SlideShare a Scribd company logo
1 of 101
Madhya Pradesh Rural
Connectivity Project
(MPRCP)
Dr Deepak Kumar Tripathi
researchenviro@gmail.com
9755104410
S.
No.
Dist
Completed
DPR
Length
(in Km)
Population
Roads in
Tribal
block
Avg. Cost
per KM
(Lakhs)
1
Chhindwa
ra 65 160.00 14647 3 24.89
2 Katni 65 143.23 20419 0 26.34
3 Umariya 21 48.36 4336 1 26.43
Total 151 351.59 39402 4
Transect Walk including
disseminate of information
• For Community Participant
• Social Safeguard
• Environment Checklist
• Road Safety Safeguard
Field Survey
• Topographic
• Traffic
• Hydraulic
• Soil / Material
Design & DPR Preparation
• Geometric Design
• Pavement Design
• Drainage Design
• Improvement as
suggested by MPRRDA
DPR have been prepared on the template
provided by World Bank.
DPR template has 19 chapters, formats &
figures.
DPR Template-DPR Template-
S. No
Chapter of DPR Templates used
by MPRRDA
Chapter of DPR templates Suggested
by World Bank for MPRCP
1 INTRODUCTION INTRODUCTION
2
PLANNING AND BASIC DESIGN
CONSIDERATION
PLANNING AND BASIC DESIGN
CONSIDERATION AND ADOPTED
GEOMETRIC DESIGN STANDARDS
3 TOPOGRAPHIC SURVEY TOPOGRAPHIC SURVEY
4
SOIL AND MATERIAL SURVEY SOIL AND MATERIAL SURVEY
5 TRAFFIC SURVEY TRAFFIC SURVEY
6 HYDROLOGICAL SURVEY HYDROLOGICAL SURVEY
7
GEOMETRIC DESIGN
STANDARDS
DESIGN OF JUNCTIONS
DPR Template-DPR Template-
Cont..
S. No
Chapter of DPR Templates
used by MPRRDA
Chapter of DPR templates
Suggested by World Bank for
MPRCP
8
ALIGNMENT DESIGN
CURVES DESIGN /
IMPROVEMENT OF EXISTING
CURVES
9 PAVEMENT DESIGN PAVEMENT DESIGN
10
DESIGN OF CROSS DRAINAGE
DESIGN OF CROSS DRAINAGE
WORKS
11
PROTECTIVE WORKS &
DRAINAGE
PROTECTION WORK AND
DRAINAGE
12 LAND ACQUISITION LAND REQUIREMENT
13
UTILITY
SHIFTING/RELOCATION
UTILITY SHIFTING/RELOCATION
14
ROAD SAFETY AND TRAFFIC
MANAGEMENT
TRAFFIC MANAGEMENT AND
ROAD SAFETY MEASURES
DPR Template-DPR Template-
Cont..
S. No
Chapter of DPR Templates used
by MPRRDA
Chapter of DPR templates
Suggested by World Bank for
MPRCP
15 SPECIFICATION SPECIFICATION
16 ENVIRONMENTAL ISSUES ENVIRONMENTAL ISSUES
17 ANALYSIS OF RATES ANALYSIS OF RATES
18 COST ESTIMATE COST ESTIMATE
19 CONSTRUCTION PROGRAM CONSTRUCTION PROGRAM
DPR Template-DPR Template-
1. Social screening and Community
Participation
2. Environment Safeguard and
Checklist
3. Emphasis on Road Safety
MPRRDA has issued guidelines time to time to
improve the DPR preparations. These are the
some important points as below-:
Letter No. 14484/World
Bank/MPRCP/MPRRDA/16 Dated 27/6/2016.
 At Start point met with the major road provide
flayer to increase visibility of both side vehicles.
 Use Road marking Thermoplastic items as
required to the curve and junction.
Letter No.19139 14484/World Bank/MPRCP-04
/MPRRDA/16 Dated 07/09/2016.
Wherever traffic load is more then 2msa, design will
be according the traffic and crust and carriageway
width should be 3.75m and road width must be 6.00m.
DPR consultant should attach Transect walk minutes
with the DPR.
Letter No.16817/22/V-12/T-3/MPRRDA/16
Dated 30/07/2016.
 Loosening, leveling and compacting gravel surface to facilitate
placement of first layer of WBM/gravel course. Scarifying
original surface up to a depth of 150mm,making proper
camber, super elevation, maintaining required longitudinal and
cross profile using suitable methods/procedures by equipments
i.e. with rollers of 80-100KN static weight to achieve the
desired density with using grader etc. mixing with water at
OMC complete as per specifications and direction of Engineer-
in-charge.
Benefits of encouraging community participation in
road development…
Involvement of primary stakeholders increases
sustainability of the road
Increases ownership which results in better maintenance
of the road
Develops supportive environment between community
members, Project Implementation Unit [PIU] and
contractors
Incorporation of community perspectives and local
realities improve the design of the road
 Grievances are resolved locally
Using transect walk as a tool for active
participation of community in each aspect of
the road
Developing relevant and contextual IEC
materials and collaterals
Going beyond the conventional ways and
means to ensure greater community
involvement and ownership
Community Participation forCommunity Participation for
Safeguard – How?Safeguard – How?
3. Collect all
the Safeguard
Related
Obligatory
Points with
Community
Consensus.
4. Detail
Discussion &
Documentation of
Community
Demand.
5. Understand & Document
women’s Requirements.
6. Identification and Documentation
of Affected Person & their Linkage
with Government Schemes.
9. Formation of
Infrastructure Support &
Grievances Redressal
Committee with Community
Consensus.
1. Information Dissemination
Before Conducting Transect
Walk.
8. Awareness
Sessions on Road
Safety &
Maintenance
Aspects with
Community
Members at End
Point of the Road.
7. Awareness
Sessions on Road
Safety Aspects with
Teachers & Students
in Schools.
2. Encourage Community
Members Specially Women
to Participant in the
Transect Walk & Share the
Objective of the Transect
Walk to the Community.
Transect Walk
An effective
Process
A. Information Dissemination Before Conducting
Transect Walk to villagers.
B. Encourage Community Specially Women to
Participate in the Transect Walk & Share the
Objective of the Transect Walk to the Community.
C. Collect all the Safeguard Related required Points
with Community Consensus.
D. Detail Discussion & Documentation of Community
Demand.
E. Understand & Document women’s Requirements
F. Identification and Documentation of Affected Person
& their Linkage with Government Schemes
G. Awareness Sessions on Road Safety Aspects with
Teachers & Students in Schools
H. Awareness Sessions on Road Safety & Maintenance
Aspects with Community Members at End Point of
the Road
I. Formation of Infrastructure Support & Grievances
Redressal Committee with Community Consensus.
Transect Walk Process Adopted by IDC
Social Safeguards and Gender
Participants
Environmental Safeguards
Road safety
FORMAT FOR RECORDING TRANSECT WALK SUMMARY
Name of District :-
Name of Block :-
Name of Road :-
Total Road Length :-
Date -
1) Number of Participants in the Transect walk
S.No. Details Qty Remark
1 ·         Female headed household: 0  
2 ·         Scheduled Caste: 7  
3 ·         Scheduled Tribe: 3  
4 . OBC/ General 0  
5 ·         Disabled: 0  
6 ·         BPL: 0  
7
·         Households losing
structure: 0  
Total Number of Participants in the Transect walk:- 10
Social Safeguards
2)
FORMAT FOR RECORDING TRANSECT WALK SUMMARY
Issues and suggestions raised by the Participants
S.No. Details Out come Remark
1 Road alignment and design in general:
Project road is proposed on existing CMGSY alignment
and up gradation of same has been considered.
2 Road width and land availability: -
Availability of road width is 8.00 m to 9.050 m in
Open area and in habitation area it is 6.46 m to 6.56
m.
3
Sensitive locations (forests, cultural properties,
etc.):
There is a temple at Rd 160 m, 10 m away from center
line of road on RHS.
4
Water-related issues (drainage lines, rivers and
water crossings, irrigation water sources, other
water bodies, etc.):
There are 1 nos of Cross Drainages existing . There is 1
well at Rd 225 m, 25 m away from center line on RHS .
5
Road safety-related issues (major junctions,
curves, bends, etc.):
There are 5 Sharp curves on present alignment.
There is School at 150 m,5 m away from center line on
LHS.Proper road safety signages, speed breakers
needs to be provided for road safety to reduce the risk
of accidents.
6
Other suggestions (such as regarding cattle
crossing, borrow pits, etc.):
Proper ramp for cattles crossing have been demanded
by the community.
3) Major Outcomes of the Transect Walk:
1 Changes to be incorporated in the design: Field crossings and ramps needs to be provided.
2
Extent of land take and
willingness/unwillingness of land owner/users
for donation: Not Required
3 Other issues: No other Issues raised by community.
Social Safeguards
Social Safeguards
Road MAP
Road MAP
Chainage wise Transect Walk Findings
Chainage (m)
Existing
Land
Width
(m)
Additional
Land
Required Losses Type of loss
Village
Remarks/
SuggestionsFrom To LHS RHS LHS RHS LHS RHS
0 100 6.2 - - BT proposed
100 200 6.1 - - BT proposed
200 300 6.1 - - BT proposed
300 400 6.2 - - BT proposed
400 500 5.8 - - BT proposed
Social Safeguards transect walk
Social Safeguards-
Transect walk Consultation
Social Safeguards -
Utility Shifting
Social Safeguard -
Land Width Availability
Gender Participant
Community Consultation
Environmental Safeguards-Environmental Safeguards-
Water Logging along the roadWater Logging along the road
Environmental Safeguards-
Protection for tree along the road
Environmental Safeguards-
Water body cross along the road
RURAL ROADS: ENVIRONMENTAL CHECKLIST
Name of District :- Katni
Name of Block :- Bahoriband
Name of Road :- Paharua to Gudiyapura
Total Road Length :- 2.3
A. Climatic Conditions
Temperature
High: 42-45 °C (May)
Low: 8-10°C (Dec)
Humidity
High: 80%(Aug)
Low: 45 % (Dec)
Rainfall 1140 mm/year
Rainy Season month 15th June to 15th September
B. Location of the Road and Generic description of Environment
S.No. Type of Ecosystem Yes No Explanation
1
Type of Terrain (Plain/Hilly/ Mountainous etc.)
(Explain the topography of the area and how many km of the road are located in the hilly area)
Plain
Altitude:
The topography of the project road is flat at almost all locations.
2
Forest Area
(Explain whether the road passes through forest areas or located along the forest areas and distance
from shoulder to the forest area)
No
Density/Vegetation Coverage
Type of Vegetation from Ch-:
Legal Status of the Forest Area:
(Reserved, National Park, Sanctuaries, Unclassified, etc.)
3
Lake/ Swap/Pond/ water logging area
(Explain the distance of the road shoulder from the edge of the lake)
No
Type of water body (Lake, pond, stream):
Status: Protected, Unprotected
From Ch-
4
Wildlife
(Explain whether there are any wildlife species in the project area)
No
Name of animals:
Endangered species (if any):
5
Inhabited Area
(habitation on both side LHS and RHS)
Yes
Gudiyapura habitation from Ch-2000 to 2300 m both side along
the projected road.
6 Agricultural Land Yes
There is agriculture land from Ch- 1100 m to 1400 m along the
projected.
7 Barren Land / Grazing land Yes
Grazing land from RD- 100 m to 1100 m & 1400m to 2000m both
side along the projected road.
8 Flat Area No
C. Description of the Road Environment
Parameter/ Component Yes No Explanation
9 Is the area along the project road prone to flooding problems? No
10
Along the road and within 500 m of the road shoulder, is there any
area with natural habitat? No
11
