Bill of Quantities 
Bill of Quantities/Schedules of Prices 
PROJECT: 
REFURBISHMNENT OF THE AGRICULTURAL LABORATORY OF THE 
WILLIAM R. TOLBERT COLLEGE OF AGRICULTURE AND FORESTRY OF 
THE UNIVERSITY OF LIBERIA 
LOCATION: FENDELL MONTSERRADO COUNTY 
DATE: JULY 2014 
I. MAIN LABORATORY BUILDING 
ITEM DESCRIPTION UNIT QTY. RATE EXTENSION 
1.0 GENERAL MOBILIZATION 
1.1 
Allow a sum for general mobilization, 
including storage, security, hand tool, 
scaffolding temp. utilities etc. 
Lump 
sum 1 
$4000.00 
$4000.00 
SUB TOTAL $4000.00 
2.0 PREPARATION FOR CONSTRUCTION 
2.1 
Clean existing concrete shell and remove all 
unwanted material, garbage, and clean and 
repair existing masonry structure for 
renovation and remodeling 
2.2 
Demolish walls as shown in dotted line and 
store debris for future use if necessary. 
Lump 
Sum 1 
$500.00 $ 5 0 0 .00 
SUB TOTAL $500.00 
3.0 EXCAVATION/ EARTH WORK 
3.1 
Excavate area as shown in working 
drawings, remove all vegetation, and a top 
soil about 12" and prepare for importation of 
required backfill to receive new floor slab CY 142 
$20.00 
$2,840.00 
3.2 
Backfill area within foundation wall to receive 
mass concrete floor slab. 12" compact CY 143 
$15.00 
$2145.00 
SUB TOTAL $4,985.00 
4.0 CONCRETE WORKS
2 
NOTE: This includes all formwork, and 
material to cast conc. Complete 
4.1 
Mix and pour class "C" concrete 1:3:5 as 
new floor slab 4" thick including wire mesh 
as shown in foundation detail. CY 48 
$175.00 
$8400.00 
4.2 
Mix and pour Class "B" concrete 1:2:4 as 
col. and beams to increase the height of 
walls to accommodate additional walls and 
create the clerestory windows as instructed 
by the architect and shown in the drawings CY 10 
$200.00 
$2000.00 
4.3 
Mix and pour class "B" concrete as new 
doors and window lintel. CY 2.5 
$200.00 $500.00 
SUB TOTAL $10900.00 
5.0 WALLS WORKS 
5.1 
Provide 8" cement block as interior and 
exterior walls shown in the drawings 
including new walls as new height and new 
partition SY 338 
$10.00 
$3380.00 
5.2 
Construct with alum and glass walls as 
shown in drawings (Laboratory Area) SF 880 
$5.00 $4400.00 
SUB TOTAL $7780.00 
6.0 ROOF 
6.1 
Construct wooden roofing frame with long 
span metal roofing system complete. SY 616 
$25.00 $15400.00 
6.2 
Provide and install complete plastic gutter 
system with 4" drain and connect to 
proposed "U" shape concrete drain Lf 152 
$10.00 
$1520.00 
SUB TOTAL $16,920.00 
7.0 FINISHINING 
7.1 
Provide terrazzo tiles on all floors as floor 
finishing 12" x 12" SY 428 
$15.00 $6,420.00 
7.2 
Provide ceramic wall tiles walls in labs. up to 
18" above countertops and floors of rest 
room including 5'-0" high on restrooms walls. SF 628 
$10.00 
$6,280.00 
7.3 
Clean existing walls and mend all masonry 
damage. 
Lump 
Sum 1 
$500.00 $500.00 
7.4 Provide 1"3 cement mix to plaster new walls SY 776 $10.00 $7760.00 
7.5 
Provide 1/4" ceiling system to all ceiling and 
under boxing using 2x4, 2x6, and all 
including ceiling strips, decorative material 
corner molding . SY 616 
$20.00 
$12320.00 
SUB TOTAL $33,530.00 
8.0 DOORS 
8.1 
Provide steel doors using 5/" square bars in 
angle irons with hinges, using European/ 
American standard locks These Door are for 
emergency door of labs as shown. (3'-0" x 
7'-0") D/1 A Set 2 
$500.00 
$1000.00 
8.2 
Provide wooden frame door, with glass, 
paint with cylinder lock, (European or 
American Standard) brass hinges, wood Set 3 
$300.00 
$900.00
3 
molding as shown (6-0"x 7'-0") D/2 
8.3 
Provide solid wood panel doors, 
varnish/paint with cylinder lock, (European or 
American Standard) brass hinges, wood 
molding as shown (6'-0" x 7'-0") D/3 Set 1 
$250.00 
$250.00 
8.4 
Provide solid wood panel doors as shown in 
drawings, varnished with cylinder lock 
(European or American Standard) with brass 
hinges, wood molding etc. Double (3'-0" x 7'- 
0") D/4 Set 5 
$175.00 
$875.00 
8.5 
Provide wood and glass door with locks , 
brass hinges, etc as shown in drawings (3'- 
0" x 7'-0") D/5 Set 4 
$200.00 
$800.00 
8.6 
Provide doors with louvers as vents. Single 
(3'-0" x 7'-0") D/6 Set 3 
$200.00 $600.00 
8.7 
Provide doors with louvers as vents. Single 
(3'-0" x 7'-0") D/7 Set 3 
$200.00 $600.00 
SUB TOTAL $5025.00 
9.0 WINDOWS 
9.1 
Provide louver and sliding glass windows as 
indicated in drawings (9'-0" x 4'-0") W/1 Set 25 
$300.00 $7500.00 
9.2 
Provide windows as indicated in dwgs. (9'-0" 
x 2'-6") W/2 Set 9 
$150.00 $1350.00 
9.3 
Provide windows as indicated in dwgs. (4'-0" 
x 4'-6") W/5 Set 3 
$150.00 $450.00 
9.4 
Provide louver and sliding glass windows as 
indicated in drawings (2'-6" x 2'-6") W/7 Set 3 
$100.00 $300.00 
9.5 
Provide windows as indicated in dwgs. (6'-0" 
x 2'-6") Jalousie louvers W/9 Set 6 
$150.00 $900.00 
NOTE; The cost for windows must 
include rogue bars using 5/8" square bar 
system 
SUB TOTAL $10,500.00 
10.0 PAINTING AND DECORATIONS 
10.1 
Provide emulsion paint to all plastered 
surfaces. 5'-0 above floor level SY 1200 
$1.00 $1200.00 
10.2 Provide ceiling paint on ceiling SY 616 $1.00 $616.00 
10.3 Provide enamel paint to lower walls SY 1200 $2.00 $2400.00 
10.4 Provide wall primer SY 3016 $0.50 $1508.00 
SUB TOTAL $5,724.00 
11.0 ELECTRICAL WORKS 
11.1 Provide double fluorescent lamps. Set 15 $15.00 $225.00 
11.2 Provide wall outlet 220V Set 25 $2.50 $62.50 
11.3 Provide wall switch. Set 19 $1.00 $28.50 
11.4 
Allow a sum for electrical conduits, wires 
clamps, junction boxes, cups etc. 
Lump 
Sum 1 
$2500.00 $2500.00 
11.5 Provide panel breaker system as per dwgs. Set 1 $250.00 $250.00 
11.6 Provide single fluorescent lamp 40W Set 1 $10.00 $10.00 
11.7 Globe Lamp 40W Set 14 $15.00 $210.00 
Sub total $3286.00 
12.0 PLUMBING WORKS
4 
12.1 Provide water closet complete Set 3 $65.00 $195.00 
12.2 Provide wash basin complete Set 3 $55.00 $165.00 
12.3 
Provide shower complete and shower head 
in lab shower in lab Set 3 
$150.00 $450.00 
12.4 
Allow a sum for in-coming water and waste 
disposal system 
Lump 
Sum 1 
$750.00 $750.00 
12.5 Allow a sum for septic tank and manholes 
Lump 
Sum 1 
$2500.00 $2500.00 
Sub total $4060.00 
10.0 MISCELLENOUS 
10.1 Allow a sum for shelves of the store rooms 
Lump 
Sum 1 
$500.00 $500.00 
10.2 
Allow a sum for the cabinet in the lab. with 
granite tops and ceramic lab sinks and lab 
faucets. (Must be approved by arch. Set 4 
$700.00 
$2100.00 
10.3 
Allow a sum for the floor board and curtain 
boxes 
Lump 
sum 1 
$500.00 $500.00 
10.4 
Allow a sum for concrete gutters as shown 
as surface drain system Lt 247 
$5.00 $1235.00 
SUB TOTAL $4,335.00 
TOTAL MATERIAL $111,575.00 
ADD FOR LABOR @25% $27,893.75 
ADD FOR TRANS. @10% $11,157.50 
ADD FOR PROFIT @10% $11,157.50 
GRAND TOTAL FOR MAIN LABORATORY BUILDING $161,783.75 
II. THE DIRTY LABORATORY AND ENTRY PORCH 
ITEM DESCRIPTION UNIT QTY. RATE EXTENSION 
1.0 EXCAVATION/ EARTH WORK 
1.1 
Excavate area as shown in working 
drawings, remove all vegetation, and a top 
soil about 6" and prepare for construction of 
the foundation system CY 232 
$20.00 
$4,640.00 
1.2 
Excavate foundation trench as shown in 
foundation plans and details. CY 62 
$20.00 $620.00 
1.3 
Backfill excavated area with Laterite and or 
approved backfill material CY 81 
$20.00 $810.00 
1.4 
Backfill area within foundation wall to receive 
mass concrete floor slab 12" compact CY 41 
$20.00 
$410.00 
Sub total $6,480.00 
2.0 CONCRETE WORKS 
NOTE: This includes all formwork, and 
material to cast conc. Complete. 
2.1 
Mix and pour class "C" concrete 1:3:5 as 
foundation column and walls footing as CY 29 
$175.00 
$5075.00
5 
shown in foundation detail 
2.2 
Mix and pour Class "B" concrete 1:2:4 as 
col. and beams including lintels and roof slab CY 22 
$200.00 
$4400.00 
Note: Roof slab includes 2" screeding 
and application of bitumen over the entire 
surface as water proof membrane. This is 
for all concrete roof surfaces 
2.3 
Mix and pour class "B" concrete as as new 
doors and window lintel. CY 1 
$200.00 $200.00 
2.4 Mix and pour conc. floor slab incl. mesh CY 12 $175.00 $2100.00 
Sub total $11,775.00 
3.0 WALLS WORKS 
3.1 
Provide 8" cement block as interior and 
exterior walls shown in the drawings 
including new walls as new height and new 
partition including foundation walls SY 217 
$10.00 
$2170.00 
3.2 
Construct honey comb block walls shown in 
drawings (dirty lab) SY 45 
