SlideShare a Scribd company logo
1 of 16
Mode and Method of
Measurement
Earthwork in Excavation and BackfillingWork
BHADANI’S FREETUTORIAL PART 1
1.
Block Levels has to be taken at the
start of the work.
The intervals can be of 3m or 5m
2.
The UoM (Unit of Measurement) is in CUM
and should be rounded off to nearest two
decimals
BHADANI’S
3.
For Pit Excavation an offset of 30 cm can be
taken on either side of the footing up to 1.5 m
depth and for more than 1.5 m depth it can be
taken as 50 to 60 cm.
BHADANI’S
4.
For Pit excavation Depth can be arrived by taking
=
Average top level – Average Bottom Level
BHADANI’S
5.
For Mass Excavation Earth work
quantity can be calculated by
using any of the rules like
Trapezoidal or Simsons rule etc.
Proper CVI (Reasons) has to be
maintained for Mass Excavation
BHADANI’S
6.
For hard rock and soft rock the top levels and bottom
levels should be taken with consultant approval.
The Quantity can be arrived with top and
bottom levels or the quantity can be arrived by
stacking the Hard rock.
The place for stacking should be selected
in accordance with clients’ approval and must be recorded
with joint measurement from client and contractor.
BHADANI’S
7.
Back filling quantity can
be arrived using
Trapezoidal
or
Bhadani’S rule.
BHADANI’S
8.
Final quantity is arrived by deducting the
volume of concrete and size stone masonry
below ground level from the total quantity.
BHADANI’S
9.
Earth brought from outside or to be carted
away is calculated by
=Total Excavated Quantity -Total Backfilling
Quantity.
IfValue is -Ve - It is Earth brought from
outside +Ve - It is Earth to be carted away.
BHADANI’S
10.
For Jungle clearance item, the area to be
considered is 5m off set all-round the building
and if for road works, 1m offset should be
considered on either side
BHADANI’S
11.
For EX:The below is the block level of area 40 m
X 20 m with levels of 5 m interval with mass
excavation to be done for entire area with
excavation bottom level as 95.2
BHADANI’S
BLOCK LEVEL
BHADANI’S
The volume can be found by taking
average rectangle/square method.
The depth of excavation
=
(98.75+98.7+98.68+98.85)/4 – 95.2
(i.e. AvgTop lvl – Bottom lvl.). = 3.545 m
BHADANI’S
Area = 5 X 5 = 25 sqmVolume of Earth
=
Area X Depth = 25 X 3.545 = 88.63 cum
BHADANI’S
SimilarlyVolume of Earth has to be calculated
for Other Square areas and to be added to get
the total quantity. If there is hard rock, it can
be stacked separately.
The volume of Hard rock stacked can be found
by taking site measurements. For Ex, refer
below sketch as stack measurement.
BHADANI’S
BHADANI’S
• Quantity Surveying Civil
• Billing / Invoice Engineering
• Tendering and Procurement
Management
• Construction Contract Management
• Construction Project Management
A Life Line For
Every Civil Engineer

More Related Content

What's hot

What's hot (7)

Estimation of CBR value using Dynamic Cone Penetrometer
Estimation of CBR value using Dynamic Cone Penetrometer  Estimation of CBR value using Dynamic Cone Penetrometer
Estimation of CBR value using Dynamic Cone Penetrometer
 
Standard Penetration Test (SPT)
Standard Penetration Test (SPT)Standard Penetration Test (SPT)
Standard Penetration Test (SPT)
 
Direct method of contouring(26 30) DCE FET IIUI
Direct method of contouring(26 30) DCE FET IIUIDirect method of contouring(26 30) DCE FET IIUI
Direct method of contouring(26 30) DCE FET IIUI
 
Standard penetration test
Standard penetration testStandard penetration test
Standard penetration test
 
Standard penetration test (spt)
Standard penetration test (spt)Standard penetration test (spt)
Standard penetration test (spt)
 
Cbr test
Cbr testCbr test
Cbr test
 
Indirect contouring 31 35 (IIUI)
Indirect contouring 31 35 (IIUI)Indirect contouring 31 35 (IIUI)
Indirect contouring 31 35 (IIUI)
 

