SlideShare a Scribd company logo
1 of 120
Download to read offline
Overcurrent Protection & Coordination for
Industrial Applications
Doug Durand, P.E.
IEEE Continuing Education Seminar - Houston, TX
November 3-4, 2015
Slide 2
Day 1
▫ Introduction
▫ Using Log-Log Paper & TCCs
▫ Types of Fault Current
▫ Protective Devices & Characteristic
Curves
▫ Coordination Time Intervals (CTIs)
▫ Effect of Fault Current Variations
▫ Multiple Source Buses
▫ Partial Differential Relaying
▫ Directional Overcurrent Coordination
Day 2
▫ Transformer Overcurrent Protection
▫ Motor Overcurrent Protection
▫ Conductor Overcurrent Protection
▫ Generator Overcurrent Protection
▫ Coordinating a System
▫ Coordination Quizzes
▫ Coordination Software
▫ References
Agenda
Introduction
Slide 4
Protection Objectives
• Personnel Safety
Slide 5
Protection Objectives
• Equipment Protection
Slide 6
Protection Objectives
• Service Continuity & Selective Fault Isolation
13.8 kV
480 V
13.8 kV/480 V
2.5 MVA
5.75%
• Faults should be quickly detected and
cleared with a minimum disruption of
service.
• Protective devices perform this
function and must be adequately
specified and coordinated.
• Errors in either specification or setting
can cause nuisance outages.
Slide 7
Types of Protection
•Distance
•High-Impedance Differential
•Current Differential
•Under/Overfrequency
•Under/Overvoltage
•Over Temperature
•Overload
•Overcurrent
Protective devices can provide the following assortment of protection, many
of which can be coordinated. We’ll focus primarily on the last one,
overcurrent.
Slide 8
Coordinating Overcurrent Devices
• Tools of the trade “in the good old days…”
Slide 9
Coordinating Overcurrent Devices
• Tools of the trade “in the good old days…”
Slide 10
Coordinating Overcurrent Devices
• Tools of the trade “in the good old days…”
Slide 11
Coordinating Overcurrent Devices
• Tools of the trade “in the good old days…”
Slide 12
Coordinating Overcurrent Devices
• Old-world craftsmanship…
Slide 13
Coordinating Overcurrent Devices
• Tools of the trade today…
Slide 14
Coordinating Overcurrent Devices
• New-world craftsmanship…
Using Log-Log Paper & TCCs
Slide 16
0.01
0.1
1
10
100
1000
Time
In
Seconds
0.1 1 10 100` 1000 10000
Current in Amperes
Time-Current Curve (TCC)
Log-Log Plots
Why log-log paper?
• Log-Log scale compresses
values to a more manageable
range.
• I2t withstand curves plot as
straight lines.
effectively
steady state
1 minute
typical motor
acceleration
typical fault
clearing
5 cycles
(interrupting)
1 cycle
(momentary)
FLC = 1 pu Fs = 13.9 pu Fp = 577 pu
I2t withstand
curves plot as
straight lines
Slide 17
0.01
0.1
1
10
100
1000
Time
In
Seconds
0.5 1 10 100` 1000 10000
Current in Amperes
5000 hp Motor TCC
Plotting A Curve
FLC = 598.9 A
LRC = 3593.5 A
Accel. Time = 2 s
4.16 kV 5000 hp
90% PF, 96% η, 598.9 A
3593.5 LRC, 2 s start
M
13.8 kV
4.16 kV
13.8/4.16 kV
10 MVA
6.5%
Slide 18
0.01
0.1
1
10
100
1000
Time
In
Seconds
0.5 1 10 100` 1000 10000
Current in Amperes
5000 hp Motor TCC with Fault on Motor Terminal
Plotting Fault Current & Scale Adjustment
FLC = 598.9 A
LRC = 3593.5 A
Accel. Time = 2 s
4.16 kV 5000 hp
90% PF, 96% η, 598.9 A
3593.5 LRC, 2 s start
15 kA
15 kA
x 10 A
M
13.8 kV
4.16 kV
13.8/4.16 kV
10 MVA
6.5%
Slide 19
0.01
0.1
1
10
100
1000
Time
In
Seconds
0.5 1 10 100` 1000 10000
Current in Amperes
5000 hp Motor TCC with Fault on Transformer Primary
Voltage Scales
4.16 kV 5000 hp
90% PF, 96% η, 598.9 A
3593.5 LRC, 2 s start
15 kA
149.3 kA
x 10 A
45 kA
= (45 x 13.8/4.16)
= 149.3 kA @ 4.16 kV
45 kA @ 13.8 kV
= ? @ 4.16 kV
x 100 A @ 4.16 kV
15 kA
M
13.8 kV
4.16 kV
13.8/4.16 kV
10 MVA
6.5%
Types of Fault Currents
Slide 21
Fault Current Options
ANSI
• Momentary Symmetrical
• Momentary Asymmetrical
• Momentary Crest
• Interrupting Symmetrical
• Adjusted Interrupting Symmetrical
IEC
• Initial Symmetrical (Ik
’’)
• Peak (Ip)
• Breaking (Ib)
• Asymmetrical Breaking (Ib,asym)
Momentary
Current
Crest/Peak
Interrupting/Breaking
Initial Symmetrical
Slide 22
Fault Current Options
• Symmetrical currents are most appropriate.
• Momentary asymmetrical should be considered when setting
instantaneous functions.
• Use of duties not strictly appropriate, but okay.
• Use of momentary/initial symmetrical currents lead to conservative CTIs.
• Use of interrupting currents will lead to lower, but still acceptable CTIs.
Momentary
Current
Crest/Peak
Interrupting/Breaking
Initial Symmetrical
Protective Devices & Characteristic
Curves
Slide 24
Electromechanical Relays (EM)
1 10 100
0.01
0.1
100
1
10
MULTIPLES OF PICK-UP SETTING
TIME
IN
SECONDS
Time
Dial
Settings
½
1
2
3
10
IFC 53
RELAY
Very Inverse Time
Time-Current
Curves
Slide 25
M
4.16 kV
4.16 kV
5000 hp
FLC = 598.9 A
SF = 1.0
IFC
53
800/5 Set AT = 4
Electromechanical Relays – Pickup Calculation
The relay should pick-up for current
values above the motor FLC ( ~ 600 A).
For the IFC53 pictured, the available
ampere-tap (AT) settings are 0.5, 0.6,
0.7, 0.8, 1, 1.2, 1.5, 2, 2.5, 3, & 4.
For this type of relay, the primary pickup
current was calculated as:
PU = CT Ratio x AT
PU = (800/5) x 3 = 480 A (too low)
= (800/5) x 4 = 640 A (107%, okay)
Slide 26
1 10 100
0.01
0.1
100
1
10
MULTIPLES OF PICK-UP SETTING
TIME
IN
SECONDS
M
4.16 kV
4.16 kV
5000 hp
598.9 A, SF = 1
IFC
53
15 kA
800/5
Setting = 4 AT (640 A pickup)
TD = ??
1.21 s
1.05 s
Time Dial 10
0.34 s
0.30 s
Time Dial 3
0.08 s
0.07 s
Time Dial ½
10000/640
= 15.6
15000/640
= 23.4
Multiple of Pick-Up
10 kA
15 kA
Fault Current
IFC 53 Relay Operating Times
0.30
1.05
1.21
0.34
10 kA
23.4
Time
Dial
Settings
½
1
2
3
10
IFC 53
RELAY
Very Inverse Time
Time-Current Curves
15.6
0.08
0.07
Electromechanical Relays – Operating Time Calculation
Slide 27
Solid-State Relays (SS)
Slide 28
Solid-State Relays (SS)
Curve selection made on the
left-side interior of the relay.
Slide 29
Microprocessor-Based Relays
2000/5
41-SWGR-01B
13.8 kV
01-52B
OCR
400/5
01-F15B
F15B
52B
52B
OC1
ANSI-Normal Inverse
Pickup = 2.13 (0.05 – 20 xCT Sec)
Time Dial = 0.96
Inst = 20 (0.05 – 20 xCT Sec)
Time Delay = 0.01 s
F15B
OC1
ANSI-Extremely Inverse
Pickup = 8 (0.05 – 20 xCT Sec)
Time Dial = 0.43
Inst = 20 (0.05 – 20 xCT Sec)
Time Delay = 0.02 s
F15B – 3P
30 kA @ 13.8 kV
52B – 3P
Amps X 100 (Plot Ref. kV=13.8)
Seconds
Slide 30
Microprocessor-Based Relays
Slide 31
Power CBs
Power MCB
Cutler-Hammer RMS 520 Series
Sensor = 3200
LT Pickup = 1 (3200 Amps)
LT Band = 4
ST Pickup = 2.5 (8000 Amps)
ST Band = 0.3 (I^x)t = OUT
Power FCB
Cutler-Hammer RMS 520 Series
Sensor = 1200
LT Pickup = 1 (1200 Amps)
LT Band = 2
ST Pickup = 4 (4500 Amps)
ST Band = 0.1 (I^x)t = OUT
Amps X 100 (Plot Ref. kV=0.48)
Seconds
Power MCB – 3P
47.4 kA @ 0.48 kV
Power FCB – 3P
90.2 kA @ 0.48 kV
16-SWGR-02A
0.48 kV
PWR MCB
3200 A
PWR FCB
1600 A
LT Pickup
LT Band
ST Pickup
ST Band
Slide 32
Insulated & Molded Case CB
16-SWGR-02A
0.48 kV
Insulated Case MCB
1200 A
Molded Case CB
250 A
Insulated Case MCB
Frame = 1250 Plug = 1200 A
LT Pickup = Fixed (1200 A)
LT Band = Fixed
ST Pickup = 4 x (4000 A)
ST Band = Fixed (I^2)t = IN
Override = 14000 A
Molded Case CB
HKD
Size = 250 A
Terminal Trip = Fixed
Magnetic Trip = 10
Insulated Case MCB
11 kA @ 0.48 kV
Amps X 100 (Plot Ref. kV=0.48)
Seconds
Fault current
< Inst. Override
Slide 33
Insulated & Molded Case CB
16-SWGR-02A
0.48 kV
Insulated Case MCB
1200 A
Molded Case CB
250 A
Insulated Case MCB
Frame = 1250 Plug = 1200 A
LT Pickup = Fixed (1200 A)
LT Band = Fixed
ST Pickup = 4 x (4000 A)
ST Band = Fixed (I^2)t = IN
Override = 14000 A
Molded Case CB
HKD
Size = 250 A
Terminal Trip = Fixed
Magnetic Trip = 10
Insulated Case MCB
42 kA @ 0.48 kV
Amps X 100 (Plot Ref. kV=0.48)
Seconds Fault current
> Inst. Override
Slide 34
Power Fuses
MCC 1
4.16 kV
Mtr Fuse
Mtr Fuse
JCL (2/03)
Standard 5.08 kV
5R
Seconds
Amps X 10 (Plot Ref. kV=4.16 kV)
Minimum
Melting
Total
Clearing
Mtr Fuse
15 kA @
4.16 kV
Coordination Time Intervals (CTIs)
Slide 36
Primary devices sense, operate
& clear the fault first.
Backup devices wait for sufficient
time to allow operation of primary
devices.
Coordination Time Intervals (CTIs)
The CTI is the amount of time allowed between a
primary device and its upstream backup.
Feeder
Main
When two such
devices are
coordinated such
that the primary
device “should”
operate first at all
fault levels, they are
“selectively”
coordinated.
Slide 37
Coordination Time Intervals – EM
Main
Feeder
30 kA
Feeder
Main
30 kA
Amps X 100 (Plot Ref. kV=13.8)
Seconds
In the good old (EM) days,
What typical CTI would we
want between the feeder and
the main breaker relays?
? s
Slide 38
Coordination Time Intervals – EM
On what did it depend?
Remember the TD setting?
It is continuously adjustable
and not exact.
So how do you really
know where TD = 5?
FIELD TESTING !
(not just hand set)
Slide 39
Coordination Time Intervals – EM
Feeder
30 kA
3x (9.6 kA), 3.3 s
5x (16 kA), 1.24 s
8x (25.6 kA), 0.63 s
Plotting the field test points.
Amps X 100 (Plot Ref. kV=13.8)
Seconds
“3x” means 3 times pickup
3 * 8 = 24 A (9.6 kA primary)
5 * 8 = 40 A (16 kA primary)
8 * 8 = 64 A (25.6 kA primary)
Slide 40
Coordination Time Intervals – EM
Feeder
30 kA
Amps X 100 (Plot Ref. kV=13.8)
Seconds
So now, if test points are not
provided what should the CTI
be?
But, if test points are provided
what should the CTI be?
Feeder
Main
30 kA
Main w/o testing
Main w/ testing
0.4 s
0.3 s
Slide 41
Coordination Time Intervals – EM
Where does the 0.3 s or 0.4 s come from?
Feeder
Main
30 kA
1. breaker operating time
2. CT, relay errors
3. disk overtravel
(Feeder breaker)
(both)
(Main relay only)
Tested Hand Set
breaker 5 cycle 0.08 s 0.08 s
Disk overtravel 0.10 s 0.10 s
CT, relay errors 0.12 s 0.22 s
TOTAL 0.30 s 0.40 s
Slide 42
Coordination Time Intervals – EM
Buff Book (IEEE 242-2001, taken from Tables 15-1 & 15-2)
Red Book (IEEE 141-1993, per Section 5.7.2.1)
Components
Obviously, CTIs can be a
subjective issue.
Components Field Tested
0.08 s
0.10 s
0.17 s
0.35 s
0.08 s
0.10 s
0.12 s
0.30 s
Slide 43
Coordination Time Intervals – EM & SS
So, lets move forward a few years….
For a modern (static) relay what part of the
margin can be dropped?
So if one of the two relays is static, we can
use 0.2 s, right?
Feeder (SS)
Main (EM)
CTI = 0.3 s
(because disk OT is
still in play)
Feeder (EM)
Main (SS)
CTI = 0.2 s
Slide 44
Coordination Time Intervals – EM & SS
Main (EM)
Feeder (SS)
0.3 s
disk OT still applicable
Feeder (SS)
Main (EM)
Feeder (SS)
30 kA @ 13.8 kV
Main (EM)
Main (SS)
Feeder EM
0.2 s
Feeder (EM)
30 kA @ 13.8 kV
Main (SS)
Feeder (EM)
Main (SS)
Amps X 100 (Plot Ref. kV=13.8)
Seconds
Amps X 100 (Plot Ref. kV=13.8)
Slide 45
Coordination Time Intervals – EM/SS with Banded Devices
OC Relay combinations with banded devices
disk overtravel
CT, relay errors
operating time
CTI
√ 0.1 s
√ 0.12 s
x -
0.22 s
disk overtravel
CT, relay errors
operating time
CTI
x -
√ 0.12 s
x -
0.12 s
Static Trip or
Molded Case
Breaker
Static Relay
Power
Fuse
Static Trip or
Molded Case
Breaker
EM Relay
Power
Fuse
Slide 46
EM-Banded
0.22 s 0.12 s
SS-Banded
Coordination Time Intervals – EM/SS with Banded Devices
EM Relay
PWR MCB SS Relay
PWR MCB
PWR MCB
EM Relay
25 kA 25 kA
Amps X 100 (Plot Ref. kV=0.48)
Seconds
Amps X 100 (Plot Ref. kV=0.48)
PWR MCB
SS Relay
Slide 47
Coordination Time Intervals – Banded Devices
• Banded characteristics include
tolerances & operating times.
• There is no intentional/
additional time delay needed
between two banded devices.
• All that is required is clear
space (CS), except…
• coordination of instantaneous
trips cannot be demonstrated
on TCCs.
• Discrimination depends on type
and size.
Slide 48
Coordination Time Intervals – Summary
Buff Book (IEEE 242-2001, Table 15-3 – Minimum CTIs a)
Effect of Fault Current Variations
Slide 50
CTI & Fault Current Magnitude
Main
Feeder
F2 = 20 kA
Feeder
Main
F2 = 20 kA
Amps X 100 (Plot Ref. kV=13.8)
Seconds 0.06 s
F1 = 10 kA
F1 = 10 kA
0.2 s
Inverse relay characteristics
imply
Relay
Current
Operating
Time
For a fault current of 10 kA the
CTI is 0.2 s.
For a fault current of 20 kA the
CTI is 0.06 s.
Conclusion – inverse-time curves
are highly susceptible to changes
in current. Add definite time when
possible.
Slide 51
Total Bus Fault versus Branch Currents
M M
M
15 kA
1 kA
2 kA
0.8 kA
1.2 kA
10 kA
• For a typical distribution bus all feeder relays will see a slightly different
maximum fault current.
• Years back, the simple approach was to use the total bus fault current as
the basis of the CTI, including main incomer.
• Using the same current for the main led to a margin of conservatism.
Slide 52
Total Bus Fault versus Branch Currents
10 kA
M
15 kA
Main
Feeder
15 kA
Amps X 100 (Plot Ref. kV=13.8)
Seconds
10 kA
Amps X 100 (Plot Ref. kV=13.8)
15 kA
Main
Feeder
0.2 s
0.8 s
Using Total Bus
Fault Current of
15 kA
Using Actual
Incomer Relay
Current of 10 kA