Along the road and within 500 m of the road shoulder, is there any
species of flora and fauna that is classified as endangered species? No
12
Along the road and within 500 m of the road shoulder, is there any
faunal breeding ground?
No
13
Along the road and within 500 m of the road shoulder, is there any
bird migration area? No
14
Are there any trees with a DbH of 30 cm or more within 10 m on
either side from the center line of the road alignment?
(If yes attach list of trees indicating the location (right or left side)and
the chainage)
Yes
Total tree:- 23 Nos
Tree will be affected: 4Nos
No. of Trees
LHS 11
RHS 12
D. Public Consultation
Consultation Activities Yes No Remarks
15
Consultation with local community was conducted before finalizing
the alignment?
(provide the issues raised by the community) Yes
Project road is proposed on existing CMGSY road so
that alignment is already finalized still the alignment
was discussed with the community.
16 Any suggestion received in finalizing the alignment No
Community expressed their happiness on learning that
the connectivity will be provided with the bituminous
Top.
17 If suggestion received do they get incorporated into design? Yes
Community demanded for field crossings pipe . Field
crossings are proposed at agriculture area and
incorporated
Attachment:
1) Sketch of strip map of the road covering details of at least 10 m on either side from the center line of the road
2) List of trees indicating location (left or right side of the road) and Chainage (as required SN 14).
3) Photographs of the project area showing important features (Atleast 6 photos).
E. Impacts and proposed Mitigation Measures ( Describe concisely the potential impacts and indicate the proposed mitigation measures by
referring to the number of the Environmental Management Standard ECOP in the main test)
Consultation Activities Yes No Remarks
18 Encroachment on historical/ cultural areas? No Project road will not be passing through any such zone.
19 Disfiguration of landscape by road embankments, cuts, fills and quarries? No
As the project road is upgradation of existing CMGSY road,
cut and fill quantities are not much to disturb the
landscape.
20 Encroachment of precious ecology (e.g. sensitive of protected areas)? No Alignment is not passing through any protected area.
21
Alteration of surface water hydrology of waterways crossed by roads,
resulting in increased sediment in streams affected by increased soil erosion
at construction site? No No major stream is passing through the project road.
22
Deterioration of surface water due to sanitary wastes from worker based
camps and chemicals and chemicals used in construction? No
As the project road is very small, normally contractors
deploy local labourer for construction work.
23
Inconvenient environmental condition due to poor sanitation and solid waste
disposal in construction camps and work sites? No
Normally no labour camps are established for the small
rural roads .
24
Inconvenient Environmental condition due possible transmission of
communicable diseases from workers to local populations? No
Precautionary measures will be adopted by the contractor
as per provisions given in the SBD
25 Deterioration of surface water quality due to silt runoff? No
26
Increased local air pollution due to rock crushing, cutting, and filling works.
And chemicals from asphalt processing? No
No such activity like rock cutting or blasting will be
involved in the project road .
27 Noise and vibration due to blasting and other civil works? No
No such activity like rock cutting or blasting will be
involved in the project road .
28 Inconvenience due to land slide of erosion? No The project road is passing through the flat terrain.
29 Dislocation or involuntary resettlement of people? No No PAP in the project road.
30
Other social concerns relating to inconveniences in living condition in the
project areas that may trigger cases of upper respiratory problems and
stress? No
Care will be taken during the construction activity by
sprilinking of water near the working / habitation zone.
31 Creation of temporary breeding habitats for mosquito vectors of disease? No
32
Accident risks associated with increased vehicular traffic leading to loss of
life? No
Proper road safety measures like cautionary and warning
signages, speed breakers PPEs etc will be placed to reduce
the risk of accidents.
33 Inconvenience due to transportation of construction materials? No
Water sprinkling will be done on the project / haulage
road, vehicles with proper PUC will be allowed to ply on
the road.
F.
Permit/ Clearance Required Prior to Commencing Civil Work
Type of Permit/ Clearance Yes No Obtained from
Remarks (recommended
time to apply for the
permit/ clearance)
1 Contractor work insurance copy Contractor
2 Forest clearance if required PIU/Contractor
3 Vehicle Pollution Under Control (PUC) certificate Contractor
4 Hot Mix plant establishment certificate by SPCB Contractor
5 Utilities shifting certificate/permissions/Letters PIU/Contractor
6 License quarry certificate Contractor/PIU
7 For water extraction Contractor
Additional land requirement the required Right of Way (ROW) for this formation width is already available. Certificate
of ground verification from the head of PIU indicates available ROW (if any) as below:
Location/Chainage Additional land (in m)
Sufficient width is available in entire length of the project road
Summary of impacts
Impact Details (if there are any impacts)
Total number of HH (house hold) affected Nil
Total number of Titleholder Nil
Total number of Non-Titleholders Nil
Total number of vulnerable HH affected due to proposed project Nil
Total number of community Property Resources affected Nil
Remarks (if any):
List of Trees
Chainage (m) Left Right
00-100 4 1
100-200 1 1
200-300 1 1
300-400 - -
400-500 1 -
500-600 - -
600-700 - -
700-800 - -
800-900 - -
900-1000 - -
1000-1100 - -
1100-1200 - -
1200-1300 - 1
1300-1400 - -
1400-1500 - -
1500-1600 1 -
1600-1700 1 2
1700-1800 1 1
1800-1900 - 2
1900-2000 1 2
2000-2100 - -
2100-2200 - -
2200-2300 - 1
1. Horizontal curves and steep vertical curves
including hairpin bends
Mitigation measures: Caution boards, Super
Elevation, Extra width, Guard post and Rumble strips,
Edge Marking
2. Junctions-Y type, T type and four legged
Mitigation measures: Flares at junctions to increase
the Visibility, Caution boards and Rumble strips, Edge
Marking
 High embankment or Hilly terrain
Mitigation measures: Guard post/crash barrier on the valley side ,
Edge Marking
 Land slide prone zones
Mitigation measures: Slope protection and caution boards
 Stream / canal running parallel to road
Mitigation measures: Slope protection to control soil erosion /
retaining wall for slope stabilization, Edge Marking
 Electric post and trees near the carriageway
Mitigation measures: Put reflectors for enhancing
visibility
Height of electric line crossing
Mitigation measures: Check for the vertical clearance
and shift / Increase height if required
Cross Drainages Hazard
Trees on the alignment
School and Junction
 High Embankment
Curve
Road Safety Hazard
Road Safety –
School and junction
Geometric design of roads deals with the dimensions
and layout of visible features of the Roads.
Proper geometric design will help in the reduction of
accidents and their severity.
Maximize the comfort, safety .
Provide efficiency in traffic operation.
Provide maximum safety at reasonable cost.
Minimize the environmental impacts.
 Design speed.
 Topography.
 Traffic.
 Environmental factors.
 Economical factors.
 Vehicles properties (dimensions, weight, operating
characteristics, etc.).
 Humans (the physical, mental and psychological
characteristics of the driver and pedestrians like the
reaction time).
Plan
straight portion and Curve
Design Speed
The proposed design speed along this project road is as follows:
Road
classification
Plain
terrain
Rolling
terrain
Mountainous
terrain
Steep terrain
Ruling Min. Ruling Min. Ruling Min. Ruling Min.
Rural Roads
(ODR and VR) 50 40 40 35 25 20 25 20
Horizontal alignment in road design consists of straight
sections of road, known as tangents, connected
by circular horizontal curves.
Terrain Classification Roadway Width (m)
Plain and Rolling
The standard roadway width is 7.50 m but
adopted 6.0 m for link road as per MoRD
guideline.
Mountainous and
Steep
6.0
Design Speed (km/hr)
Safe Stopping Sight
Distance (m)
20 20
30 30
40 45
50 60
Radius of Horizontal Curve
According to IRC recommendations/standards, the minimum radius of
horizontal curve for this project road is given below:
To minimize extra land arrangement, minimum radius used is 20 m and
design speed in these curves are also restricted to 20 km/hr.
Radius of Curve (m) Upto 20 21 - 60 Above 60
Extra Widening for 3.00 m wide
single lane carriageway, (m)
0.9 0.6 Nil
Terrain Category
Radius of Horizontal Curve (m)
Ruling Minimum Absolute Minimum
Plain 90 60
Camber & Super elevation
A camber of 3.50 % will be provided along the carriageway & 4.50% will
be provided along the earthen shoulder. The maximum super elevation
for this project road will be 7 % & 10 % in plain & hilly terrain section
respectively.
It is the design of the road in the horizontal plane.
Consists of a series of tangents (straight lines), circular
curves and transition curves.
Should provide safe travel at a uniform design speed.
is the slope across pavement surface and is fully
developed in the circular curve.
(or)
Super-elevation (banking) is the transverse slope
provided at horizontal curve to counteract the
centrifugal force, by raising the outer edge of the
pavement with respect to the inner edge, throughout
the length of the horizontal curve.
So super elevation helps the vehicle to over come the
centrifugal force on the curves on pavements
Vertical alignment is the longitudinal section (shown
on the y-axis of a road, it consists of straight grades
joined by vertical curves.
Vertical alignment specifies the elevations of points
along the roadway.
Vertical Alignment
The present road is in plain terrain and vertical alignment has been
designed well within ruling gradient. Generally, minimum gradient of
0.3% for drainage purpose is considered for designing the vertical
alignment of this road. Vertical curves are not required when grade change
is less than 1%, however a minimum vertical curve is provided to avoid
vertical kink.
Vertical Curves
For satisfactory appearance, the minimum length of vertical curve for
different design speed is taken from IRC-SP 20:2002. Vertical curves of the
road are designed to provide the visibility at least corresponding to the
safe stopping sight distance. Valley curves will be designed for headlight
sight distance.
Road Junctions are designed at places where
