SlideShare a Scribd company logo
1 of 30
SUMMER PRACTICAL TRAINING
AT
SUBMITTED BY:-
RANJAN KUMAR
14EAIEE079
B.Tech. IV Yr. VII SEM
SUBMITTED TO :-
Mr. Deepak Sharma
Head of Department
Electrical Engineering
NATIONAL THERMAL POWER CORPORATION LTD. ( NTPC )
KAHALGAON (BIHAR)
CONTENTS :-
1. Introduction
2. Coal Handling System
3. Ash Handling System
4. Boiler and its auxiliaries
5. Turbine and its auxiliaries
6. Off-Site Department
7. Electric Generator and its auxiliaries
8. Electric Transformer
9. Switchyard
10.Control and Instrumentation Department
1
1. Introduction about NTPC :-
2
NTPC Limited is the largest thermal power generating company of India.
Established in 7 November 1975.
In 1997, Government of India granted NTPC status of “Navratna” company.
NTPC became a “Maharatna”company in May, 2010, one of the only four
companies to be awarded this status in India.
 Present installed Capacity of NTPC is 51,635 MW .
Total 48 NTPC in India.
 It has 20 coal based power stations (38,755 MW) .
7 gas based power stations (4,017 MW)
9 Joint Ventures based power stations (7,216 MW).
11 renewable energy based power plant(845 MW)
Annual turnover of Rs. 73,904 cr. with profit of Rs. 13,834 Cr. for the year 2013-14.
It contributes 28.60% of total power .
National Thermal Power Corporation LTD. (NTPC)
3
Introduction about NTPC Kahalgaon Bihar :-
Location : Kahalgaon , District-Bhagalpur (Bihar) , 813214
Total Land : 3,360 acres
Land for plant : 883 acres
Land for township : 432 acres
Land for Ash dyke :1395 acres
Source of water : Ganga River
Source of coal : Rajmahal coal field of ECL (Lalmatia , Jharkhand)
 Configuration: stage -1 has 4 unit (each unit capacity 210 MW) , which
was established by Russia in 1991.
stage -2 has 3 unit (each unit capacity 500 MW) , which
was established by BHEL in 1996.
Total installed capacity : 2340 MW
Fuel Requirement : 4.1 million ton per year stage -1
: 6.62 million ton per year for stage -2 ( phase-1 )
: 3 million ton per year for stage -2 ( phase-2 )
4
5
2. Coal Handling System Equipment :
6
Wagon
 Tripler
Conveyor Belt
Pulleys
Magnetic separator
Crushing house
Vibrating screen
Pulverized coal
Storage of coal
The function of coal handling plant is automatic feeding of coal to the boiler
 A thermal power plant burns enormous amounts of coal.
 In NTPC Kahalgaon 2340MW Plant may require around 23400 tons of coal daily.
Step in coal handling plant:
7
Why Coal?
Coal
55%
Gas
10%
Diesel
1%
Hydel
26%
RES
5%
Nuclear
3%
Share of Coal in Power Generation
Advantages of Coal Fuel
•Abundantly available in India
•Low cost
•Technology for Power Generation well
developed.
•Easy to handle, transport, store and use
•India’s Coal Reserves are estimated to be 206 billion tones. Present consumption is
about 450 million tones.
•Cost of coal for producing 1 unit of electricity is Rs 0.75.
•Cost of Gas for producing 1 unit of electricity is Rs 1.20. 8
3. Ash Handling System:
 WHAT IS ASH ?
Ash is the collection of residuals producing after the combustion of coal at
constant weight under standard conditions.
Ash is oxidized form of the mineral matters present in coal.
Typical ash composition : SiO2, Al2O3, Fe2O3, CaO, MgO etc.
 WHY ASH HANDLING?
 Ash content of Indian coal used in power station is about 30 to 40 %.
 A typical 2000 MW station produce around 9000T to 12000T of ash per day.
 This huge amount of ash needs to be disposed off continuously.
 Necessary care to be taken for preventing pollution. 9
 Bottom ash can be collected at furnace bottom as Wet or Dry form.
 Bottom ash is the heavier portion of coal ash that settles on the ground in the boiler.
 Bottom ash is part of the non-combustible residue of combustion in a furnace or
incinerator.
 Approximately 80% of bottom ash consist overall of coal ash content.
1. Bottom Ash:
10
2. Fly Ash:
• Fly ash, also known as “pulverized fuel ash”.
• Ash generated in the ESP which got carried out with the flue gas is
generally known as fly ash.
• It consist of air preheater ash and economizer ash.
• Approximately 20% of fly ash consist overall of coal ash content.
• FA is collected from Air heater hopper, Eco hopper and ESP hopper.
Use of ash:
• In concrete production
• In cement production
• In stabilization of soft soils
• In bricks production
• Road construction
• Other applications include cosmetics, toothpaste, ceiling tiles, bowling balls,
flotation devices, PVC pipe, picture frames, doors, window frames, park benches
railroad ties.
11
Coal Seam
Surge Pile
Pulverize (-150)
Overburden
Fly Ash
Flue Gas
Electrostatic Precipitator
Flue Gas
Boiler
Fly Ash Bottom
Ash
Smoke
Stack
Fly Ash
Bottom Ash
12
Boiler:-
 Boiler is a long column where coal is fired to produce heat and to convert water into superheated steam.
 In NTPC – Kahalgaon, the height of the boiler is 90 meter.
 Type of boiler used in NTPC SSTPS in Stage-I and II are Water tube boilers.
