Raymond E. Levitt
Chris Fry
Steve Greene
Colleen Kaftan

Salesforce.com: The Development Dilemma
Steve Greene and Chris Fry left their August, 2006 meeting with Parker Harris carrying a
far bigger mandate than they had hoped for. As program and development managers,
respectively, they had proposed a pilot project to test a radically different approach to
software development at Salesforce.com. Founded in 1999 to build a new market in
subscription enterprise software services, the company had experienced annual growth
rates of 30 to 40 percent, both in customer usage and in head count. Revenues had been
growing at more than 80 percent per year, and net income faster than that. But the critical
software development function was faltering, even as revenues seemed poised to reach
nearly half a billion dollars for 2006.
The existing development processes had been slipping for some time. The pace of
releases of new software features—a key measure of value for customers—had slowed
from four times per year to once per year, and the latest release was taking even longer
than that. Morale was suffering across the organization, and a highly respected senior
developer had recently quit after delivering a scathing offsite presentation that criticized
nearly everything about the current situation. Furthermore, an infrastructure failure had
caused service outages that prevented customers from accessing their customer
information during the critical pre-holiday period in 2005. Another outage in early 2006
further eroded users’ trust in the reliability of Salesforce.com’s software service
capabilities.
Harris, one of four Salesforce.com founders and currently EVP-Technology & Products,
agreed with Fry and Greene that something had to change. But whereas Fry and Greene
wanted to start small and pilot the new method before rolling it out on a larger scale,
Harris was thinking big. He’d listened to their description of “agile” or “scrum”
development processes compared to the traditional “waterfall” approach, asked a lot of
questions, and then instructed them to implement the new method throughout the R&D
organization. “We need real change,” he said. “Let’s skip the pilot and go for the big
bang. Our system is broken, and we don’t have time to wait—so let’s go ahead and fix it
all at once.”


Professor Raymond E. Levitt, Chris Fry and Steve Greene of Salesforce.com, and Colleen Kaftan prepared this case under the
auspices of the Stanford Collaboratory for Research on Global Projects. CRGP cases are developed solely as the basis for classroom
discussion, and are not intended to serve as endorsements, primary data sources, or illustrations of either effective or ineffective
management practices.

Copyright © 2009 Stanford Collaboratory for Research on Global Projects, Stanford, California.
Company Background: The End of Software Revolution
Harris and his co-founders, led by CEO Marc Benioff, proclaimed the 1999 advent of
Salesforce.com as the “End of Software Revolution.” 1 After a 13-year career at Oracle,
the giant enterprise software vendor, Benioff wanted to turn the prevailing enterprise
software deployment model on its head. Instead of designing and installing complex,
customized software systems and applications to help companies manage various aspects
of their activities, Salesforce.com introduced “software as a service” in which customers
used web browsers to access centrally managed software applications designed to help
run their businesses over the Internet.
Later shortened to SaaS (pronounced “sass”), this new model offered significant upfront
cost savings for customers who no longer had to purchase, install, and maintain their own
customized enterprise software. Instead, they could pay a monthly fee for hosted services,
beginning with Salesforce.com’s standard customer relationship management (CRM)
programs, which users could shape to fit each company’s needs. The new paradigm also
came to be called “software on demand” and “software as a utility” for its subscriber-
based, externally maintained and broadly distributed availability. The Salesforce.com
logo featured the word “Software” with a slash through it, in the fashion of a “No Entry”
sign.
The model proved immediately attractive to customers. By January 2001, Salesforce.com
counted 1,500 customers, 30,000 subscribers, and 10 internal R&D staff. In 2005, with
total revenues above $175 million and net income of nearly $7.5 million, there were some
29,000 customers, 650,000 subscribers, and 200 R&D staff —and the numbers continued
to grow. Its IPO in the summer of 2004 set the company’s market value at more than a
billion dollars. (Exhibit 1 diagrams the Salesforce.com organization in 2006.)
Analysts and other observers cited Salesforce.com as a classic example of disruptive
innovation—a new concept, technology, value proposition, or approach to a market that
profoundly alters the competitive landscape. 2 Disruptive technologies were typically
cheaper, simpler, and less fully developed than existing mainstream offerings. Their
initial customers were those who preferred low cost and ease of use over complex, over-
performing products and systems. The challenge for disruptive innovators was to
maintain their ability to innovate as they grew larger and more successful.
Salesforce.com’s 2005 launch of Force.com, a hosted platform for developing
applications on the Internet, opened the gate for customers and third-party developers to
create new applications using the Salesforce.com platform. In short order, hundreds of
new applications became available for integrating other management tools with existing
Salesforce software. And until recently, Salesforce.com had been releasing new user
functionality on a regular basis.


1
    http://www.salesforce.com/company/milestones, accessed October, 2008.
2
 Clayton M. Christensen articulated the concept of disruptive innovation in The Innovator’s Dilemma:
When New Technologies Cause Great Firms to Fail (HPSP, 1997), and elaborated it along with his
colleagues in many subsequent publications, courses, and analytical tools.



                                                                                                       2
By 2006, several other nascent applications service providers had followed
Salesforce.com into the market for hosted CRM software, but their combined operations
were estimated to reach only about five percent of the traditional CRM market. So there
was plenty of room for continuing growth—but would Salesforce.com be capable of
prospering as a much larger company? Fry and Greene—and many of their colleagues—
thought the answer might depend on finding a way to fix the software development
process.

The Evolution of Project Management Methodology
Salesforce.com’s development process was an offshoot of traditional project management
methodology, which had evolved from the tools and processes used for getting work done
in the construction, aerospace, and pharmaceuticals industries beginning in the 1950s. 3 In
these industries, project management developed largely as a discipline for planning and
executing lengthy, complex one-off initiatives such as dams, highways, new aircraft or
nuclear submarines, or new drug therapies. In relatively stable market and technological
contexts, such projects and programs could be meticulously laid out in advance, and
implemented by strict adherence to plan. Detecting, documenting, and correcting any
deviations from the plan were critical management functions. 4
The 1990s movement toward reengineering the corporation used project management
practices to standardize and simplify smaller, repetitive tasks throughout an
organization. 5 Reengineering suggested that each task should have an identified
customer, suppliers, and an owner responsible for managing it to achieve a set of
schedule and quality metrics. It created accountability and focus for cross-functional
tasks, such as processing insurance claims or bank loan applications, that needed to flow
through multiple departments in large bureaucratic organizations. This approach proved
valuable in standardizing and simplifying workflows, developing a customer focus, and
creating a single point of accountability for critical tasks that could otherwise get
logjammed amidst the parochial priorities of individual departments.
At the dawn of the twenty-first century, global competition and the speedy spread of
knowledge brought a new type of project management challenge, as firms from rich,
high-wage countries scrambled to develop differentiated offerings in rapidly
commoditizing industries. Many traditional high-tech manufacturers and service
providers responded by shifting from making and selling standard sets of products to
delivering more sophisticated custom solutions, uniquely crafted and integrated to meet


3
 This section draws on Raymond Levitt, Lecture Notes from Converting Strategy Into Action, Stanford
Advanced Project Management executive program. See http://apm.stanford.edu.
4
 The tools and processes for doing so were encoded in the Project Management Body of Knowledge
(PMBOK), an internationally recognized standard for professional certification maintained by the Project
Management Institute.
5
 See, for example, Michael Hammer and James Champy, Reengineering the Corporation: A Manifesto for
Business Revolution (New York: HarperBusiness, 2001), and Thomas H. Davenport, Process Innovation:
Reengineering Work Through Information Technology (Boston: Harvard Business School Press, 1993).



                                                                                                           3
each customer’s specific needs. Others focused on developing a capacity for continuous
product innovation. A few brave competitors opted to offer both innovative products and
integrated solutions, with all the organizational complexities such a dual strategy implied.
The new array of project challenges ranged from large, complex, initiatives to smaller
concurrent daily operational improvements. The single common denominator was the
pace of competition. The most dynamic firms in the fastest growing sectors of the global
economy—semiconductors, computers, financial services, IT, and non-profits, for
example—needed a discipline for managing large numbers of big and small projects in
rapidly changing markets and technologies. Product, project, and program managers
needed a more flexible, process-light framework in which to apply their organizational
methods and tools.
The big CRM solutions companies adopted a “waterfall” approach to software
development, which—while more nimble than the traditional aircraft, construction, and
pharmaceutical industry methodologies—still relied on the sequential performance of
largely separate functional activities, based on a predefined plan and budget. Project
priorities were established centrally, usually by customer-facing product managers who
determined user needs and then worked across functional lines to push the project
forward. Exhibit 2 shows the typical sequence of functional activities in waterfall
development.

Perils of Growth at Salesforce.com
Salesforce.com started out with what Parker Harris called a much more organic
development organization, with a small group of people collaborating closely on each
release. As the company grew, however, it gravitated naturally toward the phased
waterfall development model. But as had become apparent over the years, any change or
deviation to the original plan interrupted progress and delayed the target release date.
Parker Harris described the progression since the early days:
       We started out as a small team—like 15 people in the early years. A team
       like that doesn’t really need a lot of process. We were doing releases or
       upgrading our service as frequently as possible. So when we started the
       company, we upgraded every four weeks, and then six weeks, and over the
       years that slowed down, so it’s been almost four times a year, and then it
       was two times a year, and then it was once a year.
Harris recalled how the development process evolved:
       We were perfecting processes as we grew. So we said, OK—we’ll
       definitely need to have a really good section in there for localization, we
       need to make sure we do usability, and let’s add load/stress testing. We
       added these things simply because they were important, and our customers
       were looking for more quality, more performance. We also added people,
       so the team grew significantly. And what used to be an organic process
       because we just iterated and that was the natural thing to do, as we added



                                                                                           4
all these other things we had to do, it grew into this more waterfall
       process, where everything went down the line.
The R&D group eventually organized around “feature teams”—project groups who were
assigned to develop centrally-designated user capabilities. Whenever the product
managers identified a desirable feature to develop, they would assign people from across
the functions to the team charged with building it. People were often assigned to several
teams at once, and many had trouble prioritizing their work across teams.
By the time Steve Greene and Chris Fry came to Salesforce.com in early 2005, the R&D
headcount had grown to well over 150. Fry described one drawback he observed in the
feature team model:
       There’d be a weekly meeting for each team. Everyone would show up and
       discuss all the problems for an hour, and then just go back to their desks.
       There was no accountability. You’d go to all the feature team meetings
       you were assigned to, and the next week you’d go back and say, “What
       was it I promised to do?” And nobody was tracking if you were on 20
       teams or just one.
Steve Greene elaborated:
       So basically, you’re pushing prioritization down to the individual
       contributors, because they’re on five teams and they would decide—on a
       daily basis—what’s the most important thing, and there’d be confusion
       across the organization because everybody had a different idea of what the
       highest priority was. And management didn’t have visibility into this,
       because they couldn’t attend the 20 meetings every week.
Parker Harris began to notice other problems with the feature team / waterfall
approach:
       We’d set formal user expectations and then product management would
       build a prototype and write a functional spec. Development would then
       write a technical spec, and on down the line. The timelines were fixed, and
       everybody would end up padding their estimates and still being late, and
       then blaming the delay on other people upstream in the process.
       At the end, everyone blamed QA [quality assurance], because QA is at the
       end of the waterfall. Then everyone started pointing fingers at each other,
       and it also caused really weird behavior where people would work outside
       the process: “Maybe I shouldn’t pay attention to this process, and just be
       late with my stuff—the release won’t go out without it, and if my area’s
       late, maybe we’ll get more attention later on”…and so on.
By summer of 2006, the R&D headcount reached nearly 300. Many new hires came from
bigger companies such as SAP, with centralized approaches to software development.
They brought with them a big company culture, according to Steve Greene, so that by
mid-2006, even though Salesforce.com was considerably smaller than most of its
competitors, “We were having just as much difficulty delivering releases as the big

