LAU EE TIAN
0309596
CH’NG XING YUE
0310425
Project 1: Understanding Forces in Skeletal Structure
FAM LI KIAN
0310639
WESLEY HEW XIN HAN
0307585
GOH CHIN ZHI
03145623
ELAINE BONG POH HUI
0310432
• • • • •
There are several type of forces has been applied into a popsicle sticks tower. The internal forces included tension force, torsion force, shear
strength, bending force and compression force.
Triangular Square
• Lessen the amount of sticks used by an estimation of 25% but
reduces the stability of the tower as the base surface area is lower.
• Remain in shape well when force is applied.
• Higher stability and more vertical columns to support the tower but
will increase the mass of tower.
• Easily deformed when force is exerted to the shape.
Double Layer Single Layer
Strength • Able to withstand higher pressure by increasing
the contact surface area of the popsicle sticks.
• Able to tolerate stronger compression force.
• Lighten the weight of the tower and the amount of
popsicle sticks used to increase the efficiency of the
tower.
• Time span on construction is shorten.
Weakness • Increase the weight of the tower and amount of
popsicle sticks used reducing the efficiency of the
tower
• Work labor is increased
• Increases the stress received as the force does not
distribute to other popsicle sticks.
• Hard to combine the sticks together without using
slot in
• The horizontal sticks acting as the beam for the tower are
placed upwards to reduce the possibility of the bending of the
sticks as easily as horizontally positioned stick due to the
rigidness and inflexibility of popsicle sticks.
• Upward placed stick will receive more pressure than horizontally
positioned stick due to its smaller surface area, so double layer
pinned together strengthen the joint making it acting as a three layer
unit channeling the force from the top to bottom.
Slot-in with groove
• Will reduce the structural strength of the sticks as it will break more easily when force is
exerted
• It might cause the sticks to split into half when force is applied
• It is easier to combine the sticks together using slot in compared to other methods
• Transfer of load is more efficient and direct
• The use of pin might causes the stick to split according to the direction of wood rays
• Able to fix all sticks together firmly
Slot-in with double layer
• Requires more sticks and very strong bond joining all three sticks to ensure the load force
transfer down all three sticks as one unit
• Might break easily at the joint if the load doesn’t transfer vertically down as the slot-ins are at
the end of the sticks
Square Lashing Diagonal Lashing
Strength - More aesthetic and neat
- Use lesser string
- Lesser contact area with the vertical
popsicle stick, hence lesser pressure
applying to the popsicle stick and causes
it to break
- Distribute more force among threads
- Able to hold the popsicle stick in position more
firmly
Weakness - Higher tension force in thread compared to
diagonal lashing
- Requires more effort and more time consuming in
comparison to square lashing
Strength • Able to withstand greater pressure and weight due to the spreading of force.
Weakness • The center point between two bracing become the weak point due to the
intersection of force hence easier to break.
Strength • To avoid the popsicle sticks intersection with the popsicle sticks of other floors
Weakness • Increases the height of the tower hence the center of gravity is higher, weaker
the stability of tower
Strength • Avoid unnecessary extra weight to increase the efficiency of tower
Weakness • Increases the chance of breaking due to less spreading of force at vertical
columns
Strength
Weakness Joint is extended beyond boundaries causing tower to be unstable on smaller points.
Small area of force creates higher pressure even with low force being applied.
Strength Ensuring force from shorter brace can be transferred to horizontal bracing.
Weakness Exertion of force is not efficient. Joints might break when pressure is applied.
Strength Reduces force applied on horizontal bracing by transferring it to the vertical and
diagonal brace.
Weakness Single diagonal bracing may cause tower to twist in a spiral motion .
Strength Larger surface reduces amount for pressure and force being transferred to the
ground.
Weakness Spiral direction of force abruptly ends as diagonal bracing isn’t directly in contact with
ground surface.
Strength • Withstand the greatest pressure among all bracings due to it’s triangular design
Weakness • Horizontal sticks become the weak point due to uneven distribution of forces/
sudden pressure.
• Might break at the top part when large force is exerted due to weak bonding
strength of slot in bracing
Strength Ensuring force from shorter brace can be transferred to horizontal bracing.
Weakness Extension has fewer proper connection that may result in rigid stance.
Strength Larger surface reduces amount for pressure and force being transferred to the
ground.
Weakness Horizontal brace absorbs less pressure as force from 3 directions are transferred to
end points instead.
Mass of tower: 137g
Total of sticks used: 96 sticks
Time span: 2 minutes 10 seconds
Efficiency of tower =
=
= 9.27
Load Held (g)
Mass of Tower (g) X Height of Tower (cm)
40000g
137g X 31.5cm
Bracing used: Bracing 2
Double layer vertical columns
Joint used:
Tower before model testing
• The force of the tower supposedly
to move in torsion and downwards
vertically.
• The vertical supports were
strengthen with double layer
• Additional horizontal sticks were
added at the extension gap to allow
the load from the top to transfer to the
horizontal beams below and not just
rely solely on the vertical supports.
• Alternating gaps of horizontal
beams were used(without
changing the degree or length of
the slanted bracing).
• This reduces the length of the
columns in between the
horizontal beams and increases
the load capacity.
gap
Added horizontal
sticks
Precision of the tower is very important as inaccurate measurements lead to uneven distribution of forces and contribute to the racking of the
structure. Tower built using double layer slot -ins requires higher level of accuracy due to its more complicated structure than single layer tower with
slot-ins that have grooves. This makes single layer tower easier to construct and have lighter mass but double layer structure could withstand more
load if it is built well.
Besides, internal bracings could be added to the tower to prevent the deformation of the vertical and horizontal structures.
• The tower was not
structurally straight in the
first place. Hence torsion in
opposite direction of the
bracing happened once
weight are applied. This was
the main reason of the
structure failure since the
bracings and columns could
not perform their function
well as supposed to transfer
the load.
• Since the force was wrongly
transferred, it falls on one
side at the end and causes
the horizontal element at
one of the corners breaks.
• Lack of internal bracing
allowed the deformation of
the tower to happen.
• Besides, joining the popsicle
sticks by using pin made
them crack. It might weaken
the ability of the sticks to
transfer load as it will split
with strong shear force.
• The bottom part of the tower
is still in good condition
proves that the force are not
going downwards efficiently.
Tower after model testing

