A GUIDE TO BS8534 ON PROCUREMENT
SARAH FOX
500 Words Ltd
(2015)
Page 2 ©500 Words Ltd, 2015
British Standard BS 8534:2011 on Procurement
A guide to help you understand best practice in construction procurement
On 25 September 2011, Constructing Excellence1
and the British Standards Institute
launched a new British Standard, BS8534 titled “Construction procurement policies,
strategies and procedures – code of practice.” This new standard arose from the 2008
Constructing Excellence and BSI Report “Rethinking Standards in Construction” whose
principal recommendation was to develop a new standard on construction procurement.
At the same time, the International Standards Organisation, ISO, developed two
complementary procurement standards whose main objective was the creation of a
framework to facilitate fair competition, reduces the possibility of abuse, improves the
predictability of outcome and allows the demonstration of best value. IS10845 comes in two
parts:
 Part 1: processes, methods and procedures;
 Part 2: formatting and compilation of procurement documentation.2
The difference is that BS8534 is more strategic (with its recommendation on developing
strategies and policies) and ISO10845 is more operational (as it describes processes,
methods and procedures for a procurement system).
The scope of the new British Standard is to “give recommendations and guidance on the
development within a public or private sector organisation of policies, strategies and
procedures for the procurement of construction in the built environment.”
It is based on this procurement cycle:
It covers both procurement policy3
and strategy. It requires procurers
to consider best practice on
relevant topics in determining a
suitable policy.
A procurement strategy is ‘a plan
of action for funding, organisation,
management, selection and
payment of supply chains for the
design, fabrication and which may
include the operation of
constructed facilities to achieve a
desired objective.’
The different stages in this cycle are:
 Initiation involving reviewing the business need and preparing a business case
(clause 5),
Page 3 ©500 Words Ltd, 2015
 Procurement Strategy including preparing feasibility/VM study, client brief, deciding
procurement methods, works packages, market engagement and supporting
processes (clause 6),
 Procurement Tactics including forms of contract, appointment/award (clause 7),
 Managing Performance as well as post project/occupancy evaluations, exit
strategies (clause 8).
The Standard also includes a Code of Practice which contains some aspects of procurement
policy best practice including:
 Issues of bribery and anti-competitive practice;
 Conflict of interest;
 Dispute resolution;
 Methods of identification and management of risk;
 Issues of payment and financial management;
 Issues of stakeholders in particular funds and their impact on procurement and
third party rights;
 Cost management to include best value, KPIs and incentivisation;
 Corporate social responsibility;
 Health and safety;
 Environmental sustainability; and
 Intellectual property.
CONSTRUCT
Stages 5 and 6 of the British Standard align closely with our CONSTRUCT formula for
identifying the client’s brief for a project. A comparison between stages 5 and 6 and the
CONSTRUCT checklist is overleaf.4
Author
This guide is provided by Sarah Fox of 500 Words Ltd, a speaker and trainer who helps you
write simpler contracts and understand complex ones. To see how Sarah could help you,
email: sarah@500words.co.uk or ring her mobile: 07767 342747.
Page 4 © Enjoy Legal Learning, 2013
Comparison of CONSTRUCT Checklist with Extracts from BS8534:2011
C Context 5.1.1 Once the potential need for the project has been identified, careful strategic planning should be undertaken to identify the key issues and
delivery options in relation to procurement.
5.1.3 The business objectives and outcomes that the proposed procurement project has to fulfil should be identified, taking into account the
project’s position within the overall business strategy.
6.1 In developing a procurement strategy to deliver the chosen option, the strategy should define the objectives of the project and how these are
to be achieved taking account of the risks, constraints and funding. A procurement strategy should be used to achieve the correct balance of risk,
project controls set by the client and funding for a particular project…The procurement route should deliver the procurement strategy and include
the contract strategy that can best meet the client’s needs.
O Objectives 5.1.5 The scope and purpose of the proposed project should be appropriately documented in order to ensure a shared understanding by the key
stakeholders of the proposed achievements and benefits.
5.1.7 The proposed project should have a final evaluation to confirm strategic fit with key business objectives before proceeding to the next stage
of business case development [5.2].
5.2 A business case should justify the procurement activity and expenditure, and establish whether the investment is worthwhile in value for
money (VFM) terms. The business case should be continually revisited at key points in the procurement life cycle to ensure that the project’s
original aims, objectives, user requirements and benefits continue to be met…High-level options for meeting the business need should be explored
and assessed in principle for their affordability and achievability.
5.3 In developing a procurement strategy, clients should identify their own particular objectives and determine how they want to prioritize work
stages depending on the degree to which they have pre-established approaches for funding and management of their projects.
N Needs 5.1.1 Once the potential need for a project has been identified, careful strategic planning… should first examine whether the procurement is in fact
necessary.
