SlideShare a Scribd company logo
1 of 6
Download to read offline
The mechanism of modification of public
procurement contracts during their course
under Instruction No. 1 dated 7 March 2016
and Law No. 98/2016 on public procurements
The mechanism of modification of public
procurement contracts during their
course under Instruction No. 1 dated
7 March 2016 and Law No. 98/2016 on
public procurements
Anca Dobrescu
Lawyer
Events which can cause delay to
completion of a project
Erdal Asim
Manager of Forensic Planning
Department International
Athanasios Stigas named as Executive
Director; Mihaela Vulpescu succeeds him
as Manager of Contracts Department
5
Issue 8, September 2016
Anca Dobrescu
Lawyer
6
Under Instruction 1/2016, the application of the contractual clauses is considered mechanical when it does not incur
any decision to be taken by any contracting party (or by persons nominated by the Employer, e.g. the Engineer, the
Designer, Site Engineer on FIDIC contracts) with regard to the opportunity of modification, but which is mechanical
duetothefactthatthecontractclearlyprovidesthatinsomecases,eventsorcircumstances,achangewillbeadopted.
1
____________
I. Introduction
Instruction No. 1/2016 regarding the
modification of public procurement
contracts during their validity period and
determination of whether or not
modifications are substantial (“Instruction
1/2016”), issued by the National Agency of
Public Procurements and published within
Official Gazette no. 171 dated 7 March 2016,
entered into force on the same day and
apply to all contracts including those
concluded priortothisdate.
Law no. 98/2016 on public procurements
(“Law 98/2016”), issued by the Romanian
Parliament and published within Official
Gazette no. 390 dated 23 May 2016,
entered intoforceon26May2016.
The main scope of Instruction 1/2016 is to
establish whether or not modifications of
such contracts are substantial or
insubstantial, and to eliminate differing
interpretations of such changes. The
conditions of modification of contracts
should be read in conjunction with Law
98/2016 regarding the modification of
publicprocurement contracts.
II. When are modifications considered
tobesubstantial orinsubstantial?
According to Instruction 1/2016, changes
resulting from the application of
contractual clauses do not represent a
modification of the initial contract, but
only the application of the provisions of
the initial contract, if the following
conditions aremet:
) such changes are clearly stipulated in
the contract as being “change clauses”,
which must be known by all tenderers and
must denote an objective method of
calculation of the final contract price to be
paid in order to avoid discretionary
modification during the course of the
contract which could affect the initial
conditions ofthetender;
ii) such changes are caused by the
mechanical application of change clauses
present in the initial contract, excluding
any modifications of the requirements of
theinitial contract.
For example, in the case of a FIDIC “Red-
Book” contract where the Employer is
responsible for the design, the differences
between the quantities initially estimated
by the Employer and the quantities
derived from the provisions of Clause 12,
without modification of the technical
design, would not be considered as
substantial modifications, should such
Issue 8, September 2016
AccordingtoInstruction1/2016,insubstantialmodificationsofcontractsinforcedonotrepresentanewassignmentanddonotrequireare-tenderprocedure.
____________
2
differences be due only to discrepancies
between the initial estimates and those
derived by Clause 12, without influence from
changes to the technical design or the
technical specification. However, should the
differences in quantities be due to other
modifications, such as changes to the
t e c h n i c a l d e s i g n o r t h e t e c h n i c a l
specification, then such differences would
not be considered as Clause 12 measurement
differences, as they would be evaluated as
Variations under the provisions of Clause 13.
Thus, it could be concluded that the effect of
either of these examples may lead to an
increase or decrease of the contract price,
and therefore the Employer may have to
conclude an addendum to the contract, for
budgetary reasons.
The conditions of application of “change
clauses” willnotbefulfilled, ifforexample:
( ) the method of calculation of the final
contract price tobepaid was not defined inan
objective wayintheinitial contract; or
(ii) the change of quantities/price to be
paid was not clearly specified in the contract,
but results from other events, such as
modification to the technical design during
the performance of the contract due to
defects in the initial design or supplementing
new works, which had not been envisaged
initially, orothercauses.
Any change to quantities or price which does
not result from the application of the initial
contractual provisions will be analyzed as
modifications to the contract; thus if such
modifications are considered to be
substantial, theEmployer wouldbeobliged to
organize are-tender procedure.
III. When are modifications considered
insubstantial?
According to Instruction 1/2016, a
modification shallbeconsidered insubstantial
when the following conditions are
cumulatively met:
) the modification does not introduce
conditions that were not included in the initial
tendering procedure that would have
permitted the selection of other candidates
than those initially selected ortheselection of
a tenderer other than the winner, nor does it
allow the participation of other economic
operators intheprocedure;
ii) the modification does not change the
economic balance of the contract in favor of
theContractor; and
iii) the modification does not considerably
extendthemainobjectofthecontract.
In addition to the abovementioned
conditions, in order to establish whether or
not a modification is insubstantial, the
Employer shall analyze whether the following
conditions aremet:
) the modification is associated to a
contact of services or works relating to public