$5.00 $225.00 
3.3 
Construct 8" cement block wall as foundation 
walls SY 132 
$10.00 $1320.00 
Sub total $3715.00 
4.0 ROOF 
4.1 
Construct wooden roofing frame with long 
span metal roofing system complete SY 152 
$25.00 $3800.00 
4.2 
Provide and install complete plastic gutter 
system with 4" drain and connect to 
proposed "U" shape concrete drain Lf 39 
$10.00 
$390.00 
Sub total $7905,00 
5.0 FINISHINING 
5.1 
Provide terrazzo tiles on all floors as floor 
finishing 12" x 12" SY 147 
$15.00 $2205.00 
5.2 
Provide ceramic wall tiles walls in labs up to 
18" above countertops and floors of rest 
room including 5'-0" high on restrooms walls. SF 192 
$10.00 
$1920.00 
5.3 Provide 1"3 cement mix to plaster new walls SY 654 $10.00 $6540.00 
5.4 
Provide 1/4" ceiling system to all ceiling and 
under boxing using 2x4, 2x6, and all material 
including ceiling strips, decorative corner 
molding. SY 152 
$20.00 
$3040.00 
Sub total $13,705.00 
6.0 DOORS 
6.1 
Provide steel doors using 5/" square bars in 
angle irons with hinges, using European/ 
American standard locks as shown. (6'-0" x 
7'-0") D/1 Set 2 
$500.00 
$1000.00 
6.2 
Provide solid wood panel doors as shown in 
drawings, varnished with cylinder lock 
(European or American Standard) with brass 
hinges, wood molding etc. Double (3'-0" x 7'- 
0") D/4 Set 2 
200.00 
$400.00 
6.3 Provide wood and glass door with locks , Set 1
6 
brass hinges, etc as shown in drawings (3'- 
0" x 7'-0") D/5 
$200.00 $200.00 
Sub total $1600.00 
7.0 WINDOWS 
7.1 
Provide windows as indicated in dwgs. (9'-0" 
x 2'-6") W/2 Set 4 
$125.00 $500.00 
NOTE; The cost for windows must 
include rogue bars using 5/8" square bar 
system. This is for the entire building. 
Sub total $500.00 
8.0 PAINTING AND DECORATIONS 
8.1 
Provide emulsion paint to all plastered 
surfaces. 5'-0 above floor level SY 654 
$1.00 $654.00 
8.2 Provide ceiling paint on ceiling SY 152 $1.00 $152.00 
8.3 Provide enamel paint to lower walls SY 654 $2.00 $1,308.00 
8.4 Provide wall primer SY 1460 $0.5 $730.00 
SUB TOTAL $2,844.00 
9.0 ELECTRICAL WORKS 
9.1 Provide double fluorescent lamps. Set 7 $15.00 $105.00 
9.2 Provide wall outlet 220V Set 7 $2.50 $17.50 
9.3 Provide wall switch. Set 3 $1.00 $3.00 
9.3 
Allow a sum for electrical conduits, wires 
clamps, junction boxes, cups etc. 
Lump 
Sum 1 
$1500.00 $1500.00 
9.5 Provide panel breaker system as per dwgs. Set 1 $250.00 $250.00 
Sub total $1,875.50 
10.0 PLUMBING WORKS 
Waste disposal system 
Lump 
Sum 1 
$500.00 $500.00 
Sub total $500.00 
11.0 MISCELLENOUS 
11.1 
Allow a sum for shelves of the soil storage 
room 
Lump 
Sum 1 
$500.00 $500.00 
10.3 
Allow a sum for the cabinet in the lab with 
granite tops and ceramic lab sink/ faucet Set 2 
$750.00 $1500.00 
10.4 
Allow a sum for the floor board and curtain 
boxes 
Lump 
Sum 1 
$500.00 $500.00 
Sub total $2,500.00 
TOTAL MATERIAL COST 
$53,399.50 
ADD FOR LABOR @25% 
$13,349.90 
ADD FOR TRANSPORTATION @10% 
$5,339.95 
ADD FOR PROFIT @10% 
$5,339.95 
TOTAL COST FOR DIRTY LABORATORY AND ENTRY 
PORCH 
$77,429.30
7 
III. COMPUTER LABORATORY 
ITEM DESCRIPTION UNIT QTY. RATE EXTENSION 
1.0 EXCAVATION/ EARTH WORK 
1.1 
Excavate area as shown in working 
drawings remove all vegetation, and a top 
soil about 6" and prepare for construction of 
the foundation system CY 200 
$20.00 
$4000.00 
1.2 
Excavate foundation trench as shown in 
foundation plans and details. CY 47 
$15.00 $705.00 
1.3 
Backfill excavated area with Laterite and or 
approved backfill material CY 102 
$10.00 $1,020.00 
1.4 
Backfill area within foundation wall to receive 
mass concrete floor slab 12" compact CY 51 
$10.00 
$510.00 
Sub total $6,235.00 
2.0 CONCRETE WORKS 
NOTE: This includes all formwork, and 
material to cast conc. Complete. 
2.1 
Mix and pour class "C" concrete 1:3:5 as 
foundation column and walls footing as 
shown in foundation detail CY 22 
$175.00 
$3850.00 
2.2 
Mix and pour Class "B" concrete 1:2:4 as 
col. and beams including lintels and roof slab CY 21 
$200.00 
$4,200.00 
2.3 
Mix and pour class "B" concrete as new 
doors and window lintel. CY 1 
$200.00 $200.00 
2.4 
Mix and pour floor slab 4" thick including 
mesh wire CY 17 
$200.00 $3,400.00 
Sub total $11,650.00 
3.0 WALLS WORKS 
3.1 
Provide 8" cement block as interior and 
exterior walls shown in the drawings 
including new walls as new height and new 
partition INCL. foundation walls SY 195 
$10.00 $1,950.00 
3.2 
Construct honey comb block walls shown in 
drawings (dirty lab) SY 48.75 
$5.00 $243.80 
3.3 
Construct 8" cement block wall as foundation 
walls. SY 308 
$10.00 $3,080.00 
Sub total $5,273.80 
4.0 ROOF 
4.1 
Construct wooden roofing frame with long 
span metal roofing system complete. SY 161 
$25.00 $4,025.00 
4.2 
system with 4" drain and connect to 
proposed "U" shape concrete drain Lf 47 
$10.00 $470.00 
SUB TOTAL $4,495.00 
5.0 FINISHINING 
5.1 
Provide terrazzo tiles on all floors as floor 
finishing. 12" x 12" SY 168 
$15.00 $2520.00 
5.2 
Provide ceramic wall tiles walls in 
RESTROOMS and floors. SF 300 
$10.00 $3,000.00 
5.3 Provide 1"3 cement mix to plaster new walls SY 916 $10.00 $9,160.00 
5.4 Provide 1/4" ceiling system to all ceiling and SY 161
8 
under boxing using 2x4, 2x6, and all material 
including ceiling strips, decorative corner 
molding. 
$20.00 
$3,220.00 
Sub total $17,900.00 
6.0 DOORS 
6.1 
Provide solid wood panel doors, 
varnish/paint with cylinder lock, (European or 
American Standard) brass hinges, wood 
molding as shown (6'-0" x 7'-0") D/3 Set 1 
$200.00 
$200.00 
6.2 
Provide solid wood panel doors as shown in 
drawings, varnished with cylinder lock 
(European or American Standard) with brass 
hinges, wood molding etc. Double (3'-0" x 7'- 
0") D/4 Set 2 
$200.00 
$400.00 
6.3 
Provide wood and glass door with locks , 
brass hinges, etc as shown in drawings (3'- 
0" x 7'-0") D/5 Set 1 
$200.00 
$200.00 
6.4 
Provide doors with louvers as vents. Single 
(3'-0" x 7'-0") D/6 Set 6 
$200.00 $1,200.00 
Sub total $2000.00 
7.0 WINDOWS 
7.1 
Provide louver and sliding glass windows as 
indicated in drawings (9'-0" x 4'-0") W/1 Set 2 
$150.00 
$300.00 
7.2 
Provide windows as indicated in dwgs. (9'-0" 
x 2'-6") W/2 Set 4 
$150.00 $600.00 
7.3 
Provide louver and sliding glass windows as 
indicated in drawings (6'-0" x 4'-0") W/4 Set 1 
$150.00 $150.00 
7.4 
Provide windows as indicated in dwgs. (3'-0" 
x 7-6") W/6 Set 6 
$150.00 $900.00 
7.5 
Provide louver and sliding glass windows as 
indicated in drawings (2'-6" x 2'-6") W/7 Set 5 
$150.00 $7,500.00 
NOTE; The cost for windows must 
include rogue bars using 5/8" square bar 
system. 
Sub total $9,450.00 
8.0 PAINTING AND DECORATIONS 
8.1 
Provide emulsion paint to all plastered 
surfaces. 5'-0 above floor level SY 916 
$1.00 $916.00 
8.2 Provide ceiling paint on ceiling SY 161 $1.00 $161.00 
8.3 Provide enamel paint to lower walls SY 807.75 $2.00 $1,615.50 
8.4 Provide wall primer SY 1077 $0.50 $538.50 
Sub total $3,231.00 
9.0 ELECTRICAL WORKS 
9.1 Provide ceiling lamp with fans. Set 2 $35.00 $70.00 
9.2 Provide wall outlet 220V Set 12 $2.50 $30.00 
9.3 Provide wall switch. Set 10 $1.00 $10.00 
9.4 
Allow a sum for electrical conduits, wires 
clamps, junction boxes, cups etc. 
Lump 
sum 1 
$1,500.00 $1,500.00 
9.5 Provide panel breaker system as per dwgs. Set 1 $250.00 $250.00 
9.6 Provide single fluorescent lamp 40W Set 4 $10.00 $40.00
9 
9.7 Wall lamp Set 5 $10.00 $50.00 
Sub total $1,950.00 
10.0 PLUMBING WORKS 
10.1 Provide water closet complete Set 2 $65.00 $130.00 
10.2 Provide wash basin complete Set 2 $55.00 $110.00 
10.3 Provide shower Set 3 $150.00 $450.00 
10.4 
Allow a sum for in-coming water and waste 
disposal system 
Lump 
sum 1 
$750.00 $750.00 
Sub total $1,440.00 
11.0 MISCELLENOUS 
11.1 
Allow a sum for the floor board and curtain 
boxes 
Lump 
Sum 1 
$500.00 $500.00 
Sub total $500.00 
TOTAL MATERIAL COST $59,629.80 
ADD FOR LABOR @25 
$14,907.45 
ADD FOR TRANS. @10% $5,962.98 
ADD FOR PROFIT @10% $5,962.98 
TOTAL COST OF CONSTRUCTION FOR COMPUTER 
LABORATORY 
$86,463.21 
IV. ENTRY COURT/ EMEGENCY EXIT PORCH AND RAMPS 
ITEM DESCRIPTION UNIT QTY. RATE EXTENSION 
1.0 PREPARATION FOR CONSTRUCTION 
1.1 
Grub away plant material and top soil and 
prepare by leveling the space for the entry 
court 
Lump 
sum 1 
$1,000.00 
$1,000.00 
Sub total $1,000.00 
2.0 EXCAVATION/ EARTH WORK 