 Maximum Temperature and pressure of main steam for stage -1 is 540ºc and 140 bar respectively.
 Maximum Temperature and pressure of main steam for stage -2 is 545ºc and 170 bar respectively.
 MAIN PART OF BOILER:
1. Economizer 4. super-heater
2. Deaerator 5. Re-heater
3. Furnace 6. Different type of fan
13
14
A steam turbine is a rotating device which converts thermal energy into mechanical energy.
In NTPC Kahalgaon LMZ (Russia) type steam turbine is used.
There are 3 types of Turbines used in Thermal Power Plants:
1. High pressure turbine (HP Turbine)
2. Intermediate pressure turbine (IP Turbine)
3. Low pressure turbine (LP Turbine)
 Turbine blade is air foil shape.
TURBINE :-
15
1. High Pressure Turbine:
16
1.HIGH PRESSURE TURBINE:-
 Single Flow Cylinder
 Double Casing
 Thermal expansion up to 16mm
2. Intermediate Pressure Turbine
17
2.INTERMEDIATE PRESSURE TURBINE:-
 Double Flow
 Double Casing
 Axially Split Design in both Casings
 Rigid Coupling
 Blade Shrouded & Inverted T-Root
Design
3. Low Pressure Turbine:
18
3.LOW PRESSURE TURBINE:-
 Largest Turbine
 Pressure is Very Less
 Three Shell Design
 Double Flow
 All Casings Axially Split
 Exhaust Hood Spray Arrangement
 2 Free Standing Blades in the end
19
1. Water Treatment Plant/DM plant:
Why water treatment?
 Raw water contains many dissolved minerals and organic materials.
 For removal of total solids such as Ca , Mg ,Na ,Cl , Alkalinity , silica etc.
 At high temperature certain minerals left scaling on the tube metal of the boiler and cause permanent damage.
 Some dissolved minerals leads to corrosion of tube metals.
 At high pressure and temperature an element, silica can be carried away with steam causing damage to turbine
low pressure stage.
 The performance and life expectancy of the station greatly depends on water chemistry compliance.
6. Off-Site Department:
1. Water Treatment (DM Plant)
2. Cooling Tower
 Steps of treatment process:
1. Aeration of raw water
2. Adding chemicals for bacteria removal
3. Adding chemicals for sedimentation of suspended particles
4. Flocculation
5. Filtration
6. Ion Exchange process
20
2. Cooling Tower:
A cooling tower is a heat rejection device that rejects waste heat to the atmosphere through
the cooling of a water stream to a lower temperature.
21
7. Electric Generator and its auxiliaries:
 A turbo generator is the combination of a turbine directly connected to an electric generator
for the generation of electric power.
 An electric generator is a device that converts mechanical energy to electrical energy.
 It is based upon the principle of electromagnetic induction.
 Turbogenerator:
Cooling of Generator :
 Hydrogen cooling: - Rotor core and Rotor winding.
 DM Water cooling:- Stator core and Stator winding.
 Excitation System:
 Maintain the reactive power.
 Wear and Tear problem will be minimize.
 In NTPC Kahalgaon brushless excitation is used. 22
Capacity 210 KW
Power Factor 0.85 lagging
KVA 588,000
Stator Voltage 15.75 KV
Stator current 9.03 KA
Rotor Voltage 303 V
Rotor current 2.330 KA
RPM 3000
Frequency 50 HZ
Phase 3
Connection YY
Coolant Water & Hydrogen
Gas Pressure 4 Bar
Insulation Class B
Type TG-HH-0500-2
Make Russia
Stage-1 Turbogenerator Rating:-
Capacity 500 KW
Power Factor 0.85 lagging
KVA 588,000
Stator Voltage 21 KV
Stator current 16.2 KA
Rotor Voltage 340 V
Rotor current 4040 A
RPM 3000
Frequency 50 HZ
Phase 3
Connection YY
Coolant Water & Hydrogen
Gas Pressure 4 Bar
Insulation Class B
Type TG-HH-0500-2
Make BHEL Haridwar
Stage-2 Turbogenerator Rating:-
23
8. Electric Transformer:
 A transformer is a device that transfer electrical energy from one electrical circuit to another circuit through the
medium Of magnetic field without change in frequency.
WORKING PRINCIPLE:
Definition:
 It works on FARADAY’S LAW OF
ELECTROMAGNETIC INDUCTION
(self or mutual induction depending on the type of
transformer).
Transformer used in NTPC Kahalgaon:
1. Generator transformer
2. Station transformer
3. Unit Auxiliary transformer (UAT)
4. Other Electric transformer
24
9. Switchyard:
 ELECTRICAL EQUIPMENTS:
1. Bus-Bar
2. Lightning Arrester
3. Wave Trap
4. Capacitive Voltage Transformer
5. Relay
6. Circuit Breaker
7. Instrument Transformer
8. Earthing Rod
9. PLCC
10. INSULATORS
25
 Distribution System:
Figure: Single Line Diagram of NTPC Kahalgaon 400/132 KV Switchyard
26
10. Control and Instrumentation Department:
 The main functions of the C&I dept. at
NTPC Kahalgaon are:
1. Measurement and display of various parameters.
2. To control the various parameters by Automatic
feedback controlling which involves the taking of
decision based on inputs from measurements by the
processor.
3. Protection of various equipment’s (pumps, generators
etc.) and workers from hazards by automatically tripping
a cycle when hazardous conditions are reached.
4. Alarm generation in case of a mechanical or an
electrical failure. 27
28
29