investments;
ii) the modification does not exceed
“various expenses and unanticipated” and
10%increase intheinitial contract price;
iii) the modification is strictly necessary in
order to fulfil the public procurement
contract;
iv) the modification is in direct conjunction
with the objective of the public procurement
contract; and
v) the general character of the contract
remains unchanged.
IV. When are modifications considered
substantial?
According to Instruction 1/2016, a
modification shall beconsidered substantial if
the conditions above, i.e. Section III, points i)
to v) are not met but at least one of the
following conditions ismet:
) the modification introduces conditions
that, had such conditions been included in the
initial tender procedure, would have allowed
the selection of other tenderers than those
initially selected, or it would have allowed the
contract tobeassigned toanother tenderer;
ii) the modification implies a change to the
economic balance of the contract in favor of
theContractor; and
iii) the modification substantially extends
the coverage of the contract in terms of
products, services or works which it did not
initially cover.
In the case when a modification to a public
procurement contract during its course is
considered to be substantial, the Employer is
obliged toorganize are-tender procedure.
Under Law 98/2016, modifications are
considered to be substantial and thus require
anewtenderprocedure, if:
) the modification introduces conditions
that, had such conditions been included in the
initial tender procedure, would have allowed
the selection of other tenderers than those
initially selected or the acceptance of another
offer than originally accepted, or that would
have implied more tenderers in the tender
procedure;
ii) the modification implies a change to the
economic balance of the contract in favor of
the Contractor in a manner which was not
initially provided inthecontract;
iii) the modification substantially extends
theobjective ofthecontract; or
iv) the original Contractor is replaced by a
newContractor.
V. Conclusions
The necessity to adopt Instruction No. 1 dated
7 March 2016 and to amend the law on public
procurement contracts arose from issues
that Employers and Contractors have
confronted during the course of their
contracts, namely whether to conclude an
addendum to the contract in order to reflect
modifications or to organize a new tender
procedure. How such modifications affect the
contract, and whether or not they are
substantial.
Instruction 1/2016 and Law 98/2016 provide
Employers and Contractors with a certain
degree of the means by which to avoid
differing interpretations with regard to
modifications of contracts, which may
becomenecessary duringtheirdevelopment.
construction projects and can be processed
on behalf of the contractor by our delay
analysts. One key aspect of delay analysis is
that delay to completion can be caused by
oneoracombinationofseveraloftheselisted
events, or more likely a complex mix of the
effects of these events. The time of their
occurrence and who was responsible for the
events only serves to add to the difficulty of
theanalysis:
( ) Errors and omissions in the contract
documents,asfollows:
- Missinginformation;
- Erroneousinformation;
- Absence of a phasing plan in the bid
documents,whenthesiteworkrequiresparts
oftheWorkstobeprogressedinphases;
- Conflictinginformationthatentaildesign
revisions.
(ii) Delaysforreasonsbeyondthecontractor
orowner'scontrol,asfollows:
- Labour force strikes or other similar
industrialactions;
- Outofstatemanufacturer'sshutdown;
- A subcontractor going out of business
partwaythroughtheproject;
- Unusualweatherconditions.
(iii) Owner caused delays, for reasons under
theircontrol,suchas:
- Scopechanges;
- Limiting the contractor's access to parts
ofthesite;
- Cashflowdifficulties;
- Late processing of contractor's requests
forclarificationsand/orchangeorders;
- A higher-level political factor that may
haveaffectedprogress.
(iv) Contractor caused delays, for reasons
undertheircontrol,suchas:
- Insufficientlabourforceonsite;
- Contractual problems or disputes
between the prime contractor and its
subcontractors;
Erdal Asim
Manager of Forensic Planning
Department International
Events which can cause delay to completion of a project
I. Introduction
Construction contracts typically involve
adeadlineforthecompletionoftheWorks(or
designated sections thereof) and as a
consequence, contractual agreements will
often place reliance upon programming. In
general terms, delays represent additional
costs to the Parties, either as a consequence
of late facility occupancy or other factors and
additional costs incurred compared with
budgeted costs, where actual activity
durations may be compared with anticipated
durations.
Construction projects often suffer delay
due to a wide variety of reasons, which can
have severe financial effects on the project.
As a result, delay claims will likely be filed by
the contractor. The analysis of the effects of
delays on critical (near critical or non-critical)
activities is one of the most complicated
types of analysis. It requires an expert who
has an extensive knowledge of construction
projects, the means and methods of
scheduling,andtheabilitytodevelopasound
methodology upon which the analysis should
beconducted.
Most delay claims do not reach the expert
until after completion of the project, which
often entails a detailed and intensive
retrospective research into the documents to
verify schedules, events, sequence of work,
changes during construction and the
circumstances that would evidence the delay
effectofsuchevents.
II. Ascertainingthecauseofdelays
One of the main steps in ascertaining the
cause of delay (known as 'causation') is to
research documents related to the project in
order to evidence events which may have
caused delay to completion of the Works
(or designated sections thereof). The
methodology used to ascertain the effect of
these events is at the heart of this type of