Slide 53
Curve Shaping
Amps X 100 (Plot Ref. kV=13.8)
Seconds
• Most modern relays include multiple
OC Elements.
• Using a definite time characteristic
(or delayed instantaneous) can
eliminate the affect of varying fault
current levels.
• This is a highly-recommended
change to old-school thinking.
15 kA
20 kA
10 kA
0.2 s
Slide 54
Curve Shaping – Danger of Independent OC Units
• Many software programs include the
facility to plot integrated overcurrent
units, usually a 50/51.
• However, the OC units of many
modern relays are independent and
remain active at all fault current levels.
• Under certain setting conditions, such
as with an extremely inverse
characteristic, the intended definite
time delay can be undercut at higher
fault levels.
15 kA
20 kA
10 kA
0.2 s
Amps X 100 (Plot Ref. kV=13.8)
Seconds
0.1 s
40 kA
Multiple Source Buses
Slide 56
Multiple Source Buses
• When a bus includes multiple sources, care must be taken to not
coordinate all source relays at the total fault current.
• Source relays should be plotted only to their respective fault
currents or their “normalized” plots.
• Plotting the source curves to the total bus fault current will lead to
much larger than actual CTIs.
Slide 57
Multiple Source Buses
Amps X 100 (Plot Ref. kV=13.8)
Seconds
Amps X 100 (Plot Ref. kV=13.8)
Plot to Full Fault
Level
Plot to Actual
Relay Current
2
1
30 kA
12 kA
0.2 s
30 kA
12 kA
1.1 s
2
1
12 kA 18 kA
30 kA 1
2 3
(don’t do this)
Slide 58
Curve Shifting
• Many software packages include the facility to adjust/shift the
characteristics of the source relays to line up at the bus maximum
fault currents.
• Shifting allows relay operation to be considered on a common current
basis (the max).
• The shift factor (SF) is calculated using:
SF = Bus Fault / Relay Current
• For example:
Transformer relay SF = 30/12 = 2.5
Generator relay SF = 30/18 = 1.67
Feeder relay SF = 30/30 = 1.0
12 kA 18 kA
30 kA 1
2 3
Slide 59
Curve Shifting
Amps X 100 (Plot Ref. kV=13.8)
Seconds
Amps X 100 (Plot Ref. kV=13.8)
Without shift factor
both pickups = 3000 A.
With shift factor relay 2
pickup shifts to 7500 A.
2
1
30 kA
12 kA
0.2 s
30 kA
1
2
0.2 s
12 kA 18 kA
30 kA 1
2 3
2.5 x
Doesn’t look
coordinated but is.
“7500 A pickup is
misleading/confusing
.
Slide 60
Multiple Source Buses with Closed Tie
10 kA 5 kA
10 kA
Fa = 25 kA Fb = 25 kA
15 kA (Fa)
10 kA (Fb)
Bus A Bus B
• Different fault locations cause different flows in tie.
SF(Fa) = 25 / (10 + 5) = 1.67
SF(Fb) = 25 / 10 = 2.5
• Preparing a TCC for each fault unique location will determine the
defining case.
• Cases can be done for varying sources out of service & breaker logic
used to enable different setting groups.
Partial Differential Relaying
Slide 62
Partial Differential (Summation) Relaying
• Commonly used on secondary
selective systems with normally
closed tie breakers.
• CT wiring automatically discriminates
between faults on Bus A and Bus B.
• CT wiring ensures that main breaker
relay sees the same current as the
faulted feeder.
• 51A trips Main A & tie; 51B trips
Main B & tie.
• Eliminates need for relay on tie
breaker & saves coordination step.
51A
Ip1+Ip2
Source 1 Source 2
51B
Feeder A Feeder B
Ip2
Is2
Is2
Is1
Is2
Bus A Bus B
0
Ip2
Is1+Is2
Ip1
Slide 63
Partial Differential Relaying
51A
Source 1 Source 2
51B
Feeder A Feeder B
0
0
Is1
Is1
Is1
Bus A Bus B
Is1
Ip1
0
Ip1
Open
Ip1
• Scheme works with a source or tie
breaker open.
• The relay in the open source must
remain in operation.
• Relay metering functions can be
misleading due to CT summation
wiring.
• Separate metering must be provided
on dedicated CTs or before the
currents are summed.
Slide 64
Partial Differential Relaying
51A
Ip1+Ip2+Ip3
Source 1 Source 2 51B
Feeder A Feeder B
Ip2
Is2
Is2+
Is3
Is1
Is2+
Is3
Bus A Bus B
0
Ip2+Ip3
Is1+Is2+Is3
Ip1
Source 3
Ip3
Is3
• Scheme will work for any
number of sources or bus ties.
• A dedicated relay is needed
for each bus section.
• Partial differential schemes
simplify the coordination of
multiple source buses by
ensuring the main relay for
each bus always see the
same current as the faulted
feeder.
Directional Overcurrent Relaying
Slide 66
Directional Current Relaying
67
Bus A Bus B
67
• Directional overcurrent (67) relays are required on double-ended line-ups
with normally closed ties and buses with multiple sources.
• Protection is intended to provide more sensitive and faster detection of faults
in the upstream supply system.
• Directional device provides backup protection to the transformer differential
protection.
• Normal overcurrent devices are bidirectional. A separate set of TCCs are
required to show coordination of directional units.
Transformer Overcurrent Protection
Slide 68
Transformer Overcurrent Protection
NEC Table 450.3(A) defines overcurrent setting requirements for primary &
secondary protection pickup settings.
Slide 69
Transformer Overcurrent Protection
• C37.91 defines the ANSI
withstand protection limits.
• Withstand curve defines thermal
& mechanical limits of a
transformer experiencing a
through-fault.
• Requirement to protect for
mechanical damage is based on
frequency of through faults &
transformer size.
• Right-hand side (thermal) used
for setting primary protection.
• Left-hand side (mechanical)
used for setting secondary
protection.
thermal
withstand
25 x FLC
@ 2s
based on
transformer Z
mechanical
withstand
Slide 70
Transformer Overcurrent Protection
Primary
FLC = 2.576 MVA/(√3 x 13.8) = 107.8 A
Relay PU must be ≤ 600% FLC = 646.6 A
Using a relay setting of 2.0 x CT, the relay
PU = 2 x 200 = 400 A
400 / 107.8 = 371% so okay
Secondary
FLC = 2.576 MVA / (√3 x 0.48) = 3098 A
MCB Trip must be ≤ 250% FLC = 7746 A
Breaker Trip = 3200 A per bus rating
3200 / 3098 = 103% (okay)
Time delay depends on level of protection
desired.
(ONAN/ONAN/ONAF - 2.0 x 1.12 x 1.15 = 2.576)
Seconds
Amps X 10 (Plot Ref. kV=13.8)
2.576 MVA, 5.75% Z
∆-Y Resistor Ground
PWR-MCB
Relay pickup
R-Primary
optional time
delay settings
13.8 kV
480 V
13.8/0.48 kV
2.576 MVA
5.75%
PWR-MCB
3200 A
R-Primary
200/5
Fs
Slide 71
Transformer Overcurrent Protection
∆-Y Connections – Phase-To-Phase Faults
• A phase-phase fault on the secondary
appears more severe in one phase on
the primary.
• Setting the CTI based on a three-
phase fault is not as conservative as
for a phase-phase fault.
• The secondary curve could be shifted
or a slightly larger CTI used, but can
be ignored if primary/ secondary
selectivity is not critical.
0
0.5
0.86
0.86
0.5
1.0
A
C
B
a
c
b
Amps X 100 (Plot Ref. kV=13.8)
Seconds
0.3 s
30 kA
30 x 0.86 = 26 kA
0.25 s
Slide 72
Transformer Overcurrent Protection
∆-Y Connections – Phase-To-Ground Faults
1.0
0.577
0.577
0.577
0
A
C
B
a
c
b
0 0
• A one per unit phase-ground fault on
the secondary appears as a 58%
(1/√3) phase fault on the primary.
• The transformer damage curve is
shifted 58% to the left to ensure
protection.
Amps X 10 (Plot Ref. kV=13.8)
2.576 MVA, 5.75% Z
∆-Y Resistor Ground
PWR-MCB
Seconds
∆-Y Solid Ground
R-Primary
58%
13.8 kV
480 V
13.8/0.48 kV
2.576 MVA
5.75%
PWR-MCB
3200 A
R-Primary
200/5
Fs
Slide 73
Transformer Overcurrent Protection
Inrush Current
• Use of 8-12 times FLC @ 0.1 s is an
empirical approach based on EM
relays. (based on a 1944 AIEE paper)
• The instantaneous peak value of the
inrush current can actually be much
higher than 12 times FLC.
• The inrush is not over at 0.1 s, the dot
just represents a typical rms
equivalent of the inrush from
energization to this point in time.
Seconds
Amps X 10 (Plot Ref. kV=13.8)
2.576 MVA, 5.75% Z
∆-Y Resistor Ground
PWR-MCB
8-12 x FLC
(typical)
13.8 kV
480 V
13.8/0.48 kV
2.576 MVA
5.75%
PWR-MCB
3200 A
R-Primary
200/5
Fs
Slide 74
Transformer Overcurrent Protection
Setting the primary inst. protection
• The primary relay instantaneous
(50) setting should not trip due to
the inrush or secondary fault
current.
• It was common to use the
asymmetrical rms value of
secondary fault current (1.6 x sym)
to establish the instantaneous
pickup, but most modern relays filter
out the DC component.
Seconds
Amps X 10 (Plot Ref. kV=13.8)
2.4 MVA, 5.75% Z
∆-Y Resistor Ground
PWR-MCB
8-12 x FLC
(typical)
13.8 kV
480 V
13.8/0.48 kV
2.4 MVA
5.75%
PWR-MCB
3200 A
R-Primary
Fp
Fs
200/5
Slide 75
Transformer Overcurrent Protection
∆-Y Connection & Ground Faults
• A secondary L-G fault is not sensed by the ground (zero sequence) devices on
the primary (∆) side.
• Low-resistance and solidly-grounded systems on the secondary of a ∆-Y
transformer are therefore coordinated separately from the upstream systems.
1.0
0.577
0.577
0.577
0
A
C
B
a
c
b
0 0
Phase Currents Zero Sequence Network
H X
Z0
Slide 76
Transformer Overcurrent Protection
∆-Y Connection & Ground Faults
• The ground resistor size is selected to limit the fault current while still
providing sufficient current for coordination.
• The resistor ratings include a maximum continuous current that must be
considered. (as low as 10% of the rated current)
Motor Overcurrent Protection
Slide 78
Motor Overcurrent Protection
• Fuse provides short-circuit
protection.
• 49 or 51 device provide motor
overload protection.
• Overload pickup depends on
motor FLC and service factor.
• The time delay for the 49/51
protection is based on motor
stall time.
Seconds
Amps X 10 (Plot Ref. kV=4.16)
1000 hp
4.16 kV
650% LRC
6 s Accel
Bussmann
JCL Size 9R
GE Multilin 469
Standard O/L Curve
Pickup = 1.01 X FLC
Curve Multiplier = 3
Hot
Stall
Time
M
17 kA @
4.16 kV
Slide 79
Motor Overcurrent Protection
• In the past, instantaneous OC
protection was avoided on contactor-
fed motors since the contactors could
not clear high short-circuits.
• With modern relays, a definite time
unit can be used if its setting is
coordinated with the contactor
interrupting rating.
Amps X 10 (Plot Ref. kV=4.16)
Seconds
Bussmann
JCL Size 9R
GE Multilin 469
Standard O/L Curve
Pickup = 1.01 X FLC
Curve Multiplier = 3
Contactor
6 kA Int.
M
17 kA @
4.16 kV
1000 hp
4.16 kV
650% LRC
6 s Accel
Hot
Stall
Time
Slide 80
Motor Overcurrent Protection
• The instantaneous or definite time
setting for a breaker-fed motor must
be set to not trip during motor starting.
• Electromechanical relays must be set
above the asymmetrical rms current,
either via the pickup or with a time
delay.
• Modern relays with filtering can ignore
the asymmetrical current, but it’s
advisable to include a generous
margin such as 2 x LRC.
• Note – undervoltage protection (27)
needed to trip motor on loss of power.
Seconds
Amps X 10 (Plot Ref. kV=4.16)
5000 hp
4.16 kV
650% LRC
GE Multilin 469
Standard O/L Curve
Pickup = 1.01 X FLC
Curve Multiplier = 3
Hot
M
30 kA @ 4.16 kV
Hot
Stall
Time
Conductor Overcurrent Protection
Slide 82
Conductor Overcurrent Protection
LV Cables
NEC 240.4 Protection of Conductors – conductors shall be protected against
overcurrent in accordance with their ampacities
(B) Devices Rated 800 A or Less – the next higher standard device rating
shall be permitted
(C) Devices Rated over 800 A – the ampacity of the conductors shall be ≥ the
device rating
NEC 240.91 Protection of Conductors (supervised locations, new in 2011)
(B) Devices Rated Over 800 A – allows ampacity of at least 95% of
breaker rating to be acceptable provided I2t withstand protection is provided.
- Means that 3/phase 500 kcmil conductors at 380 A each for a total of
1140 A can be protection by a 1200 A breaker.
- Does not mean you can operate the circuit at 1200 A.
Slide 83
Conductor Overcurrent Protection
NEC 240.6 Standard Ampere Ratings
(A) Fuses & Fixed-Trip Circuit Breakers – cites all standard ratings
(B) Adjustable Trip Circuit Breakers – Rating shall be equal to maximum
setting
(C) Restricted Access Adjustable-Trip Circuit Breakers – Rating can be
equal to setting if access is restricted
Slide 84
Conductor Overcurrent Protection
MV Feeders & Branch Circuits
NEC 240.101 (A) Rating or Setting of Overcurrent Protective Devices
Fuse rating ≤ 3 times conductor ampacity
Relay setting ≤ 6 times conductor ampacity
MV Motor Conductors
NEC 430.224 Size of Conductors
Conductors ampacity shall be greater than the overload setting.
Slide 85
Conductor Overcurrent Protection
1 – 3/C 350 kcmil
Copper Rubber
To = 90 deg. C
Seconds
Amps X 100 (Plot Ref. V=600)
• The insulation temperature rating
is typically used as the operating
temperature (To).
• The final temperature (Tf) depends
on the insulation type (typically
150 deg. C or 250 deg. C).
• When calculated by hand, you
only need one point and then draw
in at a -2 slope.
Generator Overcurrent Protection
Slide 87
Generator Overcurrent Protection
• A generator’s fault current
contribution decays over time.
• Overcurrent protection must allow
both for moderate overloads & be
sensitive enough to detect the steady
state contribution to a system fault.
• Voltage controlled/ restrained relays
