SlideShare a Scribd company logo
1 of 3
Download to read offline
CONTRACT REVIEW CHECKLIST
This is a checklist of items to consider at tender stage when reviewing the contract. Although long, it is not
exhaustive and is intended to reflect those terms and conditions which are most likely to have the greatest
impact on the cost of completing the project.
Specific Risks: Time
1. Is the programme realistic for the works as defined and all provisional works packages?
2. Are there contractually binding target/ interim dates?
3. Are the possession and completion dates clear and unconditional?
4. Do you need to get al programme revisions approved?
5. If the works are divided into sections, are these sequential or to be completed in parallel?1
6. Are the sections clearly defined?
7. Can you claim extensions of time for events outside your control such as employer instructions,
weather?
8. Can you claim loss and expense for events outside your control which delay the works?
9. Can you claim lost productivity for events outside your control which disrupt the works?
10. Are LADs set at a reasonable level and subject to an overall cap on the total amount deductible?2
11. If the project was delayed by 4 weeks, would the LADs deducted totally eliminate your profit margin
for the project?
12. If the project duration is long, does the contract permit price fluctuations e.g. for energy price spikes?
13. Can the employer ask you to accelerate the completion of the work and, if so, is the mechanism for
being paid additional costs clear?
Specific Risks: Cost
14. Is the employer financially secure?
15. Does the employer have a reputation for paying on time? Has it signed the Fair Payment Charter?
16. Is the project being funded and if so, are the funders financially secure?
17. Is there a separate trust account for (a) the retention, and/or (b) all payments
18. Is the retention per cent acceptable?
19. What is the period between certification of instalments and the final date for payment? Does it match
your subcontractor payment expectations/periods?
20. Are there any advance payments?
21. Is set-off allowed between payments and/or between other projects with the same employer?
22. Is the procedure for changing the price due to instructions, risk events etc. robust and workable?
23. Is the percentage of the price represented by provisional sums acceptable?
24. Can the employer omit works and, if so, how would this affect your profit margin?
Specific Risks: Quality
25. Are the documents defining the works complete?3
26. Are the designs provided sufficient in detail, buildable and produced by reputable designers?
27. If the works are divided into sections, are the sections clearly defined?
28. Are you competent to supervise any innovative design, whether by a consultant or subcontractors?
29. Are you responsible for any design of or for the works? If so, have you verified that design before
pricing the works?
30. If required, is the cost of 12 years’ of PI insurance included in your price?
31. Are there ‘fitness for purpose’ clauses (which are not insurable)?
32. Is the defects period reasonable? Check it does not start again where defects are rectified.
33. Are any specific obligations in relation to deleterious or prohibited materials workable?
34. Are ground conditions, asbestos, antiquities, reserved planning matters etc expressly mentioned and
who bears the risk?4
General Approach to Risks
35. Are the consequences (time or money) of risk events allocated to the party best able to manage the
chance of those risks events occurring, or best able to minimise the impact of those events on the
project?
36. Are any responsibilities for risk management balanced by a similar level of authority?
37. Are your responsibilities to insure against specific risk events either already covered by existing
insurances or included in your price?
38. Can the consequences (time and money) of risks allocated to you be passed to your subcontractors? If
not, can they be insured and/or managed?
39. Are the mechanisms to change the works, programme or methods of working robust and workable?
Scope of Works and Services
40. Are the works clearly defined?
41. Is it clear what is deemed included in the definition of the works?
42. Is it clear what you are not expected to do?
43. Are the client’s expectations and objectives for the project well-articulated and reasonable?
Working Together
44. Are roles and responsibilities clearly defined both within the building contract and, where known, for
other members of the project team?
45. Is the contract co-ordinated (or can it be) with those of the rest of the project team including your
proposed subcontractors?
46. Are document protocols clear (ie do electronic versions take precedence over hard copy or vice versa)?
47. What is the reputation of other members of the project team, especially the contract administrator?
48. What control does the employer have over the contract administrator and its independent duties?
49. What are the provisions relating to access during the works for third parties?
50. Are your rights to subcontract the design and/or carrying out of works clear and workable?
Miscellaneous Conditions
51. Is the form of contract suitable for the size, scope and complexity of the works?
52. Are you familiar with all your obligations, both express and implied, under the form of contract?5
53. Are the provisions on copyright and/or confidential information standard?6
54. Are you entitled to terminate the agreement?
55. What are the employer’s rights to terminate the agreement?
56. Are there additional methods for resolving disputes, other than litigation and adjudication?
57. Are the requirements to provide and procure documents such as bonds, guarantees, third party rights
notices, assignments and warranties known, limited in number and reasonable?7
58. How is the contract to be executed?8
59. What is your liability for latent defects?
60. Are there any other limits on your liability?
Author
Sarah Fox of 500 Words Ltd developed this checklist. She is a speaker and trainer who cuts through the
complexities of construction law.
She has simplified this checklist into a four point analysis to evaluate contracts from those which are ‘good to
go’ and those which are ‘disasters waiting to happen’. She runs workshops to teach you how to review your
contracts and avoid them becoming speed bumps in the contract process.
She is also author of the 500-Word Contract™.
To find out how Sarah can transform your technical training, contact her via: 07767 342747 or by email:
sarah@500words.co.uk
Footnotes
1
If sequential then ensure the date for commencement of later sections is linked to completion of the earlier sections, and is not fixed.
2
If there are no LADs then your liability for cost arising from delayed completion is unlimited. LADs act as a cap on your liability and should be
included.
3
The employer should provide drawings, bills, employer’s requirements, scope of works, specification, pre-construction plan. As a contractor
you may need to prepare some of the contractor’s proposals, contract sum analysis, detailed specification, schedule of rates, cost plan and
activity schedule.
4
If not, then the cost and time for ground conditions are at the contractor’s expense. Note you cannot rely on employer surveys.
5
You should always read the contract, but where you are not familiar it is sensible to ask a lawyer to interpret your obligations to avoid
breaching them.
6
Any licence for material should be restricted to this project.
7
These documents can take significant legal and management time to agree and administer.
8
Documents executed as a deed give a 12 year liability for breaches of the contract; otherwise the limit is 6 years.

