmissionIntegration and Transmission Current estimatesCurrent estimates –– EIAEIA –– 1,200 per kW1,200 per kW –– NPCCNPCC –– 1,175 per kW1,175 per kW
  • 34. Wind Generation in the WestWind Generation in the West 19901990 –– 1,650 MW in California1,650 MW in California 19991999 –– 1,975 MW in California + 117 MW1,975 MW in California + 117 MW 20022002 –– 3,000 MW3,000 MW 20042004 –– 4,000 MW4,000 MW 20062006 –– 5,000 MW5,000 MW 20072007 –– 8,000 MW ??8,000 MW ?? 20112011 –– 14,000 MW !!!???14,000 MW !!!???
  • 35.
  • 36.
  • 37.
  • 38.
  • 39.
  • 40.
  • 41.
  • 42.
  • 43.
  • 44.
  • 45.
  • 46. Modeling Wind Generation in AURORAModeling Wind Generation in AURORA Obtain hourly generation or wind speedsObtain hourly generation or wind speeds –– Wind speeds for Washington & OregonWind speeds for Washington & Oregon –– wwwwww--k12.atmos.washington.edu/k12/grayskies/nw_weather.htmlk12.atmos.washington.edu/k12/grayskies/nw_weather.html Adjust for tower heightAdjust for tower height –– Speed increases by a factor of 1/7th with heightSpeed increases by a factor of 1/7th with height Apply power curveApply power curve –– Power increases by a cube function with wind speedPower increases by a cube function with wind speed Normalize to average outputNormalize to average output –– Wind speed readings arenWind speed readings aren’’t always at the wind sitet always at the wind site
  • 47. Tower Height AdjustmentTower Height Adjustment www.rpc.com.au/products/windturbines/wind_faq.htmlwww.rpc.com.au/products/windturbines/wind_faq.html
  • 49. Modeling Wind Generation in AURORAModeling Wind Generation in AURORA Choose a representative week for each monthChoose a representative week for each month Convert each hourConvert each hour’’s generation into a forceds generation into a forced outage factor for each of the 168 hours of weekoutage factor for each of the 168 hours of week Result is 168 hours for 12 months per siteResult is 168 hours for 12 months per site Use monthly time series vector to refer toUse monthly time series vector to refer to appropriate weekly time series vectorappropriate weekly time series vector For each wind resource, point to the monthly timeFor each wind resource, point to the monthly time series with that resourceseries with that resource’’s forced outage values forced outage value
  • 50. ExamplesExamples Wind speed =Wind speed = mphmph 11 55 1010 1515 2020 Height adjust =Height adjust = mphmph 22 77 1515 2222 3030 Power curve =Power curve = kWkW 00 1010 8080 270270 640640 Forced outage =Forced outage = %% 100100 9999 9292 7373 3636 Wind speed =Wind speed = mphmph 2525 3030 3535 4040 Height adjust =Height adjust = mphmph 3737 4545 5252 6060 Power curve =Power curve = kWkW 10001000 10001000 10001000 00 Forced outage =Forced outage = %% 00 00 00 100100
  • 51. AURORA setupAURORA setup –– Weekly VectorsWeekly Vectors
  • 52. AURORA setupAURORA setup –– Monthly VectorsMonthly Vectors
  • 53. AURORA setupAURORA setup –– ResourcesResources
  • 54. AURORA setupAURORA setup –– FuelFuel set to zero AURORA setupAURORA setup –– AnnualAnnual actual VOM minus Production Tax Credit
  • 55. Results of Wind ShapingResults of Wind Shaping Shaped WindShaped Wind v.v. Flat WindFlat Wind OutputOutput January 2007 – Existing Wind Resources – 5,500 MW capacity
  • 56. Results of Wind ShapingResults of Wind Shaping Shaped WindShaped Wind v.v. Flat WindFlat Wind OutputOutput Year 2007 – Existing Wind Resources – 5,500 MW capacity
  • 57. Results of Wind ShapingResults of Wind Shaping Shaped WindShaped Wind v.v. Flat WindFlat Wind OutputOutput January 2007 – Future Wind Resources – 14,000 MW capacity
  • 58. Results of Wind ShapingResults of Wind Shaping Shaped WindShaped Wind v.v. Flat WindFlat Wind OutputOutput Year 2007 – Future Wind Resources – 14,000 MW capacity
  • 59. Results of Wind ShapingResults of Wind Shaping Shaped WindShaped Wind v.v. Flat WindFlat Wind PricesPrices Avg = 78.89; Stdev = 10.2 Avg = 78.18; Stdev = 9.4 January 2007 – Existing Wind Resources – Mid-C Prices
  • 60. Results of Wind ShapingResults of Wind Shaping Shaped WindShaped Wind v.v. Flat WindFlat Wind PricesPrices Avg = 73.30; Stdev = 9.5Avg = 70.36; Stdev = 16.7 January 2007 – Future Wind Resources – Mid-C Prices
  • 61. Results of Wind ShapingResults of Wind Shaping Shaped WindShaped Wind v.v. Flat WindFlat Wind PricesPrices Avg = 80.04; Stdev = 17.4 Avg = 80.04; Stdev = 17.1 Year 2007 – Existing Wind Resources – Mid-C Prices
  • 62. Results of Wind ShapingResults of Wind Shaping Shaped WindShaped Wind v.v. Flat WindFlat Wind PricesPrices Avg = 75.96; Stdev = 17.1Avg = 75.33; Stdev = 18.5 Year 2007 – Future Wind Resources – Mid-C Prices
  • 63. Geographic ConcentrationGeographic Concentration Wind generation in Washington and OregonWind generation in Washington and Oregon may grow to about 4,500 MW within fivemay grow to about 4,500 MW within five yearsyears Almost 3,000 MW is targeted to the easternAlmost 3,000 MW is targeted to the eastern Columbia River gorge and another 1,000Columbia River gorge and another 1,000 MW 50 miles east of the gorgeMW 50 miles east of the gorge How will this concentration affect the systemHow will this concentration affect the system operations and market clearing pricesoperations and market clearing prices
