Royal Lake Dredging and Restoration Project Update-June 2014
1.
2. Royal Lake: Meeting Agenda
Introductions and Opening Remarks
Project Goal and Status
Royal Lake Conditions
Project Overview
Site Access
Dredging
– Phase I and Phase II
– Dredging Alternatives
Lake Habitat and Shoreline Restoration
Project Timeline
Questions and Answers
3. Restore Sediment Pool Capacity
– Downstream water quality benefits
– Lake water quality
– Aesthetics
Improve Lake Water Quality and Habitat
Provide Long Term Maintenance Improvements
Project Goals and Benefits
4. Completed Data Collection
Completed Lake Dredging and Management Plan
Design Plans and Specifications
– Preliminary Design – Completed
– Final Design – Current design phase
Permitting – In Progress
Late 2014/Early 2015 – Complete Final Design and Permitting
Dredging Projected to Start in Late Summer, 2015
Royal Lake: Project Status
5. Royal Lake Facts
Drainage Area =
2,477 acres (3.67 square miles)
Lake Surface Area =
37.5 acres
Sediment Pool Capacity =
416,000 cubic yards (CY)
Current Sediment in Lake = 103,000
CY*
Estimated Annual Sediment Load =
4,400 CY
50 feet
103,000 CY
* Based on a 2013 bathymetric survey
8. Royal Lake: Sediment
Sampling Results
Samples were analyzed for chemicals found in typical urban
environments
All tests indicated significantly lower concentrations than state
limits except for Arsenic
Nitrogen and Phosphorous levels were elevated
With dredging of 103,000 CY:
– Approximately 8,500 lbs of Phosphorous will be removed
– Approximately 102,000 lbs of Nitrogen will be removed
9. Total Wetlands
Impact:
– 0.85 Acre
All impacts
within original
footprint of
lake
Royal Lake – Wetland Impact
13. Access During Construction
Public Access:
Pedestrian gates will be provided. Access through work areas and trails around the lake will
be possible after work hours.
14. Staging Area 1 Potential
Expansion
Berm/Cofferdam
to be built
Area to be dewatered and
backfilled to expand staging
area after berm/cofferdam
is built
15. Royal Lake: Dewatering Basin
Inactive dewatering basin
to be filled in and restored
Staging area
potential
expansion
16. Phase I and Phase II Dredging
PHASE II
48,000 CY
PHASE I
15,000 CY
PHASE I
40,000 CY
17. Dredging Alternatives
1. Wet Dredging: Mechanically dredge deposited
sediment and haul wet. Normal pool maintained.
(Note: This option will still require lake drawdown for
a short period of time to build the forebay berms)
2. Dry Dredging: Drain the lake and dry deposited
sediment in place prior to hauling
3. Project will be bid out with the option to dredge wet
or dry
Partial drawdown for Phase I dry dredging: drawing the
lake partially to the Phase I dredging limits would leave a
15 acre pool; sediment would be dried in the dewatered
section of the lake in place prior to hauling. Approximately
1/2 of the deposited sediment volume would be removed.
18. General Sequence
– Establish access and staging areas
– Conduct dredging utilizing barges
– Haul wet sediment to disposal site
for drying
Pros
– Less weather dependent
– Quicker initial start to dredging
– Less potential for schedule
extensions or delay
Concerns
– Increased sediment handling effort
at disposal area
– Potentially higher cost
Wet Dredging
19. General Sequence
– Initiate drawdown of lake
– Establish access and staging areas
– Establish diversion channels within lake
– Conduct dredging
Benefits
– Higher daily sediment removal rates
– Minimal sediment handling effort at disposal
area
– Potentially lower cost
Concerns
– Very weather dependent
– Higher potential for delays due to weather
– Even with a reduced pool, there will be a need
to relocate/salvage fish
Dry Dredging (Full or Partial
Drawdown)
20. Royal Lake: Partial Drawdown
A partial drawdown would leave 15 acre
pool with a maximum depth of 8 feet
Sediment to be removed = 55,000 CY
DRAW-DOWN 55,000 CY
21. Huntsman Lake (29 acres)
Huntsman Lake – Currently being dredged in the dry
22. Huntsman Lake Dam Rehabilitation Project Fish Relocation (May, 2013)
25. In-lake forebay
Wetland planting
Shoreline stabilization
Fish habitat
Fish stocking
Royal Lake Restoration
Fish habitat created
from salvaged trees
Lake Barton:
Fish stocking by Virginia Game and Inland Fisheries
29. Community coordination at design and construction phase
– Pardon Our Dust meeting to be scheduled after contractor selection
Late 2014/Early 2015: Complete final design
Spring 2015: Bid advertisement
Late summer 2015: Begin dredging
Project Duration:
– Phase 1, Base Dredge: Dredge approximately 55,000 CY = 5 to 6 Months
– Phase 2, Full Dredge: 9 to 12 Months (total)
Lake may be drained/partially drained for project depending on bid results
For the wet dredge option, the lake will still require lowering for a short
period to construct the forebays
Royal Lake Dredging and Restoration
Project Timeline and Coordination
32,500/160,000 = 20.3%
Land Use in Drainage Area by Type, Acres and Percentage
Residential/Business, 522 acres, 70.5%
Woodland, 118 acres, 15.9%
Transportation, 79 acres, 10.7%
Water, 13 acres, 1.8%
Grassland, 8 acres, 1.1%
Total = 740 acres
Floodpool of Woodglen Lake = 36 acres
Land Ownership:
Upstream of dam: 79% private, 21% public
Downstream of dam: 47% private, 53% public
65,000 CY/295,000 CY = 22 percent full
32,500/160,000 = 20.3%
Land Use in Drainage Area by Type, Acres and Percentage
Residential/Business, 522 acres, 70.5%
Woodland, 118 acres, 15.9%
Transportation, 79 acres, 10.7%
Water, 13 acres, 1.8%
Grassland, 8 acres, 1.1%
Total = 740 acres
Floodpool of Woodglen Lake = 36 acres
Land Ownership:
Upstream of dam: 79% private, 21% public
Downstream of dam: 47% private, 53% public