SlideShare a Scribd company logo
1 of 3
Download to read offline
S.No. Description of work No's L(in ft.) B(in ft.) D(in ft.) Quantity unit rate cost
1 V.R.C.C. 1:2:4 using 20mm HBG
metal and Fe 415 steel including all
(a) Columns
12X18 6 1.00 1.5 8.50 76.50
15X15 1 1.25 1.25 8.50 13.28
18X15 1 1.50 1.25 8.50 15.94
105.72 Cft 200 21144
(b)Slab 1 24 33.75 0.33 267.30 Cft 200 53460
(C ) Roof beams
1 1.75 202.13
1 32 0.75 1.75 42.00
3 21 0.75 1.75 82.69
326.81 Cft 250 81703
(e) lintels/sunshades
W5 2 5.00 1.5 0.25 3.75
w3 2 3 1.5 0.25 2.25
w2 2 2 1.5 0.25 1.50
v2 2 2 1.5 0.25 1.50
9.00 Cft 150 1350
(f) Lofts
1 17.50 2.00 0.25 8.75
1 7.50 2.00 0.25 3.75
12.50 Cft 150 1875
2
Supplying and fixing of teak wood
frames & Teak wood shutters,hard
ware fittings etc.
MAIN DOORS 1 3.50 7.00 24.50
24.50 Sft 929 22770
2a
Supplying and fixing of Sal wood
frames & Block board shutters,hard
ware fittings etc.
D2.5 6 2.50 6.5 97.50
97.50 Sft 465 45307
3
Supplying and fixing of Sal wood
windows with double glazed glass
etc.
W2 3 2.00 4.50 27.00
W3 2 3.00 4.50 27.00
W5 2 5.00 4.50 45.00
99.00 Sft 250 24750
4
Supplying and fixing of ventilators
with frames hardware fittings etc.
V2 2 2.00 2.00 8.00
107.00 Sft 250 26750
5
Superstructure in brick masonry
using first class brick in C.M 1:4 for
6" thk. Walls including all
1 106 0.5 8.50 450.50
GIRLS HOSTEL FLOOR ESTIMATE
115.5
Page 1 of 3
Deductions
MD -1 3.5 0.5 7.00 -12.25
D2.5 -1 2.5 0.5 6.50 -8.13
W2 -3 2.00 0.5 4.50 -13.50
W3 -2 3.00 0.5 4.50 -13.50
W5 -2 5.00 0.5 4.50 -22.50
V2 -2 2.00 0.5 2.00 -4.00
Total 6" Brick masonary 376.63 Cft 156 58664
5A
Superstructure in brick masonry
using first class brick in C.M 1:4 for
4.5" thk. Walls including all
1 13.75 0.375 8.50 43.83
1 18.00 0.375 8.50 57.38
1 4.00 0.375 8.50 12.75
1 3.50 0.375 8.50 11.16
1 8.50 0.375 8.50 27.09
Deductions
D2.5 -5 2.50 0.375 6.50 -30.47
Total 4.5" Brick masonary 121.73 Cft 119 14480
S.No. Description of work No's L(in ft.) B(in ft.) D(in ft.) Quantity unit
6
Internal plastering of 12mm thk. To
the walls with sponge finishing
C.M.1:6 including all
Internal wall area 1 47.75 8.50 405.88
Deduction area
D2.5 -5 2.50 6.50 -81.25
324.63
Sofits area 48.69
Net Plaster area 373.32 Sft 20 7466
7
External plastering 12mm thk.to the
walls with sponge finishing C.M.1:6
including all
EXternal wall area 1 106.00 8.50 901.00
Deduction area
MD -1 3.50 7.00 -24.50
D2.5 -1 2.5 6.50 -16.25
W2 -3 2.00 4.50 -27.00
W3 -2 3.00 4.50 -27.00
W5 -2 5.00 4.50 -45.00
V2 -2 2.00 2.00 -8.00
753.25
Sofits area 112.99
Net Plaster area 866.24 Sft 26 22541
8
Plastering 12mm thk.to the Ceiling
with sponge finishing C.M.1:6
including all
1
692.00 Sft 23 15916
9
Distemper for inside plastering
including all 373.32 Sft 11 4163
Same as insideside plastering
area
Page 2 of 3
9a
Distemper for ceiling plastering
including all 692.00 Sft 7 4844
10
Weather Proof paint on external
walls including all 866.24 Sft 30 25987
11
Flooring with 3/4" thick Marble
stones in CM 1:6 and joint with white
cement including all.(for all rooms)
living 1 350.00
Multipurpose 1 112.00
Sick 1 75.00
537.00 Sft 250 134250
11a
Flooring with antiskid tiles including
all.(for all toilets &utilities)
BATH 1 13.00
WC1 1 12.00
UTILITY 1 30.00
STORE 1 23.00
48.00 Sft 45 2160
12
Providing & dadoing in toilets using
ceramic tiles
BATH 1 14.75 6 88.50
WC1 1 14.50 6 87.00
UTILITY 1 15.00 5 75.00
Deductions -3 2.50 6 -45.00
Net Dadoing area 205.50 Sft 45 9248
13
Skirting with 3/4" thick Marble
stones in CM 1:6 and joined with
cement including all
1 87 0.5 43.50
1 42.5 0.5 21.25
1 38.5 0.5 19.25
staircase 20 3.125 0.5 31.25
115.25 Sft 30 3458
14 M.S railings
balconies 1 16 4 64.00
staircase handrailing 1 20 3 60.00
124.00 Sft 209 25929
Girls Hostel Floor Total 608215
contingencies 15% 91232
Estimated Cost 699447
area 808
cost per square feet 866
Same as ceiling plastering area
Same as outside plastering area
Page 3 of 3

