SlideShare a Scribd company logo
1 of 42
Download to read offline
STANDARD COSTING
ARUN KUMAR M.Com., (Ph.D.)
Asst. Professor,
Department of Commerce,
Govt. First Grade College, Koppa
g-mail: arunkumarduna@gmail.com
STANDARD
The term standard is a predetermined measurable quantity set in
defined conditions against which actual performance can be
compared.
In Simple, we can say the term standard refers to predetermined
rate against which performance is judged
STANDARD COST
Standard-cost is defined by CIMA in the following way:—A predetermined calculation of how
much cost should be used under specified working conditions.
In other words, this is theoretically the amount of money a company will have to spend to
produce a product or perform a service under normal conditions
Standard Costing
Standard costing is a technique which is used in many industries,
where production is of repetitive nature.
Standard Costing is the method of measuring the differences
between the costs actually incurred in manufacturing and the
expected costs under “standard condition”, which always refers to
a specific costing rule which serves as the basis.
Variance Analysis
A variance is the difference between the standards and the actual
performance
When the actual results are better than the expected results,
there will be a favourable variance (F)
If the actual results are worse than the expected results, there
will be an adverse variance (A)
Classification Of Variances
Functional Basis
Measurement Basis
Result Basis
Functional Basis
Functional
Basis
Variance related
to Cost factor
Material
Labour
Variance related
to Sales factor Overhead
Measurement Basis
Difference between the
standard cost and the actual
cost in terms of money is
known as absolute variance.
Difference is expressed as a
percentage of the standard
cost, it is known as relative
variance.
Result basis When the actual results are better than the
expected results, there will be a
favourable variance (F)
If the actual results are worse than the
expected results, there will be an adverse
variance (A)
Cost variance
• Cost variance = Price variance + Quantity variance
Cost variance is the difference between the standard cost and the Actual cost
• Price variance = (standard price – actual price)*Actual quantity
A price variance reflects the extent of the profit change resulting from the change in activity
level
• Quantity variance = (standard quantity – actual quantity)* standard
cost
A quantity variance reflects the extent of the profit change resulting from the change in activity level
Three types of cost variance
• Material cost variance
• Labour cost variance
• Variable overheads variance
Material Cost variance
Material Cost Variances
Material Price Variances Material Usage Variances
Material Mix Variance
Material Yield Variance
MATERIAL COST VARIANCE:
Material cost variance is the difference between standard cost and
actual cost. Mathematically it is written as
Formula:
MCV = (SQ × SP) – (AQ × AP)
Material Cost Variance = Standard quantity × Standard Price-(Actual
quantity × Actual Price)
Or
Material Price Variance:
It measures variance arises in the material cost due to difference in actual material
purchase price from standard material price. Mathematically it is written as:
Material Price Variance:
𝐴𝑐𝑡𝑢𝑎𝑙 𝑞𝑢𝑎𝑛𝑡𝑖𝑡𝑦 ∗ × (𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑝𝑟𝑖𝑐𝑒 − 𝐴𝑐𝑡𝑢𝑎𝑙 𝑝𝑟𝑖𝑐𝑒)
MPV = AQ x (SP-AP)
Or
*Here actual quantity means actual quantity of material purchased. If in
the question material purchase is not given, it is taken as equal to material
Material Usage Variance:
It measures variance in material cost due to usage/ consumption of
materials. It is computed as well
Material Usage Variance:
𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑃𝑟𝑖𝑐𝑒 × (𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑄𝑢𝑎𝑛𝑡𝑖𝑡𝑦 − 𝐴𝑐𝑡𝑢𝑎𝑙 𝑄𝑢𝑎𝑛𝑡𝑖𝑡𝑦) ∗
MUV: SP (SQ − AQ)
Or
*Here actual quantity means actual quantity of material used
Material Mix Variance:
Variance in material consumption may arise due to difference in proportion
used actually from the standard mix/ proportion. It arises only when two
more inputs are used to produce a product.
Material Mix Variance = (Revised standard quantity – Actual quantity) × Standard price
Or
MMV= (RSQ – AQ) × SP
Where;
RSQ =
𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑞𝑢𝑎𝑛𝑡𝑖𝑡𝑦 𝑜𝑓 𝑜𝑛𝑒 𝑚𝑎𝑡𝑒𝑟𝑖𝑎𝑙