More Related Content

What's hot

Chapter 01 working drawing
Chapter 01 working drawingChapter 01 working drawing
Chapter 01 working drawingObuekwec
 
Slab.beam.stair.ppt
Slab.beam.stair.pptSlab.beam.stair.ppt
Slab.beam.stair.pptapu roy
 
Architecture design studio 1 project 3 brief march 2015
Architecture design studio 1 project 3 brief march 2015Architecture design studio 1 project 3 brief march 2015
Architecture design studio 1 project 3 brief march 2015Arvindhan Balasingam
 
IMPORTANCE & TYPES OF SCALE IN ARCHITECTURE
IMPORTANCE & TYPES OF SCALE IN ARCHITECTUREIMPORTANCE & TYPES OF SCALE IN ARCHITECTURE
IMPORTANCE & TYPES OF SCALE IN ARCHITECTUREarchistudent12
 
Staircase - Introduction, Types, Parts and Design
Staircase - Introduction, Types, Parts and DesignStaircase - Introduction, Types, Parts and Design
Staircase - Introduction, Types, Parts and DesignRohan Dasgupta
 
Designing for long spans 2
Designing for long spans 2Designing for long spans 2
Designing for long spans 2SADEQ ALSALAMI
 
design of staircase
design of staircasedesign of staircase
design of staircasevasu.chawla
 
Architectural symbols
Architectural symbolsArchitectural symbols
Architectural symbolsAr. Avitesh
 
analysis of high rise building
analysis of high rise buildinganalysis of high rise building
analysis of high rise buildingishant_kukreja
 
Types of Stairs & Staircase in Building Construction
Types of Stairs & Staircase in Building ConstructionTypes of Stairs & Staircase in Building Construction
Types of Stairs & Staircase in Building ConstructionEr.Karan Chauhan
 
Cable and Tensile Structures for Architecture and Engineering
Cable and Tensile Structures for Architecture and EngineeringCable and Tensile Structures for Architecture and Engineering
Cable and Tensile Structures for Architecture and EngineeringMimi Alguidano
 
basic structural system in architecture
basic structural system in architecturebasic structural system in architecture
basic structural system in architectureshahul130103
 
Services in High Rise Building
Services in High Rise Building  Services in High Rise Building
Services in High Rise Building ShrushtiAhirrao1
 

What's hot (20)

Chapter 01 working drawing
Chapter 01 working drawingChapter 01 working drawing
Chapter 01 working drawing
 
