SlideShare a Scribd company logo
1 of 26
Download to read offline
CIPUG
CIP-002-5.1 Additional Considerations
San Diego, CA
October 13, 2015
Bryan Carr PMP, CISA, PSP
Sr. Compliance Auditor, Cyber Security
Western Electricity Coordinating Council
Speaker Intro: Bryan Carr
• Joined WECC in August 2012
• a.k.a Dr. TFE (Emeritus)
• Former CIP Program Manager
• Project manager
• 3:37 Marathoner – BQ 3:10
• Donut enthusiast
Western Electricity Coordinating Council
2
Agenda
• 2015 Audit Recap & Observations
• Q&A
• Distribution Providers
Western Electricity Coordinating Council
3
2015 Audit Recap
Slide 4
Western Electricity Coordinating Council
• 21 Onsite audits completed
– 11 v3 audits
– 10 v5 transition audits
2015 Audit Recap - Observations
• Many hesitant to leverage NERC v5 transition
guidance.
• Implementation delays due to interpretations,
waiting on Lessons Learned & FAQ.
• Entities who regularly reach out to audit team
and attend outreach were better prepared.
Western Electricity Coordinating Council
5
CIP-002-5.1 Entity Q&A
• Sources include email, audit, ERO-wide auditor
workshops/distribution lists, etc.
• Q&A sanitized to protect the innocent.
• All entities appearing in this presentation are
fictitious. Any resemblance to real entities, living
or dead, is purely coincidental.
Western Electricity Coordinating Council
6
Q1
• We plan to associate BCAs (including SPS/RAS)
with the operating voltage of the high side of the
transformer, as well as any BCA associated with
both the high and low side of the transformer
(e.g. bank differential relays). Is this a valid
approach?
Western Electricity Coordinating Council
7
A1
• Protect BCS associated with SPS/RAS at the
highest applicable impact rating.
• IRC 2.9 may bring in some BCS that would
normally be Low into scope as Medium BCS.
• Each SPS/RAS BCS should be evaluated
independently as you apply the IRC.
Western Electricity Coordinating Council
8
Q2
• In counting the number of lines coming into a
substation, should a bus bar with a tie-circuit
breaker be considered a line?
Western Electricity Coordinating Council
9
A2
• Normally a tie bus would not be considered a
transmission "line" as it does not typically
cross substation boundaries.
• If, however, the tie bus in question crosses
substation boundaries, a strict interpretation
of IRC2.5 would indicate that would qualify as
a "line" coming in and/or out of the
substation.
Western Electricity Coordinating Council
10
Q3
• For jointly owned locations – is
documentation required for who is
performing the compliance
obligations?
Slide 11
Western Electricity Coordinating Council
A3
• Yes, if a single entity is responsible for performing the
compliance obligations at a jointly owned Facility,
that should be clarified in the operating agreement,
through a memorandum, or other binding document
in which these obligations are clearly defined and
assigned to a single party.
• Without a binding document defining compliance
responsibility, WECC will look to the owner of each
applicable BCS to fulfill the compliance obligations.
Slide 12
Western Electricity Coordinating Council
Q4
Western Electricity Coordinating Council
13
• We will have only Low Impact BCS under CIP
v5, therefore we have nothing to do (no
compliance obligations) until April 1, 2017. Is
this correct?
A4
• Not quite. CIP-002-5.1 R1 & R2 and CIP-003-6 R3
& R4 must be complete (documented and
approved) by April 1, 2016 for ALL applicable
entities, including those with only Low Impact
BCS.
• Low Impact requirements in CIP-003-6 R1.2, R2,
Attachment 1 – Sections 1 & 4 must be complete
by April 1, 2017.
• Low Impact requirements in CIP-003-6 R2
Attachment 3 & 4 must be complete by
September 1, 2018.
Slide 14
Western Electricity Coordinating Council
Q5
• Should meters be considered BCA?
15
Western Electricity Coordinating Council
A5
• Certain meters may be considered BCA. For
example, tie-line (aka interchange) meters
providing data for ACE calculations are required
to have an update interval of no greater than 6
seconds (BAL-005-0.2b R8), those Cyber Assets
come into scope as real-time Cyber Assets that
support one or more BROS and should be
identified as BCA, grouped into one or more
appropriate BCS, and afforded the full protections
of the CIPv5 Standards, as applicable, based on
the impact rating of their host Facilities.
Slide 16
Western Electricity Coordinating Council
Q6
• We were just notified by PEAK that we’re now
part of an IROL, which will raise the the
impact rating of a couple of our facilities from
Low to Medium. The implementation plan
allows for 12-24 months, but when does that
clock start ticking?
