SlideShare a Scribd company logo
1 of 45
Download to read offline
Enabling works at the Olympic Park:
Effectively delivering the preparation of
the construction site for the London 2012
games
Dr Jan Hellings
Dr Jan Hellings & Associates Ltd
Formerly Project Sponsor Olympic Delivery Authority
London

October 1st 2013
SUMMARY OF PRESENTATION

•
•
•
•
•
•
•
•
•

Taking possession of the Olympic Park site
Site investigation
Ground/water considerations
Clean-up (Remediation) process
Typical contaminants
Treatment options
Materials movement & management
Photos
Lessons learned

2
Olympic Delivery Authority
LOCATION OF 2012 OLYMPIC VENUES

3
Olympic Delivery Authority
OLYMPIC PARK SITE - BEFORE

4
Olympic Delivery Authority
TAKING POSSESSION OF THE OLYMPIC PARK SITE
• The assembly of a 250 hectare site is one of largest
Compulsory Purchase Orders to have taken place in the UK.
• 2,200 land ownerships to acquire
• Approximately 200 businesses relocated

• 98% of the 4,750 jobs secured
• Over 140,000 square metres of development space,
including three new LDA business parks constructed in
areas adjacent to the Park

5
Olympic Delivery Authority
PLANNING PERMISSIONS

6
Olympic Delivery Authority
SITE PLAN

7
Olympic Delivery Authority
Site Investigation Statistics

No. of Intrusions

Total metres sampled
and tested

Geotech and contam
boreholes

880

30,800

Contam specific
boreholes

390

5,850

Window samples
(contam specific)

930

5,580

Trial pits (geotech
and contam)

600

2,400

2,800

44,630

TOTALS

8
Olympic Delivery Authority
Plan of Olympic Park
Site Investigation

9
Olympic Delivery Authority
Site Preparation Life Cycle
Global Remediation Strategy
Approvals

Site Specific Remediation Strategy

Vacant
Possession
Site Investigation
River Walls
Utility inputs
Invasive Species
Construction Roads and
Bridges (abutments)

Demolition

Remediation Method Statements (RMS)
Target
= 95%
re-use

Remediation
Bulk Earthworks

Mechanical Separation
Soil Washing
10
Olympic Delivery Authority

Bioremediation
Stabilisation

Target
= 85%
re-use

Handover to
Venue Contractor
Conceptual Site Model – Risk Driven Remediation

11
Olympic Delivery Authority
12
Olympic Delivery Authority
Treatment Methods

Soil Washing North Plant (100 tph) CZ 5b;
looking east the fine sands hydraulic separation
and output conveyor in foreground

Soil Washing Sout); looking at sludge
(fines at 15 tph *2) dewatering filter press

13
Olympic Delivery Authority

Soil Washing North Plant (100 tph) CZ 5b;
looking north to fines separation and beyond to
Coarse fraction washing.

Soil Washing South (75 tph *3); looking north
towards the two soil washing plants in cZ4.
Note washed gravel output in left foreground
Treatment Methods

Mobile Soil Stabilisation Plant set up for
Treatment Trials (45t/hr) prior to Main
Equipment being Mobilised

Bioremediation Pile Cells Aeration, Leachate and irrigation
pipe systems being established beneath bio-piles

14
Olympic Delivery Authority

Aerial view of site prior to start of projectfiled prior to
Bioremediation Pile Cells being

Soil Stabilisation Plant in South
Treatment Centre (60t/hr)

Aeration, Leachate and irrigation systems being
established, pipe work still to be connected
Treatment Methods

Complex Screening Plant setup in North
of the Park

In-situ Soil Mixer utilising Cement and/or lime to
allow geotechnical soil parameter improvement

15
Olympic Delivery Authority

Unsorted Landfill Materials at Complex
Screening Plant
Treatment Centre Locations