                                                                                        5
companies were.” Case in point: the schedule for Release 144 had already slipped several
times, and some of the features were still not ready for shipping.
Greene described the internal effect of the delay:
       We had huge morale problems. Because if you’re a technologist, you want
       to build something useful, and you want to get it out there to your
       customers to use as quickly as possible. You don’t want to just talk about
       it. And we had people who had been at salesforce more than a year—
       people we hired from larger organizations, with the promise that they
       could accomplish things quickly here—some of them had never actually
       released a feature to production.
Fry agreed:
       The institutional knowledge of how to do releases wasn’t as strong as it
       should be. And our development people like to create things that people
       use, but we weren’t getting that positive feedback into the team, so there
       was low morale across the board.
On the customers’ side, the service outages of late 2005 and early 2006 exacerbated the
development issues. Customers depended on “dial-tone reliability” for on-demand
services, and when they were unable to access their data, they began to question the new
business paradigm. If Salesforce.com couldn’t assure customers of reliable service, and
couldn’t even deliver new features on a regular basis, why should any customer base its
operations on the hosted services model?
The Shinkansen Project
In summer of 2006, Parker Harris asked Steve Greene and Chris Fry to explore the
“release train” development model that many considered to be the driving force behind
the rapid development capabilities at eBay. To underscore the ugency of speeding up
Salesforce.com’s development process, the three named their initiative Shinkansen, after
the famed Japanese bullet trains—arguably, along with France’s TGV and Germany’s
ICE, the fastest in the world.
An eBay-commissioned joint benchmarking study in 2006-2006 described the release
train system as follows:
       As the term implies, this process is like a train that has a fixed number of
       seats for passengers and a pre-set schedule. Companies decide in advance
       the number of releases they’d like to issue each year, as well as the size of
       each release. The release size is usually based on the required level of
       effort as defined by person days, or “developer days.” Teams of
       developers work furiously to complete their new products in time for a




                                                                                           6
certain release train. If they miss the train, they must wait for the next
        release. 6
Release trains departed every two weeks on schedule at eBay. When a releasable feature
made it onto the train, it would then integrate with other new features and the existing
platform much as rail cars couple together, and undergo extensive quality testing. This
late integration model proved less attractive for Salesforce.com, in part because the
company had recently developed an automated testing capability for continuous
integration of most new code. The developers were responsible for testing and integrating
whatever fell outside the automated process. Many considered this capability to be an
important competitive weapon for Salesforce.com.
Fry and Greene also encountered widespread resistance to the idea of an externally-
developed process imposed from on high. After three months of trying to plan how to
introduce the release train methodology, the project group decided to abandon the cause.
On the heels of this less-than-promising endeavor, Greene and Fry decided to propose an
“agile” development approach in August 2006. Both were familiar with the method, but
they did further research to prepare a detailed description for Harris, and set off to
persuade him to try it. If Harris agreed, they hoped to turn the Shinkansen team into an
agile development team.

Background on the Principles of Agile Development
Fry and Greene began by summarizing the history of agile methods for Harris. The Agile
movement represented a philosophy and a shared language as well as an approach to
software development. Rooted in the 1980s concepts of lean manufacturing and product
development, it had evolved to fit the software development challenges of the early
2000s. 7 Extreme Programming (XP), Scrum, and Lean were similar approaches often
subsumed under the Agile umbrella. (Exhibit 3 lists “Twelve Principles of Agile
Software,” along with the “Manifesto for Agile Software Development,” both authored in
2001 by a large group of professional developers.)
Key Concepts
Agile methodology specifically targeted product developers’ needs in fast-moving
markets. It used standing cross-functional “scrum teams” to turn out frequent,
incremental, and potentially releasable features on a regular basis, commonly after a
month-long “sprint.” A full-blown release might incorporate three one-month sprint




6
 http://www.prtm.com/uploadedFiles/Strategic_Viewpoint/Articles/Article_Content/PRTM_eBay_benchm
arking.pdf
7
 Information in this section comes from many sources, including K. Beck, Extreme Programming
Explained (Addison Wesley, 2000), M. Poppendieck and T. Poppendieck, Lean Software Development
(Addison Wesley, 2003), and M. Cohn and D. Ford, “Introducing an Agile Process to an Organization,”
Computer, June 2003, pp. 74-78. See also http://www.mountaingoatsofware.com/daily_scrum



                                                                                                      7
cycles, each of which followed a specific rhythm. (Exhibit 4 charts the activities in a
typical sprint-to-release calendar. Exhibit 5 distills the scrum lifecycle.)
Every thirty-day sprint began with a planning meeting, in which a product owner
identified desirable features, or a product backlog of “user stories,” in order of priority.
(A typical user story might read, “I can predict customer purchasing patterns,” or “I can
compile hourly sales by distribution channel.”) The scrum team evaluated the backlog
list, agreed on the number of top priority items they could deliver during the sprint, and
committed to doing so. Once that commitment was in place, no further requirements or
changes could be introduced during the month-long sprint. The scrum team of no more
than 12 people—including product managers, developers, quality engineers, user
experience designers, usability testers and technical writers—worked together every day
to accomplish their sprint commitments. They used highly visible shared tools, such as
wall-mounted task boards and Excel spreadsheets, to keep track of their progress in
completing the tasks in a “release burndown.” Team members who had completed their
tasks would step in to assist other team members who needed help completing their tasks.
Each 30-day sprint ended with a sprint review, in which team members demonstrated
their accomplishments to the team and management during the sprint. Sprint reviews
were meant to be simple, natural discussions of new capabilities, rather than highly
prepared formal presentations. This reinforced the Agile principle of only including code
that is truly “done”—i.e., coded, usability tested, QA tested and documented, and thus
ready to be integrated into the next release.
The objective was to “deliver fast and deliver early,” while avoiding the typical scope
creep and roadblocks that tended to plague extended waterfall development projects.
Every sprint could produce shippable capabilities, whether the company was ready to
release them or not. One intended side effect was to eliminate the crisis management and
panic associated with more ambitious, sequential, waterfall-based feature releases with
lengthy (and often unpredictable) development calendars.
Roles and Rituals
Agile processes required designating a product owner, a scrum master, and scrum team
members (often for multiple teams coordinated by a “scrum of scrums”) for each sprint.
People tended to stay in these roles over time, so that working relationships and team
procedures could evolve to fit the team members’ preferences and the requirements of
their specific tasks.
Perhaps the most critical daily event for a scrum team was a short morning “stand-up”
meeting—typically lasting no more than about 15 minutes—which set the context for the
coming day’s work. These meetings were held at the same time and the same location
every day, and were open to anyone who wanted to attend. There was a strict distinction
between those who were “involved” and those who were “committed” in terms of their
rights to participate in the meetings.
Scrum experts used a chicken and pig metaphor to describe the difference:




                                                                                           8
There is an old joke in which a chicken and pig are talking and the chicken
       says, “Let’s start a restaurant.” The pig relies, “Good idea, but what should
       we call it?” “How about ‘Ham and Eggs?’” says the chicken. “No thanks,
       says the pig, “I’d be committed, you’d only be involved.”
Only committed scrum team members were allowed to talk at daily meetings. Each one
had to answer just three questions, designed to reinforce team commitments and remove
roadblocks:
   •   What did I do yesterday?
   •   What will I do today?
   •   What is blocking me—i.e., what impediments are in my way?
The scrum master’s job was to remove the impediments every day, so that the team could
meet its sprint commitments. Allowing “chickens” to listen in on daily meetings was
meant to promote visibility throughout the organization without impeding the teams’
work.

Risks of a Large-Scale Rollout
Greene and Fry were pleased with Harris’s strong endorsement of their proposal and with
the mandate to “make it happen” throughout Salesforce.com. However, they both
remarked that large-scale implementation of the new methodology seemed much riskier
than trying a pilot project. They hated to think about the consequences of another failed
attempt to change the development process at Salesforce.com—especially if that failure
was organization-wide and highly visible rather than small-scale and contained. Yet it
seemed as though they had already hit a low point with the aborted Shinkansen project
and the delay of Release 144. Could things get any worse?
Maybe they could. For one thing, no one had ever adopted Agile methods on such a large
scale before. Even one of the most prominent experts in the field declined to participate
as a consultant, citing the long odds against a “big bang” rollout. Another suggested that
to make the change on such a broad scale might be possible, but only with extensive (and
expensive) outside help.
Moreover, it was hard to imagine that anybody at Salesforce.com would be interested in a
process dictated from above. The senior developers in particular were skeptical of any
process or reporting requirements that would take them away from their “real” work. And
the Shinkansen project had underscored the not-invented-here mentality that reigned
among Salesforce.com’s talented development team. Any major new program would
certainly meet great resistance unless the developers could call it their own.
But Parker Harris stood firmly behind the big bang initiative. He wanted Fry and Greene
to design and roll out their own version of Agile methodology for Salesforce.com—a
hybrid of the existing approaches tailored to the needs, temperament, and circumstances
of the in-house developers—and he wanted them to figure out how to do the necessary
training internally.



                                                                                          9
Was Harris correct in suggesting they could do it without outside help from consultants?
And would any developers agree to devote their time and energy to a changeover, with
Release 144 still stuck in project management limbo? As they thought about how to
proceed, Fry and Greene recalled Harris’s comment at their August meeting:
“Salesforce.com hasn’t made a big investment in processes because we haven’t known
which processes to implant.” If Harris was so sure that the Agile was best, how much of
the company’s time, energy, and money could they expect him to invest into making it
work?