More Related Content

What's hot

Persons involved in tenders and contract
Persons involved in tenders and contractPersons involved in tenders and contract
Persons involved in tenders and contractshiva prakash
 
Effective Contract Management
Effective Contract ManagementEffective Contract Management
Effective Contract ManagementDr Gordon Murray
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementASHISH KUMAR SINGH
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentationJeff B
 
Variations under the FIDIC form, subject to EU Procurement law
Variations under the FIDIC form, subject to EU Procurement lawVariations under the FIDIC form, subject to EU Procurement law
Variations under the FIDIC form, subject to EU Procurement law39 Essex Chambers
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkDaniel Ross
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014SHKLaw
 
Procurement Methods and their Application.
Procurement Methods and their Application.Procurement Methods and their Application.
Procurement Methods and their Application.Lilian Nwachukwu
 
Importance of Contract Management Training Courses
Importance of Contract Management Training CoursesImportance of Contract Management Training Courses
Importance of Contract Management Training Coursestraningservices
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006Melvin Lim
 
Lecture 2 project procurement and contract management .pdf
Lecture 2  project procurement and contract management .pdfLecture 2  project procurement and contract management .pdf
Lecture 2 project procurement and contract management .pdfaxmedbaasaay
 
Tendering and Procurement - Basic Principles
Tendering and Procurement   - Basic PrinciplesTendering and Procurement   - Basic Principles
Tendering and Procurement - Basic PrinciplesSHKLaw
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Fakhar-un -Nisa
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC ContractKai Yun Pang
 
Presentation - Construction Contract Dispute Resolution
Presentation - Construction Contract Dispute ResolutionPresentation - Construction Contract Dispute Resolution
Presentation - Construction Contract Dispute ResolutionJustin DeMerchant
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)mohamed Ismail
 
Types and forms of contracts
Types and forms of contracts Types and forms of contracts
Types and forms of contracts fritzlejarso
 

What's hot (20)

Persons involved in tenders and contract
Persons involved in tenders and contractPersons involved in tenders and contract
Persons involved in tenders and contract
 
Effective Contract Management
Effective Contract ManagementEffective Contract Management
Effective Contract Management
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 
Variations under the FIDIC form, subject to EU Procurement law
Variations under the FIDIC form, subject to EU Procurement lawVariations under the FIDIC form, subject to EU Procurement law
Variations under the FIDIC form, subject to EU Procurement law
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction Work
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
 
Procurement Methods and their Application.
Procurement Methods and their Application.Procurement Methods and their Application.
Procurement Methods and their Application.
 