More from BHADANI QUANTITY SURVEYING TRAINING INSTITUTE FOR CIVIL MECHANICAL AND ELECTRICAL ENGINEERS

More from BHADANI QUANTITY SURVEYING TRAINING INSTITUTE FOR CIVIL MECHANICAL AND ELECTRICAL ENGINEERS (16)

BHADANIS - PLASTER WORK ESTIMATION GUIDE
BHADANIS - PLASTER WORK ESTIMATION GUIDE BHADANIS - PLASTER WORK ESTIMATION GUIDE
BHADANIS - PLASTER WORK ESTIMATION GUIDE
 
BHADANIS - BRICK WORK ESTIMATION GUIDE CIVIL WORKS CONSTRUCTION ESTIMATION
BHADANIS - BRICK WORK ESTIMATION GUIDE CIVIL WORKS CONSTRUCTION ESTIMATIONBHADANIS - BRICK WORK ESTIMATION GUIDE CIVIL WORKS CONSTRUCTION ESTIMATION
BHADANIS - BRICK WORK ESTIMATION GUIDE CIVIL WORKS CONSTRUCTION ESTIMATION
 
ROAD WORK ESTIMATION GUIDE MATERIAL BHADANIS
ROAD WORK ESTIMATION GUIDE MATERIAL BHADANISROAD WORK ESTIMATION GUIDE MATERIAL BHADANIS
ROAD WORK ESTIMATION GUIDE MATERIAL BHADANIS
 
Bhadanis RCC WORK ESTIMATION GUIDE PCC WORK ESTIMATION
Bhadanis RCC WORK ESTIMATION GUIDE PCC WORK ESTIMATIONBhadanis RCC WORK ESTIMATION GUIDE PCC WORK ESTIMATION
Bhadanis RCC WORK ESTIMATION GUIDE PCC WORK ESTIMATION
 
Bhadanis CONCRETE WORK ESTIMATION GUIDE
Bhadanis CONCRETE WORK ESTIMATION GUIDE Bhadanis CONCRETE WORK ESTIMATION GUIDE
Bhadanis CONCRETE WORK ESTIMATION GUIDE
 
BHADANIS Construction Material Estimation Guide
BHADANIS Construction Material Estimation GuideBHADANIS Construction Material Estimation Guide
BHADANIS Construction Material Estimation Guide
 
Introduction to billing engineering
Introduction to billing engineeringIntroduction to billing engineering
Introduction to billing engineering
 
presentation quantity survey and estimate
presentation quantity survey and estimatepresentation quantity survey and estimate
presentation quantity survey and estimate
 
Construction Equipment and Planning Construction Management
Construction Equipment and Planning Construction ManagementConstruction Equipment and Planning Construction Management
Construction Equipment and Planning Construction Management
 
Quantity Surveying Course
Quantity Surveying Course Quantity Surveying Course
Quantity Surveying Course
 
Brick work Notes Tutorial PDF Free Donwnload Presentation
Brick work Notes Tutorial PDF Free Donwnload PresentationBrick work Notes Tutorial PDF Free Donwnload Presentation
Brick work Notes Tutorial PDF Free Donwnload Presentation
 
Bhadanis Plumbing Work Notes PDF Free Download
Bhadanis Plumbing Work Notes PDF Free DownloadBhadanis Plumbing Work Notes PDF Free Download
Bhadanis Plumbing Work Notes PDF Free Download
 
Building Construction Material Used Modern Materials Tutorial Notes PDF Free ...
Building Construction Material Used Modern Materials Tutorial Notes PDF Free ...Building Construction Material Used Modern Materials Tutorial Notes PDF Free ...
Building Construction Material Used Modern Materials Tutorial Notes PDF Free ...
 
