SlideShare a Scribd company logo
1 of 30
Royal Lake: Meeting Agenda
 Introductions and Opening Remarks
 Project Goal and Status
 Royal Lake Conditions
 Project Overview
 Site Access
 Dredging
– Phase I and Phase II
– Dredging Alternatives
 Lake Habitat and Shoreline Restoration
 Project Timeline
 Questions and Answers
 Restore Sediment Pool Capacity
– Downstream water quality benefits
– Lake water quality
– Aesthetics
 Improve Lake Water Quality and Habitat
 Provide Long Term Maintenance Improvements
Project Goals and Benefits
 Completed Data Collection
 Completed Lake Dredging and Management Plan
 Design Plans and Specifications
– Preliminary Design – Completed
– Final Design – Current design phase
 Permitting – In Progress
 Late 2014/Early 2015 – Complete Final Design and Permitting
 Dredging Projected to Start in Late Summer, 2015
Royal Lake: Project Status
Royal Lake Facts
 Drainage Area =
2,477 acres (3.67 square miles)
 Lake Surface Area =
37.5 acres
 Sediment Pool Capacity =
416,000 cubic yards (CY)
 Current Sediment in Lake = 103,000
CY*
 Estimated Annual Sediment Load =
4,400 CY
50 feet
103,000 CY
* Based on a 2013 bathymetric survey
Royal Lake: Sediment
Thickness
Royal Lake: Water Depth
Royal Lake: Sediment
Sampling Results
 Samples were analyzed for chemicals found in typical urban
environments
 All tests indicated significantly lower concentrations than state
limits except for Arsenic
 Nitrogen and Phosphorous levels were elevated
 With dredging of 103,000 CY:
– Approximately 8,500 lbs of Phosphorous will be removed
– Approximately 102,000 lbs of Nitrogen will be removed
 Total Wetlands
Impact:
– 0.85 Acre
 All impacts
within original
footprint of
lake
Royal Lake – Wetland Impact
Project Overview
Staging Areas
Sediment Forebays Lake grading to
restore the original
bottom elevation
Site Access and Staging
Access During Construction
Public Access:
The park will remain
open and existing
parking lot will be
available.
Access During Construction
Public Access:
Pedestrian gates will be provided. Access through work areas and trails around the lake will
be possible after work hours.
Staging Area 1 Potential
Expansion
Berm/Cofferdam
to be built
Area to be dewatered and
backfilled to expand staging
area after berm/cofferdam
is built
Royal Lake: Dewatering Basin
Inactive dewatering basin
to be filled in and restored
Staging area
potential
expansion
Phase I and Phase II Dredging
PHASE II
48,000 CY
PHASE I
15,000 CY
PHASE I
40,000 CY
Dredging Alternatives
1. Wet Dredging: Mechanically dredge deposited
sediment and haul wet. Normal pool maintained.
(Note: This option will still require lake drawdown for
a short period of time to build the forebay berms)
2. Dry Dredging: Drain the lake and dry deposited
sediment in place prior to hauling
3. Project will be bid out with the option to dredge wet
or dry
Partial drawdown for Phase I dry dredging: drawing the
lake partially to the Phase I dredging limits would leave a
15 acre pool; sediment would be dried in the dewatered
section of the lake in place prior to hauling. Approximately
1/2 of the deposited sediment volume would be removed.
 General Sequence
– Establish access and staging areas
– Conduct dredging utilizing barges
– Haul wet sediment to disposal site
for drying
 Pros
– Less weather dependent
– Quicker initial start to dredging
– Less potential for schedule
extensions or delay
 Concerns
– Increased sediment handling effort
at disposal area
– Potentially higher cost
Wet Dredging
 General Sequence
– Initiate drawdown of lake
– Establish access and staging areas
– Establish diversion channels within lake
– Conduct dredging
 Benefits
– Higher daily sediment removal rates
– Minimal sediment handling effort at disposal
area
– Potentially lower cost
 Concerns
– Very weather dependent
– Higher potential for delays due to weather
– Even with a reduced pool, there will be a need
to relocate/salvage fish
Dry Dredging (Full or Partial
Drawdown)
Royal Lake: Partial Drawdown
 A partial drawdown would leave 15 acre
pool with a maximum depth of 8 feet
 Sediment to be removed = 55,000 CY
DRAW-DOWN 55,000 CY
Huntsman Lake (29 acres)
Huntsman Lake – Currently being dredged in the dry
Huntsman Lake Dam Rehabilitation Project Fish Relocation (May, 2013)
Huntsman Lake Improvements
forebay
forebay berms
dam
embankment
Phase I dredging limits (34,500 CY)
Huntsman Lake Improvements
Huntsman Lake Dredging
June, 2014
 In-lake forebay
 Wetland planting
 Shoreline stabilization
 Fish habitat
 Fish stocking
Royal Lake Restoration
Fish habitat created
from salvaged trees
Lake Barton:
Fish stocking by Virginia Game and Inland Fisheries
Royal Lake: Shoreline
Restoration
Shoreline Protection
Fish Habitat Structures
 Community coordination at design and construction phase
– Pardon Our Dust meeting to be scheduled after contractor selection
 Late 2014/Early 2015: Complete final design
 Spring 2015: Bid advertisement
 Late summer 2015: Begin dredging
 Project Duration:
– Phase 1, Base Dredge: Dredge approximately 55,000 CY = 5 to 6 Months
– Phase 2, Full Dredge: 9 to 12 Months (total)
 Lake may be drained/partially drained for project depending on bid results
 For the wet dredge option, the lake will still require lowering for a short
period to construct the forebays
Royal Lake Dredging and Restoration
Project Timeline and Coordination
Contacts:
Martin Chang
martin.chang@fairfaxcounty.gov
Dipmani Kumar
dipmani.kumar@fairfaxcounty.gov
Matt Meyers
matthew.meyers@fairfaxcounty.gov
Stormwater Planning Division
Fairfax County DPWES
(703)324-5500, TY 711
Partners:
Royal Lake Dredging and
Restoration

