CONTRACTUAL IMPLICATIONS OF CASH FLOW ON OWNER AND
CONTRACTOR IN VILLA CONSTRUCTION PROJECTS
Mohammed Al Mohsin1
, Ali Alnuaimi2
, Sumayia Al Tobi3
1
Assistant Professor, Civil and Architectural Engineering Department, College of Engineering- University of Buraimi-
Sultanate of Oman
2
Associated Professor, Civil and Architectural Engineering Department, College of Engineering- Sultan Qaboos
University, Sultanate of Oman
3
Quantity surveyor, Ministry of Regional Municipalities and Water Resources- General directorate of technical affairs-
Department of quantities and project contracts – Sultanate of Oman
Abstract
Cash flow forecasting is one of the most essential tools toward assessing the distribution of expenditure and revenues of construction
projects with respect to the time of the project. The work presented in this paper aims to find out the minimum fund required for cash
outflow in case of delay in payments and to identify contractual implications and consequences due to failure of meeting planned cash
flow on both the owner and the contractor. Data from record files of 25 villas, in Muscat, Oman, with different sizes was analysed to
identify the minimum fund required with the contractor to maintain the progress of work in-case of delay of interim payments. The
analysis also included identification of consequences of delay of interim payments. It was found that the minimum fund required is 8.5
per cent of the contract value for maximum interim payment delay of four weeks. The value of required minimum fund increases as
the period of delay increases. In most cases the percentage of the required minimum fund increases with the increase of the contract
value. Work stoppage, delay in completion, penalties and incompletion of projects are major consequences of delay on interim
payments.
Keywords: Cash flow, Villa construction contract, Oman
----------------------------------------------------------------------***------------------------------------------------------------------------
1. INTRODUCTION
Execution of construction projects can make substantial
demands on a contractor‟s cash. Initially, the contractor faces
mobilization of workers and equipment, and setting up costs.
The contractor‟s expense on a project typically exceeds its
monthly progress payment income over an appreciable part of
the construction period. The cash deficit on the project must be
made up from the contractor‟s working capital, or money must
be borrowed to provide the necessary operating funds. „„Cash
flow‟‟ refers to a contractor‟s income and outlay of cash. The
net cash flow is the difference between disbursements and
income at any point of a time. A negative net cash flow means
disbursements are exceeding income which is a usual situation
on even a highly profitable project during the greater part of its
duration. A determination of the future rates of cash
disbursements and cash income, together with their combined
effect on the project cash balance, is called a cash flow forecast.
It is the intent of the contractor to accrue income faster than it
accrues costs. At the end of the project, this difference
represents the contractor‟s profit. The problem is that the cost
of the work put into a project is not directly related to the
resulting income. Additionally, the time delays between the
accrued costs and the cash disbursement are not the same as the
time delays between the accrued income and the cash receipts.
To forecast the amount of money the contractor must invest in
the project, it is necessary to estimate the amount and the
timing of the cash disbursements and the cash receipts [1]. The
importance of modelling and optimizing cash outflows versus
inflows can hardly be overstated. Combining these disparate
and shifted phenomena gives an uneven „saw-tooth‟ pattern that
typically will result in shortfalls [2]. Project cash flow
projections relate the schedule of the values to the construction
schedule, projecting the progress payments through the duration
of the project. The cash flow projection approximates the
progress payments for each payment period during the
construction contract. This projection is used by the owner to
make financial arrangements, which makes funds available for
the payments and optimizes investment opportunities. The
contractor uses the cash flow projection for anticipating revenue
for future periods. Projection of cash flow is directly related to
the construction schedule which is a cost estimate of planned
activities and achievements at the site. Many factors influence
the actual amount of interim payments which may produce
variances from the projection; i.e. late or early delivery of
materials; late or early completion of work activities; revisions
in sequencing of work activities; and the disproportionate
completion of work activities as planned. An approximate range
can be established for the cash flow curve, using early-start
early-finish and late-start late-finish dates defining the limits of
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_________________________________________________________________________________________
Volume: 03 Issue: 04 | Apr-2014, Available @ http://www.ijret.org 443
the range. Some contractors prefer to present a range to the
owner, as the cash flow projection is approximates. Other cash
flow projections use a single curve, with disclaimer that
amounts are approximate. Updating the cash flow projection is
necessary as the project progresses to provide current and more
accurate projections. Because the cash flow relates to the
amounts that will be requested for each progress payment, some
factors differ from those relating to the construction schedule.
The actual payments may not be equally distributed in the work
activity period [3]. Odeyinka and Kaka [4] used 6-point Likert-
type scale field survey on UK construction contractors to assess
their level of satisfaction with identified payment terms
influencing construction cash flow. Results showed that while
contractors were satisfied with most of the contractual factors
investigated under both procurement systems, they were
dissatisfied with two of the factors, namely; time lag between
entitlement to receive and actually receiving cash payment and
percentage of contract sum retained. Park et al [5] developed a
project-level cash flow forecasting model in construction stage
based on the planned earned value and the cost from a general
contractors view on a jobsite. Odeyinka et al [6] identified 11
significant financial risk factors out of 26 risk variables studied
to assess the impact of variation between the forecast and actual
construction cash flow. They applied a structured questionnaire
administered to UK contracting organizations and used mean
response analysis and uni-variant analysis of variance
(ANOVA) based on extent of occurrence. The factors were
grouped under three generic factors: changes in the design or
specification, project complexity and natural inhibition.
Senouci and El-Rayes [7] presented a multi-objective
optimization model that is capable of generating and evaluating
optimal/near-optimal construction resource utilization and
scheduling plans. The aim was to minimize the time and
maximize the profit of construction projects. Three modules
were developed as part of the model: (1) a scheduling module
that develops practical schedules for construction projects; (2) a
profit module that computes the project profit; and (3) a multi-
objective module that searches for and identifies optimal/near
optimal trade-offs between project time and profit. The model
was tested on a large scale project and found to optimize trade-
offs between construction time and profit. Al-Ali et al [8] built
a financial model that helps decision makers to select a path
required to plan cash flow based on a multivariate approach
from the expected cash inflow, priority, likelihood, and time of
construction. The model builds a chain of possible outcomes
and incorporates cash inflow from different projects when a
project is temporarily put on hold. Abdel Halim et al [9] studied
factors that lead to financial failure of contracting firms in
Malaysia. The found that problems related to cash flow and
cash flow management partially cause failure of contracting
firms. They developed a model that help contractors to project
level cash flow at tender stage. The model addresses the
possible time gaps between planned and actual payments. Liu
and Wang [10] investigated cash flow for profit optimization
and handles scheduling problems in multi-project environment.
They proposed a model that can identify the amount and timing
of individual inflow or outflow at the end of each period. The
contractors can observe the cash flow at any specific time
according to project progress. They tested their model on a
hypothetical example involving three projects to illustrate
capability of the proposed model with various constraints,
including credit limit (CL) and due dates, for scenario analysis.
The results showed that setting CLs ensures smooth financial
procedure by properly shifting activities, and assigning due
dates for projects, and helps planners to avoid project duration
extension while maximizing overall project profit. Memon et al
[11] focused on identification of significant causes affecting
large projects construction cost in MARA district in Malaysia
based on a field survey via a questionnaire. They concluded that
cash flow and financial difficulties faced by contractors,
contractor's poor site management and supervision, inadequate
contractor experience, shortage of site workers, incorrect
planning and scheduling by contractors are most severe factors
while changes in scope of project and frequent design changes
are least affecting factors on construction cost.
2. PROBLEM STATEMENT
Failure to meet cash flow requirements or minimum fund
needed for a construction project would cause many problems
or failure of contracting companies which can be reflected on
the contractual obligations between owner and contractor. As
the cash flow forecasting is an approximate based on planned
site activities, the chances of inability to meet cash inflow
requirement, during construction stage, are significant. In
construction projects, it is a must to fix and meet specific dates
for regular cash outflows, such as salaries, loan repayments,
taxes and other administration expenses. Countless research
works have been directed towards the study of cash flow and
cash flow management due to their importance in the
progression of construction projects. Models have been
developed to help contractors planning their cash flow during
the tender stage. However, most of the existing models are
either project specific or do not address the consequences of
failure to meet minimum fund required for cash outflow. This
research work aims to find out the minimum fund required for
cash outflow in case of delay in payments. In addition, it
elucidates contractual obligations of cash flow on both the
owner and the contractor and the probable consequences of
failing to meet planned cash flow.
3. METHODOLOGY
A critical key to cash flow forecasting, during tender stage, is
how to build a cash outflow model. Validation of such a model
involves application of data from on-going projects. The data
should be recent, say during the last 12 months, projects should
be similar in terms of type, environment and location, and
governing laws are the same. Cash flow can be positive or
negative depending on payments received and expenditure
made on the site activities. The cash flow is affected by profit
margins, payment retention, payment delays and credit
agreements. In this research, data about 25 villas constructed in
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_________________________________________________________________________________________
Volume: 03 Issue: 04 | Apr-2014, Available @ http://www.ijret.org 444
Muscat, Oman was collected from projects‟ files. The collected
data included the following:
1. Cash-inflow forecasting represented by:
a) Time schedule plans
b) Cost estimate of planned execution of works based on
the time schedule and detailed cost estimate
c) Contractual conditions such as contract value, retentions,
deductions, payment delay penalty
2. Cash-outflow calculation; mainly in a function of cost
estimate of planned execution of works. Mark-up is to be
removed from work executed to get cash outflow
represented by the cost incurred from production process
3. Calculation of minimum required fund to offset the
difference between the cash inflow and the cash outflow.
The data was analysed to identify the minimum cash required to
cover different periods of payment delay and the effects of
payment delay on contractor and owner. Payment delay was
sequentially incremented from no delay case to cases of four
weeks payment delay. Each one of the five delay cases (0, 1, 2,
3, 4 -week) was subjected to cash flow forecasting calculation
to find the minimum fund required to overcome the
consequences of delay. Interim profit is calculated for the