5.1.3…the factors of time, cost and performance…should be assessed and the project’s priorities defined in relation to the priorities of the
organisation and any stakeholders…sometimes difficult trade-offs [need to] be considered between these three primary variables.
6.2 …The client brief should flow directly from the context [C above], content, priorities [O above] and parameters outlined in the business case. It
should outline prioritized client objectives and provide a clear express of client ability to absorb risk or intent to transfer risk [R below].
S Structure At the feasibility stage, BS8534 recommends the procurement strategy includes issues relating to tendering, works packages, publicity, risks, roles
and responsibilities (6.1).
6.3.1 The procurement strategy should identify how and when suppliers are brought onto the project by the procurement method chosen.
Page 5 ©500 Words Ltd, 2015
T Team 5.1.2 The roles, responsibilities and accountabilities for the delivery of both the procurement programme and the proposed procurement project
should be defined and documented.
5.1.4 Professional advice may be required from…funding advisers, legal advisers, insurers, media and public relations specialists, planning and
environmental consultants, health and safety advisers, architectural and engineering designers, and project management/construction
procurement specialists.
5.1.6 It should be ensured that key stakeholders, as individuals or groups with significant influence over the project, are identified and involved.
6.3.2 The source of funding might not be an option as it can be a matter of policy or regulation for any given client, but it should be explicit. Certain
sources of finance carry constraints that should be understood and incorporated into the business case and procurement policy…Clients should
assess how the funding constrains other decisions about risk and rewards in the procurement policy.
6.3.3 The selection method should be based on the opportunities for long-term relationships with, and/or between, key supply chain partners and
should not be based on price alone.
6.3.5 The question about the involvement of designers independent of the contractors/suppliers should be resolved based on the extent to which
the client’s design exigencies take propriety over other constraints on the procurement.
6.3.7 In complex projects there might be many subcontracts some of which should be selected by the client’s team in order to harness the design
skills of specialist trade contractors or to procure items with a long lead time.
R Risks 5.2…A risk assessment should be carried out and the risks captured in a risk register, which should include the risk of time overrun, see BS
3110…some risk-based assessment for programme contingency or float should be made….For each option in [the high-level business case] it should
set out the base cost, the risk analysis and the calculated allowances for identified risks, all on a whole-life cost basis, including treatment of the
asset at the end of the contract.
6.1 The risks associated with each option including the cost of managing [the risks] through avoidance, design/reduction, acceptance, share or
transfer should be identified.
6.3.3 The methods of selection should be based on an assessment of relative value and risk to the client.
6.3.4 Clients should ensure the price basis reflects earlier decisions about risk apportionment.
6.6.2 Where there is a possibility of change for whatever reason, it should be treated as a project risk and identified in the risk management plan.
6.6.6 Risk and value management should be carried out together throughout the project. Clients should work on understanding risks, how to
handle risks (including their impact on relationships) and their attitude to them, documenting this process, before risk allocation, risk management
and risk registers [my emphasis].
U Uniqueness 5.3…In developing a procurement strategy, clients should identify their own particular objectives and determine how they want to prioritize…
C Constraints 6.1…The following factors should be assessed as they can influence the procurement strategy: the project objectives [see above]; any constraints
identified such as budget, funding, performance and the programme for delivery; risks [see above]; the client’s experience and qualifications to
manage the project…; and the length of operational service required from the facility.
6.3.1 …Clients, and their advisors, should identify and understand the relevant constraints before a procurement method selection exercise is
undertaken as decision made can be limited and influenced by constraints, e.g. legislative requirements, mandatory policy, the need to complete
construction within limited time periods.
Page 6 ©500 Words Ltd, 2015
1
The launch presentation containing an overview is available from here.
2
The objective of ISO10845 series is to provide a generic and standard set of processes, procedures and methods for a procurement system that is fair, equitable, transparent, competitive and cost
effective and which may be used to promote objectives additional to those associated with the immediate objective of the procurement itself.
3
Defined as a ‘policy which details the overarching strategic principles and objectives for the procurement of construction projects; spanning the whole project life cycle from identification of needs
through to the end of the useful life of an asset.’
4
Stage 7 of the British Standard aligns with U in BUILD™, and stage 8 is similar to D in BUILD™.
T Timescales The project definition in the brief should contain (6.2): project objectives, project scope, outline project deliverables and/or desired outcomes, any
exclusions, constraints including budget and timescale, interfaces with other projects, a description of how the project supports strategic
objectives; and the reason for the selection of the chosen option.