More Related Content

What's hot

Crook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration ProjectCrook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration ProjectFairfax County
 
Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust” Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust” Fairfax County
 
Dead Run Stream Restoration Public meeting February 18, 2015
Dead Run Stream Restoration Public meeting February 18, 2015Dead Run Stream Restoration Public meeting February 18, 2015
Dead Run Stream Restoration Public meeting February 18, 2015Fairfax County
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationWoodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationFairfax County
 
Dizak, Earth Conservancy, "AMD Treatment Alternatives and Reclamation of Mine...
Dizak, Earth Conservancy, "AMD Treatment Alternatives and Reclamation of Mine...Dizak, Earth Conservancy, "AMD Treatment Alternatives and Reclamation of Mine...
Dizak, Earth Conservancy, "AMD Treatment Alternatives and Reclamation of Mine...Michael Hewitt, GISP
 
Tripps Run Stream Improvement
Tripps Run Stream ImprovementTripps Run Stream Improvement
Tripps Run Stream ImprovementFairfax County
 
Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013
Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013
Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013Fairfax County
 
Habitat Improvement for Cleaner Water
Habitat Improvement for Cleaner WaterHabitat Improvement for Cleaner Water
Habitat Improvement for Cleaner WaterFairfax County
 
Dead Run Stream Restoration Public Meeting June 9, 2015
Dead Run Stream Restoration Public Meeting June 9, 2015Dead Run Stream Restoration Public Meeting June 9, 2015
Dead Run Stream Restoration Public Meeting June 9, 2015Fairfax County
 
ACOE Coastal Storm Management Alternative for Jamaica Bay Communities
ACOE Coastal Storm Management Alternative for Jamaica Bay CommunitiesACOE Coastal Storm Management Alternative for Jamaica Bay Communities
ACOE Coastal Storm Management Alternative for Jamaica Bay Communitiesecowatchers
 
Sequoia Park Pond Retrofit Project
Sequoia Park Pond Retrofit ProjectSequoia Park Pond Retrofit Project
Sequoia Park Pond Retrofit ProjectFairfax County
 
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...Ekonnect
 
Dead Run Stream Restoration Public Meeting April 23, 2014
Dead Run Stream Restoration Public Meeting April 23, 2014Dead Run Stream Restoration Public Meeting April 23, 2014
Dead Run Stream Restoration Public Meeting April 23, 2014Fairfax County
 
Flood Mitigation Project on Overly Drive
Flood Mitigation Project on Overly DriveFlood Mitigation Project on Overly Drive
Flood Mitigation Project on Overly DriveFairfax County
 
Stormwater Management Information Sharing with Shandong Province, China
Stormwater Management Information Sharing with Shandong Province, ChinaStormwater Management Information Sharing with Shandong Province, China
Stormwater Management Information Sharing with Shandong Province, ChinaFairfax County
 
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...Fairfax County
 
Dead Run Stream Restoration Stream Team Kick Off August 18, 2015
Dead Run Stream Restoration Stream Team Kick Off August 18, 2015Dead Run Stream Restoration Stream Team Kick Off August 18, 2015
Dead Run Stream Restoration Stream Team Kick Off August 18, 2015Fairfax County
 
Shawn Rummel, Trout Unlimited, "Recovery of Coldwater Ecosystems Following Tr...
Shawn Rummel, Trout Unlimited, "Recovery of Coldwater Ecosystems Following Tr...Shawn Rummel, Trout Unlimited, "Recovery of Coldwater Ecosystems Following Tr...
Shawn Rummel, Trout Unlimited, "Recovery of Coldwater Ecosystems Following Tr...Michael Hewitt, GISP
 