Importance of Contract Management Training Courses
Importance of Contract Management Training CoursesImportance of Contract Management Training Courses
Importance of Contract Management Training Courses
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
Lecture 2 project procurement and contract management .pdf
Lecture 2  project procurement and contract management .pdfLecture 2  project procurement and contract management .pdf
Lecture 2 project procurement and contract management .pdf
 
Tendering and Procurement - Basic Principles
Tendering and Procurement   - Basic PrinciplesTendering and Procurement   - Basic Principles
Tendering and Procurement - Basic Principles
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
Presentation - Construction Contract Dispute Resolution
Presentation - Construction Contract Dispute ResolutionPresentation - Construction Contract Dispute Resolution
Presentation - Construction Contract Dispute Resolution
 
Construction tender process
Construction tender processConstruction tender process
Construction tender process
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
Types and forms of contracts
Types and forms of contracts Types and forms of contracts
Types and forms of contracts
 
Fidic law1
Fidic law1Fidic law1
Fidic law1
 

Viewers also liked

Top 5 Methods for Resolving UK Construction Disputes
Top 5 Methods for Resolving UK Construction DisputesTop 5 Methods for Resolving UK Construction Disputes
Top 5 Methods for Resolving UK Construction DisputesSarah Fox
 
Never Sign on the Dotted Line
Never Sign on the Dotted LineNever Sign on the Dotted Line
Never Sign on the Dotted LineSarah Fox
 
10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction ContractSarah Fox
 
Guide for Construction Contract Administrators
Guide for Construction Contract AdministratorsGuide for Construction Contract Administrators
Guide for Construction Contract AdministratorsSarah Fox
 
Just how to write a legal opinion with flair and finesse.
Just how to write a legal opinion with flair and finesse.  Just how to write a legal opinion with flair and finesse.
Just how to write a legal opinion with flair and finesse. coherentliar3249
 
Creating Smart(er) Construction Contracts
Creating Smart(er) Construction ContractsCreating Smart(er) Construction Contracts
Creating Smart(er) Construction ContractsSarah Fox
 
Never Sign on the Dotted Line
Never Sign on the Dotted LineNever Sign on the Dotted Line
Never Sign on the Dotted LineSarah Fox
 
BrandsLab Media Value Session 2 | From RFP to Contract, How to Review your Ag...
BrandsLab Media Value Session 2 | From RFP to Contract, How to Review your Ag...BrandsLab Media Value Session 2 | From RFP to Contract, How to Review your Ag...
BrandsLab Media Value Session 2 | From RFP to Contract, How to Review your Ag...Ebiquity-NA
 
Reglamento Orgánico por Procesos
Reglamento Orgánico por ProcesosReglamento Orgánico por Procesos
Reglamento Orgánico por ProcesosCBDMQ2016
 
SWOT template for Construction Projects
SWOT template for Construction ProjectsSWOT template for Construction Projects
SWOT template for Construction ProjectsSarah Fox
 
Bid, No-Bid Decision Making
Bid, No-Bid Decision Making Bid, No-Bid Decision Making
Bid, No-Bid Decision Making jpeabody
 
Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Roland_Nikles
 
Drafting contract
Drafting contractDrafting contract
Drafting contractLeks&Co
 
Contract management
Contract managementContract management
Contract managementNishant Rai
 
Essentials Of Contracting
Essentials Of ContractingEssentials Of Contracting
Essentials Of Contractingmkroland
 

Viewers also liked (18)

Top 5 Methods for Resolving UK Construction Disputes
Top 5 Methods for Resolving UK Construction DisputesTop 5 Methods for Resolving UK Construction Disputes
Top 5 Methods for Resolving UK Construction Disputes
 
Never Sign on the Dotted Line
Never Sign on the Dotted LineNever Sign on the Dotted Line
Never Sign on the Dotted Line
 
rDR12r_en
rDR12r_enrDR12r_en
rDR12r_en
 
10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract
 
Guide for Construction Contract Administrators
Guide for Construction Contract AdministratorsGuide for Construction Contract Administrators
Guide for Construction Contract Administrators
 
Just how to write a legal opinion with flair and finesse.
Just how to write a legal opinion with flair and finesse.  Just how to write a legal opinion with flair and finesse.
Just how to write a legal opinion with flair and finesse.
 