purpose of comparison with the expected profit. This
comparison would point out cases where the interim profit
value exceeds the maximum expected interim profit which is
seriously looked out. Table 1 shows the process of cash flow
calculation and the minimum fund required.
Table 1: Cash flow forecasting calculation
Week # 1 2 3 4 5
Value of
work
executed
As estimated
by contractor
Retention In Oman 5%
of the work
done
Expected
revenue
after
retention
C1=A1-B1
Expected
revenue
after
retention
and delay
C1 is to be
shifted due
to payment
delay
Cumulative
revenue D1 D1+D2
D1+
D2+
D3
D1+D2+D
3+D4
D1+D2+D
3+D4+D5
Expenditure Value of
work
executed/
(1+ mark-
up)
Cumulative
expenditure
F1 F1+F2
F1+F
2+F3
F1+F2+F3
+F4
F1+F2+F3
+F4+F5
loss/profit Difference between cumulative revenues and
cumulative expenditure (E-G)
4. RESEARCH SAMPLE
The 25 villas used as research sample can be considered as a
homogenous sample due to the fact that all of cases are:
1. Accomplished during one year (2011)
2. All contract types were lump sum
3. All villas are located in Muscat.
The collected data for the sample was:
1. Time schedule of villa construction
2. Breakdowns of payment scheme
3. Advance payment amount
4. Expected mark-up percentage.
5. RESULTS
All the studied 25 villas were subjected to cash flow analysis
using five different payment‟s delay periods (0, 1, 2, 3, 4 -
week). Table 2 shows results of the cash flow analysis and
required minimum fund to keep the execution continues. Table
3 shows the maximum profit earned during the process of
construction to be compared with respect to the expected profit
for the research sample in different payment delays.
6. DISCUSSION
The minimum fund required keeping the sample projects
running in case of the five delay periods and the interim
maximum profit compared payment delays were shown in
Tables 2 and 3 using the procedure set in Table 1. Here
discussion of results is presented
6.1 Effect of Payment Delay on the Minimum Fund
As to be expected, the minimum fund required for villa
construction is directly proportional to the time of payment
delay. The rate of change of the percentage of minimum fund
required becomes very pronounce in the three-week delay
period. In most cases, as the contract value increases the
percentage of the minimum fund increases. The average
percentage of minimum fund for four weeks delay was found to
be 8.5 per cent of the contract value. This fund should be
reserved by the contractor, from the working capital, for the
four-week scenario of delay in payment. Standard deviation of
1.29 per cent reflects homogenous and consistency of sample
regardless of the diversity and random selection of villas. For a
medium size villa with contract value of Rial Omani
50,000(USD 129,000)), the contractor has to ensure availability
of about R.O. 4,250 for possible delay in payment of four
weeks, which is considered reasonable for villa contractors.
This low amount of required fund would lead to high
competition among villa contractors leading to good quality and
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_________________________________________________________________________________________
Volume: 03 Issue: 04 | Apr-2014, Available @ http://www.ijret.org 445
performance in construction industry, at the same time it
exposes villa construction business to high competition market.
The contractor may proceed with the execution of works
without reserved fund utilizing the advance payment of 10 per
cent provided that no delay more than one week is guaranteed
(rarely happens). Assuring minimum fund for possible delay in
payment would assure business continuity and avoid stoppage
or delay and enhance contractor reputation. The availability of
minimum fund for possible delay would relieve the client from
the worry of possible delay in completion and handover of the
property.
Table 2: Minimum fund vs. payment delay time
Villa
No.
Contract
value
% Percentage of minimum fund required based
on the delay in payments
0 1 2 3 4
1 40000 N/A 0.86 0.86 10.36 10.85
2 41300 N/A 2.98 2.98 8.61 8.61
3 24100 N/A N/A N/A 5.74 5.74
4 43300 N/A 3.77 3.77 3.77 3.77
5 44100 N/A N/A N/A 9.58 9.58
6 55000 N/A 2.98 2.98 8.04 8.04
7 80000 N/A 4.11 4.11 9.37 9.73
8 38260 N/A 7.68 7.68 7.68 7.68
9 67500 N/A N/A N/A 8.45 8.45
10 47800 N/A 3.03 3.03 8.67 8.67
11 64000 N/A 2.98 2.98 8.61 8.61
12 58800 N/A 2.98 2.98 8.61 8.61
13 49100 N/A 2.98 2.98 8.61 8.61
14 56600 N/A N/A N/A 8.61 8.61
15 47100 N/A N/A N/A 8.59 8.59
16 74800 N/A N/A 2.98 8.61 8.61
17 59700 N/A 3.14 3.14 9.08 9.08
18 60700 N/A 2.98 2.98 8.61 8.61
19 59850 N/A N/A N/A 9.58 9.58
20 69000 N/A 2.98 2.98 8.61 8.61
21 120000 N/A 3.3 3.3 3.3 8.05
22 157100 N/A 3.38 3.38 3.38 8.91
23 133000 N/A 3.3 3.3 3.3 8.92
24 145000 N/A 3.3 3.3 3.3 8.92
25 127800 N/A 3.3 3.3 3.3 8.92
Average N/A 3.335 3.32 7.37 8.49
Std. deviation N/A 1.22 1.19 2.37 1.29
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_________________________________________________________________________________________
Volume: 03 Issue: 04 | Apr-2014, Available @ http://www.ijret.org 446
Table 3: Interim maximum profit vs. payment delay
Villa
No.
Contract
value
Advance
payment
Total
expected
profit
% Interim maximum profit earned
0 1 2 3 4
1 40000 5700 6666.67 5611.11 5611.11 5611.11 5611.11 5611.11
2 41300 4130 6883.33 4908.34 4908.34 4908.34 4908.34 4908.34
3 24100 5510 4106.67 5027.48 5510 5510 5510 5510
4 43300 10735 7216.67 10735 10735 10735 10735 10735
5 44100 4655 7350 5251.8 5251.8 5251.8 5251.8 5251.8
6 55000 5225 9166.67 6536.54 6536.54 6536.54 6536.54 6536.54
7 80000 6700 13333.33 8607.7 8607.7 8607.7 8607.7 8607.7
8 38260 5111 6376.67 5111 5111 5111 5111 5111
9 67500 7125 11250 8038.46 8038.46 8038.46 8038.46 8038.46
10 47800 4515 7966.67 5653.85 5653.85 5653.85 5653.85 5653.85
11 64000 6080 10666.67 7606.15 7606.15 7606.15 7606.15 7606.15
12 58800 5586 9800 6988.14 6988.14 6988.14 6988.14 6988.14
13 49100 5586 8183.33 5835.35 5835.35 5835.35 5835.35 5835.35
14 56600 5377 9433.33 12103.69 12103.69 12103.69 12103.69 12103.69
15 47100 4465 7850 10059.52 10059.52 10059.52 10059.52 10059.52
16 74800 7106 12466.67 8889.692 8889.692 8889.692 8889.692 8889.692
17 59700 5671.5 9950 7095.115 7095.115 7095.115 7095.115 7095.115
18 60700 5766.5 10116.67 7213.962 7213.962 7213.962 7213.962 7213.962
19 59850 6317.5 9975 7127.436 7127.436 7127.436 7127.436 7127.436
20 69000 6555 115000 8200.385 8200.385 8200.385 11327.5 11327.5
21 120000 11400 20000 14177.19 14177.19 14177.19 14177.19 14177.19
22 157100 14905.5 26183.33 18554.18 18554.18 18554.18 18554.18 18554.18
23 133000 12635 22166.67 15713.06 15713.06 15713.06 15713.06 15713.06
24 145000 13775 24166.67 17130.77 17130.77 17130.77 17130.77 17130.77
25 127800 12141 21300 15098.71 15098.71 15098.71 15098.71 15098.71
6.2 Contractual Implications of Cash Flow Forecasting
Contractual issue is one of the most essential factors in cash
flow forecasting. This factor might help the contractor to
increase or decrease the minimum fund required for a
construction project. Payment delay is the most effective
parameter to be taken into consideration which directly affects
the minimum fund required, which has to be recorded clearly in
the agreement between the owner and contractor. It would be
more beneficial for both parties to include minimum payment
delay, to allow certainty of budgeting and cash flow forecasting
on contractor‟s side. The client has to ensure timely payment
because any delay in payment leads to penalties and may cause
stoppage of site works.
Most of villa construction agreements are lump sum type in
which payments are distributed based on the accomplished
works or stage of construction such as (earthworks,
substructures, super structure finishes, etc.). A percentage of
contract value should be paid after each stage or milestone of
the work executed. The distribution of payments on the time
schedule is the second spot to be controlled, this distribution
should assure minimum payment for contractor and avoid over
payment by owner.
Contractor‟s inability to meet minimum fund required for cash
outflow would prevent achievement of contractual obligations
and lead to delay of some activities at the site. The failure to
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_________________________________________________________________________________________
Volume: 03 Issue: 04 | Apr-2014, Available @ http://www.ijret.org 447
fulfil contractor‟s obligation towards suppliers and
subcontractors is another consequence of this problem. Inability
of payment by client is a source of disturbance for contractor
time schedule in this and other projects and affects his whole
operations of contracting. Some contractors keep their
contractual side free of surprises in terms of client payment
inability by assuring availability of different projects to utilize
his workforce and equipment in case of stoppage at one site.
Usually, this type of contractors stop the work till payment and
penalties of delay are received. On the other side, there is a risk
generated through the problem of payments which lead to
higher interim profit than the maximum expected. In this case
the contractor has received his profit in advance and the future
interim payments will be much less or of no profit. This case
has been noticed in the collected records particularly in case no.
14 and 15. Here, the possibility of the contractor leaving or
stopping the works is higher as he knows future cash inflow
may not be enough to cover the cash outflow.
7. CONCLUSIONS
From the study made in this research, the following concluding
remarks can be made;
 Cash flow forecasting and management are perfect
tools to avoid risk of incompletion of construction
projects.
 Properly planned and sized, timely interim payments
reduce the risk of imbalance cash in and out flows.
 There is a proportional relationship between payment
delay and minimum fund required for villa
construction. It was found that the contractor can start
construction without any minimum fund by utilizing
the advance payment, provided that delay in interim
payment is guaranteed to be less than one week.
 The distribution of payments should be carefully
designed based on milestone achievement related to
detailed cost estimate to avoid fund shortage leading to
stoppage of the construction process and to ensure that
contractor does not receive large profit at early stages
of the project.
 The minimum fund required for a contractor to secure
completion of villa construction is 8.5 per cent of the
total contract value. This percentage is required for a
maximum delay in interim payment of four weeks.
 A clear record should be made in the contract that
explicitly defines ways of handling payment delays,
penalties and work stoppage allowances.
REFERENCES
[1] Sears S. K., Sears, G. A., and Clough, R. H., (2008).
“Construction Project Management -A Practical Guide
to Field Construction Management”, 5th
Ed., John
Willey, 272-274
[2] Lucko, G. and Richard, C. Th. Jr. (2012), “derivation
and assessment of interest in cash flow calculations for
time-cost optimizations in construction project
management” Proceedings of the 2010 Winter
Simulation Conference.
[3] Mincks ,William R., and Johnston, H., (2004).
Construction Jobsite Management, 2nd
, Thomson Delmar
Learning, 388-389
[4] Odeyinka, H. A., Kaka, A. (2005) "An evaluation of
contractors‟ satisfaction with payment terms influencing
construction cash flow", Journal of Financial
Management of Property and Construction, 10(3), 171 -
180
[5] Park, H., Han, S., and Russell, J. (2005). ”Cash Flow
Forecasting Model for General Contractors Using
Moving Weights of Cost Categories.” Jouranl
Management in Engineering, 21(4), 164–172.
[6] Odeyinka, H. A., Lowe, J., and Kaka,A. (2008) "An
evaluation of risk factors impacting construction cash
flow forecast", Journal of Financial Management of
Property and Construction, 13(1), 5 - 17
[7] Senouci, A. and El-Rayes, K., (2009). “Time-Profit
Trade-Off Analysis for Construction Projects” Journal
of Construction Engineering and Management, 135(8),
718–725.
[8] Al-Ali,A. , Ustadi, A., Abdulla, Galadari, A., and Al-
Yousuf (2010) “Deciding the Way Forward of
Construction Contracts during Cash Flow Deficits”,
International Conference on Financial Theory and
Engineering
[9] AbHalim, M.S., Jaafar, M., Osman, O. and SherAkbar,
(2010). “The Contracting Firm‟s Failure and Financial
Related Factors: A Case Study of Malaysian Contracting
Firms”, International Research Journal of Finance and
Economics, Oct. 52 , 28-39
[10] Liu, S. and Wang, C. ,(2010).” Profit Optimization for
Multiproject Scheduling Problems Considering Cash
Flow” Journal of Construction Engineering and
Management, 136(12), 1268–1278.
[11] Memon, A. H., Abdul Rahman, I., Abdullah, M. R.,
Abdu Aziz, A. A. (2010) “Factors Affecting
Construction Cost in Mara Large Construction Project:
Perspective of Project Management Consultant”
International Journal of Sustainable Construction
Engineering & Technology, 1(2), 41-54

