Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Fresh concrete
1.
2. Soon after mixing and while it is still workable,
it is said to be Fresh concrete.
Fresh concrete – green concrete, wet concrete
or concrete in plastic state
For good hardened concrete – monitor
workability, bleeding, segregation, desired
compaction.
2
3. Easily mixed and transported
Uniform throughout a given batch and
between batches
Fluidity during transportation
Set in reasonable period of time
Ability to be fully compacted
3
4. Various stages of manufacture of concrete are
Batching
Mixing
Transporting
Placing
Compacting
Curing
Finishing
4
5. Measurement of materials for making
concrete is known as batching.
i) Volume Batching
ii) Weigh Batching
5
6. Not a good method for proportioning –
difficulty it offers to measure granular
material in terms of volume.
Volume of moist sand in loose condition
weighs lesser than volume of dry compacted
sand.
Cement is always measured by weight not in
volume
6
7. Each batch mix – one bag of cement is used
(35 litres)
Gauge box – measuring FA & CA – gauge box
volume is made equal to volume one bag
cement (35 litres)
Gauge box are called as farmas – made of
timber or steel plates
7
8. Water measured – either in kg or vol.-
because two units are same – 1 kg =1 litre.
Quantity of water = W/C ratio X weight of
cement
8
9. Correct method of measuring the materials.
Important concrete - weighing batching
should be used
It facilitates accuracy, flexibility and
simplicity.
Different types of weigh batches are available
based on type of work
9
10. Thorough mixing – production of uniform
concrete
Mixing ensures – concrete to be
homogeneous, uniformity in colour,
consistency
Types of Mixing – Hand Mixing, Machine
Mixing
10
11. Hand mixing – small scale unimportant
concrete works
10% of extra cement is added because mixing
cannot be thorough and efficient
Hand mixing should be done over an
impervious concrete floor
11
12. Two types of machine mixing- Batch mixers
and continuous mixers
Batch mixers – produce concrete batch by
batch with time interval
Continuous mixers – produce concrete
continuously
12
13. Production of concrete at faster rate
Economic
Efficient for larger works
Uniformity in colour and consistency
Better quality
13
17. Process of carrying the concrete from the
place of mixing to place of deposition
Concrete should transported to site without
any segregation and drying
17
18. Concrete should be transported to from work
quickly
Transportation cost – low
Segregation should be prevented
Prevention of drying during hot weather
condition and rain conditions
No water loss during transportation
18
19. Process of depositing the concrete in its
required position
Placing concrete – good quality of surface
19
20. Natural soil – compact the soil, remove
moisture deficiency
Rocky base – side cut in vertical side not in
slopes, remove loose particles
20
21. Reinforcement – properly tied, placed and
proper cover
Correct alignment of form work
Cement slurry leakage
Cleaning and oiling
No addition of water to concrete after placing
21
22. No placing in rainy season
Old surface – made rough, cleaned – placing
new layer of concrete
22
23. Consolidation of concrete – after placing it in
position – Compaction.
Removes air – increases density.
Variation in compaction – concrete porous,
less strength, non – homogeneous.
23
24. Compaction are of two types:
I. Hand Compaction
II. Mechanical Compaction
24
25. Ramming the concrete manually.
Used – ordinary and unimportant structures.
Low strength – because of higher W/c ratio.
25
29. Compaction – with machines – vibrator.
Used – mixes – low W/C ratio.
Reduces friction – Between particles
29
30. Better Finish and better quality.
Improves bond – steel and concrete.
Reduces creep and shrinkage.
Reduces compaction time.
Speed of placing concrete increases.
30
31. Internal Vibrator – “Immersion Vibrator” –
common type – direct contact with concrete.
Operated – petrol or electricity.
Needle diameter – 20mm to 75mm.
Length – 250mm to 900mm.
Frequency – 6000 to 12000 cycles/ min.
Period of vibration – 30 sec to 2 min.
31
33. Form Vibrator – External Vibrators – less
effective – consume more power.
Uses – thin sections, heavy reinforcement.
Compaction of stiff concrete.
Frequency – 3000 to 9000 cycles/ min.
Period of vibration – 1 to 2 min.
33
34. Surface Vibrator –Surface vibration.
Uses – roof slabs, road pavements.
Frequency – 4000 cycles/ min.
Not effective beyond 150 mm depth.
34
38. Form work –strong.
Concrete laying – 150 to 600 mm – to avoid
air trapping.
Vertical insertion of vibrators.
Remove vibrator – appearance of mortar on
the surface.
38
39. Do not touch the form work with vibrators.
Don’t use vibrators for long time.
Vibrators used only for compaction – not for
pushing – leads to segregation.
39
40. Creating an environment – setting and
hardening.
Desirable conditions – suitable temperature,
controls rate of hydration and water.
40
41. Prevent loss of water by evaporation.
To supplement water consumed in heat of
hydration.
41
42. Maintains hydration – prevents loss of water
by evaporation.
Reduces shrinkage.
Preserve the properties of concrete.
Increases Impermeability and durability.
Maintains uniform temperature.
42
46. Immersion - Prefabricated elements –
immersed in water tank.
Precast elements – concrete poles, man hole
covers, pipes etc – cured in tanks.
Ponding – surface members – pavements,
floors, roofs, slabs etc.
Small water retaining material – perimeter of
surface.
46
47. The enclosed area – divided into smaller
rectangles – flooded with water – 2 to 3
times a day.
Sprinkling – spraying of water – very
efficient – less water demand.