𝑻𝒐𝒕𝒂𝒍 𝑜𝑓 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑞𝑢𝑎𝑛𝑡𝑖𝑡𝑦 𝑜𝑓 𝐴𝑙𝑙 𝑚𝑎𝑡𝑒𝑟𝑖𝑎𝑙
× Total of Actual of all material
Material Yield Variance (or Material Sub-usage Variance):
Variance in material consumption which arise due to yield or productivity of the inputs.
It may arise due to use of sub-standard quality of materials, inefficiency of workers or
due to wrong processing.
Material Revised Usage Variance =
(𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑄𝑢𝑎𝑛𝑡𝑖𝑡𝑦 − 𝑅𝑒𝑣𝑖𝑠𝑒𝑑 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑄𝑢𝑎𝑛𝑡𝑖𝑡𝑦) × 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑃𝑟𝑖𝑐𝑒
Or
MRUV = (SQ – RSQ) SP
Material Yield Variance:
(𝐴𝑐𝑡𝑢𝑎𝑙 𝑌𝑖𝑒𝑙𝑑 − 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑌𝑖𝑒𝑙𝑑) × 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑜𝑢𝑡𝑝𝑢𝑡 𝑝𝑟𝑖𝑐𝑒
Or
MYV = (AY – SY) SOP
Verification of the Formula:
Material Cost Variance = Material Usage Variance + Material
Price Variance*
Or
Material Cost Variance = (Material Mix Variance + Material
Revised usage Variance) +Material price variance
*If material purchase quantity and material consumed quantity is same
The Standard material required to manufacture one unit of product
‘X’ is 10 Kgs, and the standard price per kg of material is ₹ 25 Kgs.
The cost account records, however reveals that 11,500 Kgs,
Materials costing ₹ 2, 76,000 were used for manufacture of 1,000
units of product ‘X’. Calculate material variances.
Illustration 1
Calculation of Material Variance
 Material cost variances = (𝑆𝑄 × 𝑆𝑃) – (𝐴𝑄 × 𝐴𝑃)
 Material Price Variance = 𝐴𝑄 × (𝑆𝑃 − 𝐴𝑃)
 Material Usage Variance = 𝑆𝑄 − 𝐴𝑄 × 𝑆𝑃
Given:
SQ: For Production of 1 unit Required 10 Kgs of Material
There fore for 1000 units = 1000 × 10 = 10,000 Kgs
AQ: 11,500 Kgs
SP: ₹ 25
AP: ₹ 24 ( 2,76,000/11,500Kgs)
The Standard material required to
manufacture one unit of product ‘X’ is 10
Kgs, and the standard price per kg of
material is ₹ 25 Kgs. The cost account
records, however reveals that 11,500 Kgs,
Materials costing ₹ 2, 76,000 were used for
manufacture of 1,000 units of product ‘X’.
= (10,000Kgs× ₹ 25) – (11,500 × ₹24)
= 2,50,000 – 2,76,000
= ₹ 26,000(A)
= (25 – 24) × 11,500
= 1 × 11,500
= ₹ 11,500 (F)
= (10,000 – 11,500) × 25
= (- 1,500) × 25
= ₹ 37,500 (A)
SQ: 10,000 Kgs
AQ : 11,500 Kgs
SP: ₹ 25
AP: ₹ 24
MCV = (SQ × SP) – (AQ × AP)
MPV = (SP – AP) × AQ
MUV = (SQ – AQ) × SP
Darling Company limited works on the standard costing system and
produces X. The standard estimates of material for the manufacturer
of 1,000 units of product X is 400 Kgs at ₹ 2.5 per kg. In the month
of January 2018, manufactured 2,000 units of product X and it is
found that 820 Kgs of material is consumed at ₹ 2.60 per kg.
Calculate - Material Variance
Illustration 2
Calculation of Material Variance
 Material cost variances = (𝑆𝑄 × 𝑆𝑃) – (𝐴𝑄 × 𝐴𝑃)
 Material Price Variance = 𝐴𝑄 × (𝑆𝑃 − 𝐴𝑃)
 Material Usage Variance = 𝑆𝑄 − 𝐴𝑄 × 𝑆𝑃
Given:
SQ = for 1000 units need 400 kgs = for 2000 units
400
1000
× 2,000 = 800
AQ = 820 kgs for 2000 units
SP = ₹ 2.5
AP = ₹ 2.6
The standard estimates of material for
the manufacturer of 1,000 units of
product X is 400 Kgs at ₹ 2.5 per kg. In
the month of January 2018,
manufactured 2,000 units of product X
and it is found that 820 Kgs of material
is consumed at ₹ 2.60 per kg.
= (800 × 2.50) – (820 × 2.60)
= 2,000 – 2132
= 132 (A)
= (2.50 – 2.60) × 820
= ( - 0.10) × 820
= 82 (A)
= (800 – 820) × 2.50
= (- 20) – 2.5
= 50 (A)
SQ: 800
AQ: 820
SP: ₹ 2.5
AP: ₹ 2.6
MCV = (SQ × SP) – (AQ × AP)
MPV = (SP – AP) × AQ
MUV = (SQ – AQ) ×SP
LABOUR VARIANCE
LABOUR COST VARIANCE
Labour cost variance is the difference between standard
labour cost allowed for actual output achieved and actual
labour cost. It is also known as wages variance.
(𝑆𝑡𝑑. ℎ𝑜𝑢𝑟 𝑓𝑜𝑟 𝑎𝑐𝑡𝑢𝑎𝑙 𝑜𝑢𝑡𝑝𝑢𝑡 × 𝑆𝑡𝑑. 𝑟𝑎𝑡𝑒 𝑝𝑒𝑟 ℎ𝑜𝑢𝑟) − (𝐴𝑐𝑡𝑢𝑎𝑙 ℎ𝑜𝑢𝑟𝑠
× 𝐴𝑐𝑡𝑢𝑎𝑙 𝑟𝑎𝑡𝑒 𝑝𝑒𝑟 ℎ𝑜𝑢𝑟)
Labour Cost Variance:
𝐿𝑎𝑏𝑜𝑢𝑟 𝐶𝑜𝑠𝑡 Variance = St. Labour Cost for actual output − Actual labour cost
or
Labour Cost Variance
Labour Efficiency Variance
Labour Yield VarianceIdle- Time VarianceLabour Mix Variance
Labour Rate Variance
Classification of Labour Cost Variance
Labour Rate (Pay) Variance
Labour rate variance arises due to “difference in actual rate paid
from standard rate”
Labour Rate Variance = (Std. Rate - Actual Rate) × Actual Hours
Labour Efficiency (Time) Variance
Labour efficiency variance arises due to “deviation in the
working hour from the set standard”