More Related Content

Similar to VRC COST ESTIMATE

Boys home shed estimation
Boys home shed estimationBoys home shed estimation
Boys home shed estimationkrkantamneni
 
Project of construction management
Project of construction managementProject of construction management
Project of construction managementMuhammad Umar Hayat
 
97170708 estimate-of-material-and-labor
97170708 estimate-of-material-and-labor97170708 estimate-of-material-and-labor
97170708 estimate-of-material-and-laborimaduddin91
 
Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal ashleyyeap
 
28725680 qarghayi-anp-estimation
28725680 qarghayi-anp-estimation28725680 qarghayi-anp-estimation
28725680 qarghayi-anp-estimationimaduddin91
 
128249253 deped-estimate
128249253 deped-estimate128249253 deped-estimate
128249253 deped-estimateimaduddin91
 
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdfTender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdfssuserd43de8
 
72747160 estimation
72747160 estimation72747160 estimation
72747160 estimationimaduddin91
 
L. labour-charges-for-11k v-system-1
L. labour-charges-for-11k v-system-1L. labour-charges-for-11k v-system-1
L. labour-charges-for-11k v-system-1Ramesh Meti
 
47093152 estimation
47093152 estimation47093152 estimation
47093152 estimationimaduddin91
 
58517990 estimating-resi-building
58517990 estimating-resi-building58517990 estimating-resi-building
58517990 estimating-resi-buildingimaduddin91
 

Similar to VRC COST ESTIMATE (20)

Boys home shed estimation
Boys home shed estimationBoys home shed estimation
Boys home shed estimation
 
Construction Management Project
Construction Management ProjectConstruction Management Project
Construction Management Project
 
Project of construction management
Project of construction managementProject of construction management
Project of construction management
 
97170708 estimate-of-material-and-labor
97170708 estimate-of-material-and-labor97170708 estimate-of-material-and-labor
97170708 estimate-of-material-and-labor
 
Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal
 
Rab
RabRab
Rab
 
28725680 qarghayi-anp-estimation
28725680 qarghayi-anp-estimation28725680 qarghayi-anp-estimation
28725680 qarghayi-anp-estimation
 
128249253 deped-estimate
128249253 deped-estimate128249253 deped-estimate
128249253 deped-estimate
 
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdfTender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
Tender_Schedule_Renovation_of_Vadakkechira_Bus_Stand.pdf
 
72747160 estimation
72747160 estimation72747160 estimation
72747160 estimation
 
GBI: Role of BS
GBI: Role of BSGBI: Role of BS
GBI: Role of BS
 
L. labour-charges-for-11k v-system-1
L. labour-charges-for-11k v-system-1L. labour-charges-for-11k v-system-1
L. labour-charges-for-11k v-system-1
 
RR Nagar
RR NagarRR Nagar
RR Nagar
 
47093152 estimation
47093152 estimation47093152 estimation
47093152 estimation
 
58517990 estimating-resi-building
58517990 estimating-resi-building58517990 estimating-resi-building
58517990 estimating-resi-building
 
E-Tender_Aanganvadi SZ 29-10-15
E-Tender_Aanganvadi SZ 29-10-15E-Tender_Aanganvadi SZ 29-10-15
E-Tender_Aanganvadi SZ 29-10-15
 
GP Report
GP ReportGP Report
GP Report
 
Abstract.pdf
Abstract.pdfAbstract.pdf
Abstract.pdf
 
Itemized project budget
Itemized project budgetItemized project budget
Itemized project budget
 
