SlideShare a Scribd company logo
1 of 35
Download to read offline
Kinnickinnic River
      Flood Management and
     Watercourse Rehabilitation
Achieving Multiple Design Objectives

        Thomas R. Sear, PE, CFM
        Short Elliott Hendrickson
         Patrick C. Elliott, MMSD
Kinnickinnic River (KKR) Watershed

                        KKR S. 6th St. to
                          I-94 Bridge
                        Project Location
Updated Floodplain
  (SEWRPC, 2008)




                   6th St Bridge
KKR FM S. 6th St. to I-94 Bridge
        Project Area Characteristics
• South 6th Street Bridge
• Upstream Watercourse Segment
  –   500 feet of concrete lined channel
  –   Confined cross-Sections
  –   Steep northern embankment
  –   MMSD CSO Facility on south
• Downstream Watercourse Segment
  –   500 feet of earthen / rock lined channel
  –   Eroded north embankment, south of 5th Street
  –   Heavily vegetated north embankment
  –   South embankment instability
KKR FM Project Limits




                        South 5th Street
Bridge




                      Downstream WC Segment
South 6th Street




                            Kinnickinnic River
KKR FM Project Limits




                                    South 5th Street
                   Bridge
South 6th Street




                                             Downstream WC Segment




                                                       Kinnickinnic River
KKR 6th St. Bridge – Upstream (West Side)
KKR 6th St. Bridge – Downstream (East Side)
KKR Upstream Watercourse Segment
• Concrete Lined Channel
  – Constructed in 1983
  – 500 ft. length, 2:1 side slopes
  – 60 ft top width, 24 ft bottom width
• Northern Embankment
  – Buried (300 ft. long) WPA Wall
  – Railroad trestle remnants
  – Steep and unstable side slopes
• Southern Embankment
  – Maintenance Ramp
  – MMSD CSO facility and outfall
KKR Upstream Watercourse Segment

          Unstable
       Embankment                 End of
       with Sand and             Concrete
         Gravel Fill              Lined
          Material               Channel




                                                           MMSD KK1
                                            Combined
                                                            Facility
                                           Sewer Outfall


             Maintenance Ramp

                        South 6th Street
KKR Upstream Watercourse Segment

            Unstable
         Embankment
         with Sand and
           Gravel Fill
            Material




                                            MMSD CSO
                                           Control Facility
                            Combined
                           Sewer Outfall
             Maintenance
                Ramp
KKR Upstream Watercourse Segment
KKR Upstream Watercourse Segment
KKR Downstream of South 6th Street Bridge
             June 7, 1961
WPA Revetment Wall Buried in 1983
Existing KKR Concrete Lined Channel
          Constructed 1983
   WPA Wall
   Weep Hole           Buried WPA
                       Revetment
                          Wall




                                    84” Diameter
                                     RCP Storm
                                    Sewer Outfall




                Combined
               Sewer Outfall
Existing KKR Concrete Lined Channel and
   Buried WPA Revetment Wall, 1983

                                               Buried WPA
                                               Revetment
                                                  Wall

                                   WPA Wall
                                   Weep Hole



     18 feet   24 feet   18 feet




                                                            Approx. 15 ft
KKR Downstream Watercourse Segment
• Earthen / Rock Lined Channel
  –   500 ft. length
  –   Channel scour and deposition
  –   Embankment erosion
  –   Storm sewer outfalls
• Northern Embankment
  – Failing Gabion Structure
  – Embankment erosion south of 5th Street
  – Vegetated riparian areas
• Southern Embankment
  – Steep / unstable side slopes
  – Collapsing stone revetment walls
  – Exposed watercourse flushing pipeline
KKR Downstream Watercourse Segment
  End of Concrete
   Lined Channel               Eroded Side Slope due to
                                   5th Street Runoff

                                                       Failing Revetment Wall

                    KKR Earthen / Rock Lined Channel

 Storm Sewer                                              Storm Sewer
   Outfalls                                                  Outfall