Moving Ahead with ADM
Greene and Fry assembled a cross-functional rollout team and adopted an agile approach
to the implementation. Members of the implementation team attended outside Scrum
Master Training programs to learn about the methodology they would soon be modeling
for the rest of the development group.
The new team decided to use an Agile-type process to “burn down the bugs” in the long-
overdue Release 144. From one day to the next, they would introduce the new
methodology throughout the R&D organization by showing everyone how to apply this
new approach to development on a pressing problem. In the process of adopting Agile
methods, they also intended to customize the approach to fit the Salesforce.com
organization. Their home-grown version would be known as Agile Development
Methodology, or ADM.
They divided the broader development organization into some 30 scrum teams, each with
six to ten members. The rollout team held 45 one-hour meetings to introduce the new
methodology, and proposed to accomplish the bug-burndown for Release 144 in three
one-month sprints. All subsequent meetings welcomed open attendance, but only
committed team members were allowed to speak. Managers from other areas had a hard
time not chiming in, so the scrum masters and team members frequently evoked the
chicken-and-pig rule. But just having managers in the room seemed unusual to many
developers, and some claimed to resent it.
As part of the new ADM approach, “drive bys”—managers poking their heads into
developers’ offices to request new features or requirements that they wanted—were
outlawed. Parker Harris worked hard to reinforce this prohibition on drive-bys to change
the culture of top down opportunistic “software redesign” at Salesforce.com.
Early Progress Report
 From the outset, the rollout team encountered both enthusiasm and resistance. Some
developers were relieved to find a process that might help them turn out useful features in
a timely manner. Several willingly volunteered to invest their time in helping their
colleagues get comfortable with ADM. Parker Harris himself promised to be an
evangelist for the process, and he directed the company’s project management office to
support the initiative to the fullest.
But there were detractors as well. Within a few weeks, the early enthusiasts collected a
list of negative comments from their colleagues, including the following:


                                                                                           10
•   “Scrum doesn’t account for the fact or the reality of the waterfall. You cannot
       deny this by superimposing scrum over it.”
   •   “It seems like we spend more time talking about scrum…than we spend time
       talking about and working on salesforce.com.”
   •   “In many ways, scrum seems like an inflexible, bureaucratic process akin to
       something at the Department of Motor Vehicles.”
   •   “Management is not proactive as we wait for decisions…Scrum gives me the
       feeling that Big Brother is watching and monitoring everything we do.”
   •   “The lingo is ridiculous!”
   •   “Ditch the stupid, annoyingly dumb Excel spreadsheet!”
   •   “Stop trying to implement scrum, and look at how many releases we can really do
       in a year.”
To make matters worse, by the middle of the third sprint in December 2006, it was
obvious that the teams would not be able to complete all the prioritized features for
Release 144. This created a dilemma for Greene and Fry: should they finish the sprint on
time, and deploy what was “done” and releasable, or should they ask Parker Harris and
the executive team for a delay?
What Next?
On the one hand, to push the release out yet again could undermine the message that
Salesforce.com really intended to implement ADM throughout the R&D organization and
beyond. But to demo an incomplete set of features might introduce ADM in less than
favorable light. Would ADM then go the way of Shinkansen and other failed initiatives?
If so, what would be the consequences, internally and in the marketplace?
Most people involved in the rollout believed that they could use the ADM process to
teach, adapt, and reinforce ADM itself. This would take time—probably measured in
multiple sprints. But where should they go from here? How should they identify the
priorities for each successive sprint? For example, should they focus on bringing the most
resistant, poor-performing groups up to speed, or start with the ones that were doing
somewhat better and eager to learn more? Would it be better to have most groups
performing adequately, or should they work on creating a few “stars” to serve as
examples for the rest of the organization? And would Salesforce.com be able to keep
adapting ADM to meet the needs of the organization as it continued to grow?
Finally, and more immediately, how should they handle Release 144—not to mention
146, 148, and others still to come? Fry and Greene thought the company’s continued
success could depend on making sure they were asking the right questions, and then
getting the answers right.




                                                                                         11
Salesforce.com: The Development Dilemma
                                       Exhibit 1: Salesforce.com Organization Chart, 2006




                                   SFDC Organization Chart - 2006
                                                                          Marc Benioff, CEO




              EVP Marketing                                                                            Parker Harris, EVP Technology




       SVP Applications Product Mgmt         SVP Platform Product Mgmt       SVP Development                   SVP QE                       SVP Program Mgmt




        Senior Director UI         Chris Fry     VP Applications   Senior Director      VP Quality     Steve Greene       Core Pgm Mgmt    Platform Program Applications
                                   VP Platform                     Core                 Assurance      Senior Director,                    Mgmt             Program Mgmt
                                                                                                       Tools & Agile
   Documentation       Usability
                                                                                                       Process
   Manager             Manager




           Applications SoS                                               Platform SoS                                                 Core SoS

                                                                   Apex       Sandbox      …         API                       Core       Automation …      Systest
            CRM         SFA        …      Content




Source: Company documents.




                                                                                                                                                                           12
Salesforce.com: The Development Dilemma
                      Exhibit 2: Chart of Waterfall Development Process




             Waterfall Software Development Process




Source: Company documents.




                                                                          13
Salesforce.com: The Development Dilemma
        Exhibit 3: 12 Principles of Agile Software and Manifesto for Agile Software Development


We follow these Twelve Principles of Agile Software:

    •     Our highest priority is to satisfy the customer through early and continuous delivery
          of valuable software.
    •     Welcome changing requirements, even late in development. Agile processes harness change for
          the customer's competitive advantage.
    •     Deliver working software frequently, from a couple of weeks to a couple of months, with a
          preference to the shorter timescale.
    •     Business people and developers must work together daily throughout the project.
    •     Build projects around motivated individuals. Give them the environment and support they need,
          and trust them to get the job done.
    •     The most efficient and effective method of conveying information to and within a development
          team is face-to-face conversation.
    •     Working software is the primary measure of progress.
    •     Agile processes promote sustainable development. The sponsors, developers, and users should be
          able to maintain a constant pace indefinitely.
    •     Continuous attention to technical excellence and good design enhances agility.
    •     Simplicity--the art of maximizing the amount of work not done--is essential.
    •     The best architectures, requirements, and designs emerge from self-organizing teams.
    •     At regular intervals, the team reflects on how to become more effective, then tunes and adjusts
          its behavior accordingly.




                                 Manifesto for Agile Software Development

We are uncovering better ways of developing software by doing it and helping others do it. Through this
work we have come to value:

                           Individuals and interactions over processes and tools

                           Working software over comprehensive documentation

                             Customer collaboration over contract negotiation

                                Responding to change over following a plan

That is, while there is value in the items on the right, we value the items on the left more.

Kent Beck, Mike Beedle, Arie van Bennekum, Alistair Cockburn, Ward Cunningham, Martin Fowler,
James Grenning, Jim Highsmith, Andrew Hunt, Ron Jeffries, Jon Kern, Brian Marick, Robert C. Martin,
Steve Mellor, Ken Schwaber, Jeff Sutherland, Dave Thomas.

© 2001, the above authors. This declaration may be freely copied in any form, but only in its entirety
through this notice.

Source: http://www.agilemanifesto.org/




                                                                                                          14
Salesforce.com: The Development Dilemma
                      Exhibit 4: Diagram of Sprint and Scrum Activities




Source: Company documents.




                                                                          15
Salesforce.com: The Development Dilemma
                              Exhibit 5: The Scrum Lifecycle




     Scrum Lifecycle

                                Daily Scrum
                                 Meeting


          Product        Sprint                                     Sprint Review:
          Backlog       Backlog                                    Demo Potentially
                                                                   Releasable New
                                                                     Functionality




                                    Retrospective




Source: Company documents.




                                                                                      16

More Related Content

What's hot

What Is Salesforce CRM, Editions, Licenses?
What Is Salesforce CRM, Editions, Licenses?What Is Salesforce CRM, Editions, Licenses?
What Is Salesforce CRM, Editions, Licenses?Thinqloud
 
Salesforce intro session_for_students_v2
Salesforce intro session_for_students_v2Salesforce intro session_for_students_v2
Salesforce intro session_for_students_v2Stephen Edache Paul
 
Ms Dynamics 365 vs Salesforce CRM
Ms Dynamics 365 vs Salesforce CRMMs Dynamics 365 vs Salesforce CRM
Ms Dynamics 365 vs Salesforce CRMStridely Solutions
 
Sales Cloud Lightning Migration Best Practices (May 12, 2017)
Sales Cloud Lightning Migration Best Practices (May 12, 2017)Sales Cloud Lightning Migration Best Practices (May 12, 2017)
Sales Cloud Lightning Migration Best Practices (May 12, 2017)Salesforce Partners
 
SalesForce Consulting Service & Customization
SalesForce Consulting Service & CustomizationSalesForce Consulting Service & Customization
SalesForce Consulting Service & Customizationvarianceinfotech
 
What Is Salesforce CRM? | Salesforce CRM Tutorial For Beginners | Salesforce ...
What Is Salesforce CRM? | Salesforce CRM Tutorial For Beginners | Salesforce ...What Is Salesforce CRM? | Salesforce CRM Tutorial For Beginners | Salesforce ...
What Is Salesforce CRM? | Salesforce CRM Tutorial For Beginners | Salesforce ...Edureka!
 
Sap integration salesforce_presentation
Sap integration salesforce_presentationSap integration salesforce_presentation
Sap integration salesforce_presentationSalesforce Deutschland
 
Salesforce Communities
Salesforce CommunitiesSalesforce Communities
Salesforce CommunitiesSunil kumar
 
Salesforce online training || Salesforce Integration | salesforce lightning
Salesforce online training || Salesforce Integration | salesforce lightningSalesforce online training || Salesforce Integration | salesforce lightning
Salesforce online training || Salesforce Integration | salesforce lightningsuresh
 
Building a Center of Excellence for your Salesforce crm team
Building a Center of Excellence for your Salesforce crm teamBuilding a Center of Excellence for your Salesforce crm team
Building a Center of Excellence for your Salesforce crm teamBuyan Thyagarajan
 
Salesforce Basic Navigation
Salesforce Basic NavigationSalesforce Basic Navigation
Salesforce Basic NavigationLorraine Pinto
 
A complete Salesforce implementation guide on how to implement Salesforce
A complete Salesforce implementation guide on how to implement SalesforceA complete Salesforce implementation guide on how to implement Salesforce
A complete Salesforce implementation guide on how to implement SalesforceSoftweb Solutions
 
Technology in Society-CRM-(Salesforce)-Business Strategy
Technology in Society-CRM-(Salesforce)-Business Strategy Technology in Society-CRM-(Salesforce)-Business Strategy
Technology in Society-CRM-(Salesforce)-Business Strategy Victoria University
 

What's hot (20)

Salesforce
SalesforceSalesforce
Salesforce
 
What Is Salesforce CRM, Editions, Licenses?
What Is Salesforce CRM, Editions, Licenses?What Is Salesforce CRM, Editions, Licenses?
What Is Salesforce CRM, Editions, Licenses?
 