second review.pptx
second review.pptxsecond review.pptx
second review.pptx
 

VRC COST ESTIMATE

  • 1. S.No. Description of work No's L(in ft.) B(in ft.) D(in ft.) Quantity unit rate cost 1 V.R.C.C. 1:2:4 using 20mm HBG metal and Fe 415 steel including all (a) Columns 12X18 6 1.00 1.5 8.50 76.50 15X15 1 1.25 1.25 8.50 13.28 18X15 1 1.50 1.25 8.50 15.94 105.72 Cft 200 21144 (b)Slab 1 24 33.75 0.33 267.30 Cft 200 53460 (C ) Roof beams 1 1.75 202.13 1 32 0.75 1.75 42.00 3 21 0.75 1.75 82.69 326.81 Cft 250 81703 (e) lintels/sunshades W5 2 5.00 1.5 0.25 3.75 w3 2 3 1.5 0.25 2.25 w2 2 2 1.5 0.25 1.50 v2 2 2 1.5 0.25 1.50 9.00 Cft 150 1350 (f) Lofts 1 17.50 2.00 0.25 8.75 1 7.50 2.00 0.25 3.75 12.50 Cft 150 1875 2 Supplying and fixing of teak wood frames & Teak wood shutters,hard ware fittings etc. MAIN DOORS 1 3.50 7.00 24.50 24.50 Sft 929 22770 2a Supplying and fixing of Sal wood frames & Block board shutters,hard ware fittings etc. D2.5 6 2.50 6.5 97.50 97.50 Sft 465 45307 3 Supplying and fixing of Sal wood windows with double glazed glass etc. W2 3 2.00 4.50 27.00 W3 2 3.00 4.50 27.00 W5 2 5.00 4.50 45.00 99.00 Sft 250 24750 4 Supplying and fixing of ventilators with frames hardware fittings etc. V2 2 2.00 2.00 8.00 107.00 Sft 250 26750 5 Superstructure in brick masonry using first class brick in C.M 1:4 for 6" thk. Walls including all 1 106 0.5 8.50 450.50 GIRLS HOSTEL FLOOR ESTIMATE 115.5 Page 1 of 3
  • 2. Deductions MD -1 3.5 0.5 7.00 -12.25 D2.5 -1 2.5 0.5 6.50 -8.13 W2 -3 2.00 0.5 4.50 -13.50 W3 -2 3.00 0.5 4.50 -13.50 W5 -2 5.00 0.5 4.50 -22.50 V2 -2 2.00 0.5 2.00 -4.00 Total 6" Brick masonary 376.63 Cft 156 58664 5A Superstructure in brick masonry using first class brick in C.M 1:4 for 4.5" thk. Walls including all 1 13.75 0.375 8.50 43.83 1 18.00 0.375 8.50 57.38 1 4.00 0.375 8.50 12.75 1 3.50 0.375 8.50 11.16 1 8.50 0.375 8.50 27.09 Deductions D2.5 -5 2.50 0.375 6.50 -30.47 Total 4.5" Brick masonary 121.73 Cft 119 14480 S.No. Description of work No's L(in ft.) B(in ft.) D(in ft.) Quantity unit 6 Internal plastering of 12mm thk. To the walls with sponge finishing C.M.1:6 including all Internal wall area 1 47.75 8.50 405.88 Deduction area D2.5 -5 2.50 6.50 -81.25 324.63 Sofits area 48.69 Net Plaster area 373.32 Sft 20 7466 7 External plastering 12mm thk.to the walls with sponge finishing C.M.1:6 including all EXternal wall area 1 106.00 8.50 901.00 Deduction area MD -1 3.50 7.00 -24.50 D2.5 -1 2.5 6.50 -16.25 W2 -3 2.00 4.50 -27.00 W3 -2 3.00 4.50 -27.00 W5 -2 5.00 4.50 -45.00 V2 -2 2.00 2.00 -8.00 753.25 Sofits area 112.99 Net Plaster area 866.24 Sft 26 22541 8 Plastering 12mm thk.to the Ceiling with sponge finishing C.M.1:6 including all 1 692.00 Sft 23 15916 9 Distemper for inside plastering including all 373.32 Sft 11 4163 Same as insideside plastering area Page 2 of 3
  • 3. 9a Distemper for ceiling plastering including all 692.00 Sft 7 4844 10 Weather Proof paint on external walls including all 866.24 Sft 30 25987 11 Flooring with 3/4" thick Marble stones in CM 1:6 and joint with white cement including all.(for all rooms) living 1 350.00 Multipurpose 1 112.00 Sick 1 75.00 537.00 Sft 250 134250 11a Flooring with antiskid tiles including all.(for all toilets &utilities) BATH 1 13.00 WC1 1 12.00 UTILITY 1 30.00 STORE 1 23.00 48.00 Sft 45 2160 12 Providing & dadoing in toilets using ceramic tiles BATH 1 14.75 6 88.50 WC1 1 14.50 6 87.00 UTILITY 1 15.00 5 75.00 Deductions -3 2.50 6 -45.00 Net Dadoing area 205.50 Sft 45 9248 13 Skirting with 3/4" thick Marble stones in CM 1:6 and joined with cement including all 1 87 0.5 43.50 1 42.5 0.5 21.25 1 38.5 0.5 19.25 staircase 20 3.125 0.5 31.25 115.25 Sft 30 3458 14 M.S railings balconies 1 16 4 64.00 staircase handrailing 1 20 3 60.00 124.00 Sft 209 25929 Girls Hostel Floor Total 608215 contingencies 15% 91232 Estimated Cost 699447 area 808 cost per square feet 866 Same as ceiling plastering area Same as outside plastering area Page 3 of 3