  • 64. Expected Geographic ConcentrationExpected Geographic Concentration about 200 MW each
  • 65. Test Geographic DispersionTest Geographic Dispersion about 200 MW each
  • 66. Results of Wind DispersionResults of Wind Dispersion Concentrated WindConcentrated Wind v.v. Dispersed WindDispersed Wind ProductionProduction January 2007 – Washington/Oregon Wind Resources
  • 67. Results of Wind DispersionResults of Wind Dispersion Concentrated WindConcentrated Wind v.v. Dispersed WindDispersed Wind ProductionProduction January 2007 – Washington/Oregon Wind Resources
  • 68. Results of Wind DispersionResults of Wind Dispersion Concentrated WindConcentrated Wind v.v. Dispersed WindDispersed Wind ProductionProduction Year 2007 – Washington/Oregon Wind Resources
  • 69. Results of Wind DispersionResults of Wind Dispersion Concentrated WindConcentrated Wind v.v. Dispersed WindDispersed Wind ProductionProduction Year 2007 – Washington/Oregon Wind Resources
  • 70. How Does Wind Produce Emissions?How Does Wind Produce Emissions? The Overlooked Environmental Cost of a WindThe Overlooked Environmental Cost of a Wind Generation Portfolio to Serve the Need for PowerGeneration Portfolio to Serve the Need for Power –– draft paper by Lincolndraft paper by Lincoln WolvertonWolverton (attached)(attached) Premise of the paperPremise of the paper –– In a closed system, wind generation may not change theIn a closed system, wind generation may not change the amount of fossil fuel burnedamount of fossil fuel burned –– In an open system, the addition of wind generation willIn an open system, the addition of wind generation will change the system operations from base load plants tochange the system operations from base load plants to cycling plantscycling plants
  • 71. Testing the Premise with AURORATesting the Premise with AURORA First, test the closed system premiseFirst, test the closed system premise –– Use AURORAUse AURORA’’s closed system dispatch features closed system dispatch feature to examine two portfoliosto examine two portfolios One portfolio has a 100 MW wind generator and aOne portfolio has a 100 MW wind generator and a 100 MW single cycle combustion turbine100 MW single cycle combustion turbine –– Heat rate = 9500Heat rate = 9500 Other portfolio has a 100 MW combined cycleOther portfolio has a 100 MW combined cycle combustion turbinecombustion turbine –– Heat rate = 7300Heat rate = 7300
  • 72. Testing the Premise with AURORATesting the Premise with AURORA Results:Results: –– Fossil fuel usage increases from wind case toFossil fuel usage increases from wind case to CCCT case by 6.6%CCCT case by 6.6% –– GHG production increases by 8.8%GHG production increases by 8.8% –– NONOxx production decreases by 73%production decreases by 73% –– SOSO22 production decreases by 33%production decreases by 33%
  • 73. Testing the Premise with AURORATesting the Premise with AURORA Next, test the open system premiseNext, test the open system premise –– Examine two casesExamine two cases First, compare the future system with windFirst, compare the future system with wind generation presentgeneration present Second, replace the future system wind with anSecond, replace the future system wind with an equivalent amount of energy production fromequivalent amount of energy production from combined cycle combustion turbinescombined cycle combustion turbines 14,000 MW of wind producing 4,13514,000 MW of wind producing 4,135 aMWaMW ofof energy replaced with combustion turbines inenergy replaced with combustion turbines in each area with wind plantseach area with wind plants
  • 74. Testing the Premise with AURORATesting the Premise with AURORA Results:Results: –– Fossil fuel usage increases from wind case to CCCTFossil fuel usage increases from wind case to CCCT case by 5.7% across all of WECCcase by 5.7% across all of WECC –– GHG production increases by 4.0%GHG production increases by 4.0% 18.7% increase in CCCT GHG offset by18.7% increase in CCCT GHG offset by peakerpeaker reductionsreductions –– NONOxx production increases by 0.8%production increases by 0.8% 18.2% increase in CCCT NO18.2% increase in CCCT NOxx offset byoffset by peakerpeaker reductionsreductions –– SOSO22 production increases by 0.1%production increases by 0.1% 19.5% increase in CCCT SO19.5% increase in CCCT SO22 offset byoffset by peakerpeaker reductionsreductions
  • 75. Testing the Premise with AURORATesting the Premise with AURORA Conclusions:Conclusions: –– Wind generation in the WECC is now of suchWind generation in the WECC is now of such size that hourly modeling is an important factorsize that hourly modeling is an important factor in predicting market clearing pricesin predicting market clearing prices –– Geographic concentration of wind generation isGeographic concentration of wind generation is more expensive tomore expensive to MCPsMCPs than diverse locationsthan diverse locations –– Emissions savings from wind generation areEmissions savings from wind generation are minimized if SCCT operation increases tominimized if SCCT operation increases to regulate wind output to meet loadregulate wind output to meet load