2.1 
Excavate foundation trench as shown in 
foundation plans and details. CY 30 
$20.00 $600.00 
2.2 
Backfill excavated area with Laterite and or 
approved backfill material CY 50 
$15.00 $750.00 
2.3 
Backfill area within foundation wall to receive 
mass concrete floor slab. 12" compact CY 56 
$10.00 
$520.00 
Sub total $1,870.00 
3.0 CONCRETE WORKS 
NOTE: This includes all formwork, and 
material to cast conc. Complete. 
3.1 
Mix and pour class "C" concrete 1:3:5 as 
foundation column and walls footing as 
shown in foundation detail. CY 24 
$175.00 
$4,200.00 
Sub total $4,200.00
10 
4.0 WALLS WORKS 
4.1 
Construct 8" cement block wall as foundation 
walls. SY 60 
$10.00 $600.00 
4.2 Construct 4" low fence wall using 4" blocks. SY 25 $10.00 $250.00 
Sub total $5,650.00 
5.0 FINISHINING 
5.1 
Provide exterior tiles on mass concrete floor 
finishing. 12" x 12" SY 168 
$15.00 $2,520.00 
5.2 Provide 1"3 cement mix to plaster new walls SY 16.4 $10.00 $164.00 
5.3 Provide ceramic brick as veneer finish SY 16.4 $8.00 $131.20 
5.4 
Fabricate galvanized railing as per drawings 
and install. SY 50 
$10.00 $500.00 
Sub total $3,315.20 
6.0 PAINTING AND DECORATIONS 
6.1 
Provide emulsion paint to all plastered 
surfaces. 5'-0 above floor level SY 60 
$1.00 $60.00 
6.2 Provide wall primer SY 60 $1.00 $60.00 
6.3 Provide enamel paint for steel railing. 
Lump 
sum 1 
$100.00 $100.00 
Sub total $220.00 
7.0 ELECTRICAL WORKS 
7.1 Provide fence lamps. Set 9 $10.00 $90.00 
7.2 Provide wall outlet 220V Set 4 $2.50 $10.00 
7.3 Provide wall switch. Set 2 $1.00 $2.00 
7.4 
Allow a sum for electrical conduits, wires 
clamps, junction boxes, cups etc. 
Lump 
Sum 1 
$1500.00 $1,500.00 
7.5 Provide panel breaker system as per dwgs. Set 1 $250.00 $250.00 
7.6 Provide single fluorescent lamp 40W Set 4 $10.00 $40.00 
7.7 Wall lamp Set 4 $10.00 $40.00 
Sub total $1,931.00 
8.0 MISCELLENOUS 
8.1 
Allow a sum to plant "Firestone Grass" to all 
courtyards as indicated in the drawings. SY 50 
$15.00 
$750.00 
8.2 
Allow a sum for the construction of waiting 
benches at various waiting areas. Set 7 
$50.00 
$350.00 
8.3 
Allow a sum for concrete gutters as shown 
as surface drain system with cover Lt 40 
$10.00 
$400.00 
8.4 
Allow a sum for construction of all ramps 
incl. steel railings. 
Lump 
sum 1 
$1500.00 $1,500.00 
Sub total $3,000.00 
TOTAL MATERIAL COST 
$11,436.20 
ADD FOR LABOR @25% 
$2,859.05 
ADD FOR TRANS. @10% $1,143.62
11 
ADD FOR PROFIT @10% 
$1,143.62 
TOTAL COST FOR BUILDING ENTRY COURT/ 
EMEGENCY EXIT PORCH AND RAMPS 
$16,582.49 
V. GENERATOR HOUSE AND ELECTRICAL SUPPLY SYSTEM 
ITEM DESCRIPTION UNIT QTY. RATE EXTENSION 
1.0 EXCAVATION/ EARTH WORK 
1.1 
Excavate area as shown in working 
drawings, remove all vegetation and a top 
soil about 6" and prepare for construction of 
the foundation system. CY 52 
$20.00 
$1,040.00 
1.2 
Excavate foundation trench as shown in 
foundation plans and details. CY 15 
$15.00 $225.00 
1.3 
Backfill excavated area with Laterite and or 
approved backfill material CY 15 
$10.00 $150.00 
1.4 
Backfill area within foundation wall to receive 
mass concrete floor slab 12" compact CY 8 
$10.00 
$80.00 
Sub total $1,495.00 
2.0 CONCRETE WORKS 
NOTE: This includes all formwork, and 
material to cast conc. Complete. 
2.1 
Mix and pour class "C" concrete 1:3:5 as 
foundation column and walls footing as 
shown in foundation detail CY 2 
$175.00 
$350.00 
2.2 
Mix and pour Class "B" concrete 1:2:4 as 
col. and beams including lintels and roof slab CY 7 
$200.00 
$1,400.00 
Note 
Roof slab includes 2" screeding and 
application of bitumen over the entire 
surface as water proof membrane. This is 
for all concrete roof surfaces. 
2.3 
Mix and pour class "B" concrete as new 
doors and window lintel. CY 0.5 
$200.00 $100.00 
2.4 Mix and pour concrete floor slab incl. mesh CY 2.5 $200.00 $500.00 
Sub total $2,350.00 
3.0 WALLS WORKS 
3.1 
Provide 8" cement block as interior and 
exterior walls shown in the drawings 
including new walls as new height and new 
partition and foundation walls SY 93 
$10.00 
$930.00 
3.2 
Construct honey comb block walls shown in 
drawings (dirty lab) SY 4 
$5.00 $20.00 
Sub total $950.00 
4.0 ROOF 
(Roof is included in concrete works Item 3.2) 
5.0 FINISHINING 
5.1 
Provide 1"3 cement mix to plaster new walls 
and screed floor. SY 141 
$10.00 $1,410.00
12 
Sub total $1,410.00 
6.0 DOORS 
6.1 Provide steel door as shown 6'-0" x7'-0' Set 1 $500.00 $500.00 
6.2 Provide steel door as shown 2'-10" x 7'-0" Set 1 $250.00 $250.00 
Sub total $750.00 
7.0 PAINTING AND DECORATIONS 
7.1 
Provide emulsion paint to all plastered 
surfaces. SY 141 
$1.00 $141.00 
7.2 Provide ceiling paint on ceiling SY 23 $1.00 $23.00 
7.3 Provide enamel paint to doors 
Lump 
sum 1 
$2.00 $2.00 
7.4 Provide wall primer SY 164 $0.50 $$82.00 
Sub total $248.00 
8.0 ELECTRICAL WORKS 
8.1 Provide double fluorescent lamps. Set 2 $15.00 $30.00 
8.2 Provide wall outlet 220V Set 1 $25.00 $25.00 
8.3 Provide wall switch. Set 2 $1.00 $2.00 
8.4 
Allow a sum for electrical conduits, wires 
clamps, junction boxes, cups etc. 
Lump 
Sum 1 
$1000.00 $1,000.00 
8.5 Provide panel breaker system as per dwgs. Set 1 $250.00 $250.00 
Sub total $1,284.50 
9.0 ELECTRICAL DISTRIBUTION SYSTEM 
9.1 
Allow a sum to distribute electrical energy to 
main building from gen. including all wires 
conduit and electrical switches etc. to make 
system good. 
Lump 
Sum 1 
$750.00 
$750.00 
Sub total $750.00 
TOTAL MATERIAL COST $9,832.50 
` 
ADD FOR LABOR @25% $2,458.13 
ADD FOR TRANS. @10% $983.25 
ADD FOR PROFIT @ 10% $983.25 
TOTAL COST FOR BUILDING GENERATOR HOUSE 
AND ELECTRICAL SUPPLY SYSTEM 
$14,257.13 
VI. WATER SUPPLY SYSTEM 
ITEM DESCRIPTION UNIT QTY. RATE EXTENSION 
1.0 EXCAVATION/ EARTH WORK 
1.1 
Excavate area as shown in working 
drawings remove all vegetation and a top 
soil about 6" and prepare for construction of 
the foundation system. CY 32 
$20.00 
$640.00 
1.2 Excavate foundation trench as shown in CY 2.9 $15.00 $43.50
13 
foundation plans and details. 
1.3 
Backfill excavated area with Laterite and or 
approved backfill material CY 2 
$10.00 $20.00 
Sub total $703.50 
2.0 CONCRETE WORKS 
NOTE: This includes all formwork, and 
material to cast conc. Complete. 
2.1 
Mix and pour class "C" concrete 1:3:5 as 
foundation column and walls footing as 
shown in foundation detail CY 2 
$175.00 
$350.00 
2.2 
Mix and pour Class "B" concrete 1:2:4 as 
col. and beams including lintels and slab CY 14 
$200.00 $2,800.00 
Sub total $3,150.00 
3.0 FINISHINING 
3.1 
Provide 1"3 cement mix to plaster new walls 
and screed floor. SY 76 
$10.00 $760.00 
Sub total $760.00 
5.0 PAINTING AND DECORATIONS 
5.1 
Provide emulsion paint to all plastered 
surfaces. SY 76 
$2.00 $152.00 
5.2 Provide wall primer SY 76 $2.00 $152.00 
Sub total $304.00 
6.0 REDESIGN RAVAGED SYSTEM 
6.1 
Provide a functional water system that is 
capable to pump from a depth of 100 feet to 
100 to water tower and 35 ft up to reservoir 
including all PVC lines need to supply 
reservoir and building water system. 
Lump 
sum 1 
$3,000.00 
$3,000.00 
Sub total $3,000.00 
7.0 ELECTRICAL DISTRIBUTION SYSTEM 
7.1 
Allow a sum to distribute electrical energy to 
water pump including conduits, conductor 
etc. and switches. 
Lump 
Sum 1 
$2000.00 
$2,000.00 
Sub total $2,000.00 
8.0 EXCAVATION OF WELL 
8.1 
Use a mechanical drill and dig well down to 
100 ft of where good water is includes all 
pipes and distribution lines to feed the 
reservoir. 
Lump 
Sum 1 
$1500.00 
$1,500.00 
Sub total $1,500.00 
9.0 Poly tank 
Supply and install 1000 gallons poly tank 
including galvanized steel ladder as shown 
in drawing Each 2 
$1500.00 
$1,500.00 
Sub total $1,500.00 
TOTAL MATERIAL COST $12,917.50
14 
ADD FOR LABOR @25% $3,229.40 
ADD FOR TRANS. @10% 
$1,291.75 
ADD FOR PROFIT @10% $1,291.75 
TOTAL COST FOR BUILDING WATER SUPPLY 
SYSTEM 
$18,730.40 
GRAND TOTAL COST FOR ENTIRE PROJECT 
$375,246.28
15 
PROJECT COST SUMMARY 
I. MAIN LABORATORY BUILDING $161,783.75 
II. 
DIRTY LABORATORY AND ENTRY 
PORCH $77,429.30 
III. COMPUTER LABORATORY $86,463.21 
IV. 
ENTRY COURT/EMERGENCY EXIT 
PORCH AND RAMP $16,582.49 
V. 
GENERATOR HOUSE AND 
ELECTRICAL SUPPLY SYSTEM $14,257.13 
VI. WATER SUPPLY SYSTEM $12,917.50 
VII GENERAL CONTINGENCY @10% $37,524.63 
VIII. TOTAL PROJECT COST $412,770.91USD