Stairs
StairsStairs
Stairs
 
Slab.beam.stair.ppt
Slab.beam.stair.pptSlab.beam.stair.ppt
Slab.beam.stair.ppt
 
Architecture design studio 1 project 3 brief march 2015
Architecture design studio 1 project 3 brief march 2015Architecture design studio 1 project 3 brief march 2015
Architecture design studio 1 project 3 brief march 2015
 
IMPORTANCE & TYPES OF SCALE IN ARCHITECTURE
IMPORTANCE & TYPES OF SCALE IN ARCHITECTUREIMPORTANCE & TYPES OF SCALE IN ARCHITECTURE
IMPORTANCE & TYPES OF SCALE IN ARCHITECTURE
 
High rise
High riseHigh rise
High rise
 
Staircase - Introduction, Types, Parts and Design
Staircase - Introduction, Types, Parts and DesignStaircase - Introduction, Types, Parts and Design
Staircase - Introduction, Types, Parts and Design
 
Theory of Architecture
Theory  of ArchitectureTheory  of Architecture
Theory of Architecture
 
Tube structures
Tube structuresTube structures
Tube structures
 
Form Active system
Form Active systemForm Active system
Form Active system
 
Designing for long spans 2
Designing for long spans 2Designing for long spans 2
Designing for long spans 2
 
design of staircase
design of staircasedesign of staircase
design of staircase
 
Architectural symbols
Architectural symbolsArchitectural symbols
Architectural symbols
 
analysis of high rise building
analysis of high rise buildinganalysis of high rise building
analysis of high rise building
 
Types of roof
Types of roofTypes of roof
Types of roof
 
Types of Stairs & Staircase in Building Construction
Types of Stairs & Staircase in Building ConstructionTypes of Stairs & Staircase in Building Construction
Types of Stairs & Staircase in Building Construction
 
Cable and Tensile Structures for Architecture and Engineering
Cable and Tensile Structures for Architecture and EngineeringCable and Tensile Structures for Architecture and Engineering
Cable and Tensile Structures for Architecture and Engineering
 
PPT OF TRUSSES
PPT OF TRUSSESPPT OF TRUSSES
PPT OF TRUSSES
 
basic structural system in architecture
basic structural system in architecturebasic structural system in architecture
basic structural system in architecture
 
Services in High Rise Building
Services in High Rise Building  Services in High Rise Building
Services in High Rise Building
 

Viewers also liked

Report 10.0 bcon xing
Report 10.0 bcon xingReport 10.0 bcon xing
Report 10.0 bcon xingElaine Bong
 
GBM package in r
GBM package in rGBM package in r
GBM package in rmark_landry
 
Construction of telecommunication towers
Construction of telecommunication towersConstruction of telecommunication towers
Construction of telecommunication towerssnookala
 
Marketing for Transit - GBT Community Engagement
Marketing for Transit - GBT Community EngagementMarketing for Transit - GBT Community Engagement
Marketing for Transit - GBT Community EngagementGreater Bridgeport Transit
 
EMF calculation sample report
EMF calculation sample reportEMF calculation sample report
EMF calculation sample reportanil parmar
 
Anuj sewage treatment plant
Anuj sewage treatment plantAnuj sewage treatment plant
Anuj sewage treatment plantanuj110
 
Building construction report
Building construction reportBuilding construction report
Building construction reportSoh Shing
 
Potential survival after entering the construction industry
Potential survival after entering the construction industryPotential survival after entering the construction industry
Potential survival after entering the construction industryDivpriya Chawla
 
SEWAGE TREATMENT PLANT,LUCKNOW
SEWAGE TREATMENT PLANT,LUCKNOWSEWAGE TREATMENT PLANT,LUCKNOW
SEWAGE TREATMENT PLANT,LUCKNOWGLA University
 
sewage treatment plant
sewage treatment plantsewage treatment plant
sewage treatment plantBhavik Patel
 
Mobile tower site, Nimay Giri
Mobile tower site, Nimay GiriMobile tower site, Nimay Giri
Mobile tower site, Nimay Girinimay1
 

Viewers also liked (15)

Report 10.0 bcon xing
Report 10.0 bcon xingReport 10.0 bcon xing
Report 10.0 bcon xing
 
AJEET GUPTA
AJEET GUPTAAJEET GUPTA
AJEET GUPTA
 
GBM package in r
GBM package in rGBM package in r
GBM package in r
 
Construction of telecommunication towers
Construction of telecommunication towersConstruction of telecommunication towers
Construction of telecommunication towers
 
Marketing for Transit - GBT Community Engagement
Marketing for Transit - GBT Community EngagementMarketing for Transit - GBT Community Engagement
Marketing for Transit - GBT Community Engagement
 