More Related Content

What's hot

VOCATIONAL TRAINING REPORT ON NTPC KORBA
VOCATIONAL TRAINING REPORT ON NTPC KORBAVOCATIONAL TRAINING REPORT ON NTPC KORBA
VOCATIONAL TRAINING REPORT ON NTPC KORBAVIKASH BAGHEL
 
vocational training report on CSPGCL korba, chhattisgarh
vocational training report on CSPGCL korba, chhattisgarhvocational training report on CSPGCL korba, chhattisgarh
vocational training report on CSPGCL korba, chhattisgarhsahilthakur03
 
Improvement of rankine efficinecy of steam power plants
Improvement of rankine efficinecy of steam power plantsImprovement of rankine efficinecy of steam power plants
Improvement of rankine efficinecy of steam power plantsDhilip Pugalenthi
 
Project Report on Industrial Summer Training at NTPC Simhadri
 Project Report on Industrial Summer Training at NTPC Simhadri Project Report on Industrial Summer Training at NTPC Simhadri
Project Report on Industrial Summer Training at NTPC SimhadriAshish Uppu
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...haxxo24
 
Industrial training report of NTPC
Industrial training report of NTPC Industrial training report of NTPC
Industrial training report of NTPC Shivam Singh
 
Summer training in NTPC ppt
Summer training in NTPC pptSummer training in NTPC ppt
Summer training in NTPC pptkirbadh
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plantSiraskarCom
 
training report NTPC Muzaffarpur Bihar
training report  NTPC Muzaffarpur Bihar training report  NTPC Muzaffarpur Bihar
training report NTPC Muzaffarpur Bihar Dilip kumar
 
gas power plant ntpc dadri
gas power plant ntpc dadrigas power plant ntpc dadri
gas power plant ntpc dadriVirat Shishodia
 
Ntpc KAHALGAON REPORT FILE
Ntpc KAHALGAON REPORT FILENtpc KAHALGAON REPORT FILE
Ntpc KAHALGAON REPORT FILERanjan kumar
 
Report on Boilers at NTPC Ramagunadam
Report on  Boilers at NTPC RamagunadamReport on  Boilers at NTPC Ramagunadam
Report on Boilers at NTPC RamagunadamAbhinay Angari
 
CONTROL AND INSTRUMENTATION OF POWER PLANT
CONTROL AND INSTRUMENTATION OF POWER PLANTCONTROL AND INSTRUMENTATION OF POWER PLANT
CONTROL AND INSTRUMENTATION OF POWER PLANTSubarna Poddar
 
NTPC summer training report
NTPC summer training reportNTPC summer training report
NTPC summer training reportsanjeevps12345
 