Salesforce intro session_for_students_v2
Salesforce intro session_for_students_v2Salesforce intro session_for_students_v2
Salesforce intro session_for_students_v2
 
Ms Dynamics 365 vs Salesforce CRM
Ms Dynamics 365 vs Salesforce CRMMs Dynamics 365 vs Salesforce CRM
Ms Dynamics 365 vs Salesforce CRM
 
Sales Cloud Lightning Migration Best Practices (May 12, 2017)
Sales Cloud Lightning Migration Best Practices (May 12, 2017)Sales Cloud Lightning Migration Best Practices (May 12, 2017)
Sales Cloud Lightning Migration Best Practices (May 12, 2017)
 
SalesForce Consulting Service & Customization
SalesForce Consulting Service & CustomizationSalesForce Consulting Service & Customization
SalesForce Consulting Service & Customization
 
What Is Salesforce CRM? | Salesforce CRM Tutorial For Beginners | Salesforce ...
What Is Salesforce CRM? | Salesforce CRM Tutorial For Beginners | Salesforce ...What Is Salesforce CRM? | Salesforce CRM Tutorial For Beginners | Salesforce ...
What Is Salesforce CRM? | Salesforce CRM Tutorial For Beginners | Salesforce ...
 
Sales Cloud Best Practices
Sales Cloud Best PracticesSales Cloud Best Practices
Sales Cloud Best Practices
 
Sap integration salesforce_presentation
Sap integration salesforce_presentationSap integration salesforce_presentation
Sap integration salesforce_presentation
 
Salesforce Communities
Salesforce CommunitiesSalesforce Communities
Salesforce Communities
 
Commerce Cloud 101
Commerce Cloud 101Commerce Cloud 101
Commerce Cloud 101
 
Salesforce online training || Salesforce Integration | salesforce lightning
Salesforce online training || Salesforce Integration | salesforce lightningSalesforce online training || Salesforce Integration | salesforce lightning
Salesforce online training || Salesforce Integration | salesforce lightning
 
Salesforce
SalesforceSalesforce
Salesforce
 
Building a Center of Excellence for your Salesforce crm team
Building a Center of Excellence for your Salesforce crm teamBuilding a Center of Excellence for your Salesforce crm team
Building a Center of Excellence for your Salesforce crm team
 
Salesforce Basic Navigation
Salesforce Basic NavigationSalesforce Basic Navigation
Salesforce Basic Navigation
 
A complete Salesforce implementation guide on how to implement Salesforce
A complete Salesforce implementation guide on how to implement SalesforceA complete Salesforce implementation guide on how to implement Salesforce
A complete Salesforce implementation guide on how to implement Salesforce
 
Salesforce Deck Template
Salesforce Deck TemplateSalesforce Deck Template
Salesforce Deck Template
 
Architect day 20181128 - Afternoon Session
Architect day 20181128 - Afternoon SessionArchitect day 20181128 - Afternoon Session
Architect day 20181128 - Afternoon Session
 
Top 10 Checklist For Successful Salesforce Implementation
Top 10 Checklist For Successful Salesforce ImplementationTop 10 Checklist For Successful Salesforce Implementation
Top 10 Checklist For Successful Salesforce Implementation
 
Technology in Society-CRM-(Salesforce)-Business Strategy
Technology in Society-CRM-(Salesforce)-Business Strategy Technology in Society-CRM-(Salesforce)-Business Strategy
Technology in Society-CRM-(Salesforce)-Business Strategy
 

Viewers also liked

Salesforce.com strategic analysis
Salesforce.com strategic analysisSalesforce.com strategic analysis
Salesforce.com strategic analysisSophie Michelot
 
MIS Presentation about SalesForce.com
MIS Presentation about SalesForce.comMIS Presentation about SalesForce.com
MIS Presentation about SalesForce.comLikhan Banik
 
Salesforce.com Agile Transformation - Agile 2007 Conference
Salesforce.com Agile Transformation - Agile 2007 ConferenceSalesforce.com Agile Transformation - Agile 2007 Conference
Salesforce.com Agile Transformation - Agile 2007 ConferenceSteve Greene
 
Sales force case study kartix
Sales force case study   kartixSales force case study   kartix
Sales force case study kartixthu ra
 
Case Studies (Questions and Answers)
Case Studies (Questions and Answers)Case Studies (Questions and Answers)
Case Studies (Questions and Answers)113068
 
Scrum Gathering 2008 Stockholm - Salesforce.com
Scrum Gathering 2008 Stockholm - Salesforce.comScrum Gathering 2008 Stockholm - Salesforce.com
Scrum Gathering 2008 Stockholm - Salesforce.comSteve Greene
 
Salesforce Advantage (8 Core Differentiators)
Salesforce Advantage (8 Core Differentiators)Salesforce Advantage (8 Core Differentiators)
Salesforce Advantage (8 Core Differentiators)Salesforce Partners
 
How Salesforce CRM works & who should use it?
How Salesforce CRM works & who should use it?How Salesforce CRM works & who should use it?
How Salesforce CRM works & who should use it?Suyati Technologies
 
Enterprise Agile Transformation Strategies
Enterprise Agile Transformation StrategiesEnterprise Agile Transformation Strategies
Enterprise Agile Transformation StrategiesMike Cottmeyer
 
Salesforce.com Overview
Salesforce.com OverviewSalesforce.com Overview
Salesforce.com OverviewEdureka!
 
Content required in the research project paper
Content required in the research project paperContent required in the research project paper
Content required in the research project paperMartha Schwer
 
The Steep Forces Driving Cloud Computing
The Steep Forces Driving Cloud ComputingThe Steep Forces Driving Cloud Computing
The Steep Forces Driving Cloud ComputingCraig Rispin
 
An Enterprise Agile Transformation Story: Türkiye Finans Participation Bank b...
An Enterprise Agile Transformation Story: Türkiye Finans Participation Bank b...An Enterprise Agile Transformation Story: Türkiye Finans Participation Bank b...
An Enterprise Agile Transformation Story: Türkiye Finans Participation Bank b...Agile ME
 
Business model innovation in the cloud v1
Business model innovation in the cloud v1Business model innovation in the cloud v1
Business model innovation in the cloud v1Michael Netzley, Ph.D.
 
The Salesforce Advantage: Understanding the Why (August 17, 2015)
The Salesforce Advantage: Understanding the Why (August 17, 2015)The Salesforce Advantage: Understanding the Why (August 17, 2015)
The Salesforce Advantage: Understanding the Why (August 17, 2015)Salesforce Partners
 

Viewers also liked (19)

Salesforce.com strategic analysis
Salesforce.com strategic analysisSalesforce.com strategic analysis
Salesforce.com strategic analysis
 
Salesforce.com
Salesforce.comSalesforce.com
Salesforce.com
 
MIS Presentation about SalesForce.com
MIS Presentation about SalesForce.comMIS Presentation about SalesForce.com
MIS Presentation about SalesForce.com
 
Salesforce.com Agile Transformation - Agile 2007 Conference
Salesforce.com Agile Transformation - Agile 2007 ConferenceSalesforce.com Agile Transformation - Agile 2007 Conference
Salesforce.com Agile Transformation - Agile 2007 Conference
 
Salesforce.com
Salesforce.comSalesforce.com
Salesforce.com
 
Sales force case study kartix
Sales force case study   kartixSales force case study   kartix
Sales force case study kartix
 
Case Studies (Questions and Answers)
Case Studies (Questions and Answers)Case Studies (Questions and Answers)
Case Studies (Questions and Answers)
 
Scrum Gathering 2008 Stockholm - Salesforce.com
Scrum Gathering 2008 Stockholm - Salesforce.comScrum Gathering 2008 Stockholm - Salesforce.com
Scrum Gathering 2008 Stockholm - Salesforce.com
 
Salesforce Advantage (8 Core Differentiators)
Salesforce Advantage (8 Core Differentiators)Salesforce Advantage (8 Core Differentiators)
Salesforce Advantage (8 Core Differentiators)
 
How Salesforce CRM works & who should use it?
How Salesforce CRM works & who should use it?How Salesforce CRM works & who should use it?
How Salesforce CRM works & who should use it?
 
Enterprise Agile Transformation Strategies
Enterprise Agile Transformation StrategiesEnterprise Agile Transformation Strategies
Enterprise Agile Transformation Strategies
 
Salesforce.com Overview
Salesforce.com OverviewSalesforce.com Overview
Salesforce.com Overview
 
Jade Magnet Cases Healthcare
Jade Magnet Cases HealthcareJade Magnet Cases Healthcare
Jade Magnet Cases Healthcare
 
Content required in the research project paper
Content required in the research project paperContent required in the research project paper
Content required in the research project paper
 
The Steep Forces Driving Cloud Computing
The Steep Forces Driving Cloud ComputingThe Steep Forces Driving Cloud Computing
The Steep Forces Driving Cloud Computing
 
An Enterprise Agile Transformation Story: Türkiye Finans Participation Bank b...
An Enterprise Agile Transformation Story: Türkiye Finans Participation Bank b...An Enterprise Agile Transformation Story: Türkiye Finans Participation Bank b...
An Enterprise Agile Transformation Story: Türkiye Finans Participation Bank b...
 
Business model innovation in the cloud v1
Business model innovation in the cloud v1Business model innovation in the cloud v1
Business model innovation in the cloud v1
 
The Salesforce Advantage: Understanding the Why (August 17, 2015)
The Salesforce Advantage: Understanding the Why (August 17, 2015)The Salesforce Advantage: Understanding the Why (August 17, 2015)
The Salesforce Advantage: Understanding the Why (August 17, 2015)
 
Agile fractal grid 7-11-14
Agile fractal grid   7-11-14Agile fractal grid   7-11-14
Agile fractal grid 7-11-14
 

Similar to Stanford Case Study - Salesforce.com Transformation

Do you need a new product development strategy
Do you need a new product development strategyDo you need a new product development strategy
Do you need a new product development strategysamatong
 
Enterprise and Applications: Definition; Types; Challenges; Opportunities
Enterprise and Applications: Definition; Types; Challenges; OpportunitiesEnterprise and Applications: Definition; Types; Challenges; Opportunities
Enterprise and Applications: Definition; Types; Challenges; OpportunitiesSudhanshuKMevat
 
Gain new visibility in your DevOps team
 Gain new visibility in your DevOps team Gain new visibility in your DevOps team
Gain new visibility in your DevOps teamAbhishek Sood
 
HP Project and Portfolio Management
HP Project and Portfolio ManagementHP Project and Portfolio Management
HP Project and Portfolio ManagementHP Enterprise Italia
 
TitleABC123 Version X1Hewlett-Packard Case Study Anal.docx
TitleABC123 Version X1Hewlett-Packard Case Study Anal.docxTitleABC123 Version X1Hewlett-Packard Case Study Anal.docx
TitleABC123 Version X1Hewlett-Packard Case Study Anal.docxjuliennehar
 
Idc roi-of-building-apps-on-salesforce
Idc roi-of-building-apps-on-salesforceIdc roi-of-building-apps-on-salesforce
Idc roi-of-building-apps-on-salesforceCMR WORLD TECH
 
Salesforce_AnalysisFinalProject_Team6
Salesforce_AnalysisFinalProject_Team6Salesforce_AnalysisFinalProject_Team6
Salesforce_AnalysisFinalProject_Team6Thomas Kurnicki
 
Product Marketing, the Salesforce Way (October 13, 2014)
Product Marketing, the Salesforce Way (October 13, 2014)Product Marketing, the Salesforce Way (October 13, 2014)
Product Marketing, the Salesforce Way (October 13, 2014)Salesforce Partners
 