analysis and the difficulties in ensuring a
sustainable claim. Owners and contractors
who realize the potential for construction
disputes and conflicts rely on the
construction claims consultants who are
experienced construction managers and
engineers.
Below is a list of commonly encountered
events which often cause delay to
Issue 8, September 2016
- InternalCashflowissues;
- Lack of proper planning and
managementoftheproject.
(v) Personality conflicts between the
membersoftheprojectteam:
- Inter-personality disagreements often
make things difficult on site, which cause
delays. In this case, each party will blame the
otherforthedelay.
The resulting category of delays can be
expressedasfollows:
( ) ByOrigin:
- EmployerRiskEvent(ERE);
- ContractorRiskEvent(CRE);
- ThirdPartyEvent.
(ii) ByCompensability:
- Excusable Compensable (additional
timeandmoneygrantedtocontractor);
- ExcusableNon-compensable(additional
timegrantedwithoutmoney);
- Non-excusable (no additional time and
moneyaregranted).
(iii) ByTiming:
- Concu rrent (i. e. separate e v e n ts
produced by both parties, each delaying
activities on the critical path, which occur at
the same time).
- Non-concurrent (i.e. separate events
produced by both parties, each delaying
activities on the critical path, which occur at
different times).
Oncethecausesofdelayhavebeenestablished
and the chronology of the events has been
reviewed, in order to identify the effected of
those delays on the activities within the
Programme of Works, a sub-network or
“fragnet” is prepared representing the event
as though it was an activity, in order to produce
a retrospective and prospective graphical
representationof“cause”fortheDelayAnalysis.
The “fragnets” must be sustained by evidence
comprising contemporaneous correspondence
and other documents, such as minutes of
meeting, daily reports, monthly reports,
photographic reports, meteorological statistics
and such like, which evidence the “cause” with
certainty.
If the events are ongoing and their effect has not
ceased, then periodic updates of the fragnets
related to continuing or new events must be
produced. This process is helpful for the
evaluation of the impact (“effect”) of the event
or the impact of combinations of multiple events
ontheCompletionDate.
Issue 8, September 2016
4
The Board of Directors (the Board) is pleased
to announce two major changes aimed at
further strengthening the Company's
leadershipteam.Thechangesare:
· The nomina tion of Mr. Athanasios
Stigas as Executive Director and Member of
theBoard
· The promotion of Mrs. Mihaela Vulpescu
asManagerofContractsDepartment.
In making the announcement, Mr. Giovanni Di
Folco, President & Senior Partner of Techno
Engineering & Associates, expressed his
appreciation:
“We are delighted to welcome Mr. Stigas to
the Board. His extensive experience on large
infrastructure projects both in Greece and
Romania will be of great benefit to TE&A, as
we are impressed by the sense of ambitious
vision, commitment and level of energy that
Mr. Stigas brings to this position. I am
delighted that he has accepted the Board's
invitation to embrace this new and very
important assignment and I am sure that
under his leadership TE&A will enjoy
unprecedented success. Mr. Stigas, whose
strong values are an example to all, has
proved over the years his worth as an
experienced civil engineer and manager. That
coupled with his outstanding contract and
claims management skills, honesty, talent and
loyalty has resulted in him being a superb
choice to replace Mr. Emanuele Lancellotti,
stepping down from the Board and having
served for the past two years as Executive
Director.Emanuelehasbeenamajorinfluence
in TE&A's developmentand he leaves with our
best wishes for the future. Mr. Stigas' skills
and background will assist TE&A to deliver the
high performance outcomes we expect from
our existing collaborations and progress the
strong development opportunities in our
assetportfolio”.
Mr. Athanasios Stigas, Executive Director,
sharedhiscomment:
5
Athanasios Stigas named as Executive Director
Mihaela Vulpescu succeeds him as Manager of Contracts Department
Issue 8, September 2016
“I am honored and privileged to be appointed
in the position of Executive Director of TE&A.
Since joining the company five years ago, I
have been very impressed by the strength and
depth of talent within our organization. I am
excited to be assuming the leadership of the
business and building the same under Mr. Di
Folco's outstanding direction. I look forward
to working with the management team as we
continue to drive profitable growth and
performanceacrossTE&A'sglobaloffices.”
Mr. Stigas brings with him unparalleled
experience and understanding of the
construction industry. He was previously
Manager of Contracts Department and Unit
Chief Contracts Manager at TE&A, having
begun his career working for major Greek
companies, where he has previously held a
variety of positions, including Construction
Manager, Production manager and Deputy
ProjectManager.
The announcement of Mr. Stigas's elevation
was accompanied by the promotion of Mrs.
MihaelaVulpescu,who will succeed himas the
new Manager of Contracts Department. The
Board is grateful for her willingness to take on
an expanded role in the organization. “Over
the past years we find Mrs Mihaela Vulpescu
as a very responsible, hardworking and
therefore valuable member of our company,
having over five years' of experience in
contract management with us. She has shown
her ability to accomplish her tasks very well
indeed, and she has performed her duties to
our full satisfaction. We had no hesitation in
promoting her. Given the right motivation,
she has the ability and the determination to
excel”,Mr.DiFolcoadded.
We are confident as a Board that they will not
only maintain the high standards with which
TE&A is associated, but will lead the Company
to become even more effective. The Board
welcomesbothofthemintheirnewroles!
Athanasios Stigas
Executive Director
Mihaela Vulpescu
Manager of Contracts Department
6
Issue 8, September 2016