Slide 17
Western Electricity Coordinating Council
A6
• The IRC 2.3 and 2.6 Lesson Learned document recently
posted on NERC’s website adds an implementation
period for Medium BCS identified prior to April 1,
2016, and extends CIP compliance for newly identified
BCS under these two IRC by 12-24 months.
• The clock starts ticking upon completion of the R1
Assessment following an IRC 2.3 or 2.6 notification, not
the date of notification itself. Should such notification
occur between now and April 1, 2016, WECC expects
re-evaluation of R1 be completed on or before April 1,
2016, at which point the implementation period would
begin.
Slide 18
Western Electricity Coordinating Council
Q7
• Our low impact substation has a backup EMS
server which is part of our High Impact
Control Center. The EMS server and Low BCS
(protection equipment) are physically located
in the same building, but are logically
separate. Does this mean the entire facility
must be treated as High Impact, or can we
separate the two somehow?
Slide 19
Western Electricity Coordinating Council
A7
• The impact rating of the facility could remain
Low under certain conditions, however the
High Impact BCS would need to be afforded all
the physical and logical protections specified
in the CIP Standards.
• Options to consider:
1. Create a separate PSP around just the High
Impact BCS.
2. Treat the entire building as a High PSP.
Slide 20
Western Electricity Coordinating Council
I’m a DP, is CIP v5 Applicable to Me?
• All DPs should implement a CIP-002-5.1 process to
evaluate their system to rule out anything that might
be applicable under the Impact Rating Criteria [IRC]
and Section 4.2.1.
• If the DP can demonstrate that NONE of its system are
applicable under this section, then they should
document the evaluation and its results.
• Under an abundance of caution, a best practice would
be to document a null list for R1.1, R1.2, and R1.3, then
apply its process at least every 15 calendar months to
ensure that no systems changed to the extent that they
came into scope under Section 4.2.1.
Slide 21
Western Electricity Coordinating Council
What if I have a UFLS/UVLS?
• If you have an applicable UFLS/UVLS under
section 4.2.1 (NERC, 2012 Nov 22, CIP-002-
5.1, p. 1), these BCS should be evaluated as
Low-impact under IRC 3.6 and, therefore, the
Facilities containing them should be listed as
Low-impact BES [R1.3].
• Any specific DP UFLS/UVLS has to meet both
conditions of Section 4.2.1.1 to come into
scope as Low-impact.
Slide 22
Western Electricity Coordinating Council
What About Blackstart Units?
• Black-start resources and their associated cranking paths
can come into scope under CIPv5 as Low-impact BES Assets
under two conditions:
– IRC 3.4: Systems and facilities critical to system restoration,
including Blackstart Resources and Cranking Paths and initial
switching requirements (CIP-002-5.1, p. 16), or
– Section 4.1.2.4: Each Cranking Path and group of Elements
meeting the initial switching requirements from a Blackstart
Resource up to and including the first interconnection point of
the starting station service of the next generation unit(s) to be
started (CIP-002-5.1, p. 1).
• You may have a small non-BES Generation unit and/or
cranking path facility that are included in a Restoration
plan. Talk to your RC and TOP to make sure that you do not.
Slide 23
Western Electricity Coordinating Council
Evaluation Results
• A prudent DP will evaluate its systems, at a
minimum, against IRC 3.4, 3.6, and Section 4.2.1
and document that it either has no applicable
systems or it has provided the appropriate
protections to its applicable systems.
• A DP with applicable systems that come into
scope under CIPv5 will generally have approved
null R1.1 and R1.2 lists, and a relatively short R1.3
list.
• A DP that does not have applicable systems
should have null lists for all three categories.
Slide 24
Western Electricity Coordinating Council
Summary
• A DP should not just assume it has no applicable
systems, implement the R1 process anyway.
• This approach is effectively no different from the LSE or
other Registered Entity that applied its RBAM every
year under CIPv3 to ensure its null lists of CAs and CCAs
were still valid.
• WECC’s compliance monitoring approach for DPs will
seek evidence that the DP implemented the process
required by CIP-002-5.1 and documented the results of
the evaluation of its systems to demonstrate
compliance with the CIPv5 Standards.
Slide 25
Western Electricity Coordinating Council
Speaker Contact Information
Bryan Carr
bcarr@wecc.biz
801-819-7691
Slide 26
Western Electricity Coordinating Council