More Related Content

What's hot

Financial management of construction contracts
Financial management of construction contractsFinancial management of construction contracts
Financial management of construction contractsidnobleg77
 
Engineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsEngineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsNam N.N Tran M.Eng, PMP
 
Critical Chain Management - ادارة السلسلة الحرجة
Critical Chain Management - ادارة السلسلة الحرجةCritical Chain Management - ادارة السلسلة الحرجة
Critical Chain Management - ادارة السلسلة الحرجةEng.Ahmed Said Mohamed Refaei
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparisonhelensuni
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsTwana Ahmad
 
Understanding the Difference Between EPC and EPCM Contracts
Understanding the Difference Between EPC and EPCM ContractsUnderstanding the Difference Between EPC and EPCM Contracts
Understanding the Difference Between EPC and EPCM ContractsUGL Engineering
 
Time cost trade off
Time cost trade offTime cost trade off
Time cost trade offzollatrix
 
Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...HIMADRI BANERJI
 
Variations under the FIDIC form, subject to EU Procurement law
Variations under the FIDIC form, subject to EU Procurement lawVariations under the FIDIC form, subject to EU Procurement law
Variations under the FIDIC form, subject to EU Procurement law39 Essex Chambers
 
Fi dic silver book
Fi dic silver bookFi dic silver book
Fi dic silver bookmoodlyd
 
The architect as contract administrator a legal perspective - presentation ...
The architect as contract administrator   a legal perspective - presentation ...The architect as contract administrator   a legal perspective - presentation ...
The architect as contract administrator a legal perspective - presentation ...Zainab Zainordin
 
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m magedDelay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m magedM Maged Hegazy, LLM, MBA, CCP, P3O
 
Construction Phase Mgmt Srvcs (2)
Construction Phase Mgmt Srvcs (2)Construction Phase Mgmt Srvcs (2)
Construction Phase Mgmt Srvcs (2)Lee Maserian R.D.I.
 
Financial and Contractual Structure of Construction Projects
Financial and Contractual Structure of Construction ProjectsFinancial and Contractual Structure of Construction Projects
Financial and Contractual Structure of Construction Projectssakibkh
 
Contract administration iowa AGC
Contract administration iowa AGCContract administration iowa AGC
Contract administration iowa AGCCordell Parvin
 

What's hot (20)

Time cost trade off with primavera (real case)
Time cost trade off with primavera (real case)Time cost trade off with primavera (real case)
Time cost trade off with primavera (real case)
 
Financial management of construction contracts
Financial management of construction contractsFinancial management of construction contracts
Financial management of construction contracts
 
Engineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsEngineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projects
 
Critical Chain Management - ادارة السلسلة الحرجة
Critical Chain Management - ادارة السلسلة الحرجةCritical Chain Management - ادارة السلسلة الحرجة
Critical Chain Management - ادارة السلسلة الحرجة
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparison
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
 
Understanding the Difference Between EPC and EPCM Contracts
Understanding the Difference Between EPC and EPCM ContractsUnderstanding the Difference Between EPC and EPCM Contracts
Understanding the Difference Between EPC and EPCM Contracts
 
Time cost trade off
Time cost trade offTime cost trade off
Time cost trade off
 
Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...
 
Variations under the FIDIC form, subject to EU Procurement law
Variations under the FIDIC form, subject to EU Procurement lawVariations under the FIDIC form, subject to EU Procurement law
Variations under the FIDIC form, subject to EU Procurement law
 
Newsletter TE&A
Newsletter TE&ANewsletter TE&A
Newsletter TE&A
 
Epc Vs Epcm
Epc Vs EpcmEpc Vs Epcm
Epc Vs Epcm
 
Fi dic silver book
Fi dic silver bookFi dic silver book
Fi dic silver book
 
The architect as contract administrator a legal perspective - presentation ...
The architect as contract administrator   a legal perspective - presentation ...The architect as contract administrator   a legal perspective - presentation ...
The architect as contract administrator a legal perspective - presentation ...
 