Labour Efficiency Variance:
𝑆𝑡𝑑. 𝑅𝑎𝑡𝑒 (𝑆𝑡𝑑. ℎ𝑜𝑢𝑟𝑠 𝑓𝑜𝑟 𝑎𝑐𝑡𝑢𝑎𝑙 𝑜𝑢𝑡𝑝𝑢𝑡 − 𝐴𝑐𝑡𝑢𝑎𝑙 𝐻𝑜𝑢𝑟𝑠) ∗
*Actual time worked
Idle Time Variance
Idle Time Variance is calculated for the unproductive
labour hours. Here idle time means labour idle time arises
due to abnormal
Idle Time Variance:𝐼𝑑𝑒𝑙 ℎ𝑜𝑢𝑟𝑠 × 𝑆𝑡𝑑. 𝑟𝑎𝑡𝑒 (or) ITV = IH × SR
Labour Mix Variance - (Gang Composition
Variance):
Labour Mix variance which arises due to change in the proportion
or combination of different skill set i.e. number of skilled workers,
semi-skilled workers and un-skilled workers.
Labour Mix Variance:(𝑅𝑒𝑣𝑖𝑠𝑒𝑑 𝑆𝑡𝑑. ℎ𝑜𝑢𝑟𝑠 − 𝐴𝑐𝑡𝑢𝑎𝑙 ℎ𝑜𝑢𝑟𝑠) × 𝑆𝑡𝑑. 𝑟𝑎𝑡𝑒
Revised Standard Hours:
𝑅𝑒𝑣𝑖𝑠𝑒𝑑 𝑠𝑡𝑎𝑛𝑑𝑎𝑟𝑑 ℎ𝑜𝑢𝑟𝑠 =
𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 ℎ𝑜𝑢𝑟𝑠 𝑜𝑓 𝑡ℎ𝑒 𝑔𝑟𝑎𝑑𝑒
𝑇𝑜𝑡𝑎𝑙 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝐻𝑜𝑢𝑟𝑠
× 𝑇𝑜𝑡𝑎𝑙 𝐴𝑐𝑡𝑢𝑎𝑙 𝐻𝑜𝑢𝑟𝑠
Labour Yield Variance
Labour Yield variance which arises due to productivity
of workers
Labour Yield Variance:
𝐴𝑐𝑡𝑢𝑎𝑙 𝑦𝑖𝑒𝑙𝑑 − 𝑆𝑡𝑑. 𝑌𝑖𝑒𝑙𝑑 𝑓𝑜𝑟 𝑎𝑐𝑡𝑢𝑎𝑙 𝑖𝑛𝑝𝑢𝑡 𝑆𝑡𝑑. 𝐿𝑎𝑏𝑜𝑢𝑟 𝑐𝑜𝑠𝑡 𝑝𝑒𝑟 𝑢𝑛𝑖𝑡 𝑜𝑓 𝑜𝑢𝑡𝑝𝑢𝑡
Labour Revised Efficiency Variance:
(𝑆𝑡𝑑. ℎ𝑜𝑢𝑟𝑠 𝑓𝑜𝑟 𝑎𝑐𝑡𝑢𝑎𝑙 𝑜𝑢𝑡𝑝𝑢𝑡 − 𝑟𝑒𝑣𝑖𝑠𝑒𝑑 𝑆𝑡𝑑. ℎ𝑜𝑢𝑟𝑠) 𝑆𝑡𝑑. 𝑟𝑎𝑡𝑒
Or
Dept. A
Actual direct wages ₹ 2,000
Standard hours 8,000
Standard rate per hour ₹ 30 paise
Actual hours worked 8,200
From the following, calculate labour variances of department A
Given:
SH : 8000
SR: ₹ 0.30
AH : 8200
AR: ?
AR = 𝐴𝑐𝑡𝑢𝑎𝑙 𝐷𝑖𝑟𝑒𝑐𝑡 𝑊𝑎𝑔𝑒𝑠
𝐴𝑐𝑡𝑢𝑎𝑙 𝐻𝑜𝑢𝑟𝑠 𝑊𝑜𝑟𝑘𝑒𝑑
= ₹ 2000
8200 ℎ𝑜𝑢𝑟𝑠
AR= 0.2439AR: ₹ 0.2439
ILLUSTRATION
Calculation of Labour variance
= (8,000 Hr × ₹0.30) – (8,200 Hr × ₹0.2439)
= ₹ 2400 – ₹ 2,000
= ₹ 400(F)
1. Labour cost variance = (SH × SR) – (AH × AR)
2. Labour rate (pay) variance = (SR – AR) × AH
3. Labour efficiency (time) variance = (SH – AH) × SR
LCV = (SH × SR) – (AH × AR)
SH : 8000
SR: ₹ 0.30
AH : 8200
AR: ₹ 0.2439
= (₹ 0.30 – ₹ 0.2439) × 8200 Hr
= ₹ .00561 × 8200 Hr
= 460 (F)
= (8000 – 8200) × ₹ 0.30
= (-200) × 0.30
= 60 (A)
LPV = (SR – AR) × AH
LEV = (SH – AH) × SR
Labour Cost Variance 400 (F)
Labour Efficiency (Time) Variance 60 (A)Labour Rate Variance 460 (F)
The information regarding composition and the weekly wages rates of labour force
engaged on a job scheduled to be completed in 60 weeks are as follows:
Types of labour
Standard Actual
No. of workers
Weekly wage rate
per hour
No. of workers
Weekly wage
rate per hour
Skilled 75 60 70 70
Semi-skilled 45 40 30 50
Unskilled 60 30 80 20
The work completed in 62 weeks.
Calculate:
(a) Labour cost variance
(b) Labour rate variance
(c) Labor efficiency variance
(d) Labour mix variance
ILLUSTRATION
Workers
Standard Mix
Hours
(No. of Workers × 60
Weeks)
Rate Per Hour Cost
Skilled 75 × 60 = 4,500 60 2,70,000
Semi-Skilled 45 × 60 = 2,700 40 1,08,000
Unskilled 60 × 60 = 3,600 30 1,08,000
Total 10,800 4,86,000
Calculation of Labour Variance:
Workers
Actual Mix
Hours
(No. of Workers ×
62 Weeks)
Rate Per Hour Cost
Skilled 70 × 62 = 4,340 70 3,03,800
Semi-Skilled 30 × 62 = 1,860 50 93,000
Unskilled 80 × 62 = 4,960 20 99,200
Total 11,160 4,96,000
Labour Cost Variance
LCV = SC - AC = ₹
Skilled = 2,70,000 - 3,03,000 = 33,800(A)
Semi- Skilled = 1,08,000 - 93,000 = 15,000 (F)
Unskilled = 1,08,000 - 99,200 = 8,800 (F)
= 10,000(A)
Labour Rate (Pay) Variance:
LRV = (SR – AR) × AH = ₹
Skilled = (60 – 70) × 4,340 = 43,400(A)
Semi- Skilled = (40 – 50) × 1,860 = 18,600 (A)
Unskilled = (30 – 20) × 4,960 = 49,600 (F)
=12,400 (A)
Labour Efficiency Variance:
LEV = (SH – AH) × SR = ₹
Skilled = (4,500 – 4,340) × 60 = 9,600 (F)
Semi- Skilled = (2,700 – 1,860) × 40 = 33,600 (F)
Unskilled = (3,600 – 4,960) × 30 = 40,800 (A)
= 2,400 (F)
Labour Mix Variance = ( 𝐑𝐒𝐓 − 𝐀𝐓) × 𝑺𝑹
Revised Standard Hours:
𝑅𝑒𝑣𝑖𝑠𝑒𝑑 𝑠𝑡𝑎𝑛𝑑𝑎𝑟𝑑 ℎ𝑜𝑢𝑟𝑠 =
𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 ℎ𝑜𝑢𝑟𝑠 𝑜𝑓 𝑡ℎ𝑒 𝑔𝑟𝑎𝑑𝑒
𝑇𝑜𝑡𝑎𝑙 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝐻𝑜𝑢𝑟𝑠
× 𝑇𝑜𝑡𝑎𝑙 𝐴𝑐𝑡𝑢𝑎𝑙 𝐻𝑜𝑢𝑟𝑠
Unskilled =
3,600
10,800
× 11,160 = 3,720
Skilled =
4,500
10,800
× 11,160 = 4,650
Semi skilled =
2,700
10,800
× 11,160 = 2,790
Workers
Standard Mix Actual Mix
Hours
(No. of Workers × 60 Weeks)
Hours
(No. of Workers × 62 Weeks)
Skilled 4,500 4,340
Semi-Skilled 2,700 1,860
Skilled 3,600 4,960
Total 10,800 11,160
Labour Mix Variance = ( 𝐑𝐒𝐓 − 𝐀𝐓) × 𝑺𝑹
LMV = (RST – AT) × SR = ₹
Skilled = (4,650 – 4,340) × 60 = 18,600 (F)
Semi- Skilled = (2,790 – 1,860) × 40 = 37,200 (F)
Unskilled = (3,720 – 4,960) × 30 = 37,200 (A)
LCV Rs. 10,000 (A)
LRV Rs. 12,400(A) LEV 2,400 (F)
Thank You