More Related Content

What's hot

Comparison of Design Bid Build vs. Design Build Finance Operate & Maintain
Comparison of Design Bid Build vs. Design Build Finance Operate & MaintainComparison of Design Bid Build vs. Design Build Finance Operate & Maintain
Comparison of Design Bid Build vs. Design Build Finance Operate & MaintainBob Prieto
 
Effective Contract Management
Effective Contract ManagementEffective Contract Management
Effective Contract ManagementDr Gordon Murray
 
Contract Administration Presentation
Contract Administration PresentationContract Administration Presentation
Contract Administration PresentationYanet Ormeno
 
Presentation - Construction Contract Dispute Resolution
Presentation - Construction Contract Dispute ResolutionPresentation - Construction Contract Dispute Resolution
Presentation - Construction Contract Dispute ResolutionJustin DeMerchant
 
Procurement system in the Indian construction industry issues and remedies
Procurement system in the Indian construction industry issues and remediesProcurement system in the Indian construction industry issues and remedies
Procurement system in the Indian construction industry issues and remediesPavitr1203
 
12.0 Project Procurement Management Overview
12.0 Project Procurement Management Overview12.0 Project Procurement Management Overview
12.0 Project Procurement Management OverviewDavidMcLachlan1
 
Exploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryExploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryMECandPMV
 
Lecture 1 introduction to construction procurement process.
Lecture 1   introduction to construction procurement process.Lecture 1   introduction to construction procurement process.
Lecture 1 introduction to construction procurement process.Aszahari Aie
 
Private Finance Initiative (PFI)
Private Finance Initiative (PFI)Private Finance Initiative (PFI)
Private Finance Initiative (PFI)tutor2u
 
Guide to Construction Procurement Strategies
Guide to Construction Procurement StrategiesGuide to Construction Procurement Strategies
Guide to Construction Procurement StrategiesSarah Fox
 
contract administration PPT
 contract administration PPT contract administration PPT
contract administration PPTKEVINMISTRY8
 
Build,Operate,Own,Transfer (BOOT)
Build,Operate,Own,Transfer (BOOT)Build,Operate,Own,Transfer (BOOT)
Build,Operate,Own,Transfer (BOOT)Mohd. Ikhwan
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contractsAnil Kumar(6)
 
Contract Management - Generating Real Value from your Contracts
Contract Management - Generating Real Value from your ContractsContract Management - Generating Real Value from your Contracts
Contract Management - Generating Real Value from your ContractsTejari
 
Fidic comparison red yellow - silver book
Fidic comparison red   yellow - silver bookFidic comparison red   yellow - silver book
Fidic comparison red yellow - silver bookHani Saad
 
Turnkey project
Turnkey projectTurnkey project
Turnkey projectzairanieto
 

What's hot (20)

Contract management general
Contract management generalContract management general
Contract management general
 
Comparison of Design Bid Build vs. Design Build Finance Operate & Maintain
Comparison of Design Bid Build vs. Design Build Finance Operate & MaintainComparison of Design Bid Build vs. Design Build Finance Operate & Maintain
Comparison of Design Bid Build vs. Design Build Finance Operate & Maintain
 
Effective Contract Management
Effective Contract ManagementEffective Contract Management
Effective Contract Management
 
Contract Administration Presentation
Contract Administration PresentationContract Administration Presentation
Contract Administration Presentation
 
Presentation - Construction Contract Dispute Resolution
Presentation - Construction Contract Dispute ResolutionPresentation - Construction Contract Dispute Resolution
Presentation - Construction Contract Dispute Resolution
 
Procurement system in the Indian construction industry issues and remedies
Procurement system in the Indian construction industry issues and remediesProcurement system in the Indian construction industry issues and remedies
Procurement system in the Indian construction industry issues and remedies
 
Procurement Methods
Procurement MethodsProcurement Methods
Procurement Methods
 
Software Report
Software ReportSoftware Report
Software Report
 
12.0 Project Procurement Management Overview
12.0 Project Procurement Management Overview12.0 Project Procurement Management Overview
12.0 Project Procurement Management Overview
 
Exploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryExploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project delivery
 
Lecture 1 introduction to construction procurement process.
Lecture 1   introduction to construction procurement process.Lecture 1   introduction to construction procurement process.
Lecture 1 introduction to construction procurement process.
 
Private Finance Initiative (PFI)
Private Finance Initiative (PFI)Private Finance Initiative (PFI)
Private Finance Initiative (PFI)
 
Guide to Construction Procurement Strategies
Guide to Construction Procurement StrategiesGuide to Construction Procurement Strategies
Guide to Construction Procurement Strategies
 
contract administration PPT
 contract administration PPT contract administration PPT
contract administration PPT
 
Build,Operate,Own,Transfer (BOOT)
Build,Operate,Own,Transfer (BOOT)Build,Operate,Own,Transfer (BOOT)
Build,Operate,Own,Transfer (BOOT)
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contracts
 
Contract Management - Generating Real Value from your Contracts
Contract Management - Generating Real Value from your ContractsContract Management - Generating Real Value from your Contracts
Contract Management - Generating Real Value from your Contracts
 
Fidic comparison red yellow - silver book
Fidic comparison red   yellow - silver bookFidic comparison red   yellow - silver book
Fidic comparison red yellow - silver book
 