Weppler jam bay task force 3 nov 21
Weppler jam bay task force  3 nov 21Weppler jam bay task force  3 nov 21
Weppler jam bay task force 3 nov 21ecowatchers
 
Little Pimmit Run at Chesterbrook Road Stream Restoration and Sanitary Reali...
 Little Pimmit Run at Chesterbrook Road Stream Restoration and Sanitary Reali... Little Pimmit Run at Chesterbrook Road Stream Restoration and Sanitary Reali...
Little Pimmit Run at Chesterbrook Road Stream Restoration and Sanitary Reali...Fairfax County
 

What's hot (20)

Crook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration ProjectCrook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration Project
 
Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust” Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust”
 
Dead Run Stream Restoration Public meeting February 18, 2015
Dead Run Stream Restoration Public meeting February 18, 2015Dead Run Stream Restoration Public meeting February 18, 2015
Dead Run Stream Restoration Public meeting February 18, 2015
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationWoodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration
 
Dizak, Earth Conservancy, "AMD Treatment Alternatives and Reclamation of Mine...
Dizak, Earth Conservancy, "AMD Treatment Alternatives and Reclamation of Mine...Dizak, Earth Conservancy, "AMD Treatment Alternatives and Reclamation of Mine...
Dizak, Earth Conservancy, "AMD Treatment Alternatives and Reclamation of Mine...
 
Tripps Run Stream Improvement
Tripps Run Stream ImprovementTripps Run Stream Improvement
Tripps Run Stream Improvement
 
Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013
Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013
Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013
 
Habitat Improvement for Cleaner Water
Habitat Improvement for Cleaner WaterHabitat Improvement for Cleaner Water
Habitat Improvement for Cleaner Water
 
Dead Run Stream Restoration Public Meeting June 9, 2015
Dead Run Stream Restoration Public Meeting June 9, 2015Dead Run Stream Restoration Public Meeting June 9, 2015
Dead Run Stream Restoration Public Meeting June 9, 2015
 
ACOE Coastal Storm Management Alternative for Jamaica Bay Communities
ACOE Coastal Storm Management Alternative for Jamaica Bay CommunitiesACOE Coastal Storm Management Alternative for Jamaica Bay Communities
ACOE Coastal Storm Management Alternative for Jamaica Bay Communities
 
Sequoia Park Pond Retrofit Project
Sequoia Park Pond Retrofit ProjectSequoia Park Pond Retrofit Project
Sequoia Park Pond Retrofit Project
 
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
 
Dead Run Stream Restoration Public Meeting April 23, 2014
Dead Run Stream Restoration Public Meeting April 23, 2014Dead Run Stream Restoration Public Meeting April 23, 2014
Dead Run Stream Restoration Public Meeting April 23, 2014
 
Flood Mitigation Project on Overly Drive
Flood Mitigation Project on Overly DriveFlood Mitigation Project on Overly Drive
Flood Mitigation Project on Overly Drive
 
Stormwater Management Information Sharing with Shandong Province, China
Stormwater Management Information Sharing with Shandong Province, ChinaStormwater Management Information Sharing with Shandong Province, China
Stormwater Management Information Sharing with Shandong Province, China
 
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
 
Dead Run Stream Restoration Stream Team Kick Off August 18, 2015
Dead Run Stream Restoration Stream Team Kick Off August 18, 2015Dead Run Stream Restoration Stream Team Kick Off August 18, 2015
Dead Run Stream Restoration Stream Team Kick Off August 18, 2015
 
Shawn Rummel, Trout Unlimited, "Recovery of Coldwater Ecosystems Following Tr...
Shawn Rummel, Trout Unlimited, "Recovery of Coldwater Ecosystems Following Tr...Shawn Rummel, Trout Unlimited, "Recovery of Coldwater Ecosystems Following Tr...
Shawn Rummel, Trout Unlimited, "Recovery of Coldwater Ecosystems Following Tr...
 
Weppler jam bay task force 3 nov 21
Weppler jam bay task force  3 nov 21Weppler jam bay task force  3 nov 21
Weppler jam bay task force 3 nov 21
 
Little Pimmit Run at Chesterbrook Road Stream Restoration and Sanitary Reali...
 Little Pimmit Run at Chesterbrook Road Stream Restoration and Sanitary Reali... Little Pimmit Run at Chesterbrook Road Stream Restoration and Sanitary Reali...
Little Pimmit Run at Chesterbrook Road Stream Restoration and Sanitary Reali...
 