(51V) are commonly used.
• Per 1986 Buff Book, the pickup at full
restraint is typically ≥ 150% of Full
Load Current (FLC).
• The pickup at no restraint must be
< FLC/Xd
.
FLC/Xd
Seconds
Amps X 10 (Plot Ref. kV=12.47)
GTG-101A
No Load
Constant Excitation
AC Fault Current
Momentary contribution
(FLC/X”d)
Interrupting contribution
(FLC/X’d)
FLC
Slide 88
Generator 51V Pickup Setting Example
Fg = FLC/Xd = 903 / 2.8 = 322.5 A
51V pickup (full restraint) > 150% FLC = 1354 A
51V pickup (no restraint) < 322.5 A
1200/5
Fg
51V
12.47 kV
19500 kVA
903 A
Xd = 280%
Slide 89
Generator 51V Pickup Setting Example
51V Setting > 1354/1200 = 1.13
Using 1.15, 51V pickup = 1.15 x 1200 A = 1380 A
With old EM relays,
51V pickup (no restraint) = 25% of 1380 A
= 345 A (> 322.5 A, not good)
With new relays a lower MF can be set, such that 51V
pickup (no restraint) = 20% of 1380 A
= 276 A (< 322.5, so okay)
Slide 90
Generator 51V Settings on TCC
GTG-101A
No Load
Constant Excitation
Total Fault Current
20% x Pickup
Pickup = 1.15 x
CT-Sec
30 kA
Seconds
Amps X 10 (Plot Ref. kV=12.47)
• At 100% voltage the overcurrent
function is fully restrained.
• As the bus voltage decreases the
restraint decreases and the
characteristic curve shifts to the left.
• There was no guidance in the 1986
Buff Book with respect to time
delay.
• Practically speaking, if the
installation is not generator-limited,
it is not possible to overload the
generator.
• To avoid nuisance tripping,
especially on islanded systems,
higher TDs are better.
no
restraint
full
restraint
decreasing
voltage
Slide 91
Generator Overload Protection per 2001 Buff Book
• C50.13, Section 4.2 discusses
stator and rotor thermal limits.
• C37.102, Section 4.1.1 provides the
associated plot.
• The 2001 Buff Book now references
this discusses a different approach
overload protection.
• The approach uses a 50 device to
control a 51. No mention of voltage.
• Note that rotor negative sequence
(I2t2) protection can be plotted on a
TCC but is applicable to 46
protection, not 51V.
Coordinating a System
Slide 93
Coordinating a System
• TCCs show both protection
& coordination.
• Most OC settings should be
shown/confirmed on TCCs.
• Showing too much on a
single TCC can make it
impossible to read.
Slide 94
Coordinating a System
•Showing a vertical
slice of the system
can reduce
crowding, but still
be hard to read.
•Upstream
equipment is
shown on multiple
and redundant
TCCs.
Slide 95
Coordinating a System
• A set of overlapping TCCs can be used to limit the amount of
information on each curve and demonstrate coordination of the
system from the bottom up.
• Protection settings should be based on equipment ratings and
available spare capacity – not simply on the present operating load
and installed equipment.
• Typical TCCs can be used to establish settings for similar
installations.
• Device settings defined on a given TCC are used as the starting
point in the next upstream TCC.
• The curves can be shown on an overall one-line of the system to
illustrate the TCC coverage (Zone Map).
Slide 96
Phase TCC Zone Map
TCC-1
TCC-2
TCC-3
TCC-307J
TCC-5
TCC-4
TCC-Comp
TCC-6
TCC-212J
TCC-101J
Slide 97
Coordinating a System: TCC-1
Zone Map
• Motor starting & protection is adequate.
• Cable ampacity & withstand protection is
adequate.
• The MCC main breaker may trip for faults
above 11 kA, but this cannot be helped.
• The switchgear feeder breaker is selective
with the MCC main breaker, although not
necessarily required
Seconds
Amps X 100 (Plot Ref. kV=0.48)
Slide 98
Coordinating a System: TCC-2
• The switchgear feeder breaker settings
established on TCC-1 set the basis for this curve.
• The main breaker is set to be selective with the
feeder at all fault levels.
• A CTI marker is not required since the
characteristic curves include all margins and
breaker operating times.
• The main breaker curve is clipped at its through-
fault current instead of the total bus fault current
to allow tighter coordination of the upstream relay.
(See TCC-3)
Zone Map
Seconds
Amps X 100 (Plot Ref. kV=0.48)
PWR FCB – 3P
42 kA @ 0.48 kV
PWR MCB – 3P
30 kA @ 0.48 kV
Slide 99
Coordinating a System: TCC-3
• The LV switchgear main breaker settings
established on TCC-2 set the basis for this curve.
• The transformer damage curve is based on frequent
faults and is not shifted since the transformer is
resistance grounded.
• The primary side OC relay is selective with the
secondary main and provides adequate transformer
and feeder cable protection.
• The primary OC relay instantaneous high enough to
pass the secondary fault current and transformer
inrush current.
Zone Map
Seconds
Amps X 100 (Plot Ref. kV=0.48)
Primary relay pickup of 546 A
is high at 512% of transformer
FLC, but meets Code.
Slide 100
Coordinating a System: TCC-307J
• This curve sets the basis for the upstream devices
since its motor is the largest on the MCC.
• Motor starting and overload protection is
acceptable.
• Motor feeder cable protection is acceptable
• The motor relay includes a definite time unit to
provide enhanced protection.
• The definite time function is delayed to ensure
fuse clears faults over the contactor rating.
Zone Map
Seconds
Amps X 10 (Plot Ref. kV=4.16)
Slide 101
Coordinating a System: TCC-4
• The 307J motor relay settings established on
TCC-307J set the basis for this curve.
• The tie breaker relay curve is plotted to the total
bus fault current to be conservative.
• The main breaker relay curve is plotted to its
let-through current.
• A coordination step is provided between the tie
and main relay although this decision is
discretionary.
• The definite time functions insulate the CTIs
from minor fault current variations.
• All devices appear selectively coordinated at all
fault current levels, but the independent OC
functions may be an issue.
Zone Map
Seconds
Amps X 10 (Plot Ref. kV=4.16)
Slide 102
Coordinating a System: TCC-5
• The MV MCC main breaker settings established on
TCC-4 set the basis for this curve.
• The transformer damage curve is based on frequent
faults and is not shifted since the transformer is
resistance grounded.
• The primary side OC relay is selective with the
secondary main and provides adequate transformer
and feeder cable protection.
• The OC relay instantaneous high enough to pass the
secondary fault current and transformer inrush current.
Zone Map
Seconds
Amps X 10 (Plot Ref. kV=13.8)
Primary relay pickup of 1000 A
is 320 % of transformer FLC.
Slide 103
Coordinating a System: TCC-Comp
• Due to the compressor size, this curve may set
the basis for the MV switchgear main breaker.
• Motor starting and overload protection is
acceptable.
• Short-circuit protection is provided by the
relay/breaker instead of a fuse as with the
1000 hp motor.
• The short-circuit protection is delayed 50 ms to
avoid nuisance tripping.
Zone Map
Seconds
Amps X 10 (Plot Ref. kV=13.8)
Slide 104
Coordinating a System: TCC-6
• The feeder breaker settings established on
TCC-3, TCC-4, and TCC-Comp are shown as
the basis for this curve.
• The settings for feeder 52A1 (to the 2.4 MVA)
could be omitted since it does not define any
requirements.
• A coordination step is provided between the tie
and main relay although this decision is
discretionary.
• All devices are selectively coordinated at all fault
current levels.
• The definite time functions insulate the CTIs from
minor fault current variations.
Zone Map
Seconds
Amps X 10 (Plot Ref. kV=13.8)
Slide 105
Ground TCC Zone Map
TCC-G1
TCC-G2
Coordination Quizzes
Slide 107
Coordination Quiz #1
Does this TCC look okay??
• There is no need to maintain a
coordination interval between
feeder breakers.
• The 0.3-s CTIs are sufficient
unless all relays are electro-
mechanical and hand set.
• Fix – base the setting of the
feeder 2 relay on its downstream
equipment and lower the time
delays if possible.
TR-FDR2
Main
2000/5
600/5
OCR
OCR
TR-FDR1
400/5 OCR
SWGR-1
0.3 s
0.3 s
Main-P
OC1
TR-FDR2-P
OC1
TR-FDR1-P
OC1
Main-3P
TR-FDR2-3P
TR-FDR1-3P
15 kA @ 13.8 kV
Seconds
Amps X 100 (Plot Ref. kV=13.8)
Slide 108
Coordination Quiz #2
Does this TCC look okay??
• The CTIs between the main and
feeders are sufficient at the fault
levels noted.
• Assuming testing EM relays, the
0.62 s CTI cannot be reduced
since the 0.30 s CTI is at the limit.
• The main relay time delay is
actually too fast since the CTI at
30 kA is less than 0.2 s.
• Fix – raise the time delay setting
of the main relay or make it less
inverse.
FDR-2
Main-1
2000/5
600/5
OCR
OCR
FDR-1
400/5 OCR
SWGR-3
0.62 s
0.30 s
Main-P
OC1
FDR-2-P
OC1
FDR-1-P
OC1
Main-3P
FDR-2-3P
FDR-1-3P
30 kA @ 13.8 kV
Seconds
Amps X 100 (Plot Ref. kV=13.8)
Slide 109
Coordination Quiz #3
Does this TCC look okay??
• The marked CTIs are okay, but….
• A main should never include an
instantaneous setting.
• Fix – delete the instantaneous on
the main relay (!!) and raise the
time delay to maintain a 0.2s CTI
at 50 kA (assuming static relays)
0.47 s
0.33 s
Main-3-P
OC1
FDR--2-P
OC1
FDR--1-P
OC1
Main-3-3P
FDR--2-3P
FDR--1-3P
50 kA @ 13.8 kV
FDR--2
Main-3
2000/5
600/5
OCR
OCR
FDR--1
400/5 OCR
SWGR-4
Seconds
Amps X 100 (Plot Ref. kV=13.8)
Slide 110
Coordination Quiz #4
Does this TCC look okay??
• Primary relay pickup is 525% of
transformer FLC, thus okay.
• Transformer frequent fault
protection is not provided by the
primary relay, but this is okay –
adequate protection is provided
by the secondary main.
• Cable withstand protection is
inadequate.
• Fix – Add instantaneous setting to
the primary relay.
Seconds
Amps X 10 (Plot Ref. kV=13.8)
Slide 111
Coordination Quiz #5
Seconds
Amps X 10 (Plot Ref. kV=13.8)
• Selectivity between Relay14 on
the transformer primary and CB44
on the secondary is not provided,
but this can be acceptable.
• Relay 14 is not, however,
selectively coordinated with
feeder breaker CB46.
• Fix – raise Relay14 time delay
setting and add CTI marker.
0.08 s
Does this TCC look okay??
Slide 112
Coordination Quiz #6
Does this TCC look okay??
• Crossing of feeder characteristics
is no problem.
• There is no need to maintain an
intentional time margin between
two LV static trip units – clear
space is sufficient.
• Fix – lower the main breaker
short-time delay band.
0.21 s
LVMain
LVFDR2
LVFDR1
LVMain – 3P
30 kA @ 0.48 kV
LVFDR2 – 3P
LVFDR1 – 3P
45 kA @ 0.48 kV
Seconds
Amps X 100 (Plot Ref. kV=0.48)
Slide 113
Coordination Quiz #7
Does this TCC look okay??
• The source relays should not be
plotted to the full bus fault level
unless their plots are shifted
based on:
SF = Total fault current / relay
current.
• Since each relay actually sees
less than the total fault current,
the CTIs are actually much higher
than 0.3 s.
• Fix – plot the source relays to
their actual fault current or apply
SF.
0.3 s
Source1 - P
OC1
Feeder - P
OC1
Source2 - P
OC1
Source1 - 3P
Source2 – 3P
Feeder – 3P
15 kA @ 13.8 kV
Seconds
Amps X 100 (Plot Ref. kV=13.8)
10 kA 5 kA
Slide 114
Coordination Quiz #8
Does this TCC look okay??
• The displayed CTI of 0.2 s is
acceptable.
• But, if the main relay’s overcurrent
elements are independent then
there is miscoordination.
• Fix – set minimum response time
(if available), raise TD of main, or
make curve less inverse.
Seconds
Amps X 100 (Plot Ref. kV=12.5)
Slide 115
Coordination Quiz #9
Does this TCC look okay??
• There are two curves to be
concerned with for a 51V – full
restraint and zero restraint.
• Assuming the full restraint curve
is shown, it is coordinated too
tightly with the feeder.
• The 51V curve will shift left and
lose selectivity with the feeder if a
close-in fault occurs and the
voltage drops.
• Fix – show both 51V curves and
raise time delay.
0.30 s
51V - P
OC1
FDR-5 - P
OC1
51V – 3P
FDR-5 – 3P
15 kA @ 13.8 kV
Seconds
Amps X 100 (Plot Ref. kV=12.5)
Coordination Software
Slide 117
Coordination Software
• Computer-aided coordination software programs
originated in the mid 1980s.
• The accuracy of the device characteristic curves was
often highly questionable.
• There are numerous, much more powerful programs
available today, many of which are very mature.
• Even still, the accuracy of the protective devices functions
and characteristics is still extremely critical.
Slide 118
Coordination Software
• For many years clients maintained separate impedance
models for power studies and protective device models
for coordination studies.
• Integrated models are now the norm and are required to
support arc-flash studies.
References
Slide 120
Selected References
• Applied Protective Relaying – Westinghouse
• Protective Relaying – Blackburn
• IEEE Std 242 – Buff Book
• IEEE Std 141 – Red Book
• IEEE Std 399 – Brown Book
• IEEE C37.90 – Relays
• IEEE C37.91 – Transformer Protection
• IEEE C37.102 – Guide for AC Generator Protection
• IEEE C50.13 – Cylindrical-Rotor Gens ≥ 10 MVA
• NFPA 70 – National Electrical Code

