SlideShare a Scribd company logo
1 of 27
Download to read offline
INFRASTRUCTURE PROJECTS UPDATE
Golf CourseArea Status: Progress: Next Step
Golf Course Holes
10,11,12,13,14,15,16, 17
& 18
• Continuous maintenance of the back nine holes ongoing
• Construction of golf cart ramp outstanding; to be completed
by Lexis on resuming works
•Continuous maintenance
•Complete construction of
hole 14 golf cart ramp on
return of the boundary wall
contractor on site.
Boundary Wall
Area Status: Progress: Next Step
Entrance Walling Clear View
•Walling at 99% complete; painting of grille outstanding
Double Masonry Wall
•Construction Complete; backfilling almost done to the
ngurunga gate
Mitini & Ngurunga Walling
•Fixing of the sliding gates to the
clear view wall
Status: Progress Summary
A. Entrance Walling:
Clear View and
Double Masonry
Walling Dashboard
• Actual Progress – 97% Complete
Double Masonary
Wall
Clear View Wall
LEGEND
Boundary Wall
Area Status: Progress: Next Step
Entrance
Walling
Sentry Box
•Construction of sentry box on going; internal plaster & fixing of
windows complete
Guard House
•Construction ongoing; 70% complete – plastering of internal
walls and fixing of windows complete.
•Construction of the turnstile houses ongoing
Gates
Erection of the gates along the wall ongoing; works at 90%
complete
•Fixing of windows and doors to sentry
boxes and guard house
•Finishes to sentry box and guard house
Road Works
Area Status: Progress: Next Step
Road
A100
1+741
• Overall completion – 96%
•Snagging and construction of culvert headwalls and storm water drainage
manholes
•Clearing/cleaning up and repairs of defective works ongoing
•Sectional Handover
Kerbs & Channels
Hardcore
LEGEND
Earthworks
Area Status: Progress Summary
Phase 1
Summary
•Actual Progress – 96% Complete
Road Works
Road WorksArea Status: Progress: Next Step
Road D100
1+467
• Overall Completion – 70%
•Earthworks to subgrade levels complete;
•Construction of culvert crossings complete
•Hand packing of hard core 50% complete
• Finish laying and hunching of
kerbs and channels
•Storm water drains construction
•Hand packing of hard core
Road Works
Area Status: Progress: Next Step
Road D101
1+156 M
•Overall Construction – 60 %
• Earthworks 97% complete; pending section at the main dam
crossing
•Laying of kerbs and channels 45% complete
•Construction of culvert crossings complete; storm water drains
construction ongoing
•Laying and hunching of kerbs and
channels
• Stone pitching for storm water drains
Bulk Earthworks ongoing
LEGEND
Road Works
Area Status: Progress: Next Step
Road D102,
D103, D104,
D105
1+216 M
• Overall Construction – 60 %
• Earthworks 85% complete; pending section at the box culvert
crossing
•Construction of box culvert next to hole 14 ongoing
•Laying of kerbs and channels 40% complete
•Construction of culvert crossings complete; storm water drains
construction ongoing
•Completion of Earthworks
•Laying and hunching of kerbs and
channels
•Stone pitching for storm water drains
Bulk Earthworks ongoing
LEGEND
Electric Fence
Status: Progress Summary
A. Electric Fence:
Southern Boundary &
Northern Boundary
Dashboard
• Actual Progress – 90% Complete
Southern Boundary
Northern
Boundary
Mitini Scapes
LEGEND
Electric Fence
Area Status: Progress: Next Step
Section 1:
Southern
Boundary &
Mitini Section
Overall Progress – 98% against projected progress of 100%
•Clearance and restraining of the fence line complete
• Laying of power cables for powering the line complete; Energizing
complete
•Testing and commissioning of
fence
•Continuous maintenance of
the fence line
Section 2:
Northern
Boundary
Overall Progress – 95% against projected progress of 100%
•Erection of the poles and wiring complete on the northern side – 100%
complete;
•Erection of solar panel complete and energizers delivered to site
•Powering to be done on completion of the northern sentry box