More Related Content

Viewers also liked (13)

Unido_industry-4_final
Unido_industry-4_finalUnido_industry-4_final
Unido_industry-4_final
 
CurbsideCleanUpAppScreenShots
CurbsideCleanUpAppScreenShotsCurbsideCleanUpAppScreenShots
CurbsideCleanUpAppScreenShots
 
Arquivo 482 22
Arquivo 482 22Arquivo 482 22
Arquivo 482 22
 
Seguros de tranporte internacional de mercancia
Seguros de tranporte internacional de mercanciaSeguros de tranporte internacional de mercancia
Seguros de tranporte internacional de mercancia
 
Neighborhood App Images
Neighborhood App ImagesNeighborhood App Images
Neighborhood App Images
 
Stanley J Marek, Jr Resume
Stanley J Marek, Jr ResumeStanley J Marek, Jr Resume
Stanley J Marek, Jr Resume
 
GarageSalePacket2016
GarageSalePacket2016GarageSalePacket2016
GarageSalePacket2016
 
General presentation Luxury Mints 2016 show
General presentation Luxury Mints 2016 showGeneral presentation Luxury Mints 2016 show
General presentation Luxury Mints 2016 show
 
Heitham Muweis CV1
Heitham Muweis CV1Heitham Muweis CV1
Heitham Muweis CV1
 
Muscular y tegumentario
Muscular y tegumentarioMuscular y tegumentario
Muscular y tegumentario
 
Herramientas informaticas
Herramientas informaticasHerramientas informaticas
Herramientas informaticas
 
catalogo contem1g 2017
catalogo contem1g 2017catalogo contem1g 2017
catalogo contem1g 2017
 
Presentation_Version 5 Attachment G - Notice of Audit_01-29-15
Presentation_Version 5 Attachment G - Notice of Audit_01-29-15Presentation_Version 5 Attachment G - Notice of Audit_01-29-15
Presentation_Version 5 Attachment G - Notice of Audit_01-29-15
 

Similar to 06 CIP-002-5.1 Additional Consideration - 10 13 15

So just-what-rule
So just-what-ruleSo just-what-rule
So just-what-rule
Mike Beck
 
Aquaculture Facility Rehabilitation - Presentation 04-29-2013
Aquaculture Facility Rehabilitation - Presentation 04-29-2013Aquaculture Facility Rehabilitation - Presentation 04-29-2013
Aquaculture Facility Rehabilitation - Presentation 04-29-2013
David M. Athey, PE
 
PERFORMANCE TOOLS FOR ELECTRIC COOPERATIVES
PERFORMANCE TOOLS FOR ELECTRIC COOPERATIVESPERFORMANCE TOOLS FOR ELECTRIC COOPERATIVES
PERFORMANCE TOOLS FOR ELECTRIC COOPERATIVES
jo bitonio
 

Similar to 06 CIP-002-5.1 Additional Consideration - 10 13 15 (20)

Alan Bull CTOTF NERC Presentation
Alan Bull CTOTF NERC PresentationAlan Bull CTOTF NERC Presentation
Alan Bull CTOTF NERC Presentation
 
NERC CIP Compliance 101 Workshop - Smart Grid Security East 2011
NERC CIP Compliance 101 Workshop - Smart Grid Security East 2011NERC CIP Compliance 101 Workshop - Smart Grid Security East 2011
NERC CIP Compliance 101 Workshop - Smart Grid Security East 2011
 
Explore the Implicit Requirements of the NERC CIP RSAWs
Explore the Implicit Requirements of the NERC CIP RSAWsExplore the Implicit Requirements of the NERC CIP RSAWs
Explore the Implicit Requirements of the NERC CIP RSAWs
 
Seun_slides_icann day
Seun_slides_icann daySeun_slides_icann day
Seun_slides_icann day
 