More Related Content

What's hot

Construction Law Final Report
Construction Law Final ReportConstruction Law Final Report
Construction Law Final ReportArissa Loh
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014SHKLaw
 
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...Divyanshu Dayal
 
IAS 11
IAS 11IAS 11
IAS 11RS P
 
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...Praveen Premkumar
 
International construction contract
International construction contractInternational construction contract
International construction contractGlobal Negotiator
 
contract administration PPT
 contract administration PPT contract administration PPT
contract administration PPTKEVINMISTRY8
 
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr  ias 11 construction contract presentation by MOHSIN MUMTAZCfr  ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZmianmohsinmumtazshb
 
Construction Law - Presentation - Construction Contractual Claims
Construction Law - Presentation - Construction Contractual ClaimsConstruction Law - Presentation - Construction Contractual Claims
Construction Law - Presentation - Construction Contractual ClaimsYee Len Wan
 
CL Final Report
CL Final ReportCL Final Report
CL Final ReportMelvin Lim
 
LAW ON PUBLIC PROCUREMENT CONTRACTS
LAW ON PUBLIC PROCUREMENT CONTRACTSLAW ON PUBLIC PROCUREMENT CONTRACTS
LAW ON PUBLIC PROCUREMENT CONTRACTSauthors boards
 
Types of contracts
Types of contracts   Types of contracts
Types of contracts MANNU KUMAR
 
types of contracts
 types of contracts types of contracts
types of contractsKEVINMISTRY8
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14마 이환
 
Construction contract
Construction contract Construction contract
Construction contract Rakshith Reddy
 

What's hot (20)

Construction Law Final Report
Construction Law Final ReportConstruction Law Final Report
Construction Law Final Report
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
 
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
 
Chapter 2- Contract Management
Chapter 2- Contract ManagementChapter 2- Contract Management
Chapter 2- Contract Management
 
IAS 11
IAS 11IAS 11
IAS 11
 
Audit of contracts version 2
Audit of contracts version 2Audit of contracts version 2
Audit of contracts version 2
 
Defects liability
Defects liabilityDefects liability
Defects liability
 
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
 
International construction contract
International construction contractInternational construction contract
International construction contract
 
contract administration PPT
 contract administration PPT contract administration PPT
contract administration PPT
 
Document samples
Document samplesDocument samples
Document samples
 
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr  ias 11 construction contract presentation by MOHSIN MUMTAZCfr  ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
 
Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]
 
Construction Law - Presentation - Construction Contractual Claims
Construction Law - Presentation - Construction Contractual ClaimsConstruction Law - Presentation - Construction Contractual Claims
Construction Law - Presentation - Construction Contractual Claims
 
CL Final Report
CL Final ReportCL Final Report
CL Final Report
 
LAW ON PUBLIC PROCUREMENT CONTRACTS
LAW ON PUBLIC PROCUREMENT CONTRACTSLAW ON PUBLIC PROCUREMENT CONTRACTS
LAW ON PUBLIC PROCUREMENT CONTRACTS
 
Types of contracts
Types of contracts   Types of contracts
Types of contracts
 
types of contracts
 types of contracts types of contracts
types of contracts
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14
 
Construction contract
Construction contract Construction contract
Construction contract
 

Similar to Mechanism of Modifying Public Procurement Contracts

Contract management , GFR Rules, Sampling and Testing.pptx
Contract management , GFR Rules, Sampling and Testing.pptxContract management , GFR Rules, Sampling and Testing.pptx
Contract management , GFR Rules, Sampling and Testing.pptxsumitmmmecce
 
Variation: it’s Regulation & Management under the MDB-FIDIC (2006) & the PPA ...
Variation: it’s Regulation & Management under the MDB-FIDIC (2006) & the PPA ...Variation: it’s Regulation & Management under the MDB-FIDIC (2006) & the PPA ...
Variation: it’s Regulation & Management under the MDB-FIDIC (2006) & the PPA ...MMS presentation firm
 
Variations under the FIDIC form, subject to EU Procurement law
Variations under the FIDIC form, subject to EU Procurement lawVariations under the FIDIC form, subject to EU Procurement law
Variations under the FIDIC form, subject to EU Procurement law39 Essex Chambers
 
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيدالمحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيدEgyptian Engineers Association
 
Vietnam Accounting Standards - VAS 15 Construction contracts
Vietnam Accounting Standards - VAS 15 Construction contractsVietnam Accounting Standards - VAS 15 Construction contracts
Vietnam Accounting Standards - VAS 15 Construction contractsAC&C Consulting Co., Ltd.
 
Seb Oram - The 2015 CDM Regulations - changes and impact on litigation
Seb Oram - The 2015 CDM Regulations - changes and impact on litigationSeb Oram - The 2015 CDM Regulations - changes and impact on litigation
Seb Oram - The 2015 CDM Regulations - changes and impact on litigationSeb Oram
 
TE&A's Newsletter, April, 2019
TE&A's Newsletter, April, 2019TE&A's Newsletter, April, 2019
TE&A's Newsletter, April, 2019Cerasela Angelescu
 
Procurement Problems In The Credit Crunch
Procurement Problems In The Credit CrunchProcurement Problems In The Credit Crunch
Procurement Problems In The Credit Crunchjohnmunton
 
