SlideShare a Scribd company logo
1 of 4
Download to read offline
1
UND METRADO P.U. TOTALES METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO %
01 TRABAJOS PRELIMINARES
01.01 TRAZO Y REPLANTEO GENERAL m2 3,047.31 1.44 4,388.13 0.00 0.00 0.00% 2387.00 3437.28 78.33% 2387.00 3437.28 78.33% 660.31 950.85 21.67%
01.02 LIMPIEZA GENERAL m2 3,047.31 1.59 4,845.22 0.00 0.00 0.00% 2387.00 3795.33 78.33% 2387.00 3795.33 78.33% 660.31 1,049.89 21.67%
01.03 CARTEL DE IDENTIFICACION DE OBRA 3.60 x 2.40m und 1.00 646.98 646.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 646.98 100.00%
01.05 ALMACEN DE OBRA m2 40.00 56.12 2,244.80 0.00 0.00 0.00% 40.00 2244.80 100.00% 40.00 2244.80 100.00% 0.00 0.00 0.00%
02 EQUIPOS DE SEGURIDAD
02.01 EQUIPOS DE PROTECCION glb 1.00 4,027.00 4,027.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,027.00 100.00%
03 OBRAS SANITARIAS
03.01 SISTEMA DE DESAGUE Y ALCANTARILLADO
03.01.01 SUMINISTRO E INSTALACION DE RED MATRIZ DE ALCANTARILLADO D=200 mm
03.01.01.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO m2 269.67 1.40 377.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 269.67 377.54 100.00%
03.01.01.02 EXCAVACION DE ZANJA C/MAQ. TERRENO NORMAL H=1.20 M. P/TUB. m3 295.54 17.89 5,287.21 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 295.54 5,287.21 100.00%
03.01.01.03 REFINE, NIVELACION Y CONFORMACION DE FONDOS m 337.07 2.29 771.89 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 337.07 771.89 100.00%
03.01.01.04 CAMA DE APOYO P/TUBERIA m 337.07 5.57 1,877.48 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 337.07 1,877.48 100.00%
03.01.01.05 TENDIDO, COLOCACION Y PRUEBA DE TUB PVC SAL 200 MM S-25 UF m 337.07 83.65 28,195.91 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 337.07 28,195.91 100.00%
03.01.01.06 RELLENO COMPACTADO DE ZANJAS CON ARENA m3 26.97 82.62 2,228.26 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 26.97 2,228.26 100.00%
03.01.01.07 RELLENO COMPACTADO DE ZANJAS CON MATERIAL PROPIO m3 268.55 17.62 4,731.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 268.55 4,731.85 100.00%
03.01.01.08 ELIMINACION MATERIAL EXCEDENTE m3 29.58 43.09 1,274.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 29.58 1,274.60 100.00%
03.01.01.09 PRUEBA HIDRAULICA m 337.07 3.00 1,011.21 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 337.07 1,011.21 100.00%
03.01.02 SUMINISTROS E INSTALACIONES DOMICILIARIAS DE DESAGUE
03.01.02.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO m2 69.44 1.40 97.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 69.44 97.22 100.00%
03.01.02.02 EXCAVACION DE ZANJAS HASTA H=1.20M m3 79.93 22.24 1,777.64 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 79.93 1,777.64 100.00%
03.01.02.03 REFINE, NIVELACION Y CONFORMACION DE FONDOS m 145.92 1.95 284.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 145.92 284.54 100.00%
03.01.02.04 CAMA DE APOYO P/TUBERIA m 138.88 5.57 773.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 138.88 773.56 100.00%
03.01.02.05 TENDIDO, COLOCACION Y PRUEBA DE TUB PVC SAL 160 MM UF m 138.88 63.65 8,839.71 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 138.88 8,839.71 100.00%