Ask the Expert: The Hazardous Waste Generator Improvements Rule
Ask the Expert: The Hazardous Waste Generator Improvements RuleAsk the Expert: The Hazardous Waste Generator Improvements Rule
Ask the Expert: The Hazardous Waste Generator Improvements Rule
 
ICC Banking Commission Technical Meeting
ICC Banking Commission Technical MeetingICC Banking Commission Technical Meeting
ICC Banking Commission Technical Meeting
 
Grid code
Grid codeGrid code
Grid code
 
The Hazardous Waste Generator Improvements Rule Proposal
The Hazardous Waste Generator Improvements Rule ProposalThe Hazardous Waste Generator Improvements Rule Proposal
The Hazardous Waste Generator Improvements Rule Proposal
 
So just-what-rule
So just-what-ruleSo just-what-rule
So just-what-rule
 
Availing the Net metering facility: impact of BOI's reforms
Availing the Net metering facility: impact of BOI's reformsAvailing the Net metering facility: impact of BOI's reforms
Availing the Net metering facility: impact of BOI's reforms
 
ICC BANKING COMMISSION MIAMI MEETING 2018: Day 2 @ 11:45 E-compatibility of I...
ICC BANKING COMMISSION MIAMI MEETING 2018: Day 2 @ 11:45 E-compatibility of I...ICC BANKING COMMISSION MIAMI MEETING 2018: Day 2 @ 11:45 E-compatibility of I...
ICC BANKING COMMISSION MIAMI MEETING 2018: Day 2 @ 11:45 E-compatibility of I...
 
Intellibind Top Ten Most Violated Standards Presentation 2011 01 27 (F)
Intellibind   Top Ten Most Violated Standards Presentation   2011 01 27 (F)Intellibind   Top Ten Most Violated Standards Presentation   2011 01 27 (F)
Intellibind Top Ten Most Violated Standards Presentation 2011 01 27 (F)
 
IEGC_PPT_SLDC.ppt
IEGC_PPT_SLDC.pptIEGC_PPT_SLDC.ppt
IEGC_PPT_SLDC.ppt
 
EUCA22 - Patch Management ISO_IEC 15408 & 18045
EUCA22 - Patch Management ISO_IEC 15408 & 18045EUCA22 - Patch Management ISO_IEC 15408 & 18045
EUCA22 - Patch Management ISO_IEC 15408 & 18045
 
SLAs the heart of Outsourcing
SLAs the heart of OutsourcingSLAs the heart of Outsourcing
SLAs the heart of Outsourcing
 
Amendments To O Reg 153 04
Amendments To O Reg 153 04Amendments To O Reg 153 04
Amendments To O Reg 153 04
 
Aquaculture Facility Rehabilitation - Presentation 04-29-2013
Aquaculture Facility Rehabilitation - Presentation 04-29-2013Aquaculture Facility Rehabilitation - Presentation 04-29-2013
Aquaculture Facility Rehabilitation - Presentation 04-29-2013
 
PERFORMANCE TOOLS FOR ELECTRIC COOPERATIVES
PERFORMANCE TOOLS FOR ELECTRIC COOPERATIVESPERFORMANCE TOOLS FOR ELECTRIC COOPERATIVES
PERFORMANCE TOOLS FOR ELECTRIC COOPERATIVES
 
Importance of the NERC PRC-005 Standard - Challenges and Audit Tips
Importance of the NERC PRC-005 Standard - Challenges and Audit TipsImportance of the NERC PRC-005 Standard - Challenges and Audit Tips
Importance of the NERC PRC-005 Standard - Challenges and Audit Tips
 
Calgary Oil & Gas Regulatory and Standards Day January 18th 2023
Calgary Oil & Gas Regulatory and Standards Day January 18th 2023Calgary Oil & Gas Regulatory and Standards Day January 18th 2023
Calgary Oil & Gas Regulatory and Standards Day January 18th 2023
 