EMF calculation sample report
EMF calculation sample reportEMF calculation sample report
EMF calculation sample report
 
Anuj sewage treatment plant
Anuj sewage treatment plantAnuj sewage treatment plant
Anuj sewage treatment plant
 
Building construction report
Building construction reportBuilding construction report
Building construction report
 
Cooling tower
Cooling towerCooling tower
Cooling tower
 
Potential survival after entering the construction industry
Potential survival after entering the construction industryPotential survival after entering the construction industry
Potential survival after entering the construction industry
 
Tl book
Tl bookTl book
Tl book
 
SEWAGE TREATMENT PLANT,LUCKNOW
SEWAGE TREATMENT PLANT,LUCKNOWSEWAGE TREATMENT PLANT,LUCKNOW
SEWAGE TREATMENT PLANT,LUCKNOW
 
sewage treatment plant
sewage treatment plantsewage treatment plant
sewage treatment plant
 
Mobile tower site, Nimay Giri
Mobile tower site, Nimay GiriMobile tower site, Nimay Giri
Mobile tower site, Nimay Giri
 
Build Features, Not Apps
Build Features, Not AppsBuild Features, Not Apps
Build Features, Not Apps
 

Similar to DOCUMENT Understanding Forces in Skeletal Structures

Report - Project 1 [BCON2]
Report - Project 1 [BCON2]Report - Project 1 [BCON2]
Report - Project 1 [BCON2]Esther Lau
 
Tube structures and its type with comparison .
Tube structures and its type with comparison .Tube structures and its type with comparison .
Tube structures and its type with comparison .Udayram Patil
 
Building Construction 2 Project 1 Report
Building Construction 2 Project 1 ReportBuilding Construction 2 Project 1 Report
Building Construction 2 Project 1 Reporthiewyennee
 
FORM ACTIVE.pptx
FORM ACTIVE.pptxFORM ACTIVE.pptx
FORM ACTIVE.pptxTaranJot7
 
FORM ACTIVE.pdf
FORM ACTIVE.pdfFORM ACTIVE.pdf
FORM ACTIVE.pdfTaranJot7
 
Form active structure system (1)
 Form active structure system (1) Form active structure system (1)
Form active structure system (1)Prince Pathania
 
Tube structures
 Tube structures  Tube structures
Tube structures hamzah0001
 
seismic behaviour of beam column joint
seismic behaviour of beam column jointseismic behaviour of beam column joint
seismic behaviour of beam column jointsaurabh gehlod
 
Folded Plate structures
Folded Plate structures Folded Plate structures
Folded Plate structures rohan joshi
 
Unit 1 lesson 01 (introduction to reinforced concrete design)
Unit 1   lesson 01 (introduction to reinforced concrete design)Unit 1   lesson 01 (introduction to reinforced concrete design)
Unit 1 lesson 01 (introduction to reinforced concrete design)LumagbasProduction
 
Building desighn in seiemic environment
Building desighn in seiemic environmentBuilding desighn in seiemic environment
Building desighn in seiemic environmentZiaUlHassanMamoon1
 
Behavior of rc structure under earthquake loading
Behavior of rc structure under earthquake loadingBehavior of rc structure under earthquake loading
Behavior of rc structure under earthquake loadingBinay Shrestha
 

Similar to DOCUMENT Understanding Forces in Skeletal Structures (20)

Report - Project 1 [BCON2]
Report - Project 1 [BCON2]Report - Project 1 [BCON2]
Report - Project 1 [BCON2]
 
Tube structures and its type with comparison .
Tube structures and its type with comparison .Tube structures and its type with comparison .
Tube structures and its type with comparison .
 
Building Construction 2 Project 1 Report
Building Construction 2 Project 1 ReportBuilding Construction 2 Project 1 Report
Building Construction 2 Project 1 Report
 
FORM ACTIVE.pptx
FORM ACTIVE.pptxFORM ACTIVE.pptx
FORM ACTIVE.pptx
 
FORM ACTIVE.pdf
FORM ACTIVE.pdfFORM ACTIVE.pdf
FORM ACTIVE.pdf
 
Form active structure system (1)
 Form active structure system (1) Form active structure system (1)
Form active structure system (1)
 
Tube structures
 Tube structures  Tube structures
Tube structures
 
seismic behaviour of beam column joint
seismic behaviour of beam column jointseismic behaviour of beam column joint
seismic behaviour of beam column joint
 