More Related Content

What's hot

Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works ALI HYDER GADHI
 
Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and materialALI HYDER GADHI
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveyingAnchit Agrawal
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structuresRithika Ravishankar
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction Mereia Kali
 
Excavation 2014a-Lecture2
Excavation 2014a-Lecture2Excavation 2014a-Lecture2
Excavation 2014a-Lecture2Anne Allan
 
Bill of Quantities ( Door and Window )
Bill of Quantities ( Door and Window )Bill of Quantities ( Door and Window )
Bill of Quantities ( Door and Window )Lee Pei Gie
 
50451783 taking-off-quantity
50451783 taking-off-quantity50451783 taking-off-quantity
50451783 taking-off-quantityhlksd
 
Building Construction 1: project 1
Building Construction 1: project 1Building Construction 1: project 1
Building Construction 1: project 1Nabeel Joomun
 
Smm2 second edition
Smm2 second editionSmm2 second edition
Smm2 second editionBt Lee
 
Finishing works (Building Construction)
Finishing works (Building Construction)Finishing works (Building Construction)
Finishing works (Building Construction)Zairul Zaiky
 
Bq preamble
Bq preambleBq preamble
Bq preambleaizat76
 
Bungalow
Bungalow Bungalow
Bungalow Ah Jun
 
Specifications of buildings
Specifications of buildingsSpecifications of buildings
Specifications of buildingsSimarpreet Singh
 
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITYTHUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITYSSudhaVelan
 
5) int walls finishes bq
5) int walls finishes bq5) int walls finishes bq
5) int walls finishes bqJeanne Hoo
 
MEASUREMENT 4 SLIDES
MEASUREMENT 4 SLIDESMEASUREMENT 4 SLIDES
MEASUREMENT 4 SLIDESwendyteosy
 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveyingAwanish Shukla
 

What's hot (20)

Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works
 
Bq floor
Bq floorBq floor
Bq floor
 
Earthwork support
Earthwork supportEarthwork support
Earthwork support
 
Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and material
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structures
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction
 
Excavation 2014a-Lecture2
Excavation 2014a-Lecture2Excavation 2014a-Lecture2
Excavation 2014a-Lecture2
 
Bill of Quantities ( Door and Window )
Bill of Quantities ( Door and Window )Bill of Quantities ( Door and Window )
Bill of Quantities ( Door and Window )
 
50451783 taking-off-quantity
50451783 taking-off-quantity50451783 taking-off-quantity
50451783 taking-off-quantity
 
Building Construction 1: project 1
Building Construction 1: project 1Building Construction 1: project 1
Building Construction 1: project 1
 
Smm2 second edition
Smm2 second editionSmm2 second edition
Smm2 second edition
 
Finishing works (Building Construction)
Finishing works (Building Construction)Finishing works (Building Construction)
Finishing works (Building Construction)
 