•Energizing the fence
Section 3:
Along Moru
Ridge
Progress – 95%
•Erection of the poles and wiring – 100% complete;
•Erection of solar panel complete; powering of fence to be done on
completion of the corner sentry in hole 14
• Energizing of the fence
Electric Fence
Water Supply
Area Status: Progress: Next Step
Water Reticulation –
Phase 1
•Overall Progress – 85% against projected progress of 100%
Completion
•Excavation of 21 Km of the pipe line (110mm, 80mm &
63mm) complete - along road A100,D100, D200, D300,
D400, D500, D600, D601, C100; E200,
•Laying of pipes ongoing subsequent with the trenching; 18
Km HDPE pipes laid
•Trenching for water lines and
laying of water lines
Water Supply
Remaining Water Lines
Trenched Water Lines
LEGEND
Infrastructure Update
Area Status: Progress: Next Step
Golf Course
Irrigation
Pump
•Pump already delivered to the irrigation contractor, installation to
commence on completion of the pump house construction
•Working with the irrigation contractor to construct the pump house
•Pump house construction
Sewer
Treatment
Plant
•Sewer treatment plant already delivered to site; Part installation
complete; awaiting fixing of control panel
•Construction of the control room to commence on agreement
with the lexis international
• Complete installation of the
plant control panel
•Testing and commissioning of
plant
Power Supply • Power supply to sewer treatment plant complete together with
installation of the distribution board
• Power supply works to plot G722 ongoing; erection and pulling of LV
lines complete;
•Installation of transformer complete, request for quotation from
Mehta electrical to install a high mast security light along the
northern boundary
•Installation of security light along
northern boundary
Cabbro sample 40sqm to specification
Wadi Degla
• We are pleased to inform you that Migaa has entered into a partnership
with the Egyptian conglomerate Wadi Degla Holdings through their local
subsidiary Wadi Degla Investment (K) ltd.
• The agreement between Migaa and Wadi Degla involves development of
the remaining front nine holes of Migaa 18 hole championship golf course,
Sports Facilities, Club House and management of the golf course to serve
the residents of Migaa.
• Each Migaa plot owner or unit owner will get a free Wadi Degla
membership and will have a chance to reciprocate to any other Wadi
Degla branches both locally and abroad and shall have rights to the
facilities managed by Wadi Degla anywhere in the world.
• Wadi Degla is expected to complete construction within 12 months after
commencement.
Wadi Degla
• Proposed Club House Phase 1
Wadi Degla
• Proposed Club House Phase 2
Wadi Degla
• Proposed Sports Facilities
MITINI SCAPES
• The completed Phase 1 comprises of 82 units; 12
cottages and 70 apartments and sits on
approximately 6 acres.
• Currently we have 4 residents who are already
residing.
Progress
PROGRESS UPDATE
Contemporary Chic Modern
CONSTRUCTION UPDATE
Overall Project Progress 42%
Projected completion date 31st December 2016
Block 4
•Internal Plaster for ground ,1st , 2nd & 3rd Floor
85% Complete while 4th , 5th & 6th Floor 75%
Complete.
•External Cladding 75% Complete.
•Roofing Works 70% Complete.
PROGRESS UPDATE
Contemporary Chic Modern
Block 1(IPL Block)
• 7th Slab Complete.
•Internal Plaster for ground ,1st , 2nd & 3rd
Floor 85% Complete while 4th & 5th is at
50% Complete.
•External Plaster 70% Complete.
PROGRESS UPDATE
Contemporary Chic Modern
Block 2
• 7th floor slab complete.
•Internal Plaster for ground, 1st & 2nd
floor 65% Complete.
•External Plaster 50% Complete
PROGRESS UPDATE
Contemporary Chic Modern
Block 3
•4th Floor Slab 60% Complete.
•Internal Plaster works in ground floor
80% Complete.
SHOW APARTMENT PROGRESS PHOTOS
Contemporary Chic Modern
Show Apartment Remaining Items
• (OS & E) Operating Supplies and
Equipments and (FF& E) Furniture
Fixtures and Equipments.