vehicular traffic can move in different directions in a
systematic way. Road Junctions decrease the
probability of accidents. The traffic at Road junctions
is controlled and resumed in a systematic way to
proceed further in their respective directions with
the help of traffic signals. Design of Road Junctions
is a crucial subject. Understanding the nature of
traffic, the kind of area, density of population etc is
very important so as to propose a suitable road
Junction design.
T-Junction Y-Junction
Acute Angle Junction Staggered Junction
Road Name- Navegaon to Path Block- Chhindwara
Dist.- Chhindwara CMGSY Length- 1.6 Km
Gap Length- 1.465
CMGSY Start Point Gap Start Point
Bituminous surfacing serves the following
purposes:
Improves the riding quality
Seals the surface, thus preventing the entry of water
which would otherwise weaken the pavement
structure.
Protects the granular base from the damaging
effects of traffic.
1.1. Specifications for Rural Roads, MORD(2004).Specifications for Rural Roads, MORD(2004).
2.2. Rural Roads Manual IRC:SP:20-2002.Rural Roads Manual IRC:SP:20-2002.
3. MORD Quality Assurance Hand book for Rural Roads3. MORD Quality Assurance Hand book for Rural Roads
Volume I and II :2007Volume I and II :2007
4. Hill Road Manual: IRC:SP:48-1998.4. Hill Road Manual: IRC:SP:48-1998.
5. IRC:SP: 72-2007: Guidelines for design of flexible5. IRC:SP: 72-2007: Guidelines for design of flexible
pavements for low volume Rural Roadspavements for low volume Rural Roads
6. IRC:SP: 62-2004 Guidelines for Design6. IRC:SP: 62-2004 Guidelines for Design
of Rigid Pavements for Rural Roadsof Rigid Pavements for Rural Roads
General
Criteria for determining the pavement (flexible)
Thickness is vertical compressive strain comes to the
subgrade due to the standard axle laden of magnitude 8.17
kN (8170 kg) , if more than this causes permanent
deformation in form of rutting. The maximum rutting can
be accepted in village road as 50 mm before maintenance
and the analytical evaluation can be done according to
IRC:37.
For rigid and semi-rigid pavement tensile stress is taken as
the design criteria.
Subgrade Sub-base course
Base course Surface course
Sub grade
To provide support to the pavement as its foundation.
Top 30 cm of the cutting or embankment at formation
level in rural roads consider as sub-grade.
A minimum of 100% of standard proctor compaction
should be attain in sub-grade.
For clayey soil 95% and moisture content of 2% in excess
of optimum value.
Soil below sub-grade should be compacted to 97% of
standard proctor compaction.
Sub-base course:
Selected materials placed on sub-grade which is
compacted to 98% of IS heavy compaction.
Function of sub-base is to distribute the stresses over a
wide area of the sub-grade imposed by the traffic.
Materials:
CBR of 15%
Passing through 425 micron IS sieve
L.L<25 and P.I<6
Base course
to with stand high stress concentrations which develop
due to traffic under the wearing surface.
Different types of base course used are:
WBM
Crusher-run macadam
Dry lean concrete
Soft aggregate base course
Lime-fly ash concrete
Surface course:
Thickness of surface course depend upon the traffic
volume and type of material used for it.
For gravel roads extra thickness should be provided
because of lost in thickness due to the traffic action.
Bituminous wearing courses must be made up of good
quality aggregate with aggregate impact value not
exceeding 30 % in order to reduce degradation of
aggregates by crushing.
New Roads/Upgradation
Estimation of Traffic
Assessment of sub grade strength
Determination of pavement thickness and
composition
Composition of Rural Traffic
Traffic cannot calculated of AADT
Traffic Growth Rate
As per IRC-72-2015, It is recommended that an average
annual growth rate of 6% over the design life may be
adopted.
Design Life
A design life of 10 years is recommended for purposes of
pavement design.
Determination of ESAL
The Vehicle Damage Factor (VDF) is a multiplier for
converting the number of commercial vehicles of different
axel loads to the number of standard axel load repetitions.
As per IRC- 72-2015
Vehicle Type Laden Unladed/Partially Laden
HCC 2.86 0.31
MCV 0.34 0.02
N=T0 x 365 x [(1+0.01r)n -1/0.01r] x L
Where T0 = ESAL per day = number of commercial
vehicles per day in the year of opening x VDF
And L = lane distribution factor; L = 1 for single
lane /intermediate lane
The traffic parameter has been categorized into 7
categories as under:
T1 : 10,000 to 30,000 ESAL applications
T2 : 30,000 to 60,000 ESAL applications
T3 : 60,000 to 1,00,000 ESAL applications
T4 : 1,00,000 to 2,00,000 ESAL applications
T5 : 2,00,000 to 3,00,000 ESAL applications
T6 : 3,00,000 to 6,00,000 ESAL applications
T7 : 6,00,000 to 10,00,000 ESAL applications
Soil Surveys
For each of the soil groups thus identified, at
least one CBR test should be conducted with
the soil compacted to the standard Proctor
density and at a moisture content
corresponding to the wettest state
considered appropriate to the site conditions.
There are five sub grade strength classes S1,
S2, S3, S4 & S5 covering a range of CBR values
from 2 to 15, for each of which, the pavement
thickness and composition requirements are
given under different traffic categories in
terms of ESAL applications.
Traffic Survey Soil Investigation
Traffic-
As per the IRC:37 design traffic should be 0.1 msa to 2 msa
(million standard axles).
Weight of commercial vehicle (laden) is considered as 3
tones or more.
For design traffic we consider the existing traffic and rate
of growth is 6 % consider.
Traffic study should be done as per the IRC:37.
Road Name - T08 To Rampetdwami
Dist – Chhinidwara, Block - Sausar
Design Standards for culverts has been prepared based on standard
codes and guidelines of IRC: SP: 20: 2002 and similar type of
ongoing projects. General features of the designed cross drainage
structures are given below: -
 Width of Culvert: 7.5 m including thickness of parapet.
 Width of Bridge: 6.0 m with parapet.
 Invert Level: Fixed 15 cm below existing GL/Drain bed
level as shown in drawing.
 Finished Level: Top level of culverts generally will match
with the finished road level and wherever is not
possible the profile will be matched by
providing 1 (V): 25 (H).
Are constructed to carry traffic over natural waterways that
flow below the right of way of the Roads .
They also provide the flow of water below the Roads , along
the natural channel without disturbing its course.
Concern is always to provide adequate size structure
(opening is sufficiently large to discharge expected flow of
water).
Major Structures: Bridges
Minor Structures: short-span bridges and culverts
 Important to select culvert location (Station no.), alignment, and
grade
 Location:
1. Bottom of depression where no natural water course exist.
2. Where natural stream intersect the roadway.
 Alignment:
1. Conform with natural stream
2. Cross roadway at right angles (economy)
3. Skew culverts are needed sometimes
 Grade:
1. Conform to existing grade of stream
2. Reduced grades through culverts…..velocity
reduction…..sediments deposition….reduce capacity
3. Increasing culvert grade…..velocity increase…..erosion at outlet
and beyond.
 Categories:
1- Longitudinal drains:
 pipes laid in trenches within the pavement structure and parallel to
the center line of the HWY.
 Used to lower the water table below the pavement structure .
 Used to remove seeping water into the .
 When water table is very high, two rows of longitudinal drains can
be used.
2- Transverse drains:
 Place transversely below the pavement, perpendicular to the center
line.
3- Horizontal drains:
 Used to relieve pore pressure at slopes of cuts and embankments on
the Roads.
 Consist of small-diameter perforated pipes inserted into the slopes
of the cut or fill
Control of groundwater encountered in Roads locations.
Purpose: control seepage, lowering ground water table, base
and shallow sub grade drains.
Circular pipes laid at suitable depth in a trench, which is
then backfilled with porous granular material.
Pipes materials: Porous concrete, perforated metal, or
vitrified clay
Slope: steep enough to prevent deposition or setting of
materials entering the pipe through joints or perforations.
Intercepting drains, lowering water table, and base drainage.
1. Obtain all site data & plot a roadway cross section
at the culvert site, including a profile of the
stream channel.
2. Establish the culvert elevations, inlets and outlets,
and determine culvert length and slope.
3. Select a type and size of culvert.
4. Examine the need for energy dissipaters.
 Major Phases
1. Estimate quantity of water that is expected to reach the
system.
2. The hydraulic design of each element in the system.
3. The comparison of alternative system to select most
economical system.
Purpose:
To provide a drainage facility or system that will
adequately and economically drain the
estimated flow throughout the design life
without unreasonable risks to the roadway
structure or near by property.
Estimate of Run Off
Existing stream…..use available records.
Return Period (RP): Estimated frequency for rare
events (floods) (i.e. peak design flow).
R P = 50yrs for interstate, = 10 – 25 yrs for streets
and roads, and 5 – 10 yrs for light traffic facilities.
Flood frequency
Statistical based
Indicate mean annual flood as a function of the size of the
drainage area for each hydrological region.
Engineers design drainage facilities to accommodate the
peak flow.
 Rain fall intensity is function of
1. Duration of rainfall.
2. Occurrence (return period).
Note: Small durations provide higher rainfall intensity.
 Duration of rainfall is chosen based on the time of
concentration
Time of concentration: It is the duration of rainfall required
to produce the max. rate of run off.
Time of concentration = Time of flow (over land + in
drainage system)
Time of over land flow: time for a water particle to travel
from most remote point in drainage area to point where it
enters the drainage system.
Time of over land flow = F (Slope, type of surface, length,…)
Estimates of flow in drainage system can be made from
observed or computed velocities of flow.
Q = CM 3/4
M = Catchment area in Sq. Km
C = Constant varying from 14-19 in MP (Consider C
=17)
Small bridge-(site length of which exceeds 15 m)
was decided & designed after joint visit by STA
and S.E. as per SP-20 & SP-13 and relevant IRC
Codes for Bridges.
V = [R2/3
* S1/2
]/ n
V = Mean Velocity (m/s).
R = Hydraulic radius (m) = [Area / wetted perimeter].
S = Slope of channel.
n = Manning’s roughness coefficient.
Q = A V
WB funded Rural Road Projects MPRCP
WB funded Rural Road Projects MPRCP
WB funded Rural Road Projects MPRCP