Folded Plate structures
Folded Plate structures Folded Plate structures
Folded Plate structures
 
2 column
2 column2 column
2 column
 
civil RCC.pdf
civil RCC.pdfcivil RCC.pdf
civil RCC.pdf
 
BEAM.pptx
BEAM.pptxBEAM.pptx
BEAM.pptx
 
Beams and columns
Beams and columns Beams and columns
Beams and columns
 
Unit 1 lesson 01 (introduction to reinforced concrete design)
Unit 1   lesson 01 (introduction to reinforced concrete design)Unit 1   lesson 01 (introduction to reinforced concrete design)
Unit 1 lesson 01 (introduction to reinforced concrete design)
 
Earthquake damages
Earthquake damagesEarthquake damages
Earthquake damages
 
Framed structures
Framed structures Framed structures
Framed structures
 
Building desighn in seiemic environment
Building desighn in seiemic environmentBuilding desighn in seiemic environment
Building desighn in seiemic environment
 
Behavior of rc structure under earthquake loading
Behavior of rc structure under earthquake loadingBehavior of rc structure under earthquake loading
Behavior of rc structure under earthquake loading
 
Residential Apartment Building
Residential Apartment BuildingResidential Apartment Building
Residential Apartment Building
 
Bcon report final
Bcon report finalBcon report final
Bcon report final
 

More from XingYue0907

Project Management | P1
Project Management | P1Project Management | P1
Project Management | P1XingYue0907
 
Building Technology 2 P2
Building Technology 2 P2Building Technology 2 P2
Building Technology 2 P2XingYue0907
 
Building Technology report
Building Technology reportBuilding Technology report
Building Technology reportXingYue0907
 
Design studio 5 group board
Design studio 5 group boardDesign studio 5 group board
Design studio 5 group boardXingYue0907
 
Project 1 part 2 Jane Jacobs
Project 1 part 2 Jane JacobsProject 1 part 2 Jane Jacobs
Project 1 part 2 Jane JacobsXingYue0907
 
Project 2 IOI Boulevard and Jane Jacob
Project 2 IOI Boulevard and Jane JacobProject 2 IOI Boulevard and Jane Jacob
Project 2 IOI Boulevard and Jane JacobXingYue0907
 
Theories project 1 group
Theories project 1 groupTheories project 1 group
Theories project 1 groupXingYue0907
 
Building services project 2
Building services project 2Building services project 2
Building services project 2XingYue0907
 
Building services group report
Building services group report Building services group report
Building services group report XingYue0907
 
Solaris Singapore report
Solaris Singapore report Solaris Singapore report
Solaris Singapore report XingYue0907
 
Lot 2C2 Building Science Report
Lot 2C2 Building Science ReportLot 2C2 Building Science Report
Lot 2C2 Building Science ReportXingYue0907
 
Bechtler Museum Construction
Bechtler Museum ConstructionBechtler Museum Construction
Bechtler Museum ConstructionXingYue0907
 
Building construction 1 group report
Building construction 1 group reportBuilding construction 1 group report
Building construction 1 group reportXingYue0907
 
Bm mood board ..
Bm mood board ..Bm mood board ..
Bm mood board ..XingYue0907
 
CnH 1 Florence Cathedral essay
CnH 1 Florence Cathedral essayCnH 1 Florence Cathedral essay
CnH 1 Florence Cathedral essayXingYue0907
 
CnC photobook xing yue
CnC photobook xing yueCnC photobook xing yue
CnC photobook xing yueXingYue0907
 
Materials and structure
Materials and structure Materials and structure
Materials and structure XingYue0907
 
What is animal cruelty 2
What is animal cruelty 2What is animal cruelty 2
What is animal cruelty 2XingYue0907
 

More from XingYue0907 (19)

Project Management | P1
Project Management | P1Project Management | P1
Project Management | P1
 
Building Technology 2 P2
Building Technology 2 P2Building Technology 2 P2
Building Technology 2 P2
 
Building Technology report
Building Technology reportBuilding Technology report
Building Technology report
 
Design studio 5 group board
Design studio 5 group boardDesign studio 5 group board
Design studio 5 group board
 
Project 1 part 2 Jane Jacobs
Project 1 part 2 Jane JacobsProject 1 part 2 Jane Jacobs
Project 1 part 2 Jane Jacobs
 
Project 2 IOI Boulevard and Jane Jacob
Project 2 IOI Boulevard and Jane JacobProject 2 IOI Boulevard and Jane Jacob
Project 2 IOI Boulevard and Jane Jacob
 