Industrial training report of thermal power plant
Industrial training report of thermal power plantIndustrial training report of thermal power plant
Industrial training report of thermal power plantRavinder Jangid
 
Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT Abhijeet Thakur
 
Supercritical Power Plants
Supercritical Power PlantsSupercritical Power Plants
Supercritical Power PlantsErwan Yulianto
 

What's hot (20)

VOCATIONAL TRAINING REPORT ON NTPC KORBA
VOCATIONAL TRAINING REPORT ON NTPC KORBAVOCATIONAL TRAINING REPORT ON NTPC KORBA
VOCATIONAL TRAINING REPORT ON NTPC KORBA
 
vocational training report on CSPGCL korba, chhattisgarh
vocational training report on CSPGCL korba, chhattisgarhvocational training report on CSPGCL korba, chhattisgarh
vocational training report on CSPGCL korba, chhattisgarh
 
Improvement of rankine efficinecy of steam power plants
Improvement of rankine efficinecy of steam power plantsImprovement of rankine efficinecy of steam power plants
Improvement of rankine efficinecy of steam power plants
 
Report ON NTPC DADRI .BY ....EMAM
Report ON NTPC DADRI  .BY ....EMAMReport ON NTPC DADRI  .BY ....EMAM
Report ON NTPC DADRI .BY ....EMAM
 
Heat rate of coal fired power plant
Heat rate of coal fired power plantHeat rate of coal fired power plant
Heat rate of coal fired power plant
 
Project Report on Industrial Summer Training at NTPC Simhadri
 Project Report on Industrial Summer Training at NTPC Simhadri Project Report on Industrial Summer Training at NTPC Simhadri
Project Report on Industrial Summer Training at NTPC Simhadri
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
 
Industrial training report of NTPC
Industrial training report of NTPC Industrial training report of NTPC
Industrial training report of NTPC
 
Summer training in NTPC ppt
Summer training in NTPC pptSummer training in NTPC ppt
Summer training in NTPC ppt
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
training report NTPC Muzaffarpur Bihar
training report  NTPC Muzaffarpur Bihar training report  NTPC Muzaffarpur Bihar
training report NTPC Muzaffarpur Bihar
 
gas power plant ntpc dadri
gas power plant ntpc dadrigas power plant ntpc dadri
gas power plant ntpc dadri
 
Ntpc KAHALGAON REPORT FILE
Ntpc KAHALGAON REPORT FILENtpc KAHALGAON REPORT FILE
Ntpc KAHALGAON REPORT FILE
 
Report on Boilers at NTPC Ramagunadam
Report on  Boilers at NTPC RamagunadamReport on  Boilers at NTPC Ramagunadam
Report on Boilers at NTPC Ramagunadam
 
Harsh ntpc
Harsh ntpcHarsh ntpc
Harsh ntpc
 
CONTROL AND INSTRUMENTATION OF POWER PLANT
CONTROL AND INSTRUMENTATION OF POWER PLANTCONTROL AND INSTRUMENTATION OF POWER PLANT
CONTROL AND INSTRUMENTATION OF POWER PLANT
 
NTPC summer training report
NTPC summer training reportNTPC summer training report
NTPC summer training report
 
Industrial training report of thermal power plant
Industrial training report of thermal power plantIndustrial training report of thermal power plant
Industrial training report of thermal power plant
 
Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT
 
Supercritical Power Plants
Supercritical Power PlantsSupercritical Power Plants
Supercritical Power Plants
 

Similar to Ranjan NTPC KAHALGAON ppt

NTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training ReportNTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training ReportAditya Shekhar
 
NTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training ReportNTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training ReportAditya Shekhar
 
Tarun Project Report On NTPC Kanti
Tarun  Project Report On NTPC KantiTarun  Project Report On NTPC Kanti
Tarun Project Report On NTPC KantiTarun Kumar
 
panki power plant training.ppt
panki power plant training.pptpanki power plant training.ppt
panki power plant training.pptAbhishek Awasthi
 
NTPC faridabad nd badarpur
NTPC faridabad nd badarpurNTPC faridabad nd badarpur
NTPC faridabad nd badarpurShrey Dhasmana
 
MAHI REPORT.docx
MAHI REPORT.docxMAHI REPORT.docx
MAHI REPORT.docxAjmal Khan
 
MAHI REPORT.docx
MAHI REPORT.docxMAHI REPORT.docx
MAHI REPORT.docxAjmal Khan
 
MAHI REPORT.docx
MAHI REPORT.docxMAHI REPORT.docx
MAHI REPORT.docxAjmal Khan
 
thermal power plant NTPC singrauli
thermal power plant NTPC singrauli thermal power plant NTPC singrauli
thermal power plant NTPC singrauli Ram Narayan Shah
 