Turnkey project
Turnkey projectTurnkey project
Turnkey project
 
Application of BIM
Application of BIMApplication of BIM
Application of BIM
 

Similar to Guide to BS8534 British Standard on Procurement

Tender evaluation-strategy-template317
Tender evaluation-strategy-template317Tender evaluation-strategy-template317
Tender evaluation-strategy-template317dooooooost
 
Plan procurement management
Plan procurement management Plan procurement management
Plan procurement management Shereef Sabri
 
Auditing projects in the early stages.pdf
Auditing projects in the early stages.pdfAuditing projects in the early stages.pdf
Auditing projects in the early stages.pdfAddisu15
 
ProjectManagementDocs.comProcurement Management Plan Temp.docx
ProjectManagementDocs.comProcurement Management Plan Temp.docxProjectManagementDocs.comProcurement Management Plan Temp.docx
ProjectManagementDocs.comProcurement Management Plan Temp.docxtienmixon
 
ProjectManagementDocs.comProcurement Management Plan Temp.docx
 ProjectManagementDocs.comProcurement Management Plan Temp.docx ProjectManagementDocs.comProcurement Management Plan Temp.docx
ProjectManagementDocs.comProcurement Management Plan Temp.docxgertrudebellgrove
 
Conduct procurements
Conduct procurements Conduct procurements
Conduct procurements Shereef Sabri
 
Green book guidance_short_plain_english_guide_to_assessing_business_cases
Green book guidance_short_plain_english_guide_to_assessing_business_casesGreen book guidance_short_plain_english_guide_to_assessing_business_cases
Green book guidance_short_plain_english_guide_to_assessing_business_casestmelnik
 
E3 CER A Powerful tool for Governance
E3 CER A Powerful tool for GovernanceE3 CER A Powerful tool for Governance
E3 CER A Powerful tool for GovernanceMagued Moftah
 
E3 cer a powerful tool for governance
E3 cer a powerful tool for governanceE3 cer a powerful tool for governance
E3 cer a powerful tool for governanceMagued Moftah
 
L7_PROJECT PROCUREMENT Management.pdf
L7_PROJECT PROCUREMENT Management.pdfL7_PROJECT PROCUREMENT Management.pdf
L7_PROJECT PROCUREMENT Management.pdfMUST
 
Feasibility and viability
Feasibility and viabilityFeasibility and viability
Feasibility and viabilityAnjan991
 
Lincoln crowne merger & acquisition deal filters 2011 note
Lincoln crowne merger & acquisition deal filters 2011 noteLincoln crowne merger & acquisition deal filters 2011 note
Lincoln crowne merger & acquisition deal filters 2011 noteLincoln Crowne & Company
 
Lincoln crowne merger & acquisition deal filters 2011 note
Lincoln crowne merger & acquisition deal filters 2011 noteLincoln crowne merger & acquisition deal filters 2011 note
Lincoln crowne merger & acquisition deal filters 2011 noteNick Assef
 
New merged capital procurement checklist final 2007-12_11
New   merged capital procurement checklist final  2007-12_11New   merged capital procurement checklist final  2007-12_11
New merged capital procurement checklist final 2007-12_11Google
 
Procurement management-plan template
Procurement management-plan templateProcurement management-plan template
Procurement management-plan templateVivek Srivastava
 
Chapter 8 information system Strategy
Chapter 8 information system StrategyChapter 8 information system Strategy
Chapter 8 information system Strategyahmadjaini_97
 
PMO and Tollgate Process
PMO and Tollgate Process PMO and Tollgate Process
PMO and Tollgate Process Bob Prieto
 
Roadmap to a successful sourcing partnership with a CRO
Roadmap to a successful sourcing partnership with a CRORoadmap to a successful sourcing partnership with a CRO
Roadmap to a successful sourcing partnership with a CROJas Randhawa
 

Similar to Guide to BS8534 British Standard on Procurement (20)

Tender evaluation-strategy-template317
Tender evaluation-strategy-template317Tender evaluation-strategy-template317
Tender evaluation-strategy-template317
 
Project Auditing
Project AuditingProject Auditing
Project Auditing
 
Plan procurement management
Plan procurement management Plan procurement management
Plan procurement management
 
Procurement evaluation-vivich
Procurement evaluation-vivichProcurement evaluation-vivich
Procurement evaluation-vivich
 
Auditing projects in the early stages.pdf
Auditing projects in the early stages.pdfAuditing projects in the early stages.pdf
Auditing projects in the early stages.pdf
 
ProjectManagementDocs.comProcurement Management Plan Temp.docx
ProjectManagementDocs.comProcurement Management Plan Temp.docxProjectManagementDocs.comProcurement Management Plan Temp.docx
ProjectManagementDocs.comProcurement Management Plan Temp.docx
 