More Related Content

Similar to 2015-11-03-Overcurrent-Coordination-Industrial-Applications (2).pdf

Solucionario circuitos eléctricos 6ta Edición Dorf Svoboda.pdf
Solucionario circuitos eléctricos 6ta Edición Dorf Svoboda.pdfSolucionario circuitos eléctricos 6ta Edición Dorf Svoboda.pdf
Solucionario circuitos eléctricos 6ta Edición Dorf Svoboda.pdfSANTIAGO PABLO ALBERTO
 
Original IGBT N-CHANNEL STGP7NC60HD GP7NC60HD 7NC60 14A 600V TO-220 New
Original IGBT N-CHANNEL STGP7NC60HD GP7NC60HD 7NC60 14A 600V TO-220 NewOriginal IGBT N-CHANNEL STGP7NC60HD GP7NC60HD 7NC60 14A 600V TO-220 New
Original IGBT N-CHANNEL STGP7NC60HD GP7NC60HD 7NC60 14A 600V TO-220 Newauthelectroniccom
 
Design of electrical machines
Design of electrical machines Design of electrical machines
Design of electrical machines ariwala palak
 
Original IGBT STGP6NC60HD 6N60 600V 15A TO-220 New STMicroelectronics
Original IGBT STGP6NC60HD 6N60 600V 15A TO-220 New STMicroelectronicsOriginal IGBT STGP6NC60HD 6N60 600V 15A TO-220 New STMicroelectronics
Original IGBT STGP6NC60HD 6N60 600V 15A TO-220 New STMicroelectronicsauthelectroniccom
 
Original IGBT STGP6NC60HD GP6NC60 6N60 600V 15A TO-220 New STMicroelectronics
Original IGBT STGP6NC60HD GP6NC60 6N60 600V 15A TO-220 New STMicroelectronicsOriginal IGBT STGP6NC60HD GP6NC60 6N60 600V 15A TO-220 New STMicroelectronics
Original IGBT STGP6NC60HD GP6NC60 6N60 600V 15A TO-220 New STMicroelectronicsAUTHELECTRONIC
 
Synchronous machines
Synchronous machinesSynchronous machines
Synchronous machinesmichaeljmack
 
Original N-CHANNEL MOSFET GP8NC60KD 8NC60KD 8NC60 15A 600V TO-220 New STMicro...
Original N-CHANNEL MOSFET GP8NC60KD 8NC60KD 8NC60 15A 600V TO-220 New STMicro...Original N-CHANNEL MOSFET GP8NC60KD 8NC60KD 8NC60 15A 600V TO-220 New STMicro...
Original N-CHANNEL MOSFET GP8NC60KD 8NC60KD 8NC60 15A 600V TO-220 New STMicro...AUTHELECTRONIC
 
Original Opto TLP620GB TLP620 P620 620 DIP-4 New ToshibaOriginal Opto TLP620G...
Original Opto TLP620GB TLP620 P620 620 DIP-4 New ToshibaOriginal Opto TLP620G...Original Opto TLP620GB TLP620 P620 620 DIP-4 New ToshibaOriginal Opto TLP620G...
Original Opto TLP620GB TLP620 P620 620 DIP-4 New ToshibaOriginal Opto TLP620G...authelectroniccom
 
Superconducting Generators
Superconducting GeneratorsSuperconducting Generators
Superconducting GeneratorsRafed Hossain
 
Original Transistor NPN MJE13003 KSE13003 E13003 13003 1.5A 400V TO-126 New
Original Transistor NPN MJE13003 KSE13003 E13003 13003 1.5A 400V TO-126 NewOriginal Transistor NPN MJE13003 KSE13003 E13003 13003 1.5A 400V TO-126 New
Original Transistor NPN MJE13003 KSE13003 E13003 13003 1.5A 400V TO-126 NewAUTHELECTRONIC
 
Current Transformers parameter design and graphs - size and design requirements
Current Transformers parameter design and graphs - size and design requirementsCurrent Transformers parameter design and graphs - size and design requirements
Current Transformers parameter design and graphs - size and design requirementsssuser39bdb9
 
Original Opto PC853H P853 853H 853 DIP-4 New SHARP
Original Opto PC853H P853 853H 853 DIP-4 New SHARPOriginal Opto PC853H P853 853H 853 DIP-4 New SHARP
Original Opto PC853H P853 853H 853 DIP-4 New SHARPauthelectroniccom
 
90981041 control-system-lab-manual
90981041 control-system-lab-manual90981041 control-system-lab-manual
90981041 control-system-lab-manualGopinath.B.L Naidu
 
Refurbishment of a Three-Phase Induction Motor Reflecting Local Voltage Condi...
Refurbishment of a Three-Phase Induction Motor Reflecting Local Voltage Condi...Refurbishment of a Three-Phase Induction Motor Reflecting Local Voltage Condi...
Refurbishment of a Three-Phase Induction Motor Reflecting Local Voltage Condi...IOSR Journals
 
Original IGBT G15M65DF2 STGF15M65DF2 G15M65 650V 15A TO-220 New ST
Original IGBT G15M65DF2 STGF15M65DF2 G15M65 650V 15A TO-220 New STOriginal IGBT G15M65DF2 STGF15M65DF2 G15M65 650V 15A TO-220 New ST
Original IGBT G15M65DF2 STGF15M65DF2 G15M65 650V 15A TO-220 New STauthelectroniccom
 
Original IGBT IKB06N60T K06T60 06T60 06N60 6N60 TO-263 New Infineon
Original IGBT IKB06N60T K06T60 06T60 06N60 6N60 TO-263 New InfineonOriginal IGBT IKB06N60T K06T60 06T60 06N60 6N60 TO-263 New Infineon
Original IGBT IKB06N60T K06T60 06T60 06N60 6N60 TO-263 New InfineonAUTHELECTRONIC
 
Original N-CHANNEL IGBT GB10NC60KD STGB10NC60KDT4 10A 600V TO-263 New STMicro...
Original N-CHANNEL IGBT GB10NC60KD STGB10NC60KDT4 10A 600V TO-263 New STMicro...Original N-CHANNEL IGBT GB10NC60KD STGB10NC60KDT4 10A 600V TO-263 New STMicro...
Original N-CHANNEL IGBT GB10NC60KD STGB10NC60KDT4 10A 600V TO-263 New STMicro...authelectroniccom
 
Solved problems to_chapter_09
Solved problems to_chapter_09Solved problems to_chapter_09
Solved problems to_chapter_09Shah Zaib
 

Similar to 2015-11-03-Overcurrent-Coordination-Industrial-Applications (2).pdf (20)

Solucionario circuitos eléctricos 6ta Edición Dorf Svoboda.pdf
Solucionario circuitos eléctricos 6ta Edición Dorf Svoboda.pdfSolucionario circuitos eléctricos 6ta Edición Dorf Svoboda.pdf
Solucionario circuitos eléctricos 6ta Edición Dorf Svoboda.pdf
 
Original IGBT N-CHANNEL STGP7NC60HD GP7NC60HD 7NC60 14A 600V TO-220 New
Original IGBT N-CHANNEL STGP7NC60HD GP7NC60HD 7NC60 14A 600V TO-220 NewOriginal IGBT N-CHANNEL STGP7NC60HD GP7NC60HD 7NC60 14A 600V TO-220 New
Original IGBT N-CHANNEL STGP7NC60HD GP7NC60HD 7NC60 14A 600V TO-220 New
 
Design of electrical machines
Design of electrical machines Design of electrical machines
Design of electrical machines
 
Original IGBT STGP6NC60HD 6N60 600V 15A TO-220 New STMicroelectronics
Original IGBT STGP6NC60HD 6N60 600V 15A TO-220 New STMicroelectronicsOriginal IGBT STGP6NC60HD 6N60 600V 15A TO-220 New STMicroelectronics
Original IGBT STGP6NC60HD 6N60 600V 15A TO-220 New STMicroelectronics
 
Original IGBT STGP6NC60HD GP6NC60 6N60 600V 15A TO-220 New STMicroelectronics
Original IGBT STGP6NC60HD GP6NC60 6N60 600V 15A TO-220 New STMicroelectronicsOriginal IGBT STGP6NC60HD GP6NC60 6N60 600V 15A TO-220 New STMicroelectronics
Original IGBT STGP6NC60HD GP6NC60 6N60 600V 15A TO-220 New STMicroelectronics
 
Synchronous machines
Synchronous machinesSynchronous machines
Synchronous machines
 
Original N-CHANNEL MOSFET GP8NC60KD 8NC60KD 8NC60 15A 600V TO-220 New STMicro...
Original N-CHANNEL MOSFET GP8NC60KD 8NC60KD 8NC60 15A 600V TO-220 New STMicro...Original N-CHANNEL MOSFET GP8NC60KD 8NC60KD 8NC60 15A 600V TO-220 New STMicro...
Original N-CHANNEL MOSFET GP8NC60KD 8NC60KD 8NC60 15A 600V TO-220 New STMicro...
 
