This document provides a summary of valuation of work advances for a construction project in January 2022. It shows the planned, valued, and remaining amounts for various line items of direct costs, general expenses, supervision expenses, and liquidation expenses. The total direct costs planned were $102,821.30, of which $9,477.41 (9.22%) was valued, leaving $93,343.89 (90.78%) remaining. General expenses of $36,650 and supervision expenses of $9,200 were fully planned but not yet valued.
Resumen de valorizaciones de avance de obra del mes de enero del 2022
1. 1
UND METRADO P.U. TOTALES METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO %
01 TRABAJOS PRELIMINARES
01.01 TRAZO Y REPLANTEO GENERAL m2 3,047.31 1.44 4,388.13 0.00 0.00 0.00% 2387.00 3437.28 78.33% 2387.00 3437.28 78.33% 660.31 950.85 21.67%
01.02 LIMPIEZA GENERAL m2 3,047.31 1.59 4,845.22 0.00 0.00 0.00% 2387.00 3795.33 78.33% 2387.00 3795.33 78.33% 660.31 1,049.89 21.67%
01.03 CARTEL DE IDENTIFICACION DE OBRA 3.60 x 2.40m und 1.00 646.98 646.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 646.98 100.00%
01.05 ALMACEN DE OBRA m2 40.00 56.12 2,244.80 0.00 0.00 0.00% 40.00 2244.80 100.00% 40.00 2244.80 100.00% 0.00 0.00 0.00%
02 EQUIPOS DE SEGURIDAD
02.01 EQUIPOS DE PROTECCION glb 1.00 4,027.00 4,027.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,027.00 100.00%
03 OBRAS SANITARIAS
03.01 SISTEMA DE DESAGUE Y ALCANTARILLADO
03.01.01 SUMINISTRO E INSTALACION DE RED MATRIZ DE ALCANTARILLADO D=200 mm
03.01.01.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO m2 269.67 1.40 377.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 269.67 377.54 100.00%
03.01.01.02 EXCAVACION DE ZANJA C/MAQ. TERRENO NORMAL H=1.20 M. P/TUB. m3 295.54 17.89 5,287.21 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 295.54 5,287.21 100.00%
03.01.01.03 REFINE, NIVELACION Y CONFORMACION DE FONDOS m 337.07 2.29 771.89 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 337.07 771.89 100.00%
03.01.01.04 CAMA DE APOYO P/TUBERIA m 337.07 5.57 1,877.48 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 337.07 1,877.48 100.00%
03.01.01.05 TENDIDO, COLOCACION Y PRUEBA DE TUB PVC SAL 200 MM S-25 UF m 337.07 83.65 28,195.91 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 337.07 28,195.91 100.00%
03.01.01.06 RELLENO COMPACTADO DE ZANJAS CON ARENA m3 26.97 82.62 2,228.26 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 26.97 2,228.26 100.00%
03.01.01.07 RELLENO COMPACTADO DE ZANJAS CON MATERIAL PROPIO m3 268.55 17.62 4,731.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 268.55 4,731.85 100.00%
03.01.01.08 ELIMINACION MATERIAL EXCEDENTE m3 29.58 43.09 1,274.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 29.58 1,274.60 100.00%
03.01.01.09 PRUEBA HIDRAULICA m 337.07 3.00 1,011.21 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 337.07 1,011.21 100.00%
03.01.02 SUMINISTROS E INSTALACIONES DOMICILIARIAS DE DESAGUE
03.01.02.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO m2 69.44 1.40 97.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 69.44 97.22 100.00%
03.01.02.02 EXCAVACION DE ZANJAS HASTA H=1.20M m3 79.93 22.24 1,777.64 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 79.93 1,777.64 100.00%
03.01.02.03 REFINE, NIVELACION Y CONFORMACION DE FONDOS m 145.92 1.95 284.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 145.92 284.54 100.00%
03.01.02.04 CAMA DE APOYO P/TUBERIA m 138.88 5.57 773.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 138.88 773.56 100.00%
03.01.02.05 TENDIDO, COLOCACION Y PRUEBA DE TUB PVC SAL 160 MM UF m 138.88 63.65 8,839.71 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 138.88 8,839.71 100.00%
03.01.02.06 EMPALME DE TUBERIA PVC 160MM A RED MATRIZ DE DESAGUE PVC 200 MM und 20.00 321.88 6,437.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.00 6,437.60 100.00%