Covid-19-and-NEC4.pdf
Covid-19-and-NEC4.pdfCovid-19-and-NEC4.pdf
Covid-19-and-NEC4.pdfShingFaatWong
 
dokumen.tips_fidic-power-point-presentation.pdf
dokumen.tips_fidic-power-point-presentation.pdfdokumen.tips_fidic-power-point-presentation.pdf
dokumen.tips_fidic-power-point-presentation.pdfafadlalla
 
Techno Engineering & Associates
Techno Engineering & AssociatesTechno Engineering & Associates
Techno Engineering & AssociatesCerasela Angelescu
 
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...tdartnell
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2Shze Hwa Lee
 

Similar to Mechanism of Modifying Public Procurement Contracts (20)

ICDS : Construction Contracts
ICDS : Construction ContractsICDS : Construction Contracts
ICDS : Construction Contracts
 
UK Adjudicators Newsletter August 2021
UK Adjudicators Newsletter August 2021UK Adjudicators Newsletter August 2021
UK Adjudicators Newsletter August 2021
 
Pp2 asignment-1
Pp2 asignment-1Pp2 asignment-1
Pp2 asignment-1
 
Contract management , GFR Rules, Sampling and Testing.pptx
Contract management , GFR Rules, Sampling and Testing.pptxContract management , GFR Rules, Sampling and Testing.pptx
Contract management , GFR Rules, Sampling and Testing.pptx
 
Variation: it’s Regulation & Management under the MDB-FIDIC (2006) & the PPA ...
Variation: it’s Regulation & Management under the MDB-FIDIC (2006) & the PPA ...Variation: it’s Regulation & Management under the MDB-FIDIC (2006) & the PPA ...
Variation: it’s Regulation & Management under the MDB-FIDIC (2006) & the PPA ...
 
Variations under the FIDIC form, subject to EU Procurement law
Variations under the FIDIC form, subject to EU Procurement lawVariations under the FIDIC form, subject to EU Procurement law
Variations under the FIDIC form, subject to EU Procurement law
 
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيدالمحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
 
Vietnam Accounting Standards - VAS 15 Construction contracts
Vietnam Accounting Standards - VAS 15 Construction contractsVietnam Accounting Standards - VAS 15 Construction contracts
Vietnam Accounting Standards - VAS 15 Construction contracts
 
Cl report final
Cl report finalCl report final
Cl report final
 
Seb Oram - The 2015 CDM Regulations - changes and impact on litigation
Seb Oram - The 2015 CDM Regulations - changes and impact on litigationSeb Oram - The 2015 CDM Regulations - changes and impact on litigation
Seb Oram - The 2015 CDM Regulations - changes and impact on litigation
 
TOPIC7.pdf
TOPIC7.pdfTOPIC7.pdf
TOPIC7.pdf
 
TE&A's Newsletter, April, 2019
TE&A's Newsletter, April, 2019TE&A's Newsletter, April, 2019
TE&A's Newsletter, April, 2019
 
Procurement Problems In The Credit Crunch
Procurement Problems In The Credit CrunchProcurement Problems In The Credit Crunch
Procurement Problems In The Credit Crunch
 
Covid-19-and-NEC4.pdf
Covid-19-and-NEC4.pdfCovid-19-and-NEC4.pdf
Covid-19-and-NEC4.pdf
 
dokumen.tips_fidic-power-point-presentation.pdf
dokumen.tips_fidic-power-point-presentation.pdfdokumen.tips_fidic-power-point-presentation.pdf
dokumen.tips_fidic-power-point-presentation.pdf
 
Jbcc - out with the old
Jbcc - out with the oldJbcc - out with the old
Jbcc - out with the old
 
Techno Engineering & Associates
Techno Engineering & AssociatesTechno Engineering & Associates
Techno Engineering & Associates
 
Implications of different_types_of_variation_under_fidic_1999_redbook
Implications of different_types_of_variation_under_fidic_1999_redbookImplications of different_types_of_variation_under_fidic_1999_redbook
Implications of different_types_of_variation_under_fidic_1999_redbook
 
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
Bcd4 standard building_contract_(without_quantities)_and_schedule_of_contract...
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 

More from Cerasela Angelescu

FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...
FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...
FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...Cerasela Angelescu
 
Understanding the Importance of Risk
Understanding the Importance of RiskUnderstanding the Importance of Risk
Understanding the Importance of RiskCerasela Angelescu
 
Letters of Intent, Bonds & Guarantees, Defects Liability Periods
Letters of Intent, Bonds & Guarantees, Defects Liability PeriodsLetters of Intent, Bonds & Guarantees, Defects Liability Periods
Letters of Intent, Bonds & Guarantees, Defects Liability PeriodsCerasela Angelescu
 
Enforcement of a DAB decision in Arbitration. Part I
Enforcement of a DAB decision in Arbitration. Part IEnforcement of a DAB decision in Arbitration. Part I
Enforcement of a DAB decision in Arbitration. Part ICerasela Angelescu
 

More from Cerasela Angelescu (10)

Newsletter TE&A
Newsletter TE&ANewsletter TE&A
Newsletter TE&A
 
FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...
FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...
FIDIC-ACEG European Regional Infrastructure Conference, 6-7 March 2018, Tbili...
 