Viewers also liked

Transportation Funding Discussion: Board Retreat 2012
Transportation Funding Discussion: Board Retreat 2012Transportation Funding Discussion: Board Retreat 2012
Transportation Funding Discussion: Board Retreat 2012Fairfax County
 
Braddock Road Multimodal Study: Guinea Road to I-495
Braddock Road Multimodal Study: Guinea Road to I-495Braddock Road Multimodal Study: Guinea Road to I-495
Braddock Road Multimodal Study: Guinea Road to I-495Fairfax County
 
Economic Success Presentation to the Northern Virginia Building Industry Asso...
Economic Success Presentation to the Northern Virginia Building Industry Asso...Economic Success Presentation to the Northern Virginia Building Industry Asso...
Economic Success Presentation to the Northern Virginia Building Industry Asso...Fairfax County
 
Presentation to MDLUC: May 24, 2016
Presentation to MDLUC: May 24, 2016Presentation to MDLUC: May 24, 2016
Presentation to MDLUC: May 24, 2016Fairfax County
 
Fairfax County Land Use February 2014
Fairfax County Land Use February 2014Fairfax County Land Use February 2014
Fairfax County Land Use February 2014Fairfax County
 
SY2014-2015 Fairfax County Youth Survey Highlights
SY2014-2015 Fairfax County Youth Survey HighlightsSY2014-2015 Fairfax County Youth Survey Highlights
SY2014-2015 Fairfax County Youth Survey HighlightsFairfax County
 
The Health Insurance Marketplace: Basic Information for Fairfax County Employees
The Health Insurance Marketplace: Basic Information for Fairfax County EmployeesThe Health Insurance Marketplace: Basic Information for Fairfax County Employees
The Health Insurance Marketplace: Basic Information for Fairfax County EmployeesFairfax County
 
OCR: Fairfax County Revitalization Program
OCR: Fairfax County Revitalization ProgramOCR: Fairfax County Revitalization Program
OCR: Fairfax County Revitalization ProgramFairfax County
 
Fairfax County Youth Survey School Year 2014-2015: Depression, Suicide and Un...
Fairfax County Youth Survey School Year 2014-2015: Depression, Suicide and Un...Fairfax County Youth Survey School Year 2014-2015: Depression, Suicide and Un...
Fairfax County Youth Survey School Year 2014-2015: Depression, Suicide and Un...Fairfax County
 
Diversion First Overview
Diversion First OverviewDiversion First Overview
Diversion First OverviewFairfax County
 
FY 2017 Fiscal Forecast School Operating Fund
FY 2017 Fiscal Forecast School Operating FundFY 2017 Fiscal Forecast School Operating Fund
FY 2017 Fiscal Forecast School Operating FundFairfax County
 
Strategic Plan to Facilitate the Economic Success of Fairfax County (Jan. 27,...
Strategic Plan to Facilitate the Economic Success of Fairfax County (Jan. 27,...Strategic Plan to Facilitate the Economic Success of Fairfax County (Jan. 27,...
Strategic Plan to Facilitate the Economic Success of Fairfax County (Jan. 27,...Fairfax County
 
NVBIA-NAIOP Presentation
NVBIA-NAIOP Presentation NVBIA-NAIOP Presentation
NVBIA-NAIOP Presentation Fairfax County
 
Lake Development Authority_ CEO
Lake Development Authority_ CEOLake Development Authority_ CEO
Lake Development Authority_ CEOPankaja Date
 
Flatlick Branch - Phase 1 Stream Restoration
Flatlick Branch - Phase 1 Stream RestorationFlatlick Branch - Phase 1 Stream Restoration
Flatlick Branch - Phase 1 Stream RestorationFairfax County
 
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...Fairfax County
 
Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...
Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...
Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...Fairfax County
 
2017 VDOT Repaving and Restriping Reston: Bicycle, Pedestrian and Traffic Saf...
2017 VDOT Repaving and Restriping Reston: Bicycle, Pedestrian and Traffic Saf...2017 VDOT Repaving and Restriping Reston: Bicycle, Pedestrian and Traffic Saf...
2017 VDOT Repaving and Restriping Reston: Bicycle, Pedestrian and Traffic Saf...Fairfax County
 

Viewers also liked (19)

Transportation Funding Discussion: Board Retreat 2012
Transportation Funding Discussion: Board Retreat 2012Transportation Funding Discussion: Board Retreat 2012
Transportation Funding Discussion: Board Retreat 2012
 
Braddock Road Multimodal Study: Guinea Road to I-495
Braddock Road Multimodal Study: Guinea Road to I-495Braddock Road Multimodal Study: Guinea Road to I-495
Braddock Road Multimodal Study: Guinea Road to I-495
 
Muskegon Lake Restoration: A Success Story
Muskegon Lake Restoration: A Success StoryMuskegon Lake Restoration: A Success Story
Muskegon Lake Restoration: A Success Story
 
Economic Success Presentation to the Northern Virginia Building Industry Asso...
Economic Success Presentation to the Northern Virginia Building Industry Asso...Economic Success Presentation to the Northern Virginia Building Industry Asso...
Economic Success Presentation to the Northern Virginia Building Industry Asso...
 