03.01.02.06 EMPALME DE TUBERIA PVC 160MM A RED MATRIZ DE DESAGUE PVC 200 MM und 20.00 321.88 6,437.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.00 6,437.60 100.00%
03.01.02.07 RELLENO COMPACTADO DE ZANJAS CON ARENA m3 6.94 82.62 573.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.94 573.38 100.00%
03.01.02.08 RELLENO COMPACTADO DE ZANJAS CON MATERIAL PROPIO m3 72.99 17.62 1,286.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 72.99 1,286.08 100.00%
03.01.02.09 ELIMINACION MATERIAL EXCEDENTE m3 7.99 43.09 344.29 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.99 344.29 100.00%
03.01.02.10 PRUEBA HIDRAULICA m 138.88 3.00 416.64 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 138.88 416.64 100.00%
03.01.03 CONSTRUCCION DE BUZONES DE ALCANTARILLADO
03.01.03.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO m2 10.18 1.40 14.25 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.18 14.25 99.99%
03.01.03.02 EXCAVACION DE ZANJAS HASTA H=1.20M m3 13.06 22.24 290.45 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 13.06 290.45 100.00%
03.01.03.03 REFINE, NIVELACION Y CONFORMACION DE FONDOS m 10.18 2.29 23.31 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.18 23.31 99.99%
03.01.03.04 ELIMINACION MATERIAL EXCEDENTE m3 16.98 43.09 731.67 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.98 731.67 100.00%
03.01.03.05 CONCRETO f'c=175 kg/cm2 PARA FONDOS Y MUROS m3 9.92 370.71 3,677.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.92 3,677.44 100.00%
03.01.03.06 CONCRETO f'c=210 kg/cm2 PARA LOSA m3 2.54 401.89 1,020.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.54 1,020.80 100.00%
03.01.03.07 ENCOFRADO Y DESENCOFRADO DE BUZON m2 53.72 42.67 2,292.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 53.72 2,292.23 100.00%
03.01.03.08 ACERO DE REFUERZO F'Y= 4200 KG/CM2 kg 834.46 4.42 3,688.31 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 834.46 3,688.31 100.00%
03.01.03.09 SUMINISTRO Y COLOCACION DE TAPAS DE CONCRETO P/BUZONES und 9.00 139.09 1,251.81 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.00 1,251.81 100.00%
03.01.03.10 CURADO DE CONCRETO m2 47.50 0.38 18.05 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 47.50 18.05 100.00%
03.01.03.11 OTROS IMPLEMENTOS glb 1.00 574.24 574.24 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 574.24 100.00%
04 PLAN COVID 19
04.01 PLAN COVID glb 1.00 6,500.00 6,500.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 6,500.00 100.00%
CD 102,821.33 9477.41 9.22% 93343.89 90.78%
COSTO DIRECTO
PROGRAMADO ANTERIOR ACTUAL
RESUMEN DE VALORIZACIONES DE AVANCE DE OBRA DEL MES DE ENERO DEL 2022
“Año del fortalecimiento de la soberania nacional”
SALDOS
ITEM DESCRIPCION
MUNICIPALIDAD DISTRITAL DE SAYLLA
ACUMULADO
SUB GERENCIA DE INFRAESTRUCTURA
MONTO DE OBRA CUSCO
FECHA DE INICIO DE OBRA 25/01/2022 DEPARTAMENTO CUSCO
PLAZO DE EJECUCIÓN TOTAL 60 CUSCO
FECHA DE TERMINO
REPROGRAMADO 26/03/2022 SAYLLA
APV JUAN VELAZCO
ANTERIOR
S/. Valorizado
S/.
% Valorizado
S/.
% Valorizado
S/.
% Valorizado
S/.
%
1 PROGRAMADO (CD) 102,821.30 - 0.00% 9,477.41 9.22% 9,477.41 9.22% 93,343.89 90.78%
2 MAYORES METRADOS - 0.00% - -
3 PARTIDAS NUEVAS - - - -
4 DEDUCTIVOS - 0.00% - -