ProjectManagementDocs.comProcurement Management Plan Temp.docx
 ProjectManagementDocs.comProcurement Management Plan Temp.docx ProjectManagementDocs.comProcurement Management Plan Temp.docx
ProjectManagementDocs.comProcurement Management Plan Temp.docx
 
Conduct procurements
Conduct procurements Conduct procurements
Conduct procurements
 
Green book guidance_short_plain_english_guide_to_assessing_business_cases
Green book guidance_short_plain_english_guide_to_assessing_business_casesGreen book guidance_short_plain_english_guide_to_assessing_business_cases
Green book guidance_short_plain_english_guide_to_assessing_business_cases
 
E3 CER A Powerful tool for Governance
E3 CER A Powerful tool for GovernanceE3 CER A Powerful tool for Governance
E3 CER A Powerful tool for Governance
 
E3 cer a powerful tool for governance
E3 cer a powerful tool for governanceE3 cer a powerful tool for governance
E3 cer a powerful tool for governance
 
L7_PROJECT PROCUREMENT Management.pdf
L7_PROJECT PROCUREMENT Management.pdfL7_PROJECT PROCUREMENT Management.pdf
L7_PROJECT PROCUREMENT Management.pdf
 
Feasibility and viability
Feasibility and viabilityFeasibility and viability
Feasibility and viability
 
Lincoln crowne merger & acquisition deal filters 2011 note
Lincoln crowne merger & acquisition deal filters 2011 noteLincoln crowne merger & acquisition deal filters 2011 note
Lincoln crowne merger & acquisition deal filters 2011 note
 
Lincoln crowne merger & acquisition deal filters 2011 note
Lincoln crowne merger & acquisition deal filters 2011 noteLincoln crowne merger & acquisition deal filters 2011 note
Lincoln crowne merger & acquisition deal filters 2011 note
 
New merged capital procurement checklist final 2007-12_11
New   merged capital procurement checklist final  2007-12_11New   merged capital procurement checklist final  2007-12_11
New merged capital procurement checklist final 2007-12_11
 
Procurement management-plan template
Procurement management-plan templateProcurement management-plan template
Procurement management-plan template
 
Chapter 8 information system Strategy
Chapter 8 information system StrategyChapter 8 information system Strategy
Chapter 8 information system Strategy
 
PMO and Tollgate Process
PMO and Tollgate Process PMO and Tollgate Process
PMO and Tollgate Process
 
Roadmap to a successful sourcing partnership with a CRO
Roadmap to a successful sourcing partnership with a CRORoadmap to a successful sourcing partnership with a CRO
Roadmap to a successful sourcing partnership with a CRO
 

More from Sarah Fox

Why use 50000 words when 500 will do? (March 2020)
Why use 50000 words when 500 will do? (March 2020)Why use 50000 words when 500 will do? (March 2020)
Why use 50000 words when 500 will do? (March 2020)Sarah Fox
 
How accessibility, simplicity and clarity can stop contracts being a burden a...
How accessibility, simplicity and clarity can stop contracts being a burden a...How accessibility, simplicity and clarity can stop contracts being a burden a...
How accessibility, simplicity and clarity can stop contracts being a burden a...Sarah Fox
 
Creating effective contracts
Creating effective contracts Creating effective contracts
Creating effective contracts Sarah Fox
 
Managing Risks and Changes under NEC4
Managing Risks and Changes under NEC4Managing Risks and Changes under NEC4
Managing Risks and Changes under NEC4Sarah Fox
 
From Captive Cult to Culture Change: Sarah Fox
From Captive Cult to Culture Change: Sarah FoxFrom Captive Cult to Culture Change: Sarah Fox
From Captive Cult to Culture Change: Sarah FoxSarah Fox
 
Checklist for SMEs for GDPR compliance
Checklist for SMEs for GDPR complianceChecklist for SMEs for GDPR compliance
Checklist for SMEs for GDPR complianceSarah Fox
 
10 Tips to Improve Your Legal Writing
10 Tips to Improve Your Legal Writing10 Tips to Improve Your Legal Writing
10 Tips to Improve Your Legal WritingSarah Fox
 
Top 5 Methods for Resolving UK Construction Disputes
Top 5 Methods for Resolving UK Construction DisputesTop 5 Methods for Resolving UK Construction Disputes
Top 5 Methods for Resolving UK Construction DisputesSarah Fox
 
Never Sign on the Dotted Line
Never Sign on the Dotted LineNever Sign on the Dotted Line
Never Sign on the Dotted LineSarah Fox
 
Creating Smart(er) Construction Contracts
Creating Smart(er) Construction ContractsCreating Smart(er) Construction Contracts
Creating Smart(er) Construction ContractsSarah Fox
 
8 Habits of Highly Defective Contracts
8 Habits of Highly Defective Contracts8 Habits of Highly Defective Contracts
8 Habits of Highly Defective ContractsSarah Fox
 