Presentation to MDLUC: May 24, 2016
Presentation to MDLUC: May 24, 2016Presentation to MDLUC: May 24, 2016
Presentation to MDLUC: May 24, 2016
 
Fairfax County Land Use February 2014
Fairfax County Land Use February 2014Fairfax County Land Use February 2014
Fairfax County Land Use February 2014
 
SY2014-2015 Fairfax County Youth Survey Highlights
SY2014-2015 Fairfax County Youth Survey HighlightsSY2014-2015 Fairfax County Youth Survey Highlights
SY2014-2015 Fairfax County Youth Survey Highlights
 
The Health Insurance Marketplace: Basic Information for Fairfax County Employees
The Health Insurance Marketplace: Basic Information for Fairfax County EmployeesThe Health Insurance Marketplace: Basic Information for Fairfax County Employees
The Health Insurance Marketplace: Basic Information for Fairfax County Employees
 
OCR: Fairfax County Revitalization Program
OCR: Fairfax County Revitalization ProgramOCR: Fairfax County Revitalization Program
OCR: Fairfax County Revitalization Program
 
Fairfax County Youth Survey School Year 2014-2015: Depression, Suicide and Un...
Fairfax County Youth Survey School Year 2014-2015: Depression, Suicide and Un...Fairfax County Youth Survey School Year 2014-2015: Depression, Suicide and Un...
Fairfax County Youth Survey School Year 2014-2015: Depression, Suicide and Un...
 
Diversion First Overview
Diversion First OverviewDiversion First Overview
Diversion First Overview
 
FY 2017 Fiscal Forecast School Operating Fund
FY 2017 Fiscal Forecast School Operating FundFY 2017 Fiscal Forecast School Operating Fund
FY 2017 Fiscal Forecast School Operating Fund
 
Strategic Plan to Facilitate the Economic Success of Fairfax County (Jan. 27,...
Strategic Plan to Facilitate the Economic Success of Fairfax County (Jan. 27,...Strategic Plan to Facilitate the Economic Success of Fairfax County (Jan. 27,...
Strategic Plan to Facilitate the Economic Success of Fairfax County (Jan. 27,...
 
NVBIA-NAIOP Presentation
NVBIA-NAIOP Presentation NVBIA-NAIOP Presentation
NVBIA-NAIOP Presentation
 
Lake Development Authority_ CEO
Lake Development Authority_ CEOLake Development Authority_ CEO
Lake Development Authority_ CEO
 
Flatlick Branch - Phase 1 Stream Restoration
Flatlick Branch - Phase 1 Stream RestorationFlatlick Branch - Phase 1 Stream Restoration
Flatlick Branch - Phase 1 Stream Restoration
 
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...
 
Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...
Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...
Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...
 
2017 VDOT Repaving and Restriping Reston: Bicycle, Pedestrian and Traffic Saf...
2017 VDOT Repaving and Restriping Reston: Bicycle, Pedestrian and Traffic Saf...2017 VDOT Repaving and Restriping Reston: Bicycle, Pedestrian and Traffic Saf...
2017 VDOT Repaving and Restriping Reston: Bicycle, Pedestrian and Traffic Saf...
 

Similar to Royal Lake Dredging and Restoration Project Update-June 2014

Feb 11 2014 public meeting show
Feb 11 2014 public meeting showFeb 11 2014 public meeting show
Feb 11 2014 public meeting showMCDEP
 
Feb 11 2014 public meeting
Feb 11 2014 public meetingFeb 11 2014 public meeting
Feb 11 2014 public meetingMCDEP
 
Huntsman Lake Dredging January 2015
Huntsman Lake Dredging January 2015Huntsman Lake Dredging January 2015
Huntsman Lake Dredging January 2015Fairfax County
 
Abberton ICE Meeting
Abberton ICE MeetingAbberton ICE Meeting
Abberton ICE MeetingICEEssex
 
Abberton ICE Meeting
Abberton ICE MeetingAbberton ICE Meeting
Abberton ICE MeetingICEEssex
 
Planning of reservoir
Planning of reservoirPlanning of reservoir
Planning of reservoirnumber113
 
Rury 206PM Room B_Integr Hab Restor & Stormwater Treat
Rury 206PM Room B_Integr Hab Restor & Stormwater TreatRury 206PM Room B_Integr Hab Restor & Stormwater Treat
Rury 206PM Room B_Integr Hab Restor & Stormwater TreatPhillip Rury
 
Accotink Tributary at Danbury Forest
Accotink Tributary at Danbury ForestAccotink Tributary at Danbury Forest
Accotink Tributary at Danbury ForestFairfax County
 
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...Ekonnect Knowledge Foundation
 
Dam Removal and Stream Restoration
Dam Removal and Stream RestorationDam Removal and Stream Restoration
Dam Removal and Stream Restorationkylejanco
 
IID ASCE_Red Hill Bay projecy-10.26a.16
IID ASCE_Red Hill Bay projecy-10.26a.16IID ASCE_Red Hill Bay projecy-10.26a.16
IID ASCE_Red Hill Bay projecy-10.26a.16Graeme Donaldson
 