Internship Report on thermal power station in vizag steel plant
Internship Report on thermal power station in vizag steel plantInternship Report on thermal power station in vizag steel plant
Internship Report on thermal power station in vizag steel plantAbhishek Kumar
 
Ntpc badarpur summer training
Ntpc badarpur summer trainingNtpc badarpur summer training
Ntpc badarpur summer trainingAnubhav Ghosh
 
Thermal power plant from A.I.C.E Jaipur
Thermal power plant from A.I.C.E JaipurThermal power plant from A.I.C.E Jaipur
Thermal power plant from A.I.C.E JaipurChandra veer singh
 
Power plant technical overview report
Power plant technical overview reportPower plant technical overview report
Power plant technical overview reportASHOKKUMARPAL1
 
A summer training presentation on national thermal power
A summer training presentation on national thermal powerA summer training presentation on national thermal power
A summer training presentation on national thermal powerShishupal03012015
 
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial ReportELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial ReportUtkarsh Chaubey
 
Nuclear power plant kakarapar
Nuclear power plant kakaraparNuclear power plant kakarapar
Nuclear power plant kakaraparnaitik997
 

Similar to Ranjan NTPC KAHALGAON ppt (20)

NTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training ReportNTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training Report
 
NTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training ReportNTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training Report
 
Tarun Project Report On NTPC Kanti
Tarun  Project Report On NTPC KantiTarun  Project Report On NTPC Kanti
Tarun Project Report On NTPC Kanti
 
panki power plant training.ppt
panki power plant training.pptpanki power plant training.ppt
panki power plant training.ppt
 
V.T ppt
V.T pptV.T ppt
V.T ppt
 
NTPC faridabad nd badarpur
NTPC faridabad nd badarpurNTPC faridabad nd badarpur
NTPC faridabad nd badarpur
 
MAHI REPORT.docx
MAHI REPORT.docxMAHI REPORT.docx
MAHI REPORT.docx
 
MAHI REPORT.docx
MAHI REPORT.docxMAHI REPORT.docx
MAHI REPORT.docx
 
MAHI REPORT.docx
MAHI REPORT.docxMAHI REPORT.docx
MAHI REPORT.docx
 
thermal power plant NTPC singrauli
thermal power plant NTPC singrauli thermal power plant NTPC singrauli
thermal power plant NTPC singrauli
 
Internship Report on thermal power station in vizag steel plant
Internship Report on thermal power station in vizag steel plantInternship Report on thermal power station in vizag steel plant
Internship Report on thermal power station in vizag steel plant
 
Ntpc badarpur summer training
Ntpc badarpur summer trainingNtpc badarpur summer training
Ntpc badarpur summer training
 
adi ntpc.pptx
adi ntpc.pptxadi ntpc.pptx
adi ntpc.pptx
 
MTPS Bappa main
MTPS Bappa mainMTPS Bappa main
MTPS Bappa main
 
Thermal power plant from A.I.C.E Jaipur
Thermal power plant from A.I.C.E JaipurThermal power plant from A.I.C.E Jaipur
Thermal power plant from A.I.C.E Jaipur
 
Power plant technical overview report
Power plant technical overview reportPower plant technical overview report
Power plant technical overview report
 
A summer training presentation on national thermal power
A summer training presentation on national thermal powerA summer training presentation on national thermal power
A summer training presentation on national thermal power
 
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial ReportELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
 
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
 
Nuclear power plant kakarapar
Nuclear power plant kakaraparNuclear power plant kakarapar
Nuclear power plant kakarapar
 

More from Ranjan kumar

Seminar report theory
Seminar report theorySeminar report theory
Seminar report theoryRanjan kumar
 
Seminar report main page 2
Seminar report main page 2Seminar report main page 2
Seminar report main page 2Ranjan kumar
 
Seminar report main page 1
Seminar report main page 1Seminar report main page 1
Seminar report main page 1Ranjan kumar
 
Seminar report cover page
Seminar report cover pageSeminar report cover page
Seminar report cover pageRanjan kumar
 
Seminar presentation
Seminar presentationSeminar presentation
Seminar presentationRanjan kumar
 
Project main page 2
Project main page 2Project main page 2
Project main page 2Ranjan kumar
 
Project main page 2
Project main page 2Project main page 2
Project main page 2Ranjan kumar
 
Project main page 1
Project main page 1Project main page 1
Project main page 1Ranjan kumar
 
Project main page 1
Project main page 1Project main page 1
Project main page 1Ranjan kumar
 