Bq preamble
Bq preambleBq preamble
Bq preamble
 
Bungalow
Bungalow Bungalow
Bungalow
 
Specifications of buildings
Specifications of buildingsSpecifications of buildings
Specifications of buildings
 
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITYTHUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
 
5) int walls finishes bq
5) int walls finishes bq5) int walls finishes bq
5) int walls finishes bq
 
MEASUREMENT 4 SLIDES
MEASUREMENT 4 SLIDESMEASUREMENT 4 SLIDES
MEASUREMENT 4 SLIDES
 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveying
 

Similar to Bill Of Quantities

Sample qto credible estimating
Sample qto   credible estimatingSample qto   credible estimating
Sample qto credible estimatingcredibleestimating
 
M3 Lecture 10 timber roof structure answer
M3 Lecture 10 timber roof structure answerM3 Lecture 10 timber roof structure answer
M3 Lecture 10 timber roof structure answerEst
 
22274325 engineer-s-estimate-construction-of-technical-building-for-national-...
22274325 engineer-s-estimate-construction-of-technical-building-for-national-...22274325 engineer-s-estimate-construction-of-technical-building-for-national-...
22274325 engineer-s-estimate-construction-of-technical-building-for-national-...imaduddin91
 
Tim dettlaff presentation fmli nov 13 2014
Tim dettlaff presentation   fmli nov 13 2014Tim dettlaff presentation   fmli nov 13 2014
Tim dettlaff presentation fmli nov 13 2014MikeWorsfold
 
Home improvement costs for 2010
Home improvement costs for 2010Home improvement costs for 2010
Home improvement costs for 2010Roofers World
 
Dri expansion cost breakdown pdf-1
Dri expansion cost breakdown   pdf-1Dri expansion cost breakdown   pdf-1
Dri expansion cost breakdown pdf-1Tumehfamily
 
Everhaus Tiny house
Everhaus Tiny houseEverhaus Tiny house
Everhaus Tiny houseMatis Velt
 
Desiree tiny house
Desiree tiny houseDesiree tiny house
Desiree tiny houseMatis Velt
 
Visual Dictionary - Archess
Visual Dictionary - ArchessVisual Dictionary - Archess
Visual Dictionary - ArchessArchess
 
Passive House in California: Overkill or Appropriate?
Passive House in California: Overkill or Appropriate?Passive House in California: Overkill or Appropriate?
Passive House in California: Overkill or Appropriate?Bronwyn Barry
 
Girls home estimation
Girls home estimationGirls home estimation
Girls home estimationkrkantamneni
 
Girls home estimation
Girls home estimationGirls home estimation
Girls home estimationkrkantamneni
 
House Plan For Robert Ledwaba
House Plan For Robert LedwabaHouse Plan For Robert Ledwaba
House Plan For Robert LedwabaJan Malesela
 
House Messinger Proposal 2-Sections & Elevations
House Messinger Proposal 2-Sections & ElevationsHouse Messinger Proposal 2-Sections & Elevations
House Messinger Proposal 2-Sections & ElevationsAyla Damon
 

Similar to Bill Of Quantities (20)

Sample qto credible estimating
Sample qto   credible estimatingSample qto   credible estimating
Sample qto credible estimating
 
PARADISE ESTIMATING
PARADISE ESTIMATINGPARADISE ESTIMATING
PARADISE ESTIMATING
 
M3 Lecture 10 timber roof structure answer
M3 Lecture 10 timber roof structure answerM3 Lecture 10 timber roof structure answer
M3 Lecture 10 timber roof structure answer
 
22274325 engineer-s-estimate-construction-of-technical-building-for-national-...
22274325 engineer-s-estimate-construction-of-technical-building-for-national-...22274325 engineer-s-estimate-construction-of-technical-building-for-national-...
22274325 engineer-s-estimate-construction-of-technical-building-for-national-...
 
Nasir Documents
Nasir DocumentsNasir Documents
Nasir Documents
 
final dcc
final dccfinal dcc
final dcc
 
Structural Design Project
Structural Design ProjectStructural Design Project
Structural Design Project
 
Tim dettlaff presentation fmli nov 13 2014
Tim dettlaff presentation   fmli nov 13 2014Tim dettlaff presentation   fmli nov 13 2014
Tim dettlaff presentation fmli nov 13 2014
 
Home improvement costs for 2010
Home improvement costs for 2010Home improvement costs for 2010
Home improvement costs for 2010
 
Dri expansion cost breakdown pdf-1
Dri expansion cost breakdown   pdf-1Dri expansion cost breakdown   pdf-1
Dri expansion cost breakdown pdf-1
 
Everhaus Tiny house
Everhaus Tiny houseEverhaus Tiny house
Everhaus Tiny house
 
Desiree tiny house
Desiree tiny houseDesiree tiny house
Desiree tiny house
 
Visual Dictionary - Archess
Visual Dictionary - ArchessVisual Dictionary - Archess
Visual Dictionary - Archess
 
Passive House in California: Overkill or Appropriate?
Passive House in California: Overkill or Appropriate?Passive House in California: Overkill or Appropriate?
Passive House in California: Overkill or Appropriate?
 
Girls home estimation
Girls home estimationGirls home estimation
Girls home estimation
 
Girls home estimation
Girls home estimationGirls home estimation
Girls home estimation
 
RR Nagar
RR NagarRR Nagar
RR Nagar
 
8 months work
8 months work8 months work
8 months work
 
House Plan For Robert Ledwaba
House Plan For Robert LedwabaHouse Plan For Robert Ledwaba
House Plan For Robert Ledwaba
 
House Messinger Proposal 2-Sections & Elevations
House Messinger Proposal 2-Sections & ElevationsHouse Messinger Proposal 2-Sections & Elevations
House Messinger Proposal 2-Sections & Elevations
 