03.01.02.07 RELLENO COMPACTADO DE ZANJAS CON ARENA m3 6.94 82.62 573.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.94 573.38 100.00%
03.01.02.08 RELLENO COMPACTADO DE ZANJAS CON MATERIAL PROPIO m3 72.99 17.62 1,286.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 72.99 1,286.08 100.00%
03.01.02.09 ELIMINACION MATERIAL EXCEDENTE m3 7.99 43.09 344.29 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.99 344.29 100.00%
03.01.02.10 PRUEBA HIDRAULICA m 138.88 3.00 416.64 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 138.88 416.64 100.00%
03.01.03 CONSTRUCCION DE BUZONES DE ALCANTARILLADO
03.01.03.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO m2 10.18 1.40 14.25 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.18 14.25 99.99%
03.01.03.02 EXCAVACION DE ZANJAS HASTA H=1.20M m3 13.06 22.24 290.45 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 13.06 290.45 100.00%
03.01.03.03 REFINE, NIVELACION Y CONFORMACION DE FONDOS m 10.18 2.29 23.31 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.18 23.31 99.99%
03.01.03.04 ELIMINACION MATERIAL EXCEDENTE m3 16.98 43.09 731.67 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.98 731.67 100.00%
03.01.03.05 CONCRETO f'c=175 kg/cm2 PARA FONDOS Y MUROS m3 9.92 370.71 3,677.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.92 3,677.44 100.00%
03.01.03.06 CONCRETO f'c=210 kg/cm2 PARA LOSA m3 2.54 401.89 1,020.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.54 1,020.80 100.00%
03.01.03.07 ENCOFRADO Y DESENCOFRADO DE BUZON m2 53.72 42.67 2,292.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 53.72 2,292.23 100.00%
03.01.03.08 ACERO DE REFUERZO F'Y= 4200 KG/CM2 kg 834.46 4.42 3,688.31 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 834.46 3,688.31 100.00%
03.01.03.09 SUMINISTRO Y COLOCACION DE TAPAS DE CONCRETO P/BUZONES und 9.00 139.09 1,251.81 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.00 1,251.81 100.00%
03.01.03.10 CURADO DE CONCRETO m2 47.50 0.38 18.05 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 47.50 18.05 100.00%
03.01.03.11 OTROS IMPLEMENTOS glb 1.00 574.24 574.24 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 574.24 100.00%
04 PLAN COVID 19
04.01 PLAN COVID glb 1.00 6,500.00 6,500.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 6,500.00 100.00%
CD 102,821.33 9477.41 9.22% 93343.89 90.78%
COSTO DIRECTO
PROGRAMADO ANTERIOR ACTUAL
RESUMEN DE VALORIZACIONES DE AVANCE DE OBRA DEL MES DE ENERO DEL 2022
“Año del fortalecimiento de la soberania nacional”
SALDOS
ITEM DESCRIPCION
MUNICIPALIDAD DISTRITAL DE SAYLLA
ACUMULADO
SUB GERENCIA DE INFRAESTRUCTURA
2. MONTO DE OBRA CUSCO
FECHA DE INICIO DE OBRA 25/01/2022 DEPARTAMENTO CUSCO
PLAZO DE EJECUCIÓN TOTAL 60 CUSCO
FECHA DE TERMINO
REPROGRAMADO 26/03/2022 SAYLLA
APV JUAN VELAZCO
ANTERIOR
S/. Valorizado
S/.
% Valorizado
S/.
% Valorizado
S/.
% Valorizado
S/.
%
1 PROGRAMADO (CD) 102,821.30 - 0.00% 9,477.41 9.22% 9,477.41 9.22% 93,343.89 90.78%
2 MAYORES METRADOS - 0.00% - -
3 PARTIDAS NUEVAS - - - -
4 DEDUCTIVOS - 0.00% - -
COSTO DIRECTO 102,821.30 - 0.00% 9,477.41 9.22% 9,477.41 9.22% 93,343.89 90.78%
GASTOS GENERALES (35.64 %) 36,650.00 - 0.00% - 0.00% - 0.00% 36,650.00 100.00%
GASTOS DE SUPERVISION (8.95 %) 9,200.00 - - - 0.00% - 0.00% 9,200.00 100.00%
GASTOS DE LIQUIDACION (3.89 %) 4,000.00 0.00% - 0.00% - 0.00% 4,000.00 100.00%
EXPEDIENTE TECNICO (0%) 0.00 0.00% - 0.00% - 0.00% -
PRESUPUESTO TOTAL 152,671.31 0.00% 9,477.41 9.22% 9,477.41 9.22% 143,193.90 6.21%
DISTRITO
LOCALIDAD
PROVINCIA
MUNICIPALIDAD DISTRITAL DE SAYLLA
SUB GERENCIA DE INFRAESTRUCTURA
“Año del fortalecimiento de la soberania nacional”
RESUMEN DE VALORIZACIONES DE AVANCE DE OBRA DEL MES DE ENERO DEL 2022
OBRA:
“Construcción de Red de Alcantarillado y conexión domiciliaria de alcantarillado en la APV Juan Velazco Alvarado distrito de Saylla, Provincia de Cusco,
Departamento del Cusco.”