A New Reservoir Project 30 Years in the Making - Tom Kula and Mike Rickman
A New Reservoir Project 30 Years in the Making - Tom Kula and Mike RickmanA New Reservoir Project 30 Years in the Making - Tom Kula and Mike Rickman
A New Reservoir Project 30 Years in the Making - Tom Kula and Mike RickmanTWCA
 
Paul Spring Branch at Sherwood Hall Stream Restoration Project
Paul Spring Branch at Sherwood Hall Stream Restoration ProjectPaul Spring Branch at Sherwood Hall Stream Restoration Project
Paul Spring Branch at Sherwood Hall Stream Restoration ProjectFairfax County
 

Similar to Royal Lake Dredging and Restoration Project Update-June 2014 (20)

Feb 11 2014 public meeting show
Feb 11 2014 public meeting showFeb 11 2014 public meeting show
Feb 11 2014 public meeting show
 
Lecture 5
Lecture 5Lecture 5
Lecture 5
 
Feb 11 2014 public meeting
Feb 11 2014 public meetingFeb 11 2014 public meeting
Feb 11 2014 public meeting
 
Huntsman Lake Dredging January 2015
Huntsman Lake Dredging January 2015Huntsman Lake Dredging January 2015
Huntsman Lake Dredging January 2015
 
Abberton ICE Meeting
Abberton ICE MeetingAbberton ICE Meeting
Abberton ICE Meeting
 
Abberton ICE Meeting
Abberton ICE MeetingAbberton ICE Meeting
Abberton ICE Meeting
 
10. Restoring the River Camac - Mary-Liz Walshe, DCC
10. Restoring the River Camac - Mary-Liz Walshe, DCC10. Restoring the River Camac - Mary-Liz Walshe, DCC
10. Restoring the River Camac - Mary-Liz Walshe, DCC
 
Orlando 2015
Orlando 2015Orlando 2015
Orlando 2015
 
Planning of reservoir
Planning of reservoirPlanning of reservoir
Planning of reservoir
 
Rury 206PM Room B_Integr Hab Restor & Stormwater Treat
Rury 206PM Room B_Integr Hab Restor & Stormwater TreatRury 206PM Room B_Integr Hab Restor & Stormwater Treat
Rury 206PM Room B_Integr Hab Restor & Stormwater Treat
 
Stream rehabilitation seminar june 11 2014
Stream rehabilitation seminar june 11 2014Stream rehabilitation seminar june 11 2014
Stream rehabilitation seminar june 11 2014
 
Accotink Tributary at Danbury Forest
Accotink Tributary at Danbury ForestAccotink Tributary at Danbury Forest
Accotink Tributary at Danbury Forest
 
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
 
Dam Removal and Stream Restoration
Dam Removal and Stream RestorationDam Removal and Stream Restoration
Dam Removal and Stream Restoration
 
Truckee River Restoration
Truckee River RestorationTruckee River Restoration
Truckee River Restoration
 
IID ASCE_Red Hill Bay projecy-10.26a.16
IID ASCE_Red Hill Bay projecy-10.26a.16IID ASCE_Red Hill Bay projecy-10.26a.16
IID ASCE_Red Hill Bay projecy-10.26a.16
 
A New Reservoir Project 30 Years in the Making - Tom Kula and Mike Rickman
A New Reservoir Project 30 Years in the Making - Tom Kula and Mike RickmanA New Reservoir Project 30 Years in the Making - Tom Kula and Mike Rickman
A New Reservoir Project 30 Years in the Making - Tom Kula and Mike Rickman
 
Lake shady plans
Lake shady plansLake shady plans
Lake shady plans
 
Paul Spring Branch at Sherwood Hall Stream Restoration Project
Paul Spring Branch at Sherwood Hall Stream Restoration ProjectPaul Spring Branch at Sherwood Hall Stream Restoration Project
Paul Spring Branch at Sherwood Hall Stream Restoration Project
 
Calbiga River Care
Calbiga River CareCalbiga River Care
Calbiga River Care
 

More from Fairfax County

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS Fairfax County
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22Fairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19 Fairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction ProgressFairfax County
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IVFairfax County
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxFairfax County
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilFairfax County
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap UpFairfax County
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
 

More from Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 

Recently uploaded

Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost LoverPowerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost LoverPsychicRuben LoveSpells
 
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...srinuseo15
 
05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's DevelopmentNara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Developmentnarsireddynannuri1
 
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...hyt3577
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)Delhi Call girls
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)Delhi Call girls
 
04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Kishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdfKishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdfKISHAN REDDY OFFICE
 