Uses – floor slab, plastered surface,
columns and piers.
47
54. Steam curing – two favourable conditions –
concrete subjected to high temperature and
maintains the wetness in concrete.
Strength development – very rapid.
Steam curing – at atmospheric pressure or
under pressure.
54
55. 1 day steam curing concrete = 28 day normal
curing concrete.
Steam Curing – employed to achieve 50 -70%
of strength.
Followed by 7 days curing atleast.
Uses – Precast prestressed concrete sleepers
and bridge girders.
55
57. Low Pressure Steam Curing
I. Steam curing – atmospheric pressure.
II. Can be continuous or intermittent.
High Pressure Steam Curing
I. Cylindrical chambers used – Autoclave.
I. Exhibits higher strength and durabillity.
57
58. Calcium chloride – coating material and
admixtures.
Obsorbs moisture – retains on concrete
surface.
reduces evaporation – increases rate of
hydration.
58
59. Curing method – providing moisture from within
the concrete.
LWA – ability to retain water – additional moisture
to concrete.
For lower W/C ratio (0.3) – around 60 – 180
kg/m3 of LWA – provide additional moisture-
increase in strength and durability.
Internal moist curing accompanied by external
curing method
59
60. Do’s
Use fresh cement.
Well graded aggregates.
Concreting – skilled supervision.
Concreting – man power, equipment and
tools.
Favourable weather conditions.
60
61. Suitable mix.
Use water free from impurities.
Do slump testing before concreting.
Verify – site conditions, reinforcement covers
etc..
Concrete – place within 15 – 20 min after adding
water.
61
62. Proper compaction.
Check the stability of form work frequently.
Proper finishing at joints.
Attention towards bleeding.
Proper curing.
62
63. Don’ts
No damage form work.
No unwashed aggregates.
No volumetric batching.
63
64. No addition of water while concreting for easy
placements.
No semi dry concrete – honey comb.
Don’t drop concrete from greater heights –
segregation.
No early removal of form work.
No concreting during rain.
64
65. Concrete placed in massive structures like dams,
bridge piers etc. – mass concrete.
Low slump – stiffer concrete.
Main problem in mass concrete – heat of hydration.
Excessive heat leads to shrinkage cracks.
Low heat cement used – prevents shrinkage cracks.
Continuous curing.
65
66. Placing the concrete in small lifts.
Concreting is done in winter.
Cast concrete should be cured in cold water.
66
68. Property determining the effort required
manipulate a freshly mixed quantity of
concrete with minimum loss of homogeneity.
68
69. Water Content – higher water content higher
fluidity.
Mix Proportion
Size of aggregates –Bigger the size – lesser
surface area – requires less water to wet the
surface – higher workability.
Shape of aggregates – angular or flaky
aggregates – harsh conncrete
69
70. Surface texture of aggregates - rough surface
– poor workability – smooth surface – better
workability.
Grading of aggregates – well graded – lesser
voids- higher workability.
Use of Admixtures – improves the workability.
Temperature – increases – workability
decreases.
70
71. Slump test
Compaction Factor test
Vee – Bee consistometer test
Flow test
71
72. Most widely used method to determine the
workability.
Suitable – for medium workability concrete
mix – not for very wet or very dry mix.
72
74. Mould - Internal surface is cleaned.
Mould is placed over a smooth, horizontal and
non – absorbent surface.
Concrete is filled in 4 layers – 25 tamps each.
Remove mould by lifting slowly – subside of
concrete is called slump.
Height of mould – height of subside concrete =
SLUMP taken in “mm”
74
75. More efficient than slump test
Suitable for very low workability concrete.
C.F = W/W’
75
77. Fill the hopper A by concrete at top.
Opening the trap door of hopper A concrete
allowed to fall to hopper B.
Opening the trap door of hopper B concrete
allowed to fall to cylinder C.
Take weight of the concrete “W”.
Now compact the concrete in cylinder in
layers to achieve full compaction. Let the
weight be “W’”.
77
80. Separation of coarse aggregate from mortar
resulting in their non-uniform distribution
difference in size of particles and in specific
gravity of constituents – prime cause
Separation of CA from mortar leaves voids in
CA unfilled and it is called as
“Honeycombing”
80
83. Improper mix proportioning
Dropping concrete from greater heights
Over compaction
Leakage of mortar through form works
Too vibratory or too long transportation
methods
83
84. Proper grading of aggregates
Strict supervision – all concrete activities
Restricting height of pour
Optimum usage of water in mixing
Reducing continuous vibration for long time
Adding air entraing agents – reduces water usage
84
85. Also known as ‘Water Gain’
Rise of water with cement particles to the
surface of freshly laid concrete –Bleeding
More water than required – solid constituents
are able to hold all mixing water
Result – porous, weak, non-durable concrete
85
87. Excess of water
Deficient of FA in mix
Over compacting
87
88. Controlling the water content
Using finely ground cement
Controlled compaction
88
89. Consistence – describes how stiff or runny.
Soft enough to work with it- not too wet
Indicator of workability
Every batch of concrete – consistent quality –
achieved by using same materials for all
batches
89
90. Ease with which concrete can flow into the
formwork around steel, ability to be moulded.
Depends on type of formwork, arrangement
of steel, time lag b/w mixing and pouring
90
91. Ease with which concrete can be compacted
Compactability depends – amount, che.
Composition of cement, amount of water,
grade & shape of aggregates etc.
Addition of admixture – increases
compactability without increase in slump
91