- 1. Start Date Length (In Days) End Date Adjusted Length
Build Schedule 12/1/16 2 12/5/16 4
Set Budget 12/5/16 2 12/7/16 2
Hire Crew 12/7/16 3 12/12/16 5
Location Scouting 12/13/16 2 12/15/16 2
Build Set 12/13/16 2 12/15/16 2
Rehearsal 12/19/16 3 12/22/16 3
Shoot Video 12/27/16 2 12/29/16 2
Editing Scenes 1/3/17 7 1/12/17 9
Editing Audio/Sound 1/3/17 7 1/12/17 9
Key: Pre-Production Activities
Production Activities
Post-Production Activities
4
2
5
2
2
3
2
9
9
12/1/16 12/6/16 12/11/16 12/16/16 12/21/16 12/26/16 12/31/16 1/5/17 1/10/17 1/15/17
Build Schedule
Set Budget
Hire Crew
Location Scouting
Build Set
Rehearsal
Shoot Video
Editing Scenes
Editing Audio/Sound