                                                  Exposed Abandoned
                                                   Flushing Pipeline
                      Steep and
                     Unstable Side
                        Slopes
KKR Downstream Watercourse Segment


  Storm Sewer                   Eroded Side Slope due to
    Outfalls                        5th Street Runoff
                                                           Storm Sewer
                                                              Outfall

                       KKR Earthen / Rock Lined Channel




                                                   Failing Revetment Wall

                 Steep and
                Unstable Side               Exposed Abandoned
                   Slopes                    Flushing Pipeline
KKR Downstream Watercourse Segment
KKR Downstream Watercourse Segment
Stakeholder Involvement

• KK River Neighborhood Plan
  – Plan for overall KK River Flood Management
    Project
  – Coordination with local government agencies
    and community groups
  – Successfully accommodated various design
    requests from stakeholders
• Public Meetings
Proposed Improvements
         KKR S. 6th Street Bridge
• Design Objectives
  – Significantly reduce upstream WSE’s
  – Maintenance / bike path beneath bridge
• Proposed Design Features
  – Clear span concrete girder bridge
  – Functional, durable and attractive bridge
• Final Design Complete
  – Currently Under Construction
  – Scheduled for Completion in Dec. 2010
Proposed Bridge
11-02-10 Bridge Construction
Proposed Improvements
  KKR Upstream Watercourse Segment
• Design Objectives
  – Rehabilitated Main Channel
  – Maintain stable side slopes / hydraulic capacity
  – Maintenance / bike path alignment
• Design Features
  – Realigned channel centerline
  – Stone lined channel with riffles and pools
  – Tiered retaining walls, both sides
  – Recycle WPA wall limestone blocks
  – 15 ft. wide maintenance / bike path
Upstream KKR Improvements


                           Minimum 2:1
                           Side Slopes
               Retaining
                Walls




     Future KKR
      Bike Trail
Upstream KKR Cross-Sections
Proposed Improvements
KKR Downstream Watercourse Segment
• Design Goals
  – Rehabilitated main channel and floodplain
  – Stable embankment slopes
  – Native vegetation plantings
  – Promote watercourse sediment continuity
• Design Features
  – Stone lined channel with riffles and pools
  – 2:1 to 4:1 native vegetated side slopes
  – Reuse of limestone blocks / streambed stone
  – 15 ft. wide maintenance / bike path
Downstream KKR Improvements

Repair erosion          Five Pools within
 from 5th St.             Main Channel
    runoff




                                   3:1 Side Slope,
                                    where space
                                       allows
 Future KKR
  Bike Path
KKR Downstream Cross-Section




                     Typical Riffle Section
KKR Main Channel Cross-Sections




                      Typical Pool Section
KKR Watercourse Rehabilitation
       Improvements Schedule
• Advertisement – May 2010
• Construction Start – Oct. 2010
• Construction Completion – Dec. 2011
• Upstream Improvements
  – Finishing Preliminary Engineering
  – Starting Home Acquisition/Deconstruction
Kinnickinnic River Project Team
            Acknowledgements


• Dale Miller, Mainstream Restoration

• Rose Chmielewski, Ecological Services
 of Milwaukee

• Doug Bath, Gestra Engineering

More Related Content

What's hot

Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...
Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...
Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...Tonyamis
 
RCC OT Case Studies - JYoung RCC2015
RCC OT Case Studies - JYoung RCC2015RCC OT Case Studies - JYoung RCC2015
RCC OT Case Studies - JYoung RCC2015Jeremy Young, PE
 
Quay failure in barcelona harbour
Quay failure in barcelona harbourQuay failure in barcelona harbour
Quay failure in barcelona harbourFHRahman1
 
Bridge and culvert
Bridge and culvertBridge and culvert
Bridge and culvertfarazsugh
 
20150421031337318
2015042103133731820150421031337318
20150421031337318James Prs
 
Henn, Ray (LONG) w-o PhD 2014 (NEW)
Henn, Ray  (LONG) w-o PhD 2014 (NEW)Henn, Ray  (LONG) w-o PhD 2014 (NEW)
Henn, Ray (LONG) w-o PhD 2014 (NEW)Raymond Henn
 