06 CIP-002-5.1 Additional Consideration - 10 13 15

  • 1. CIPUG CIP-002-5.1 Additional Considerations San Diego, CA October 13, 2015 Bryan Carr PMP, CISA, PSP Sr. Compliance Auditor, Cyber Security Western Electricity Coordinating Council
  • 2. Speaker Intro: Bryan Carr • Joined WECC in August 2012 • a.k.a Dr. TFE (Emeritus) • Former CIP Program Manager • Project manager • 3:37 Marathoner – BQ 3:10 • Donut enthusiast Western Electricity Coordinating Council 2
  • 3. Agenda • 2015 Audit Recap & Observations • Q&A • Distribution Providers Western Electricity Coordinating Council 3
  • 4. 2015 Audit Recap Slide 4 Western Electricity Coordinating Council • 21 Onsite audits completed – 11 v3 audits – 10 v5 transition audits
  • 5. 2015 Audit Recap - Observations • Many hesitant to leverage NERC v5 transition guidance. • Implementation delays due to interpretations, waiting on Lessons Learned & FAQ. • Entities who regularly reach out to audit team and attend outreach were better prepared. Western Electricity Coordinating Council 5
  • 6. CIP-002-5.1 Entity Q&A • Sources include email, audit, ERO-wide auditor workshops/distribution lists, etc. • Q&A sanitized to protect the innocent. • All entities appearing in this presentation are fictitious. Any resemblance to real entities, living or dead, is purely coincidental. Western Electricity Coordinating Council 6
  • 7. Q1 • We plan to associate BCAs (including SPS/RAS) with the operating voltage of the high side of the transformer, as well as any BCA associated with both the high and low side of the transformer (e.g. bank differential relays). Is this a valid approach? Western Electricity Coordinating Council 7
  • 8. A1 • Protect BCS associated with SPS/RAS at the highest applicable impact rating. • IRC 2.9 may bring in some BCS that would normally be Low into scope as Medium BCS. • Each SPS/RAS BCS should be evaluated independently as you apply the IRC. Western Electricity Coordinating Council 8
  • 9. Q2 • In counting the number of lines coming into a substation, should a bus bar with a tie-circuit breaker be considered a line? Western Electricity Coordinating Council 9
  • 10. A2 • Normally a tie bus would not be considered a transmission "line" as it does not typically cross substation boundaries. • If, however, the tie bus in question crosses substation boundaries, a strict interpretation of IRC2.5 would indicate that would qualify as a "line" coming in and/or out of the substation. Western Electricity Coordinating Council 10
  • 11. Q3 • For jointly owned locations – is documentation required for who is performing the compliance obligations? Slide 11 Western Electricity Coordinating Council
  • 12. A3 • Yes, if a single entity is responsible for performing the compliance obligations at a jointly owned Facility, that should be clarified in the operating agreement, through a memorandum, or other binding document in which these obligations are clearly defined and assigned to a single party. • Without a binding document defining compliance responsibility, WECC will look to the owner of each applicable BCS to fulfill the compliance obligations. Slide 12 Western Electricity Coordinating Council
  • 13. Q4 Western Electricity Coordinating Council 13 • We will have only Low Impact BCS under CIP v5, therefore we have nothing to do (no compliance obligations) until April 1, 2017. Is this correct?
  • 14. A4 • Not quite. CIP-002-5.1 R1 & R2 and CIP-003-6 R3 & R4 must be complete (documented and approved) by April 1, 2016 for ALL applicable entities, including those with only Low Impact BCS. • Low Impact requirements in CIP-003-6 R1.2, R2, Attachment 1 – Sections 1 & 4 must be complete by April 1, 2017. • Low Impact requirements in CIP-003-6 R2 Attachment 3 & 4 must be complete by September 1, 2018. Slide 14 Western Electricity Coordinating Council
  • 15. Q5 • Should meters be considered BCA? 15 Western Electricity Coordinating Council
  • 16. A5 • Certain meters may be considered BCA. For example, tie-line (aka interchange) meters providing data for ACE calculations are required to have an update interval of no greater than 6 seconds (BAL-005-0.2b R8), those Cyber Assets come into scope as real-time Cyber Assets that support one or more BROS and should be identified as BCA, grouped into one or more appropriate BCS, and afforded the full protections of the CIPv5 Standards, as applicable, based on the impact rating of their host Facilities. Slide 16 Western Electricity Coordinating Council
  • 17. Q6 • We were just notified by PEAK that we’re now part of an IROL, which will raise the the impact rating of a couple of our facilities from Low to Medium. The implementation plan allows for 12-24 months, but when does that clock start ticking? Slide 17 Western Electricity Coordinating Council