COSTO DIRECTO 102,821.30 - 0.00% 9,477.41 9.22% 9,477.41 9.22% 93,343.89 90.78%
GASTOS GENERALES (35.64 %) 36,650.00 - 0.00% - 0.00% - 0.00% 36,650.00 100.00%
GASTOS DE SUPERVISION (8.95 %) 9,200.00 - - - 0.00% - 0.00% 9,200.00 100.00%
GASTOS DE LIQUIDACION (3.89 %) 4,000.00 0.00% - 0.00% - 0.00% 4,000.00 100.00%
EXPEDIENTE TECNICO (0%) 0.00 0.00% - 0.00% - 0.00% -
PRESUPUESTO TOTAL 152,671.31 0.00% 9,477.41 9.22% 9,477.41 9.22% 143,193.90 6.21%
DISTRITO
LOCALIDAD
PROVINCIA
MUNICIPALIDAD DISTRITAL DE SAYLLA
SUB GERENCIA DE INFRAESTRUCTURA
“Año del fortalecimiento de la soberania nacional”
RESUMEN DE VALORIZACIONES DE AVANCE DE OBRA DEL MES DE ENERO DEL 2022
OBRA:
“Construcción de Red de Alcantarillado y conexión domiciliaria de alcantarillado en la APV Juan Velazco Alvarado distrito de Saylla, Provincia de Cusco,
Departamento del Cusco.”
REGION
ITEM VALORIZACION
PRESUPUESTO
AVANCES
SALDO
ACTUAL ACUMULADO
1 de 1
OBRA:
PARTIDA DESCRIPCION MEDIDA METRADO
01 TRABAJOS PRELIMINARES
01.01 TRAZO Y REPLANTEO GENERAL m2 2,387.00
01.02 LIMPIEZA GENERAL m2 2,387.00
01.05 ALMACEN DE OBRA m2 40.00
RESUMEN DE METRADO DEL MES DE ENERO 2022
SUB GERENCIA DE INFRAESTRUCTURA
MUNICIPALIDAD DISTRITAL DE SAYLLA
“Construcción de Red de Alcantarillado y conexión domiciliaria de alcantarillado en la APV Juan Velazco Alvarado
distrito de Saylla, Provincia de Cusco, Departamento del Cusco.”
RESUMEN DE VALORIZACIONES DE AVANCE DE OBRA DEL MES DE ENERO DEL 2022
“Año del fortalecimiento de la soberania nacional”
OBRA:
PRESUPUESTO TOTAL DEL PROYECTO S/.152,671.31 REGION CUSCO
PRESUPUESTO COSTO DIRECTO S/.102,821.30 DEPARTAMENTO CUSCO
PRESUPUESTO ASIGNADO PIM 2022 S/.152,671.31 PROVINCIA CUSCO
FECHA DE INICIO DE OBRA 25/01/2022 DISTRITO SAYLLA
FECHA FIN 25/03/2022 LOCALIDAD C.C.ANAHUARQUE
ANTERIOR
S/. Valorizado
S/.
% Valorizado
S/.
% Valorizado
S/.
% Valorizado
S/.
%
1 RED DE ALCANTARILLADO 100,315.64 - 0.00% 9,477.41 9.45% 9,477.41 9.45% 90,838.23 90.55%
2 CONEXIÓN DOMICILIARIA DE ALCANTARILLADO 39,155.66 - 0.00% - 0.00% - 0.00% 39,155.66 100.00%
COSTO DIRECTO 139,471.29 - 0.00% 9,477.41 6.80% 9,477.40 6.80% 129,993.89 93.20%
NOTA: LA VALORIZACION ES A COSTO DIRECTO
ANTERIOR
S/. Valorizado
S/.
% Valorizado
S/.
% Valorizado
S/.
% Valorizado
S/.
%
0.00 - #¡DIV/0! - #¡DIV/0! - #¡DIV/0! - #¡DIV/0!
9,200.00 - 0.00% - 0.00% - 0.00% 9,200.00 100.00%
4,000.00 - 0.00% - 0.00% - 0.00% 4,000.00 100.00%
0.00 - 0.00% - 0.00% - 0.00% - 0.00%
152,671.30 - 0.00% - 0.00% - 0.00% 152,671.30 100.00%
NOTA: LA VALORIZACION DE GASTOS GENERALES ES A NIVEL DE DEVENGANDO
GASTOS GENERALES - GG
GASTOS DE SUPERVISION - GS
GASTOS DE LIQUIDACION - GL
GASTOS POR EXP. TEC. - GET
PRESUPUESTO TOTAL
ITEM DESCRIPCION
PRESUPUESTO
VALORIZACION DE AVANCE FINACIERO "ENERO - 2022"
ACTUAL ACUMULADO SALDO
ITEM DESCRIPCION
PRESUPUESTO
VALORIZACION DE AVANCE FISICO REAL (CD) "ENERO 2022"
ACTUAL ACUMULADO SALDO
MUNICIPALIDAD DISTRITAL DE SAYLLA
SUB GERENCIA DE INFRAESTRUCTURA
“Año del fortalecimiento de la soberania nacional”
RESUMEN VALORIZACION FISICO Y FINANCIERO
VALORIZACION DE AVANCE DE OBRA N° 01 - MES ENERO POR COMPONENTE
CONSTRUCCION DEL CERCO PERIMETRICO Y TRIBUNA Y/O PALCO EN ESTADIO MUNICIPAL DISTRITO DE SAYLLA, PROVINCIA CUSCO, DEPARTAMENTO CUSCO