More Related Content

What's hot

indian infrastructure and pune metro project (feasibility analysis)
indian infrastructure and pune metro project (feasibility analysis)indian infrastructure and pune metro project (feasibility analysis)
indian infrastructure and pune metro project (feasibility analysis)Gurjit Kaur Kaler
 
Transit-oriented development (TOD): Integrating rail and commercial developme...
Transit-oriented development (TOD): Integrating rail and commercial developme...Transit-oriented development (TOD): Integrating rail and commercial developme...
Transit-oriented development (TOD): Integrating rail and commercial developme...Atkins
 
Especificaciones tecnicas ambientales para obras viales
Especificaciones tecnicas ambientales para obras vialesEspecificaciones tecnicas ambientales para obras viales
Especificaciones tecnicas ambientales para obras vialesDaniel Libe
 
Land use transportation cycle
Land use transportation cycleLand use transportation cycle
Land use transportation cycleUday Yadav
 
Infrastructure and Transportation Planning Study Notes
Infrastructure and Transportation Planning Study NotesInfrastructure and Transportation Planning Study Notes
Infrastructure and Transportation Planning Study NotesYash Shah
 
Public transportation planning
Public transportation planningPublic transportation planning
Public transportation planningNEENA VS
 
Perspective plan of bubaneshwar cuttack urban complex
Perspective plan of bubaneshwar cuttack urban complexPerspective plan of bubaneshwar cuttack urban complex
Perspective plan of bubaneshwar cuttack urban complexSneha Manjunath
 
Review of Development Plans/ Master Plans of selected cities of India.
Review of Development Plans/ Master Plans of selected cities of India.Review of Development Plans/ Master Plans of selected cities of India.
Review of Development Plans/ Master Plans of selected cities of India.KARTHICK KRISHNA
 
Urban Areas: Policy, Planning and Zoning Recommendations
Urban Areas: Policy, Planning and Zoning RecommendationsUrban Areas: Policy, Planning and Zoning Recommendations
Urban Areas: Policy, Planning and Zoning RecommendationsAr. Md Shahroz Alam
 
Provision in the project formulation for Environment for Road projects
Provision in the project formulation for Environment for Road projectsProvision in the project formulation for Environment for Road projects
Provision in the project formulation for Environment for Road projectsDr Deepak Kumar Tripathi
 
CORRIDOR-PLANNING-in-Transportation
CORRIDOR-PLANNING-in-TransportationCORRIDOR-PLANNING-in-Transportation
CORRIDOR-PLANNING-in-TransportationRennieMaeBChua
 
What do you understand by Infrastructure Planning Explain the role of Infrast...
What do you understand by Infrastructure Planning Explain the role of Infrast...What do you understand by Infrastructure Planning Explain the role of Infrast...
What do you understand by Infrastructure Planning Explain the role of Infrast...sonalidalal4
 
Lec 15 Transit Operations (Transportation Engineering Dr.Lina Shbeeb)
Lec 15 Transit Operations (Transportation Engineering Dr.Lina Shbeeb)Lec 15 Transit Operations (Transportation Engineering Dr.Lina Shbeeb)
Lec 15 Transit Operations (Transportation Engineering Dr.Lina Shbeeb)Hossam Shafiq I
 

What's hot (20)

indian infrastructure and pune metro project (feasibility analysis)
indian infrastructure and pune metro project (feasibility analysis)indian infrastructure and pune metro project (feasibility analysis)
indian infrastructure and pune metro project (feasibility analysis)
 
Transit-oriented development (TOD): Integrating rail and commercial developme...
Transit-oriented development (TOD): Integrating rail and commercial developme...Transit-oriented development (TOD): Integrating rail and commercial developme...
Transit-oriented development (TOD): Integrating rail and commercial developme...
 
Especificaciones tecnicas ambientales para obras viales
Especificaciones tecnicas ambientales para obras vialesEspecificaciones tecnicas ambientales para obras viales
Especificaciones tecnicas ambientales para obras viales
 
Land use transportation cycle
Land use transportation cycleLand use transportation cycle
Land use transportation cycle
 
Need for MRTS
Need for MRTSNeed for MRTS
Need for MRTS
 
Patan
PatanPatan
Patan
 
Infrastructure and Transportation Planning Study Notes
Infrastructure and Transportation Planning Study NotesInfrastructure and Transportation Planning Study Notes
Infrastructure and Transportation Planning Study Notes
 
Sustainable Planning Fundamentals
Sustainable Planning FundamentalsSustainable Planning Fundamentals
Sustainable Planning Fundamentals
 
Public transportation planning
Public transportation planningPublic transportation planning
Public transportation planning
 
Perspective plan of bubaneshwar cuttack urban complex
Perspective plan of bubaneshwar cuttack urban complexPerspective plan of bubaneshwar cuttack urban complex
Perspective plan of bubaneshwar cuttack urban complex
 
Review of Development Plans/ Master Plans of selected cities of India.
Review of Development Plans/ Master Plans of selected cities of India.Review of Development Plans/ Master Plans of selected cities of India.
Review of Development Plans/ Master Plans of selected cities of India.
 
Dmic presentation
Dmic presentation Dmic presentation
Dmic presentation
 
Smart village
Smart villageSmart village
Smart village
 
Urban Areas: Policy, Planning and Zoning Recommendations
Urban Areas: Policy, Planning and Zoning RecommendationsUrban Areas: Policy, Planning and Zoning Recommendations
Urban Areas: Policy, Planning and Zoning Recommendations
 
Provision in the project formulation for Environment for Road projects
Provision in the project formulation for Environment for Road projectsProvision in the project formulation for Environment for Road projects
Provision in the project formulation for Environment for Road projects
 
Green Mobility
Green MobilityGreen Mobility
Green Mobility
 
CORRIDOR-PLANNING-in-Transportation
CORRIDOR-PLANNING-in-TransportationCORRIDOR-PLANNING-in-Transportation
CORRIDOR-PLANNING-in-Transportation
 
What do you understand by Infrastructure Planning Explain the role of Infrast...
What do you understand by Infrastructure Planning Explain the role of Infrast...What do you understand by Infrastructure Planning Explain the role of Infrast...
What do you understand by Infrastructure Planning Explain the role of Infrast...
 
TOD in India
TOD in IndiaTOD in India
TOD in India
 
Lec 15 Transit Operations (Transportation Engineering Dr.Lina Shbeeb)
Lec 15 Transit Operations (Transportation Engineering Dr.Lina Shbeeb)Lec 15 Transit Operations (Transportation Engineering Dr.Lina Shbeeb)
Lec 15 Transit Operations (Transportation Engineering Dr.Lina Shbeeb)
 

Similar to WB funded Rural Road Projects MPRCP

Environment Social and road safety safeguard
Environment Social and road safety safeguardEnvironment Social and road safety safeguard
Environment Social and road safety safeguardDr Deepak Kumar Tripathi
 
Eia mumbai metro
Eia mumbai metroEia mumbai metro
Eia mumbai metro1392pramod
 
Burlington Bike Path Improvement Public Forum
Burlington Bike Path Improvement Public ForumBurlington Bike Path Improvement Public Forum
Burlington Bike Path Improvement Public Forumchapinspencer
 
Rick Hall: Place & Mobility
Rick Hall: Place & MobilityRick Hall: Place & Mobility
Rick Hall: Place & Mobilityguest7106fd
 
Roadway element design for the Rural area in India.
Roadway element design for the Rural area in India.Roadway element design for the Rural area in India.
Roadway element design for the Rural area in India.Mayank Panchal
 
Highway and railway geometric design-Revised.pptx
Highway and railway geometric design-Revised.pptxHighway and railway geometric design-Revised.pptx
Highway and railway geometric design-Revised.pptxkiranmaqsood5
 
The Study on Method to Determine the Priority in Sidewalk Installation on Rur...
The Study on Method to Determine the Priority in Sidewalk Installation on Rur...The Study on Method to Determine the Priority in Sidewalk Installation on Rur...
The Study on Method to Determine the Priority in Sidewalk Installation on Rur...inventionjournals
 
Helvetas Nepal Trail bridge experience
Helvetas Nepal Trail bridge experienceHelvetas Nepal Trail bridge experience
Helvetas Nepal Trail bridge experiencewalkafine
 
02 sectoral planning 02_
02 sectoral planning 02_02 sectoral planning 02_
02 sectoral planning 02_Primum Nocere
 
Changing scenario in Cities in green technology
Changing scenario in Cities in green technologyChanging scenario in Cities in green technology
Changing scenario in Cities in green technologyspreya772
 
Introduction to highway engineering
Introduction to highway engineeringIntroduction to highway engineering
Introduction to highway engineeringAavani Thampi
 
Project brief updated_aug081
Project brief updated_aug081Project brief updated_aug081
Project brief updated_aug081Anush verma
 
Northern Transport Summit: Danny Crump, Broadway Malyan & Nicola Kane, TfGM
Northern Transport Summit: Danny Crump, Broadway Malyan & Nicola Kane, TfGMNorthern Transport Summit: Danny Crump, Broadway Malyan & Nicola Kane, TfGM
Northern Transport Summit: Danny Crump, Broadway Malyan & Nicola Kane, TfGMPlace North West
 

Similar to WB funded Rural Road Projects MPRCP (20)

Environment Social and road safety safeguard
Environment Social and road safety safeguardEnvironment Social and road safety safeguard
Environment Social and road safety safeguard
 
East Don Trail - Design Concepts
East Don Trail - Design ConceptsEast Don Trail - Design Concepts
East Don Trail - Design Concepts
 
Eia mumbai metro
Eia mumbai metroEia mumbai metro
Eia mumbai metro
 
CWSC Chairs' Presentation to Planning Board
CWSC Chairs' Presentation to Planning BoardCWSC Chairs' Presentation to Planning Board
CWSC Chairs' Presentation to Planning Board
 
Burlington Bike Path Improvement Public Forum
Burlington Bike Path Improvement Public ForumBurlington Bike Path Improvement Public Forum
Burlington Bike Path Improvement Public Forum
 
Rick Hall: Place & Mobility
Rick Hall: Place & MobilityRick Hall: Place & Mobility
Rick Hall: Place & Mobility
 
APSE - Street Cleansing Seminar 2015 - Grass verges and Roadsides - Alan Plom
APSE - Street Cleansing Seminar 2015 - Grass verges and Roadsides - Alan PlomAPSE - Street Cleansing Seminar 2015 - Grass verges and Roadsides - Alan Plom
APSE - Street Cleansing Seminar 2015 - Grass verges and Roadsides - Alan Plom
 
Roadway element design for the Rural area in India.
Roadway element design for the Rural area in India.Roadway element design for the Rural area in India.
Roadway element design for the Rural area in India.
 