More Related Content

What's hot

Responsibility Accounting and Transfer pricing
Responsibility Accounting and Transfer pricingResponsibility Accounting and Transfer pricing
Responsibility Accounting and Transfer pricingPrathmesh Amberkar
 
Cost volume profit analysis
Cost volume profit analysisCost volume profit analysis
Cost volume profit analysiskamran
 
Ca chap 13 standard costing&variance analysis(2)
Ca chap 13 standard costing&variance analysis(2)Ca chap 13 standard costing&variance analysis(2)
Ca chap 13 standard costing&variance analysis(2)DSDEVDA
 
Introduction to cost & management accounting
Introduction to cost & management accountingIntroduction to cost & management accounting
Introduction to cost & management accountingHassan Samoon
 
Responsibility accounting
Responsibility  accountingResponsibility  accounting
Responsibility accountingKriti Avasthi
 
Inventories and the Cost of Goods Sold
Inventories and the Cost of Goods SoldInventories and the Cost of Goods Sold
Inventories and the Cost of Goods SoldMuhammad Unaib Aslam
 
Financial Statement
Financial StatementFinancial Statement
Financial StatementPadum Chetry
 
Reconciliation of cost and financial accounts
Reconciliation of cost and financial accountsReconciliation of cost and financial accounts
Reconciliation of cost and financial accountsMahesh Chandra Sharma
 
Overhead cost variance
Overhead cost varianceOverhead cost variance
Overhead cost variancePAWANGUPTA327
 
Management -accounting ppt
Management -accounting pptManagement -accounting ppt
Management -accounting pptBabasab Patil
 
Cost Behavior Analysis
Cost Behavior AnalysisCost Behavior Analysis
Cost Behavior AnalysisJhOnie JhOan
 
Flexible Budgeting
Flexible BudgetingFlexible Budgeting
Flexible BudgetingJunaid Inam
 
Absorption Costing and Marginal Costing ppt
Absorption Costing and Marginal Costing pptAbsorption Costing and Marginal Costing ppt
Absorption Costing and Marginal Costing pptVaseemParry
 

What's hot (20)

Responsibility Accounting and Transfer pricing
Responsibility Accounting and Transfer pricingResponsibility Accounting and Transfer pricing
Responsibility Accounting and Transfer pricing
 
Cost volume profit analysis
Cost volume profit analysisCost volume profit analysis
Cost volume profit analysis
 
Ca chap 13 standard costing&variance analysis(2)
Ca chap 13 standard costing&variance analysis(2)Ca chap 13 standard costing&variance analysis(2)
Ca chap 13 standard costing&variance analysis(2)
 
Introduction to cost & management accounting
Introduction to cost & management accountingIntroduction to cost & management accounting
Introduction to cost & management accounting
 
Profit Maximization
Profit MaximizationProfit Maximization
Profit Maximization
 
Standard costing
Standard costingStandard costing
Standard costing
 
Job and batch costing
Job and batch costingJob and batch costing
Job and batch costing
 
Responsibility accounting
Responsibility  accountingResponsibility  accounting
Responsibility accounting
 
Inventories and the Cost of Goods Sold
Inventories and the Cost of Goods SoldInventories and the Cost of Goods Sold
Inventories and the Cost of Goods Sold
 
Financial Statement
Financial StatementFinancial Statement
Financial Statement
 
Activity-Based Costing System
Activity-Based Costing SystemActivity-Based Costing System
Activity-Based Costing System
 
Reconciliation of cost and financial accounts
Reconciliation of cost and financial accountsReconciliation of cost and financial accounts
Reconciliation of cost and financial accounts
 
Overhead cost variance
Overhead cost varianceOverhead cost variance
Overhead cost variance
 
Management -accounting ppt
Management -accounting pptManagement -accounting ppt
Management -accounting ppt
 
Cost sheet preparation.pptx
Cost sheet preparation.pptxCost sheet preparation.pptx
Cost sheet preparation.pptx
 
Inventory Accounting
Inventory AccountingInventory Accounting
Inventory Accounting
 
Cost Behavior Analysis
Cost Behavior AnalysisCost Behavior Analysis
Cost Behavior Analysis
 
Basic cost concepts
Basic cost conceptsBasic cost concepts
Basic cost concepts
 
Flexible Budgeting
Flexible BudgetingFlexible Budgeting
Flexible Budgeting
 
Absorption Costing and Marginal Costing ppt
Absorption Costing and Marginal Costing pptAbsorption Costing and Marginal Costing ppt
Absorption Costing and Marginal Costing ppt
 

Similar to Standard costing and Variance Analysis

Akaun Chapter 11
Akaun Chapter 11Akaun Chapter 11
Akaun Chapter 11WanBK Leo
 
Standard-Costing-Variance-Analysis.ppt
Standard-Costing-Variance-Analysis.pptStandard-Costing-Variance-Analysis.ppt
Standard-Costing-Variance-Analysis.pptJomarDoctora
 