Nicholas Hoffmeyer - Adobe Systems - BL_S2_2016
Nicholas Hoffmeyer  - Adobe Systems - BL_S2_2016Nicholas Hoffmeyer  - Adobe Systems - BL_S2_2016
Nicholas Hoffmeyer - Adobe Systems - BL_S2_2016Nick Hoffmeyer
 
Assessment Of An Enterprise-Level Business System
Assessment Of An Enterprise-Level Business SystemAssessment Of An Enterprise-Level Business System
Assessment Of An Enterprise-Level Business SystemTiffany Graham
 
Mongo db better_faster_leaner
Mongo db better_faster_leanerMongo db better_faster_leaner
Mongo db better_faster_leanerDrew LaMonte
 
Lead User Innovation at Salesforce.com
Lead User Innovation at Salesforce.comLead User Innovation at Salesforce.com
Lead User Innovation at Salesforce.comGarrett Dodge
 
Salesforce.com    January  2015  .docx
Salesforce.com    January  2015  .docxSalesforce.com    January  2015  .docx
Salesforce.com    January  2015  .docxrtodd599
 
The Five Essential Truths of the Application Economy
The Five Essential Truths of the Application EconomyThe Five Essential Truths of the Application Economy
The Five Essential Truths of the Application EconomyCA Technologies
 
Uses Of New And Emerging Technologies In Marketing Software
Uses Of New And Emerging Technologies In Marketing SoftwareUses Of New And Emerging Technologies In Marketing Software
Uses Of New And Emerging Technologies In Marketing SoftwareJenny Mancini
 
Embedded Analytics in CRM and Marketing
Embedded Analytics in CRM and Marketing Embedded Analytics in CRM and Marketing
Embedded Analytics in CRM and Marketing Pentaho
 
OPEN SOURCE BPM vs. Programación (RED HAT)
OPEN SOURCE BPM vs. Programación (RED HAT)OPEN SOURCE BPM vs. Programación (RED HAT)
OPEN SOURCE BPM vs. Programación (RED HAT)Kay Winkler
 

Similar to Stanford Case Study - Salesforce.com Transformation (20)

Do you need a new product development strategy
Do you need a new product development strategyDo you need a new product development strategy
Do you need a new product development strategy
 
Enterprise and Applications: Definition; Types; Challenges; Opportunities
Enterprise and Applications: Definition; Types; Challenges; OpportunitiesEnterprise and Applications: Definition; Types; Challenges; Opportunities
Enterprise and Applications: Definition; Types; Challenges; Opportunities
 
Gain new visibility in your DevOps team
 Gain new visibility in your DevOps team Gain new visibility in your DevOps team
Gain new visibility in your DevOps team
 
Manage in the Cloud: Prepare to be Future Ready
Manage in the Cloud: Prepare to be Future ReadyManage in the Cloud: Prepare to be Future Ready
Manage in the Cloud: Prepare to be Future Ready
 
HP Project and Portfolio Management
HP Project and Portfolio ManagementHP Project and Portfolio Management
HP Project and Portfolio Management
 
TitleABC123 Version X1Hewlett-Packard Case Study Anal.docx
TitleABC123 Version X1Hewlett-Packard Case Study Anal.docxTitleABC123 Version X1Hewlett-Packard Case Study Anal.docx
TitleABC123 Version X1Hewlett-Packard Case Study Anal.docx
 
Idc roi-of-building-apps-on-salesforce
Idc roi-of-building-apps-on-salesforceIdc roi-of-building-apps-on-salesforce
Idc roi-of-building-apps-on-salesforce
 
Salesforce_AnalysisFinalProject_Team6
Salesforce_AnalysisFinalProject_Team6Salesforce_AnalysisFinalProject_Team6
Salesforce_AnalysisFinalProject_Team6
 
Product Marketing, the Salesforce Way (October 13, 2014)
Product Marketing, the Salesforce Way (October 13, 2014)Product Marketing, the Salesforce Way (October 13, 2014)
Product Marketing, the Salesforce Way (October 13, 2014)
 
Nicholas Hoffmeyer - Adobe Systems - BL_S2_2016
Nicholas Hoffmeyer  - Adobe Systems - BL_S2_2016Nicholas Hoffmeyer  - Adobe Systems - BL_S2_2016
Nicholas Hoffmeyer - Adobe Systems - BL_S2_2016
 
Assessment Of An Enterprise-Level Business System
Assessment Of An Enterprise-Level Business SystemAssessment Of An Enterprise-Level Business System
Assessment Of An Enterprise-Level Business System
 
Mongo db better_faster_leaner
Mongo db better_faster_leanerMongo db better_faster_leaner
Mongo db better_faster_leaner
 
Lead User Innovation at Salesforce.com
Lead User Innovation at Salesforce.comLead User Innovation at Salesforce.com
Lead User Innovation at Salesforce.com
 
Market readiness levels
Market readiness levels Market readiness levels
Market readiness levels
 
Salesforce.com    January  2015  .docx
Salesforce.com    January  2015  .docxSalesforce.com    January  2015  .docx
Salesforce.com    January  2015  .docx
 
The Five Essential Truths of the Application Economy
The Five Essential Truths of the Application EconomyThe Five Essential Truths of the Application Economy
The Five Essential Truths of the Application Economy
 
Uses Of New And Emerging Technologies In Marketing Software
Uses Of New And Emerging Technologies In Marketing SoftwareUses Of New And Emerging Technologies In Marketing Software
Uses Of New And Emerging Technologies In Marketing Software
 
Embedded Analytics in CRM and Marketing
Embedded Analytics in CRM and Marketing Embedded Analytics in CRM and Marketing
Embedded Analytics in CRM and Marketing
 
Assignment 1
Assignment 1Assignment 1
Assignment 1
 
OPEN SOURCE BPM vs. Programación (RED HAT)
OPEN SOURCE BPM vs. Programación (RED HAT)OPEN SOURCE BPM vs. Programación (RED HAT)
OPEN SOURCE BPM vs. Programación (RED HAT)
 

More from Steve Greene

Comparing Agile transformation approaches at Twitter and Salesforce
Comparing Agile transformation approaches at Twitter and SalesforceComparing Agile transformation approaches at Twitter and Salesforce
Comparing Agile transformation approaches at Twitter and SalesforceSteve Greene
 
Successfully Scaling an Agile Innovation Culture with Perforce - 2011 Perforc...
Successfully Scaling an Agile Innovation Culture with Perforce - 2011 Perforc...Successfully Scaling an Agile Innovation Culture with Perforce - 2011 Perforc...
Successfully Scaling an Agile Innovation Culture with Perforce - 2011 Perforc...Steve Greene
 
Dreamforce 2010 - Agile Development for Force.com
Dreamforce 2010 - Agile Development for Force.comDreamforce 2010 - Agile Development for Force.com
Dreamforce 2010 - Agile Development for Force.comSteve Greene
 
Dreamforce Executive Summit - Accelerating Innovation and Growth
Dreamforce Executive Summit  - Accelerating Innovation and GrowthDreamforce Executive Summit  - Accelerating Innovation and Growth
Dreamforce Executive Summit - Accelerating Innovation and GrowthSteve Greene
 
Agile 2010 conference - a holistic approach to scaling agile at salesforce
Agile 2010 conference - a holistic approach to scaling agile at salesforceAgile 2010 conference - a holistic approach to scaling agile at salesforce
Agile 2010 conference - a holistic approach to scaling agile at salesforceSteve Greene
 
Transforming Your Organization to Agile
Transforming Your Organization to AgileTransforming Your Organization to Agile
Transforming Your Organization to AgileSteve Greene
 
Dreamforce 2009: IT Success with Agile Development Processes
Dreamforce 2009: IT Success with Agile Development ProcessesDreamforce 2009: IT Success with Agile Development Processes
Dreamforce 2009: IT Success with Agile Development ProcessesSteve Greene
 
Dreamforce 2009: Behind-the-Scenes at Salesforce.com: Delivering 3 Major Rele...
Dreamforce 2009: Behind-the-Scenes at Salesforce.com: Delivering 3 Major Rele...Dreamforce 2009: Behind-the-Scenes at Salesforce.com: Delivering 3 Major Rele...
Dreamforce 2009: Behind-the-Scenes at Salesforce.com: Delivering 3 Major Rele...Steve Greene
 
Weird Myths In Business
Weird Myths In BusinessWeird Myths In Business
Weird Myths In BusinessSteve Greene
 
Agile Development Meets Cloud Computing for Extraordinary Results at Salesfor...
Agile Development Meets Cloud Computing for Extraordinary Results at Salesfor...Agile Development Meets Cloud Computing for Extraordinary Results at Salesfor...
Agile Development Meets Cloud Computing for Extraordinary Results at Salesfor...Steve Greene
 
Agile Survey Sample
Agile Survey SampleAgile Survey Sample
Agile Survey SampleSteve Greene
 
Unleashing The Fossa Agile Leadership Summit 2009
Unleashing The Fossa   Agile Leadership Summit 2009Unleashing The Fossa   Agile Leadership Summit 2009
Unleashing The Fossa Agile Leadership Summit 2009Steve Greene
 
Dependency Management In A Large Agile Environment
Dependency Management In A Large Agile EnvironmentDependency Management In A Large Agile Environment
Dependency Management In A Large Agile EnvironmentSteve Greene
 
Q Con 2008 - Unleashing the Fossa
Q Con 2008 - Unleashing the FossaQ Con 2008 - Unleashing the Fossa
Q Con 2008 - Unleashing the FossaSteve Greene
 
Dreamforce 2008 : Transforming IT Success with Agile Development Processes
Dreamforce 2008 : Transforming IT Success with Agile Development ProcessesDreamforce 2008 : Transforming IT Success with Agile Development Processes
Dreamforce 2008 : Transforming IT Success with Agile Development ProcessesSteve Greene
 
Agile Leadership Summit: Unleashing The Fossa : Scaling Agile in an Ambitious...
Agile Leadership Summit: Unleashing The Fossa : Scaling Agile in an Ambitious...Agile Leadership Summit: Unleashing The Fossa : Scaling Agile in an Ambitious...
Agile Leadership Summit: Unleashing The Fossa : Scaling Agile in an Ambitious...Steve Greene
 
Dreamforce 2008 : Behind-the-Scenes @ Salesforce.com R&D: How We Deliver 3 Ma...
Dreamforce 2008 : Behind-the-Scenes @ Salesforce.com R&D: How We Deliver 3 Ma...Dreamforce 2008 : Behind-the-Scenes @ Salesforce.com R&D: How We Deliver 3 Ma...
Dreamforce 2008 : Behind-the-Scenes @ Salesforce.com R&D: How We Deliver 3 Ma...Steve Greene
 
Large Scale Agile Transformation in an On-Demand World
Large Scale Agile Transformation in an On-Demand WorldLarge Scale Agile Transformation in an On-Demand World
Large Scale Agile Transformation in an On-Demand WorldSteve Greene
 
Writing within an Agile Development Environment
Writing within an Agile Development EnvironmentWriting within an Agile Development Environment
Writing within an Agile Development EnvironmentSteve Greene
 
The Doctor is “In” : Using the Office Hours Concept to Make Limited Resources...
The Doctor is “In” : Using the Office Hours Concept to Make Limited Resources...The Doctor is “In” : Using the Office Hours Concept to Make Limited Resources...
The Doctor is “In” : Using the Office Hours Concept to Make Limited Resources...Steve Greene
 

More from Steve Greene (20)

Comparing Agile transformation approaches at Twitter and Salesforce
Comparing Agile transformation approaches at Twitter and SalesforceComparing Agile transformation approaches at Twitter and Salesforce
Comparing Agile transformation approaches at Twitter and Salesforce
 
Successfully Scaling an Agile Innovation Culture with Perforce - 2011 Perforc...
Successfully Scaling an Agile Innovation Culture with Perforce - 2011 Perforc...Successfully Scaling an Agile Innovation Culture with Perforce - 2011 Perforc...
Successfully Scaling an Agile Innovation Culture with Perforce - 2011 Perforc...
 