Project cover page
Project cover pageProject cover page
Project cover pageRanjan kumar
 
Project cover page
Project cover pageProject cover page
Project cover pageRanjan kumar
 
NTPC KAHALGAON Main page
 NTPC KAHALGAON Main page NTPC KAHALGAON Main page
NTPC KAHALGAON Main pageRanjan kumar
 
NTPC KAHALGAON Cover page
NTPC KAHALGAON Cover pageNTPC KAHALGAON Cover page
NTPC KAHALGAON Cover pageRanjan kumar
 
SMART GRID TECHNOLOGY
SMART GRID TECHNOLOGYSMART GRID TECHNOLOGY
SMART GRID TECHNOLOGYRanjan kumar
 

More from Ranjan kumar (18)

Seminar report theory
Seminar report theorySeminar report theory
Seminar report theory
 
Seminar report main page 2
Seminar report main page 2Seminar report main page 2
Seminar report main page 2
 
Seminar report main page 1
Seminar report main page 1Seminar report main page 1
Seminar report main page 1
 
Seminar report cover page
Seminar report cover pageSeminar report cover page
Seminar report cover page
 
Seminar presentation
Seminar presentationSeminar presentation
Seminar presentation
 
Project report
Project reportProject report
Project report
 
Project report
Project reportProject report
Project report
 
Project main page 2
Project main page 2Project main page 2
Project main page 2
 
Project main page 2
Project main page 2Project main page 2
Project main page 2
 
Project main page 1
Project main page 1Project main page 1
Project main page 1
 
Project main page 1
Project main page 1Project main page 1
Project main page 1
 
Project cover page
Project cover pageProject cover page
Project cover page
 
Project cover page
Project cover pageProject cover page
Project cover page
 
NTPC KAHALGAON Main page
 NTPC KAHALGAON Main page NTPC KAHALGAON Main page
NTPC KAHALGAON Main page
 
NTPC KAHALGAON Cover page
NTPC KAHALGAON Cover pageNTPC KAHALGAON Cover page
NTPC KAHALGAON Cover page
 
Ranjan resume
Ranjan  resumeRanjan  resume
Ranjan resume
 
SMART GRID TECHNOLOGY
SMART GRID TECHNOLOGYSMART GRID TECHNOLOGY
SMART GRID TECHNOLOGY
 
RANJAN RESUME 1
RANJAN RESUME 1RANJAN RESUME 1
RANJAN RESUME 1
 

Recently uploaded

ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxEyham Joco
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Jisc
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupJonathanParaisoCruz
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitolTechU
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...jaredbarbolino94
 
MICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxMICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxabhijeetpadhi001
 
Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxUnboundStockton
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 

Recently uploaded (20)

ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptx
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized Group
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptx
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...
 
MICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxMICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptx
 
Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docx
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 