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m magedDelay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
 
Epc overview
Epc  overviewEpc  overview
Epc overview
 
Construction Phase Mgmt Srvcs (2)
Construction Phase Mgmt Srvcs (2)Construction Phase Mgmt Srvcs (2)
Construction Phase Mgmt Srvcs (2)
 
Financial and Contractual Structure of Construction Projects
Financial and Contractual Structure of Construction ProjectsFinancial and Contractual Structure of Construction Projects
Financial and Contractual Structure of Construction Projects
 
Contract administration iowa AGC
Contract administration iowa AGCContract administration iowa AGC
Contract administration iowa AGC
 
Practice notes for_quantity_surveyors_fi
Practice notes for_quantity_surveyors_fiPractice notes for_quantity_surveyors_fi
Practice notes for_quantity_surveyors_fi
 

Viewers also liked

A comparative flow analysis of naca 6409 and naca 4412 aerofoil
A comparative flow analysis of naca 6409 and naca 4412 aerofoilA comparative flow analysis of naca 6409 and naca 4412 aerofoil
A comparative flow analysis of naca 6409 and naca 4412 aerofoileSAT Publishing House
 
Investigation of behaviour of 3 degrees of freedom
Investigation of behaviour of 3 degrees of freedomInvestigation of behaviour of 3 degrees of freedom
Investigation of behaviour of 3 degrees of freedomeSAT Publishing House
 
Investigation and computational analysis of divergent orifice in fuel injecto...
Investigation and computational analysis of divergent orifice in fuel injecto...Investigation and computational analysis of divergent orifice in fuel injecto...
Investigation and computational analysis of divergent orifice in fuel injecto...eSAT Publishing House
 
Modelling of fuzzy logic controller for variablestep
Modelling of fuzzy logic controller for variablestepModelling of fuzzy logic controller for variablestep
Modelling of fuzzy logic controller for variablestepeSAT Publishing House
 
Two level data security using steganography and 2 d cellular automata
Two level data security using steganography and 2 d cellular automataTwo level data security using steganography and 2 d cellular automata
Two level data security using steganography and 2 d cellular automataeSAT Publishing House
 
Study of in filter phosphorus removal mechanisms in an
Study of in filter phosphorus removal mechanisms in anStudy of in filter phosphorus removal mechanisms in an
Study of in filter phosphorus removal mechanisms in aneSAT Publishing House
 
Outage analysis of simo system over nakagami n fading channel
Outage analysis of simo system over nakagami n fading channelOutage analysis of simo system over nakagami n fading channel
Outage analysis of simo system over nakagami n fading channeleSAT Publishing House
 
Performance evaluation of broadcast mac and aloha mac protocol for underwater...
Performance evaluation of broadcast mac and aloha mac protocol for underwater...Performance evaluation of broadcast mac and aloha mac protocol for underwater...
Performance evaluation of broadcast mac and aloha mac protocol for underwater...eSAT Publishing House
 
Discovering adaptive wireless sensor network using β synchronizer
Discovering adaptive wireless sensor network using β synchronizerDiscovering adaptive wireless sensor network using β synchronizer
Discovering adaptive wireless sensor network using β synchronizereSAT Publishing House
 
Investigation of mechanical properties on vinylester based bio composite with...
Investigation of mechanical properties on vinylester based bio composite with...Investigation of mechanical properties on vinylester based bio composite with...
Investigation of mechanical properties on vinylester based bio composite with...eSAT Publishing House
 
Exposure hazard analysis in cement fiber sheet
Exposure hazard analysis in cement fiber sheetExposure hazard analysis in cement fiber sheet
Exposure hazard analysis in cement fiber sheeteSAT Publishing House
 
Spectral threat in tcp over optical burst switched networks
Spectral threat in tcp over optical burst switched networksSpectral threat in tcp over optical burst switched networks
Spectral threat in tcp over optical burst switched networkseSAT Publishing House
 
New optimization scheme for cooperative spectrum sensing taking different snr...
New optimization scheme for cooperative spectrum sensing taking different snr...New optimization scheme for cooperative spectrum sensing taking different snr...
New optimization scheme for cooperative spectrum sensing taking different snr...eSAT Publishing House
 
A simulation and analysis of secured aodv protocol in
A simulation and analysis of secured aodv protocol inA simulation and analysis of secured aodv protocol in
A simulation and analysis of secured aodv protocol ineSAT Publishing House
 
Performance analysis of vrla batteries under
Performance analysis of vrla batteries underPerformance analysis of vrla batteries under
Performance analysis of vrla batteries undereSAT Publishing House
 
Nutrients retention in functional beef burgers with especial emphasis on lipi...
Nutrients retention in functional beef burgers with especial emphasis on lipi...Nutrients retention in functional beef burgers with especial emphasis on lipi...
Nutrients retention in functional beef burgers with especial emphasis on lipi...eSAT Publishing House
 
Solar system as a radio telescope by the formation of virtual lenses above an...
Solar system as a radio telescope by the formation of virtual lenses above an...Solar system as a radio telescope by the formation of virtual lenses above an...
Solar system as a radio telescope by the formation of virtual lenses above an...eSAT Publishing House
 
Semantic approach utilizing data mining and case based reasoning for it suppo...
Semantic approach utilizing data mining and case based reasoning for it suppo...Semantic approach utilizing data mining and case based reasoning for it suppo...
Semantic approach utilizing data mining and case based reasoning for it suppo...eSAT Publishing House
 
A software framework for dynamic modeling of dc motors at robot joints
A software framework for dynamic modeling of dc motors at robot jointsA software framework for dynamic modeling of dc motors at robot joints
A software framework for dynamic modeling of dc motors at robot jointseSAT Publishing House
 
Hardback solution to accelerate multimedia computation through mgp in cmp
Hardback solution to accelerate multimedia computation through mgp in cmpHardback solution to accelerate multimedia computation through mgp in cmp
Hardback solution to accelerate multimedia computation through mgp in cmpeSAT Publishing House
 

Viewers also liked (20)

A comparative flow analysis of naca 6409 and naca 4412 aerofoil
A comparative flow analysis of naca 6409 and naca 4412 aerofoilA comparative flow analysis of naca 6409 and naca 4412 aerofoil
A comparative flow analysis of naca 6409 and naca 4412 aerofoil
 
Investigation of behaviour of 3 degrees of freedom
Investigation of behaviour of 3 degrees of freedomInvestigation of behaviour of 3 degrees of freedom
Investigation of behaviour of 3 degrees of freedom
 
Investigation and computational analysis of divergent orifice in fuel injecto...
Investigation and computational analysis of divergent orifice in fuel injecto...Investigation and computational analysis of divergent orifice in fuel injecto...
Investigation and computational analysis of divergent orifice in fuel injecto...
 
Modelling of fuzzy logic controller for variablestep
Modelling of fuzzy logic controller for variablestepModelling of fuzzy logic controller for variablestep
Modelling of fuzzy logic controller for variablestep
 
Two level data security using steganography and 2 d cellular automata
Two level data security using steganography and 2 d cellular automataTwo level data security using steganography and 2 d cellular automata
Two level data security using steganography and 2 d cellular automata
 
Study of in filter phosphorus removal mechanisms in an
Study of in filter phosphorus removal mechanisms in anStudy of in filter phosphorus removal mechanisms in an
Study of in filter phosphorus removal mechanisms in an
 
Outage analysis of simo system over nakagami n fading channel
Outage analysis of simo system over nakagami n fading channelOutage analysis of simo system over nakagami n fading channel
Outage analysis of simo system over nakagami n fading channel
 
Performance evaluation of broadcast mac and aloha mac protocol for underwater...
Performance evaluation of broadcast mac and aloha mac protocol for underwater...Performance evaluation of broadcast mac and aloha mac protocol for underwater...
Performance evaluation of broadcast mac and aloha mac protocol for underwater...
 
Discovering adaptive wireless sensor network using β synchronizer
Discovering adaptive wireless sensor network using β synchronizerDiscovering adaptive wireless sensor network using β synchronizer
Discovering adaptive wireless sensor network using β synchronizer
 
Investigation of mechanical properties on vinylester based bio composite with...
Investigation of mechanical properties on vinylester based bio composite with...Investigation of mechanical properties on vinylester based bio composite with...
Investigation of mechanical properties on vinylester based bio composite with...
 
Exposure hazard analysis in cement fiber sheet
Exposure hazard analysis in cement fiber sheetExposure hazard analysis in cement fiber sheet
Exposure hazard analysis in cement fiber sheet
 
Spectral threat in tcp over optical burst switched networks
Spectral threat in tcp over optical burst switched networksSpectral threat in tcp over optical burst switched networks
Spectral threat in tcp over optical burst switched networks
 
New optimization scheme for cooperative spectrum sensing taking different snr...
New optimization scheme for cooperative spectrum sensing taking different snr...New optimization scheme for cooperative spectrum sensing taking different snr...
New optimization scheme for cooperative spectrum sensing taking different snr...
 