Feb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress ReportFeb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress ReportHonolulu Civil Beat
 
1206765 634528654292080000
1206765 6345286542920800001206765 634528654292080000
1206765 634528654292080000Civil Engineers
 
May 2016 M37 RH Milner AS PUBLISHED
May 2016 M37 RH Milner AS PUBLISHEDMay 2016 M37 RH Milner AS PUBLISHED
May 2016 M37 RH Milner AS PUBLISHEDDean Bassett
 
Dismantling, Project, Supply, Pre-Fabrication and Construction of a 3000 m3 G...
Dismantling, Project, Supply, Pre-Fabrication and Construction of a 3000 m3 G...Dismantling, Project, Supply, Pre-Fabrication and Construction of a 3000 m3 G...
Dismantling, Project, Supply, Pre-Fabrication and Construction of a 3000 m3 G...RuiPLima
 
Water edge Structure
Water edge StructureWater edge Structure
Water edge StructureDms1999
 
Gabion information manufacturing & installation
Gabion information manufacturing  & installationGabion information manufacturing  & installation
Gabion information manufacturing & installationmanufabindia
 

What's hot (20)

Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...
Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...
Integrating Geothermal Loops into the Diaphragm walls of the Knightsbridge Pa...
 
RCC OT Case Studies - JYoung RCC2015
RCC OT Case Studies - JYoung RCC2015RCC OT Case Studies - JYoung RCC2015
RCC OT Case Studies - JYoung RCC2015
 
Quay failure in barcelona harbour
Quay failure in barcelona harbourQuay failure in barcelona harbour
Quay failure in barcelona harbour
 
Sabol Sess3 100909
Sabol Sess3 100909Sabol Sess3 100909
Sabol Sess3 100909
 
Bridge and culvert
Bridge and culvertBridge and culvert
Bridge and culvert
 
20150421031337318
2015042103133731820150421031337318
20150421031337318
 
Henn, Ray (LONG) w-o PhD 2014 (NEW)
Henn, Ray  (LONG) w-o PhD 2014 (NEW)Henn, Ray  (LONG) w-o PhD 2014 (NEW)
Henn, Ray (LONG) w-o PhD 2014 (NEW)
 
FOUNDATION
FOUNDATIONFOUNDATION
FOUNDATION
 
Lemay Shores
Lemay ShoresLemay Shores
Lemay Shores
 
Construction Job Story in GeoDrilling International
Construction Job Story in GeoDrilling InternationalConstruction Job Story in GeoDrilling International
Construction Job Story in GeoDrilling International
 
Piles a
Piles aPiles a
Piles a
 
Feb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress ReportFeb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress Report
 
1206765 634528654292080000
1206765 6345286542920800001206765 634528654292080000
1206765 634528654292080000
 
Canals
Canals Canals
Canals
 
May 2016 M37 RH Milner AS PUBLISHED
May 2016 M37 RH Milner AS PUBLISHEDMay 2016 M37 RH Milner AS PUBLISHED
May 2016 M37 RH Milner AS PUBLISHED
 
Dismantling, Project, Supply, Pre-Fabrication and Construction of a 3000 m3 G...
Dismantling, Project, Supply, Pre-Fabrication and Construction of a 3000 m3 G...Dismantling, Project, Supply, Pre-Fabrication and Construction of a 3000 m3 G...
Dismantling, Project, Supply, Pre-Fabrication and Construction of a 3000 m3 G...
 