TE&A news
TE&A newsTE&A news
TE&A news
 
Against all odds
Against all odds Against all odds
Against all odds
 
Newsletter august
Newsletter augustNewsletter august
Newsletter august
 
December Newsletter
December NewsletterDecember Newsletter
December Newsletter
 
Understanding the Importance of Risk
Understanding the Importance of RiskUnderstanding the Importance of Risk
Understanding the Importance of Risk
 
Letters of Intent, Bonds & Guarantees, Defects Liability Periods
Letters of Intent, Bonds & Guarantees, Defects Liability PeriodsLetters of Intent, Bonds & Guarantees, Defects Liability Periods
Letters of Intent, Bonds & Guarantees, Defects Liability Periods
 
Let's pick a TE&A news
Let's pick a TE&A newsLet's pick a TE&A news
Let's pick a TE&A news
 
Enforcement of a DAB decision in Arbitration. Part I
Enforcement of a DAB decision in Arbitration. Part IEnforcement of a DAB decision in Arbitration. Part I
Enforcement of a DAB decision in Arbitration. Part I
 

Recently uploaded

Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdfOrient Homes
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfmuskan1121w
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...lizamodels9
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...lizamodels9
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...lizamodels9
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Serviceankitnayak356677
 

Recently uploaded (20)

Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdf
 
rishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdfrishikeshgirls.in- Rishikesh call girl.pdf
rishikeshgirls.in- Rishikesh call girl.pdf
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
Best Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting PartnershipBest Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting Partnership
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
 