Original Opto TLP620GB TLP620 P620 620 DIP-4 New ToshibaOriginal Opto TLP620G...
Original Opto TLP620GB TLP620 P620 620 DIP-4 New ToshibaOriginal Opto TLP620G...Original Opto TLP620GB TLP620 P620 620 DIP-4 New ToshibaOriginal Opto TLP620G...
Original Opto TLP620GB TLP620 P620 620 DIP-4 New ToshibaOriginal Opto TLP620G...
 
Superconducting Generators
Superconducting GeneratorsSuperconducting Generators
Superconducting Generators
 
Original Transistor NPN MJE13003 KSE13003 E13003 13003 1.5A 400V TO-126 New
Original Transistor NPN MJE13003 KSE13003 E13003 13003 1.5A 400V TO-126 NewOriginal Transistor NPN MJE13003 KSE13003 E13003 13003 1.5A 400V TO-126 New
Original Transistor NPN MJE13003 KSE13003 E13003 13003 1.5A 400V TO-126 New
 
Current Transformers parameter design and graphs - size and design requirements
Current Transformers parameter design and graphs - size and design requirementsCurrent Transformers parameter design and graphs - size and design requirements
Current Transformers parameter design and graphs - size and design requirements
 
Original Opto PC853H P853 853H 853 DIP-4 New SHARP
Original Opto PC853H P853 853H 853 DIP-4 New SHARPOriginal Opto PC853H P853 853H 853 DIP-4 New SHARP
Original Opto PC853H P853 853H 853 DIP-4 New SHARP
 
FINAL
FINALFINAL
FINAL
 
90981041 control-system-lab-manual
90981041 control-system-lab-manual90981041 control-system-lab-manual
90981041 control-system-lab-manual
 
Refurbishment of a Three-Phase Induction Motor Reflecting Local Voltage Condi...
Refurbishment of a Three-Phase Induction Motor Reflecting Local Voltage Condi...Refurbishment of a Three-Phase Induction Motor Reflecting Local Voltage Condi...
Refurbishment of a Three-Phase Induction Motor Reflecting Local Voltage Condi...
 
Original IGBT G15M65DF2 STGF15M65DF2 G15M65 650V 15A TO-220 New ST
Original IGBT G15M65DF2 STGF15M65DF2 G15M65 650V 15A TO-220 New STOriginal IGBT G15M65DF2 STGF15M65DF2 G15M65 650V 15A TO-220 New ST
Original IGBT G15M65DF2 STGF15M65DF2 G15M65 650V 15A TO-220 New ST
 
Mcbelcb
McbelcbMcbelcb
Mcbelcb
 
Original IGBT IKB06N60T K06T60 06T60 06N60 6N60 TO-263 New Infineon
Original IGBT IKB06N60T K06T60 06T60 06N60 6N60 TO-263 New InfineonOriginal IGBT IKB06N60T K06T60 06T60 06N60 6N60 TO-263 New Infineon
Original IGBT IKB06N60T K06T60 06T60 06N60 6N60 TO-263 New Infineon
 
Original N-CHANNEL IGBT GB10NC60KD STGB10NC60KDT4 10A 600V TO-263 New STMicro...
Original N-CHANNEL IGBT GB10NC60KD STGB10NC60KDT4 10A 600V TO-263 New STMicro...Original N-CHANNEL IGBT GB10NC60KD STGB10NC60KDT4 10A 600V TO-263 New STMicro...
Original N-CHANNEL IGBT GB10NC60KD STGB10NC60KDT4 10A 600V TO-263 New STMicro...
 
Solved problems to_chapter_09
Solved problems to_chapter_09Solved problems to_chapter_09
Solved problems to_chapter_09
 

More from ChadWood16

17thEdition.ppt
17thEdition.ppt17thEdition.ppt
17thEdition.pptChadWood16
 
cable sizing.ppt
cable sizing.pptcable sizing.ppt
cable sizing.pptChadWood16
 
Electrical and Magnetic force fileds.pdf
Electrical and Magnetic force fileds.pdfElectrical and Magnetic force fileds.pdf
Electrical and Magnetic force fileds.pdfChadWood16
 
OverCurrent(1).pdf
OverCurrent(1).pdfOverCurrent(1).pdf
OverCurrent(1).pdfChadWood16
 
Lecture 12 Overcurrent Protection.pdf
Lecture 12 Overcurrent Protection.pdfLecture 12 Overcurrent Protection.pdf
Lecture 12 Overcurrent Protection.pdfChadWood16
 
Line Protection.pdf
Line Protection.pdfLine Protection.pdf
Line Protection.pdfChadWood16
 
187787508-Over-Current-Earth-Fault-Setting-Calculations.pdf
187787508-Over-Current-Earth-Fault-Setting-Calculations.pdf187787508-Over-Current-Earth-Fault-Setting-Calculations.pdf
187787508-Over-Current-Earth-Fault-Setting-Calculations.pdfChadWood16
 
CH4_Transfo_Mesure(SP).pdf
CH4_Transfo_Mesure(SP).pdfCH4_Transfo_Mesure(SP).pdf
CH4_Transfo_Mesure(SP).pdfChadWood16
 
CH3_MALT_Reseaux(2016-01-20).pdf
CH3_MALT_Reseaux(2016-01-20).pdfCH3_MALT_Reseaux(2016-01-20).pdf
CH3_MALT_Reseaux(2016-01-20).pdfChadWood16
 

More from ChadWood16 (10)

17thEdition.ppt
17thEdition.ppt17thEdition.ppt
17thEdition.ppt
 
cable sizing.ppt
cable sizing.pptcable sizing.ppt
cable sizing.ppt
 
Electrical and Magnetic force fileds.pdf
Electrical and Magnetic force fileds.pdfElectrical and Magnetic force fileds.pdf
Electrical and Magnetic force fileds.pdf
 
OverCurrent(1).pdf
OverCurrent(1).pdfOverCurrent(1).pdf
OverCurrent(1).pdf
 
Lecture 12 Overcurrent Protection.pdf
Lecture 12 Overcurrent Protection.pdfLecture 12 Overcurrent Protection.pdf
Lecture 12 Overcurrent Protection.pdf
 
Line Protection.pdf
Line Protection.pdfLine Protection.pdf
Line Protection.pdf
 
187787508-Over-Current-Earth-Fault-Setting-Calculations.pdf
187787508-Over-Current-Earth-Fault-Setting-Calculations.pdf187787508-Over-Current-Earth-Fault-Setting-Calculations.pdf
187787508-Over-Current-Earth-Fault-Setting-Calculations.pdf
 
CH4_Transfo_Mesure(SP).pdf
CH4_Transfo_Mesure(SP).pdfCH4_Transfo_Mesure(SP).pdf
CH4_Transfo_Mesure(SP).pdf
 
CH3_MALT_Reseaux(2016-01-20).pdf
CH3_MALT_Reseaux(2016-01-20).pdfCH3_MALT_Reseaux(2016-01-20).pdf
CH3_MALT_Reseaux(2016-01-20).pdf
 
CH2_.pdf
CH2_.pdfCH2_.pdf
CH2_.pdf
 

Recently uploaded

complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction managementMariconPadriquez1
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 

Recently uploaded (20)

complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction management
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 