Theories project 1 group
Theories project 1 groupTheories project 1 group
Theories project 1 group
 
Building services project 2
Building services project 2Building services project 2
Building services project 2
 
Building services group report
Building services group report Building services group report
Building services group report
 
Solaris Singapore report
Solaris Singapore report Solaris Singapore report
Solaris Singapore report
 
Lot 2C2 Building Science Report
Lot 2C2 Building Science ReportLot 2C2 Building Science Report
Lot 2C2 Building Science Report
 
Bechtler Museum Construction
Bechtler Museum ConstructionBechtler Museum Construction
Bechtler Museum Construction
 
Building construction 1 group report
Building construction 1 group reportBuilding construction 1 group report
Building construction 1 group report
 
Bmats1
Bmats1Bmats1
Bmats1
 
Bm mood board ..
Bm mood board ..Bm mood board ..
Bm mood board ..
 
CnH 1 Florence Cathedral essay
CnH 1 Florence Cathedral essayCnH 1 Florence Cathedral essay
CnH 1 Florence Cathedral essay
 
CnC photobook xing yue
CnC photobook xing yueCnC photobook xing yue
CnC photobook xing yue
 
Materials and structure
Materials and structure Materials and structure
Materials and structure
 
What is animal cruelty 2
What is animal cruelty 2What is animal cruelty 2
What is animal cruelty 2
 

Recently uploaded

原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档208367051
 
CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10
CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10
CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10uasjlagroup
 
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档208367051
 
PORTAFOLIO 2024_ ANASTASIYA KUDINOVA
PORTAFOLIO   2024_  ANASTASIYA  KUDINOVAPORTAFOLIO   2024_  ANASTASIYA  KUDINOVA
PORTAFOLIO 2024_ ANASTASIYA KUDINOVAAnastasiya Kudinova
 
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一F dds
 
Pharmaceutical Packaging for the elderly.pdf
Pharmaceutical Packaging for the elderly.pdfPharmaceutical Packaging for the elderly.pdf
Pharmaceutical Packaging for the elderly.pdfAayushChavan5
 
Architecture case study India Habitat Centre, Delhi.pdf
Architecture case study India Habitat Centre, Delhi.pdfArchitecture case study India Habitat Centre, Delhi.pdf
Architecture case study India Habitat Centre, Delhi.pdfSumit Lathwal
 
Call In girls Bhikaji Cama Place 🔝 ⇛8377877756 FULL Enjoy Delhi NCR
Call In girls Bhikaji Cama Place 🔝 ⇛8377877756 FULL Enjoy Delhi NCRCall In girls Bhikaji Cama Place 🔝 ⇛8377877756 FULL Enjoy Delhi NCR
Call In girls Bhikaji Cama Place 🔝 ⇛8377877756 FULL Enjoy Delhi NCRdollysharma2066
 
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCRdollysharma2066
 
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
3D Printing And Designing Final Report.pdf
3D Printing And Designing Final Report.pdf3D Printing And Designing Final Report.pdf
3D Printing And Designing Final Report.pdfSwaraliBorhade
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Rndexperts
 
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一F La
 
group_15_empirya_p1projectIndustrial.pdf
group_15_empirya_p1projectIndustrial.pdfgroup_15_empirya_p1projectIndustrial.pdf
group_15_empirya_p1projectIndustrial.pdfneelspinoy
 
西北大学毕业证学位证成绩单-怎么样办伪造
西北大学毕业证学位证成绩单-怎么样办伪造西北大学毕业证学位证成绩单-怎么样办伪造
西北大学毕业证学位证成绩单-怎么样办伪造kbdhl05e
 
How to Empower the future of UX Design with Gen AI
How to Empower the future of UX Design with Gen AIHow to Empower the future of UX Design with Gen AI
How to Empower the future of UX Design with Gen AIyuj
 
Cosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable BricksCosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable Bricksabhishekparmar618
 
Untitled presedddddddddddddddddntation (1).pptx
Untitled presedddddddddddddddddntation (1).pptxUntitled presedddddddddddddddddntation (1).pptx
Untitled presedddddddddddddddddntation (1).pptxmapanig881
 
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,Aginakm1
 

Recently uploaded (20)

原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
 
CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10
CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10
CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10
 
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档
 
PORTAFOLIO 2024_ ANASTASIYA KUDINOVA
PORTAFOLIO   2024_  ANASTASIYA  KUDINOVAPORTAFOLIO   2024_  ANASTASIYA  KUDINOVA
PORTAFOLIO 2024_ ANASTASIYA KUDINOVA
 