Ranjan NTPC KAHALGAON ppt

  • 1. SUMMER PRACTICAL TRAINING AT SUBMITTED BY:- RANJAN KUMAR 14EAIEE079 B.Tech. IV Yr. VII SEM SUBMITTED TO :- Mr. Deepak Sharma Head of Department Electrical Engineering NATIONAL THERMAL POWER CORPORATION LTD. ( NTPC ) KAHALGAON (BIHAR)
  • 2. CONTENTS :- 1. Introduction 2. Coal Handling System 3. Ash Handling System 4. Boiler and its auxiliaries 5. Turbine and its auxiliaries 6. Off-Site Department 7. Electric Generator and its auxiliaries 8. Electric Transformer 9. Switchyard 10.Control and Instrumentation Department 1
  • 3. 1. Introduction about NTPC :- 2 NTPC Limited is the largest thermal power generating company of India. Established in 7 November 1975. In 1997, Government of India granted NTPC status of “Navratna” company. NTPC became a “Maharatna”company in May, 2010, one of the only four companies to be awarded this status in India.  Present installed Capacity of NTPC is 51,635 MW . Total 48 NTPC in India.  It has 20 coal based power stations (38,755 MW) . 7 gas based power stations (4,017 MW) 9 Joint Ventures based power stations (7,216 MW). 11 renewable energy based power plant(845 MW) Annual turnover of Rs. 73,904 cr. with profit of Rs. 13,834 Cr. for the year 2013-14. It contributes 28.60% of total power .
  • 4. National Thermal Power Corporation LTD. (NTPC) 3
  • 5. Introduction about NTPC Kahalgaon Bihar :- Location : Kahalgaon , District-Bhagalpur (Bihar) , 813214 Total Land : 3,360 acres Land for plant : 883 acres Land for township : 432 acres Land for Ash dyke :1395 acres Source of water : Ganga River Source of coal : Rajmahal coal field of ECL (Lalmatia , Jharkhand)  Configuration: stage -1 has 4 unit (each unit capacity 210 MW) , which was established by Russia in 1991. stage -2 has 3 unit (each unit capacity 500 MW) , which was established by BHEL in 1996. Total installed capacity : 2340 MW Fuel Requirement : 4.1 million ton per year stage -1 : 6.62 million ton per year for stage -2 ( phase-1 ) : 3 million ton per year for stage -2 ( phase-2 ) 4
  • 6. 5
  • 7. 2. Coal Handling System Equipment : 6 Wagon  Tripler Conveyor Belt Pulleys Magnetic separator Crushing house Vibrating screen Pulverized coal Storage of coal The function of coal handling plant is automatic feeding of coal to the boiler  A thermal power plant burns enormous amounts of coal.  In NTPC Kahalgaon 2340MW Plant may require around 23400 tons of coal daily. Step in coal handling plant:
  • 8. 7
  • 9. Why Coal? Coal 55% Gas 10% Diesel 1% Hydel 26% RES 5% Nuclear 3% Share of Coal in Power Generation Advantages of Coal Fuel •Abundantly available in India •Low cost •Technology for Power Generation well developed. •Easy to handle, transport, store and use •India’s Coal Reserves are estimated to be 206 billion tones. Present consumption is about 450 million tones. •Cost of coal for producing 1 unit of electricity is Rs 0.75. •Cost of Gas for producing 1 unit of electricity is Rs 1.20. 8
  • 10. 3. Ash Handling System:  WHAT IS ASH ? Ash is the collection of residuals producing after the combustion of coal at constant weight under standard conditions. Ash is oxidized form of the mineral matters present in coal. Typical ash composition : SiO2, Al2O3, Fe2O3, CaO, MgO etc.  WHY ASH HANDLING?  Ash content of Indian coal used in power station is about 30 to 40 %.  A typical 2000 MW station produce around 9000T to 12000T of ash per day.  This huge amount of ash needs to be disposed off continuously.  Necessary care to be taken for preventing pollution. 9
  • 11.  Bottom ash can be collected at furnace bottom as Wet or Dry form.  Bottom ash is the heavier portion of coal ash that settles on the ground in the boiler.  Bottom ash is part of the non-combustible residue of combustion in a furnace or incinerator.  Approximately 80% of bottom ash consist overall of coal ash content. 1. Bottom Ash: 10
  • 12. 2. Fly Ash: • Fly ash, also known as “pulverized fuel ash”. • Ash generated in the ESP which got carried out with the flue gas is generally known as fly ash. • It consist of air preheater ash and economizer ash. • Approximately 20% of fly ash consist overall of coal ash content. • FA is collected from Air heater hopper, Eco hopper and ESP hopper. Use of ash: • In concrete production • In cement production • In stabilization of soft soils • In bricks production • Road construction • Other applications include cosmetics, toothpaste, ceiling tiles, bowling balls, flotation devices, PVC pipe, picture frames, doors, window frames, park benches railroad ties. 11
  • 13. Coal Seam Surge Pile Pulverize (-150) Overburden Fly Ash Flue Gas Electrostatic Precipitator Flue Gas Boiler Fly Ash Bottom Ash Smoke Stack Fly Ash Bottom Ash 12
  • 14. Boiler:-  Boiler is a long column where coal is fired to produce heat and to convert water into superheated steam.  In NTPC – Kahalgaon, the height of the boiler is 90 meter.  Type of boiler used in NTPC SSTPS in Stage-I and II are Water tube boilers.  Maximum Temperature and pressure of main steam for stage -1 is 540ºc and 140 bar respectively.  Maximum Temperature and pressure of main steam for stage -2 is 545ºc and 170 bar respectively.  MAIN PART OF BOILER: 1. Economizer 4. super-heater 2. Deaerator 5. Re-heater 3. Furnace 6. Different type of fan 13