Bill Of Quantities

  • 1. 1 Bill of Quantities Bill of Quantities/Schedules of Prices PROJECT: REFURBISHMNENT OF THE AGRICULTURAL LABORATORY OF THE WILLIAM R. TOLBERT COLLEGE OF AGRICULTURE AND FORESTRY OF THE UNIVERSITY OF LIBERIA LOCATION: FENDELL MONTSERRADO COUNTY DATE: JULY 2014 I. MAIN LABORATORY BUILDING ITEM DESCRIPTION UNIT QTY. RATE EXTENSION 1.0 GENERAL MOBILIZATION 1.1 Allow a sum for general mobilization, including storage, security, hand tool, scaffolding temp. utilities etc. Lump sum 1 $4000.00 $4000.00 SUB TOTAL $4000.00 2.0 PREPARATION FOR CONSTRUCTION 2.1 Clean existing concrete shell and remove all unwanted material, garbage, and clean and repair existing masonry structure for renovation and remodeling 2.2 Demolish walls as shown in dotted line and store debris for future use if necessary. Lump Sum 1 $500.00 $ 5 0 0 .00 SUB TOTAL $500.00 3.0 EXCAVATION/ EARTH WORK 3.1 Excavate area as shown in working drawings, remove all vegetation, and a top soil about 12" and prepare for importation of required backfill to receive new floor slab CY 142 $20.00 $2,840.00 3.2 Backfill area within foundation wall to receive mass concrete floor slab. 12" compact CY 143 $15.00 $2145.00 SUB TOTAL $4,985.00 4.0 CONCRETE WORKS
  • 2. 2 NOTE: This includes all formwork, and material to cast conc. Complete 4.1 Mix and pour class "C" concrete 1:3:5 as new floor slab 4" thick including wire mesh as shown in foundation detail. CY 48 $175.00 $8400.00 4.2 Mix and pour Class "B" concrete 1:2:4 as col. and beams to increase the height of walls to accommodate additional walls and create the clerestory windows as instructed by the architect and shown in the drawings CY 10 $200.00 $2000.00 4.3 Mix and pour class "B" concrete as new doors and window lintel. CY 2.5 $200.00 $500.00 SUB TOTAL $10900.00 5.0 WALLS WORKS 5.1 Provide 8" cement block as interior and exterior walls shown in the drawings including new walls as new height and new partition SY 338 $10.00 $3380.00 5.2 Construct with alum and glass walls as shown in drawings (Laboratory Area) SF 880 $5.00 $4400.00 SUB TOTAL $7780.00 6.0 ROOF 6.1 Construct wooden roofing frame with long span metal roofing system complete. SY 616 $25.00 $15400.00 6.2 Provide and install complete plastic gutter system with 4" drain and connect to proposed "U" shape concrete drain Lf 152 $10.00 $1520.00 SUB TOTAL $16,920.00 7.0 FINISHINING 7.1 Provide terrazzo tiles on all floors as floor finishing 12" x 12" SY 428 $15.00 $6,420.00 7.2 Provide ceramic wall tiles walls in labs. up to 18" above countertops and floors of rest room including 5'-0" high on restrooms walls. SF 628 $10.00 $6,280.00 7.3 Clean existing walls and mend all masonry damage. Lump Sum 1 $500.00 $500.00 7.4 Provide 1"3 cement mix to plaster new walls SY 776 $10.00 $7760.00 7.5 Provide 1/4" ceiling system to all ceiling and under boxing using 2x4, 2x6, and all including ceiling strips, decorative material corner molding . SY 616 $20.00 $12320.00 SUB TOTAL $33,530.00 8.0 DOORS 8.1 Provide steel doors using 5/" square bars in angle irons with hinges, using European/ American standard locks These Door are for emergency door of labs as shown. (3'-0" x 7'-0") D/1 A Set 2 $500.00 $1000.00 8.2 Provide wooden frame door, with glass, paint with cylinder lock, (European or American Standard) brass hinges, wood Set 3 $300.00 $900.00
  • 3. 3 molding as shown (6-0"x 7'-0") D/2 8.3 Provide solid wood panel doors, varnish/paint with cylinder lock, (European or American Standard) brass hinges, wood molding as shown (6'-0" x 7'-0") D/3 Set 1 $250.00 $250.00 8.4 Provide solid wood panel doors as shown in drawings, varnished with cylinder lock (European or American Standard) with brass hinges, wood molding etc. Double (3'-0" x 7'- 0") D/4 Set 5 $175.00 $875.00 8.5 Provide wood and glass door with locks , brass hinges, etc as shown in drawings (3'- 0" x 7'-0") D/5 Set 4 $200.00 $800.00 8.6 Provide doors with louvers as vents. Single (3'-0" x 7'-0") D/6 Set 3 $200.00 $600.00 8.7 Provide doors with louvers as vents. Single (3'-0" x 7'-0") D/7 Set 3 $200.00 $600.00 SUB TOTAL $5025.00 9.0 WINDOWS 9.1 Provide louver and sliding glass windows as indicated in drawings (9'-0" x 4'-0") W/1 Set 25 $300.00 $7500.00 9.2 Provide windows as indicated in dwgs. (9'-0" x 2'-6") W/2 Set 9 $150.00 $1350.00 9.3 Provide windows as indicated in dwgs. (4'-0" x 4'-6") W/5 Set 3 $150.00 $450.00 9.4 Provide louver and sliding glass windows as indicated in drawings (2'-6" x 2'-6") W/7 Set 3 $100.00 $300.00 9.5 Provide windows as indicated in dwgs. (6'-0" x 2'-6") Jalousie louvers W/9 Set 6 $150.00 $900.00 NOTE; The cost for windows must include rogue bars using 5/8" square bar system SUB TOTAL $10,500.00 10.0 PAINTING AND DECORATIONS 10.1 Provide emulsion paint to all plastered surfaces. 5'-0 above floor level SY 1200 $1.00 $1200.00 10.2 Provide ceiling paint on ceiling SY 616 $1.00 $616.00 10.3 Provide enamel paint to lower walls SY 1200 $2.00 $2400.00 10.4 Provide wall primer SY 3016 $0.50 $1508.00 SUB TOTAL $5,724.00 11.0 ELECTRICAL WORKS 11.1 Provide double fluorescent lamps. Set 15 $15.00 $225.00 11.2 Provide wall outlet 220V Set 25 $2.50 $62.50 11.3 Provide wall switch. Set 19 $1.00 $28.50 11.4 Allow a sum for electrical conduits, wires clamps, junction boxes, cups etc. Lump Sum 1 $2500.00 $2500.00 11.5 Provide panel breaker system as per dwgs. Set 1 $250.00 $250.00 11.6 Provide single fluorescent lamp 40W Set 1 $10.00 $10.00 11.7 Globe Lamp 40W Set 14 $15.00 $210.00 Sub total $3286.00 12.0 PLUMBING WORKS
  • 4. 4 12.1 Provide water closet complete Set 3 $65.00 $195.00 12.2 Provide wash basin complete Set 3 $55.00 $165.00 12.3 Provide shower complete and shower head in lab shower in lab Set 3 $150.00 $450.00 12.4 Allow a sum for in-coming water and waste disposal system Lump Sum 1 $750.00 $750.00 12.5 Allow a sum for septic tank and manholes Lump Sum 1 $2500.00 $2500.00 Sub total $4060.00 10.0 MISCELLENOUS 10.1 Allow a sum for shelves of the store rooms Lump Sum 1 $500.00 $500.00 10.2 Allow a sum for the cabinet in the lab. with granite tops and ceramic lab sinks and lab faucets. (Must be approved by arch. Set 4 $700.00 $2100.00 10.3 Allow a sum for the floor board and curtain boxes Lump sum 1 $500.00 $500.00 10.4 Allow a sum for concrete gutters as shown as surface drain system Lt 247 $5.00 $1235.00 SUB TOTAL $4,335.00 TOTAL MATERIAL $111,575.00 ADD FOR LABOR @25% $27,893.75 ADD FOR TRANS. @10% $11,157.50 ADD FOR PROFIT @10% $11,157.50 GRAND TOTAL FOR MAIN LABORATORY BUILDING $161,783.75 II. THE DIRTY LABORATORY AND ENTRY PORCH ITEM DESCRIPTION UNIT QTY. RATE EXTENSION 1.0 EXCAVATION/ EARTH WORK 1.1 Excavate area as shown in working drawings, remove all vegetation, and a top soil about 6" and prepare for construction of the foundation system CY 232 $20.00 $4,640.00 1.2 Excavate foundation trench as shown in foundation plans and details. CY 62 $20.00 $620.00 1.3 Backfill excavated area with Laterite and or approved backfill material CY 81 $20.00 $810.00 1.4 Backfill area within foundation wall to receive mass concrete floor slab 12" compact CY 41 $20.00 $410.00 Sub total $6,480.00 2.0 CONCRETE WORKS NOTE: This includes all formwork, and material to cast conc. Complete. 2.1 Mix and pour class "C" concrete 1:3:5 as foundation column and walls footing as CY 29 $175.00 $5075.00