Dreamforce 2010 - Agile Development for Force.com
Dreamforce 2010 - Agile Development for Force.comDreamforce 2010 - Agile Development for Force.com
Dreamforce 2010 - Agile Development for Force.com
 
Dreamforce Executive Summit - Accelerating Innovation and Growth
Dreamforce Executive Summit  - Accelerating Innovation and GrowthDreamforce Executive Summit  - Accelerating Innovation and Growth
Dreamforce Executive Summit - Accelerating Innovation and Growth
 
Agile 2010 conference - a holistic approach to scaling agile at salesforce
Agile 2010 conference - a holistic approach to scaling agile at salesforceAgile 2010 conference - a holistic approach to scaling agile at salesforce
Agile 2010 conference - a holistic approach to scaling agile at salesforce
 
Transforming Your Organization to Agile
Transforming Your Organization to AgileTransforming Your Organization to Agile
Transforming Your Organization to Agile
 
Dreamforce 2009: IT Success with Agile Development Processes
Dreamforce 2009: IT Success with Agile Development ProcessesDreamforce 2009: IT Success with Agile Development Processes
Dreamforce 2009: IT Success with Agile Development Processes
 
Dreamforce 2009: Behind-the-Scenes at Salesforce.com: Delivering 3 Major Rele...
Dreamforce 2009: Behind-the-Scenes at Salesforce.com: Delivering 3 Major Rele...Dreamforce 2009: Behind-the-Scenes at Salesforce.com: Delivering 3 Major Rele...
Dreamforce 2009: Behind-the-Scenes at Salesforce.com: Delivering 3 Major Rele...
 
Weird Myths In Business
Weird Myths In BusinessWeird Myths In Business
Weird Myths In Business
 
Agile Development Meets Cloud Computing for Extraordinary Results at Salesfor...
Agile Development Meets Cloud Computing for Extraordinary Results at Salesfor...Agile Development Meets Cloud Computing for Extraordinary Results at Salesfor...
Agile Development Meets Cloud Computing for Extraordinary Results at Salesfor...
 
Agile Survey Sample
Agile Survey SampleAgile Survey Sample
Agile Survey Sample
 
Unleashing The Fossa Agile Leadership Summit 2009
Unleashing The Fossa   Agile Leadership Summit 2009Unleashing The Fossa   Agile Leadership Summit 2009
Unleashing The Fossa Agile Leadership Summit 2009
 
Dependency Management In A Large Agile Environment
Dependency Management In A Large Agile EnvironmentDependency Management In A Large Agile Environment
Dependency Management In A Large Agile Environment
 
Q Con 2008 - Unleashing the Fossa
Q Con 2008 - Unleashing the FossaQ Con 2008 - Unleashing the Fossa
Q Con 2008 - Unleashing the Fossa
 
Dreamforce 2008 : Transforming IT Success with Agile Development Processes
Dreamforce 2008 : Transforming IT Success with Agile Development ProcessesDreamforce 2008 : Transforming IT Success with Agile Development Processes
Dreamforce 2008 : Transforming IT Success with Agile Development Processes
 
Agile Leadership Summit: Unleashing The Fossa : Scaling Agile in an Ambitious...
Agile Leadership Summit: Unleashing The Fossa : Scaling Agile in an Ambitious...Agile Leadership Summit: Unleashing The Fossa : Scaling Agile in an Ambitious...
Agile Leadership Summit: Unleashing The Fossa : Scaling Agile in an Ambitious...
 
Dreamforce 2008 : Behind-the-Scenes @ Salesforce.com R&D: How We Deliver 3 Ma...
Dreamforce 2008 : Behind-the-Scenes @ Salesforce.com R&D: How We Deliver 3 Ma...Dreamforce 2008 : Behind-the-Scenes @ Salesforce.com R&D: How We Deliver 3 Ma...
Dreamforce 2008 : Behind-the-Scenes @ Salesforce.com R&D: How We Deliver 3 Ma...
 
Large Scale Agile Transformation in an On-Demand World
Large Scale Agile Transformation in an On-Demand WorldLarge Scale Agile Transformation in an On-Demand World
Large Scale Agile Transformation in an On-Demand World
 
Writing within an Agile Development Environment
Writing within an Agile Development EnvironmentWriting within an Agile Development Environment
Writing within an Agile Development Environment
 
The Doctor is “In” : Using the Office Hours Concept to Make Limited Resources...
The Doctor is “In” : Using the Office Hours Concept to Make Limited Resources...The Doctor is “In” : Using the Office Hours Concept to Make Limited Resources...
The Doctor is “In” : Using the Office Hours Concept to Make Limited Resources...
 