June 23, 2020 BPAC Virtual Meeting
June 23, 2020 BPAC Virtual MeetingJune 23, 2020 BPAC Virtual Meeting
June 23, 2020 BPAC Virtual Meeting
 
Highway and railway geometric design-Revised.pptx
Highway and railway geometric design-Revised.pptxHighway and railway geometric design-Revised.pptx
Highway and railway geometric design-Revised.pptx
 
Complete Streets in Large Urban Counties
Complete Streets in Large Urban CountiesComplete Streets in Large Urban Counties
Complete Streets in Large Urban Counties
 
design.pptx
design.pptxdesign.pptx
design.pptx
 
The Study on Method to Determine the Priority in Sidewalk Installation on Rur...
The Study on Method to Determine the Priority in Sidewalk Installation on Rur...The Study on Method to Determine the Priority in Sidewalk Installation on Rur...
The Study on Method to Determine the Priority in Sidewalk Installation on Rur...
 
Helvetas Nepal Trail bridge experience
Helvetas Nepal Trail bridge experienceHelvetas Nepal Trail bridge experience
Helvetas Nepal Trail bridge experience
 
02 sectoral planning 02_
02 sectoral planning 02_02 sectoral planning 02_
02 sectoral planning 02_
 
Chief Minister Gram Sadak Yojana (CMGSY)
Chief Minister Gram Sadak Yojana (CMGSY)Chief Minister Gram Sadak Yojana (CMGSY)
Chief Minister Gram Sadak Yojana (CMGSY)
 
Changing scenario in Cities in green technology
Changing scenario in Cities in green technologyChanging scenario in Cities in green technology
Changing scenario in Cities in green technology
 
Introduction to highway engineering
Introduction to highway engineeringIntroduction to highway engineering
Introduction to highway engineering
 
Project brief updated_aug081
Project brief updated_aug081Project brief updated_aug081
Project brief updated_aug081
 
Northern Transport Summit: Danny Crump, Broadway Malyan & Nicola Kane, TfGM
Northern Transport Summit: Danny Crump, Broadway Malyan & Nicola Kane, TfGMNorthern Transport Summit: Danny Crump, Broadway Malyan & Nicola Kane, TfGM
Northern Transport Summit: Danny Crump, Broadway Malyan & Nicola Kane, TfGM
 

More from Dr Deepak Kumar Tripathi

More from Dr Deepak Kumar Tripathi (8)

Environmental safeguards
Environmental safeguards Environmental safeguards
Environmental safeguards
 
Environmental law
Environmental lawEnvironmental law
Environmental law
 
Basic concept of environment safeguard
Basic concept of environment safeguardBasic concept of environment safeguard
Basic concept of environment safeguard
 
ECoP provision and applicability
ECoP provision and applicabilityECoP provision and applicability
ECoP provision and applicability
 
Environment Social and road safety safeguard
Environment Social and road safety safeguardEnvironment Social and road safety safeguard
Environment Social and road safety safeguard
 
IEE,EMaP plan for Road projects
IEE,EMaP plan for Road projectsIEE,EMaP plan for Road projects
IEE,EMaP plan for Road projects
 
Environment Social Health and Safety (ESHS) safeguard
Environment Social Health and Safety (ESHS) safeguardEnvironment Social Health and Safety (ESHS) safeguard
Environment Social Health and Safety (ESHS) safeguard
 
Environment safeguard for Road projects
Environment safeguard for Road projectsEnvironment safeguard for Road projects
Environment safeguard for Road projects
 

Recently uploaded

原版1:1复刻塔夫斯大学毕业证Tufts毕业证留信学历认证
原版1:1复刻塔夫斯大学毕业证Tufts毕业证留信学历认证原版1:1复刻塔夫斯大学毕业证Tufts毕业证留信学历认证
原版1:1复刻塔夫斯大学毕业证Tufts毕业证留信学历认证jdkhjh
 
Environmental and Social Impact Assessment
Environmental and Social Impact AssessmentEnvironmental and Social Impact Assessment
Environmental and Social Impact AssessmentTesfahunTesema
 
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhidelih Escorts
 
Thessaly master plan- WWF presentation_18.04.24.pdf
Thessaly master plan- WWF presentation_18.04.24.pdfThessaly master plan- WWF presentation_18.04.24.pdf
Thessaly master plan- WWF presentation_18.04.24.pdfTheaMan11
 
885MTAMount DMU University Bachelor's Diploma in Education
885MTAMount DMU University Bachelor's Diploma in Education885MTAMount DMU University Bachelor's Diploma in Education
885MTAMount DMU University Bachelor's Diploma in Educationz xss
 
Delivering nature-based solution outcomes by addressing policy, institutiona...
Delivering nature-based solution outcomes by addressing  policy, institutiona...Delivering nature-based solution outcomes by addressing  policy, institutiona...
Delivering nature-based solution outcomes by addressing policy, institutiona...CIFOR-ICRAF
 
Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170
Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170
Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170simranguptaxx69
 
Species composition, diversity and community structure of mangroves in Barang...
Species composition, diversity and community structure of mangroves in Barang...Species composition, diversity and community structure of mangroves in Barang...
Species composition, diversity and community structure of mangroves in Barang...Open Access Research Paper
 
Hi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
Hi FI Call Girl Ahmedabad 7397865700 Independent Call GirlsHi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
Hi FI Call Girl Ahmedabad 7397865700 Independent Call Girlsssuser7cb4ff
 
Private Escorts Aliganj \ 9548273370 Indian Call Girls Service Lucknow ₹,9527
Private Escorts Aliganj \ 9548273370 Indian Call Girls Service Lucknow ₹,9527Private Escorts Aliganj \ 9548273370 Indian Call Girls Service Lucknow ₹,9527
Private Escorts Aliganj \ 9548273370 Indian Call Girls Service Lucknow ₹,9527nagunakhan
 
NO1 Famous Amil In Karachi Best Amil In Karachi Bangali Baba In Karachi Aamil...
NO1 Famous Amil In Karachi Best Amil In Karachi Bangali Baba In Karachi Aamil...NO1 Famous Amil In Karachi Best Amil In Karachi Bangali Baba In Karachi Aamil...
NO1 Famous Amil In Karachi Best Amil In Karachi Bangali Baba In Karachi Aamil...Amil baba
 
Air pollution soli pollution water pollution noise pollution land pollution
Air pollution soli pollution water pollution noise pollution land pollutionAir pollution soli pollution water pollution noise pollution land pollution
Air pollution soli pollution water pollution noise pollution land pollutionrgxv72jrgc
 
办理La Trobe学位证(文凭证书)拉筹伯大学毕业证成绩单原版一模一样
办理La Trobe学位证(文凭证书)拉筹伯大学毕业证成绩单原版一模一样办理La Trobe学位证(文凭证书)拉筹伯大学毕业证成绩单原版一模一样
办理La Trobe学位证(文凭证书)拉筹伯大学毕业证成绩单原版一模一样umasea
 
EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...
EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...
EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...Aqsa Yasmin
 
Call Girls Abids 7001305949 all area service COD available Any Time
Call Girls Abids 7001305949 all area service COD available Any TimeCall Girls Abids 7001305949 all area service COD available Any Time
Call Girls Abids 7001305949 all area service COD available Any Timedelhimodelshub1
 

Recently uploaded (20)

原版1:1复刻塔夫斯大学毕业证Tufts毕业证留信学历认证
原版1:1复刻塔夫斯大学毕业证Tufts毕业证留信学历认证原版1:1复刻塔夫斯大学毕业证Tufts毕业证留信学历认证
原版1:1复刻塔夫斯大学毕业证Tufts毕业证留信学历认证
 
Environmental and Social Impact Assessment
Environmental and Social Impact AssessmentEnvironmental and Social Impact Assessment
Environmental and Social Impact Assessment
 
Gandhi Nagar (Delhi) 9953330565 Escorts, Call Girls Services
Gandhi Nagar (Delhi) 9953330565 Escorts, Call Girls ServicesGandhi Nagar (Delhi) 9953330565 Escorts, Call Girls Services
Gandhi Nagar (Delhi) 9953330565 Escorts, Call Girls Services
 
young call girls in Janakpuri🔝 9953056974 🔝 escort Service
young call girls in Janakpuri🔝 9953056974 🔝 escort Serviceyoung call girls in Janakpuri🔝 9953056974 🔝 escort Service
young call girls in Janakpuri🔝 9953056974 🔝 escort Service
 
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi
 
Thessaly master plan- WWF presentation_18.04.24.pdf
Thessaly master plan- WWF presentation_18.04.24.pdfThessaly master plan- WWF presentation_18.04.24.pdf
Thessaly master plan- WWF presentation_18.04.24.pdf
 
885MTAMount DMU University Bachelor's Diploma in Education
885MTAMount DMU University Bachelor's Diploma in Education885MTAMount DMU University Bachelor's Diploma in Education
885MTAMount DMU University Bachelor's Diploma in Education
 
Delivering nature-based solution outcomes by addressing policy, institutiona...
Delivering nature-based solution outcomes by addressing  policy, institutiona...Delivering nature-based solution outcomes by addressing  policy, institutiona...
Delivering nature-based solution outcomes by addressing policy, institutiona...
 
Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170
Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170
Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170
 
Species composition, diversity and community structure of mangroves in Barang...
Species composition, diversity and community structure of mangroves in Barang...Species composition, diversity and community structure of mangroves in Barang...
Species composition, diversity and community structure of mangroves in Barang...
 
Hi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
Hi FI Call Girl Ahmedabad 7397865700 Independent Call GirlsHi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
Hi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
 
Private Escorts Aliganj \ 9548273370 Indian Call Girls Service Lucknow ₹,9527
Private Escorts Aliganj \ 9548273370 Indian Call Girls Service Lucknow ₹,9527Private Escorts Aliganj \ 9548273370 Indian Call Girls Service Lucknow ₹,9527
Private Escorts Aliganj \ 9548273370 Indian Call Girls Service Lucknow ₹,9527
 
Call Girls In R.K. Puram 9953056974 Escorts ServiCe In Delhi Ncr
Call Girls In R.K. Puram 9953056974 Escorts ServiCe In Delhi NcrCall Girls In R.K. Puram 9953056974 Escorts ServiCe In Delhi Ncr
Call Girls In R.K. Puram 9953056974 Escorts ServiCe In Delhi Ncr
 
Escort Service Call Girls In Shakti Nagar, 99530°56974 Delhi NCR
Escort Service Call Girls In Shakti Nagar, 99530°56974 Delhi NCREscort Service Call Girls In Shakti Nagar, 99530°56974 Delhi NCR
Escort Service Call Girls In Shakti Nagar, 99530°56974 Delhi NCR
 
Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...
Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...
Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...
 
