4. THE CONCEPTION OF THE
PROJECT
THIS SYSTEM IS ABLE TO PRODUCE THE CHLORINE
DIOXIDE CLO2 QUANTITY REQUIRED FOR THE
TREATMENT OF BOTH POTABLE WATER TREATMENT
SYSTEM AND PRODUCT WATER STORAGE SYSTEM.
CHLORINE DIOXIDE IS GENERATED ACCORDING TO
THE FOLLOWING REACTION:
5 NACLO2 + 4 HCL 4 CLO2 + 5 NACL + 2 H2O
14. Construction and building
I. Civil Constructions
II. Tanks and container installation.
III. Mechanical erections.
IV. Electrical installation.
V. I&C installation.
15. Safety First.
- The Project started at very critical time and it was big challenge to get our work done with the spread
of the Covied-19 without spreading the infection among team members .
- And our great safety achievement was implementing +1000 of working hours with 0 recorded infection
cases and
0 accidents .
- Daily Activities TBT carried at the site for team awareness of daily activities and how to finish their
duties safely .
- Daily Covied-19 TBT AS per ASME (The American society of Mechanical Engineers) - OSHA Guidelines
for Engineers working during the Pandemic
22. II. Tanks and container installation.
GRVe Tanks Delivery and installation
- 2 GRVe tanks with 21.5 Cubic. Meter capacity ,one tank for HCL and other one for Naclo2 .
- Fume trap for HCL fumes
- Tanks Specs : DIA 2200 X 5835 (SHELL HEIGHT) .
55. Commissioning
Chemical Commissioning & System Efficiency test
Yielding Test
• Sampling Clo2 From Reactors with the c
and Approved 3rd party laboratory
• Testing Clo2 Concentration and system
56. Commissioning
Recallability Running
24 H Running
As Per Contract system
put in service for 24 H/
60 days as reliability
running process under
DECO monitoring and
operation .
57. Commissioning
System in Service
New Clo2 System at L-STN is Serving at DE
Jable ali , JABS
System is serving desalination Plant at L-ST
L1 & L2
Clo2 is serving
• around 11000 m3/h at L1.
• And 5000 m3/h at L2 .
59. Owner Handover
- Operation training for DEWA operation shifts .
- Maintenance Training for DEWA maintenance te
.
- 60 days reliability running for the system .
- Handover System manual documents .
- System handover to DEWA .