Water edge Structure
Water edge StructureWater edge Structure
Water edge Structure
 
Dams in Pakistan
Dams in PakistanDams in Pakistan
Dams in Pakistan
 
Gabion information manufacturing & installation
Gabion information manufacturing  & installationGabion information manufacturing  & installation
Gabion information manufacturing & installation
 
Newport Marina Presentation March 2015
Newport Marina Presentation March 2015Newport Marina Presentation March 2015
Newport Marina Presentation March 2015
 

Viewers also liked

Rivers Report -- Summer 2012
Rivers Report -- Summer 2012Rivers Report -- Summer 2012
Rivers Report -- Summer 2012Sweet Water
 
Coutour & topography
Coutour & topographyCoutour & topography
Coutour & topographyJoyeeLee0131
 
Basic topographic mapping
Basic topographic mappingBasic topographic mapping
Basic topographic mappingBhok Millare
 
Highway engineering at high altitudes
Highway engineering at high altitudesHighway engineering at high altitudes
Highway engineering at high altitudesPrashant Shekhar
 
Orthorectification and triangulation
Orthorectification and triangulationOrthorectification and triangulation
Orthorectification and triangulationMesfin Yeshitla
 
Design and construction of highway (flexible pavement
Design and construction of highway (flexible pavementDesign and construction of highway (flexible pavement
Design and construction of highway (flexible pavementsuraj vishwakarma
 
TLE 9 (Technical Drafting) - Theory and Concepts of Site Development Plan
TLE 9 (Technical Drafting) - Theory and Concepts of Site Development PlanTLE 9 (Technical Drafting) - Theory and Concepts of Site Development Plan
TLE 9 (Technical Drafting) - Theory and Concepts of Site Development PlanJuan Miguel Palero
 
Site Planning and Design Principles - اساسيات تخطيط وتصميم المواقع
Site Planning and Design Principles - اساسيات تخطيط وتصميم المواقعSite Planning and Design Principles - اساسيات تخطيط وتصميم المواقع
Site Planning and Design Principles - اساسيات تخطيط وتصميم المواقعGalala University
 
Site planning kevin lynch
Site planning kevin lynchSite planning kevin lynch
Site planning kevin lynchXtian Escala
 
Site analysis-example
Site analysis-exampleSite analysis-example
Site analysis-exampleAnu PA
 
Photogrammetry - areaotriangulation
Photogrammetry - areaotriangulationPhotogrammetry - areaotriangulation
Photogrammetry - areaotriangulationjayan_sri
 

Viewers also liked (20)

Russel Site Plan Review
Russel Site Plan ReviewRussel Site Plan Review
Russel Site Plan Review
 
Rivers Report -- Summer 2012
Rivers Report -- Summer 2012Rivers Report -- Summer 2012
Rivers Report -- Summer 2012
 
Principles of dsign
Principles of dsignPrinciples of dsign
Principles of dsign
 
Climate pdf
Climate pdfClimate pdf
Climate pdf
 
Coutour & topography
Coutour & topographyCoutour & topography
Coutour & topography
 
Basic topographic mapping
Basic topographic mappingBasic topographic mapping
Basic topographic mapping
 
Highway engineering at high altitudes
Highway engineering at high altitudesHighway engineering at high altitudes
Highway engineering at high altitudes
 
Orthorectification and triangulation
Orthorectification and triangulationOrthorectification and triangulation
Orthorectification and triangulation
 
Design and construction of highway (flexible pavement
Design and construction of highway (flexible pavementDesign and construction of highway (flexible pavement
Design and construction of highway (flexible pavement
 
What is Topography
What is TopographyWhat is Topography
What is Topography
 
Geometric design
Geometric designGeometric design
Geometric design
 
TLE 9 (Technical Drafting) - Theory and Concepts of Site Development Plan
TLE 9 (Technical Drafting) - Theory and Concepts of Site Development PlanTLE 9 (Technical Drafting) - Theory and Concepts of Site Development Plan
TLE 9 (Technical Drafting) - Theory and Concepts of Site Development Plan
 
Site Planning
Site PlanningSite Planning
Site Planning
 
Site Planning and Design Principles - اساسيات تخطيط وتصميم المواقع
Site Planning and Design Principles - اساسيات تخطيط وتصميم المواقعSite Planning and Design Principles - اساسيات تخطيط وتصميم المواقع
Site Planning and Design Principles - اساسيات تخطيط وتصميم المواقع
 