A simulation and analysis of secured aodv protocol in
A simulation and analysis of secured aodv protocol inA simulation and analysis of secured aodv protocol in
A simulation and analysis of secured aodv protocol in
 
Performance analysis of vrla batteries under
Performance analysis of vrla batteries underPerformance analysis of vrla batteries under
Performance analysis of vrla batteries under
 
Nutrients retention in functional beef burgers with especial emphasis on lipi...
Nutrients retention in functional beef burgers with especial emphasis on lipi...Nutrients retention in functional beef burgers with especial emphasis on lipi...
Nutrients retention in functional beef burgers with especial emphasis on lipi...
 
Solar system as a radio telescope by the formation of virtual lenses above an...
Solar system as a radio telescope by the formation of virtual lenses above an...Solar system as a radio telescope by the formation of virtual lenses above an...
Solar system as a radio telescope by the formation of virtual lenses above an...
 
Semantic approach utilizing data mining and case based reasoning for it suppo...
Semantic approach utilizing data mining and case based reasoning for it suppo...Semantic approach utilizing data mining and case based reasoning for it suppo...
Semantic approach utilizing data mining and case based reasoning for it suppo...
 
A software framework for dynamic modeling of dc motors at robot joints
A software framework for dynamic modeling of dc motors at robot jointsA software framework for dynamic modeling of dc motors at robot joints
A software framework for dynamic modeling of dc motors at robot joints
 
Hardback solution to accelerate multimedia computation through mgp in cmp
Hardback solution to accelerate multimedia computation through mgp in cmpHardback solution to accelerate multimedia computation through mgp in cmp
Hardback solution to accelerate multimedia computation through mgp in cmp
 

Similar to Contractual implications of cash flow on owner and contractor in villa construction projects

A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...IRJET Journal
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...IRJET Journal
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET Journal
 
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...Gaurav Verma
 
Asim 20prasad-131008015750-phpapp02
Asim 20prasad-131008015750-phpapp02Asim 20prasad-131008015750-phpapp02
Asim 20prasad-131008015750-phpapp02PMI_IREP_TP
 
Asim prasad
Asim prasadAsim prasad
Asim prasadPMI2011
 
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow Management
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow ManagementA Multi-Objective Fuzzy Linear Programming Model for Cash Flow Management
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow ManagementIJERA Editor
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET Journal
 
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET Journal
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectseSAT Journals
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectseSAT Journals
 
Procurement principle towards effective management of construction projects
Procurement principle towards effective management of construction projectsProcurement principle towards effective management of construction projects
Procurement principle towards effective management of construction projectseSAT Publishing House
 
Tracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementTracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementIRJET Journal
 
Contractual Steps for Smooth Delivery of Infrastructure Projects
Contractual Steps for Smooth Delivery of Infrastructure ProjectsContractual Steps for Smooth Delivery of Infrastructure Projects
Contractual Steps for Smooth Delivery of Infrastructure ProjectsAM Publications
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Gregoire Lesecq
 
I0313048051
I0313048051I0313048051
I0313048051theijes
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...IRJET Journal
 
IRJET- Daily Updates on Construction Sites Progress
IRJET- Daily Updates on Construction Sites ProgressIRJET- Daily Updates on Construction Sites Progress
IRJET- Daily Updates on Construction Sites ProgressIRJET Journal
 
Identification of Factors Affecting Construction Cash Flow: A Statistical Ana...
Identification of Factors Affecting Construction Cash Flow: A Statistical Ana...Identification of Factors Affecting Construction Cash Flow: A Statistical Ana...
Identification of Factors Affecting Construction Cash Flow: A Statistical Ana...IRJET Journal
 

Similar to Contractual implications of cash flow on owner and contractor in villa construction projects (20)

A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building Project
 
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
 
H1303055462
H1303055462H1303055462
H1303055462
 
Asim 20prasad-131008015750-phpapp02
Asim 20prasad-131008015750-phpapp02Asim 20prasad-131008015750-phpapp02
Asim 20prasad-131008015750-phpapp02
 
Asim prasad
Asim prasadAsim prasad
Asim prasad
 
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow Management
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow ManagementA Multi-Objective Fuzzy Linear Programming Model for Cash Flow Management
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow Management
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
 
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projects
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projects
 
Procurement principle towards effective management of construction projects
Procurement principle towards effective management of construction projectsProcurement principle towards effective management of construction projects
Procurement principle towards effective management of construction projects
 
Tracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementTracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value Management
 
Contractual Steps for Smooth Delivery of Infrastructure Projects
Contractual Steps for Smooth Delivery of Infrastructure ProjectsContractual Steps for Smooth Delivery of Infrastructure Projects
Contractual Steps for Smooth Delivery of Infrastructure Projects
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
I0313048051
I0313048051I0313048051
I0313048051
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...
 
IRJET- Daily Updates on Construction Sites Progress
IRJET- Daily Updates on Construction Sites ProgressIRJET- Daily Updates on Construction Sites Progress
IRJET- Daily Updates on Construction Sites Progress
 
Identification of Factors Affecting Construction Cash Flow: A Statistical Ana...
Identification of Factors Affecting Construction Cash Flow: A Statistical Ana...Identification of Factors Affecting Construction Cash Flow: A Statistical Ana...
Identification of Factors Affecting Construction Cash Flow: A Statistical Ana...
 

More from eSAT Publishing House

Likely impacts of hudhud on the environment of visakhapatnam
Likely impacts of hudhud on the environment of visakhapatnamLikely impacts of hudhud on the environment of visakhapatnam
Likely impacts of hudhud on the environment of visakhapatnameSAT Publishing House
 
Impact of flood disaster in a drought prone area – case study of alampur vill...
Impact of flood disaster in a drought prone area – case study of alampur vill...Impact of flood disaster in a drought prone area – case study of alampur vill...
Impact of flood disaster in a drought prone area – case study of alampur vill...eSAT Publishing House
 
Hudhud cyclone – a severe disaster in visakhapatnam
Hudhud cyclone – a severe disaster in visakhapatnamHudhud cyclone – a severe disaster in visakhapatnam
Hudhud cyclone – a severe disaster in visakhapatnameSAT Publishing House
 
Groundwater investigation using geophysical methods a case study of pydibhim...
Groundwater investigation using geophysical methods  a case study of pydibhim...Groundwater investigation using geophysical methods  a case study of pydibhim...
Groundwater investigation using geophysical methods a case study of pydibhim...eSAT Publishing House
 
Flood related disasters concerned to urban flooding in bangalore, india
Flood related disasters concerned to urban flooding in bangalore, indiaFlood related disasters concerned to urban flooding in bangalore, india
Flood related disasters concerned to urban flooding in bangalore, indiaeSAT Publishing House
 
Enhancing post disaster recovery by optimal infrastructure capacity building
Enhancing post disaster recovery by optimal infrastructure capacity buildingEnhancing post disaster recovery by optimal infrastructure capacity building
Enhancing post disaster recovery by optimal infrastructure capacity buildingeSAT Publishing House
 
Effect of lintel and lintel band on the global performance of reinforced conc...
Effect of lintel and lintel band on the global performance of reinforced conc...Effect of lintel and lintel band on the global performance of reinforced conc...
Effect of lintel and lintel band on the global performance of reinforced conc...eSAT Publishing House
 
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...eSAT Publishing House
 
Wind damage to buildings, infrastrucuture and landscape elements along the be...
Wind damage to buildings, infrastrucuture and landscape elements along the be...Wind damage to buildings, infrastrucuture and landscape elements along the be...
Wind damage to buildings, infrastrucuture and landscape elements along the be...eSAT Publishing House
 
Shear strength of rc deep beam panels – a review
Shear strength of rc deep beam panels – a reviewShear strength of rc deep beam panels – a review
Shear strength of rc deep beam panels – a revieweSAT Publishing House
 
Role of voluntary teams of professional engineers in dissater management – ex...
Role of voluntary teams of professional engineers in dissater management – ex...Role of voluntary teams of professional engineers in dissater management – ex...
Role of voluntary teams of professional engineers in dissater management – ex...eSAT Publishing House
 
Risk analysis and environmental hazard management
Risk analysis and environmental hazard managementRisk analysis and environmental hazard management
Risk analysis and environmental hazard managementeSAT Publishing House
 
Review study on performance of seismically tested repaired shear walls
Review study on performance of seismically tested repaired shear wallsReview study on performance of seismically tested repaired shear walls
Review study on performance of seismically tested repaired shear wallseSAT Publishing House
 
Monitoring and assessment of air quality with reference to dust particles (pm...
Monitoring and assessment of air quality with reference to dust particles (pm...Monitoring and assessment of air quality with reference to dust particles (pm...
Monitoring and assessment of air quality with reference to dust particles (pm...eSAT Publishing House
 
Low cost wireless sensor networks and smartphone applications for disaster ma...
Low cost wireless sensor networks and smartphone applications for disaster ma...Low cost wireless sensor networks and smartphone applications for disaster ma...
Low cost wireless sensor networks and smartphone applications for disaster ma...eSAT Publishing House
 
Coastal zones – seismic vulnerability an analysis from east coast of india
Coastal zones – seismic vulnerability an analysis from east coast of indiaCoastal zones – seismic vulnerability an analysis from east coast of india
Coastal zones – seismic vulnerability an analysis from east coast of indiaeSAT Publishing House
 
Can fracture mechanics predict damage due disaster of structures
Can fracture mechanics predict damage due disaster of structuresCan fracture mechanics predict damage due disaster of structures
Can fracture mechanics predict damage due disaster of structureseSAT Publishing House
 
Assessment of seismic susceptibility of rc buildings
Assessment of seismic susceptibility of rc buildingsAssessment of seismic susceptibility of rc buildings
Assessment of seismic susceptibility of rc buildingseSAT Publishing House
 
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...eSAT Publishing House
 
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...eSAT Publishing House
 

More from eSAT Publishing House (20)

Likely impacts of hudhud on the environment of visakhapatnam
Likely impacts of hudhud on the environment of visakhapatnamLikely impacts of hudhud on the environment of visakhapatnam
Likely impacts of hudhud on the environment of visakhapatnam
 
Impact of flood disaster in a drought prone area – case study of alampur vill...
Impact of flood disaster in a drought prone area – case study of alampur vill...Impact of flood disaster in a drought prone area – case study of alampur vill...
Impact of flood disaster in a drought prone area – case study of alampur vill...
 