Amresh management accounting
Amresh management accountingAmresh management accounting
Amresh management accountingAMRESH VELGEKAR
 
Standard cost, labor & material variance
Standard cost, labor & material varianceStandard cost, labor & material variance
Standard cost, labor & material varianceAwais052
 
9. Chapter 23, 24 Performance Evaluation.pdf
9. Chapter 23, 24 Performance Evaluation.pdf9. Chapter 23, 24 Performance Evaluation.pdf
9. Chapter 23, 24 Performance Evaluation.pdfThyLinhLTh6
 
Managerial Accounting Project.pptx
Managerial Accounting Project.pptxManagerial Accounting Project.pptx
Managerial Accounting Project.pptxTeeshaGehaniJagdesh
 
Stdcostingppt
StdcostingpptStdcostingppt
StdcostingpptTaha Rais
 
Standard costing and variances
Standard costing and variancesStandard costing and variances
Standard costing and variancespankajmaini
 
Management accounting overhead variance
Management accounting   overhead varianceManagement accounting   overhead variance
Management accounting overhead varianceBiswajit Bhattacharjee
 
Standard Costing Operational Performance Measures And
Standard Costing Operational Performance Measures AndStandard Costing Operational Performance Measures And
Standard Costing Operational Performance Measures Andafiali
 
Lecture_5_-_Standard_Costing_and_variance_analysis.pdf
Lecture_5_-_Standard_Costing_and_variance_analysis.pdfLecture_5_-_Standard_Costing_and_variance_analysis.pdf
Lecture_5_-_Standard_Costing_and_variance_analysis.pdfNeoRamalivhana
 
Acc mgt noreen08 standard costs
Acc mgt noreen08 standard costsAcc mgt noreen08 standard costs
Acc mgt noreen08 standard costsJudianto Nugroho
 
Standard costing
Standard costingStandard costing
Standard costingramla khan
 
Understanding SAP production order variance
Understanding SAP production order varianceUnderstanding SAP production order variance
Understanding SAP production order varianceDhaval Gala
 

Similar to Standard costing and Variance Analysis (20)

Projecto variance
Projecto varianceProjecto variance
Projecto variance
 
Akaun Chapter 11
Akaun Chapter 11Akaun Chapter 11
Akaun Chapter 11
 
Standard Costing
Standard Costing Standard Costing
Standard Costing
 
Standard-Costing-Variance-Analysis.ppt
Standard-Costing-Variance-Analysis.pptStandard-Costing-Variance-Analysis.ppt
Standard-Costing-Variance-Analysis.ppt
 
Amresh management accounting
Amresh management accountingAmresh management accounting
Amresh management accounting
 
management accounting
 management accounting management accounting
management accounting
 
Standard cost, labor & material variance
Standard cost, labor & material varianceStandard cost, labor & material variance
Standard cost, labor & material variance
 
9. Chapter 23, 24 Performance Evaluation.pdf
9. Chapter 23, 24 Performance Evaluation.pdf9. Chapter 23, 24 Performance Evaluation.pdf
9. Chapter 23, 24 Performance Evaluation.pdf
 
Managerial Accounting Project.pptx
Managerial Accounting Project.pptxManagerial Accounting Project.pptx
Managerial Accounting Project.pptx
 
Stdcostingppt
StdcostingpptStdcostingppt
Stdcostingppt
 
Standard costing and variances
Standard costing and variancesStandard costing and variances
Standard costing and variances
 
Management accounting overhead variance
Management accounting   overhead varianceManagement accounting   overhead variance
Management accounting overhead variance
 
Standard Costing Operational Performance Measures And
Standard Costing Operational Performance Measures AndStandard Costing Operational Performance Measures And
Standard Costing Operational Performance Measures And
 
Chapter 10
Chapter 10Chapter 10
Chapter 10
 
Lecture_5_-_Standard_Costing_and_variance_analysis.pdf
Lecture_5_-_Standard_Costing_and_variance_analysis.pdfLecture_5_-_Standard_Costing_and_variance_analysis.pdf
Lecture_5_-_Standard_Costing_and_variance_analysis.pdf
 
Acc mgt noreen08 standard costs
Acc mgt noreen08 standard costsAcc mgt noreen08 standard costs
Acc mgt noreen08 standard costs
 
Labor and material variances
Labor and material variancesLabor and material variances
Labor and material variances
 
3901853 standard-costing
3901853 standard-costing3901853 standard-costing
3901853 standard-costing
 
Standard costing
Standard costingStandard costing
Standard costing
 
Understanding SAP production order variance
Understanding SAP production order varianceUnderstanding SAP production order variance
Understanding SAP production order variance
 

Recently uploaded

“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxEyham Joco
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfUjwalaBharambe
 
CELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxCELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxJiesonDelaCerna
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitolTechU
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...jaredbarbolino94
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxsocialsciencegdgrohi
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceSamikshaHamane
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfMahmoud M. Sallam
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,Virag Sontakke
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerunnathinaik
 

Recently uploaded (20)

“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptx
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
 
CELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxCELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptx
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptx
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
 
ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in Pharmacovigilance
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdf
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developer
 