Creating Smart(er) Construction Contracts
Creating Smart(er) Construction ContractsCreating Smart(er) Construction Contracts
Creating Smart(er) Construction Contracts
 
LEGAL OPINION
LEGAL OPINIONLEGAL OPINION
LEGAL OPINION
 
Never Sign on the Dotted Line
Never Sign on the Dotted LineNever Sign on the Dotted Line
Never Sign on the Dotted Line
 
Killer Contract Provisions
Killer Contract ProvisionsKiller Contract Provisions
Killer Contract Provisions
 
BrandsLab Media Value Session 2 | From RFP to Contract, How to Review your Ag...
BrandsLab Media Value Session 2 | From RFP to Contract, How to Review your Ag...BrandsLab Media Value Session 2 | From RFP to Contract, How to Review your Ag...
BrandsLab Media Value Session 2 | From RFP to Contract, How to Review your Ag...
 
Reglamento Orgánico por Procesos
Reglamento Orgánico por ProcesosReglamento Orgánico por Procesos
Reglamento Orgánico por Procesos
 
SWOT template for Construction Projects
SWOT template for Construction ProjectsSWOT template for Construction Projects
SWOT template for Construction Projects
 
Bid, No-Bid Decision Making
Bid, No-Bid Decision Making Bid, No-Bid Decision Making
Bid, No-Bid Decision Making
 
Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)
 
Drafting contract
Drafting contractDrafting contract
Drafting contract
 
Contract management
Contract managementContract management
Contract management
 
Essentials Of Contracting
Essentials Of ContractingEssentials Of Contracting
Essentials Of Contracting
 

Similar to Construction Contract Review Checklist

Fidic contract administration
Fidic contract administrationFidic contract administration
Fidic contract administrationZabeel Institute
 
Chapter 5.1 Contracts Management - Contract Administration-owners perspective...
Chapter 5.1 Contracts Management - Contract Administration-owners perspective...Chapter 5.1 Contracts Management - Contract Administration-owners perspective...
Chapter 5.1 Contracts Management - Contract Administration-owners perspective...ChandanLawrence
 
Ipwea inspire-issue-12- nov-2019- managing contractors (1)
Ipwea inspire-issue-12- nov-2019- managing contractors (1)Ipwea inspire-issue-12- nov-2019- managing contractors (1)
Ipwea inspire-issue-12- nov-2019- managing contractors (1)James Baker
 
HOW TO SURVIVE CONSTRUCTION PROJECTS DURING TIMES OF ECONOMIC INSANITY
HOW TO SURVIVE CONSTRUCTION PROJECTS DURING TIMES OF ECONOMIC INSANITYHOW TO SURVIVE CONSTRUCTION PROJECTS DURING TIMES OF ECONOMIC INSANITY
HOW TO SURVIVE CONSTRUCTION PROJECTS DURING TIMES OF ECONOMIC INSANITYBurns White LLC
 
Scope Of Work in Engineering economy
Scope Of Work in Engineering economyScope Of Work in Engineering economy
Scope Of Work in Engineering economyNzar Braim
 
Project management
Project managementProject management
Project managementArsh Koul
 
Winning tenders / securing tenderers in a competitive construction market - N...
Winning tenders / securing tenderers in a competitive construction market - N...Winning tenders / securing tenderers in a competitive construction market - N...
Winning tenders / securing tenderers in a competitive construction market - N...Browne Jacobson LLP
 
Best practices checklist copy
Best practices checklist   copyBest practices checklist   copy
Best practices checklist copyConfidential
 
Best practices checklist
Best practices checklistBest practices checklist
Best practices checklistConfidential
 
Best practices checklist copy
Best practices checklist   copyBest practices checklist   copy
Best practices checklist copyConfidential
 
Best practices checklist
Best practices checklistBest practices checklist
Best practices checklistConfidential
 
Distributed Agile teams and alternative contractual forms - what works best?
Distributed Agile teams and alternative contractual forms - what works best?Distributed Agile teams and alternative contractual forms - what works best?
Distributed Agile teams and alternative contractual forms - what works best?Greg Hutchings
 