More Related Content

What's hot

Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Crosstown TO
 
Yuhua 5-Year Master Plan (2016 -2020)
Yuhua 5-Year Master Plan (2016 -2020)Yuhua 5-Year Master Plan (2016 -2020)
Yuhua 5-Year Master Plan (2016 -2020)ChowKinFai
 
Meeting of the Verdun / Le Sud Ouest - good neighbourly relations committee ...
Meeting of the Verdun / Le Sud Ouest -  good neighbourly relations committee ...Meeting of the Verdun / Le Sud Ouest -  good neighbourly relations committee ...
Meeting of the Verdun / Le Sud Ouest - good neighbourly relations committee ...Pont Samuel-De Champlain Bridge
 
Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019Crosstown TO
 
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017Fairfax County
 
November 10, 2014 Parkmerced Transition and Vision Update
November 10, 2014 Parkmerced Transition and Vision UpdateNovember 10, 2014 Parkmerced Transition and Vision Update
November 10, 2014 Parkmerced Transition and Vision Updateparkmercedvision
 
West Ox DVS Maintenance Facility Ugrades
West Ox DVS Maintenance Facility UgradesWest Ox DVS Maintenance Facility Ugrades
West Ox DVS Maintenance Facility UgradesFairfax County
 
Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020
Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020
Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020Fairfax County
 
Emergency Repair of Sanitary Sewer Line Crossing Lake Thoreau January 2016
Emergency Repair of Sanitary Sewer Line Crossing Lake Thoreau January 2016Emergency Repair of Sanitary Sewer Line Crossing Lake Thoreau January 2016
Emergency Repair of Sanitary Sewer Line Crossing Lake Thoreau January 2016Fairfax County
 
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...Pont Samuel-De Champlain Bridge
 
AllenCon Capability
AllenCon CapabilityAllenCon Capability
AllenCon CapabilityDamien Allen
 
Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November  Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November Crosstown TO
 
DJC Top Projects 2015 - Breathe Building Project Description - Final
DJC Top Projects 2015 - Breathe Building Project Description - FinalDJC Top Projects 2015 - Breathe Building Project Description - Final
DJC Top Projects 2015 - Breathe Building Project Description - FinalChris Humphries
 
Kevin Quigley Portfolio Condensed
Kevin Quigley Portfolio CondensedKevin Quigley Portfolio Condensed
Kevin Quigley Portfolio Condensedkevin quigley
 
Affordable housing in Gurgaon
Affordable housing in GurgaonAffordable housing in Gurgaon
Affordable housing in GurgaonTapeventsggn
 
Walking Mountains Science Center - LEED Platinum in a Small Mountain Town
Walking Mountains Science Center - LEED Platinum in a Small Mountain TownWalking Mountains Science Center - LEED Platinum in a Small Mountain Town
Walking Mountains Science Center - LEED Platinum in a Small Mountain TownBrian Sipes
 
Brossard Good Neighbourly Relations Committee - May 17, 2017
Brossard Good Neighbourly Relations Committee - May 17, 2017Brossard Good Neighbourly Relations Committee - May 17, 2017
Brossard Good Neighbourly Relations Committee - May 17, 2017Pont Samuel-De Champlain Bridge
 

What's hot (19)

Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
 
Yuhua 5-Year Master Plan (2016 -2020)
Yuhua 5-Year Master Plan (2016 -2020)Yuhua 5-Year Master Plan (2016 -2020)
Yuhua 5-Year Master Plan (2016 -2020)
 
Meeting of the Verdun / Le Sud Ouest - good neighbourly relations committee ...
Meeting of the Verdun / Le Sud Ouest -  good neighbourly relations committee ...Meeting of the Verdun / Le Sud Ouest -  good neighbourly relations committee ...
Meeting of the Verdun / Le Sud Ouest - good neighbourly relations committee ...
 
Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019
 
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
Hayfield Road Project Citizens Association Meeting Oct. 18, 2017
 
Northpoint Crossing Rezoning
Northpoint Crossing RezoningNorthpoint Crossing Rezoning
Northpoint Crossing Rezoning
 
November 10, 2014 Parkmerced Transition and Vision Update
November 10, 2014 Parkmerced Transition and Vision UpdateNovember 10, 2014 Parkmerced Transition and Vision Update
November 10, 2014 Parkmerced Transition and Vision Update
 
site proj 1
site proj 1site proj 1
site proj 1
 
West Ox DVS Maintenance Facility Ugrades
West Ox DVS Maintenance Facility UgradesWest Ox DVS Maintenance Facility Ugrades
West Ox DVS Maintenance Facility Ugrades
 
Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020
Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020
Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020
 
Emergency Repair of Sanitary Sewer Line Crossing Lake Thoreau January 2016
Emergency Repair of Sanitary Sewer Line Crossing Lake Thoreau January 2016Emergency Repair of Sanitary Sewer Line Crossing Lake Thoreau January 2016
Emergency Repair of Sanitary Sewer Line Crossing Lake Thoreau January 2016
 
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...
Meeting of the verdun le sud ouest good neighbourly relations committee - Apr...
 