  • 18. A6 • The IRC 2.3 and 2.6 Lesson Learned document recently posted on NERC’s website adds an implementation period for Medium BCS identified prior to April 1, 2016, and extends CIP compliance for newly identified BCS under these two IRC by 12-24 months. • The clock starts ticking upon completion of the R1 Assessment following an IRC 2.3 or 2.6 notification, not the date of notification itself. Should such notification occur between now and April 1, 2016, WECC expects re-evaluation of R1 be completed on or before April 1, 2016, at which point the implementation period would begin. Slide 18 Western Electricity Coordinating Council
  • 19. Q7 • Our low impact substation has a backup EMS server which is part of our High Impact Control Center. The EMS server and Low BCS (protection equipment) are physically located in the same building, but are logically separate. Does this mean the entire facility must be treated as High Impact, or can we separate the two somehow? Slide 19 Western Electricity Coordinating Council
  • 20. A7 • The impact rating of the facility could remain Low under certain conditions, however the High Impact BCS would need to be afforded all the physical and logical protections specified in the CIP Standards. • Options to consider: 1. Create a separate PSP around just the High Impact BCS. 2. Treat the entire building as a High PSP. Slide 20 Western Electricity Coordinating Council
  • 21. I’m a DP, is CIP v5 Applicable to Me? • All DPs should implement a CIP-002-5.1 process to evaluate their system to rule out anything that might be applicable under the Impact Rating Criteria [IRC] and Section 4.2.1. • If the DP can demonstrate that NONE of its system are applicable under this section, then they should document the evaluation and its results. • Under an abundance of caution, a best practice would be to document a null list for R1.1, R1.2, and R1.3, then apply its process at least every 15 calendar months to ensure that no systems changed to the extent that they came into scope under Section 4.2.1. Slide 21 Western Electricity Coordinating Council
  • 22. What if I have a UFLS/UVLS? • If you have an applicable UFLS/UVLS under section 4.2.1 (NERC, 2012 Nov 22, CIP-002- 5.1, p. 1), these BCS should be evaluated as Low-impact under IRC 3.6 and, therefore, the Facilities containing them should be listed as Low-impact BES [R1.3]. • Any specific DP UFLS/UVLS has to meet both conditions of Section 4.2.1.1 to come into scope as Low-impact. Slide 22 Western Electricity Coordinating Council
  • 23. What About Blackstart Units? • Black-start resources and their associated cranking paths can come into scope under CIPv5 as Low-impact BES Assets under two conditions: – IRC 3.4: Systems and facilities critical to system restoration, including Blackstart Resources and Cranking Paths and initial switching requirements (CIP-002-5.1, p. 16), or – Section 4.1.2.4: Each Cranking Path and group of Elements meeting the initial switching requirements from a Blackstart Resource up to and including the first interconnection point of the starting station service of the next generation unit(s) to be started (CIP-002-5.1, p. 1). • You may have a small non-BES Generation unit and/or cranking path facility that are included in a Restoration plan. Talk to your RC and TOP to make sure that you do not. Slide 23 Western Electricity Coordinating Council
  • 24. Evaluation Results • A prudent DP will evaluate its systems, at a minimum, against IRC 3.4, 3.6, and Section 4.2.1 and document that it either has no applicable systems or it has provided the appropriate protections to its applicable systems. • A DP with applicable systems that come into scope under CIPv5 will generally have approved null R1.1 and R1.2 lists, and a relatively short R1.3 list. • A DP that does not have applicable systems should have null lists for all three categories. Slide 24 Western Electricity Coordinating Council
  • 25. Summary • A DP should not just assume it has no applicable systems, implement the R1 process anyway. • This approach is effectively no different from the LSE or other Registered Entity that applied its RBAM every year under CIPv3 to ensure its null lists of CAs and CCAs were still valid. • WECC’s compliance monitoring approach for DPs will seek evidence that the DP implemented the process required by CIP-002-5.1 and documented the results of the evaluation of its systems to demonstrate compliance with the CIPv5 Standards. Slide 25 Western Electricity Coordinating Council
  • 26. Speaker Contact Information Bryan Carr bcarr@wecc.biz 801-819-7691 Slide 26 Western Electricity Coordinating Council