Hudhud cyclone – a severe disaster in visakhapatnam
Hudhud cyclone – a severe disaster in visakhapatnamHudhud cyclone – a severe disaster in visakhapatnam
Hudhud cyclone – a severe disaster in visakhapatnam
 
Groundwater investigation using geophysical methods a case study of pydibhim...
Groundwater investigation using geophysical methods  a case study of pydibhim...Groundwater investigation using geophysical methods  a case study of pydibhim...
Groundwater investigation using geophysical methods a case study of pydibhim...
 
Flood related disasters concerned to urban flooding in bangalore, india
Flood related disasters concerned to urban flooding in bangalore, indiaFlood related disasters concerned to urban flooding in bangalore, india
Flood related disasters concerned to urban flooding in bangalore, india
 
Enhancing post disaster recovery by optimal infrastructure capacity building
Enhancing post disaster recovery by optimal infrastructure capacity buildingEnhancing post disaster recovery by optimal infrastructure capacity building
Enhancing post disaster recovery by optimal infrastructure capacity building
 
Effect of lintel and lintel band on the global performance of reinforced conc...
Effect of lintel and lintel band on the global performance of reinforced conc...Effect of lintel and lintel band on the global performance of reinforced conc...
Effect of lintel and lintel band on the global performance of reinforced conc...
 
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...
 
Wind damage to buildings, infrastrucuture and landscape elements along the be...
Wind damage to buildings, infrastrucuture and landscape elements along the be...Wind damage to buildings, infrastrucuture and landscape elements along the be...
Wind damage to buildings, infrastrucuture and landscape elements along the be...
 
Shear strength of rc deep beam panels – a review
Shear strength of rc deep beam panels – a reviewShear strength of rc deep beam panels – a review
Shear strength of rc deep beam panels – a review
 
Role of voluntary teams of professional engineers in dissater management – ex...
Role of voluntary teams of professional engineers in dissater management – ex...Role of voluntary teams of professional engineers in dissater management – ex...
Role of voluntary teams of professional engineers in dissater management – ex...
 
Risk analysis and environmental hazard management
Risk analysis and environmental hazard managementRisk analysis and environmental hazard management
Risk analysis and environmental hazard management
 
Review study on performance of seismically tested repaired shear walls
Review study on performance of seismically tested repaired shear wallsReview study on performance of seismically tested repaired shear walls
Review study on performance of seismically tested repaired shear walls
 
Monitoring and assessment of air quality with reference to dust particles (pm...
Monitoring and assessment of air quality with reference to dust particles (pm...Monitoring and assessment of air quality with reference to dust particles (pm...
Monitoring and assessment of air quality with reference to dust particles (pm...
 
Low cost wireless sensor networks and smartphone applications for disaster ma...
Low cost wireless sensor networks and smartphone applications for disaster ma...Low cost wireless sensor networks and smartphone applications for disaster ma...
Low cost wireless sensor networks and smartphone applications for disaster ma...
 
Coastal zones – seismic vulnerability an analysis from east coast of india
Coastal zones – seismic vulnerability an analysis from east coast of indiaCoastal zones – seismic vulnerability an analysis from east coast of india
Coastal zones – seismic vulnerability an analysis from east coast of india
 
Can fracture mechanics predict damage due disaster of structures
Can fracture mechanics predict damage due disaster of structuresCan fracture mechanics predict damage due disaster of structures
Can fracture mechanics predict damage due disaster of structures
 
Assessment of seismic susceptibility of rc buildings
Assessment of seismic susceptibility of rc buildingsAssessment of seismic susceptibility of rc buildings
Assessment of seismic susceptibility of rc buildings
 
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...
 
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...
 

Recently uploaded

Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniquesugginaramesh
 

Recently uploaded (20)

Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniques
 

Contractual implications of cash flow on owner and contractor in villa construction projects