AllenCon Capability
AllenCon CapabilityAllenCon Capability
AllenCon Capability
 
Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November  Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November
 
DJC Top Projects 2015 - Breathe Building Project Description - Final
DJC Top Projects 2015 - Breathe Building Project Description - FinalDJC Top Projects 2015 - Breathe Building Project Description - Final
DJC Top Projects 2015 - Breathe Building Project Description - Final
 
Kevin Quigley Portfolio Condensed
Kevin Quigley Portfolio CondensedKevin Quigley Portfolio Condensed
Kevin Quigley Portfolio Condensed
 
Affordable housing in Gurgaon
Affordable housing in GurgaonAffordable housing in Gurgaon
Affordable housing in Gurgaon
 
Walking Mountains Science Center - LEED Platinum in a Small Mountain Town
Walking Mountains Science Center - LEED Platinum in a Small Mountain TownWalking Mountains Science Center - LEED Platinum in a Small Mountain Town
Walking Mountains Science Center - LEED Platinum in a Small Mountain Town
 
Brossard Good Neighbourly Relations Committee - May 17, 2017
Brossard Good Neighbourly Relations Committee - May 17, 2017Brossard Good Neighbourly Relations Committee - May 17, 2017
Brossard Good Neighbourly Relations Committee - May 17, 2017
 

Similar to Migaa progress update september 2016-1

East Virtual Open House
East Virtual Open HouseEast Virtual Open House
East Virtual Open HouseCrosstown TO
 
Virtual Open House: Eastern Works
Virtual Open House: Eastern WorksVirtual Open House: Eastern Works
Virtual Open House: Eastern WorksCrosstown TO
 
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020Crosstown TO
 
Powerpoint - Langley School Pump Station and Force Main Project
Powerpoint  -  Langley School Pump Station and Force Main ProjectPowerpoint  -  Langley School Pump Station and Force Main Project
Powerpoint - Langley School Pump Station and Force Main ProjectFairfax County
 
Addison Capital Projects Update
Addison Capital Projects UpdateAddison Capital Projects Update
Addison Capital Projects UpdateTownofAddison
 
Final central east open house oct282020
Final central east open house oct282020Final central east open house oct282020
Final central east open house oct282020Crosstown TO
 
Eastern Virtual Open House Deck
Eastern Virtual Open House DeckEastern Virtual Open House Deck
Eastern Virtual Open House DeckCrosstown TO
 
Pardon Our Thunderdust 2011-2012
Pardon Our Thunderdust 2011-2012Pardon Our Thunderdust 2011-2012
Pardon Our Thunderdust 2011-2012richlandcollegetx
 
West works open house deck March 12 2020
West works open house deck   March 12 2020 West works open house deck   March 12 2020
West works open house deck March 12 2020 Crosstown TO
 
JAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE NavyJAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE NavyMike Bisland
 
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue StationsFall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue StationsCrosstown TO
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Crosstown TO
 
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017Crosstown TO
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...Crosstown TO
 
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Leaside - Laird Construction Liaison Committee Meeting  - July 2017Leaside - Laird Construction Liaison Committee Meeting  - July 2017
Leaside - Laird Construction Liaison Committee Meeting - July 2017Crosstown TO
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)Crosstown TO
 
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Crosstown TO
 
Western works final
Western works final Western works final
Western works final Crosstown TO
 

Similar to Migaa progress update september 2016-1 (20)

Uniworld garden-2 up date
Uniworld garden-2 up dateUniworld garden-2 up date
Uniworld garden-2 up date
 
East Virtual Open House
East Virtual Open HouseEast Virtual Open House
East Virtual Open House
 
Virtual Open House: Eastern Works
Virtual Open House: Eastern WorksVirtual Open House: Eastern Works
Virtual Open House: Eastern Works
 
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
 
Monthly Progress Report - September 2014
Monthly Progress Report - September 2014Monthly Progress Report - September 2014
Monthly Progress Report - September 2014
 
Powerpoint - Langley School Pump Station and Force Main Project
Powerpoint  -  Langley School Pump Station and Force Main ProjectPowerpoint  -  Langley School Pump Station and Force Main Project
Powerpoint - Langley School Pump Station and Force Main Project
 
Addison Capital Projects Update
Addison Capital Projects UpdateAddison Capital Projects Update
Addison Capital Projects Update
 
Final central east open house oct282020
Final central east open house oct282020Final central east open house oct282020
Final central east open house oct282020
 
