Hugh Smith / East Library Study Presentation to Park Board on 8/12/2013
Upcoming SlideShare
Loading in...5
×
 

Hugh Smith / East Library Study Presentation to Park Board on 8/12/2013

on

  • 1,261 views

 

Statistics

Views

Total Views
1,261
Views on SlideShare
702
Embed Views
559

Actions

Likes
0
Downloads
0
Comments
0

1 Embed 559

http://naturallyfun.org 559

Accessibility

Categories

Upload Details

Uploaded via as Microsoft PowerPoint

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

Hugh Smith / East Library Study Presentation to Park Board on 8/12/2013 Hugh Smith / East Library Study Presentation to Park Board on 8/12/2013 Presentation Transcript

  • Arlington Parks & Recreation August 12, 2013 Hugh Smith/East Arlington Library Assessment
  • Budget: $130,000 2008 Bond Funds
  • Purpose of the Project • Condition assessment for Hugh Smith • Programmatic assessment for both facilities • Evaluation of site alternatives • Feasibility of co-locating facilities • Evaluate alternatives for senior services • Identification of aquatic needs
  • History of Facilities Hugh Smith Recreation Center & Pool • Originally built in 1963 by the YMCA • Transferred ownership to city in 1972 • 25,000 SF two story building • 25 yard, 5 lane pool
  • History of Facilities Senior Center • Constructed in 1994 • 10,000 SF building East Arlington Library • Opened in 1970, first branch library • In 2000 renovated/expanded building to10,000 SF
  • Status Update • Architect has completed a visual assessment of buildings • Council approval of 14 member citizen committee 6-18-13 • First committee meeting held July 30th • First public meeting held August 3rd • Architect compiling information from public meeting
  • Schedule 2nd Committee Workshop August 28, 2013 2nd Public Meeting Sept 7, 2013 Review of Design Options Sept 10-18th City Council & Park/Library Board Committee October 1-22nd 3rd Committee Workshop October 29, 2013 City Council & Park/Library Board approval November 1 - 28th Draft Report December 4, 2013 Final Report February 5, 2014
  • Questions?