Site planning
Site planningSite planning
Site planning
 
Site planning
Site planningSite planning
Site planning
 
Site planning kevin lynch
Site planning kevin lynchSite planning kevin lynch
Site planning kevin lynch
 
Site analysis-example
Site analysis-exampleSite analysis-example
Site analysis-example
 
Plan, section, elevation revised
Plan, section, elevation revisedPlan, section, elevation revised
Plan, section, elevation revised
 
Photogrammetry - areaotriangulation
Photogrammetry - areaotriangulationPhotogrammetry - areaotriangulation
Photogrammetry - areaotriangulation
 

Similar to Kinnickinnic River Flood Management and Watercourse Rehabilitation

Clean Rivers, Clean Lake 8 -- New Projects on KK and Menomonee Rivers -- Dave...
Clean Rivers, Clean Lake 8 -- New Projects on KK and Menomonee Rivers -- Dave...Clean Rivers, Clean Lake 8 -- New Projects on KK and Menomonee Rivers -- Dave...
Clean Rivers, Clean Lake 8 -- New Projects on KK and Menomonee Rivers -- Dave...Sweet Water
 
Failures of an earthen dam
Failures of an earthen damFailures of an earthen dam
Failures of an earthen damDivya Vishnoi
 
Schoharie Creek Bridge Collapse - Case Study
Schoharie Creek Bridge Collapse - Case StudySchoharie Creek Bridge Collapse - Case Study
Schoharie Creek Bridge Collapse - Case StudyThings Simplified
 
Presentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canalPresentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canalIEI GSC
 
Dam construction
Dam constructionDam construction
Dam constructionalizay41
 
hydraulic structures in civil engineering
hydraulic structures in civil engineeringhydraulic structures in civil engineering
hydraulic structures in civil engineeringBittuRajkumar
 
Bridgeprojectsource online-120723110339-phpapp02
Bridgeprojectsource online-120723110339-phpapp02Bridgeprojectsource online-120723110339-phpapp02
Bridgeprojectsource online-120723110339-phpapp02Ferit Fazliu
 
design of gravity dam
design of gravity damdesign of gravity dam
design of gravity damRisso Johnny
 
Robert W. Fairbanks and Richard N. St. Jean, Coastal Shoreline Protection Usi...
Robert W. Fairbanks and Richard N. St. Jean, Coastal Shoreline Protection Usi...Robert W. Fairbanks and Richard N. St. Jean, Coastal Shoreline Protection Usi...
Robert W. Fairbanks and Richard N. St. Jean, Coastal Shoreline Protection Usi...riseagrant
 
Bridge-Plate & Multi-Plate Applications and Case Studies (Ron Prychitko, P.Eng.)
Bridge-Plate & Multi-Plate Applications and Case Studies (Ron Prychitko, P.Eng.)Bridge-Plate & Multi-Plate Applications and Case Studies (Ron Prychitko, P.Eng.)
Bridge-Plate & Multi-Plate Applications and Case Studies (Ron Prychitko, P.Eng.)Communications Branding
 
Flood resilient presentation 05.16.12
Flood resilient presentation 05.16.12Flood resilient presentation 05.16.12
Flood resilient presentation 05.16.12Christopher Hayes
 

Similar to Kinnickinnic River Flood Management and Watercourse Rehabilitation (20)

Clean Rivers, Clean Lake 8 -- New Projects on KK and Menomonee Rivers -- Dave...
Clean Rivers, Clean Lake 8 -- New Projects on KK and Menomonee Rivers -- Dave...Clean Rivers, Clean Lake 8 -- New Projects on KK and Menomonee Rivers -- Dave...
Clean Rivers, Clean Lake 8 -- New Projects on KK and Menomonee Rivers -- Dave...
 