Busty Desi⚡Call Girls in Sector 62 Noida Escorts >༒8448380779 Escort Service
Busty Desi⚡Call Girls in Sector 62 Noida Escorts >༒8448380779 Escort ServiceBusty Desi⚡Call Girls in Sector 62 Noida Escorts >༒8448380779 Escort Service
Busty Desi⚡Call Girls in Sector 62 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
1971 war india pakistan bangladesh liberation.ppt
1971 war india pakistan bangladesh liberation.ppt1971 war india pakistan bangladesh liberation.ppt
1971 war india pakistan bangladesh liberation.pptsammehtumblr
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)Delhi Call girls
 
06052024_First India Newspaper Jaipur.pdf
06052024_First India Newspaper Jaipur.pdf06052024_First India Newspaper Jaipur.pdf
06052024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreieGujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreiebhavenpr
 
China's soft power in 21st century .pptx
China's soft power in 21st century   .pptxChina's soft power in 21st century   .pptx
China's soft power in 21st century .pptxYasinAhmad20
 
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...Faga1939
 
Julius Randle's Injury Status: Surgery Not Off the Table
Julius Randle's Injury Status: Surgery Not Off the TableJulius Randle's Injury Status: Surgery Not Off the Table
Julius Randle's Injury Status: Surgery Not Off the Tableget joys
 
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)Delhi Call girls
 
Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...
Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...
Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...narsireddynannuri1
 
₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...
₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...
₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...Diya Sharma
 

Recently uploaded (20)

Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost LoverPowerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
 
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
 
05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf
 
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's DevelopmentNara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
 
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)
 
04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf
 
Kishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdfKishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdf
 
Busty Desi⚡Call Girls in Sector 62 Noida Escorts >༒8448380779 Escort Service
Busty Desi⚡Call Girls in Sector 62 Noida Escorts >༒8448380779 Escort ServiceBusty Desi⚡Call Girls in Sector 62 Noida Escorts >༒8448380779 Escort Service
Busty Desi⚡Call Girls in Sector 62 Noida Escorts >༒8448380779 Escort Service
 
1971 war india pakistan bangladesh liberation.ppt
1971 war india pakistan bangladesh liberation.ppt1971 war india pakistan bangladesh liberation.ppt
1971 war india pakistan bangladesh liberation.ppt
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
 
06052024_First India Newspaper Jaipur.pdf
06052024_First India Newspaper Jaipur.pdf06052024_First India Newspaper Jaipur.pdf
06052024_First India Newspaper Jaipur.pdf
 
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreieGujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
 
China's soft power in 21st century .pptx
China's soft power in 21st century   .pptxChina's soft power in 21st century   .pptx
China's soft power in 21st century .pptx
 
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
 
Julius Randle's Injury Status: Surgery Not Off the Table
Julius Randle's Injury Status: Surgery Not Off the TableJulius Randle's Injury Status: Surgery Not Off the Table
Julius Randle's Injury Status: Surgery Not Off the Table
 
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
 
Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...
Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...
Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...
 
₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...
₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...
₹5.5k {Cash Payment} Independent Greater Noida Call Girls In [Delhi INAYA] 🔝|...
 