What goes wrong on complex projects
What goes wrong on complex projectsWhat goes wrong on complex projects
What goes wrong on complex projectsWalter Akers
 
Auditing projects in the early stages.pdf
Auditing projects in the early stages.pdfAuditing projects in the early stages.pdf
Auditing projects in the early stages.pdfAddisu15
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITIONByishimoBTCChef
 
Project Manager Job Description
Project Manager Job DescriptionProject Manager Job Description
Project Manager Job DescriptionTrevor Rutter
 

Similar to Construction Contract Review Checklist (20)

Fidic contract administration
Fidic contract administrationFidic contract administration
Fidic contract administration
 
Contact management
Contact managementContact management
Contact management
 
Chapter 5.1 Contracts Management - Contract Administration-owners perspective...
Chapter 5.1 Contracts Management - Contract Administration-owners perspective...Chapter 5.1 Contracts Management - Contract Administration-owners perspective...
Chapter 5.1 Contracts Management - Contract Administration-owners perspective...
 
Ipwea inspire-issue-12- nov-2019- managing contractors (1)
Ipwea inspire-issue-12- nov-2019- managing contractors (1)Ipwea inspire-issue-12- nov-2019- managing contractors (1)
Ipwea inspire-issue-12- nov-2019- managing contractors (1)
 
HOW TO SURVIVE CONSTRUCTION PROJECTS DURING TIMES OF ECONOMIC INSANITY
HOW TO SURVIVE CONSTRUCTION PROJECTS DURING TIMES OF ECONOMIC INSANITYHOW TO SURVIVE CONSTRUCTION PROJECTS DURING TIMES OF ECONOMIC INSANITY
HOW TO SURVIVE CONSTRUCTION PROJECTS DURING TIMES OF ECONOMIC INSANITY
 
Scope Of Work in Engineering economy
Scope Of Work in Engineering economyScope Of Work in Engineering economy
Scope Of Work in Engineering economy
 
Project management
Project managementProject management
Project management
 
Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]
 
Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]
 
Winning tenders / securing tenderers in a competitive construction market - N...
Winning tenders / securing tenderers in a competitive construction market - N...Winning tenders / securing tenderers in a competitive construction market - N...
Winning tenders / securing tenderers in a competitive construction market - N...
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 
Best practices checklist copy
Best practices checklist   copyBest practices checklist   copy
Best practices checklist copy
 
Best practices checklist
Best practices checklistBest practices checklist
Best practices checklist
 
Best practices checklist copy
Best practices checklist   copyBest practices checklist   copy
Best practices checklist copy
 
Best practices checklist
Best practices checklistBest practices checklist
Best practices checklist
 
Distributed Agile teams and alternative contractual forms - what works best?
Distributed Agile teams and alternative contractual forms - what works best?Distributed Agile teams and alternative contractual forms - what works best?
Distributed Agile teams and alternative contractual forms - what works best?
 
What goes wrong on complex projects
What goes wrong on complex projectsWhat goes wrong on complex projects
What goes wrong on complex projects
 
Auditing projects in the early stages.pdf
Auditing projects in the early stages.pdfAuditing projects in the early stages.pdf
Auditing projects in the early stages.pdf
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
Project Manager Job Description
Project Manager Job DescriptionProject Manager Job Description
Project Manager Job Description
 

More from Sarah Fox

Why use 50000 words when 500 will do? (March 2020)
Why use 50000 words when 500 will do? (March 2020)Why use 50000 words when 500 will do? (March 2020)
Why use 50000 words when 500 will do? (March 2020)Sarah Fox
 
How accessibility, simplicity and clarity can stop contracts being a burden a...
How accessibility, simplicity and clarity can stop contracts being a burden a...How accessibility, simplicity and clarity can stop contracts being a burden a...
How accessibility, simplicity and clarity can stop contracts being a burden a...Sarah Fox
 
Creating effective contracts
Creating effective contracts Creating effective contracts
Creating effective contracts Sarah Fox
 
Managing Risks and Changes under NEC4
Managing Risks and Changes under NEC4Managing Risks and Changes under NEC4
Managing Risks and Changes under NEC4Sarah Fox
 
From Captive Cult to Culture Change: Sarah Fox
From Captive Cult to Culture Change: Sarah FoxFrom Captive Cult to Culture Change: Sarah Fox
From Captive Cult to Culture Change: Sarah FoxSarah Fox
 