Standard costing and Variance Analysis

  • 1. STANDARD COSTING ARUN KUMAR M.Com., (Ph.D.) Asst. Professor, Department of Commerce, Govt. First Grade College, Koppa g-mail: arunkumarduna@gmail.com
  • 2. STANDARD The term standard is a predetermined measurable quantity set in defined conditions against which actual performance can be compared. In Simple, we can say the term standard refers to predetermined rate against which performance is judged
  • 3. STANDARD COST Standard-cost is defined by CIMA in the following way:—A predetermined calculation of how much cost should be used under specified working conditions. In other words, this is theoretically the amount of money a company will have to spend to produce a product or perform a service under normal conditions
  • 4. Standard Costing Standard costing is a technique which is used in many industries, where production is of repetitive nature. Standard Costing is the method of measuring the differences between the costs actually incurred in manufacturing and the expected costs under “standard condition”, which always refers to a specific costing rule which serves as the basis.
  • 5. Variance Analysis A variance is the difference between the standards and the actual performance When the actual results are better than the expected results, there will be a favourable variance (F) If the actual results are worse than the expected results, there will be an adverse variance (A)
  • 6. Classification Of Variances Functional Basis Measurement Basis Result Basis
  • 7. Functional Basis Functional Basis Variance related to Cost factor Material Labour Variance related to Sales factor Overhead
  • 8. Measurement Basis Difference between the standard cost and the actual cost in terms of money is known as absolute variance. Difference is expressed as a percentage of the standard cost, it is known as relative variance.
  • 9. Result basis When the actual results are better than the expected results, there will be a favourable variance (F) If the actual results are worse than the expected results, there will be an adverse variance (A)
  • 10. Cost variance • Cost variance = Price variance + Quantity variance Cost variance is the difference between the standard cost and the Actual cost • Price variance = (standard price – actual price)*Actual quantity A price variance reflects the extent of the profit change resulting from the change in activity level • Quantity variance = (standard quantity – actual quantity)* standard cost A quantity variance reflects the extent of the profit change resulting from the change in activity level
  • 11. Three types of cost variance • Material cost variance • Labour cost variance • Variable overheads variance
  • 12. Material Cost variance Material Cost Variances Material Price Variances Material Usage Variances Material Mix Variance Material Yield Variance
  • 13. MATERIAL COST VARIANCE: Material cost variance is the difference between standard cost and actual cost. Mathematically it is written as Formula: MCV = (SQ × SP) – (AQ × AP) Material Cost Variance = Standard quantity × Standard Price-(Actual quantity × Actual Price) Or
  • 14. Material Price Variance: It measures variance arises in the material cost due to difference in actual material purchase price from standard material price. Mathematically it is written as: Material Price Variance: 𝐴𝑐𝑡𝑢𝑎𝑙 𝑞𝑢𝑎𝑛𝑡𝑖𝑡𝑦 ∗ × (𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑝𝑟𝑖𝑐𝑒 − 𝐴𝑐𝑡𝑢𝑎𝑙 𝑝𝑟𝑖𝑐𝑒) MPV = AQ x (SP-AP) Or *Here actual quantity means actual quantity of material purchased. If in the question material purchase is not given, it is taken as equal to material
  • 15. Material Usage Variance: It measures variance in material cost due to usage/ consumption of materials. It is computed as well Material Usage Variance: 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑃𝑟𝑖𝑐𝑒 × (𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑄𝑢𝑎𝑛𝑡𝑖𝑡𝑦 − 𝐴𝑐𝑡𝑢𝑎𝑙 𝑄𝑢𝑎𝑛𝑡𝑖𝑡𝑦) ∗ MUV: SP (SQ − AQ) Or *Here actual quantity means actual quantity of material used
  • 16. Material Mix Variance: Variance in material consumption may arise due to difference in proportion used actually from the standard mix/ proportion. It arises only when two more inputs are used to produce a product. Material Mix Variance = (Revised standard quantity – Actual quantity) × Standard price Or MMV= (RSQ – AQ) × SP Where; RSQ = 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑞𝑢𝑎𝑛𝑡𝑖𝑡𝑦 𝑜𝑓 𝑜𝑛𝑒 𝑚𝑎𝑡𝑒𝑟𝑖𝑎𝑙 𝑻𝒐𝒕𝒂𝒍 𝑜𝑓 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑞𝑢𝑎𝑛𝑡𝑖𝑡𝑦 𝑜𝑓 𝐴𝑙𝑙 𝑚𝑎𝑡𝑒𝑟𝑖𝑎𝑙 × Total of Actual of all material