Eastern Virtual Open House Deck
Eastern Virtual Open House DeckEastern Virtual Open House Deck
Eastern Virtual Open House Deck
 
Pardon Our Thunderdust 2011-2012
Pardon Our Thunderdust 2011-2012Pardon Our Thunderdust 2011-2012
Pardon Our Thunderdust 2011-2012
 
West works open house deck March 12 2020
West works open house deck   March 12 2020 West works open house deck   March 12 2020
West works open house deck March 12 2020
 
JAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE NavyJAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE Navy
 
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue StationsFall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2017
 
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
Chaplin - Avenue Construction Liaison Committee Meeting - June 2017
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
 
Leaside - Laird Construction Liaison Committee Meeting - July 2017
Leaside - Laird Construction Liaison Committee Meeting  - July 2017Leaside - Laird Construction Liaison Committee Meeting  - July 2017
Leaside - Laird Construction Liaison Committee Meeting - July 2017
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
 
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017
 
Western works final
Western works final Western works final
Western works final
 

Recently uploaded

Low Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In Delhi
Low Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In DelhiLow Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In Delhi
Low Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In Delhiasmaqueen5
 
TENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports Work
TENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports WorkTENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports Work
TENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports WorkTurbo Tenant
 
2k Shot Call girls Aiims Delhi 9205541914
2k Shot Call girls Aiims Delhi 92055419142k Shot Call girls Aiims Delhi 9205541914
2k Shot Call girls Aiims Delhi 9205541914Delhi Call girls
 
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️soniya singh
 
Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...
Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...
Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...ApartmentWala1
 
2k Shots ≽ 9205541914 ≼ Call Girls In Sainik Farm (Delhi)
2k Shots ≽ 9205541914 ≼ Call Girls In Sainik Farm (Delhi)2k Shots ≽ 9205541914 ≼ Call Girls In Sainik Farm (Delhi)
2k Shots ≽ 9205541914 ≼ Call Girls In Sainik Farm (Delhi)Delhi Call girls
 
Premium Villa Projects in Sarjapur Road Bengaluru
Premium Villa Projects in Sarjapur Road BengaluruPremium Villa Projects in Sarjapur Road Bengaluru
Premium Villa Projects in Sarjapur Road BengaluruShivaSeo3
 
Properties for Sale in Istanbul with Schools and Parks | Antalya Development
Properties for Sale in Istanbul with Schools and Parks | Antalya DevelopmentProperties for Sale in Istanbul with Schools and Parks | Antalya Development
Properties for Sale in Istanbul with Schools and Parks | Antalya DevelopmentAntalya Development
 
9990771857 Call Girls in Dwarka Sector 7 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 7 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 7 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 7 Delhi (Call Girls) Delhidelhimodel235
 
Greater Vancouver Realtors Statistics Package April 2024
Greater Vancouver Realtors Statistics Package April 2024Greater Vancouver Realtors Statistics Package April 2024
Greater Vancouver Realtors Statistics Package April 2024VickyAulakh1
 
2k Shot Call girls Karol Bagh Delhi 9205541914
2k Shot Call girls Karol Bagh Delhi 92055419142k Shot Call girls Karol Bagh Delhi 9205541914
2k Shot Call girls Karol Bagh Delhi 9205541914Delhi Call girls
 
M3M 129 E Brochure Noida Expressway, Sector 129, Noida
M3M 129 E Brochure Noida Expressway, Sector 129, NoidaM3M 129 E Brochure Noida Expressway, Sector 129, Noida
M3M 129 E Brochure Noida Expressway, Sector 129, Noidasarak0han45400
 
Call girls in new Ashok NagarDelhi꧁ 8447779280꧂ Escort Service Women Seeking ...
Call girls in new Ashok NagarDelhi꧁ 8447779280꧂ Escort Service Women Seeking ...Call girls in new Ashok NagarDelhi꧁ 8447779280꧂ Escort Service Women Seeking ...
Call girls in new Ashok NagarDelhi꧁ 8447779280꧂ Escort Service Women Seeking ...asmaqueen5
 
Call Girls In Mayur Vihar Delhi ☆↫8447779280 ❤Escorts Service In Delhi
Call Girls In Mayur Vihar Delhi ☆↫8447779280 ❤Escorts Service In DelhiCall Girls In Mayur Vihar Delhi ☆↫8447779280 ❤Escorts Service In Delhi
Call Girls In Mayur Vihar Delhi ☆↫8447779280 ❤Escorts Service In Delhiasmaqueen5
 