REGION
ITEM VALORIZACION
PRESUPUESTO
AVANCES
SALDO
ACTUAL ACUMULADO
1 de 1
3. OBRA:
PARTIDA DESCRIPCION MEDIDA METRADO
01 TRABAJOS PRELIMINARES
01.01 TRAZO Y REPLANTEO GENERAL m2 2,387.00
01.02 LIMPIEZA GENERAL m2 2,387.00
01.05 ALMACEN DE OBRA m2 40.00
RESUMEN DE METRADO DEL MES DE ENERO 2022
SUB GERENCIA DE INFRAESTRUCTURA
MUNICIPALIDAD DISTRITAL DE SAYLLA
“Construcción de Red de Alcantarillado y conexión domiciliaria de alcantarillado en la APV Juan Velazco Alvarado
distrito de Saylla, Provincia de Cusco, Departamento del Cusco.”
RESUMEN DE VALORIZACIONES DE AVANCE DE OBRA DEL MES DE ENERO DEL 2022
“Año del fortalecimiento de la soberania nacional”
4. OBRA:
PRESUPUESTO TOTAL DEL PROYECTO S/.152,671.31 REGION CUSCO
PRESUPUESTO COSTO DIRECTO S/.102,821.30 DEPARTAMENTO CUSCO
PRESUPUESTO ASIGNADO PIM 2022 S/.152,671.31 PROVINCIA CUSCO
FECHA DE INICIO DE OBRA 25/01/2022 DISTRITO SAYLLA
FECHA FIN 25/03/2022 LOCALIDAD C.C.ANAHUARQUE
ANTERIOR
S/. Valorizado
S/.
% Valorizado
S/.
% Valorizado
S/.
% Valorizado
S/.
%
1 RED DE ALCANTARILLADO 100,315.64 - 0.00% 9,477.41 9.45% 9,477.41 9.45% 90,838.23 90.55%
2 CONEXIÓN DOMICILIARIA DE ALCANTARILLADO 39,155.66 - 0.00% - 0.00% - 0.00% 39,155.66 100.00%
COSTO DIRECTO 139,471.29 - 0.00% 9,477.41 6.80% 9,477.40 6.80% 129,993.89 93.20%
NOTA: LA VALORIZACION ES A COSTO DIRECTO
ANTERIOR
S/. Valorizado
S/.
% Valorizado
S/.
% Valorizado
S/.
% Valorizado
S/.
%
0.00 - #¡DIV/0! - #¡DIV/0! - #¡DIV/0! - #¡DIV/0!
9,200.00 - 0.00% - 0.00% - 0.00% 9,200.00 100.00%
4,000.00 - 0.00% - 0.00% - 0.00% 4,000.00 100.00%
0.00 - 0.00% - 0.00% - 0.00% - 0.00%
152,671.30 - 0.00% - 0.00% - 0.00% 152,671.30 100.00%
NOTA: LA VALORIZACION DE GASTOS GENERALES ES A NIVEL DE DEVENGANDO
GASTOS GENERALES - GG
GASTOS DE SUPERVISION - GS
GASTOS DE LIQUIDACION - GL
GASTOS POR EXP. TEC. - GET
PRESUPUESTO TOTAL
ITEM DESCRIPCION
PRESUPUESTO
VALORIZACION DE AVANCE FINACIERO "ENERO - 2022"
ACTUAL ACUMULADO SALDO
ITEM DESCRIPCION
PRESUPUESTO
VALORIZACION DE AVANCE FISICO REAL (CD) "ENERO 2022"
ACTUAL ACUMULADO SALDO
MUNICIPALIDAD DISTRITAL DE SAYLLA
SUB GERENCIA DE INFRAESTRUCTURA
“Año del fortalecimiento de la soberania nacional”
RESUMEN VALORIZACION FISICO Y FINANCIERO
VALORIZACION DE AVANCE DE OBRA N° 01 - MES ENERO POR COMPONENTE
CONSTRUCCION DEL CERCO PERIMETRICO Y TRIBUNA Y/O PALCO EN ESTADIO MUNICIPAL DISTRITO DE SAYLLA, PROVINCIA CUSCO, DEPARTAMENTO CUSCO