Checklist for SMEs for GDPR compliance
Checklist for SMEs for GDPR complianceChecklist for SMEs for GDPR compliance
Checklist for SMEs for GDPR complianceSarah Fox
 
10 Tips to Improve Your Legal Writing
10 Tips to Improve Your Legal Writing10 Tips to Improve Your Legal Writing
10 Tips to Improve Your Legal WritingSarah Fox
 
8 Habits of Highly Defective Contracts
8 Habits of Highly Defective Contracts8 Habits of Highly Defective Contracts
8 Habits of Highly Defective ContractsSarah Fox
 
Why Use 50,000 Words When 500 Will Do?
Why Use 50,000 Words When 500 Will Do? Why Use 50,000 Words When 500 Will Do?
Why Use 50,000 Words When 500 Will Do? Sarah Fox
 
Guide to Tort in Construction
Guide to Tort in ConstructionGuide to Tort in Construction
Guide to Tort in ConstructionSarah Fox
 
Excluding Liability for Latent Defects
Excluding Liability for Latent DefectsExcluding Liability for Latent Defects
Excluding Liability for Latent DefectsSarah Fox
 
What's So Great About Construction?
What's So Great About Construction?What's So Great About Construction?
What's So Great About Construction?Sarah Fox
 
How Courts Decide Whose Terms Apply
How Courts Decide Whose Terms ApplyHow Courts Decide Whose Terms Apply
How Courts Decide Whose Terms ApplySarah Fox
 
Checklist for Trainers & Facilitators
Checklist for Trainers & FacilitatorsChecklist for Trainers & Facilitators
Checklist for Trainers & FacilitatorsSarah Fox
 
Summary of Construction Acts 1996 & 2009
Summary of Construction Acts 1996 & 2009Summary of Construction Acts 1996 & 2009
Summary of Construction Acts 1996 & 2009Sarah Fox
 
When Do Liquidated Damages Become an Irrecoverable Penalty?
When Do Liquidated Damages Become an Irrecoverable Penalty?When Do Liquidated Damages Become an Irrecoverable Penalty?
When Do Liquidated Damages Become an Irrecoverable Penalty?Sarah Fox
 
A Legal Checklist
A Legal Checklist A Legal Checklist
A Legal Checklist Sarah Fox
 
Guide to Construction Procurement Strategies
Guide to Construction Procurement StrategiesGuide to Construction Procurement Strategies
Guide to Construction Procurement StrategiesSarah Fox
 
Guide to BS8534 British Standard on Procurement
Guide to BS8534 British Standard on ProcurementGuide to BS8534 British Standard on Procurement
Guide to BS8534 British Standard on ProcurementSarah Fox
 
Briefing Checklist for Advisers on Construction Projects
Briefing Checklist for Advisers on Construction ProjectsBriefing Checklist for Advisers on Construction Projects
Briefing Checklist for Advisers on Construction ProjectsSarah Fox
 

More from Sarah Fox (20)

Why use 50000 words when 500 will do? (March 2020)
Why use 50000 words when 500 will do? (March 2020)Why use 50000 words when 500 will do? (March 2020)
Why use 50000 words when 500 will do? (March 2020)
 
How accessibility, simplicity and clarity can stop contracts being a burden a...
How accessibility, simplicity and clarity can stop contracts being a burden a...How accessibility, simplicity and clarity can stop contracts being a burden a...
How accessibility, simplicity and clarity can stop contracts being a burden a...
 
Creating effective contracts
Creating effective contracts Creating effective contracts
Creating effective contracts
 
Managing Risks and Changes under NEC4
Managing Risks and Changes under NEC4Managing Risks and Changes under NEC4
Managing Risks and Changes under NEC4
 
From Captive Cult to Culture Change: Sarah Fox
From Captive Cult to Culture Change: Sarah FoxFrom Captive Cult to Culture Change: Sarah Fox
From Captive Cult to Culture Change: Sarah Fox
 
Checklist for SMEs for GDPR compliance
Checklist for SMEs for GDPR complianceChecklist for SMEs for GDPR compliance
Checklist for SMEs for GDPR compliance
 
10 Tips to Improve Your Legal Writing
10 Tips to Improve Your Legal Writing10 Tips to Improve Your Legal Writing
10 Tips to Improve Your Legal Writing
 
8 Habits of Highly Defective Contracts
8 Habits of Highly Defective Contracts8 Habits of Highly Defective Contracts
8 Habits of Highly Defective Contracts
 
Why Use 50,000 Words When 500 Will Do?
Why Use 50,000 Words When 500 Will Do? Why Use 50,000 Words When 500 Will Do?
Why Use 50,000 Words When 500 Will Do?
 