More Related Content

Similar to Resumen de valorizaciones de avance de obra del mes de enero del 2022

Operation - OR for JAN 23.pptx
Operation - OR for JAN 23.pptxOperation - OR for JAN 23.pptx
Operation - OR for JAN 23.pptxPowerMurugan
 
Tarea 2 hidraulica iii-cabrera arias roberto alejandro
Tarea 2 hidraulica iii-cabrera arias roberto alejandroTarea 2 hidraulica iii-cabrera arias roberto alejandro
Tarea 2 hidraulica iii-cabrera arias roberto alejandroAlejandro Cabrera
 
ANEXO 4 CUADRO MULTIANUAL DE NECESIDADES DRAT
ANEXO 4 CUADRO MULTIANUAL DE NECESIDADES DRATANEXO 4 CUADRO MULTIANUAL DE NECESIDADES DRAT
ANEXO 4 CUADRO MULTIANUAL DE NECESIDADES DRATalexanderlaragarces
 
Boiler ea case study 16 jan 2012 varanasi
Boiler ea case study  16 jan 2012 varanasiBoiler ea case study  16 jan 2012 varanasi
Boiler ea case study 16 jan 2012 varanasiD.Pawan Kumar
 
Laterite Concrete
Laterite ConcreteLaterite Concrete
Laterite ConcreteNikilq Cb
 
Study on baltim field,b.sc graduation project 2015, by atam team
Study on baltim field,b.sc graduation project 2015, by atam teamStudy on baltim field,b.sc graduation project 2015, by atam team
Study on baltim field,b.sc graduation project 2015, by atam teamPE Mahmoud Jad
 
Lista de precios (1)
Lista de precios (1)Lista de precios (1)
Lista de precios (1)Hugo Yucra
 
PackageOutline.pdf
PackageOutline.pdfPackageOutline.pdf
PackageOutline.pdfAhmedAydn2
 
Cálculo hidráulicor
Cálculo hidráulicorCálculo hidráulicor
Cálculo hidráulicorjorge
 
Report sending mails to dealers for Accepted and
Report  sending  mails to dealers for Accepted andReport  sending  mails to dealers for Accepted and
Report sending mails to dealers for Accepted andsusanta subudhi
 

Similar to Resumen de valorizaciones de avance de obra del mes de enero del 2022 (19)

P33_Nal_Comercial.pdf
P33_Nal_Comercial.pdfP33_Nal_Comercial.pdf
P33_Nal_Comercial.pdf
 