2015-11-03-Overcurrent-Coordination-Industrial-Applications (2).pdf

  • 1. Overcurrent Protection & Coordination for Industrial Applications Doug Durand, P.E. IEEE Continuing Education Seminar - Houston, TX November 3-4, 2015
  • 2. Slide 2 Day 1 ▫ Introduction ▫ Using Log-Log Paper & TCCs ▫ Types of Fault Current ▫ Protective Devices & Characteristic Curves ▫ Coordination Time Intervals (CTIs) ▫ Effect of Fault Current Variations ▫ Multiple Source Buses ▫ Partial Differential Relaying ▫ Directional Overcurrent Coordination Day 2 ▫ Transformer Overcurrent Protection ▫ Motor Overcurrent Protection ▫ Conductor Overcurrent Protection ▫ Generator Overcurrent Protection ▫ Coordinating a System ▫ Coordination Quizzes ▫ Coordination Software ▫ References Agenda
  • 5. Slide 5 Protection Objectives • Equipment Protection
  • 6. Slide 6 Protection Objectives • Service Continuity & Selective Fault Isolation 13.8 kV 480 V 13.8 kV/480 V 2.5 MVA 5.75% • Faults should be quickly detected and cleared with a minimum disruption of service. • Protective devices perform this function and must be adequately specified and coordinated. • Errors in either specification or setting can cause nuisance outages.
  • 7. Slide 7 Types of Protection •Distance •High-Impedance Differential •Current Differential •Under/Overfrequency •Under/Overvoltage •Over Temperature •Overload •Overcurrent Protective devices can provide the following assortment of protection, many of which can be coordinated. We’ll focus primarily on the last one, overcurrent.
  • 8. Slide 8 Coordinating Overcurrent Devices • Tools of the trade “in the good old days…”
  • 9. Slide 9 Coordinating Overcurrent Devices • Tools of the trade “in the good old days…”
  • 10. Slide 10 Coordinating Overcurrent Devices • Tools of the trade “in the good old days…”
  • 11. Slide 11 Coordinating Overcurrent Devices • Tools of the trade “in the good old days…”
  • 12. Slide 12 Coordinating Overcurrent Devices • Old-world craftsmanship…
  • 13. Slide 13 Coordinating Overcurrent Devices • Tools of the trade today…
  • 14. Slide 14 Coordinating Overcurrent Devices • New-world craftsmanship…
  • 16. Slide 16 0.01 0.1 1 10 100 1000 Time In Seconds 0.1 1 10 100` 1000 10000 Current in Amperes Time-Current Curve (TCC) Log-Log Plots Why log-log paper? • Log-Log scale compresses values to a more manageable range. • I2t withstand curves plot as straight lines. effectively steady state 1 minute typical motor acceleration typical fault clearing 5 cycles (interrupting) 1 cycle (momentary) FLC = 1 pu Fs = 13.9 pu Fp = 577 pu I2t withstand curves plot as straight lines
  • 17. Slide 17 0.01 0.1 1 10 100 1000 Time In Seconds 0.5 1 10 100` 1000 10000 Current in Amperes 5000 hp Motor TCC Plotting A Curve FLC = 598.9 A LRC = 3593.5 A Accel. Time = 2 s 4.16 kV 5000 hp 90% PF, 96% η, 598.9 A 3593.5 LRC, 2 s start M 13.8 kV 4.16 kV 13.8/4.16 kV 10 MVA 6.5%
  • 18. Slide 18 0.01 0.1 1 10 100 1000 Time In Seconds 0.5 1 10 100` 1000 10000 Current in Amperes 5000 hp Motor TCC with Fault on Motor Terminal Plotting Fault Current & Scale Adjustment FLC = 598.9 A LRC = 3593.5 A Accel. Time = 2 s 4.16 kV 5000 hp 90% PF, 96% η, 598.9 A 3593.5 LRC, 2 s start 15 kA 15 kA x 10 A M 13.8 kV 4.16 kV 13.8/4.16 kV 10 MVA 6.5%
  • 19. Slide 19 0.01 0.1 1 10 100 1000 Time In Seconds 0.5 1 10 100` 1000 10000 Current in Amperes 5000 hp Motor TCC with Fault on Transformer Primary Voltage Scales 4.16 kV 5000 hp 90% PF, 96% η, 598.9 A 3593.5 LRC, 2 s start 15 kA 149.3 kA x 10 A 45 kA = (45 x 13.8/4.16) = 149.3 kA @ 4.16 kV 45 kA @ 13.8 kV = ? @ 4.16 kV x 100 A @ 4.16 kV 15 kA M 13.8 kV 4.16 kV 13.8/4.16 kV 10 MVA 6.5%
  • 20. Types of Fault Currents
  • 21. Slide 21 Fault Current Options ANSI • Momentary Symmetrical • Momentary Asymmetrical • Momentary Crest • Interrupting Symmetrical • Adjusted Interrupting Symmetrical IEC • Initial Symmetrical (Ik ’’) • Peak (Ip) • Breaking (Ib) • Asymmetrical Breaking (Ib,asym) Momentary Current Crest/Peak Interrupting/Breaking Initial Symmetrical
  • 22. Slide 22 Fault Current Options • Symmetrical currents are most appropriate. • Momentary asymmetrical should be considered when setting instantaneous functions. • Use of duties not strictly appropriate, but okay. • Use of momentary/initial symmetrical currents lead to conservative CTIs. • Use of interrupting currents will lead to lower, but still acceptable CTIs. Momentary Current Crest/Peak Interrupting/Breaking Initial Symmetrical
  • 23. Protective Devices & Characteristic Curves
  • 24. Slide 24 Electromechanical Relays (EM) 1 10 100 0.01 0.1 100 1 10 MULTIPLES OF PICK-UP SETTING TIME IN SECONDS Time Dial Settings ½ 1 2 3 10 IFC 53 RELAY Very Inverse Time Time-Current Curves
  • 25. Slide 25 M 4.16 kV 4.16 kV 5000 hp FLC = 598.9 A SF = 1.0 IFC 53 800/5 Set AT = 4 Electromechanical Relays – Pickup Calculation The relay should pick-up for current values above the motor FLC ( ~ 600 A). For the IFC53 pictured, the available ampere-tap (AT) settings are 0.5, 0.6, 0.7, 0.8, 1, 1.2, 1.5, 2, 2.5, 3, & 4. For this type of relay, the primary pickup current was calculated as: PU = CT Ratio x AT PU = (800/5) x 3 = 480 A (too low) = (800/5) x 4 = 640 A (107%, okay)
  • 26. Slide 26 1 10 100 0.01 0.1 100 1 10 MULTIPLES OF PICK-UP SETTING TIME IN SECONDS M 4.16 kV 4.16 kV 5000 hp 598.9 A, SF = 1 IFC 53 15 kA 800/5 Setting = 4 AT (640 A pickup) TD = ?? 1.21 s 1.05 s Time Dial 10 0.34 s 0.30 s Time Dial 3 0.08 s 0.07 s Time Dial ½ 10000/640 = 15.6 15000/640 = 23.4 Multiple of Pick-Up 10 kA 15 kA Fault Current IFC 53 Relay Operating Times 0.30 1.05 1.21 0.34 10 kA 23.4 Time Dial Settings ½ 1 2 3 10 IFC 53 RELAY Very Inverse Time Time-Current Curves 15.6 0.08 0.07 Electromechanical Relays – Operating Time Calculation
  • 28. Slide 28 Solid-State Relays (SS) Curve selection made on the left-side interior of the relay.
  • 29. Slide 29 Microprocessor-Based Relays 2000/5 41-SWGR-01B 13.8 kV 01-52B OCR 400/5 01-F15B F15B 52B 52B OC1 ANSI-Normal Inverse Pickup = 2.13 (0.05 – 20 xCT Sec) Time Dial = 0.96 Inst = 20 (0.05 – 20 xCT Sec) Time Delay = 0.01 s F15B OC1 ANSI-Extremely Inverse Pickup = 8 (0.05 – 20 xCT Sec) Time Dial = 0.43 Inst = 20 (0.05 – 20 xCT Sec) Time Delay = 0.02 s F15B – 3P 30 kA @ 13.8 kV 52B – 3P Amps X 100 (Plot Ref. kV=13.8) Seconds
  • 31. Slide 31 Power CBs Power MCB Cutler-Hammer RMS 520 Series Sensor = 3200 LT Pickup = 1 (3200 Amps) LT Band = 4 ST Pickup = 2.5 (8000 Amps) ST Band = 0.3 (I^x)t = OUT Power FCB Cutler-Hammer RMS 520 Series Sensor = 1200 LT Pickup = 1 (1200 Amps) LT Band = 2 ST Pickup = 4 (4500 Amps) ST Band = 0.1 (I^x)t = OUT Amps X 100 (Plot Ref. kV=0.48) Seconds Power MCB – 3P 47.4 kA @ 0.48 kV Power FCB – 3P 90.2 kA @ 0.48 kV 16-SWGR-02A 0.48 kV PWR MCB 3200 A PWR FCB 1600 A LT Pickup LT Band ST Pickup ST Band
  • 32. Slide 32 Insulated & Molded Case CB 16-SWGR-02A 0.48 kV Insulated Case MCB 1200 A Molded Case CB 250 A Insulated Case MCB Frame = 1250 Plug = 1200 A LT Pickup = Fixed (1200 A) LT Band = Fixed ST Pickup = 4 x (4000 A) ST Band = Fixed (I^2)t = IN Override = 14000 A Molded Case CB HKD Size = 250 A Terminal Trip = Fixed Magnetic Trip = 10 Insulated Case MCB 11 kA @ 0.48 kV Amps X 100 (Plot Ref. kV=0.48) Seconds Fault current < Inst. Override
  • 33. Slide 33 Insulated & Molded Case CB 16-SWGR-02A 0.48 kV Insulated Case MCB 1200 A Molded Case CB 250 A Insulated Case MCB Frame = 1250 Plug = 1200 A LT Pickup = Fixed (1200 A) LT Band = Fixed ST Pickup = 4 x (4000 A) ST Band = Fixed (I^2)t = IN Override = 14000 A Molded Case CB HKD Size = 250 A Terminal Trip = Fixed Magnetic Trip = 10 Insulated Case MCB 42 kA @ 0.48 kV Amps X 100 (Plot Ref. kV=0.48) Seconds Fault current > Inst. Override
  • 34. Slide 34 Power Fuses MCC 1 4.16 kV Mtr Fuse Mtr Fuse JCL (2/03) Standard 5.08 kV 5R Seconds Amps X 10 (Plot Ref. kV=4.16 kV) Minimum Melting Total Clearing Mtr Fuse 15 kA @ 4.16 kV
  • 36. Slide 36 Primary devices sense, operate & clear the fault first. Backup devices wait for sufficient time to allow operation of primary devices. Coordination Time Intervals (CTIs) The CTI is the amount of time allowed between a primary device and its upstream backup. Feeder Main When two such devices are coordinated such that the primary device “should” operate first at all fault levels, they are “selectively” coordinated.
  • 37. Slide 37 Coordination Time Intervals – EM Main Feeder 30 kA Feeder Main 30 kA Amps X 100 (Plot Ref. kV=13.8) Seconds In the good old (EM) days, What typical CTI would we want between the feeder and the main breaker relays? ? s
  • 38. Slide 38 Coordination Time Intervals – EM On what did it depend? Remember the TD setting? It is continuously adjustable and not exact. So how do you really know where TD = 5? FIELD TESTING ! (not just hand set)
  • 39. Slide 39 Coordination Time Intervals – EM Feeder 30 kA 3x (9.6 kA), 3.3 s 5x (16 kA), 1.24 s 8x (25.6 kA), 0.63 s Plotting the field test points. Amps X 100 (Plot Ref. kV=13.8) Seconds “3x” means 3 times pickup 3 * 8 = 24 A (9.6 kA primary) 5 * 8 = 40 A (16 kA primary) 8 * 8 = 64 A (25.6 kA primary)
  • 40. Slide 40 Coordination Time Intervals – EM Feeder 30 kA Amps X 100 (Plot Ref. kV=13.8) Seconds So now, if test points are not provided what should the CTI be? But, if test points are provided what should the CTI be? Feeder Main 30 kA Main w/o testing Main w/ testing 0.4 s 0.3 s
  • 41. Slide 41 Coordination Time Intervals – EM Where does the 0.3 s or 0.4 s come from? Feeder Main 30 kA 1. breaker operating time 2. CT, relay errors 3. disk overtravel (Feeder breaker) (both) (Main relay only) Tested Hand Set breaker 5 cycle 0.08 s 0.08 s Disk overtravel 0.10 s 0.10 s CT, relay errors 0.12 s 0.22 s TOTAL 0.30 s 0.40 s
  • 42. Slide 42 Coordination Time Intervals – EM Buff Book (IEEE 242-2001, taken from Tables 15-1 & 15-2) Red Book (IEEE 141-1993, per Section 5.7.2.1) Components Obviously, CTIs can be a subjective issue. Components Field Tested 0.08 s 0.10 s 0.17 s 0.35 s 0.08 s 0.10 s 0.12 s 0.30 s
  • 43. Slide 43 Coordination Time Intervals – EM & SS So, lets move forward a few years…. For a modern (static) relay what part of the margin can be dropped? So if one of the two relays is static, we can use 0.2 s, right? Feeder (SS) Main (EM) CTI = 0.3 s (because disk OT is still in play) Feeder (EM) Main (SS) CTI = 0.2 s
  • 44. Slide 44 Coordination Time Intervals – EM & SS Main (EM) Feeder (SS) 0.3 s disk OT still applicable Feeder (SS) Main (EM) Feeder (SS) 30 kA @ 13.8 kV Main (EM) Main (SS) Feeder EM 0.2 s Feeder (EM) 30 kA @ 13.8 kV Main (SS) Feeder (EM) Main (SS) Amps X 100 (Plot Ref. kV=13.8) Seconds Amps X 100 (Plot Ref. kV=13.8)
  • 45. Slide 45 Coordination Time Intervals – EM/SS with Banded Devices OC Relay combinations with banded devices disk overtravel CT, relay errors operating time CTI √ 0.1 s √ 0.12 s x - 0.22 s disk overtravel CT, relay errors operating time CTI x - √ 0.12 s x - 0.12 s Static Trip or Molded Case Breaker Static Relay Power Fuse Static Trip or Molded Case Breaker EM Relay Power Fuse
  • 46. Slide 46 EM-Banded 0.22 s 0.12 s SS-Banded Coordination Time Intervals – EM/SS with Banded Devices EM Relay PWR MCB SS Relay PWR MCB PWR MCB EM Relay 25 kA 25 kA Amps X 100 (Plot Ref. kV=0.48) Seconds Amps X 100 (Plot Ref. kV=0.48) PWR MCB SS Relay
  • 47. Slide 47 Coordination Time Intervals – Banded Devices • Banded characteristics include tolerances & operating times. • There is no intentional/ additional time delay needed between two banded devices. • All that is required is clear space (CS), except… • coordination of instantaneous trips cannot be demonstrated on TCCs. • Discrimination depends on type and size.
  • 48. Slide 48 Coordination Time Intervals – Summary Buff Book (IEEE 242-2001, Table 15-3 – Minimum CTIs a)
  • 49. Effect of Fault Current Variations
  • 50. Slide 50 CTI & Fault Current Magnitude Main Feeder F2 = 20 kA Feeder Main F2 = 20 kA Amps X 100 (Plot Ref. kV=13.8) Seconds 0.06 s F1 = 10 kA F1 = 10 kA 0.2 s Inverse relay characteristics imply Relay Current Operating Time For a fault current of 10 kA the CTI is 0.2 s. For a fault current of 20 kA the CTI is 0.06 s. Conclusion – inverse-time curves are highly susceptible to changes in current. Add definite time when possible.
  • 51. Slide 51 Total Bus Fault versus Branch Currents M M M 15 kA 1 kA 2 kA 0.8 kA 1.2 kA 10 kA • For a typical distribution bus all feeder relays will see a slightly different maximum fault current. • Years back, the simple approach was to use the total bus fault current as the basis of the CTI, including main incomer. • Using the same current for the main led to a margin of conservatism.
  • 52. Slide 52 Total Bus Fault versus Branch Currents 10 kA M 15 kA Main Feeder 15 kA Amps X 100 (Plot Ref. kV=13.8) Seconds 10 kA Amps X 100 (Plot Ref. kV=13.8) 15 kA Main Feeder 0.2 s 0.8 s Using Total Bus Fault Current of 15 kA Using Actual Incomer Relay Current of 10 kA