9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhi
9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhi9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhi
9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhidelhimodel235
 
BDSM⚡Call Girls in Sector 57 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 57 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 57 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 57 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
Mahindra Happinest Tathawade Pune Brochure.pdf
Mahindra Happinest Tathawade Pune Brochure.pdfMahindra Happinest Tathawade Pune Brochure.pdf
Mahindra Happinest Tathawade Pune Brochure.pdfBabyrudram
 
9990771857 Call Girls in Dwarka Sector 3 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 3 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 3 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 3 Delhi (Call Girls) Delhidelhimodel235
 
M3M The Line Brochure - Premium Investment Opportunity for Commercial Ventures
M3M The Line Brochure - Premium Investment Opportunity for Commercial VenturesM3M The Line Brochure - Premium Investment Opportunity for Commercial Ventures
M3M The Line Brochure - Premium Investment Opportunity for Commercial Venturessheltercareglobal
 
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhidelhimodel235
 

Recently uploaded (20)

Low Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In Delhi
Low Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In DelhiLow Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In Delhi
Low Rate ↬Call Girls in Trilokpuri Delhi ↫8447779280}Escorts Service In Delhi
 
TENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports Work
TENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports WorkTENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports Work
TENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports Work
 
2k Shot Call girls Aiims Delhi 9205541914
2k Shot Call girls Aiims Delhi 92055419142k Shot Call girls Aiims Delhi 9205541914
2k Shot Call girls Aiims Delhi 9205541914
 
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️
call girls in ganesh nagar Delhi 8264348440 ✅ call girls ❤️
 
Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...
Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...
Best Deal Virtual Space in Satya The Hive Tata Zudio 750 Sqft 1.89 Cr All inc...
 
2k Shots ≽ 9205541914 ≼ Call Girls In Sainik Farm (Delhi)
2k Shots ≽ 9205541914 ≼ Call Girls In Sainik Farm (Delhi)2k Shots ≽ 9205541914 ≼ Call Girls In Sainik Farm (Delhi)
2k Shots ≽ 9205541914 ≼ Call Girls In Sainik Farm (Delhi)
 
Premium Villa Projects in Sarjapur Road Bengaluru
Premium Villa Projects in Sarjapur Road BengaluruPremium Villa Projects in Sarjapur Road Bengaluru
Premium Villa Projects in Sarjapur Road Bengaluru
 
Properties for Sale in Istanbul with Schools and Parks | Antalya Development
Properties for Sale in Istanbul with Schools and Parks | Antalya DevelopmentProperties for Sale in Istanbul with Schools and Parks | Antalya Development
Properties for Sale in Istanbul with Schools and Parks | Antalya Development
 
9990771857 Call Girls in Dwarka Sector 7 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 7 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 7 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 7 Delhi (Call Girls) Delhi
 
Greater Vancouver Realtors Statistics Package April 2024
Greater Vancouver Realtors Statistics Package April 2024Greater Vancouver Realtors Statistics Package April 2024
Greater Vancouver Realtors Statistics Package April 2024
 
2k Shot Call girls Karol Bagh Delhi 9205541914
2k Shot Call girls Karol Bagh Delhi 92055419142k Shot Call girls Karol Bagh Delhi 9205541914
2k Shot Call girls Karol Bagh Delhi 9205541914
 
M3M 129 E Brochure Noida Expressway, Sector 129, Noida
M3M 129 E Brochure Noida Expressway, Sector 129, NoidaM3M 129 E Brochure Noida Expressway, Sector 129, Noida
M3M 129 E Brochure Noida Expressway, Sector 129, Noida
 
Call girls in new Ashok NagarDelhi꧁ 8447779280꧂ Escort Service Women Seeking ...
Call girls in new Ashok NagarDelhi꧁ 8447779280꧂ Escort Service Women Seeking ...Call girls in new Ashok NagarDelhi꧁ 8447779280꧂ Escort Service Women Seeking ...
Call girls in new Ashok NagarDelhi꧁ 8447779280꧂ Escort Service Women Seeking ...
 