  • 5. 5 shown in foundation detail 2.2 Mix and pour Class "B" concrete 1:2:4 as col. and beams including lintels and roof slab CY 22 $200.00 $4400.00 Note: Roof slab includes 2" screeding and application of bitumen over the entire surface as water proof membrane. This is for all concrete roof surfaces 2.3 Mix and pour class "B" concrete as as new doors and window lintel. CY 1 $200.00 $200.00 2.4 Mix and pour conc. floor slab incl. mesh CY 12 $175.00 $2100.00 Sub total $11,775.00 3.0 WALLS WORKS 3.1 Provide 8" cement block as interior and exterior walls shown in the drawings including new walls as new height and new partition including foundation walls SY 217 $10.00 $2170.00 3.2 Construct honey comb block walls shown in drawings (dirty lab) SY 45 $5.00 $225.00 3.3 Construct 8" cement block wall as foundation walls SY 132 $10.00 $1320.00 Sub total $3715.00 4.0 ROOF 4.1 Construct wooden roofing frame with long span metal roofing system complete SY 152 $25.00 $3800.00 4.2 Provide and install complete plastic gutter system with 4" drain and connect to proposed "U" shape concrete drain Lf 39 $10.00 $390.00 Sub total $7905,00 5.0 FINISHINING 5.1 Provide terrazzo tiles on all floors as floor finishing 12" x 12" SY 147 $15.00 $2205.00 5.2 Provide ceramic wall tiles walls in labs up to 18" above countertops and floors of rest room including 5'-0" high on restrooms walls. SF 192 $10.00 $1920.00 5.3 Provide 1"3 cement mix to plaster new walls SY 654 $10.00 $6540.00 5.4 Provide 1/4" ceiling system to all ceiling and under boxing using 2x4, 2x6, and all material including ceiling strips, decorative corner molding. SY 152 $20.00 $3040.00 Sub total $13,705.00 6.0 DOORS 6.1 Provide steel doors using 5/" square bars in angle irons with hinges, using European/ American standard locks as shown. (6'-0" x 7'-0") D/1 Set 2 $500.00 $1000.00 6.2 Provide solid wood panel doors as shown in drawings, varnished with cylinder lock (European or American Standard) with brass hinges, wood molding etc. Double (3'-0" x 7'- 0") D/4 Set 2 200.00 $400.00 6.3 Provide wood and glass door with locks , Set 1
  • 6. 6 brass hinges, etc as shown in drawings (3'- 0" x 7'-0") D/5 $200.00 $200.00 Sub total $1600.00 7.0 WINDOWS 7.1 Provide windows as indicated in dwgs. (9'-0" x 2'-6") W/2 Set 4 $125.00 $500.00 NOTE; The cost for windows must include rogue bars using 5/8" square bar system. This is for the entire building. Sub total $500.00 8.0 PAINTING AND DECORATIONS 8.1 Provide emulsion paint to all plastered surfaces. 5'-0 above floor level SY 654 $1.00 $654.00 8.2 Provide ceiling paint on ceiling SY 152 $1.00 $152.00 8.3 Provide enamel paint to lower walls SY 654 $2.00 $1,308.00 8.4 Provide wall primer SY 1460 $0.5 $730.00 SUB TOTAL $2,844.00 9.0 ELECTRICAL WORKS 9.1 Provide double fluorescent lamps. Set 7 $15.00 $105.00 9.2 Provide wall outlet 220V Set 7 $2.50 $17.50 9.3 Provide wall switch. Set 3 $1.00 $3.00 9.3 Allow a sum for electrical conduits, wires clamps, junction boxes, cups etc. Lump Sum 1 $1500.00 $1500.00 9.5 Provide panel breaker system as per dwgs. Set 1 $250.00 $250.00 Sub total $1,875.50 10.0 PLUMBING WORKS Waste disposal system Lump Sum 1 $500.00 $500.00 Sub total $500.00 11.0 MISCELLENOUS 11.1 Allow a sum for shelves of the soil storage room Lump Sum 1 $500.00 $500.00 10.3 Allow a sum for the cabinet in the lab with granite tops and ceramic lab sink/ faucet Set 2 $750.00 $1500.00 10.4 Allow a sum for the floor board and curtain boxes Lump Sum 1 $500.00 $500.00 Sub total $2,500.00 TOTAL MATERIAL COST $53,399.50 ADD FOR LABOR @25% $13,349.90 ADD FOR TRANSPORTATION @10% $5,339.95 ADD FOR PROFIT @10% $5,339.95 TOTAL COST FOR DIRTY LABORATORY AND ENTRY PORCH $77,429.30
  • 7. 7 III. COMPUTER LABORATORY ITEM DESCRIPTION UNIT QTY. RATE EXTENSION 1.0 EXCAVATION/ EARTH WORK 1.1 Excavate area as shown in working drawings remove all vegetation, and a top soil about 6" and prepare for construction of the foundation system CY 200 $20.00 $4000.00 1.2 Excavate foundation trench as shown in foundation plans and details. CY 47 $15.00 $705.00 1.3 Backfill excavated area with Laterite and or approved backfill material CY 102 $10.00 $1,020.00 1.4 Backfill area within foundation wall to receive mass concrete floor slab 12" compact CY 51 $10.00 $510.00 Sub total $6,235.00 2.0 CONCRETE WORKS NOTE: This includes all formwork, and material to cast conc. Complete. 2.1 Mix and pour class "C" concrete 1:3:5 as foundation column and walls footing as shown in foundation detail CY 22 $175.00 $3850.00 2.2 Mix and pour Class "B" concrete 1:2:4 as col. and beams including lintels and roof slab CY 21 $200.00 $4,200.00 2.3 Mix and pour class "B" concrete as new doors and window lintel. CY 1 $200.00 $200.00 2.4 Mix and pour floor slab 4" thick including mesh wire CY 17 $200.00 $3,400.00 Sub total $11,650.00 3.0 WALLS WORKS 3.1 Provide 8" cement block as interior and exterior walls shown in the drawings including new walls as new height and new partition INCL. foundation walls SY 195 $10.00 $1,950.00 3.2 Construct honey comb block walls shown in drawings (dirty lab) SY 48.75 $5.00 $243.80 3.3 Construct 8" cement block wall as foundation walls. SY 308 $10.00 $3,080.00 Sub total $5,273.80 4.0 ROOF 4.1 Construct wooden roofing frame with long span metal roofing system complete. SY 161 $25.00 $4,025.00 4.2 system with 4" drain and connect to proposed "U" shape concrete drain Lf 47 $10.00 $470.00 SUB TOTAL $4,495.00 5.0 FINISHINING 5.1 Provide terrazzo tiles on all floors as floor finishing. 12" x 12" SY 168 $15.00 $2520.00 5.2 Provide ceramic wall tiles walls in RESTROOMS and floors. SF 300 $10.00 $3,000.00 5.3 Provide 1"3 cement mix to plaster new walls SY 916 $10.00 $9,160.00 5.4 Provide 1/4" ceiling system to all ceiling and SY 161
  • 8. 8 under boxing using 2x4, 2x6, and all material including ceiling strips, decorative corner molding. $20.00 $3,220.00 Sub total $17,900.00 6.0 DOORS 6.1 Provide solid wood panel doors, varnish/paint with cylinder lock, (European or American Standard) brass hinges, wood molding as shown (6'-0" x 7'-0") D/3 Set 1 $200.00 $200.00 6.2 Provide solid wood panel doors as shown in drawings, varnished with cylinder lock (European or American Standard) with brass hinges, wood molding etc. Double (3'-0" x 7'- 0") D/4 Set 2 $200.00 $400.00 6.3 Provide wood and glass door with locks , brass hinges, etc as shown in drawings (3'- 0" x 7'-0") D/5 Set 1 $200.00 $200.00 6.4 Provide doors with louvers as vents. Single (3'-0" x 7'-0") D/6 Set 6 $200.00 $1,200.00 Sub total $2000.00 7.0 WINDOWS 7.1 Provide louver and sliding glass windows as indicated in drawings (9'-0" x 4'-0") W/1 Set 2 $150.00 $300.00 7.2 Provide windows as indicated in dwgs. (9'-0" x 2'-6") W/2 Set 4 $150.00 $600.00 7.3 Provide louver and sliding glass windows as indicated in drawings (6'-0" x 4'-0") W/4 Set 1 $150.00 $150.00 7.4 Provide windows as indicated in dwgs. (3'-0" x 7-6") W/6 Set 6 $150.00 $900.00 7.5 Provide louver and sliding glass windows as indicated in drawings (2'-6" x 2'-6") W/7 Set 5 $150.00 $7,500.00 NOTE; The cost for windows must include rogue bars using 5/8" square bar system. Sub total $9,450.00 8.0 PAINTING AND DECORATIONS 8.1 Provide emulsion paint to all plastered surfaces. 5'-0 above floor level SY 916 $1.00 $916.00 8.2 Provide ceiling paint on ceiling SY 161 $1.00 $161.00 8.3 Provide enamel paint to lower walls SY 807.75 $2.00 $1,615.50 8.4 Provide wall primer SY 1077 $0.50 $538.50 Sub total $3,231.00 9.0 ELECTRICAL WORKS 9.1 Provide ceiling lamp with fans. Set 2 $35.00 $70.00 9.2 Provide wall outlet 220V Set 12 $2.50 $30.00 9.3 Provide wall switch. Set 10 $1.00 $10.00 9.4 Allow a sum for electrical conduits, wires clamps, junction boxes, cups etc. Lump sum 1 $1,500.00 $1,500.00 9.5 Provide panel breaker system as per dwgs. Set 1 $250.00 $250.00 9.6 Provide single fluorescent lamp 40W Set 4 $10.00 $40.00
  • 9. 9 9.7 Wall lamp Set 5 $10.00 $50.00 Sub total $1,950.00 10.0 PLUMBING WORKS 10.1 Provide water closet complete Set 2 $65.00 $130.00 10.2 Provide wash basin complete Set 2 $55.00 $110.00 10.3 Provide shower Set 3 $150.00 $450.00 10.4 Allow a sum for in-coming water and waste disposal system Lump sum 1 $750.00 $750.00 Sub total $1,440.00 11.0 MISCELLENOUS 11.1 Allow a sum for the floor board and curtain boxes Lump Sum 1 $500.00 $500.00 Sub total $500.00 TOTAL MATERIAL COST $59,629.80 ADD FOR LABOR @25 $14,907.45 ADD FOR TRANS. @10% $5,962.98 ADD FOR PROFIT @10% $5,962.98 TOTAL COST OF CONSTRUCTION FOR COMPUTER LABORATORY $86,463.21 IV. ENTRY COURT/ EMEGENCY EXIT PORCH AND RAMPS ITEM DESCRIPTION UNIT QTY. RATE EXTENSION 1.0 PREPARATION FOR CONSTRUCTION 1.1 Grub away plant material and top soil and prepare by leveling the space for the entry court Lump sum 1 $1,000.00 $1,000.00 Sub total $1,000.00 2.0 EXCAVATION/ EARTH WORK 2.1 Excavate foundation trench as shown in foundation plans and details. CY 30 $20.00 $600.00 2.2 Backfill excavated area with Laterite and or approved backfill material CY 50 $15.00 $750.00 2.3 Backfill area within foundation wall to receive mass concrete floor slab. 12" compact CY 56 $10.00 $520.00 Sub total $1,870.00 3.0 CONCRETE WORKS NOTE: This includes all formwork, and material to cast conc. Complete. 3.1 Mix and pour class "C" concrete 1:3:5 as foundation column and walls footing as shown in foundation detail. CY 24 $175.00 $4,200.00 Sub total $4,200.00