Failures of an earthen dam
Failures of an earthen damFailures of an earthen dam
Failures of an earthen dam
 
Schoharie Creek Bridge Collapse - Case Study
Schoharie Creek Bridge Collapse - Case StudySchoharie Creek Bridge Collapse - Case Study
Schoharie Creek Bridge Collapse - Case Study
 
Presentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canalPresentation application-of-geosynthetics-in-canal
Presentation application-of-geosynthetics-in-canal
 
Eearthen channel design
Eearthen channel designEearthen channel design
Eearthen channel design
 
Dams.ppt
Dams.pptDams.ppt
Dams.ppt
 
Water Management
Water ManagementWater Management
Water Management
 
ASCEMLSTPRESENTATION 05-06-03.PPT
ASCEMLSTPRESENTATION 05-06-03.PPTASCEMLSTPRESENTATION 05-06-03.PPT
ASCEMLSTPRESENTATION 05-06-03.PPT
 
Dam construction
Dam constructionDam construction
Dam construction
 
hydraulic structures in civil engineering
hydraulic structures in civil engineeringhydraulic structures in civil engineering
hydraulic structures in civil engineering
 
Bridge project
Bridge projectBridge project
Bridge project
 
Bridgeprojectsource online-120723110339-phpapp02
Bridgeprojectsource online-120723110339-phpapp02Bridgeprojectsource online-120723110339-phpapp02
Bridgeprojectsource online-120723110339-phpapp02
 
Bridge project
Bridge projectBridge project
Bridge project
 
design of gravity dam
design of gravity damdesign of gravity dam
design of gravity dam
 
Robert W. Fairbanks and Richard N. St. Jean, Coastal Shoreline Protection Usi...
Robert W. Fairbanks and Richard N. St. Jean, Coastal Shoreline Protection Usi...Robert W. Fairbanks and Richard N. St. Jean, Coastal Shoreline Protection Usi...
Robert W. Fairbanks and Richard N. St. Jean, Coastal Shoreline Protection Usi...
 
12. Canal Head Regulation.1.pdf
12. Canal Head Regulation.1.pdf12. Canal Head Regulation.1.pdf
12. Canal Head Regulation.1.pdf
 
Damconstruction 1
Damconstruction 1Damconstruction 1
Damconstruction 1
 
Cross drainage work
Cross drainage workCross drainage work
Cross drainage work
 
Bridge-Plate & Multi-Plate Applications and Case Studies (Ron Prychitko, P.Eng.)
Bridge-Plate & Multi-Plate Applications and Case Studies (Ron Prychitko, P.Eng.)Bridge-Plate & Multi-Plate Applications and Case Studies (Ron Prychitko, P.Eng.)
Bridge-Plate & Multi-Plate Applications and Case Studies (Ron Prychitko, P.Eng.)
 
Flood resilient presentation 05.16.12
Flood resilient presentation 05.16.12Flood resilient presentation 05.16.12
Flood resilient presentation 05.16.12
 

More from Matthew Hahm

Kerry Centre - Beloit, WI
Kerry Centre - Beloit, WIKerry Centre - Beloit, WI
Kerry Centre - Beloit, WIMatthew Hahm
 
Urban Water Quality Management
Urban Water Quality ManagementUrban Water Quality Management
Urban Water Quality ManagementMatthew Hahm
 
Retention Basins: Canada Geese Factories and Shelters
Retention Basins: Canada Geese Factories and SheltersRetention Basins: Canada Geese Factories and Shelters
Retention Basins: Canada Geese Factories and SheltersMatthew Hahm
 
Water Quality BMPs Near Airports
Water Quality BMPs Near AirportsWater Quality BMPs Near Airports
Water Quality BMPs Near AirportsMatthew Hahm
 
Spring Green 2008 Flooding and Flood Control Options
Spring Green 2008 Flooding and Flood Control OptionsSpring Green 2008 Flooding and Flood Control Options
Spring Green 2008 Flooding and Flood Control OptionsMatthew Hahm
 
Moving a Town: The Story of Gays Mills
Moving a Town: The Story of Gays MillsMoving a Town: The Story of Gays Mills
Moving a Town: The Story of Gays MillsMatthew Hahm
 