BhadaniS Microsoft Project Manual Training
BhadaniS Microsoft Project Manual TrainingBhadaniS Microsoft Project Manual Training
BhadaniS Microsoft Project Manual Training
 
Steel Work in Construction Works Civil Works Steel Works Notes PDF Free
Steel Work in Construction Works Civil Works Steel Works Notes PDF FreeSteel Work in Construction Works Civil Works Steel Works Notes PDF Free
Steel Work in Construction Works Civil Works Steel Works Notes PDF Free
 
Quantity Surveying Civil
Quantity Surveying CivilQuantity Surveying Civil
Quantity Surveying Civil
 

Recently uploaded

psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docxPoojaSen20
 
Third Battle of Panipat detailed notes.pptx
Third Battle of Panipat detailed notes.pptxThird Battle of Panipat detailed notes.pptx
Third Battle of Panipat detailed notes.pptxAmita Gupta
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxVishalSingh1417
 
ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701bronxfugly43
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxRamakrishna Reddy Bijjam
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17Celine George
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSCeline George
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17Celine George
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfNirmal Dwivedi
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxnegromaestrong
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Association for Project Management
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhikauryashika82
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxSKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxAmanpreet Kaur
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptxMaritesTamaniVerdade
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
Magic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptxMagic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptxdhanalakshmis0310
 

Recently uploaded (20)

psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docx
 
Third Battle of Panipat detailed notes.pptx
Third Battle of Panipat detailed notes.pptxThird Battle of Panipat detailed notes.pptx
Third Battle of Panipat detailed notes.pptx
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxSKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Magic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptxMagic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptx
 

BhadaniS Part 1 Free Tutorial Mode and method of measurement bhadanis

  • 1. Mode and Method of Measurement Earthwork in Excavation and BackfillingWork BHADANI’S FREETUTORIAL PART 1
  • 2. 1. Block Levels has to be taken at the start of the work. The intervals can be of 3m or 5m 2. The UoM (Unit of Measurement) is in CUM and should be rounded off to nearest two decimals BHADANI’S
  • 3. 3. For Pit Excavation an offset of 30 cm can be taken on either side of the footing up to 1.5 m depth and for more than 1.5 m depth it can be taken as 50 to 60 cm. BHADANI’S
  • 4. 4. For Pit excavation Depth can be arrived by taking = Average top level – Average Bottom Level BHADANI’S
  • 5. 5. For Mass Excavation Earth work quantity can be calculated by using any of the rules like Trapezoidal or Simsons rule etc. Proper CVI (Reasons) has to be maintained for Mass Excavation BHADANI’S
  • 6. 6. For hard rock and soft rock the top levels and bottom levels should be taken with consultant approval. The Quantity can be arrived with top and bottom levels or the quantity can be arrived by stacking the Hard rock. The place for stacking should be selected in accordance with clients’ approval and must be recorded with joint measurement from client and contractor. BHADANI’S
  • 7. 7. Back filling quantity can be arrived using Trapezoidal or Bhadani’S rule. BHADANI’S
  • 8. 8. Final quantity is arrived by deducting the volume of concrete and size stone masonry below ground level from the total quantity. BHADANI’S
  • 9. 9. Earth brought from outside or to be carted away is calculated by =Total Excavated Quantity -Total Backfilling Quantity. IfValue is -Ve - It is Earth brought from outside +Ve - It is Earth to be carted away. BHADANI’S
  • 10. 10. For Jungle clearance item, the area to be considered is 5m off set all-round the building and if for road works, 1m offset should be considered on either side BHADANI’S
  • 11. 11. For EX:The below is the block level of area 40 m X 20 m with levels of 5 m interval with mass excavation to be done for entire area with excavation bottom level as 95.2 BHADANI’S
  • 13. The volume can be found by taking average rectangle/square method. The depth of excavation = (98.75+98.7+98.68+98.85)/4 – 95.2 (i.e. AvgTop lvl – Bottom lvl.). = 3.545 m BHADANI’S
  • 14. Area = 5 X 5 = 25 sqmVolume of Earth = Area X Depth = 25 X 3.545 = 88.63 cum BHADANI’S
  • 15. SimilarlyVolume of Earth has to be calculated for Other Square areas and to be added to get the total quantity. If there is hard rock, it can be stacked separately. The volume of Hard rock stacked can be found by taking site measurements. For Ex, refer below sketch as stack measurement. BHADANI’S
  • 16. BHADANI’S • Quantity Surveying Civil • Billing / Invoice Engineering • Tendering and Procurement Management • Construction Contract Management • Construction Project Management A Life Line For Every Civil Engineer