  • 53. Slide 53 Curve Shaping Amps X 100 (Plot Ref. kV=13.8) Seconds • Most modern relays include multiple OC Elements. • Using a definite time characteristic (or delayed instantaneous) can eliminate the affect of varying fault current levels. • This is a highly-recommended change to old-school thinking. 15 kA 20 kA 10 kA 0.2 s
  • 54. Slide 54 Curve Shaping – Danger of Independent OC Units • Many software programs include the facility to plot integrated overcurrent units, usually a 50/51. • However, the OC units of many modern relays are independent and remain active at all fault current levels. • Under certain setting conditions, such as with an extremely inverse characteristic, the intended definite time delay can be undercut at higher fault levels. 15 kA 20 kA 10 kA 0.2 s Amps X 100 (Plot Ref. kV=13.8) Seconds 0.1 s 40 kA
  • 56. Slide 56 Multiple Source Buses • When a bus includes multiple sources, care must be taken to not coordinate all source relays at the total fault current. • Source relays should be plotted only to their respective fault currents or their “normalized” plots. • Plotting the source curves to the total bus fault current will lead to much larger than actual CTIs.
  • 57. Slide 57 Multiple Source Buses Amps X 100 (Plot Ref. kV=13.8) Seconds Amps X 100 (Plot Ref. kV=13.8) Plot to Full Fault Level Plot to Actual Relay Current 2 1 30 kA 12 kA 0.2 s 30 kA 12 kA 1.1 s 2 1 12 kA 18 kA 30 kA 1 2 3 (don’t do this)
  • 58. Slide 58 Curve Shifting • Many software packages include the facility to adjust/shift the characteristics of the source relays to line up at the bus maximum fault currents. • Shifting allows relay operation to be considered on a common current basis (the max). • The shift factor (SF) is calculated using: SF = Bus Fault / Relay Current • For example: Transformer relay SF = 30/12 = 2.5 Generator relay SF = 30/18 = 1.67 Feeder relay SF = 30/30 = 1.0 12 kA 18 kA 30 kA 1 2 3
  • 59. Slide 59 Curve Shifting Amps X 100 (Plot Ref. kV=13.8) Seconds Amps X 100 (Plot Ref. kV=13.8) Without shift factor both pickups = 3000 A. With shift factor relay 2 pickup shifts to 7500 A. 2 1 30 kA 12 kA 0.2 s 30 kA 1 2 0.2 s 12 kA 18 kA 30 kA 1 2 3 2.5 x Doesn’t look coordinated but is. “7500 A pickup is misleading/confusing .
  • 60. Slide 60 Multiple Source Buses with Closed Tie 10 kA 5 kA 10 kA Fa = 25 kA Fb = 25 kA 15 kA (Fa) 10 kA (Fb) Bus A Bus B • Different fault locations cause different flows in tie. SF(Fa) = 25 / (10 + 5) = 1.67 SF(Fb) = 25 / 10 = 2.5 • Preparing a TCC for each fault unique location will determine the defining case. • Cases can be done for varying sources out of service & breaker logic used to enable different setting groups.
  • 62. Slide 62 Partial Differential (Summation) Relaying • Commonly used on secondary selective systems with normally closed tie breakers. • CT wiring automatically discriminates between faults on Bus A and Bus B. • CT wiring ensures that main breaker relay sees the same current as the faulted feeder. • 51A trips Main A & tie; 51B trips Main B & tie. • Eliminates need for relay on tie breaker & saves coordination step. 51A Ip1+Ip2 Source 1 Source 2 51B Feeder A Feeder B Ip2 Is2 Is2 Is1 Is2 Bus A Bus B 0 Ip2 Is1+Is2 Ip1
  • 63. Slide 63 Partial Differential Relaying 51A Source 1 Source 2 51B Feeder A Feeder B 0 0 Is1 Is1 Is1 Bus A Bus B Is1 Ip1 0 Ip1 Open Ip1 • Scheme works with a source or tie breaker open. • The relay in the open source must remain in operation. • Relay metering functions can be misleading due to CT summation wiring. • Separate metering must be provided on dedicated CTs or before the currents are summed.
  • 64. Slide 64 Partial Differential Relaying 51A Ip1+Ip2+Ip3 Source 1 Source 2 51B Feeder A Feeder B Ip2 Is2 Is2+ Is3 Is1 Is2+ Is3 Bus A Bus B 0 Ip2+Ip3 Is1+Is2+Is3 Ip1 Source 3 Ip3 Is3 • Scheme will work for any number of sources or bus ties. • A dedicated relay is needed for each bus section. • Partial differential schemes simplify the coordination of multiple source buses by ensuring the main relay for each bus always see the same current as the faulted feeder.
  • 66. Slide 66 Directional Current Relaying 67 Bus A Bus B 67 • Directional overcurrent (67) relays are required on double-ended line-ups with normally closed ties and buses with multiple sources. • Protection is intended to provide more sensitive and faster detection of faults in the upstream supply system. • Directional device provides backup protection to the transformer differential protection. • Normal overcurrent devices are bidirectional. A separate set of TCCs are required to show coordination of directional units.
  • 68. Slide 68 Transformer Overcurrent Protection NEC Table 450.3(A) defines overcurrent setting requirements for primary & secondary protection pickup settings.
  • 69. Slide 69 Transformer Overcurrent Protection • C37.91 defines the ANSI withstand protection limits. • Withstand curve defines thermal & mechanical limits of a transformer experiencing a through-fault. • Requirement to protect for mechanical damage is based on frequency of through faults & transformer size. • Right-hand side (thermal) used for setting primary protection. • Left-hand side (mechanical) used for setting secondary protection. thermal withstand 25 x FLC @ 2s based on transformer Z mechanical withstand
  • 70. Slide 70 Transformer Overcurrent Protection Primary FLC = 2.576 MVA/(√3 x 13.8) = 107.8 A Relay PU must be ≤ 600% FLC = 646.6 A Using a relay setting of 2.0 x CT, the relay PU = 2 x 200 = 400 A 400 / 107.8 = 371% so okay Secondary FLC = 2.576 MVA / (√3 x 0.48) = 3098 A MCB Trip must be ≤ 250% FLC = 7746 A Breaker Trip = 3200 A per bus rating 3200 / 3098 = 103% (okay) Time delay depends on level of protection desired. (ONAN/ONAN/ONAF - 2.0 x 1.12 x 1.15 = 2.576) Seconds Amps X 10 (Plot Ref. kV=13.8) 2.576 MVA, 5.75% Z ∆-Y Resistor Ground PWR-MCB Relay pickup R-Primary optional time delay settings 13.8 kV 480 V 13.8/0.48 kV 2.576 MVA 5.75% PWR-MCB 3200 A R-Primary 200/5 Fs
  • 71. Slide 71 Transformer Overcurrent Protection ∆-Y Connections – Phase-To-Phase Faults • A phase-phase fault on the secondary appears more severe in one phase on the primary. • Setting the CTI based on a three- phase fault is not as conservative as for a phase-phase fault. • The secondary curve could be shifted or a slightly larger CTI used, but can be ignored if primary/ secondary selectivity is not critical. 0 0.5 0.86 0.86 0.5 1.0 A C B a c b Amps X 100 (Plot Ref. kV=13.8) Seconds 0.3 s 30 kA 30 x 0.86 = 26 kA 0.25 s
  • 72. Slide 72 Transformer Overcurrent Protection ∆-Y Connections – Phase-To-Ground Faults 1.0 0.577 0.577 0.577 0 A C B a c b 0 0 • A one per unit phase-ground fault on the secondary appears as a 58% (1/√3) phase fault on the primary. • The transformer damage curve is shifted 58% to the left to ensure protection. Amps X 10 (Plot Ref. kV=13.8) 2.576 MVA, 5.75% Z ∆-Y Resistor Ground PWR-MCB Seconds ∆-Y Solid Ground R-Primary 58% 13.8 kV 480 V 13.8/0.48 kV 2.576 MVA 5.75% PWR-MCB 3200 A R-Primary 200/5 Fs
  • 73. Slide 73 Transformer Overcurrent Protection Inrush Current • Use of 8-12 times FLC @ 0.1 s is an empirical approach based on EM relays. (based on a 1944 AIEE paper) • The instantaneous peak value of the inrush current can actually be much higher than 12 times FLC. • The inrush is not over at 0.1 s, the dot just represents a typical rms equivalent of the inrush from energization to this point in time. Seconds Amps X 10 (Plot Ref. kV=13.8) 2.576 MVA, 5.75% Z ∆-Y Resistor Ground PWR-MCB 8-12 x FLC (typical) 13.8 kV 480 V 13.8/0.48 kV 2.576 MVA 5.75% PWR-MCB 3200 A R-Primary 200/5 Fs
  • 74. Slide 74 Transformer Overcurrent Protection Setting the primary inst. protection • The primary relay instantaneous (50) setting should not trip due to the inrush or secondary fault current. • It was common to use the asymmetrical rms value of secondary fault current (1.6 x sym) to establish the instantaneous pickup, but most modern relays filter out the DC component. Seconds Amps X 10 (Plot Ref. kV=13.8) 2.4 MVA, 5.75% Z ∆-Y Resistor Ground PWR-MCB 8-12 x FLC (typical) 13.8 kV 480 V 13.8/0.48 kV 2.4 MVA 5.75% PWR-MCB 3200 A R-Primary Fp Fs 200/5
  • 75. Slide 75 Transformer Overcurrent Protection ∆-Y Connection & Ground Faults • A secondary L-G fault is not sensed by the ground (zero sequence) devices on the primary (∆) side. • Low-resistance and solidly-grounded systems on the secondary of a ∆-Y transformer are therefore coordinated separately from the upstream systems. 1.0 0.577 0.577 0.577 0 A C B a c b 0 0 Phase Currents Zero Sequence Network H X Z0
  • 76. Slide 76 Transformer Overcurrent Protection ∆-Y Connection & Ground Faults • The ground resistor size is selected to limit the fault current while still providing sufficient current for coordination. • The resistor ratings include a maximum continuous current that must be considered. (as low as 10% of the rated current)
  • 78. Slide 78 Motor Overcurrent Protection • Fuse provides short-circuit protection. • 49 or 51 device provide motor overload protection. • Overload pickup depends on motor FLC and service factor. • The time delay for the 49/51 protection is based on motor stall time. Seconds Amps X 10 (Plot Ref. kV=4.16) 1000 hp 4.16 kV 650% LRC 6 s Accel Bussmann JCL Size 9R GE Multilin 469 Standard O/L Curve Pickup = 1.01 X FLC Curve Multiplier = 3 Hot Stall Time M 17 kA @ 4.16 kV
  • 79. Slide 79 Motor Overcurrent Protection • In the past, instantaneous OC protection was avoided on contactor- fed motors since the contactors could not clear high short-circuits. • With modern relays, a definite time unit can be used if its setting is coordinated with the contactor interrupting rating. Amps X 10 (Plot Ref. kV=4.16) Seconds Bussmann JCL Size 9R GE Multilin 469 Standard O/L Curve Pickup = 1.01 X FLC Curve Multiplier = 3 Contactor 6 kA Int. M 17 kA @ 4.16 kV 1000 hp 4.16 kV 650% LRC 6 s Accel Hot Stall Time
  • 80. Slide 80 Motor Overcurrent Protection • The instantaneous or definite time setting for a breaker-fed motor must be set to not trip during motor starting. • Electromechanical relays must be set above the asymmetrical rms current, either via the pickup or with a time delay. • Modern relays with filtering can ignore the asymmetrical current, but it’s advisable to include a generous margin such as 2 x LRC. • Note – undervoltage protection (27) needed to trip motor on loss of power. Seconds Amps X 10 (Plot Ref. kV=4.16) 5000 hp 4.16 kV 650% LRC GE Multilin 469 Standard O/L Curve Pickup = 1.01 X FLC Curve Multiplier = 3 Hot M 30 kA @ 4.16 kV Hot Stall Time
  • 82. Slide 82 Conductor Overcurrent Protection LV Cables NEC 240.4 Protection of Conductors – conductors shall be protected against overcurrent in accordance with their ampacities (B) Devices Rated 800 A or Less – the next higher standard device rating shall be permitted (C) Devices Rated over 800 A – the ampacity of the conductors shall be ≥ the device rating NEC 240.91 Protection of Conductors (supervised locations, new in 2011) (B) Devices Rated Over 800 A – allows ampacity of at least 95% of breaker rating to be acceptable provided I2t withstand protection is provided. - Means that 3/phase 500 kcmil conductors at 380 A each for a total of 1140 A can be protection by a 1200 A breaker. - Does not mean you can operate the circuit at 1200 A.
  • 83. Slide 83 Conductor Overcurrent Protection NEC 240.6 Standard Ampere Ratings (A) Fuses & Fixed-Trip Circuit Breakers – cites all standard ratings (B) Adjustable Trip Circuit Breakers – Rating shall be equal to maximum setting (C) Restricted Access Adjustable-Trip Circuit Breakers – Rating can be equal to setting if access is restricted
  • 84. Slide 84 Conductor Overcurrent Protection MV Feeders & Branch Circuits NEC 240.101 (A) Rating or Setting of Overcurrent Protective Devices Fuse rating ≤ 3 times conductor ampacity Relay setting ≤ 6 times conductor ampacity MV Motor Conductors NEC 430.224 Size of Conductors Conductors ampacity shall be greater than the overload setting.
  • 85. Slide 85 Conductor Overcurrent Protection 1 – 3/C 350 kcmil Copper Rubber To = 90 deg. C Seconds Amps X 100 (Plot Ref. V=600) • The insulation temperature rating is typically used as the operating temperature (To). • The final temperature (Tf) depends on the insulation type (typically 150 deg. C or 250 deg. C). • When calculated by hand, you only need one point and then draw in at a -2 slope.
  • 87. Slide 87 Generator Overcurrent Protection • A generator’s fault current contribution decays over time. • Overcurrent protection must allow both for moderate overloads & be sensitive enough to detect the steady state contribution to a system fault. • Voltage controlled/ restrained relays (51V) are commonly used. • Per 1986 Buff Book, the pickup at full restraint is typically ≥ 150% of Full Load Current (FLC). • The pickup at no restraint must be < FLC/Xd . FLC/Xd Seconds Amps X 10 (Plot Ref. kV=12.47) GTG-101A No Load Constant Excitation AC Fault Current Momentary contribution (FLC/X”d) Interrupting contribution (FLC/X’d) FLC