Why Use 50,000 Words When 500 Will Do?
Why Use 50,000 Words When 500 Will Do? Why Use 50,000 Words When 500 Will Do?
Why Use 50,000 Words When 500 Will Do? Sarah Fox
 
Never Sign on the Dotted Line
Never Sign on the Dotted LineNever Sign on the Dotted Line
Never Sign on the Dotted LineSarah Fox
 
Guide to Tort in Construction
Guide to Tort in ConstructionGuide to Tort in Construction
Guide to Tort in ConstructionSarah Fox
 
Guide for Construction Contract Administrators
Guide for Construction Contract AdministratorsGuide for Construction Contract Administrators
Guide for Construction Contract AdministratorsSarah Fox
 
Excluding Liability for Latent Defects
Excluding Liability for Latent DefectsExcluding Liability for Latent Defects
Excluding Liability for Latent DefectsSarah Fox
 
What's So Great About Construction?
What's So Great About Construction?What's So Great About Construction?
What's So Great About Construction?Sarah Fox
 
10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction ContractSarah Fox
 
How Courts Decide Whose Terms Apply
How Courts Decide Whose Terms ApplyHow Courts Decide Whose Terms Apply
How Courts Decide Whose Terms ApplySarah Fox
 
Construction Contract Review Checklist
Construction Contract Review ChecklistConstruction Contract Review Checklist
Construction Contract Review ChecklistSarah Fox
 

More from Sarah Fox (20)

Why use 50000 words when 500 will do? (March 2020)
Why use 50000 words when 500 will do? (March 2020)Why use 50000 words when 500 will do? (March 2020)
Why use 50000 words when 500 will do? (March 2020)
 
How accessibility, simplicity and clarity can stop contracts being a burden a...
How accessibility, simplicity and clarity can stop contracts being a burden a...How accessibility, simplicity and clarity can stop contracts being a burden a...
How accessibility, simplicity and clarity can stop contracts being a burden a...
 
Creating effective contracts
Creating effective contracts Creating effective contracts
Creating effective contracts
 
Managing Risks and Changes under NEC4
Managing Risks and Changes under NEC4Managing Risks and Changes under NEC4
Managing Risks and Changes under NEC4
 
From Captive Cult to Culture Change: Sarah Fox
From Captive Cult to Culture Change: Sarah FoxFrom Captive Cult to Culture Change: Sarah Fox
From Captive Cult to Culture Change: Sarah Fox
 
Checklist for SMEs for GDPR compliance
Checklist for SMEs for GDPR complianceChecklist for SMEs for GDPR compliance
Checklist for SMEs for GDPR compliance
 
10 Tips to Improve Your Legal Writing
10 Tips to Improve Your Legal Writing10 Tips to Improve Your Legal Writing
10 Tips to Improve Your Legal Writing
 
Top 5 Methods for Resolving UK Construction Disputes
Top 5 Methods for Resolving UK Construction DisputesTop 5 Methods for Resolving UK Construction Disputes
Top 5 Methods for Resolving UK Construction Disputes
 
Never Sign on the Dotted Line
Never Sign on the Dotted LineNever Sign on the Dotted Line
Never Sign on the Dotted Line
 
Creating Smart(er) Construction Contracts
Creating Smart(er) Construction ContractsCreating Smart(er) Construction Contracts
Creating Smart(er) Construction Contracts
 
8 Habits of Highly Defective Contracts
8 Habits of Highly Defective Contracts8 Habits of Highly Defective Contracts
8 Habits of Highly Defective Contracts
 
Why Use 50,000 Words When 500 Will Do?
Why Use 50,000 Words When 500 Will Do? Why Use 50,000 Words When 500 Will Do?
Why Use 50,000 Words When 500 Will Do?
 
Never Sign on the Dotted Line
Never Sign on the Dotted LineNever Sign on the Dotted Line
Never Sign on the Dotted Line
 
Guide to Tort in Construction
Guide to Tort in ConstructionGuide to Tort in Construction
Guide to Tort in Construction
 
Guide for Construction Contract Administrators
Guide for Construction Contract AdministratorsGuide for Construction Contract Administrators
Guide for Construction Contract Administrators
 
Excluding Liability for Latent Defects
Excluding Liability for Latent DefectsExcluding Liability for Latent Defects
Excluding Liability for Latent Defects
 
What's So Great About Construction?
What's So Great About Construction?What's So Great About Construction?
What's So Great About Construction?
 