NO1 Famous Amil In Karachi Best Amil In Karachi Bangali Baba In Karachi Aamil...
NO1 Famous Amil In Karachi Best Amil In Karachi Bangali Baba In Karachi Aamil...NO1 Famous Amil In Karachi Best Amil In Karachi Bangali Baba In Karachi Aamil...
NO1 Famous Amil In Karachi Best Amil In Karachi Bangali Baba In Karachi Aamil...
 
Air pollution soli pollution water pollution noise pollution land pollution
Air pollution soli pollution water pollution noise pollution land pollutionAir pollution soli pollution water pollution noise pollution land pollution
Air pollution soli pollution water pollution noise pollution land pollution
 
办理La Trobe学位证(文凭证书)拉筹伯大学毕业证成绩单原版一模一样
办理La Trobe学位证(文凭证书)拉筹伯大学毕业证成绩单原版一模一样办理La Trobe学位证(文凭证书)拉筹伯大学毕业证成绩单原版一模一样
办理La Trobe学位证(文凭证书)拉筹伯大学毕业证成绩单原版一模一样
 
EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...
EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...
EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...
 
Call Girls Abids 7001305949 all area service COD available Any Time
Call Girls Abids 7001305949 all area service COD available Any TimeCall Girls Abids 7001305949 all area service COD available Any Time
Call Girls Abids 7001305949 all area service COD available Any Time
 