Stanford Case Study - Salesforce.com Transformation

  • 1. Raymond E. Levitt Chris Fry Steve Greene Colleen Kaftan Salesforce.com: The Development Dilemma Steve Greene and Chris Fry left their August, 2006 meeting with Parker Harris carrying a far bigger mandate than they had hoped for. As program and development managers, respectively, they had proposed a pilot project to test a radically different approach to software development at Salesforce.com. Founded in 1999 to build a new market in subscription enterprise software services, the company had experienced annual growth rates of 30 to 40 percent, both in customer usage and in head count. Revenues had been growing at more than 80 percent per year, and net income faster than that. But the critical software development function was faltering, even as revenues seemed poised to reach nearly half a billion dollars for 2006. The existing development processes had been slipping for some time. The pace of releases of new software features—a key measure of value for customers—had slowed from four times per year to once per year, and the latest release was taking even longer than that. Morale was suffering across the organization, and a highly respected senior developer had recently quit after delivering a scathing offsite presentation that criticized nearly everything about the current situation. Furthermore, an infrastructure failure had caused service outages that prevented customers from accessing their customer information during the critical pre-holiday period in 2005. Another outage in early 2006 further eroded users’ trust in the reliability of Salesforce.com’s software service capabilities. Harris, one of four Salesforce.com founders and currently EVP-Technology & Products, agreed with Fry and Greene that something had to change. But whereas Fry and Greene wanted to start small and pilot the new method before rolling it out on a larger scale, Harris was thinking big. He’d listened to their description of “agile” or “scrum” development processes compared to the traditional “waterfall” approach, asked a lot of questions, and then instructed them to implement the new method throughout the R&D organization. “We need real change,” he said. “Let’s skip the pilot and go for the big bang. Our system is broken, and we don’t have time to wait—so let’s go ahead and fix it all at once.” Professor Raymond E. Levitt, Chris Fry and Steve Greene of Salesforce.com, and Colleen Kaftan prepared this case under the auspices of the Stanford Collaboratory for Research on Global Projects. CRGP cases are developed solely as the basis for classroom discussion, and are not intended to serve as endorsements, primary data sources, or illustrations of either effective or ineffective management practices. Copyright © 2009 Stanford Collaboratory for Research on Global Projects, Stanford, California.
  • 2. Company Background: The End of Software Revolution Harris and his co-founders, led by CEO Marc Benioff, proclaimed the 1999 advent of Salesforce.com as the “End of Software Revolution.” 1 After a 13-year career at Oracle, the giant enterprise software vendor, Benioff wanted to turn the prevailing enterprise software deployment model on its head. Instead of designing and installing complex, customized software systems and applications to help companies manage various aspects of their activities, Salesforce.com introduced “software as a service” in which customers used web browsers to access centrally managed software applications designed to help run their businesses over the Internet. Later shortened to SaaS (pronounced “sass”), this new model offered significant upfront cost savings for customers who no longer had to purchase, install, and maintain their own customized enterprise software. Instead, they could pay a monthly fee for hosted services, beginning with Salesforce.com’s standard customer relationship management (CRM) programs, which users could shape to fit each company’s needs. The new paradigm also came to be called “software on demand” and “software as a utility” for its subscriber- based, externally maintained and broadly distributed availability. The Salesforce.com logo featured the word “Software” with a slash through it, in the fashion of a “No Entry” sign. The model proved immediately attractive to customers. By January 2001, Salesforce.com counted 1,500 customers, 30,000 subscribers, and 10 internal R&D staff. In 2005, with total revenues above $175 million and net income of nearly $7.5 million, there were some 29,000 customers, 650,000 subscribers, and 200 R&D staff —and the numbers continued to grow. Its IPO in the summer of 2004 set the company’s market value at more than a billion dollars. (Exhibit 1 diagrams the Salesforce.com organization in 2006.) Analysts and other observers cited Salesforce.com as a classic example of disruptive innovation—a new concept, technology, value proposition, or approach to a market that profoundly alters the competitive landscape. 2 Disruptive technologies were typically cheaper, simpler, and less fully developed than existing mainstream offerings. Their initial customers were those who preferred low cost and ease of use over complex, over- performing products and systems. The challenge for disruptive innovators was to maintain their ability to innovate as they grew larger and more successful. Salesforce.com’s 2005 launch of Force.com, a hosted platform for developing applications on the Internet, opened the gate for customers and third-party developers to create new applications using the Salesforce.com platform. In short order, hundreds of new applications became available for integrating other management tools with existing Salesforce software. And until recently, Salesforce.com had been releasing new user functionality on a regular basis. 1 http://www.salesforce.com/company/milestones, accessed October, 2008. 2 Clayton M. Christensen articulated the concept of disruptive innovation in The Innovator’s Dilemma: When New Technologies Cause Great Firms to Fail (HPSP, 1997), and elaborated it along with his colleagues in many subsequent publications, courses, and analytical tools. 2
  • 3. By 2006, several other nascent applications service providers had followed Salesforce.com into the market for hosted CRM software, but their combined operations were estimated to reach only about five percent of the traditional CRM market. So there was plenty of room for continuing growth—but would Salesforce.com be capable of prospering as a much larger company? Fry and Greene—and many of their colleagues— thought the answer might depend on finding a way to fix the software development process. The Evolution of Project Management Methodology Salesforce.com’s development process was an offshoot of traditional project management methodology, which had evolved from the tools and processes used for getting work done in the construction, aerospace, and pharmaceuticals industries beginning in the 1950s. 3 In these industries, project management developed largely as a discipline for planning and executing lengthy, complex one-off initiatives such as dams, highways, new aircraft or nuclear submarines, or new drug therapies. In relatively stable market and technological contexts, such projects and programs could be meticulously laid out in advance, and implemented by strict adherence to plan. Detecting, documenting, and correcting any deviations from the plan were critical management functions. 4 The 1990s movement toward reengineering the corporation used project management practices to standardize and simplify smaller, repetitive tasks throughout an organization. 5 Reengineering suggested that each task should have an identified customer, suppliers, and an owner responsible for managing it to achieve a set of schedule and quality metrics. It created accountability and focus for cross-functional tasks, such as processing insurance claims or bank loan applications, that needed to flow through multiple departments in large bureaucratic organizations. This approach proved valuable in standardizing and simplifying workflows, developing a customer focus, and creating a single point of accountability for critical tasks that could otherwise get logjammed amidst the parochial priorities of individual departments. At the dawn of the twenty-first century, global competition and the speedy spread of knowledge brought a new type of project management challenge, as firms from rich, high-wage countries scrambled to develop differentiated offerings in rapidly commoditizing industries. Many traditional high-tech manufacturers and service providers responded by shifting from making and selling standard sets of products to delivering more sophisticated custom solutions, uniquely crafted and integrated to meet 3 This section draws on Raymond Levitt, Lecture Notes from Converting Strategy Into Action, Stanford Advanced Project Management executive program. See http://apm.stanford.edu. 4 The tools and processes for doing so were encoded in the Project Management Body of Knowledge (PMBOK), an internationally recognized standard for professional certification maintained by the Project Management Institute. 5 See, for example, Michael Hammer and James Champy, Reengineering the Corporation: A Manifesto for Business Revolution (New York: HarperBusiness, 2001), and Thomas H. Davenport, Process Innovation: Reengineering Work Through Information Technology (Boston: Harvard Business School Press, 1993). 3
  • 4. each customer’s specific needs. Others focused on developing a capacity for continuous product innovation. A few brave competitors opted to offer both innovative products and integrated solutions, with all the organizational complexities such a dual strategy implied. The new array of project challenges ranged from large, complex, initiatives to smaller concurrent daily operational improvements. The single common denominator was the pace of competition. The most dynamic firms in the fastest growing sectors of the global economy—semiconductors, computers, financial services, IT, and non-profits, for example—needed a discipline for managing large numbers of big and small projects in rapidly changing markets and technologies. Product, project, and program managers needed a more flexible, process-light framework in which to apply their organizational methods and tools. The big CRM solutions companies adopted a “waterfall” approach to software development, which—while more nimble than the traditional aircraft, construction, and pharmaceutical industry methodologies—still relied on the sequential performance of largely separate functional activities, based on a predefined plan and budget. Project priorities were established centrally, usually by customer-facing product managers who determined user needs and then worked across functional lines to push the project forward. Exhibit 2 shows the typical sequence of functional activities in waterfall development. Perils of Growth at Salesforce.com Salesforce.com started out with what Parker Harris called a much more organic development organization, with a small group of people collaborating closely on each release. As the company grew, however, it gravitated naturally toward the phased waterfall development model. But as had become apparent over the years, any change or deviation to the original plan interrupted progress and delayed the target release date. Parker Harris described the progression since the early days: We started out as a small team—like 15 people in the early years. A team like that doesn’t really need a lot of process. We were doing releases or upgrading our service as frequently as possible. So when we started the company, we upgraded every four weeks, and then six weeks, and over the years that slowed down, so it’s been almost four times a year, and then it was two times a year, and then it was once a year. Harris recalled how the development process evolved: We were perfecting processes as we grew. So we said, OK—we’ll definitely need to have a really good section in there for localization, we need to make sure we do usability, and let’s add load/stress testing. We added these things simply because they were important, and our customers were looking for more quality, more performance. We also added people, so the team grew significantly. And what used to be an organic process because we just iterated and that was the natural thing to do, as we added 4
  • 5. all these other things we had to do, it grew into this more waterfall process, where everything went down the line. The R&D group eventually organized around “feature teams”—project groups who were assigned to develop centrally-designated user capabilities. Whenever the product managers identified a desirable feature to develop, they would assign people from across the functions to the team charged with building it. People were often assigned to several teams at once, and many had trouble prioritizing their work across teams. By the time Steve Greene and Chris Fry came to Salesforce.com in early 2005, the R&D headcount had grown to well over 150. Fry described one drawback he observed in the feature team model: There’d be a weekly meeting for each team. Everyone would show up and discuss all the problems for an hour, and then just go back to their desks. There was no accountability. You’d go to all the feature team meetings you were assigned to, and the next week you’d go back and say, “What was it I promised to do?” And nobody was tracking if you were on 20 teams or just one. Steve Greene elaborated: So basically, you’re pushing prioritization down to the individual contributors, because they’re on five teams and they would decide—on a daily basis—what’s the most important thing, and there’d be confusion across the organization because everybody had a different idea of what the highest priority was. And management didn’t have visibility into this, because they couldn’t attend the 20 meetings every week. Parker Harris began to notice other problems with the feature team / waterfall approach: We’d set formal user expectations and then product management would build a prototype and write a functional spec. Development would then write a technical spec, and on down the line. The timelines were fixed, and everybody would end up padding their estimates and still being late, and then blaming the delay on other people upstream in the process. At the end, everyone blamed QA [quality assurance], because QA is at the end of the waterfall. Then everyone started pointing fingers at each other, and it also caused really weird behavior where people would work outside the process: “Maybe I shouldn’t pay attention to this process, and just be late with my stuff—the release won’t go out without it, and if my area’s late, maybe we’ll get more attention later on”…and so on. By summer of 2006, the R&D headcount reached nearly 300. Many new hires came from bigger companies such as SAP, with centralized approaches to software development. They brought with them a big company culture, according to Steve Greene, so that by mid-2006, even though Salesforce.com was considerably smaller than most of its competitors, “We were having just as much difficulty delivering releases as the big 5
  • 6. companies were.” Case in point: the schedule for Release 144 had already slipped several times, and some of the features were still not ready for shipping. Greene described the internal effect of the delay: We had huge morale problems. Because if you’re a technologist, you want to build something useful, and you want to get it out there to your customers to use as quickly as possible. You don’t want to just talk about it. And we had people who had been at salesforce more than a year— people we hired from larger organizations, with the promise that they could accomplish things quickly here—some of them had never actually released a feature to production. Fry agreed: The institutional knowledge of how to do releases wasn’t as strong as it should be. And our development people like to create things that people use, but we weren’t getting that positive feedback into the team, so there was low morale across the board. On the customers’ side, the service outages of late 2005 and early 2006 exacerbated the development issues. Customers depended on “dial-tone reliability” for on-demand services, and when they were unable to access their data, they began to question the new business paradigm. If Salesforce.com couldn’t assure customers of reliable service, and couldn’t even deliver new features on a regular basis, why should any customer base its operations on the hosted services model? The Shinkansen Project In summer of 2006, Parker Harris asked Steve Greene and Chris Fry to explore the “release train” development model that many considered to be the driving force behind the rapid development capabilities at eBay. To underscore the ugency of speeding up Salesforce.com’s development process, the three named their initiative Shinkansen, after the famed Japanese bullet trains—arguably, along with France’s TGV and Germany’s ICE, the fastest in the world. An eBay-commissioned joint benchmarking study in 2006-2006 described the release train system as follows: As the term implies, this process is like a train that has a fixed number of seats for passengers and a pre-set schedule. Companies decide in advance the number of releases they’d like to issue each year, as well as the size of each release. The release size is usually based on the required level of effort as defined by person days, or “developer days.” Teams of developers work furiously to complete their new products in time for a 6