10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract
 
How Courts Decide Whose Terms Apply
How Courts Decide Whose Terms ApplyHow Courts Decide Whose Terms Apply
How Courts Decide Whose Terms Apply
 
Construction Contract Review Checklist
Construction Contract Review ChecklistConstruction Contract Review Checklist
Construction Contract Review Checklist
 

Recently uploaded

Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentationuneakwhite
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableSeo
 
Business Model Canvas (BMC)- A new venture concept
Business Model Canvas (BMC)-  A new venture conceptBusiness Model Canvas (BMC)-  A new venture concept
Business Model Canvas (BMC)- A new venture conceptP&CO
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with CultureSeta Wicaksana
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...amitlee9823
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756dollysharma2066
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1kcpayne
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...lizamodels9
 

Recently uploaded (20)

Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
Business Model Canvas (BMC)- A new venture concept
Business Model Canvas (BMC)-  A new venture conceptBusiness Model Canvas (BMC)-  A new venture concept
Business Model Canvas (BMC)- A new venture concept
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
 

Guide to BS8534 British Standard on Procurement

  • 1. Page 1 ©500 Words Ltd, 2015 A GUIDE TO BS8534 ON PROCUREMENT SARAH FOX 500 Words Ltd (2015)
  • 2. Page 2 ©500 Words Ltd, 2015 British Standard BS 8534:2011 on Procurement A guide to help you understand best practice in construction procurement On 25 September 2011, Constructing Excellence1 and the British Standards Institute launched a new British Standard, BS8534 titled “Construction procurement policies, strategies and procedures – code of practice.” This new standard arose from the 2008 Constructing Excellence and BSI Report “Rethinking Standards in Construction” whose principal recommendation was to develop a new standard on construction procurement. At the same time, the International Standards Organisation, ISO, developed two complementary procurement standards whose main objective was the creation of a framework to facilitate fair competition, reduces the possibility of abuse, improves the predictability of outcome and allows the demonstration of best value. IS10845 comes in two parts:  Part 1: processes, methods and procedures;  Part 2: formatting and compilation of procurement documentation.2 The difference is that BS8534 is more strategic (with its recommendation on developing strategies and policies) and ISO10845 is more operational (as it describes processes, methods and procedures for a procurement system). The scope of the new British Standard is to “give recommendations and guidance on the development within a public or private sector organisation of policies, strategies and procedures for the procurement of construction in the built environment.” It is based on this procurement cycle: It covers both procurement policy3 and strategy. It requires procurers to consider best practice on relevant topics in determining a suitable policy. A procurement strategy is ‘a plan of action for funding, organisation, management, selection and payment of supply chains for the design, fabrication and which may include the operation of constructed facilities to achieve a desired objective.’ The different stages in this cycle are:  Initiation involving reviewing the business need and preparing a business case (clause 5),
  • 3. Page 3 ©500 Words Ltd, 2015  Procurement Strategy including preparing feasibility/VM study, client brief, deciding procurement methods, works packages, market engagement and supporting processes (clause 6),  Procurement Tactics including forms of contract, appointment/award (clause 7),  Managing Performance as well as post project/occupancy evaluations, exit strategies (clause 8). The Standard also includes a Code of Practice which contains some aspects of procurement policy best practice including:  Issues of bribery and anti-competitive practice;  Conflict of interest;  Dispute resolution;  Methods of identification and management of risk;  Issues of payment and financial management;  Issues of stakeholders in particular funds and their impact on procurement and third party rights;  Cost management to include best value, KPIs and incentivisation;  Corporate social responsibility;  Health and safety;  Environmental sustainability; and  Intellectual property. CONSTRUCT Stages 5 and 6 of the British Standard align closely with our CONSTRUCT formula for identifying the client’s brief for a project. A comparison between stages 5 and 6 and the CONSTRUCT checklist is overleaf.4 Author This guide is provided by Sarah Fox of 500 Words Ltd, a speaker and trainer who helps you write simpler contracts and understand complex ones. To see how Sarah could help you, email: sarah@500words.co.uk or ring her mobile: 07767 342747.
  • 4. Page 4 © Enjoy Legal Learning, 2013 Comparison of CONSTRUCT Checklist with Extracts from BS8534:2011 C Context 5.1.1 Once the potential need for the project has been identified, careful strategic planning should be undertaken to identify the key issues and delivery options in relation to procurement. 5.1.3 The business objectives and outcomes that the proposed procurement project has to fulfil should be identified, taking into account the project’s position within the overall business strategy. 6.1 In developing a procurement strategy to deliver the chosen option, the strategy should define the objectives of the project and how these are to be achieved taking account of the risks, constraints and funding. A procurement strategy should be used to achieve the correct balance of risk, project controls set by the client and funding for a particular project…The procurement route should deliver the procurement strategy and include the contract strategy that can best meet the client’s needs. O Objectives 5.1.5 The scope and purpose of the proposed project should be appropriately documented in order to ensure a shared understanding by the key stakeholders of the proposed achievements and benefits. 5.1.7 The proposed project should have a final evaluation to confirm strategic fit with key business objectives before proceeding to the next stage of business case development [5.2]. 