Mechanism of Modifying Public Procurement Contracts

  • 1. The mechanism of modification of public procurement contracts during their course under Instruction No. 1 dated 7 March 2016 and Law No. 98/2016 on public procurements The mechanism of modification of public procurement contracts during their course under Instruction No. 1 dated 7 March 2016 and Law No. 98/2016 on public procurements Anca Dobrescu Lawyer Events which can cause delay to completion of a project Erdal Asim Manager of Forensic Planning Department International Athanasios Stigas named as Executive Director; Mihaela Vulpescu succeeds him as Manager of Contracts Department 5 Issue 8, September 2016 Anca Dobrescu Lawyer 6 Under Instruction 1/2016, the application of the contractual clauses is considered mechanical when it does not incur any decision to be taken by any contracting party (or by persons nominated by the Employer, e.g. the Engineer, the Designer, Site Engineer on FIDIC contracts) with regard to the opportunity of modification, but which is mechanical duetothefactthatthecontractclearlyprovidesthatinsomecases,eventsorcircumstances,achangewillbeadopted. 1 ____________ I. Introduction Instruction No. 1/2016 regarding the modification of public procurement contracts during their validity period and determination of whether or not modifications are substantial (“Instruction 1/2016”), issued by the National Agency of Public Procurements and published within Official Gazette no. 171 dated 7 March 2016, entered into force on the same day and apply to all contracts including those concluded priortothisdate. Law no. 98/2016 on public procurements (“Law 98/2016”), issued by the Romanian Parliament and published within Official Gazette no. 390 dated 23 May 2016, entered intoforceon26May2016. The main scope of Instruction 1/2016 is to establish whether or not modifications of such contracts are substantial or insubstantial, and to eliminate differing interpretations of such changes. The conditions of modification of contracts should be read in conjunction with Law 98/2016 regarding the modification of publicprocurement contracts. II. When are modifications considered tobesubstantial orinsubstantial? According to Instruction 1/2016, changes resulting from the application of contractual clauses do not represent a modification of the initial contract, but only the application of the provisions of the initial contract, if the following conditions aremet: ) such changes are clearly stipulated in the contract as being “change clauses”, which must be known by all tenderers and must denote an objective method of calculation of the final contract price to be paid in order to avoid discretionary modification during the course of the contract which could affect the initial conditions ofthetender; ii) such changes are caused by the mechanical application of change clauses present in the initial contract, excluding any modifications of the requirements of theinitial contract. For example, in the case of a FIDIC “Red- Book” contract where the Employer is responsible for the design, the differences between the quantities initially estimated by the Employer and the quantities derived from the provisions of Clause 12, without modification of the technical design, would not be considered as substantial modifications, should such
  • 2. Issue 8, September 2016 AccordingtoInstruction1/2016,insubstantialmodificationsofcontractsinforcedonotrepresentanewassignmentanddonotrequireare-tenderprocedure. ____________ 2 differences be due only to discrepancies between the initial estimates and those derived by Clause 12, without influence from changes to the technical design or the technical specification. However, should the differences in quantities be due to other modifications, such as changes to the t e c h n i c a l d e s i g n o r t h e t e c h n i c a l specification, then such differences would not be considered as Clause 12 measurement differences, as they would be evaluated as Variations under the provisions of Clause 13. Thus, it could be concluded that the effect of either of these examples may lead to an increase or decrease of the contract price, and therefore the Employer may have to conclude an addendum to the contract, for budgetary reasons. The conditions of application of “change clauses” willnotbefulfilled, ifforexample: ( ) the method of calculation of the final contract price tobepaid was not defined inan objective wayintheinitial contract; or (ii) the change of quantities/price to be paid was not clearly specified in the contract, but results from other events, such as modification to the technical design during the performance of the contract due to defects in the initial design or supplementing new works, which had not been envisaged initially, orothercauses. Any change to quantities or price which does not result from the application of the initial contractual provisions will be analyzed as modifications to the contract; thus if such modifications are considered to be substantial, theEmployer wouldbeobliged to organize are-tender procedure. III. When are modifications considered insubstantial? According to Instruction 1/2016, a modification shallbeconsidered insubstantial when the following conditions are cumulatively met: ) the modification does not introduce conditions that were not included in the initial tendering procedure that would have permitted the selection of other candidates than those initially selected ortheselection of a tenderer other than the winner, nor does it allow the participation of other economic operators intheprocedure; ii) the modification does not change the economic balance of the contract in favor of theContractor; and iii) the modification does not considerably extendthemainobjectofthecontract. In addition to the abovementioned conditions, in order to establish whether or not a modification is insubstantial, the Employer shall analyze whether the following conditions aremet: ) the modification is associated to a contact of services or works relating to public investments; ii) the modification does not exceed “various expenses and unanticipated” and 10%increase intheinitial contract price; iii) the modification is strictly necessary in order to fulfil the public procurement contract; iv) the modification is in direct conjunction with the objective of the public procurement contract; and v) the general character of the contract remains unchanged. IV. When are modifications considered substantial? According to Instruction 1/2016, a modification shall beconsidered substantial if the conditions above, i.e. Section III, points i) to v) are not met but at least one of the following conditions ismet: ) the modification introduces conditions that, had such conditions been included in the initial tender procedure, would have allowed the selection of other tenderers than those initially selected, or it would have allowed the contract tobeassigned toanother tenderer; ii) the modification implies a change to the economic balance of the contract in favor of theContractor; and iii) the modification substantially extends the coverage of the contract in terms of products, services or works which it did not initially cover. In the case when a modification to a public procurement contract during its course is considered to be substantial, the Employer is obliged toorganize are-tender procedure. Under Law 98/2016, modifications are considered to be substantial and thus require anewtenderprocedure, if: ) the modification introduces conditions that, had such conditions been included in the initial tender procedure, would have allowed the selection of other tenderers than those initially selected or the acceptance of another offer than originally accepted, or that would have implied more tenderers in the tender procedure; ii) the modification implies a change to the economic balance of the contract in favor of the Contractor in a manner which was not initially provided inthecontract; iii) the modification substantially extends theobjective ofthecontract; or iv) the original Contractor is replaced by a newContractor. V. Conclusions The necessity to adopt Instruction No. 1 dated 7 March 2016 and to amend the law on public procurement contracts arose from issues that Employers and Contractors have confronted during the course of their contracts, namely whether to conclude an addendum to the contract in order to reflect modifications or to organize a new tender procedure. How such modifications affect the contract, and whether or not they are substantial. Instruction 1/2016 and Law 98/2016 provide Employers and Contractors with a certain degree of the means by which to avoid differing interpretations with regard to modifications of contracts, which may becomenecessary duringtheirdevelopment.