  • 1. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _________________________________________________________________________________________ Volume: 03 Issue: 04 | Apr-2014, Available @ http://www.ijret.org 442 CONTRACTUAL IMPLICATIONS OF CASH FLOW ON OWNER AND CONTRACTOR IN VILLA CONSTRUCTION PROJECTS Mohammed Al Mohsin1 , Ali Alnuaimi2 , Sumayia Al Tobi3 1 Assistant Professor, Civil and Architectural Engineering Department, College of Engineering- University of Buraimi- Sultanate of Oman 2 Associated Professor, Civil and Architectural Engineering Department, College of Engineering- Sultan Qaboos University, Sultanate of Oman 3 Quantity surveyor, Ministry of Regional Municipalities and Water Resources- General directorate of technical affairs- Department of quantities and project contracts – Sultanate of Oman Abstract Cash flow forecasting is one of the most essential tools toward assessing the distribution of expenditure and revenues of construction projects with respect to the time of the project. The work presented in this paper aims to find out the minimum fund required for cash outflow in case of delay in payments and to identify contractual implications and consequences due to failure of meeting planned cash flow on both the owner and the contractor. Data from record files of 25 villas, in Muscat, Oman, with different sizes was analysed to identify the minimum fund required with the contractor to maintain the progress of work in-case of delay of interim payments. The analysis also included identification of consequences of delay of interim payments. It was found that the minimum fund required is 8.5 per cent of the contract value for maximum interim payment delay of four weeks. The value of required minimum fund increases as the period of delay increases. In most cases the percentage of the required minimum fund increases with the increase of the contract value. Work stoppage, delay in completion, penalties and incompletion of projects are major consequences of delay on interim payments. Keywords: Cash flow, Villa construction contract, Oman ----------------------------------------------------------------------***------------------------------------------------------------------------ 1. INTRODUCTION Execution of construction projects can make substantial demands on a contractor‟s cash. Initially, the contractor faces mobilization of workers and equipment, and setting up costs. The contractor‟s expense on a project typically exceeds its monthly progress payment income over an appreciable part of the construction period. The cash deficit on the project must be made up from the contractor‟s working capital, or money must be borrowed to provide the necessary operating funds. „„Cash flow‟‟ refers to a contractor‟s income and outlay of cash. The net cash flow is the difference between disbursements and income at any point of a time. A negative net cash flow means disbursements are exceeding income which is a usual situation on even a highly profitable project during the greater part of its duration. A determination of the future rates of cash disbursements and cash income, together with their combined effect on the project cash balance, is called a cash flow forecast. It is the intent of the contractor to accrue income faster than it accrues costs. At the end of the project, this difference represents the contractor‟s profit. The problem is that the cost of the work put into a project is not directly related to the resulting income. Additionally, the time delays between the accrued costs and the cash disbursement are not the same as the time delays between the accrued income and the cash receipts. To forecast the amount of money the contractor must invest in the project, it is necessary to estimate the amount and the timing of the cash disbursements and the cash receipts [1]. The importance of modelling and optimizing cash outflows versus inflows can hardly be overstated. Combining these disparate and shifted phenomena gives an uneven „saw-tooth‟ pattern that typically will result in shortfalls [2]. Project cash flow projections relate the schedule of the values to the construction schedule, projecting the progress payments through the duration of the project. The cash flow projection approximates the progress payments for each payment period during the construction contract. This projection is used by the owner to make financial arrangements, which makes funds available for the payments and optimizes investment opportunities. The contractor uses the cash flow projection for anticipating revenue for future periods. Projection of cash flow is directly related to the construction schedule which is a cost estimate of planned activities and achievements at the site. Many factors influence the actual amount of interim payments which may produce variances from the projection; i.e. late or early delivery of materials; late or early completion of work activities; revisions in sequencing of work activities; and the disproportionate completion of work activities as planned. An approximate range can be established for the cash flow curve, using early-start early-finish and late-start late-finish dates defining the limits of
  • 2. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _________________________________________________________________________________________ Volume: 03 Issue: 04 | Apr-2014, Available @ http://www.ijret.org 443 the range. Some contractors prefer to present a range to the owner, as the cash flow projection is approximates. Other cash flow projections use a single curve, with disclaimer that amounts are approximate. Updating the cash flow projection is necessary as the project progresses to provide current and more accurate projections. Because the cash flow relates to the amounts that will be requested for each progress payment, some factors differ from those relating to the construction schedule. The actual payments may not be equally distributed in the work activity period [3]. Odeyinka and Kaka [4] used 6-point Likert- type scale field survey on UK construction contractors to assess their level of satisfaction with identified payment terms influencing construction cash flow. Results showed that while contractors were satisfied with most of the contractual factors investigated under both procurement systems, they were dissatisfied with two of the factors, namely; time lag between entitlement to receive and actually receiving cash payment and percentage of contract sum retained. Park et al [5] developed a project-level cash flow forecasting model in construction stage based on the planned earned value and the cost from a general contractors view on a jobsite. Odeyinka et al [6] identified 11 significant financial risk factors out of 26 risk variables studied to assess the impact of variation between the forecast and actual construction cash flow. They applied a structured questionnaire administered to UK contracting organizations and used mean response analysis and uni-variant analysis of variance (ANOVA) based on extent of occurrence. The factors were grouped under three generic factors: changes in the design or specification, project complexity and natural inhibition. Senouci and El-Rayes [7] presented a multi-objective optimization model that is capable of generating and evaluating optimal/near-optimal construction resource utilization and scheduling plans. The aim was to minimize the time and maximize the profit of construction projects. Three modules were developed as part of the model: (1) a scheduling module that develops practical schedules for construction projects; (2) a profit module that computes the project profit; and (3) a multi- objective module that searches for and identifies optimal/near optimal trade-offs between project time and profit. The model was tested on a large scale project and found to optimize trade- offs between construction time and profit. Al-Ali et al [8] built a financial model that helps decision makers to select a path required to plan cash flow based on a multivariate approach from the expected cash inflow, priority, likelihood, and time of construction. The model builds a chain of possible outcomes and incorporates cash inflow from different projects when a project is temporarily put on hold. Abdel Halim et al [9] studied factors that lead to financial failure of contracting firms in Malaysia. The found that problems related to cash flow and cash flow management partially cause failure of contracting firms. They developed a model that help contractors to project level cash flow at tender stage. The model addresses the possible time gaps between planned and actual payments. Liu and Wang [10] investigated cash flow for profit optimization and handles scheduling problems in multi-project environment. They proposed a model that can identify the amount and timing of individual inflow or outflow at the end of each period. The contractors can observe the cash flow at any specific time according to project progress. They tested their model on a hypothetical example involving three projects to illustrate capability of the proposed model with various constraints, including credit limit (CL) and due dates, for scenario analysis. The results showed that setting CLs ensures smooth financial procedure by properly shifting activities, and assigning due dates for projects, and helps planners to avoid project duration extension while maximizing overall project profit. Memon et al [11] focused on identification of significant causes affecting large projects construction cost in MARA district in Malaysia based on a field survey via a questionnaire. They concluded that cash flow and financial difficulties faced by contractors, contractor's poor site management and supervision, inadequate contractor experience, shortage of site workers, incorrect planning and scheduling by contractors are most severe factors while changes in scope of project and frequent design changes are least affecting factors on construction cost. 2. PROBLEM STATEMENT Failure to meet cash flow requirements or minimum fund needed for a construction project would cause many problems or failure of contracting companies which can be reflected on the contractual obligations between owner and contractor. As the cash flow forecasting is an approximate based on planned site activities, the chances of inability to meet cash inflow requirement, during construction stage, are significant. In construction projects, it is a must to fix and meet specific dates for regular cash outflows, such as salaries, loan repayments, taxes and other administration expenses. Countless research works have been directed towards the study of cash flow and cash flow management due to their importance in the progression of construction projects. Models have been developed to help contractors planning their cash flow during the tender stage. However, most of the existing models are either project specific or do not address the consequences of failure to meet minimum fund required for cash outflow. This research work aims to find out the minimum fund required for cash outflow in case of delay in payments. In addition, it elucidates contractual obligations of cash flow on both the owner and the contractor and the probable consequences of failing to meet planned cash flow. 3. METHODOLOGY A critical key to cash flow forecasting, during tender stage, is how to build a cash outflow model. Validation of such a model involves application of data from on-going projects. The data should be recent, say during the last 12 months, projects should be similar in terms of type, environment and location, and governing laws are the same. Cash flow can be positive or negative depending on payments received and expenditure made on the site activities. The cash flow is affected by profit margins, payment retention, payment delays and credit agreements. In this research, data about 25 villas constructed in