WEIGHTING TABLE
WEIGHTING TABLEWEIGHTING TABLE
WEIGHTING TABLE
 
Operation - OR for JAN 23.pptx
Operation - OR for JAN 23.pptxOperation - OR for JAN 23.pptx
Operation - OR for JAN 23.pptx
 
P33_Total_Nal.pdf
P33_Total_Nal.pdfP33_Total_Nal.pdf
P33_Total_Nal.pdf
 
Tarea 2 hidraulica iii-cabrera arias roberto alejandro
Tarea 2 hidraulica iii-cabrera arias roberto alejandroTarea 2 hidraulica iii-cabrera arias roberto alejandro
Tarea 2 hidraulica iii-cabrera arias roberto alejandro
 
009 planta de tratamiento de agua potable (ptap)
009 planta de tratamiento de agua potable (ptap)009 planta de tratamiento de agua potable (ptap)
009 planta de tratamiento de agua potable (ptap)
 
ANEXO 4 CUADRO MULTIANUAL DE NECESIDADES DRAT
ANEXO 4 CUADRO MULTIANUAL DE NECESIDADES DRATANEXO 4 CUADRO MULTIANUAL DE NECESIDADES DRAT
ANEXO 4 CUADRO MULTIANUAL DE NECESIDADES DRAT
 
Boiler ea case study 16 jan 2012 varanasi
Boiler ea case study  16 jan 2012 varanasiBoiler ea case study  16 jan 2012 varanasi
Boiler ea case study 16 jan 2012 varanasi
 
Rab
RabRab
Rab
 
Laterite Concrete
Laterite ConcreteLaterite Concrete
Laterite Concrete
 
Prov ca
Prov caProv ca
Prov ca
 
Study on baltim field,b.sc graduation project 2015, by atam team
Study on baltim field,b.sc graduation project 2015, by atam teamStudy on baltim field,b.sc graduation project 2015, by atam team
Study on baltim field,b.sc graduation project 2015, by atam team
 
LBA-1.pdf
LBA-1.pdfLBA-1.pdf
LBA-1.pdf
 
Lista de precios (1)
Lista de precios (1)Lista de precios (1)
Lista de precios (1)
 
Capitulo 02 grupo 01
Capitulo 02 grupo 01Capitulo 02 grupo 01
Capitulo 02 grupo 01
 
Pass Thru Pay
Pass Thru PayPass Thru Pay
Pass Thru Pay
 
PackageOutline.pdf
PackageOutline.pdfPackageOutline.pdf
PackageOutline.pdf
 
Cálculo hidráulicor
Cálculo hidráulicorCálculo hidráulicor
Cálculo hidráulicor
 
Report sending mails to dealers for Accepted and
Report  sending  mails to dealers for Accepted andReport  sending  mails to dealers for Accepted and
Report sending mails to dealers for Accepted and
 

Recently uploaded

DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 

Recently uploaded (20)

Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 

Resumen de valorizaciones de avance de obra del mes de enero del 2022

  • 1. 1 UND METRADO P.U. TOTALES METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % 01 TRABAJOS PRELIMINARES 01.01 TRAZO Y REPLANTEO GENERAL m2 3,047.31 1.44 4,388.13 0.00 0.00 0.00% 2387.00 3437.28 78.33% 2387.00 3437.28 78.33% 660.31 950.85 21.67% 01.02 LIMPIEZA GENERAL m2 3,047.31 1.59 4,845.22 0.00 0.00 0.00% 2387.00 3795.33 78.33% 2387.00 3795.33 78.33% 660.31 1,049.89 21.67% 01.03 CARTEL DE IDENTIFICACION DE OBRA 3.60 x 2.40m und 1.00 646.98 646.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 646.98 100.00% 01.05 ALMACEN DE OBRA m2 40.00 56.12 2,244.80 0.00 0.00 0.00% 40.00 2244.80 100.00% 40.00 2244.80 100.00% 0.00 0.00 0.00% 02 EQUIPOS DE SEGURIDAD 02.01 EQUIPOS DE PROTECCION glb 1.00 4,027.00 4,027.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 4,027.00 100.00% 03 OBRAS SANITARIAS 03.01 SISTEMA DE DESAGUE Y ALCANTARILLADO 03.01.01 SUMINISTRO E INSTALACION DE RED MATRIZ DE ALCANTARILLADO D=200 mm 03.01.01.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO m2 269.67 1.40 377.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 269.67 377.54 100.00% 03.01.01.02 EXCAVACION DE ZANJA C/MAQ. TERRENO NORMAL H=1.20 M. P/TUB. m3 295.54 17.89 5,287.21 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 295.54 5,287.21 100.00% 03.01.01.03 REFINE, NIVELACION Y CONFORMACION DE FONDOS m 337.07 2.29 771.89 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 337.07 771.89 100.00% 03.01.01.04 CAMA DE APOYO P/TUBERIA m 337.07 5.57 1,877.48 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 337.07 1,877.48 100.00% 03.01.01.05 TENDIDO, COLOCACION Y PRUEBA DE TUB PVC SAL 200 MM S-25 UF m 337.07 83.65 28,195.91 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 337.07 28,195.91 100.00% 03.01.01.06 RELLENO COMPACTADO DE ZANJAS CON ARENA m3 26.97 82.62 2,228.26 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 26.97 2,228.26 100.00% 03.01.01.07 RELLENO COMPACTADO DE ZANJAS CON MATERIAL PROPIO m3 268.55 17.62 4,731.85 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 268.55 4,731.85 100.00% 03.01.01.08 ELIMINACION MATERIAL EXCEDENTE m3 29.58 43.09 1,274.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 29.58 1,274.60 100.00% 03.01.01.09 PRUEBA HIDRAULICA m 337.07 3.00 1,011.21 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 337.07 1,011.21 100.00% 03.01.02 SUMINISTROS E INSTALACIONES DOMICILIARIAS DE DESAGUE 03.01.02.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO m2 69.44 1.40 97.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 69.44 97.22 100.00% 03.01.02.02 EXCAVACION DE ZANJAS HASTA H=1.20M m3 79.93 22.24 1,777.64 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 79.93 1,777.64 100.00% 03.01.02.03 REFINE, NIVELACION Y CONFORMACION DE FONDOS m 145.92 1.95 284.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 145.92 284.54 100.00% 03.01.02.04 CAMA DE APOYO P/TUBERIA m 138.88 5.57 773.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 138.88 773.56 100.00% 03.01.02.05 TENDIDO, COLOCACION Y PRUEBA DE TUB PVC SAL 160 MM UF m 138.88 63.65 8,839.71 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 138.88 8,839.71 100.00% 03.01.02.06 EMPALME DE TUBERIA PVC 160MM A RED MATRIZ DE DESAGUE PVC 200 MM und 20.00 321.88 6,437.