WB funded Rural Road Projects MPRCP

  • 1. Madhya Pradesh Rural Connectivity Project (MPRCP) Dr Deepak Kumar Tripathi researchenviro@gmail.com 9755104410
  • 2. S. No. Dist Completed DPR Length (in Km) Population Roads in Tribal block Avg. Cost per KM (Lakhs) 1 Chhindwa ra 65 160.00 14647 3 24.89 2 Katni 65 143.23 20419 0 26.34 3 Umariya 21 48.36 4336 1 26.43 Total 151 351.59 39402 4
  • 3. Transect Walk including disseminate of information • For Community Participant • Social Safeguard • Environment Checklist • Road Safety Safeguard Field Survey • Topographic • Traffic • Hydraulic • Soil / Material Design & DPR Preparation • Geometric Design • Pavement Design • Drainage Design • Improvement as suggested by MPRRDA
  • 4. DPR have been prepared on the template provided by World Bank. DPR template has 19 chapters, formats & figures. DPR Template-DPR Template-
  • 5. S. No Chapter of DPR Templates used by MPRRDA Chapter of DPR templates Suggested by World Bank for MPRCP 1 INTRODUCTION INTRODUCTION 2 PLANNING AND BASIC DESIGN CONSIDERATION PLANNING AND BASIC DESIGN CONSIDERATION AND ADOPTED GEOMETRIC DESIGN STANDARDS 3 TOPOGRAPHIC SURVEY TOPOGRAPHIC SURVEY 4 SOIL AND MATERIAL SURVEY SOIL AND MATERIAL SURVEY 5 TRAFFIC SURVEY TRAFFIC SURVEY 6 HYDROLOGICAL SURVEY HYDROLOGICAL SURVEY 7 GEOMETRIC DESIGN STANDARDS DESIGN OF JUNCTIONS DPR Template-DPR Template- Cont..
  • 6. S. No Chapter of DPR Templates used by MPRRDA Chapter of DPR templates Suggested by World Bank for MPRCP 8 ALIGNMENT DESIGN CURVES DESIGN / IMPROVEMENT OF EXISTING CURVES 9 PAVEMENT DESIGN PAVEMENT DESIGN 10 DESIGN OF CROSS DRAINAGE DESIGN OF CROSS DRAINAGE WORKS 11 PROTECTIVE WORKS & DRAINAGE PROTECTION WORK AND DRAINAGE 12 LAND ACQUISITION LAND REQUIREMENT 13 UTILITY SHIFTING/RELOCATION UTILITY SHIFTING/RELOCATION 14 ROAD SAFETY AND TRAFFIC MANAGEMENT TRAFFIC MANAGEMENT AND ROAD SAFETY MEASURES DPR Template-DPR Template- Cont..
  • 7. S. No Chapter of DPR Templates used by MPRRDA Chapter of DPR templates Suggested by World Bank for MPRCP 15 SPECIFICATION SPECIFICATION 16 ENVIRONMENTAL ISSUES ENVIRONMENTAL ISSUES 17 ANALYSIS OF RATES ANALYSIS OF RATES 18 COST ESTIMATE COST ESTIMATE 19 CONSTRUCTION PROGRAM CONSTRUCTION PROGRAM DPR Template-DPR Template-
  • 8. 1. Social screening and Community Participation 2. Environment Safeguard and Checklist 3. Emphasis on Road Safety
  • 9. MPRRDA has issued guidelines time to time to improve the DPR preparations. These are the some important points as below-: Letter No. 14484/World Bank/MPRCP/MPRRDA/16 Dated 27/6/2016.  At Start point met with the major road provide flayer to increase visibility of both side vehicles.  Use Road marking Thermoplastic items as required to the curve and junction.
  • 10. Letter No.19139 14484/World Bank/MPRCP-04 /MPRRDA/16 Dated 07/09/2016. Wherever traffic load is more then 2msa, design will be according the traffic and crust and carriageway width should be 3.75m and road width must be 6.00m. DPR consultant should attach Transect walk minutes with the DPR.
  • 11. Letter No.16817/22/V-12/T-3/MPRRDA/16 Dated 30/07/2016.  Loosening, leveling and compacting gravel surface to facilitate placement of first layer of WBM/gravel course. Scarifying original surface up to a depth of 150mm,making proper camber, super elevation, maintaining required longitudinal and cross profile using suitable methods/procedures by equipments i.e. with rollers of 80-100KN static weight to achieve the desired density with using grader etc. mixing with water at OMC complete as per specifications and direction of Engineer- in-charge.
  • 12. Benefits of encouraging community participation in road development… Involvement of primary stakeholders increases sustainability of the road Increases ownership which results in better maintenance of the road Develops supportive environment between community members, Project Implementation Unit [PIU] and contractors Incorporation of community perspectives and local realities improve the design of the road  Grievances are resolved locally
  • 13.
  • 14. Using transect walk as a tool for active participation of community in each aspect of the road Developing relevant and contextual IEC materials and collaterals Going beyond the conventional ways and means to ensure greater community involvement and ownership Community Participation forCommunity Participation for Safeguard – How?Safeguard – How?
  • 15. 3. Collect all the Safeguard Related Obligatory Points with Community Consensus. 4. Detail Discussion & Documentation of Community Demand. 5. Understand & Document women’s Requirements. 6. Identification and Documentation of Affected Person & their Linkage with Government Schemes. 9. Formation of Infrastructure Support & Grievances Redressal Committee with Community Consensus. 1. Information Dissemination Before Conducting Transect Walk. 8. Awareness Sessions on Road Safety & Maintenance Aspects with Community Members at End Point of the Road. 7. Awareness Sessions on Road Safety Aspects with Teachers & Students in Schools. 2. Encourage Community Members Specially Women to Participant in the Transect Walk & Share the Objective of the Transect Walk to the Community. Transect Walk An effective Process
  • 16. A. Information Dissemination Before Conducting Transect Walk to villagers. B. Encourage Community Specially Women to Participate in the Transect Walk & Share the Objective of the Transect Walk to the Community. C. Collect all the Safeguard Related required Points with Community Consensus. D. Detail Discussion & Documentation of Community Demand. E. Understand & Document women’s Requirements
  • 17. F. Identification and Documentation of Affected Person & their Linkage with Government Schemes G. Awareness Sessions on Road Safety Aspects with Teachers & Students in Schools H. Awareness Sessions on Road Safety & Maintenance Aspects with Community Members at End Point of the Road I. Formation of Infrastructure Support & Grievances Redressal Committee with Community Consensus. Transect Walk Process Adopted by IDC
  • 18. Social Safeguards and Gender Participants Environmental Safeguards Road safety
  • 19. FORMAT FOR RECORDING TRANSECT WALK SUMMARY Name of District :- Name of Block :- Name of Road :- Total Road Length :- Date - 1) Number of Participants in the Transect walk S.No. Details Qty Remark 1 ·         Female headed household: 0   2 ·         Scheduled Caste: 7   3 ·         Scheduled Tribe: 3   4 . OBC/ General 0   5 ·         Disabled: 0   6 ·         BPL: 0   7 ·         Households losing structure: 0   Total Number of Participants in the Transect walk:- 10 Social Safeguards
  • 20. 2) FORMAT FOR RECORDING TRANSECT WALK SUMMARY Issues and suggestions raised by the Participants S.No. Details Out come Remark 1 Road alignment and design in general: Project road is proposed on existing CMGSY alignment and up gradation of same has been considered. 2 Road width and land availability: - Availability of road width is 8.00 m to 9.050 m in Open area and in habitation area it is 6.46 m to 6.56 m. 3 Sensitive locations (forests, cultural properties, etc.): There is a temple at Rd 160 m, 10 m away from center line of road on RHS. 4 Water-related issues (drainage lines, rivers and water crossings, irrigation water sources, other water bodies, etc.): There are 1 nos of Cross Drainages existing . There is 1 well at Rd 225 m, 25 m away from center line on RHS . 5 Road safety-related issues (major junctions, curves, bends, etc.): There are 5 Sharp curves on present alignment. There is School at 150 m,5 m away from center line on LHS.Proper road safety signages, speed breakers needs to be provided for road safety to reduce the risk of accidents. 6 Other suggestions (such as regarding cattle crossing, borrow pits, etc.): Proper ramp for cattles crossing have been demanded by the community. 3) Major Outcomes of the Transect Walk: 1 Changes to be incorporated in the design: Field crossings and ramps needs to be provided. 2 Extent of land take and willingness/unwillingness of land owner/users for donation: Not Required 3 Other issues: No other Issues raised by community. Social Safeguards
  • 24. Chainage wise Transect Walk Findings Chainage (m) Existing Land Width (m) Additional Land Required Losses Type of loss Village Remarks/ SuggestionsFrom To LHS RHS LHS RHS LHS RHS 0 100 6.2 - - BT proposed 100 200 6.1 - - BT proposed 200 300 6.1 - - BT proposed 300 400 6.2 - - BT proposed 400 500 5.8 - - BT proposed Social Safeguards transect walk
  • 27. Social Safeguard - Land Width Availability
  • 29. Environmental Safeguards-Environmental Safeguards- Water Logging along the roadWater Logging along the road
  • 31. Environmental Safeguards- Water body cross along the road
  • 32. RURAL ROADS: ENVIRONMENTAL CHECKLIST Name of District :- Katni Name of Block :- Bahoriband Name of Road :- Paharua to Gudiyapura Total Road Length :- 2.3 A. Climatic Conditions Temperature High: 42-45 °C (May) Low: 8-10°C (Dec) Humidity High: 80%(Aug) Low: 45 % (Dec) Rainfall 1140 mm/year Rainy Season month 15th June to 15th September B. Location of the Road and Generic description of Environment S.No. Type of Ecosystem Yes No Explanation 1 Type of Terrain (Plain/Hilly/ Mountainous etc.) (Explain the topography of the area and how many km of the road are located in the hilly area) Plain Altitude: The topography of the project road is flat at almost all locations. 2 Forest Area (Explain whether the road passes through forest areas or located along the forest areas and distance from shoulder to the forest area) No Density/Vegetation Coverage Type of Vegetation from Ch-: Legal Status of the Forest Area: (Reserved, National Park, Sanctuaries, Unclassified, etc.) 3 Lake/ Swap/Pond/ water logging area (Explain the distance of the road shoulder from the edge of the lake) No Type of water body (Lake, pond, stream): Status: Protected, Unprotected From Ch- 4 Wildlife (Explain whether there are any wildlife species in the project area) No Name of animals: Endangered species (if any): 5 Inhabited Area (habitation on both side LHS and RHS) Yes Gudiyapura habitation from Ch-2000 to 2300 m both side along the projected road. 6 Agricultural Land Yes There is agriculture land from Ch- 1100 m to 1400 m along the projected. 7 Barren Land / Grazing land Yes Grazing land from RD- 100 m to 1100 m & 1400m to 2000m both side along the projected road. 8 Flat Area No
  • 33. C. Description of the Road Environment Parameter/ Component Yes No Explanation 9 Is the area along the project road prone to flooding problems? No 10 Along the road and within 500 m of the road shoulder, is there any area with natural habitat? No 11 Along the road and within 500 m of the road shoulder, is there any species of flora and fauna that is classified as endangered species? No 12 Along the road and within 500 m of the road shoulder, is there any faunal breeding ground? No 13 Along the road and within 500 m of the road shoulder, is there any bird migration area? No 14 Are there any trees with a DbH of 30 cm or more within 10 m on either side from the center line of the road alignment? (If yes attach list of trees indicating the location (right or left side)and the chainage) Yes Total tree:- 23 Nos Tree will be affected: 4Nos No. of Trees LHS 11 RHS 12 D. Public Consultation Consultation Activities Yes No Remarks 15 Consultation with local community was conducted before finalizing the alignment? (provide the issues raised by the community) Yes Project road is proposed on existing CMGSY road so that alignment is already finalized still the alignment was discussed with the community. 16 Any suggestion received in finalizing the alignment No Community expressed their happiness on learning that the connectivity will be provided with the bituminous Top. 17 If suggestion received do they get incorporated into design? Yes Community demanded for field crossings pipe . Field crossings are proposed at agriculture area and incorporated Attachment: 1) Sketch of strip map of the road covering details of at least 10 m on either side from the center line of the road 2) List of trees indicating location (left or right side of the road) and Chainage (as required SN 14). 3) Photographs of the project area showing important features (Atleast 6 photos).
  • 34. E. Impacts and proposed Mitigation Measures ( Describe concisely the potential impacts and indicate the proposed mitigation measures by referring to the number of the Environmental Management Standard ECOP in the main test) Consultation Activities Yes No Remarks 18 Encroachment on historical/ cultural areas? No Project road will not be passing through any such zone. 19 Disfiguration of landscape by road embankments, cuts, fills and quarries? No As the project road is upgradation of existing CMGSY road, cut and fill quantities are not much to disturb the landscape. 20 Encroachment of precious ecology (e.g. sensitive of protected areas)? No Alignment is not passing through any protected area. 21 Alteration of surface water hydrology of waterways crossed by roads, resulting in increased sediment in streams affected by increased soil erosion at construction site? No No major stream is passing through the project road. 22 Deterioration of surface water due to sanitary wastes from worker based camps and chemicals and chemicals used in construction? No As the project road is very small, normally contractors deploy local labourer for construction work. 23 Inconvenient environmental condition due to poor sanitation and solid waste disposal in construction camps and work sites? No Normally no labour camps are established for the small rural roads . 24 Inconvenient Environmental condition due possible transmission of communicable diseases from workers to local populations? No Precautionary measures will be adopted by the contractor as per provisions given in the SBD 25 Deterioration of surface water quality due to silt runoff? No 26 Increased local air pollution due to rock crushing, cutting, and filling works. And chemicals from asphalt processing? No No such activity like rock cutting or blasting will be involved in the project road . 27 Noise and vibration due to blasting and other civil works? No No such activity like rock cutting or blasting will be involved in the project road . 28 Inconvenience due to land slide of erosion? No The project road is passing through the flat terrain. 29 Dislocation or involuntary resettlement of people? No No PAP in the project road. 30 Other social concerns relating to inconveniences in living condition in the project areas that may trigger cases of upper respiratory problems and stress? No Care will be taken during the construction activity by sprilinking of water near the working / habitation zone. 31 Creation of temporary breeding habitats for mosquito vectors of disease? No 32 Accident risks associated with increased vehicular traffic leading to loss of life? No Proper road safety measures like cautionary and warning signages, speed breakers PPEs etc will be placed to reduce the risk of accidents. 33 Inconvenience due to transportation of construction materials? No Water sprinkling will be done on the project / haulage road, vehicles with proper PUC will be allowed to ply on the road.
  • 35. F. Permit/ Clearance Required Prior to Commencing Civil Work Type of Permit/ Clearance Yes No Obtained from Remarks (recommended time to apply for the permit/ clearance) 1 Contractor work insurance copy Contractor 2 Forest clearance if required PIU/Contractor 3 Vehicle Pollution Under Control (PUC) certificate Contractor 4 Hot Mix plant establishment certificate by SPCB Contractor 5 Utilities shifting certificate/permissions/Letters PIU/Contractor 6 License quarry certificate Contractor/PIU 7 For water extraction Contractor Additional land requirement the required Right of Way (ROW) for this formation width is already available. Certificate of ground verification from the head of PIU indicates available ROW (if any) as below: Location/Chainage Additional land (in m) Sufficient width is available in entire length of the project road Summary of impacts Impact Details (if there are any impacts) Total number of HH (house hold) affected Nil Total number of Titleholder Nil Total number of Non-Titleholders Nil Total number of vulnerable HH affected due to proposed project Nil Total number of community Property Resources affected Nil Remarks (if any):