5.2 A business case should justify the procurement activity and expenditure, and establish whether the investment is worthwhile in value for money (VFM) terms. The business case should be continually revisited at key points in the procurement life cycle to ensure that the project’s original aims, objectives, user requirements and benefits continue to be met…High-level options for meeting the business need should be explored and assessed in principle for their affordability and achievability. 5.3 In developing a procurement strategy, clients should identify their own particular objectives and determine how they want to prioritize work stages depending on the degree to which they have pre-established approaches for funding and management of their projects. N Needs 5.1.1 Once the potential need for a project has been identified, careful strategic planning… should first examine whether the procurement is in fact necessary. 5.1.3…the factors of time, cost and performance…should be assessed and the project’s priorities defined in relation to the priorities of the organisation and any stakeholders…sometimes difficult trade-offs [need to] be considered between these three primary variables. 6.2 …The client brief should flow directly from the context [C above], content, priorities [O above] and parameters outlined in the business case. It should outline prioritized client objectives and provide a clear express of client ability to absorb risk or intent to transfer risk [R below]. S Structure At the feasibility stage, BS8534 recommends the procurement strategy includes issues relating to tendering, works packages, publicity, risks, roles and responsibilities (6.1). 6.3.1 The procurement strategy should identify how and when suppliers are brought onto the project by the procurement method chosen.
  • 5. Page 5 ©500 Words Ltd, 2015 T Team 5.1.2 The roles, responsibilities and accountabilities for the delivery of both the procurement programme and the proposed procurement project should be defined and documented. 5.1.4 Professional advice may be required from…funding advisers, legal advisers, insurers, media and public relations specialists, planning and environmental consultants, health and safety advisers, architectural and engineering designers, and project management/construction procurement specialists. 5.1.6 It should be ensured that key stakeholders, as individuals or groups with significant influence over the project, are identified and involved. 6.3.2 The source of funding might not be an option as it can be a matter of policy or regulation for any given client, but it should be explicit. Certain sources of finance carry constraints that should be understood and incorporated into the business case and procurement policy…Clients should assess how the funding constrains other decisions about risk and rewards in the procurement policy. 6.3.3 The selection method should be based on the opportunities for long-term relationships with, and/or between, key supply chain partners and should not be based on price alone. 6.3.5 The question about the involvement of designers independent of the contractors/suppliers should be resolved based on the extent to which the client’s design exigencies take propriety over other constraints on the procurement. 6.3.7 In complex projects there might be many subcontracts some of which should be selected by the client’s team in order to harness the design skills of specialist trade contractors or to procure items with a long lead time. R Risks 5.2…A risk assessment should be carried out and the risks captured in a risk register, which should include the risk of time overrun, see BS 3110…some risk-based assessment for programme contingency or float should be made….For each option in [the high-level business case] it should set out the base cost, the risk analysis and the calculated allowances for identified risks, all on a whole-life cost basis, including treatment of the asset at the end of the contract. 6.1 The risks associated with each option including the cost of managing [the risks] through avoidance, design/reduction, acceptance, share or transfer should be identified. 6.3.3 The methods of selection should be based on an assessment of relative value and risk to the client. 6.3.4 Clients should ensure the price basis reflects earlier decisions about risk apportionment. 6.6.2 Where there is a possibility of change for whatever reason, it should be treated as a project risk and identified in the risk management plan. 6.6.6 Risk and value management should be carried out together throughout the project. Clients should work on understanding risks, how to handle risks (including their impact on relationships) and their attitude to them, documenting this process, before risk allocation, risk management and risk registers [my emphasis]. U Uniqueness 5.3…In developing a procurement strategy, clients should identify their own particular objectives and determine how they want to prioritize… C Constraints 6.1…The following factors should be assessed as they can influence the procurement strategy: the project objectives [see above]; any constraints identified such as budget, funding, performance and the programme for delivery; risks [see above]; the client’s experience and qualifications to manage the project…; and the length of operational service required from the facility. 6.3.1 …Clients, and their advisors, should identify and understand the relevant constraints before a procurement method selection exercise is undertaken as decision made can be limited and influenced by constraints, e.g. legislative requirements, mandatory policy, the need to complete construction within limited time periods.
  • 6. Page 6 ©500 Words Ltd, 2015 1 The launch presentation containing an overview is available from here. 2 The objective of ISO10845 series is to provide a generic and standard set of processes, procedures and methods for a procurement system that is fair, equitable, transparent, competitive and cost effective and which may be used to promote objectives additional to those associated with the immediate objective of the procurement itself. 3 Defined as a ‘policy which details the overarching strategic principles and objectives for the procurement of construction projects; spanning the whole project life cycle from identification of needs through to the end of the useful life of an asset.’ 4 Stage 7 of the British Standard aligns with U in BUILD™, and stage 8 is similar to D in BUILD™. T Timescales The project definition in the brief should contain (6.2): project objectives, project scope, outline project deliverables and/or desired outcomes, any exclusions, constraints including budget and timescale, interfaces with other projects, a description of how the project supports strategic objectives; and the reason for the selection of the chosen option.