  • 3. construction projects and can be processed on behalf of the contractor by our delay analysts. One key aspect of delay analysis is that delay to completion can be caused by oneoracombinationofseveraloftheselisted events, or more likely a complex mix of the effects of these events. The time of their occurrence and who was responsible for the events only serves to add to the difficulty of theanalysis: ( ) Errors and omissions in the contract documents,asfollows: - Missinginformation; - Erroneousinformation; - Absence of a phasing plan in the bid documents,whenthesiteworkrequiresparts oftheWorkstobeprogressedinphases; - Conflictinginformationthatentaildesign revisions. (ii) Delaysforreasonsbeyondthecontractor orowner'scontrol,asfollows: - Labour force strikes or other similar industrialactions; - Outofstatemanufacturer'sshutdown; - A subcontractor going out of business partwaythroughtheproject; - Unusualweatherconditions. (iii) Owner caused delays, for reasons under theircontrol,suchas: - Scopechanges; - Limiting the contractor's access to parts ofthesite; - Cashflowdifficulties; - Late processing of contractor's requests forclarificationsand/orchangeorders; - A higher-level political factor that may haveaffectedprogress. (iv) Contractor caused delays, for reasons undertheircontrol,suchas: - Insufficientlabourforceonsite; - Contractual problems or disputes between the prime contractor and its subcontractors; Erdal Asim Manager of Forensic Planning Department International Events which can cause delay to completion of a project I. Introduction Construction contracts typically involve adeadlineforthecompletionoftheWorks(or designated sections thereof) and as a consequence, contractual agreements will often place reliance upon programming. In general terms, delays represent additional costs to the Parties, either as a consequence of late facility occupancy or other factors and additional costs incurred compared with budgeted costs, where actual activity durations may be compared with anticipated durations. Construction projects often suffer delay due to a wide variety of reasons, which can have severe financial effects on the project. As a result, delay claims will likely be filed by the contractor. The analysis of the effects of delays on critical (near critical or non-critical) activities is one of the most complicated types of analysis. It requires an expert who has an extensive knowledge of construction projects, the means and methods of scheduling,andtheabilitytodevelopasound methodology upon which the analysis should beconducted. Most delay claims do not reach the expert until after completion of the project, which often entails a detailed and intensive retrospective research into the documents to verify schedules, events, sequence of work, changes during construction and the circumstances that would evidence the delay effectofsuchevents. II. Ascertainingthecauseofdelays One of the main steps in ascertaining the cause of delay (known as 'causation') is to research documents related to the project in order to evidence events which may have caused delay to completion of the Works (or designated sections thereof). The methodology used to ascertain the effect of these events is at the heart of this type of analysis and the difficulties in ensuring a sustainable claim. Owners and contractors who realize the potential for construction disputes and conflicts rely on the construction claims consultants who are experienced construction managers and engineers. Below is a list of commonly encountered events which often cause delay to Issue 8, September 2016
  • 4. - InternalCashflowissues; - Lack of proper planning and managementoftheproject. (v) Personality conflicts between the membersoftheprojectteam: - Inter-personality disagreements often make things difficult on site, which cause delays. In this case, each party will blame the otherforthedelay. The resulting category of delays can be expressedasfollows: ( ) ByOrigin: - EmployerRiskEvent(ERE); - ContractorRiskEvent(CRE); - ThirdPartyEvent. (ii) ByCompensability: - Excusable Compensable (additional timeandmoneygrantedtocontractor); - ExcusableNon-compensable(additional timegrantedwithoutmoney); - Non-excusable (no additional time and moneyaregranted). (iii) ByTiming: - Concu rrent (i. e. separate e v e n ts produced by both parties, each delaying activities on the critical path, which occur at the same time). - Non-concurrent (i.e. separate events produced by both parties, each delaying activities on the critical path, which occur at different times). Oncethecausesofdelayhavebeenestablished and the chronology of the events has been reviewed, in order to identify the effected of those delays on the activities within the Programme of Works, a sub-network or “fragnet” is prepared representing the event as though it was an activity, in order to produce a retrospective and prospective graphical representationof“cause”fortheDelayAnalysis. The “fragnets” must be sustained by evidence comprising contemporaneous correspondence and other documents, such as minutes of meeting, daily reports, monthly reports, photographic reports, meteorological statistics and such like, which evidence the “cause” with certainty. If the events are ongoing and their effect has not ceased, then periodic updates of the fragnets related to continuing or new events must be produced. This process is helpful for the evaluation of the impact (“effect”) of the event or the impact of combinations of multiple events ontheCompletionDate. Issue 8, September 2016 4
  • 5. The Board of Directors (the Board) is pleased to announce two major changes aimed at further strengthening the Company's leadershipteam.Thechangesare: · The nomina tion of Mr. Athanasios Stigas as Executive Director and Member of theBoard · The promotion of Mrs. Mihaela Vulpescu asManagerofContractsDepartment. In making the announcement, Mr. Giovanni Di Folco, President & Senior Partner of Techno Engineering & Associates, expressed his appreciation: “We are delighted to welcome Mr. Stigas to the Board. His extensive experience on large infrastructure projects both in Greece and Romania will be of great benefit to TE&A, as we are impressed by the sense of ambitious vision, commitment and level of energy that Mr. Stigas brings to this position. I am delighted that he has accepted the Board's invitation to embrace this new and very important assignment and I am sure that under his leadership TE&A will enjoy unprecedented success. Mr. Stigas, whose strong values are an example to all, has proved over the years his worth as an experienced civil engineer and manager. That coupled with his outstanding contract and claims management skills, honesty, talent and loyalty has resulted in him being a superb choice to replace Mr. Emanuele Lancellotti, stepping down from the Board and having served for the past two years as Executive Director.Emanuelehasbeenamajorinfluence in TE&A's developmentand he leaves with our best wishes for the future. Mr. Stigas' skills and background will assist TE&A to deliver the high performance outcomes we expect from our existing collaborations and progress the strong development opportunities in our assetportfolio”. Mr. Athanasios Stigas, Executive Director, sharedhiscomment: 5 Athanasios Stigas named as Executive Director Mihaela Vulpescu succeeds him as Manager of Contracts Department Issue 8, September 2016 “I am honored and privileged to be appointed in the position of Executive Director of TE&A. Since joining the company five years ago, I have been very impressed by the strength and depth of talent within our organization. I am excited to be assuming the leadership of the business and building the same under Mr. Di Folco's outstanding direction. I look forward to working with the management team as we continue to drive profitable growth and performanceacrossTE&A'sglobaloffices.” Mr. Stigas brings with him unparalleled experience and understanding of the construction industry. He was previously Manager of Contracts Department and Unit Chief Contracts Manager at TE&A, having begun his career working for major Greek companies, where he has previously held a variety of positions, including Construction Manager, Production manager and Deputy ProjectManager. The announcement of Mr. Stigas's elevation was accompanied by the promotion of Mrs. MihaelaVulpescu,who will succeed himas the new Manager of Contracts Department. The Board is grateful for her willingness to take on an expanded role in the organization. “Over the past years we find Mrs Mihaela Vulpescu as a very responsible, hardworking and therefore valuable member of our company, having over five years' of experience in contract management with us. She has shown her ability to accomplish her tasks very well indeed, and she has performed her duties to our full satisfaction. We had no hesitation in promoting her. Given the right motivation, she has the ability and the determination to excel”,Mr.DiFolcoadded. We are confident as a Board that they will not only maintain the high standards with which TE&A is associated, but will lead the Company to become even more effective. The Board welcomesbothofthemintheirnewroles! Athanasios Stigas Executive Director Mihaela Vulpescu Manager of Contracts Department