  • 15. 14
  • 16. A steam turbine is a rotating device which converts thermal energy into mechanical energy. In NTPC Kahalgaon LMZ (Russia) type steam turbine is used. There are 3 types of Turbines used in Thermal Power Plants: 1. High pressure turbine (HP Turbine) 2. Intermediate pressure turbine (IP Turbine) 3. Low pressure turbine (LP Turbine)  Turbine blade is air foil shape. TURBINE :- 15
  • 17. 1. High Pressure Turbine: 16 1.HIGH PRESSURE TURBINE:-  Single Flow Cylinder  Double Casing  Thermal expansion up to 16mm
  • 18. 2. Intermediate Pressure Turbine 17 2.INTERMEDIATE PRESSURE TURBINE:-  Double Flow  Double Casing  Axially Split Design in both Casings  Rigid Coupling  Blade Shrouded & Inverted T-Root Design
  • 19. 3. Low Pressure Turbine: 18 3.LOW PRESSURE TURBINE:-  Largest Turbine  Pressure is Very Less  Three Shell Design  Double Flow  All Casings Axially Split  Exhaust Hood Spray Arrangement  2 Free Standing Blades in the end
  • 20. 19
  • 21. 1. Water Treatment Plant/DM plant: Why water treatment?  Raw water contains many dissolved minerals and organic materials.  For removal of total solids such as Ca , Mg ,Na ,Cl , Alkalinity , silica etc.  At high temperature certain minerals left scaling on the tube metal of the boiler and cause permanent damage.  Some dissolved minerals leads to corrosion of tube metals.  At high pressure and temperature an element, silica can be carried away with steam causing damage to turbine low pressure stage.  The performance and life expectancy of the station greatly depends on water chemistry compliance. 6. Off-Site Department: 1. Water Treatment (DM Plant) 2. Cooling Tower  Steps of treatment process: 1. Aeration of raw water 2. Adding chemicals for bacteria removal 3. Adding chemicals for sedimentation of suspended particles 4. Flocculation 5. Filtration 6. Ion Exchange process 20
  • 22. 2. Cooling Tower: A cooling tower is a heat rejection device that rejects waste heat to the atmosphere through the cooling of a water stream to a lower temperature. 21
  • 23. 7. Electric Generator and its auxiliaries:  A turbo generator is the combination of a turbine directly connected to an electric generator for the generation of electric power.  An electric generator is a device that converts mechanical energy to electrical energy.  It is based upon the principle of electromagnetic induction.  Turbogenerator: Cooling of Generator :  Hydrogen cooling: - Rotor core and Rotor winding.  DM Water cooling:- Stator core and Stator winding.  Excitation System:  Maintain the reactive power.  Wear and Tear problem will be minimize.  In NTPC Kahalgaon brushless excitation is used. 22
  • 24. Capacity 210 KW Power Factor 0.85 lagging KVA 588,000 Stator Voltage 15.75 KV Stator current 9.03 KA Rotor Voltage 303 V Rotor current 2.330 KA RPM 3000 Frequency 50 HZ Phase 3 Connection YY Coolant Water & Hydrogen Gas Pressure 4 Bar Insulation Class B Type TG-HH-0500-2 Make Russia Stage-1 Turbogenerator Rating:- Capacity 500 KW Power Factor 0.85 lagging KVA 588,000 Stator Voltage 21 KV Stator current 16.2 KA Rotor Voltage 340 V Rotor current 4040 A RPM 3000 Frequency 50 HZ Phase 3 Connection YY Coolant Water & Hydrogen Gas Pressure 4 Bar Insulation Class B Type TG-HH-0500-2 Make BHEL Haridwar Stage-2 Turbogenerator Rating:- 23
  • 25. 8. Electric Transformer:  A transformer is a device that transfer electrical energy from one electrical circuit to another circuit through the medium Of magnetic field without change in frequency. WORKING PRINCIPLE: Definition:  It works on FARADAY’S LAW OF ELECTROMAGNETIC INDUCTION (self or mutual induction depending on the type of transformer). Transformer used in NTPC Kahalgaon: 1. Generator transformer 2. Station transformer 3. Unit Auxiliary transformer (UAT) 4. Other Electric transformer 24
  • 26. 9. Switchyard:  ELECTRICAL EQUIPMENTS: 1. Bus-Bar 2. Lightning Arrester 3. Wave Trap 4. Capacitive Voltage Transformer 5. Relay 6. Circuit Breaker 7. Instrument Transformer 8. Earthing Rod 9. PLCC 10. INSULATORS 25
  • 27.  Distribution System: Figure: Single Line Diagram of NTPC Kahalgaon 400/132 KV Switchyard 26
  • 28. 10. Control and Instrumentation Department:  The main functions of the C&I dept. at NTPC Kahalgaon are: 1. Measurement and display of various parameters. 2. To control the various parameters by Automatic feedback controlling which involves the taking of decision based on inputs from measurements by the processor. 3. Protection of various equipment’s (pumps, generators etc.) and workers from hazards by automatically tripping a cycle when hazardous conditions are reached. 4. Alarm generation in case of a mechanical or an electrical failure. 27
  • 29. 28
  • 30. 29