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
 
Pharmaceutical Packaging for the elderly.pdf
Pharmaceutical Packaging for the elderly.pdfPharmaceutical Packaging for the elderly.pdf
Pharmaceutical Packaging for the elderly.pdf
 
Architecture case study India Habitat Centre, Delhi.pdf
Architecture case study India Habitat Centre, Delhi.pdfArchitecture case study India Habitat Centre, Delhi.pdf
Architecture case study India Habitat Centre, Delhi.pdf
 
Call In girls Bhikaji Cama Place 🔝 ⇛8377877756 FULL Enjoy Delhi NCR
Call In girls Bhikaji Cama Place 🔝 ⇛8377877756 FULL Enjoy Delhi NCRCall In girls Bhikaji Cama Place 🔝 ⇛8377877756 FULL Enjoy Delhi NCR
Call In girls Bhikaji Cama Place 🔝 ⇛8377877756 FULL Enjoy Delhi NCR
 
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
 
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Okhla Delhi 💯Call Us 🔝8264348440🔝
 
Call Girls in Pratap Nagar, 9953056974 Escort Service
Call Girls in Pratap Nagar,  9953056974 Escort ServiceCall Girls in Pratap Nagar,  9953056974 Escort Service
Call Girls in Pratap Nagar, 9953056974 Escort Service
 
3D Printing And Designing Final Report.pdf
3D Printing And Designing Final Report.pdf3D Printing And Designing Final Report.pdf
3D Printing And Designing Final Report.pdf
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025
 
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
 
group_15_empirya_p1projectIndustrial.pdf
group_15_empirya_p1projectIndustrial.pdfgroup_15_empirya_p1projectIndustrial.pdf
group_15_empirya_p1projectIndustrial.pdf
 
西北大学毕业证学位证成绩单-怎么样办伪造
西北大学毕业证学位证成绩单-怎么样办伪造西北大学毕业证学位证成绩单-怎么样办伪造
西北大学毕业证学位证成绩单-怎么样办伪造
 
How to Empower the future of UX Design with Gen AI
How to Empower the future of UX Design with Gen AIHow to Empower the future of UX Design with Gen AI
How to Empower the future of UX Design with Gen AI
 
Cosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable BricksCosumer Willingness to Pay for Sustainable Bricks
Cosumer Willingness to Pay for Sustainable Bricks
 
Untitled presedddddddddddddddddntation (1).pptx
Untitled presedddddddddddddddddntation (1).pptxUntitled presedddddddddddddddddntation (1).pptx
Untitled presedddddddddddddddddntation (1).pptx
 