Guide to Tort in Construction
Guide to Tort in ConstructionGuide to Tort in Construction
Guide to Tort in Construction
 
Excluding Liability for Latent Defects
Excluding Liability for Latent DefectsExcluding Liability for Latent Defects
Excluding Liability for Latent Defects
 
What's So Great About Construction?
What's So Great About Construction?What's So Great About Construction?
What's So Great About Construction?
 
How Courts Decide Whose Terms Apply
How Courts Decide Whose Terms ApplyHow Courts Decide Whose Terms Apply
How Courts Decide Whose Terms Apply
 
Checklist for Trainers & Facilitators
Checklist for Trainers & FacilitatorsChecklist for Trainers & Facilitators
Checklist for Trainers & Facilitators
 
Summary of Construction Acts 1996 & 2009
Summary of Construction Acts 1996 & 2009Summary of Construction Acts 1996 & 2009
Summary of Construction Acts 1996 & 2009
 
When Do Liquidated Damages Become an Irrecoverable Penalty?
When Do Liquidated Damages Become an Irrecoverable Penalty?When Do Liquidated Damages Become an Irrecoverable Penalty?
When Do Liquidated Damages Become an Irrecoverable Penalty?
 
A Legal Checklist
A Legal Checklist A Legal Checklist
A Legal Checklist
 
Guide to Construction Procurement Strategies
Guide to Construction Procurement StrategiesGuide to Construction Procurement Strategies
Guide to Construction Procurement Strategies
 
Guide to BS8534 British Standard on Procurement
Guide to BS8534 British Standard on ProcurementGuide to BS8534 British Standard on Procurement
Guide to BS8534 British Standard on Procurement
 
Briefing Checklist for Advisers on Construction Projects
Briefing Checklist for Advisers on Construction ProjectsBriefing Checklist for Advisers on Construction Projects
Briefing Checklist for Advisers on Construction Projects
 

Recently uploaded

7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxpriyanshujha201
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876dlhescort
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaShree Krishna Exports
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...Suhani Kapoor
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Roland Driesen
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 

Recently uploaded (20)

unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in India
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 