  • 10. 10 4.0 WALLS WORKS 4.1 Construct 8" cement block wall as foundation walls. SY 60 $10.00 $600.00 4.2 Construct 4" low fence wall using 4" blocks. SY 25 $10.00 $250.00 Sub total $5,650.00 5.0 FINISHINING 5.1 Provide exterior tiles on mass concrete floor finishing. 12" x 12" SY 168 $15.00 $2,520.00 5.2 Provide 1"3 cement mix to plaster new walls SY 16.4 $10.00 $164.00 5.3 Provide ceramic brick as veneer finish SY 16.4 $8.00 $131.20 5.4 Fabricate galvanized railing as per drawings and install. SY 50 $10.00 $500.00 Sub total $3,315.20 6.0 PAINTING AND DECORATIONS 6.1 Provide emulsion paint to all plastered surfaces. 5'-0 above floor level SY 60 $1.00 $60.00 6.2 Provide wall primer SY 60 $1.00 $60.00 6.3 Provide enamel paint for steel railing. Lump sum 1 $100.00 $100.00 Sub total $220.00 7.0 ELECTRICAL WORKS 7.1 Provide fence lamps. Set 9 $10.00 $90.00 7.2 Provide wall outlet 220V Set 4 $2.50 $10.00 7.3 Provide wall switch. Set 2 $1.00 $2.00 7.4 Allow a sum for electrical conduits, wires clamps, junction boxes, cups etc. Lump Sum 1 $1500.00 $1,500.00 7.5 Provide panel breaker system as per dwgs. Set 1 $250.00 $250.00 7.6 Provide single fluorescent lamp 40W Set 4 $10.00 $40.00 7.7 Wall lamp Set 4 $10.00 $40.00 Sub total $1,931.00 8.0 MISCELLENOUS 8.1 Allow a sum to plant "Firestone Grass" to all courtyards as indicated in the drawings. SY 50 $15.00 $750.00 8.2 Allow a sum for the construction of waiting benches at various waiting areas. Set 7 $50.00 $350.00 8.3 Allow a sum for concrete gutters as shown as surface drain system with cover Lt 40 $10.00 $400.00 8.4 Allow a sum for construction of all ramps incl. steel railings. Lump sum 1 $1500.00 $1,500.00 Sub total $3,000.00 TOTAL MATERIAL COST $11,436.20 ADD FOR LABOR @25% $2,859.05 ADD FOR TRANS. @10% $1,143.62
  • 11. 11 ADD FOR PROFIT @10% $1,143.62 TOTAL COST FOR BUILDING ENTRY COURT/ EMEGENCY EXIT PORCH AND RAMPS $16,582.49 V. GENERATOR HOUSE AND ELECTRICAL SUPPLY SYSTEM ITEM DESCRIPTION UNIT QTY. RATE EXTENSION 1.0 EXCAVATION/ EARTH WORK 1.1 Excavate area as shown in working drawings, remove all vegetation and a top soil about 6" and prepare for construction of the foundation system. CY 52 $20.00 $1,040.00 1.2 Excavate foundation trench as shown in foundation plans and details. CY 15 $15.00 $225.00 1.3 Backfill excavated area with Laterite and or approved backfill material CY 15 $10.00 $150.00 1.4 Backfill area within foundation wall to receive mass concrete floor slab 12" compact CY 8 $10.00 $80.00 Sub total $1,495.00 2.0 CONCRETE WORKS NOTE: This includes all formwork, and material to cast conc. Complete. 2.1 Mix and pour class "C" concrete 1:3:5 as foundation column and walls footing as shown in foundation detail CY 2 $175.00 $350.00 2.2 Mix and pour Class "B" concrete 1:2:4 as col. and beams including lintels and roof slab CY 7 $200.00 $1,400.00 Note Roof slab includes 2" screeding and application of bitumen over the entire surface as water proof membrane. This is for all concrete roof surfaces. 2.3 Mix and pour class "B" concrete as new doors and window lintel. CY 0.5 $200.00 $100.00 2.4 Mix and pour concrete floor slab incl. mesh CY 2.5 $200.00 $500.00 Sub total $2,350.00 3.0 WALLS WORKS 3.1 Provide 8" cement block as interior and exterior walls shown in the drawings including new walls as new height and new partition and foundation walls SY 93 $10.00 $930.00 3.2 Construct honey comb block walls shown in drawings (dirty lab) SY 4 $5.00 $20.00 Sub total $950.00 4.0 ROOF (Roof is included in concrete works Item 3.2) 5.0 FINISHINING 5.1 Provide 1"3 cement mix to plaster new walls and screed floor. SY 141 $10.00 $1,410.00
  • 12. 12 Sub total $1,410.00 6.0 DOORS 6.1 Provide steel door as shown 6'-0" x7'-0' Set 1 $500.00 $500.00 6.2 Provide steel door as shown 2'-10" x 7'-0" Set 1 $250.00 $250.00 Sub total $750.00 7.0 PAINTING AND DECORATIONS 7.1 Provide emulsion paint to all plastered surfaces. SY 141 $1.00 $141.00 7.2 Provide ceiling paint on ceiling SY 23 $1.00 $23.00 7.3 Provide enamel paint to doors Lump sum 1 $2.00 $2.00 7.4 Provide wall primer SY 164 $0.50 $$82.00 Sub total $248.00 8.0 ELECTRICAL WORKS 8.1 Provide double fluorescent lamps. Set 2 $15.00 $30.00 8.2 Provide wall outlet 220V Set 1 $25.00 $25.00 8.3 Provide wall switch. Set 2 $1.00 $2.00 8.4 Allow a sum for electrical conduits, wires clamps, junction boxes, cups etc. Lump Sum 1 $1000.00 $1,000.00 8.5 Provide panel breaker system as per dwgs. Set 1 $250.00 $250.00 Sub total $1,284.50 9.0 ELECTRICAL DISTRIBUTION SYSTEM 9.1 Allow a sum to distribute electrical energy to main building from gen. including all wires conduit and electrical switches etc. to make system good. Lump Sum 1 $750.00 $750.00 Sub total $750.00 TOTAL MATERIAL COST $9,832.50 ` ADD FOR LABOR @25% $2,458.13 ADD FOR TRANS. @10% $983.25 ADD FOR PROFIT @ 10% $983.25 TOTAL COST FOR BUILDING GENERATOR HOUSE AND ELECTRICAL SUPPLY SYSTEM $14,257.13 VI. WATER SUPPLY SYSTEM ITEM DESCRIPTION UNIT QTY. RATE EXTENSION 1.0 EXCAVATION/ EARTH WORK 1.1 Excavate area as shown in working drawings remove all vegetation and a top soil about 6" and prepare for construction of the foundation system. CY 32 $20.00 $640.00 1.2 Excavate foundation trench as shown in CY 2.9 $15.00 $43.50
  • 13. 13 foundation plans and details. 1.3 Backfill excavated area with Laterite and or approved backfill material CY 2 $10.00 $20.00 Sub total $703.50 2.0 CONCRETE WORKS NOTE: This includes all formwork, and material to cast conc. Complete. 2.1 Mix and pour class "C" concrete 1:3:5 as foundation column and walls footing as shown in foundation detail CY 2 $175.00 $350.00 2.2 Mix and pour Class "B" concrete 1:2:4 as col. and beams including lintels and slab CY 14 $200.00 $2,800.00 Sub total $3,150.00 3.0 FINISHINING 3.1 Provide 1"3 cement mix to plaster new walls and screed floor. SY 76 $10.00 $760.00 Sub total $760.00 5.0 PAINTING AND DECORATIONS 5.1 Provide emulsion paint to all plastered surfaces. SY 76 $2.00 $152.00 5.2 Provide wall primer SY 76 $2.00 $152.00 Sub total $304.00 6.0 REDESIGN RAVAGED SYSTEM 6.1 Provide a functional water system that is capable to pump from a depth of 100 feet to 100 to water tower and 35 ft up to reservoir including all PVC lines need to supply reservoir and building water system. Lump sum 1 $3,000.00 $3,000.00 Sub total $3,000.00 7.0 ELECTRICAL DISTRIBUTION SYSTEM 7.1 Allow a sum to distribute electrical energy to water pump including conduits, conductor etc. and switches. Lump Sum 1 $2000.00 $2,000.00 Sub total $2,000.00 8.0 EXCAVATION OF WELL 8.1 Use a mechanical drill and dig well down to 100 ft of where good water is includes all pipes and distribution lines to feed the reservoir. Lump Sum 1 $1500.00 $1,500.00 Sub total $1,500.00 9.0 Poly tank Supply and install 1000 gallons poly tank including galvanized steel ladder as shown in drawing Each 2 $1500.00 $1,500.00 Sub total $1,500.00 TOTAL MATERIAL COST $12,917.50
  • 14. 14 ADD FOR LABOR @25% $3,229.40 ADD FOR TRANS. @10% $1,291.75 ADD FOR PROFIT @10% $1,291.75 TOTAL COST FOR BUILDING WATER SUPPLY SYSTEM $18,730.40 GRAND TOTAL COST FOR ENTIRE PROJECT $375,246.28
  • 15. 15 PROJECT COST SUMMARY I. MAIN LABORATORY BUILDING $161,783.75 II. DIRTY LABORATORY AND ENTRY PORCH $77,429.30 III. COMPUTER LABORATORY $86,463.21 IV. ENTRY COURT/EMERGENCY EXIT PORCH AND RAMP $16,582.49 V. GENERATOR HOUSE AND ELECTRICAL SUPPLY SYSTEM $14,257.13 VI. WATER SUPPLY SYSTEM $12,917.50 VII GENERAL CONTINGENCY @10% $37,524.63 VIII. TOTAL PROJECT COST $412,770.91USD