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,
'CASE STUDY OF INDIRA PARYAVARAN BHAVAN DELHI ,
 

DOCUMENT Understanding Forces in Skeletal Structures

  • 1. LAU EE TIAN 0309596 CH’NG XING YUE 0310425 Project 1: Understanding Forces in Skeletal Structure FAM LI KIAN 0310639 WESLEY HEW XIN HAN 0307585 GOH CHIN ZHI 03145623 ELAINE BONG POH HUI 0310432 • • • • •
  • 2. There are several type of forces has been applied into a popsicle sticks tower. The internal forces included tension force, torsion force, shear strength, bending force and compression force. Triangular Square • Lessen the amount of sticks used by an estimation of 25% but reduces the stability of the tower as the base surface area is lower. • Remain in shape well when force is applied. • Higher stability and more vertical columns to support the tower but will increase the mass of tower. • Easily deformed when force is exerted to the shape.
  • 3. Double Layer Single Layer Strength • Able to withstand higher pressure by increasing the contact surface area of the popsicle sticks. • Able to tolerate stronger compression force. • Lighten the weight of the tower and the amount of popsicle sticks used to increase the efficiency of the tower. • Time span on construction is shorten. Weakness • Increase the weight of the tower and amount of popsicle sticks used reducing the efficiency of the tower • Work labor is increased • Increases the stress received as the force does not distribute to other popsicle sticks. • Hard to combine the sticks together without using slot in • The horizontal sticks acting as the beam for the tower are placed upwards to reduce the possibility of the bending of the sticks as easily as horizontally positioned stick due to the rigidness and inflexibility of popsicle sticks. • Upward placed stick will receive more pressure than horizontally positioned stick due to its smaller surface area, so double layer pinned together strengthen the joint making it acting as a three layer unit channeling the force from the top to bottom.
  • 4. Slot-in with groove • Will reduce the structural strength of the sticks as it will break more easily when force is exerted • It might cause the sticks to split into half when force is applied • It is easier to combine the sticks together using slot in compared to other methods • Transfer of load is more efficient and direct • The use of pin might causes the stick to split according to the direction of wood rays • Able to fix all sticks together firmly Slot-in with double layer • Requires more sticks and very strong bond joining all three sticks to ensure the load force transfer down all three sticks as one unit • Might break easily at the joint if the load doesn’t transfer vertically down as the slot-ins are at the end of the sticks
  • 5. Square Lashing Diagonal Lashing Strength - More aesthetic and neat - Use lesser string - Lesser contact area with the vertical popsicle stick, hence lesser pressure applying to the popsicle stick and causes it to break - Distribute more force among threads - Able to hold the popsicle stick in position more firmly Weakness - Higher tension force in thread compared to diagonal lashing - Requires more effort and more time consuming in comparison to square lashing
  • 6. Strength • Able to withstand greater pressure and weight due to the spreading of force. Weakness • The center point between two bracing become the weak point due to the intersection of force hence easier to break. Strength • To avoid the popsicle sticks intersection with the popsicle sticks of other floors Weakness • Increases the height of the tower hence the center of gravity is higher, weaker the stability of tower Strength • Avoid unnecessary extra weight to increase the efficiency of tower Weakness • Increases the chance of breaking due to less spreading of force at vertical columns Strength Weakness Joint is extended beyond boundaries causing tower to be unstable on smaller points. Small area of force creates higher pressure even with low force being applied.
  • 7. Strength Ensuring force from shorter brace can be transferred to horizontal bracing. Weakness Exertion of force is not efficient. Joints might break when pressure is applied. Strength Reduces force applied on horizontal bracing by transferring it to the vertical and diagonal brace. Weakness Single diagonal bracing may cause tower to twist in a spiral motion . Strength Larger surface reduces amount for pressure and force being transferred to the ground. Weakness Spiral direction of force abruptly ends as diagonal bracing isn’t directly in contact with ground surface.
  • 8. Strength • Withstand the greatest pressure among all bracings due to it’s triangular design Weakness • Horizontal sticks become the weak point due to uneven distribution of forces/ sudden pressure. • Might break at the top part when large force is exerted due to weak bonding strength of slot in bracing Strength Ensuring force from shorter brace can be transferred to horizontal bracing. Weakness Extension has fewer proper connection that may result in rigid stance. Strength Larger surface reduces amount for pressure and force being transferred to the ground. Weakness Horizontal brace absorbs less pressure as force from 3 directions are transferred to end points instead.
  • 9. Mass of tower: 137g Total of sticks used: 96 sticks Time span: 2 minutes 10 seconds Efficiency of tower = = = 9.27 Load Held (g) Mass of Tower (g) X Height of Tower (cm) 40000g 137g X 31.5cm Bracing used: Bracing 2 Double layer vertical columns Joint used:
  • 10.
  • 11. Tower before model testing • The force of the tower supposedly to move in torsion and downwards vertically. • The vertical supports were strengthen with double layer • Additional horizontal sticks were added at the extension gap to allow the load from the top to transfer to the horizontal beams below and not just rely solely on the vertical supports. • Alternating gaps of horizontal beams were used(without changing the degree or length of the slanted bracing). • This reduces the length of the columns in between the horizontal beams and increases the load capacity. gap Added horizontal sticks
  • 12. Precision of the tower is very important as inaccurate measurements lead to uneven distribution of forces and contribute to the racking of the structure. Tower built using double layer slot -ins requires higher level of accuracy due to its more complicated structure than single layer tower with slot-ins that have grooves. This makes single layer tower easier to construct and have lighter mass but double layer structure could withstand more load if it is built well. Besides, internal bracings could be added to the tower to prevent the deformation of the vertical and horizontal structures. • The tower was not structurally straight in the first place. Hence torsion in opposite direction of the bracing happened once weight are applied. This was the main reason of the structure failure since the bracings and columns could not perform their function well as supposed to transfer the load. • Since the force was wrongly transferred, it falls on one side at the end and causes the horizontal element at one of the corners breaks. • Lack of internal bracing allowed the deformation of the tower to happen. • Besides, joining the popsicle sticks by using pin made them crack. It might weaken the ability of the sticks to transfer load as it will split with strong shear force. • The bottom part of the tower is still in good condition proves that the force are not going downwards efficiently. Tower after model testing