  • 88. Slide 88 Generator 51V Pickup Setting Example Fg = FLC/Xd = 903 / 2.8 = 322.5 A 51V pickup (full restraint) > 150% FLC = 1354 A 51V pickup (no restraint) < 322.5 A 1200/5 Fg 51V 12.47 kV 19500 kVA 903 A Xd = 280%
  • 89. Slide 89 Generator 51V Pickup Setting Example 51V Setting > 1354/1200 = 1.13 Using 1.15, 51V pickup = 1.15 x 1200 A = 1380 A With old EM relays, 51V pickup (no restraint) = 25% of 1380 A = 345 A (> 322.5 A, not good) With new relays a lower MF can be set, such that 51V pickup (no restraint) = 20% of 1380 A = 276 A (< 322.5, so okay)
  • 90. Slide 90 Generator 51V Settings on TCC GTG-101A No Load Constant Excitation Total Fault Current 20% x Pickup Pickup = 1.15 x CT-Sec 30 kA Seconds Amps X 10 (Plot Ref. kV=12.47) • At 100% voltage the overcurrent function is fully restrained. • As the bus voltage decreases the restraint decreases and the characteristic curve shifts to the left. • There was no guidance in the 1986 Buff Book with respect to time delay. • Practically speaking, if the installation is not generator-limited, it is not possible to overload the generator. • To avoid nuisance tripping, especially on islanded systems, higher TDs are better. no restraint full restraint decreasing voltage
  • 91. Slide 91 Generator Overload Protection per 2001 Buff Book • C50.13, Section 4.2 discusses stator and rotor thermal limits. • C37.102, Section 4.1.1 provides the associated plot. • The 2001 Buff Book now references this discusses a different approach overload protection. • The approach uses a 50 device to control a 51. No mention of voltage. • Note that rotor negative sequence (I2t2) protection can be plotted on a TCC but is applicable to 46 protection, not 51V.
  • 93. Slide 93 Coordinating a System • TCCs show both protection & coordination. • Most OC settings should be shown/confirmed on TCCs. • Showing too much on a single TCC can make it impossible to read.
  • 94. Slide 94 Coordinating a System •Showing a vertical slice of the system can reduce crowding, but still be hard to read. •Upstream equipment is shown on multiple and redundant TCCs.
  • 95. Slide 95 Coordinating a System • A set of overlapping TCCs can be used to limit the amount of information on each curve and demonstrate coordination of the system from the bottom up. • Protection settings should be based on equipment ratings and available spare capacity – not simply on the present operating load and installed equipment. • Typical TCCs can be used to establish settings for similar installations. • Device settings defined on a given TCC are used as the starting point in the next upstream TCC. • The curves can be shown on an overall one-line of the system to illustrate the TCC coverage (Zone Map).
  • 96. Slide 96 Phase TCC Zone Map TCC-1 TCC-2 TCC-3 TCC-307J TCC-5 TCC-4 TCC-Comp TCC-6 TCC-212J TCC-101J
  • 97. Slide 97 Coordinating a System: TCC-1 Zone Map • Motor starting & protection is adequate. • Cable ampacity & withstand protection is adequate. • The MCC main breaker may trip for faults above 11 kA, but this cannot be helped. • The switchgear feeder breaker is selective with the MCC main breaker, although not necessarily required Seconds Amps X 100 (Plot Ref. kV=0.48)
  • 98. Slide 98 Coordinating a System: TCC-2 • The switchgear feeder breaker settings established on TCC-1 set the basis for this curve. • The main breaker is set to be selective with the feeder at all fault levels. • A CTI marker is not required since the characteristic curves include all margins and breaker operating times. • The main breaker curve is clipped at its through- fault current instead of the total bus fault current to allow tighter coordination of the upstream relay. (See TCC-3) Zone Map Seconds Amps X 100 (Plot Ref. kV=0.48) PWR FCB – 3P 42 kA @ 0.48 kV PWR MCB – 3P 30 kA @ 0.48 kV
  • 99. Slide 99 Coordinating a System: TCC-3 • The LV switchgear main breaker settings established on TCC-2 set the basis for this curve. • The transformer damage curve is based on frequent faults and is not shifted since the transformer is resistance grounded. • The primary side OC relay is selective with the secondary main and provides adequate transformer and feeder cable protection. • The primary OC relay instantaneous high enough to pass the secondary fault current and transformer inrush current. Zone Map Seconds Amps X 100 (Plot Ref. kV=0.48) Primary relay pickup of 546 A is high at 512% of transformer FLC, but meets Code.
  • 100. Slide 100 Coordinating a System: TCC-307J • This curve sets the basis for the upstream devices since its motor is the largest on the MCC. • Motor starting and overload protection is acceptable. • Motor feeder cable protection is acceptable • The motor relay includes a definite time unit to provide enhanced protection. • The definite time function is delayed to ensure fuse clears faults over the contactor rating. Zone Map Seconds Amps X 10 (Plot Ref. kV=4.16)
  • 101. Slide 101 Coordinating a System: TCC-4 • The 307J motor relay settings established on TCC-307J set the basis for this curve. • The tie breaker relay curve is plotted to the total bus fault current to be conservative. • The main breaker relay curve is plotted to its let-through current. • A coordination step is provided between the tie and main relay although this decision is discretionary. • The definite time functions insulate the CTIs from minor fault current variations. • All devices appear selectively coordinated at all fault current levels, but the independent OC functions may be an issue. Zone Map Seconds Amps X 10 (Plot Ref. kV=4.16)
  • 102. Slide 102 Coordinating a System: TCC-5 • The MV MCC main breaker settings established on TCC-4 set the basis for this curve. • The transformer damage curve is based on frequent faults and is not shifted since the transformer is resistance grounded. • The primary side OC relay is selective with the secondary main and provides adequate transformer and feeder cable protection. • The OC relay instantaneous high enough to pass the secondary fault current and transformer inrush current. Zone Map Seconds Amps X 10 (Plot Ref. kV=13.8) Primary relay pickup of 1000 A is 320 % of transformer FLC.
  • 103. Slide 103 Coordinating a System: TCC-Comp • Due to the compressor size, this curve may set the basis for the MV switchgear main breaker. • Motor starting and overload protection is acceptable. • Short-circuit protection is provided by the relay/breaker instead of a fuse as with the 1000 hp motor. • The short-circuit protection is delayed 50 ms to avoid nuisance tripping. Zone Map Seconds Amps X 10 (Plot Ref. kV=13.8)
  • 104. Slide 104 Coordinating a System: TCC-6 • The feeder breaker settings established on TCC-3, TCC-4, and TCC-Comp are shown as the basis for this curve. • The settings for feeder 52A1 (to the 2.4 MVA) could be omitted since it does not define any requirements. • A coordination step is provided between the tie and main relay although this decision is discretionary. • All devices are selectively coordinated at all fault current levels. • The definite time functions insulate the CTIs from minor fault current variations. Zone Map Seconds Amps X 10 (Plot Ref. kV=13.8)
  • 105. Slide 105 Ground TCC Zone Map TCC-G1 TCC-G2
  • 107. Slide 107 Coordination Quiz #1 Does this TCC look okay?? • There is no need to maintain a coordination interval between feeder breakers. • The 0.3-s CTIs are sufficient unless all relays are electro- mechanical and hand set. • Fix – base the setting of the feeder 2 relay on its downstream equipment and lower the time delays if possible. TR-FDR2 Main 2000/5 600/5 OCR OCR TR-FDR1 400/5 OCR SWGR-1 0.3 s 0.3 s Main-P OC1 TR-FDR2-P OC1 TR-FDR1-P OC1 Main-3P TR-FDR2-3P TR-FDR1-3P 15 kA @ 13.8 kV Seconds Amps X 100 (Plot Ref. kV=13.8)
  • 108. Slide 108 Coordination Quiz #2 Does this TCC look okay?? • The CTIs between the main and feeders are sufficient at the fault levels noted. • Assuming testing EM relays, the 0.62 s CTI cannot be reduced since the 0.30 s CTI is at the limit. • The main relay time delay is actually too fast since the CTI at 30 kA is less than 0.2 s. • Fix – raise the time delay setting of the main relay or make it less inverse. FDR-2 Main-1 2000/5 600/5 OCR OCR FDR-1 400/5 OCR SWGR-3 0.62 s 0.30 s Main-P OC1 FDR-2-P OC1 FDR-1-P OC1 Main-3P FDR-2-3P FDR-1-3P 30 kA @ 13.8 kV Seconds Amps X 100 (Plot Ref. kV=13.8)
  • 109. Slide 109 Coordination Quiz #3 Does this TCC look okay?? • The marked CTIs are okay, but…. • A main should never include an instantaneous setting. • Fix – delete the instantaneous on the main relay (!!) and raise the time delay to maintain a 0.2s CTI at 50 kA (assuming static relays) 0.47 s 0.33 s Main-3-P OC1 FDR--2-P OC1 FDR--1-P OC1 Main-3-3P FDR--2-3P FDR--1-3P 50 kA @ 13.8 kV FDR--2 Main-3 2000/5 600/5 OCR OCR FDR--1 400/5 OCR SWGR-4 Seconds Amps X 100 (Plot Ref. kV=13.8)
  • 110. Slide 110 Coordination Quiz #4 Does this TCC look okay?? • Primary relay pickup is 525% of transformer FLC, thus okay. • Transformer frequent fault protection is not provided by the primary relay, but this is okay – adequate protection is provided by the secondary main. • Cable withstand protection is inadequate. • Fix – Add instantaneous setting to the primary relay. Seconds Amps X 10 (Plot Ref. kV=13.8)
  • 111. Slide 111 Coordination Quiz #5 Seconds Amps X 10 (Plot Ref. kV=13.8) • Selectivity between Relay14 on the transformer primary and CB44 on the secondary is not provided, but this can be acceptable. • Relay 14 is not, however, selectively coordinated with feeder breaker CB46. • Fix – raise Relay14 time delay setting and add CTI marker. 0.08 s Does this TCC look okay??
  • 112. Slide 112 Coordination Quiz #6 Does this TCC look okay?? • Crossing of feeder characteristics is no problem. • There is no need to maintain an intentional time margin between two LV static trip units – clear space is sufficient. • Fix – lower the main breaker short-time delay band. 0.21 s LVMain LVFDR2 LVFDR1 LVMain – 3P 30 kA @ 0.48 kV LVFDR2 – 3P LVFDR1 – 3P 45 kA @ 0.48 kV Seconds Amps X 100 (Plot Ref. kV=0.48)
  • 113. Slide 113 Coordination Quiz #7 Does this TCC look okay?? • The source relays should not be plotted to the full bus fault level unless their plots are shifted based on: SF = Total fault current / relay current. • Since each relay actually sees less than the total fault current, the CTIs are actually much higher than 0.3 s. • Fix – plot the source relays to their actual fault current or apply SF. 0.3 s Source1 - P OC1 Feeder - P OC1 Source2 - P OC1 Source1 - 3P Source2 – 3P Feeder – 3P 15 kA @ 13.8 kV Seconds Amps X 100 (Plot Ref. kV=13.8) 10 kA 5 kA
  • 114. Slide 114 Coordination Quiz #8 Does this TCC look okay?? • The displayed CTI of 0.2 s is acceptable. • But, if the main relay’s overcurrent elements are independent then there is miscoordination. • Fix – set minimum response time (if available), raise TD of main, or make curve less inverse. Seconds Amps X 100 (Plot Ref. kV=12.5)
  • 115. Slide 115 Coordination Quiz #9 Does this TCC look okay?? • There are two curves to be concerned with for a 51V – full restraint and zero restraint. • Assuming the full restraint curve is shown, it is coordinated too tightly with the feeder. • The 51V curve will shift left and lose selectivity with the feeder if a close-in fault occurs and the voltage drops. • Fix – show both 51V curves and raise time delay. 0.30 s 51V - P OC1 FDR-5 - P OC1 51V – 3P FDR-5 – 3P 15 kA @ 13.8 kV Seconds Amps X 100 (Plot Ref. kV=12.5)
  • 117. Slide 117 Coordination Software • Computer-aided coordination software programs originated in the mid 1980s. • The accuracy of the device characteristic curves was often highly questionable. • There are numerous, much more powerful programs available today, many of which are very mature. • Even still, the accuracy of the protective devices functions and characteristics is still extremely critical.
  • 118. Slide 118 Coordination Software • For many years clients maintained separate impedance models for power studies and protective device models for coordination studies. • Integrated models are now the norm and are required to support arc-flash studies.
  • 120. Slide 120 Selected References • Applied Protective Relaying – Westinghouse • Protective Relaying – Blackburn • IEEE Std 242 – Buff Book • IEEE Std 141 – Red Book • IEEE Std 399 – Brown Book • IEEE C37.90 – Relays • IEEE C37.91 – Transformer Protection • IEEE C37.102 – Guide for AC Generator Protection • IEEE C50.13 – Cylindrical-Rotor Gens ≥ 10 MVA • NFPA 70 – National Electrical Code