Linking Great Lakes Beach Water Quality to Land Use
Linking Great Lakes Beach Water Quality to Land UseLinking Great Lakes Beach Water Quality to Land Use
Linking Great Lakes Beach Water Quality to Land UseMatthew Hahm
 
Stormwater regulations and their relationship to tmd ls
Stormwater regulations and their relationship to tmd lsStormwater regulations and their relationship to tmd ls
Stormwater regulations and their relationship to tmd lsMatthew Hahm
 

More from Matthew Hahm (8)

Kerry Centre - Beloit, WI
Kerry Centre - Beloit, WIKerry Centre - Beloit, WI
Kerry Centre - Beloit, WI
 
Urban Water Quality Management
Urban Water Quality ManagementUrban Water Quality Management
Urban Water Quality Management
 
Retention Basins: Canada Geese Factories and Shelters
Retention Basins: Canada Geese Factories and SheltersRetention Basins: Canada Geese Factories and Shelters
Retention Basins: Canada Geese Factories and Shelters
 
Water Quality BMPs Near Airports
Water Quality BMPs Near AirportsWater Quality BMPs Near Airports
Water Quality BMPs Near Airports
 
Spring Green 2008 Flooding and Flood Control Options
Spring Green 2008 Flooding and Flood Control OptionsSpring Green 2008 Flooding and Flood Control Options
Spring Green 2008 Flooding and Flood Control Options
 
Moving a Town: The Story of Gays Mills
Moving a Town: The Story of Gays MillsMoving a Town: The Story of Gays Mills
Moving a Town: The Story of Gays Mills
 
Linking Great Lakes Beach Water Quality to Land Use
Linking Great Lakes Beach Water Quality to Land UseLinking Great Lakes Beach Water Quality to Land Use
Linking Great Lakes Beach Water Quality to Land Use
 
Stormwater regulations and their relationship to tmd ls
Stormwater regulations and their relationship to tmd lsStormwater regulations and their relationship to tmd ls
Stormwater regulations and their relationship to tmd ls
 