  • 17. Material Yield Variance (or Material Sub-usage Variance): Variance in material consumption which arise due to yield or productivity of the inputs. It may arise due to use of sub-standard quality of materials, inefficiency of workers or due to wrong processing. Material Revised Usage Variance = (𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑄𝑢𝑎𝑛𝑡𝑖𝑡𝑦 − 𝑅𝑒𝑣𝑖𝑠𝑒𝑑 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑄𝑢𝑎𝑛𝑡𝑖𝑡𝑦) × 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑃𝑟𝑖𝑐𝑒 Or MRUV = (SQ – RSQ) SP Material Yield Variance: (𝐴𝑐𝑡𝑢𝑎𝑙 𝑌𝑖𝑒𝑙𝑑 − 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑌𝑖𝑒𝑙𝑑) × 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝑜𝑢𝑡𝑝𝑢𝑡 𝑝𝑟𝑖𝑐𝑒 Or MYV = (AY – SY) SOP
  • 18. Verification of the Formula: Material Cost Variance = Material Usage Variance + Material Price Variance* Or Material Cost Variance = (Material Mix Variance + Material Revised usage Variance) +Material price variance *If material purchase quantity and material consumed quantity is same
  • 19. The Standard material required to manufacture one unit of product ‘X’ is 10 Kgs, and the standard price per kg of material is ₹ 25 Kgs. The cost account records, however reveals that 11,500 Kgs, Materials costing ₹ 2, 76,000 were used for manufacture of 1,000 units of product ‘X’. Calculate material variances. Illustration 1
  • 20. Calculation of Material Variance  Material cost variances = (𝑆𝑄 × 𝑆𝑃) – (𝐴𝑄 × 𝐴𝑃)  Material Price Variance = 𝐴𝑄 × (𝑆𝑃 − 𝐴𝑃)  Material Usage Variance = 𝑆𝑄 − 𝐴𝑄 × 𝑆𝑃 Given: SQ: For Production of 1 unit Required 10 Kgs of Material There fore for 1000 units = 1000 × 10 = 10,000 Kgs AQ: 11,500 Kgs SP: ₹ 25 AP: ₹ 24 ( 2,76,000/11,500Kgs) The Standard material required to manufacture one unit of product ‘X’ is 10 Kgs, and the standard price per kg of material is ₹ 25 Kgs. The cost account records, however reveals that 11,500 Kgs, Materials costing ₹ 2, 76,000 were used for manufacture of 1,000 units of product ‘X’.
  • 21. = (10,000Kgs× ₹ 25) – (11,500 × ₹24) = 2,50,000 – 2,76,000 = ₹ 26,000(A) = (25 – 24) × 11,500 = 1 × 11,500 = ₹ 11,500 (F) = (10,000 – 11,500) × 25 = (- 1,500) × 25 = ₹ 37,500 (A) SQ: 10,000 Kgs AQ : 11,500 Kgs SP: ₹ 25 AP: ₹ 24 MCV = (SQ × SP) – (AQ × AP) MPV = (SP – AP) × AQ MUV = (SQ – AQ) × SP
  • 22. Darling Company limited works on the standard costing system and produces X. The standard estimates of material for the manufacturer of 1,000 units of product X is 400 Kgs at ₹ 2.5 per kg. In the month of January 2018, manufactured 2,000 units of product X and it is found that 820 Kgs of material is consumed at ₹ 2.60 per kg. Calculate - Material Variance Illustration 2
  • 23. Calculation of Material Variance  Material cost variances = (𝑆𝑄 × 𝑆𝑃) – (𝐴𝑄 × 𝐴𝑃)  Material Price Variance = 𝐴𝑄 × (𝑆𝑃 − 𝐴𝑃)  Material Usage Variance = 𝑆𝑄 − 𝐴𝑄 × 𝑆𝑃 Given: SQ = for 1000 units need 400 kgs = for 2000 units 400 1000 × 2,000 = 800 AQ = 820 kgs for 2000 units SP = ₹ 2.5 AP = ₹ 2.6 The standard estimates of material for the manufacturer of 1,000 units of product X is 400 Kgs at ₹ 2.5 per kg. In the month of January 2018, manufactured 2,000 units of product X and it is found that 820 Kgs of material is consumed at ₹ 2.60 per kg.
  • 24. = (800 × 2.50) – (820 × 2.60) = 2,000 – 2132 = 132 (A) = (2.50 – 2.60) × 820 = ( - 0.10) × 820 = 82 (A) = (800 – 820) × 2.50 = (- 20) – 2.5 = 50 (A) SQ: 800 AQ: 820 SP: ₹ 2.5 AP: ₹ 2.6 MCV = (SQ × SP) – (AQ × AP) MPV = (SP – AP) × AQ MUV = (SQ – AQ) ×SP
  • 26. LABOUR COST VARIANCE Labour cost variance is the difference between standard labour cost allowed for actual output achieved and actual labour cost. It is also known as wages variance. (𝑆𝑡𝑑. ℎ𝑜𝑢𝑟 𝑓𝑜𝑟 𝑎𝑐𝑡𝑢𝑎𝑙 𝑜𝑢𝑡𝑝𝑢𝑡 × 𝑆𝑡𝑑. 𝑟𝑎𝑡𝑒 𝑝𝑒𝑟 ℎ𝑜𝑢𝑟) − (𝐴𝑐𝑡𝑢𝑎𝑙 ℎ𝑜𝑢𝑟𝑠 × 𝐴𝑐𝑡𝑢𝑎𝑙 𝑟𝑎𝑡𝑒 𝑝𝑒𝑟 ℎ𝑜𝑢𝑟) Labour Cost Variance: 𝐿𝑎𝑏𝑜𝑢𝑟 𝐶𝑜𝑠𝑡 Variance = St. Labour Cost for actual output − Actual labour cost or
  • 27. Labour Cost Variance Labour Efficiency Variance Labour Yield VarianceIdle- Time VarianceLabour Mix Variance Labour Rate Variance Classification of Labour Cost Variance
  • 28. Labour Rate (Pay) Variance Labour rate variance arises due to “difference in actual rate paid from standard rate” Labour Rate Variance = (Std. Rate - Actual Rate) × Actual Hours
  • 29. Labour Efficiency (Time) Variance Labour efficiency variance arises due to “deviation in the working hour from the set standard” Labour Efficiency Variance: 𝑆𝑡𝑑. 𝑅𝑎𝑡𝑒 (𝑆𝑡𝑑. ℎ𝑜𝑢𝑟𝑠 𝑓𝑜𝑟 𝑎𝑐𝑡𝑢𝑎𝑙 𝑜𝑢𝑡𝑝𝑢𝑡 − 𝐴𝑐𝑡𝑢𝑎𝑙 𝐻𝑜𝑢𝑟𝑠) ∗ *Actual time worked