Construction Contract Review Checklist

  • 1. CONTRACT REVIEW CHECKLIST This is a checklist of items to consider at tender stage when reviewing the contract. Although long, it is not exhaustive and is intended to reflect those terms and conditions which are most likely to have the greatest impact on the cost of completing the project. Specific Risks: Time 1. Is the programme realistic for the works as defined and all provisional works packages? 2. Are there contractually binding target/ interim dates? 3. Are the possession and completion dates clear and unconditional? 4. Do you need to get al programme revisions approved? 5. If the works are divided into sections, are these sequential or to be completed in parallel?1 6. Are the sections clearly defined? 7. Can you claim extensions of time for events outside your control such as employer instructions, weather? 8. Can you claim loss and expense for events outside your control which delay the works? 9. Can you claim lost productivity for events outside your control which disrupt the works? 10. Are LADs set at a reasonable level and subject to an overall cap on the total amount deductible?2 11. If the project was delayed by 4 weeks, would the LADs deducted totally eliminate your profit margin for the project? 12. If the project duration is long, does the contract permit price fluctuations e.g. for energy price spikes? 13. Can the employer ask you to accelerate the completion of the work and, if so, is the mechanism for being paid additional costs clear? Specific Risks: Cost 14. Is the employer financially secure? 15. Does the employer have a reputation for paying on time? Has it signed the Fair Payment Charter? 16. Is the project being funded and if so, are the funders financially secure? 17. Is there a separate trust account for (a) the retention, and/or (b) all payments 18. Is the retention per cent acceptable? 19. What is the period between certification of instalments and the final date for payment? Does it match your subcontractor payment expectations/periods? 20. Are there any advance payments? 21. Is set-off allowed between payments and/or between other projects with the same employer? 22. Is the procedure for changing the price due to instructions, risk events etc. robust and workable? 23. Is the percentage of the price represented by provisional sums acceptable? 24. Can the employer omit works and, if so, how would this affect your profit margin?
  • 2. Specific Risks: Quality 25. Are the documents defining the works complete?3 26. Are the designs provided sufficient in detail, buildable and produced by reputable designers? 27. If the works are divided into sections, are the sections clearly defined? 28. Are you competent to supervise any innovative design, whether by a consultant or subcontractors? 29. Are you responsible for any design of or for the works? If so, have you verified that design before pricing the works? 30. If required, is the cost of 12 years’ of PI insurance included in your price? 31. Are there ‘fitness for purpose’ clauses (which are not insurable)? 32. Is the defects period reasonable? Check it does not start again where defects are rectified. 33. Are any specific obligations in relation to deleterious or prohibited materials workable? 34. Are ground conditions, asbestos, antiquities, reserved planning matters etc expressly mentioned and who bears the risk?4 General Approach to Risks 35. Are the consequences (time or money) of risk events allocated to the party best able to manage the chance of those risks events occurring, or best able to minimise the impact of those events on the project? 36. Are any responsibilities for risk management balanced by a similar level of authority? 37. Are your responsibilities to insure against specific risk events either already covered by existing insurances or included in your price? 38. Can the consequences (time and money) of risks allocated to you be passed to your subcontractors? If not, can they be insured and/or managed? 39. Are the mechanisms to change the works, programme or methods of working robust and workable? Scope of Works and Services 40. Are the works clearly defined? 41. Is it clear what is deemed included in the definition of the works? 42. Is it clear what you are not expected to do? 43. Are the client’s expectations and objectives for the project well-articulated and reasonable? Working Together 44. Are roles and responsibilities clearly defined both within the building contract and, where known, for other members of the project team? 45. Is the contract co-ordinated (or can it be) with those of the rest of the project team including your proposed subcontractors? 46. Are document protocols clear (ie do electronic versions take precedence over hard copy or vice versa)? 47. What is the reputation of other members of the project team, especially the contract administrator? 48. What control does the employer have over the contract administrator and its independent duties? 49. What are the provisions relating to access during the works for third parties? 50. Are your rights to subcontract the design and/or carrying out of works clear and workable? Miscellaneous Conditions 51. Is the form of contract suitable for the size, scope and complexity of the works? 52. Are you familiar with all your obligations, both express and implied, under the form of contract?5 53. Are the provisions on copyright and/or confidential information standard?6 54. Are you entitled to terminate the agreement? 55. What are the employer’s rights to terminate the agreement? 56. Are there additional methods for resolving disputes, other than litigation and adjudication? 57. Are the requirements to provide and procure documents such as bonds, guarantees, third party rights notices, assignments and warranties known, limited in number and reasonable?7 58. How is the contract to be executed?8 59. What is your liability for latent defects? 60. Are there any other limits on your liability?
  • 3. Author Sarah Fox of 500 Words Ltd developed this checklist. She is a speaker and trainer who cuts through the complexities of construction law. She has simplified this checklist into a four point analysis to evaluate contracts from those which are ‘good to go’ and those which are ‘disasters waiting to happen’. She runs workshops to teach you how to review your contracts and avoid them becoming speed bumps in the contract process. She is also author of the 500-Word Contract™. To find out how Sarah can transform your technical training, contact her via: 07767 342747 or by email: sarah@500words.co.uk Footnotes 1 If sequential then ensure the date for commencement of later sections is linked to completion of the earlier sections, and is not fixed. 2 If there are no LADs then your liability for cost arising from delayed completion is unlimited. LADs act as a cap on your liability and should be included. 3 The employer should provide drawings, bills, employer’s requirements, scope of works, specification, pre-construction plan. As a contractor you may need to prepare some of the contractor’s proposals, contract sum analysis, detailed specification, schedule of rates, cost plan and activity schedule. 4 If not, then the cost and time for ground conditions are at the contractor’s expense. Note you cannot rely on employer surveys. 5 You should always read the contract, but where you are not familiar it is sensible to ask a lawyer to interpret your obligations to avoid breaching them. 6 Any licence for material should be restricted to this project. 7 These documents can take significant legal and management time to agree and administer. 8 Documents executed as a deed give a 12 year liability for breaches of the contract; otherwise the limit is 6 years.