  • 7. certain release train. If they miss the train, they must wait for the next release. 6 Release trains departed every two weeks on schedule at eBay. When a releasable feature made it onto the train, it would then integrate with other new features and the existing platform much as rail cars couple together, and undergo extensive quality testing. This late integration model proved less attractive for Salesforce.com, in part because the company had recently developed an automated testing capability for continuous integration of most new code. The developers were responsible for testing and integrating whatever fell outside the automated process. Many considered this capability to be an important competitive weapon for Salesforce.com. Fry and Greene also encountered widespread resistance to the idea of an externally- developed process imposed from on high. After three months of trying to plan how to introduce the release train methodology, the project group decided to abandon the cause. On the heels of this less-than-promising endeavor, Greene and Fry decided to propose an “agile” development approach in August 2006. Both were familiar with the method, but they did further research to prepare a detailed description for Harris, and set off to persuade him to try it. If Harris agreed, they hoped to turn the Shinkansen team into an agile development team. Background on the Principles of Agile Development Fry and Greene began by summarizing the history of agile methods for Harris. The Agile movement represented a philosophy and a shared language as well as an approach to software development. Rooted in the 1980s concepts of lean manufacturing and product development, it had evolved to fit the software development challenges of the early 2000s. 7 Extreme Programming (XP), Scrum, and Lean were similar approaches often subsumed under the Agile umbrella. (Exhibit 3 lists “Twelve Principles of Agile Software,” along with the “Manifesto for Agile Software Development,” both authored in 2001 by a large group of professional developers.) Key Concepts Agile methodology specifically targeted product developers’ needs in fast-moving markets. It used standing cross-functional “scrum teams” to turn out frequent, incremental, and potentially releasable features on a regular basis, commonly after a month-long “sprint.” A full-blown release might incorporate three one-month sprint 6 http://www.prtm.com/uploadedFiles/Strategic_Viewpoint/Articles/Article_Content/PRTM_eBay_benchm arking.pdf 7 Information in this section comes from many sources, including K. Beck, Extreme Programming Explained (Addison Wesley, 2000), M. Poppendieck and T. Poppendieck, Lean Software Development (Addison Wesley, 2003), and M. Cohn and D. Ford, “Introducing an Agile Process to an Organization,” Computer, June 2003, pp. 74-78. See also http://www.mountaingoatsofware.com/daily_scrum 7
  • 8. cycles, each of which followed a specific rhythm. (Exhibit 4 charts the activities in a typical sprint-to-release calendar. Exhibit 5 distills the scrum lifecycle.) Every thirty-day sprint began with a planning meeting, in which a product owner identified desirable features, or a product backlog of “user stories,” in order of priority. (A typical user story might read, “I can predict customer purchasing patterns,” or “I can compile hourly sales by distribution channel.”) The scrum team evaluated the backlog list, agreed on the number of top priority items they could deliver during the sprint, and committed to doing so. Once that commitment was in place, no further requirements or changes could be introduced during the month-long sprint. The scrum team of no more than 12 people—including product managers, developers, quality engineers, user experience designers, usability testers and technical writers—worked together every day to accomplish their sprint commitments. They used highly visible shared tools, such as wall-mounted task boards and Excel spreadsheets, to keep track of their progress in completing the tasks in a “release burndown.” Team members who had completed their tasks would step in to assist other team members who needed help completing their tasks. Each 30-day sprint ended with a sprint review, in which team members demonstrated their accomplishments to the team and management during the sprint. Sprint reviews were meant to be simple, natural discussions of new capabilities, rather than highly prepared formal presentations. This reinforced the Agile principle of only including code that is truly “done”—i.e., coded, usability tested, QA tested and documented, and thus ready to be integrated into the next release. The objective was to “deliver fast and deliver early,” while avoiding the typical scope creep and roadblocks that tended to plague extended waterfall development projects. Every sprint could produce shippable capabilities, whether the company was ready to release them or not. One intended side effect was to eliminate the crisis management and panic associated with more ambitious, sequential, waterfall-based feature releases with lengthy (and often unpredictable) development calendars. Roles and Rituals Agile processes required designating a product owner, a scrum master, and scrum team members (often for multiple teams coordinated by a “scrum of scrums”) for each sprint. People tended to stay in these roles over time, so that working relationships and team procedures could evolve to fit the team members’ preferences and the requirements of their specific tasks. Perhaps the most critical daily event for a scrum team was a short morning “stand-up” meeting—typically lasting no more than about 15 minutes—which set the context for the coming day’s work. These meetings were held at the same time and the same location every day, and were open to anyone who wanted to attend. There was a strict distinction between those who were “involved” and those who were “committed” in terms of their rights to participate in the meetings. Scrum experts used a chicken and pig metaphor to describe the difference: 8
  • 9. There is an old joke in which a chicken and pig are talking and the chicken says, “Let’s start a restaurant.” The pig relies, “Good idea, but what should we call it?” “How about ‘Ham and Eggs?’” says the chicken. “No thanks, says the pig, “I’d be committed, you’d only be involved.” Only committed scrum team members were allowed to talk at daily meetings. Each one had to answer just three questions, designed to reinforce team commitments and remove roadblocks: • What did I do yesterday? • What will I do today? • What is blocking me—i.e., what impediments are in my way? The scrum master’s job was to remove the impediments every day, so that the team could meet its sprint commitments. Allowing “chickens” to listen in on daily meetings was meant to promote visibility throughout the organization without impeding the teams’ work. Risks of a Large-Scale Rollout Greene and Fry were pleased with Harris’s strong endorsement of their proposal and with the mandate to “make it happen” throughout Salesforce.com. However, they both remarked that large-scale implementation of the new methodology seemed much riskier than trying a pilot project. They hated to think about the consequences of another failed attempt to change the development process at Salesforce.com—especially if that failure was organization-wide and highly visible rather than small-scale and contained. Yet it seemed as though they had already hit a low point with the aborted Shinkansen project and the delay of Release 144. Could things get any worse? Maybe they could. For one thing, no one had ever adopted Agile methods on such a large scale before. Even one of the most prominent experts in the field declined to participate as a consultant, citing the long odds against a “big bang” rollout. Another suggested that to make the change on such a broad scale might be possible, but only with extensive (and expensive) outside help. Moreover, it was hard to imagine that anybody at Salesforce.com would be interested in a process dictated from above. The senior developers in particular were skeptical of any process or reporting requirements that would take them away from their “real” work. And the Shinkansen project had underscored the not-invented-here mentality that reigned among Salesforce.com’s talented development team. Any major new program would certainly meet great resistance unless the developers could call it their own. But Parker Harris stood firmly behind the big bang initiative. He wanted Fry and Greene to design and roll out their own version of Agile methodology for Salesforce.com—a hybrid of the existing approaches tailored to the needs, temperament, and circumstances of the in-house developers—and he wanted them to figure out how to do the necessary training internally. 9
  • 10. Was Harris correct in suggesting they could do it without outside help from consultants? And would any developers agree to devote their time and energy to a changeover, with Release 144 still stuck in project management limbo? As they thought about how to proceed, Fry and Greene recalled Harris’s comment at their August meeting: “Salesforce.com hasn’t made a big investment in processes because we haven’t known which processes to implant.” If Harris was so sure that the Agile was best, how much of the company’s time, energy, and money could they expect him to invest into making it work? Moving Ahead with ADM Greene and Fry assembled a cross-functional rollout team and adopted an agile approach to the implementation. Members of the implementation team attended outside Scrum Master Training programs to learn about the methodology they would soon be modeling for the rest of the development group. The new team decided to use an Agile-type process to “burn down the bugs” in the long- overdue Release 144. From one day to the next, they would introduce the new methodology throughout the R&D organization by showing everyone how to apply this new approach to development on a pressing problem. In the process of adopting Agile methods, they also intended to customize the approach to fit the Salesforce.com organization. Their home-grown version would be known as Agile Development Methodology, or ADM. They divided the broader development organization into some 30 scrum teams, each with six to ten members. The rollout team held 45 one-hour meetings to introduce the new methodology, and proposed to accomplish the bug-burndown for Release 144 in three one-month sprints. All subsequent meetings welcomed open attendance, but only committed team members were allowed to speak. Managers from other areas had a hard time not chiming in, so the scrum masters and team members frequently evoked the chicken-and-pig rule. But just having managers in the room seemed unusual to many developers, and some claimed to resent it. As part of the new ADM approach, “drive bys”—managers poking their heads into developers’ offices to request new features or requirements that they wanted—were outlawed. Parker Harris worked hard to reinforce this prohibition on drive-bys to change the culture of top down opportunistic “software redesign” at Salesforce.com. Early Progress Report From the outset, the rollout team encountered both enthusiasm and resistance. Some developers were relieved to find a process that might help them turn out useful features in a timely manner. Several willingly volunteered to invest their time in helping their colleagues get comfortable with ADM. Parker Harris himself promised to be an evangelist for the process, and he directed the company’s project management office to support the initiative to the fullest. But there were detractors as well. Within a few weeks, the early enthusiasts collected a list of negative comments from their colleagues, including the following: 10
  • 11. “Scrum doesn’t account for the fact or the reality of the waterfall. You cannot deny this by superimposing scrum over it.” • “It seems like we spend more time talking about scrum…than we spend time talking about and working on salesforce.com.” • “In many ways, scrum seems like an inflexible, bureaucratic process akin to something at the Department of Motor Vehicles.” • “Management is not proactive as we wait for decisions…Scrum gives me the feeling that Big Brother is watching and monitoring everything we do.” • “The lingo is ridiculous!” • “Ditch the stupid, annoyingly dumb Excel spreadsheet!” • “Stop trying to implement scrum, and look at how many releases we can really do in a year.” To make matters worse, by the middle of the third sprint in December 2006, it was obvious that the teams would not be able to complete all the prioritized features for Release 144. This created a dilemma for Greene and Fry: should they finish the sprint on time, and deploy what was “done” and releasable, or should they ask Parker Harris and the executive team for a delay? What Next? On the one hand, to push the release out yet again could undermine the message that Salesforce.com really intended to implement ADM throughout the R&D organization and beyond. But to demo an incomplete set of features might introduce ADM in less than favorable light. Would ADM then go the way of Shinkansen and other failed initiatives? If so, what would be the consequences, internally and in the marketplace? Most people involved in the rollout believed that they could use the ADM process to teach, adapt, and reinforce ADM itself. This would take time—probably measured in multiple sprints. But where should they go from here? How should they identify the priorities for each successive sprint? For example, should they focus on bringing the most resistant, poor-performing groups up to speed, or start with the ones that were doing somewhat better and eager to learn more? Would it be better to have most groups performing adequately, or should they work on creating a few “stars” to serve as examples for the rest of the organization? And would Salesforce.com be able to keep adapting ADM to meet the needs of the organization as it continued to grow? Finally, and more immediately, how should they handle Release 144—not to mention 146, 148, and others still to come? Fry and Greene thought the company’s continued success could depend on making sure they were asking the right questions, and then getting the answers right. 11
  • 12. Salesforce.com: The Development Dilemma Exhibit 1: Salesforce.com Organization Chart, 2006 SFDC Organization Chart - 2006 Marc Benioff, CEO EVP Marketing Parker Harris, EVP Technology SVP Applications Product Mgmt SVP Platform Product Mgmt SVP Development SVP QE SVP Program Mgmt Senior Director UI Chris Fry VP Applications Senior Director VP Quality Steve Greene Core Pgm Mgmt Platform Program Applications VP Platform Core Assurance Senior Director, Mgmt Program Mgmt Tools & Agile Documentation Usability Process Manager Manager Applications SoS Platform SoS Core SoS Apex Sandbox … API Core Automation … Systest CRM SFA … Content Source: Company documents. 12
  • 13. Salesforce.com: The Development Dilemma Exhibit 2: Chart of Waterfall Development Process Waterfall Software Development Process Source: Company documents. 13
  • 14. Salesforce.com: The Development Dilemma Exhibit 3: 12 Principles of Agile Software and Manifesto for Agile Software Development We follow these Twelve Principles of Agile Software: • Our highest priority is to satisfy the customer through early and continuous delivery of valuable software. • Welcome changing requirements, even late in development. Agile processes harness change for the customer's competitive advantage. • Deliver working software frequently, from a couple of weeks to a couple of months, with a preference to the shorter timescale. • Business people and developers must work together daily throughout the project. • Build projects around motivated individuals. Give them the environment and support they need, and trust them to get the job done. • The most efficient and effective method of conveying information to and within a development team is face-to-face conversation. • Working software is the primary measure of progress. • Agile processes promote sustainable development. The sponsors, developers, and users should be able to maintain a constant pace indefinitely. • Continuous attention to technical excellence and good design enhances agility. • Simplicity--the art of maximizing the amount of work not done--is essential. • The best architectures, requirements, and designs emerge from self-organizing teams. • At regular intervals, the team reflects on how to become more effective, then tunes and adjusts its behavior accordingly. Manifesto for Agile Software Development We are uncovering better ways of developing software by doing it and helping others do it. Through this work we have come to value: Individuals and interactions over processes and tools Working software over comprehensive documentation Customer collaboration over contract negotiation Responding to change over following a plan That is, while there is value in the items on the right, we value the items on the left more. Kent Beck, Mike Beedle, Arie van Bennekum, Alistair Cockburn, Ward Cunningham, Martin Fowler, James Grenning, Jim Highsmith, Andrew Hunt, Ron Jeffries, Jon Kern, Brian Marick, Robert C. Martin, Steve Mellor, Ken Schwaber, Jeff Sutherland, Dave Thomas. © 2001, the above authors. This declaration may be freely copied in any form, but only in its entirety through this notice. Source: http://www.agilemanifesto.org/ 14
  • 15. Salesforce.com: The Development Dilemma Exhibit 4: Diagram of Sprint and Scrum Activities Source: Company documents. 15
  • 16. Salesforce.com: The Development Dilemma Exhibit 5: The Scrum Lifecycle Scrum Lifecycle Daily Scrum Meeting Product Sprint Sprint Review: Backlog Backlog Demo Potentially Releasable New Functionality Retrospective Source: Company documents. 16