  • 30. Idle Time Variance Idle Time Variance is calculated for the unproductive labour hours. Here idle time means labour idle time arises due to abnormal Idle Time Variance:𝐼𝑑𝑒𝑙 ℎ𝑜𝑢𝑟𝑠 × 𝑆𝑡𝑑. 𝑟𝑎𝑡𝑒 (or) ITV = IH × SR
  • 31. Labour Mix Variance - (Gang Composition Variance): Labour Mix variance which arises due to change in the proportion or combination of different skill set i.e. number of skilled workers, semi-skilled workers and un-skilled workers. Labour Mix Variance:(𝑅𝑒𝑣𝑖𝑠𝑒𝑑 𝑆𝑡𝑑. ℎ𝑜𝑢𝑟𝑠 − 𝐴𝑐𝑡𝑢𝑎𝑙 ℎ𝑜𝑢𝑟𝑠) × 𝑆𝑡𝑑. 𝑟𝑎𝑡𝑒 Revised Standard Hours: 𝑅𝑒𝑣𝑖𝑠𝑒𝑑 𝑠𝑡𝑎𝑛𝑑𝑎𝑟𝑑 ℎ𝑜𝑢𝑟𝑠 = 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 ℎ𝑜𝑢𝑟𝑠 𝑜𝑓 𝑡ℎ𝑒 𝑔𝑟𝑎𝑑𝑒 𝑇𝑜𝑡𝑎𝑙 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝐻𝑜𝑢𝑟𝑠 × 𝑇𝑜𝑡𝑎𝑙 𝐴𝑐𝑡𝑢𝑎𝑙 𝐻𝑜𝑢𝑟𝑠
  • 32. Labour Yield Variance Labour Yield variance which arises due to productivity of workers Labour Yield Variance: 𝐴𝑐𝑡𝑢𝑎𝑙 𝑦𝑖𝑒𝑙𝑑 − 𝑆𝑡𝑑. 𝑌𝑖𝑒𝑙𝑑 𝑓𝑜𝑟 𝑎𝑐𝑡𝑢𝑎𝑙 𝑖𝑛𝑝𝑢𝑡 𝑆𝑡𝑑. 𝐿𝑎𝑏𝑜𝑢𝑟 𝑐𝑜𝑠𝑡 𝑝𝑒𝑟 𝑢𝑛𝑖𝑡 𝑜𝑓 𝑜𝑢𝑡𝑝𝑢𝑡 Labour Revised Efficiency Variance: (𝑆𝑡𝑑. ℎ𝑜𝑢𝑟𝑠 𝑓𝑜𝑟 𝑎𝑐𝑡𝑢𝑎𝑙 𝑜𝑢𝑡𝑝𝑢𝑡 − 𝑟𝑒𝑣𝑖𝑠𝑒𝑑 𝑆𝑡𝑑. ℎ𝑜𝑢𝑟𝑠) 𝑆𝑡𝑑. 𝑟𝑎𝑡𝑒 Or
  • 33. Dept. A Actual direct wages ₹ 2,000 Standard hours 8,000 Standard rate per hour ₹ 30 paise Actual hours worked 8,200 From the following, calculate labour variances of department A Given: SH : 8000 SR: ₹ 0.30 AH : 8200 AR: ? AR = 𝐴𝑐𝑡𝑢𝑎𝑙 𝐷𝑖𝑟𝑒𝑐𝑡 𝑊𝑎𝑔𝑒𝑠 𝐴𝑐𝑡𝑢𝑎𝑙 𝐻𝑜𝑢𝑟𝑠 𝑊𝑜𝑟𝑘𝑒𝑑 = ₹ 2000 8200 ℎ𝑜𝑢𝑟𝑠 AR= 0.2439AR: ₹ 0.2439 ILLUSTRATION
  • 34. Calculation of Labour variance = (8,000 Hr × ₹0.30) – (8,200 Hr × ₹0.2439) = ₹ 2400 – ₹ 2,000 = ₹ 400(F) 1. Labour cost variance = (SH × SR) – (AH × AR) 2. Labour rate (pay) variance = (SR – AR) × AH 3. Labour efficiency (time) variance = (SH – AH) × SR LCV = (SH × SR) – (AH × AR) SH : 8000 SR: ₹ 0.30 AH : 8200 AR: ₹ 0.2439
  • 35. = (₹ 0.30 – ₹ 0.2439) × 8200 Hr = ₹ .00561 × 8200 Hr = 460 (F) = (8000 – 8200) × ₹ 0.30 = (-200) × 0.30 = 60 (A) LPV = (SR – AR) × AH LEV = (SH – AH) × SR Labour Cost Variance 400 (F) Labour Efficiency (Time) Variance 60 (A)Labour Rate Variance 460 (F)
  • 36. The information regarding composition and the weekly wages rates of labour force engaged on a job scheduled to be completed in 60 weeks are as follows: Types of labour Standard Actual No. of workers Weekly wage rate per hour No. of workers Weekly wage rate per hour Skilled 75 60 70 70 Semi-skilled 45 40 30 50 Unskilled 60 30 80 20 The work completed in 62 weeks. Calculate: (a) Labour cost variance (b) Labour rate variance (c) Labor efficiency variance (d) Labour mix variance ILLUSTRATION
  • 37. Workers Standard Mix Hours (No. of Workers × 60 Weeks) Rate Per Hour Cost Skilled 75 × 60 = 4,500 60 2,70,000 Semi-Skilled 45 × 60 = 2,700 40 1,08,000 Unskilled 60 × 60 = 3,600 30 1,08,000 Total 10,800 4,86,000 Calculation of Labour Variance: Workers Actual Mix Hours (No. of Workers × 62 Weeks) Rate Per Hour Cost Skilled 70 × 62 = 4,340 70 3,03,800 Semi-Skilled 30 × 62 = 1,860 50 93,000 Unskilled 80 × 62 = 4,960 20 99,200 Total 11,160 4,96,000
  • 38. Labour Cost Variance LCV = SC - AC = ₹ Skilled = 2,70,000 - 3,03,000 = 33,800(A) Semi- Skilled = 1,08,000 - 93,000 = 15,000 (F) Unskilled = 1,08,000 - 99,200 = 8,800 (F) = 10,000(A) Labour Rate (Pay) Variance: LRV = (SR – AR) × AH = ₹ Skilled = (60 – 70) × 4,340 = 43,400(A) Semi- Skilled = (40 – 50) × 1,860 = 18,600 (A) Unskilled = (30 – 20) × 4,960 = 49,600 (F) =12,400 (A)
  • 39. Labour Efficiency Variance: LEV = (SH – AH) × SR = ₹ Skilled = (4,500 – 4,340) × 60 = 9,600 (F) Semi- Skilled = (2,700 – 1,860) × 40 = 33,600 (F) Unskilled = (3,600 – 4,960) × 30 = 40,800 (A) = 2,400 (F) Labour Mix Variance = ( 𝐑𝐒𝐓 − 𝐀𝐓) × 𝑺𝑹
  • 40. Revised Standard Hours: 𝑅𝑒𝑣𝑖𝑠𝑒𝑑 𝑠𝑡𝑎𝑛𝑑𝑎𝑟𝑑 ℎ𝑜𝑢𝑟𝑠 = 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 ℎ𝑜𝑢𝑟𝑠 𝑜𝑓 𝑡ℎ𝑒 𝑔𝑟𝑎𝑑𝑒 𝑇𝑜𝑡𝑎𝑙 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 𝐻𝑜𝑢𝑟𝑠 × 𝑇𝑜𝑡𝑎𝑙 𝐴𝑐𝑡𝑢𝑎𝑙 𝐻𝑜𝑢𝑟𝑠 Unskilled = 3,600 10,800 × 11,160 = 3,720 Skilled = 4,500 10,800 × 11,160 = 4,650 Semi skilled = 2,700 10,800 × 11,160 = 2,790 Workers Standard Mix Actual Mix Hours (No. of Workers × 60 Weeks) Hours (No. of Workers × 62 Weeks) Skilled 4,500 4,340 Semi-Skilled 2,700 1,860 Skilled 3,600 4,960 Total 10,800 11,160
  • 41. Labour Mix Variance = ( 𝐑𝐒𝐓 − 𝐀𝐓) × 𝑺𝑹 LMV = (RST – AT) × SR = ₹ Skilled = (4,650 – 4,340) × 60 = 18,600 (F) Semi- Skilled = (2,790 – 1,860) × 40 = 37,200 (F) Unskilled = (3,720 – 4,960) × 30 = 37,200 (A) LCV Rs. 10,000 (A) LRV Rs. 12,400(A) LEV 2,400 (F)