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.00 6,437.60 100.00% 03.01.02.07 RELLENO COMPACTADO DE ZANJAS CON ARENA m3 6.94 82.62 573.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.94 573.38 100.00% 03.01.02.08 RELLENO COMPACTADO DE ZANJAS CON MATERIAL PROPIO m3 72.99 17.62 1,286.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 72.99 1,286.08 100.00% 03.01.02.09 ELIMINACION MATERIAL EXCEDENTE m3 7.99 43.09 344.29 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.99 344.29 100.00% 03.01.02.10 PRUEBA HIDRAULICA m 138.88 3.00 416.64 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 138.88 416.64 100.00% 03.01.03 CONSTRUCCION DE BUZONES DE ALCANTARILLADO 03.01.03.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO m2 10.18 1.40 14.25 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.18 14.25 99.99% 03.01.03.02 EXCAVACION DE ZANJAS HASTA H=1.20M m3 13.06 22.24 290.45 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 13.06 290.45 100.00% 03.01.03.03 REFINE, NIVELACION Y CONFORMACION DE FONDOS m 10.18 2.29 23.31 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.18 23.31 99.99% 03.01.03.04 ELIMINACION MATERIAL EXCEDENTE m3 16.98 43.09 731.67 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.98 731.67 100.00% 03.01.03.05 CONCRETO f'c=175 kg/cm2 PARA FONDOS Y MUROS m3 9.92 370.71 3,677.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.92 3,677.44 100.00% 03.01.03.06 CONCRETO f'c=210 kg/cm2 PARA LOSA m3 2.54 401.89 1,020.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.54 1,020.80 100.00% 03.01.03.07 ENCOFRADO Y DESENCOFRADO DE BUZON m2 53.72 42.67 2,292.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 53.72 2,292.23 100.00% 03.01.03.08 ACERO DE REFUERZO F'Y= 4200 KG/CM2 kg 834.46 4.42 3,688.31 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 834.46 3,688.31 100.00% 03.01.03.09 SUMINISTRO Y COLOCACION DE TAPAS DE CONCRETO P/BUZONES und 9.00 139.09 1,251.81 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.00 1,251.81 100.00% 03.01.03.10 CURADO DE CONCRETO m2 47.50 0.38 18.05 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 47.50 18.05 100.00% 03.01.03.11 OTROS IMPLEMENTOS glb 1.00 574.24 574.24 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 574.24 100.00% 04 PLAN COVID 19 04.01 PLAN COVID glb 1.00 6,500.00 6,500.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 6,500.00 100.00% CD 102,821.33 9477.41 9.22% 93343.89 90.78% COSTO DIRECTO PROGRAMADO ANTERIOR ACTUAL RESUMEN DE VALORIZACIONES DE AVANCE DE OBRA DEL MES DE ENERO DEL 2022 “Año del fortalecimiento de la soberania nacional” SALDOS ITEM DESCRIPCION MUNICIPALIDAD DISTRITAL DE SAYLLA ACUMULADO SUB GERENCIA DE INFRAESTRUCTURA