Call Girls In Mayur Vihar Delhi ☆↫8447779280 ❤Escorts Service In Delhi
Call Girls In Mayur Vihar Delhi ☆↫8447779280 ❤Escorts Service In DelhiCall Girls In Mayur Vihar Delhi ☆↫8447779280 ❤Escorts Service In Delhi
Call Girls In Mayur Vihar Delhi ☆↫8447779280 ❤Escorts Service In Delhi
 
9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhi
9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhi9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhi
9990771857 Call Girls Dwarka Sector 9 Delhi (Call Girls ) Delhi
 
BDSM⚡Call Girls in Sector 57 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 57 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 57 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 57 Noida Escorts >༒8448380779 Escort Service
 
Mahindra Happinest Tathawade Pune Brochure.pdf
Mahindra Happinest Tathawade Pune Brochure.pdfMahindra Happinest Tathawade Pune Brochure.pdf
Mahindra Happinest Tathawade Pune Brochure.pdf
 
9990771857 Call Girls in Dwarka Sector 3 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 3 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 3 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 3 Delhi (Call Girls) Delhi
 
M3M The Line Brochure - Premium Investment Opportunity for Commercial Ventures
M3M The Line Brochure - Premium Investment Opportunity for Commercial VenturesM3M The Line Brochure - Premium Investment Opportunity for Commercial Ventures
M3M The Line Brochure - Premium Investment Opportunity for Commercial Ventures
 