Royal Lake Dredging and Restoration Project Update-June 2014

  • 1.
  • 2. Royal Lake: Meeting Agenda  Introductions and Opening Remarks  Project Goal and Status  Royal Lake Conditions  Project Overview  Site Access  Dredging – Phase I and Phase II – Dredging Alternatives  Lake Habitat and Shoreline Restoration  Project Timeline  Questions and Answers
  • 3.  Restore Sediment Pool Capacity – Downstream water quality benefits – Lake water quality – Aesthetics  Improve Lake Water Quality and Habitat  Provide Long Term Maintenance Improvements Project Goals and Benefits
  • 4.  Completed Data Collection  Completed Lake Dredging and Management Plan  Design Plans and Specifications – Preliminary Design – Completed – Final Design – Current design phase  Permitting – In Progress  Late 2014/Early 2015 – Complete Final Design and Permitting  Dredging Projected to Start in Late Summer, 2015 Royal Lake: Project Status
  • 5. Royal Lake Facts  Drainage Area = 2,477 acres (3.67 square miles)  Lake Surface Area = 37.5 acres  Sediment Pool Capacity = 416,000 cubic yards (CY)  Current Sediment in Lake = 103,000 CY*  Estimated Annual Sediment Load = 4,400 CY 50 feet 103,000 CY * Based on a 2013 bathymetric survey
  • 8. Royal Lake: Sediment Sampling Results  Samples were analyzed for chemicals found in typical urban environments  All tests indicated significantly lower concentrations than state limits except for Arsenic  Nitrogen and Phosphorous levels were elevated  With dredging of 103,000 CY: – Approximately 8,500 lbs of Phosphorous will be removed – Approximately 102,000 lbs of Nitrogen will be removed
  • 9.  Total Wetlands Impact: – 0.85 Acre  All impacts within original footprint of lake Royal Lake – Wetland Impact
  • 10. Project Overview Staging Areas Sediment Forebays Lake grading to restore the original bottom elevation
  • 11. Site Access and Staging
  • 12. Access During Construction Public Access: The park will remain open and existing parking lot will be available.
  • 13. Access During Construction Public Access: Pedestrian gates will be provided. Access through work areas and trails around the lake will be possible after work hours.
  • 14. Staging Area 1 Potential Expansion Berm/Cofferdam to be built Area to be dewatered and backfilled to expand staging area after berm/cofferdam is built
  • 15. Royal Lake: Dewatering Basin Inactive dewatering basin to be filled in and restored Staging area potential expansion
  • 16. Phase I and Phase II Dredging PHASE II 48,000 CY PHASE I 15,000 CY PHASE I 40,000 CY
  • 17. Dredging Alternatives 1. Wet Dredging: Mechanically dredge deposited sediment and haul wet. Normal pool maintained. (Note: This option will still require lake drawdown for a short period of time to build the forebay berms) 2. Dry Dredging: Drain the lake and dry deposited sediment in place prior to hauling 3. Project will be bid out with the option to dredge wet or dry Partial drawdown for Phase I dry dredging: drawing the lake partially to the Phase I dredging limits would leave a 15 acre pool; sediment would be dried in the dewatered section of the lake in place prior to hauling. Approximately 1/2 of the deposited sediment volume would be removed.
  • 18.  General Sequence – Establish access and staging areas – Conduct dredging utilizing barges – Haul wet sediment to disposal site for drying  Pros – Less weather dependent – Quicker initial start to dredging – Less potential for schedule extensions or delay  Concerns – Increased sediment handling effort at disposal area – Potentially higher cost Wet Dredging
  • 19.  General Sequence – Initiate drawdown of lake – Establish access and staging areas – Establish diversion channels within lake – Conduct dredging  Benefits – Higher daily sediment removal rates – Minimal sediment handling effort at disposal area – Potentially lower cost  Concerns – Very weather dependent – Higher potential for delays due to weather – Even with a reduced pool, there will be a need to relocate/salvage fish Dry Dredging (Full or Partial Drawdown)
  • 20. Royal Lake: Partial Drawdown  A partial drawdown would leave 15 acre pool with a maximum depth of 8 feet  Sediment to be removed = 55,000 CY DRAW-DOWN 55,000 CY
  • 21. Huntsman Lake (29 acres) Huntsman Lake – Currently being dredged in the dry
  • 22. Huntsman Lake Dam Rehabilitation Project Fish Relocation (May, 2013)
  • 23. Huntsman Lake Improvements forebay forebay berms dam embankment Phase I dredging limits (34,500 CY) Huntsman Lake Improvements
  • 25.  In-lake forebay  Wetland planting  Shoreline stabilization  Fish habitat  Fish stocking Royal Lake Restoration Fish habitat created from salvaged trees Lake Barton: Fish stocking by Virginia Game and Inland Fisheries
  • 29.  Community coordination at design and construction phase – Pardon Our Dust meeting to be scheduled after contractor selection  Late 2014/Early 2015: Complete final design  Spring 2015: Bid advertisement  Late summer 2015: Begin dredging  Project Duration: – Phase 1, Base Dredge: Dredge approximately 55,000 CY = 5 to 6 Months – Phase 2, Full Dredge: 9 to 12 Months (total)  Lake may be drained/partially drained for project depending on bid results  For the wet dredge option, the lake will still require lowering for a short period to construct the forebays Royal Lake Dredging and Restoration Project Timeline and Coordination
  • 30. Contacts: Martin Chang martin.chang@fairfaxcounty.gov Dipmani Kumar dipmani.kumar@fairfaxcounty.gov Matt Meyers matthew.meyers@fairfaxcounty.gov Stormwater Planning Division Fairfax County DPWES (703)324-5500, TY 711 Partners: Royal Lake Dredging and Restoration

Editor's Notes

  1. 32,500/160,000 = 20.3% Land Use in Drainage Area by Type, Acres and Percentage Residential/Business, 522 acres, 70.5% Woodland, 118 acres, 15.9% Transportation, 79 acres, 10.7% Water, 13 acres, 1.8% Grassland, 8 acres, 1.1% Total = 740 acres Floodpool of Woodglen Lake = 36 acres Land Ownership: Upstream of dam: 79% private, 21% public Downstream of dam: 47% private, 53% public
  2. 65,000 CY/295,000 CY = 22 percent full
  3. 32,500/160,000 = 20.3% Land Use in Drainage Area by Type, Acres and Percentage Residential/Business, 522 acres, 70.5% Woodland, 118 acres, 15.9% Transportation, 79 acres, 10.7% Water, 13 acres, 1.8% Grassland, 8 acres, 1.1% Total = 740 acres Floodpool of Woodglen Lake = 36 acres Land Ownership: Upstream of dam: 79% private, 21% public Downstream of dam: 47% private, 53% public
  4. Built in 1973 as a flood-control dam
  5. Built in 1973 as a flood-control dam
  6. Built in 1973 as a flood-control dam