  • 2. MONTO DE OBRA CUSCO FECHA DE INICIO DE OBRA 25/01/2022 DEPARTAMENTO CUSCO PLAZO DE EJECUCIÓN TOTAL 60 CUSCO FECHA DE TERMINO REPROGRAMADO 26/03/2022 SAYLLA APV JUAN VELAZCO ANTERIOR S/. Valorizado S/. % Valorizado S/. % Valorizado S/. % Valorizado S/. % 1 PROGRAMADO (CD) 102,821.30 - 0.00% 9,477.41 9.22% 9,477.41 9.22% 93,343.89 90.78% 2 MAYORES METRADOS - 0.00% - - 3 PARTIDAS NUEVAS - - - - 4 DEDUCTIVOS - 0.00% - - COSTO DIRECTO 102,821.30 - 0.00% 9,477.41 9.22% 9,477.41 9.22% 93,343.89 90.78% GASTOS GENERALES (35.64 %) 36,650.00 - 0.00% - 0.00% - 0.00% 36,650.00 100.00% GASTOS DE SUPERVISION (8.95 %) 9,200.00 - - - 0.00% - 0.00% 9,200.00 100.00% GASTOS DE LIQUIDACION (3.89 %) 4,000.00 0.00% - 0.00% - 0.00% 4,000.00 100.00% EXPEDIENTE TECNICO (0%) 0.00 0.00% - 0.00% - 0.00% - PRESUPUESTO TOTAL 152,671.31 0.00% 9,477.41 9.22% 9,477.41 9.22% 143,193.90 6.21% DISTRITO LOCALIDAD PROVINCIA MUNICIPALIDAD DISTRITAL DE SAYLLA SUB GERENCIA DE INFRAESTRUCTURA “Año del fortalecimiento de la soberania nacional” RESUMEN DE VALORIZACIONES DE AVANCE DE OBRA DEL MES DE ENERO DEL 2022 OBRA: “Construcción de Red de Alcantarillado y conexión domiciliaria de alcantarillado en la APV Juan Velazco Alvarado distrito de Saylla, Provincia de Cusco, Departamento del Cusco.” REGION ITEM VALORIZACION PRESUPUESTO AVANCES SALDO ACTUAL ACUMULADO 1 de 1
  • 3. OBRA: PARTIDA DESCRIPCION MEDIDA METRADO 01 TRABAJOS PRELIMINARES 01.01 TRAZO Y REPLANTEO GENERAL m2 2,387.00 01.02 LIMPIEZA GENERAL m2 2,387.00 01.05 ALMACEN DE OBRA m2 40.00 RESUMEN DE METRADO DEL MES DE ENERO 2022 SUB GERENCIA DE INFRAESTRUCTURA MUNICIPALIDAD DISTRITAL DE SAYLLA “Construcción de Red de Alcantarillado y conexión domiciliaria de alcantarillado en la APV Juan Velazco Alvarado distrito de Saylla, Provincia de Cusco, Departamento del Cusco.” RESUMEN DE VALORIZACIONES DE AVANCE DE OBRA DEL MES DE ENERO DEL 2022 “Año del fortalecimiento de la soberania nacional”
  • 4. OBRA: PRESUPUESTO TOTAL DEL PROYECTO S/.152,671.31 REGION CUSCO PRESUPUESTO COSTO DIRECTO S/.102,821.30 DEPARTAMENTO CUSCO PRESUPUESTO ASIGNADO PIM 2022 S/.152,671.31 PROVINCIA CUSCO FECHA DE INICIO DE OBRA 25/01/2022 DISTRITO SAYLLA FECHA FIN 25/03/2022 LOCALIDAD C.C.ANAHUARQUE ANTERIOR S/. Valorizado S/. % Valorizado S/. % Valorizado S/. % Valorizado S/. % 1 RED DE ALCANTARILLADO 100,315.64 - 0.00% 9,477.41 9.45% 9,477.41 9.45% 90,838.23 90.55% 2 CONEXIÓN DOMICILIARIA DE ALCANTARILLADO 39,155.66 - 0.00% - 0.00% - 0.00% 39,155.66 100.00% COSTO DIRECTO 139,471.29 - 0.00% 9,477.41 6.80% 9,477.40 6.80% 129,993.89 93.20% NOTA: LA VALORIZACION ES A COSTO DIRECTO ANTERIOR S/. Valorizado S/. % Valorizado S/. % Valorizado S/. % Valorizado S/. % 0.00 - #¡DIV/0! - #¡DIV/0! - #¡DIV/0! - #¡DIV/0! 9,200.00 - 0.00% - 0.00% - 0.00% 9,200.00 100.00% 4,000.00 - 0.00% - 0.00% - 0.00% 4,000.00 100.00% 0.00 - 0.00% - 0.00% - 0.00% - 0.00% 152,671.30 - 0.00% - 0.00% - 0.00% 152,671.30 100.00% NOTA: LA VALORIZACION DE GASTOS GENERALES ES A NIVEL DE DEVENGANDO GASTOS GENERALES - GG GASTOS DE SUPERVISION - GS GASTOS DE LIQUIDACION - GL GASTOS POR EXP. TEC. - GET PRESUPUESTO TOTAL ITEM DESCRIPCION PRESUPUESTO VALORIZACION DE AVANCE FINACIERO "ENERO - 2022" ACTUAL ACUMULADO SALDO ITEM DESCRIPCION PRESUPUESTO VALORIZACION DE AVANCE FISICO REAL (CD) "ENERO 2022" ACTUAL ACUMULADO SALDO MUNICIPALIDAD DISTRITAL DE SAYLLA SUB GERENCIA DE INFRAESTRUCTURA “Año del fortalecimiento de la soberania nacional” RESUMEN VALORIZACION FISICO Y FINANCIERO VALORIZACION DE AVANCE DE OBRA N° 01 - MES ENERO POR COMPONENTE CONSTRUCCION DEL CERCO PERIMETRICO Y TRIBUNA Y/O PALCO EN ESTADIO MUNICIPAL DISTRITO DE SAYLLA, PROVINCIA CUSCO, DEPARTAMENTO CUSCO