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
 

Migaa progress update september 2016-1

  • 2. Golf CourseArea Status: Progress: Next Step Golf Course Holes 10,11,12,13,14,15,16, 17 & 18 • Continuous maintenance of the back nine holes ongoing • Construction of golf cart ramp outstanding; to be completed by Lexis on resuming works •Continuous maintenance •Complete construction of hole 14 golf cart ramp on return of the boundary wall contractor on site.
  • 3. Boundary Wall Area Status: Progress: Next Step Entrance Walling Clear View •Walling at 99% complete; painting of grille outstanding Double Masonry Wall •Construction Complete; backfilling almost done to the ngurunga gate Mitini & Ngurunga Walling •Fixing of the sliding gates to the clear view wall Status: Progress Summary A. Entrance Walling: Clear View and Double Masonry Walling Dashboard • Actual Progress – 97% Complete Double Masonary Wall Clear View Wall LEGEND
  • 4. Boundary Wall Area Status: Progress: Next Step Entrance Walling Sentry Box •Construction of sentry box on going; internal plaster & fixing of windows complete Guard House •Construction ongoing; 70% complete – plastering of internal walls and fixing of windows complete. •Construction of the turnstile houses ongoing Gates Erection of the gates along the wall ongoing; works at 90% complete •Fixing of windows and doors to sentry boxes and guard house •Finishes to sentry box and guard house
  • 5. Road Works Area Status: Progress: Next Step Road A100 1+741 • Overall completion – 96% •Snagging and construction of culvert headwalls and storm water drainage manholes •Clearing/cleaning up and repairs of defective works ongoing •Sectional Handover Kerbs & Channels Hardcore LEGEND Earthworks Area Status: Progress Summary Phase 1 Summary •Actual Progress – 96% Complete
  • 7. Road WorksArea Status: Progress: Next Step Road D100 1+467 • Overall Completion – 70% •Earthworks to subgrade levels complete; •Construction of culvert crossings complete •Hand packing of hard core 50% complete • Finish laying and hunching of kerbs and channels •Storm water drains construction •Hand packing of hard core
  • 8. Road Works Area Status: Progress: Next Step Road D101 1+156 M •Overall Construction – 60 % • Earthworks 97% complete; pending section at the main dam crossing •Laying of kerbs and channels 45% complete •Construction of culvert crossings complete; storm water drains construction ongoing •Laying and hunching of kerbs and channels • Stone pitching for storm water drains Bulk Earthworks ongoing LEGEND
  • 9. Road Works Area Status: Progress: Next Step Road D102, D103, D104, D105 1+216 M • Overall Construction – 60 % • Earthworks 85% complete; pending section at the box culvert crossing •Construction of box culvert next to hole 14 ongoing •Laying of kerbs and channels 40% complete •Construction of culvert crossings complete; storm water drains construction ongoing •Completion of Earthworks •Laying and hunching of kerbs and channels •Stone pitching for storm water drains Bulk Earthworks ongoing LEGEND
  • 10. Electric Fence Status: Progress Summary A. Electric Fence: Southern Boundary & Northern Boundary Dashboard • Actual Progress – 90% Complete Southern Boundary Northern Boundary Mitini Scapes LEGEND
  • 11. Electric Fence Area Status: Progress: Next Step Section 1: Southern Boundary & Mitini Section Overall Progress – 98% against projected progress of 100% •Clearance and restraining of the fence line complete • Laying of power cables for powering the line complete; Energizing complete •Testing and commissioning of fence •Continuous maintenance of the fence line Section 2: Northern Boundary Overall Progress – 95% against projected progress of 100% •Erection of the poles and wiring complete on the northern side – 100% complete; •Erection of solar panel complete and energizers delivered to site •Powering to be done on completion of the northern sentry box •Energizing the fence Section 3: Along Moru Ridge Progress – 95% •Erection of the poles and wiring – 100% complete; •Erection of solar panel complete; powering of fence to be done on completion of the corner sentry in hole 14 • Energizing of the fence
  • 13. Water Supply Area Status: Progress: Next Step Water Reticulation – Phase 1 •Overall Progress – 85% against projected progress of 100% Completion •Excavation of 21 Km of the pipe line (110mm, 80mm & 63mm) complete - along road A100,D100, D200, D300, D400, D500, D600, D601, C100; E200, •Laying of pipes ongoing subsequent with the trenching; 18 Km HDPE pipes laid •Trenching for water lines and laying of water lines
  • 14. Water Supply Remaining Water Lines Trenched Water Lines LEGEND
  • 15. Infrastructure Update Area Status: Progress: Next Step Golf Course Irrigation Pump •Pump already delivered to the irrigation contractor, installation to commence on completion of the pump house construction •Working with the irrigation contractor to construct the pump house •Pump house construction Sewer Treatment Plant •Sewer treatment plant already delivered to site; Part installation complete; awaiting fixing of control panel •Construction of the control room to commence on agreement with the lexis international • Complete installation of the plant control panel •Testing and commissioning of plant Power Supply • Power supply to sewer treatment plant complete together with installation of the distribution board • Power supply works to plot G722 ongoing; erection and pulling of LV lines complete; •Installation of transformer complete, request for quotation from Mehta electrical to install a high mast security light along the northern boundary •Installation of security light along northern boundary
  • 16. Cabbro sample 40sqm to specification
  • 17. Wadi Degla • We are pleased to inform you that Migaa has entered into a partnership with the Egyptian conglomerate Wadi Degla Holdings through their local subsidiary Wadi Degla Investment (K) ltd. • The agreement between Migaa and Wadi Degla involves development of the remaining front nine holes of Migaa 18 hole championship golf course, Sports Facilities, Club House and management of the golf course to serve the residents of Migaa. • Each Migaa plot owner or unit owner will get a free Wadi Degla membership and will have a chance to reciprocate to any other Wadi Degla branches both locally and abroad and shall have rights to the facilities managed by Wadi Degla anywhere in the world. • Wadi Degla is expected to complete construction within 12 months after commencement.
  • 18. Wadi Degla • Proposed Club House Phase 1
  • 19. Wadi Degla • Proposed Club House Phase 2
  • 20. Wadi Degla • Proposed Sports Facilities
  • 21. MITINI SCAPES • The completed Phase 1 comprises of 82 units; 12 cottages and 70 apartments and sits on approximately 6 acres. • Currently we have 4 residents who are already residing.
  • 23. PROGRESS UPDATE Contemporary Chic Modern CONSTRUCTION UPDATE Overall Project Progress 42% Projected completion date 31st December 2016 Block 4 •Internal Plaster for ground ,1st , 2nd & 3rd Floor 85% Complete while 4th , 5th & 6th Floor 75% Complete. •External Cladding 75% Complete. •Roofing Works 70% Complete.
  • 24. PROGRESS UPDATE Contemporary Chic Modern Block 1(IPL Block) • 7th Slab Complete. •Internal Plaster for ground ,1st , 2nd & 3rd Floor 85% Complete while 4th & 5th is at 50% Complete. •External Plaster 70% Complete.
  • 25. PROGRESS UPDATE Contemporary Chic Modern Block 2 • 7th floor slab complete. •Internal Plaster for ground, 1st & 2nd floor 65% Complete. •External Plaster 50% Complete
  • 26. PROGRESS UPDATE Contemporary Chic Modern Block 3 •4th Floor Slab 60% Complete. •Internal Plaster works in ground floor 80% Complete.
  • 27. SHOW APARTMENT PROGRESS PHOTOS Contemporary Chic Modern Show Apartment Remaining Items • (OS & E) Operating Supplies and Equipments and (FF& E) Furniture Fixtures and Equipments.