Kinnickinnic River Flood Management and Watercourse Rehabilitation

  • 1. Kinnickinnic River Flood Management and Watercourse Rehabilitation Achieving Multiple Design Objectives Thomas R. Sear, PE, CFM Short Elliott Hendrickson Patrick C. Elliott, MMSD
  • 2. Kinnickinnic River (KKR) Watershed KKR S. 6th St. to I-94 Bridge Project Location
  • 3. Updated Floodplain (SEWRPC, 2008) 6th St Bridge
  • 4. KKR FM S. 6th St. to I-94 Bridge Project Area Characteristics • South 6th Street Bridge • Upstream Watercourse Segment – 500 feet of concrete lined channel – Confined cross-Sections – Steep northern embankment – MMSD CSO Facility on south • Downstream Watercourse Segment – 500 feet of earthen / rock lined channel – Eroded north embankment, south of 5th Street – Heavily vegetated north embankment – South embankment instability
  • 5. KKR FM Project Limits South 5th Street Bridge Downstream WC Segment South 6th Street Kinnickinnic River
  • 6. KKR FM Project Limits South 5th Street Bridge South 6th Street Downstream WC Segment Kinnickinnic River
  • 7. KKR 6th St. Bridge – Upstream (West Side)
  • 8. KKR 6th St. Bridge – Downstream (East Side)
  • 9. KKR Upstream Watercourse Segment • Concrete Lined Channel – Constructed in 1983 – 500 ft. length, 2:1 side slopes – 60 ft top width, 24 ft bottom width • Northern Embankment – Buried (300 ft. long) WPA Wall – Railroad trestle remnants – Steep and unstable side slopes • Southern Embankment – Maintenance Ramp – MMSD CSO facility and outfall
  • 10. KKR Upstream Watercourse Segment Unstable Embankment End of with Sand and Concrete Gravel Fill Lined Material Channel MMSD KK1 Combined Facility Sewer Outfall Maintenance Ramp South 6th Street
  • 11. KKR Upstream Watercourse Segment Unstable Embankment with Sand and Gravel Fill Material MMSD CSO Control Facility Combined Sewer Outfall Maintenance Ramp
  • 14. KKR Downstream of South 6th Street Bridge June 7, 1961
  • 15. WPA Revetment Wall Buried in 1983
  • 16. Existing KKR Concrete Lined Channel Constructed 1983 WPA Wall Weep Hole Buried WPA Revetment Wall 84” Diameter RCP Storm Sewer Outfall Combined Sewer Outfall
  • 17. Existing KKR Concrete Lined Channel and Buried WPA Revetment Wall, 1983 Buried WPA Revetment Wall WPA Wall Weep Hole 18 feet 24 feet 18 feet Approx. 15 ft
  • 18. KKR Downstream Watercourse Segment • Earthen / Rock Lined Channel – 500 ft. length – Channel scour and deposition – Embankment erosion – Storm sewer outfalls • Northern Embankment – Failing Gabion Structure – Embankment erosion south of 5th Street – Vegetated riparian areas • Southern Embankment – Steep / unstable side slopes – Collapsing stone revetment walls – Exposed watercourse flushing pipeline
  • 19. KKR Downstream Watercourse Segment End of Concrete Lined Channel Eroded Side Slope due to 5th Street Runoff Failing Revetment Wall KKR Earthen / Rock Lined Channel Storm Sewer Storm Sewer Outfalls Outfall Exposed Abandoned Flushing Pipeline Steep and Unstable Side Slopes
  • 20. KKR Downstream Watercourse Segment Storm Sewer Eroded Side Slope due to Outfalls 5th Street Runoff Storm Sewer Outfall KKR Earthen / Rock Lined Channel Failing Revetment Wall Steep and Unstable Side Exposed Abandoned Slopes Flushing Pipeline
  • 23. Stakeholder Involvement • KK River Neighborhood Plan – Plan for overall KK River Flood Management Project – Coordination with local government agencies and community groups – Successfully accommodated various design requests from stakeholders • Public Meetings
  • 24. Proposed Improvements KKR S. 6th Street Bridge • Design Objectives – Significantly reduce upstream WSE’s – Maintenance / bike path beneath bridge • Proposed Design Features – Clear span concrete girder bridge – Functional, durable and attractive bridge • Final Design Complete – Currently Under Construction – Scheduled for Completion in Dec. 2010
  • 27. Proposed Improvements KKR Upstream Watercourse Segment • Design Objectives – Rehabilitated Main Channel – Maintain stable side slopes / hydraulic capacity – Maintenance / bike path alignment • Design Features – Realigned channel centerline – Stone lined channel with riffles and pools – Tiered retaining walls, both sides – Recycle WPA wall limestone blocks – 15 ft. wide maintenance / bike path
  • 28. Upstream KKR Improvements Minimum 2:1 Side Slopes Retaining Walls Future KKR Bike Trail
  • 30. Proposed Improvements KKR Downstream Watercourse Segment • Design Goals – Rehabilitated main channel and floodplain – Stable embankment slopes – Native vegetation plantings – Promote watercourse sediment continuity • Design Features – Stone lined channel with riffles and pools – 2:1 to 4:1 native vegetated side slopes – Reuse of limestone blocks / streambed stone – 15 ft. wide maintenance / bike path
  • 31. Downstream KKR Improvements Repair erosion Five Pools within from 5th St. Main Channel runoff 3:1 Side Slope, where space allows Future KKR Bike Path
  • 32. KKR Downstream Cross-Section Typical Riffle Section
  • 33. KKR Main Channel Cross-Sections Typical Pool Section
  • 34. KKR Watercourse Rehabilitation Improvements Schedule • Advertisement – May 2010 • Construction Start – Oct. 2010 • Construction Completion – Dec. 2011 • Upstream Improvements – Finishing Preliminary Engineering – Starting Home Acquisition/Deconstruction
  • 35. Kinnickinnic River Project Team Acknowledgements • Dale Miller, Mainstream Restoration • Rose Chmielewski, Ecological Services of Milwaukee • Doug Bath, Gestra Engineering