  • 36. List of Trees Chainage (m) Left Right 00-100 4 1 100-200 1 1 200-300 1 1 300-400 - - 400-500 1 - 500-600 - - 600-700 - - 700-800 - - 800-900 - - 900-1000 - - 1000-1100 - - 1100-1200 - - 1200-1300 - 1 1300-1400 - - 1400-1500 - - 1500-1600 1 - 1600-1700 1 2 1700-1800 1 1 1800-1900 - 2 1900-2000 1 2 2000-2100 - - 2100-2200 - - 2200-2300 - 1
  • 37. 1. Horizontal curves and steep vertical curves including hairpin bends Mitigation measures: Caution boards, Super Elevation, Extra width, Guard post and Rumble strips, Edge Marking 2. Junctions-Y type, T type and four legged Mitigation measures: Flares at junctions to increase the Visibility, Caution boards and Rumble strips, Edge Marking
  • 38.  High embankment or Hilly terrain Mitigation measures: Guard post/crash barrier on the valley side , Edge Marking  Land slide prone zones Mitigation measures: Slope protection and caution boards  Stream / canal running parallel to road Mitigation measures: Slope protection to control soil erosion / retaining wall for slope stabilization, Edge Marking
  • 39.  Electric post and trees near the carriageway Mitigation measures: Put reflectors for enhancing visibility Height of electric line crossing Mitigation measures: Check for the vertical clearance and shift / Increase height if required
  • 40. Cross Drainages Hazard Trees on the alignment School and Junction  High Embankment Curve
  • 42.
  • 43. Road Safety – School and junction
  • 44.
  • 45.
  • 46.
  • 47. Geometric design of roads deals with the dimensions and layout of visible features of the Roads. Proper geometric design will help in the reduction of accidents and their severity. Maximize the comfort, safety . Provide efficiency in traffic operation. Provide maximum safety at reasonable cost. Minimize the environmental impacts.
  • 48.  Design speed.  Topography.  Traffic.  Environmental factors.  Economical factors.  Vehicles properties (dimensions, weight, operating characteristics, etc.).  Humans (the physical, mental and psychological characteristics of the driver and pedestrians like the reaction time).
  • 49. Plan straight portion and Curve Design Speed The proposed design speed along this project road is as follows: Road classification Plain terrain Rolling terrain Mountainous terrain Steep terrain Ruling Min. Ruling Min. Ruling Min. Ruling Min. Rural Roads (ODR and VR) 50 40 40 35 25 20 25 20
  • 50. Horizontal alignment in road design consists of straight sections of road, known as tangents, connected by circular horizontal curves.
  • 51. Terrain Classification Roadway Width (m) Plain and Rolling The standard roadway width is 7.50 m but adopted 6.0 m for link road as per MoRD guideline. Mountainous and Steep 6.0
  • 52. Design Speed (km/hr) Safe Stopping Sight Distance (m) 20 20 30 30 40 45 50 60
  • 53. Radius of Horizontal Curve According to IRC recommendations/standards, the minimum radius of horizontal curve for this project road is given below: To minimize extra land arrangement, minimum radius used is 20 m and design speed in these curves are also restricted to 20 km/hr. Radius of Curve (m) Upto 20 21 - 60 Above 60 Extra Widening for 3.00 m wide single lane carriageway, (m) 0.9 0.6 Nil Terrain Category Radius of Horizontal Curve (m) Ruling Minimum Absolute Minimum Plain 90 60
  • 54. Camber & Super elevation A camber of 3.50 % will be provided along the carriageway & 4.50% will be provided along the earthen shoulder. The maximum super elevation for this project road will be 7 % & 10 % in plain & hilly terrain section respectively.
  • 55. It is the design of the road in the horizontal plane. Consists of a series of tangents (straight lines), circular curves and transition curves. Should provide safe travel at a uniform design speed.
  • 56. is the slope across pavement surface and is fully developed in the circular curve. (or) Super-elevation (banking) is the transverse slope provided at horizontal curve to counteract the centrifugal force, by raising the outer edge of the pavement with respect to the inner edge, throughout the length of the horizontal curve. So super elevation helps the vehicle to over come the centrifugal force on the curves on pavements
  • 57. Vertical alignment is the longitudinal section (shown on the y-axis of a road, it consists of straight grades joined by vertical curves. Vertical alignment specifies the elevations of points along the roadway.
  • 58. Vertical Alignment The present road is in plain terrain and vertical alignment has been designed well within ruling gradient. Generally, minimum gradient of 0.3% for drainage purpose is considered for designing the vertical alignment of this road. Vertical curves are not required when grade change is less than 1%, however a minimum vertical curve is provided to avoid vertical kink. Vertical Curves For satisfactory appearance, the minimum length of vertical curve for different design speed is taken from IRC-SP 20:2002. Vertical curves of the road are designed to provide the visibility at least corresponding to the safe stopping sight distance. Valley curves will be designed for headlight sight distance.
  • 59.
  • 60. Road Junctions are designed at places where vehicular traffic can move in different directions in a systematic way. Road Junctions decrease the probability of accidents. The traffic at Road junctions is controlled and resumed in a systematic way to proceed further in their respective directions with the help of traffic signals. Design of Road Junctions is a crucial subject. Understanding the nature of traffic, the kind of area, density of population etc is very important so as to propose a suitable road Junction design.
  • 61. T-Junction Y-Junction Acute Angle Junction Staggered Junction
  • 62. Road Name- Navegaon to Path Block- Chhindwara Dist.- Chhindwara CMGSY Length- 1.6 Km Gap Length- 1.465 CMGSY Start Point Gap Start Point
  • 63.
  • 64. Bituminous surfacing serves the following purposes: Improves the riding quality Seals the surface, thus preventing the entry of water which would otherwise weaken the pavement structure. Protects the granular base from the damaging effects of traffic.
  • 65. 1.1. Specifications for Rural Roads, MORD(2004).Specifications for Rural Roads, MORD(2004). 2.2. Rural Roads Manual IRC:SP:20-2002.Rural Roads Manual IRC:SP:20-2002. 3. MORD Quality Assurance Hand book for Rural Roads3. MORD Quality Assurance Hand book for Rural Roads Volume I and II :2007Volume I and II :2007 4. Hill Road Manual: IRC:SP:48-1998.4. Hill Road Manual: IRC:SP:48-1998. 5. IRC:SP: 72-2007: Guidelines for design of flexible5. IRC:SP: 72-2007: Guidelines for design of flexible pavements for low volume Rural Roadspavements for low volume Rural Roads 6. IRC:SP: 62-2004 Guidelines for Design6. IRC:SP: 62-2004 Guidelines for Design of Rigid Pavements for Rural Roadsof Rigid Pavements for Rural Roads
  • 66. General Criteria for determining the pavement (flexible) Thickness is vertical compressive strain comes to the subgrade due to the standard axle laden of magnitude 8.17 kN (8170 kg) , if more than this causes permanent deformation in form of rutting. The maximum rutting can be accepted in village road as 50 mm before maintenance and the analytical evaluation can be done according to IRC:37. For rigid and semi-rigid pavement tensile stress is taken as the design criteria.
  • 67. Subgrade Sub-base course Base course Surface course
  • 68. Sub grade To provide support to the pavement as its foundation. Top 30 cm of the cutting or embankment at formation level in rural roads consider as sub-grade. A minimum of 100% of standard proctor compaction should be attain in sub-grade. For clayey soil 95% and moisture content of 2% in excess of optimum value. Soil below sub-grade should be compacted to 97% of standard proctor compaction.
  • 69. Sub-base course: Selected materials placed on sub-grade which is compacted to 98% of IS heavy compaction. Function of sub-base is to distribute the stresses over a wide area of the sub-grade imposed by the traffic. Materials: CBR of 15% Passing through 425 micron IS sieve L.L<25 and P.I<6
  • 70. Base course to with stand high stress concentrations which develop due to traffic under the wearing surface. Different types of base course used are: WBM Crusher-run macadam Dry lean concrete Soft aggregate base course Lime-fly ash concrete
  • 71. Surface course: Thickness of surface course depend upon the traffic volume and type of material used for it. For gravel roads extra thickness should be provided because of lost in thickness due to the traffic action. Bituminous wearing courses must be made up of good quality aggregate with aggregate impact value not exceeding 30 % in order to reduce degradation of aggregates by crushing.
  • 72. New Roads/Upgradation Estimation of Traffic Assessment of sub grade strength Determination of pavement thickness and composition
  • 73. Composition of Rural Traffic Traffic cannot calculated of AADT Traffic Growth Rate As per IRC-72-2015, It is recommended that an average annual growth rate of 6% over the design life may be adopted. Design Life A design life of 10 years is recommended for purposes of pavement design.
  • 74. Determination of ESAL The Vehicle Damage Factor (VDF) is a multiplier for converting the number of commercial vehicles of different axel loads to the number of standard axel load repetitions. As per IRC- 72-2015 Vehicle Type Laden Unladed/Partially Laden HCC 2.86 0.31 MCV 0.34 0.02 N=T0 x 365 x [(1+0.01r)n -1/0.01r] x L
  • 75. Where T0 = ESAL per day = number of commercial vehicles per day in the year of opening x VDF And L = lane distribution factor; L = 1 for single lane /intermediate lane
  • 76. The traffic parameter has been categorized into 7 categories as under: T1 : 10,000 to 30,000 ESAL applications T2 : 30,000 to 60,000 ESAL applications T3 : 60,000 to 1,00,000 ESAL applications T4 : 1,00,000 to 2,00,000 ESAL applications T5 : 2,00,000 to 3,00,000 ESAL applications T6 : 3,00,000 to 6,00,000 ESAL applications T7 : 6,00,000 to 10,00,000 ESAL applications
  • 77. Soil Surveys For each of the soil groups thus identified, at least one CBR test should be conducted with the soil compacted to the standard Proctor density and at a moisture content corresponding to the wettest state considered appropriate to the site conditions.
  • 78. There are five sub grade strength classes S1, S2, S3, S4 & S5 covering a range of CBR values from 2 to 15, for each of which, the pavement thickness and composition requirements are given under different traffic categories in terms of ESAL applications.
  • 79. Traffic Survey Soil Investigation
  • 80.
  • 81. Traffic- As per the IRC:37 design traffic should be 0.1 msa to 2 msa (million standard axles). Weight of commercial vehicle (laden) is considered as 3 tones or more. For design traffic we consider the existing traffic and rate of growth is 6 % consider. Traffic study should be done as per the IRC:37.
  • 82. Road Name - T08 To Rampetdwami Dist – Chhinidwara, Block - Sausar
  • 83.
  • 84.
  • 85. Design Standards for culverts has been prepared based on standard codes and guidelines of IRC: SP: 20: 2002 and similar type of ongoing projects. General features of the designed cross drainage structures are given below: -  Width of Culvert: 7.5 m including thickness of parapet.  Width of Bridge: 6.0 m with parapet.  Invert Level: Fixed 15 cm below existing GL/Drain bed level as shown in drawing.  Finished Level: Top level of culverts generally will match with the finished road level and wherever is not possible the profile will be matched by providing 1 (V): 25 (H).
  • 86. Are constructed to carry traffic over natural waterways that flow below the right of way of the Roads . They also provide the flow of water below the Roads , along the natural channel without disturbing its course. Concern is always to provide adequate size structure (opening is sufficiently large to discharge expected flow of water). Major Structures: Bridges Minor Structures: short-span bridges and culverts
  • 87.  Important to select culvert location (Station no.), alignment, and grade  Location: 1. Bottom of depression where no natural water course exist. 2. Where natural stream intersect the roadway.  Alignment: 1. Conform with natural stream 2. Cross roadway at right angles (economy) 3. Skew culverts are needed sometimes  Grade: 1. Conform to existing grade of stream 2. Reduced grades through culverts…..velocity reduction…..sediments deposition….reduce capacity 3. Increasing culvert grade…..velocity increase…..erosion at outlet and beyond.
  • 88.  Categories: 1- Longitudinal drains:  pipes laid in trenches within the pavement structure and parallel to the center line of the HWY.  Used to lower the water table below the pavement structure .  Used to remove seeping water into the .  When water table is very high, two rows of longitudinal drains can be used. 2- Transverse drains:  Place transversely below the pavement, perpendicular to the center line. 3- Horizontal drains:  Used to relieve pore pressure at slopes of cuts and embankments on the Roads.  Consist of small-diameter perforated pipes inserted into the slopes of the cut or fill
  • 89. Control of groundwater encountered in Roads locations. Purpose: control seepage, lowering ground water table, base and shallow sub grade drains. Circular pipes laid at suitable depth in a trench, which is then backfilled with porous granular material. Pipes materials: Porous concrete, perforated metal, or vitrified clay Slope: steep enough to prevent deposition or setting of materials entering the pipe through joints or perforations. Intercepting drains, lowering water table, and base drainage.
  • 90. 1. Obtain all site data & plot a roadway cross section at the culvert site, including a profile of the stream channel. 2. Establish the culvert elevations, inlets and outlets, and determine culvert length and slope. 3. Select a type and size of culvert. 4. Examine the need for energy dissipaters.
  • 91.  Major Phases 1. Estimate quantity of water that is expected to reach the system. 2. The hydraulic design of each element in the system. 3. The comparison of alternative system to select most economical system.
  • 92. Purpose: To provide a drainage facility or system that will adequately and economically drain the estimated flow throughout the design life without unreasonable risks to the roadway structure or near by property.
  • 93. Estimate of Run Off Existing stream…..use available records. Return Period (RP): Estimated frequency for rare events (floods) (i.e. peak design flow). R P = 50yrs for interstate, = 10 – 25 yrs for streets and roads, and 5 – 10 yrs for light traffic facilities.
  • 94. Flood frequency Statistical based Indicate mean annual flood as a function of the size of the drainage area for each hydrological region. Engineers design drainage facilities to accommodate the peak flow.
  • 95.  Rain fall intensity is function of 1. Duration of rainfall. 2. Occurrence (return period). Note: Small durations provide higher rainfall intensity.  Duration of rainfall is chosen based on the time of concentration
  • 96. Time of concentration: It is the duration of rainfall required to produce the max. rate of run off. Time of concentration = Time of flow (over land + in drainage system) Time of over land flow: time for a water particle to travel from most remote point in drainage area to point where it enters the drainage system. Time of over land flow = F (Slope, type of surface, length,…) Estimates of flow in drainage system can be made from observed or computed velocities of flow.
  • 97. Q = CM 3/4 M = Catchment area in Sq. Km C = Constant varying from 14-19 in MP (Consider C =17) Small bridge-(site length of which exceeds 15 m) was decided & designed after joint visit by STA and S.E. as per SP-20 & SP-13 and relevant IRC Codes for Bridges.
  • 98. V = [R2/3 * S1/2 ]/ n V = Mean Velocity (m/s). R = Hydraulic radius (m) = [Area / wetted perimeter]. S = Slope of channel. n = Manning’s roughness coefficient. Q = A V