  • 3. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _________________________________________________________________________________________ Volume: 03 Issue: 04 | Apr-2014, Available @ http://www.ijret.org 444 Muscat, Oman was collected from projects‟ files. The collected data included the following: 1. Cash-inflow forecasting represented by: a) Time schedule plans b) Cost estimate of planned execution of works based on the time schedule and detailed cost estimate c) Contractual conditions such as contract value, retentions, deductions, payment delay penalty 2. Cash-outflow calculation; mainly in a function of cost estimate of planned execution of works. Mark-up is to be removed from work executed to get cash outflow represented by the cost incurred from production process 3. Calculation of minimum required fund to offset the difference between the cash inflow and the cash outflow. The data was analysed to identify the minimum cash required to cover different periods of payment delay and the effects of payment delay on contractor and owner. Payment delay was sequentially incremented from no delay case to cases of four weeks payment delay. Each one of the five delay cases (0, 1, 2, 3, 4 -week) was subjected to cash flow forecasting calculation to find the minimum fund required to overcome the consequences of delay. Interim profit is calculated for the purpose of comparison with the expected profit. This comparison would point out cases where the interim profit value exceeds the maximum expected interim profit which is seriously looked out. Table 1 shows the process of cash flow calculation and the minimum fund required. Table 1: Cash flow forecasting calculation Week # 1 2 3 4 5 Value of work executed As estimated by contractor Retention In Oman 5% of the work done Expected revenue after retention C1=A1-B1 Expected revenue after retention and delay C1 is to be shifted due to payment delay Cumulative revenue D1 D1+D2 D1+ D2+ D3 D1+D2+D 3+D4 D1+D2+D 3+D4+D5 Expenditure Value of work executed/ (1+ mark- up) Cumulative expenditure F1 F1+F2 F1+F 2+F3 F1+F2+F3 +F4 F1+F2+F3 +F4+F5 loss/profit Difference between cumulative revenues and cumulative expenditure (E-G) 4. RESEARCH SAMPLE The 25 villas used as research sample can be considered as a homogenous sample due to the fact that all of cases are: 1. Accomplished during one year (2011) 2. All contract types were lump sum 3. All villas are located in Muscat. The collected data for the sample was: 1. Time schedule of villa construction 2. Breakdowns of payment scheme 3. Advance payment amount 4. Expected mark-up percentage. 5. RESULTS All the studied 25 villas were subjected to cash flow analysis using five different payment‟s delay periods (0, 1, 2, 3, 4 - week). Table 2 shows results of the cash flow analysis and required minimum fund to keep the execution continues. Table 3 shows the maximum profit earned during the process of construction to be compared with respect to the expected profit for the research sample in different payment delays. 6. DISCUSSION The minimum fund required keeping the sample projects running in case of the five delay periods and the interim maximum profit compared payment delays were shown in Tables 2 and 3 using the procedure set in Table 1. Here discussion of results is presented 6.1 Effect of Payment Delay on the Minimum Fund As to be expected, the minimum fund required for villa construction is directly proportional to the time of payment delay. The rate of change of the percentage of minimum fund required becomes very pronounce in the three-week delay period. In most cases, as the contract value increases the percentage of the minimum fund increases. The average percentage of minimum fund for four weeks delay was found to be 8.5 per cent of the contract value. This fund should be reserved by the contractor, from the working capital, for the four-week scenario of delay in payment. Standard deviation of 1.29 per cent reflects homogenous and consistency of sample regardless of the diversity and random selection of villas. For a medium size villa with contract value of Rial Omani 50,000(USD 129,000)), the contractor has to ensure availability of about R.O. 4,250 for possible delay in payment of four weeks, which is considered reasonable for villa contractors. This low amount of required fund would lead to high competition among villa contractors leading to good quality and
  • 4. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _________________________________________________________________________________________ Volume: 03 Issue: 04 | Apr-2014, Available @ http://www.ijret.org 445 performance in construction industry, at the same time it exposes villa construction business to high competition market. The contractor may proceed with the execution of works without reserved fund utilizing the advance payment of 10 per cent provided that no delay more than one week is guaranteed (rarely happens). Assuring minimum fund for possible delay in payment would assure business continuity and avoid stoppage or delay and enhance contractor reputation. The availability of minimum fund for possible delay would relieve the client from the worry of possible delay in completion and handover of the property. Table 2: Minimum fund vs. payment delay time Villa No. Contract value % Percentage of minimum fund required based on the delay in payments 0 1 2 3 4 1 40000 N/A 0.86 0.86 10.36 10.85 2 41300 N/A 2.98 2.98 8.61 8.61 3 24100 N/A N/A N/A 5.74 5.74 4 43300 N/A 3.77 3.77 3.77 3.77 5 44100 N/A N/A N/A 9.58 9.58 6 55000 N/A 2.98 2.98 8.04 8.04 7 80000 N/A 4.11 4.11 9.37 9.73 8 38260 N/A 7.68 7.68 7.68 7.68 9 67500 N/A N/A N/A 8.45 8.45 10 47800 N/A 3.03 3.03 8.67 8.67 11 64000 N/A 2.98 2.98 8.61 8.61 12 58800 N/A 2.98 2.98 8.61 8.61 13 49100 N/A 2.98 2.98 8.61 8.61 14 56600 N/A N/A N/A 8.61 8.61 15 47100 N/A N/A N/A 8.59 8.59 16 74800 N/A N/A 2.98 8.61 8.61 17 59700 N/A 3.14 3.14 9.08 9.08 18 60700 N/A 2.98 2.98 8.61 8.61 19 59850 N/A N/A N/A 9.58 9.58 20 69000 N/A 2.98 2.98 8.61 8.61 21 120000 N/A 3.3 3.3 3.3 8.05 22 157100 N/A 3.38 3.38 3.38 8.91 23 133000 N/A 3.3 3.3 3.3 8.92 24 145000 N/A 3.3 3.3 3.3 8.92 25 127800 N/A 3.3 3.3 3.3 8.92 Average N/A 3.335 3.32 7.37 8.49 Std. deviation N/A 1.22 1.19 2.37 1.29
  • 5. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _________________________________________________________________________________________ Volume: 03 Issue: 04 | Apr-2014, Available @ http://www.ijret.org 446 Table 3: Interim maximum profit vs. payment delay Villa No. Contract value Advance payment Total expected profit % Interim maximum profit earned 0 1 2 3 4 1 40000 5700 6666.67 5611.11 5611.11 5611.11 5611.11 5611.11 2 41300 4130 6883.33 4908.34 4908.34 4908.34 4908.34 4908.34 3 24100 5510 4106.67 5027.48 5510 5510 5510 5510 4 43300 10735 7216.67 10735 10735 10735 10735 10735 5 44100 4655 7350 5251.8 5251.8 5251.8 5251.8 5251.8 6 55000 5225 9166.67 6536.54 6536.54 6536.54 6536.54 6536.54 7 80000 6700 13333.33 8607.7 8607.7 8607.7 8607.7 8607.7 8 38260 5111 6376.67 5111 5111 5111 5111 5111 9 67500 7125 11250 8038.46 8038.46 8038.46 8038.46 8038.46 10 47800 4515 7966.67 5653.85 5653.85 5653.85 5653.85 5653.85 11 64000 6080 10666.67 7606.15 7606.15 7606.15 7606.15 7606.15 12 58800 5586 9800 6988.14 6988.14 6988.14 6988.14 6988.14 13 49100 5586 8183.33 5835.35 5835.35 5835.35 5835.35 5835.35 14 56600 5377 9433.33 12103.69 12103.69 12103.69 12103.69 12103.69 15 47100 4465 7850 10059.52 10059.52 10059.52 10059.52 10059.52 16 74800 7106 12466.67 8889.692 8889.692 8889.692 8889.692 8889.692 17 59700 5671.5 9950 7095.115 7095.115 7095.115 7095.115 7095.115 18 60700 5766.5 10116.67 7213.962 7213.962 7213.962 7213.962 7213.962 19 59850 6317.5 9975 7127.436 7127.436 7127.436 7127.436 7127.436 20 69000 6555 115000 8200.385 8200.385 8200.385 11327.5 11327.5 21 120000 11400 20000 14177.19 14177.19 14177.19 14177.19 14177.19 22 157100 14905.5 26183.33 18554.18 18554.18 18554.18 18554.18 18554.18 23 133000 12635 22166.67 15713.06 15713.06 15713.06 15713.06 15713.06 24 145000 13775 24166.67 17130.77 17130.77 17130.77 17130.77 17130.77 25 127800 12141 21300 15098.71 15098.71 15098.71 15098.71 15098.71 6.2 Contractual Implications of Cash Flow Forecasting Contractual issue is one of the most essential factors in cash flow forecasting. This factor might help the contractor to increase or decrease the minimum fund required for a construction project. Payment delay is the most effective parameter to be taken into consideration which directly affects the minimum fund required, which has to be recorded clearly in the agreement between the owner and contractor. It would be more beneficial for both parties to include minimum payment delay, to allow certainty of budgeting and cash flow forecasting on contractor‟s side. The client has to ensure timely payment because any delay in payment leads to penalties and may cause stoppage of site works. Most of villa construction agreements are lump sum type in which payments are distributed based on the accomplished works or stage of construction such as (earthworks, substructures, super structure finishes, etc.). A percentage of contract value should be paid after each stage or milestone of the work executed. The distribution of payments on the time schedule is the second spot to be controlled, this distribution should assure minimum payment for contractor and avoid over payment by owner. Contractor‟s inability to meet minimum fund required for cash outflow would prevent achievement of contractual obligations and lead to delay of some activities at the site. The failure to
  • 6. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _________________________________________________________________________________________ Volume: 03 Issue: 04 | Apr-2014, Available @ http://www.ijret.org 447 fulfil contractor‟s obligation towards suppliers and subcontractors is another consequence of this problem. Inability of payment by client is a source of disturbance for contractor time schedule in this and other projects and affects his whole operations of contracting. Some contractors keep their contractual side free of surprises in terms of client payment inability by assuring availability of different projects to utilize his workforce and equipment in case of stoppage at one site. Usually, this type of contractors stop the work till payment and penalties of delay are received. On the other side, there is a risk generated through the problem of payments which lead to higher interim profit than the maximum expected. In this case the contractor has received his profit in advance and the future interim payments will be much less or of no profit. This case has been noticed in the collected records particularly in case no. 14 and 15. Here, the possibility of the contractor leaving or stopping the works is higher as he knows future cash inflow may not be enough to cover the cash outflow. 7. CONCLUSIONS From the study made in this research, the following concluding remarks can be made;  Cash flow forecasting and management are perfect tools to avoid risk of incompletion of construction projects.  Properly planned and sized, timely interim payments reduce the risk of imbalance cash in and out flows.  There is a proportional relationship between payment delay and minimum fund required for villa construction. It was found that the contractor can start construction without any minimum fund by utilizing the advance payment, provided that delay in interim payment is guaranteed to be less than one week.  The distribution of payments should be carefully designed based on milestone achievement related to detailed cost estimate to avoid fund shortage leading to stoppage of the construction process and to ensure that contractor does not receive large profit at early stages of the project.  The minimum fund required for a contractor to secure completion of villa construction is 8.5 per cent of the total contract value. This percentage is required for a maximum delay in interim payment of four weeks.  A clear record should be made in the contract that explicitly defines ways of handling payment delays, penalties and work stoppage allowances. REFERENCES [1] Sears S. K., Sears, G. A., and Clough, R. H., (2008). “Construction Project Management -A Practical Guide to Field Construction Management”, 5th Ed., John Willey, 272-274 [2] Lucko, G. and Richard, C. Th. Jr. (2012), “derivation and assessment of interest in cash flow calculations for time-cost optimizations in construction project management” Proceedings of the 2010 Winter Simulation Conference. [3] Mincks ,William R., and Johnston, H., (2004). Construction Jobsite Management, 2nd , Thomson Delmar Learning, 388-389 [4] Odeyinka, H. A., Kaka, A. (2005) "An evaluation of contractors‟ satisfaction with payment terms influencing construction cash flow", Journal of Financial Management of Property and Construction, 10(3), 171 - 180 [5] Park, H., Han, S., and Russell, J. (2005). ”Cash Flow Forecasting Model for General Contractors Using Moving Weights of Cost Categories.” Jouranl Management in Engineering, 21(4), 164–172. [6] Odeyinka, H. A., Lowe, J., and Kaka,A. (2008) "An evaluation of risk factors impacting construction cash flow forecast", Journal of Financial Management of Property and Construction, 13(1), 5 - 17 [7] Senouci, A. and El-Rayes, K., (2009). “Time-Profit Trade-Off Analysis for Construction Projects” Journal of Construction Engineering and Management, 135(8), 718–725. [8] Al-Ali,A. , Ustadi, A., Abdulla, Galadari, A., and Al- Yousuf (2010) “Deciding the Way Forward of Construction Contracts during Cash Flow Deficits”, International Conference on Financial Theory and Engineering [9] AbHalim, M.S., Jaafar, M., Osman, O. and SherAkbar, (2010). “The Contracting Firm‟s Failure and Financial Related Factors: A Case Study of Malaysian Contracting Firms”, International Research Journal of Finance and Economics, Oct. 52 , 28-39 [10] Liu, S. and Wang, C. ,(2010).” Profit Optimization for Multiproject Scheduling Problems Considering Cash Flow” Journal of Construction Engineering and Management, 136(12), 1268–1278. [11] Memon, A. H., Abdul Rahman, I., Abdullah, M. R., Abdu Aziz, A. A. (2010) “Factors Affecting Construction Cost in Mara Large Construction Project: Perspective of Project Management Consultant” International Journal of Sustainable Construction Engineering & Technology, 1(2), 41-54