• Two treatment centres
established – one in the north
and one in the south
• Each treatment centre has
several treatment processes
available
• Flexibility of approach and
competition between treatment
methods is encouraged
• Five soil washing plants at
site.
• Soil stabilisation
• Bioremediation cell pads
constructed
16
Olympic Delivery Authority
• Materials Total approximately (2.5 Million m3)
• Demolition (500,000m3)
• Excavated Soil
(1.8 Million m3 cut of which 820,000m3 treated )
• Tunnelling soil (approximately 200,000m3)

17

• Beneficial and optimal reuse strategies
• General fill (approximately 50% untreated)
• Separation layer (approximately 50%)
•Base coarse and sub-base
•Selected engineering fill

Olympic Delivery Authority
Materials Balance – Enabling Works

Washed
Gravels

Sludge

18
Olympic Delivery Authority

Washed
Sands

Waste
Demolition of Tower
Blocks on CZ6b, Clays
Lane

19
Olympic Delivery Authority
Demolition of warehouse/office building

20
Olympic Delivery Authority
Oblique photo looking North

21
Olympic Delivery Authority
STADIUM SITE MID 2007

22
Olympic Delivery Authority
OLYMPIC PARK LOOKING NORTH – JULY 2008

23
Olympic Delivery Authority
OLYMPIC PARK LOOKING NORTH – AUGUST 2008

24
Olympic Delivery Authority
OLYMPIC PARK LOOKING NORTH – NOVEMBER 2008

25
Olympic Delivery Authority
OLYMPIC PARK LOOKING NORTH – MID 2009

26
Olympic Delivery Authority
PARK VIEW LOOKING SOUTH – MID 2008

27
Olympic Delivery Authority
PARK VIEW LOOKING SOUTH – November 2008

28
Olympic Delivery Authority
PARK VIEW LOOKING SOUTH – MID 2009

29
Olympic Delivery Authority
AQUATICS SITE – MID 2008

30
Olympic Delivery Authority
AQUATICS SITE – MID 2009

31
Olympic Delivery Authority
AQUATICS ROOF – NOV 2009

32
Olympic Delivery Authority
LOOKING SOUTH – DEC 2011

33
Olympic Delivery Authority
PARK – GAMES MODE

34
Olympic Delivery Authority
AQUATICS COMPLEX

35
Olympic Delivery Authority
VILLAGE - LEGACY

36
Olympic Delivery Authority
MAIN STADIUM

37
Olympic Delivery Authority
THE QUEEN LEAVES BUCKINGHAM PALACE WITH
JAMES BOND FOR THE OPENING CEREMONY

38
Olympic Delivery Authority
THE QUEEN PARACHUTES INTO THE STADUIM –
OPENING CEREMONY

39
Olympic Delivery Authority
OPENING CEREMONY
41
Olympic Delivery Authority
THE LEGACY FRAMEWORK FOR THE PARK

•
•
•
•

•
•

42
Olympic Delivery Authority

110 ha open space
Development platforms
comprising > circa 950,000 sqm
development
4,000 new housing units within
the village (> 9,000 overall)
Major investments in waterways,
rims, park edges
Venues transformed for legacy
Provides strong basis for further
development
43
Olympic Delivery Authority
CLOSURE

The 2012 London Olympic and Paralympic Games
were a great success. We engineers can do the
‘impossible’!

Muito obrigado
jan@janhellings.com
44
Olympic Delivery Authority
Dia 1:Ativando obras no parque olímpico,Jan Hellings, Jan Hellings & Associates Ltd_UK

More Related Content

What's hot

Wastewater Master Plan Update -- Northgate
Wastewater Master Plan Update -- NorthgateWastewater Master Plan Update -- Northgate
Wastewater Master Plan Update -- Northgate
City of College Station
 
Piotr Blaut Student Placement
Piotr Blaut Student PlacementPiotr Blaut Student Placement
Piotr Blaut Student Placement
Piotr Blaut
 
Session 3 - Michael Berna Indiana Logistics Summit 2012
Session 3 - Michael Berna Indiana Logistics Summit 2012Session 3 - Michael Berna Indiana Logistics Summit 2012
Session 3 - Michael Berna Indiana Logistics Summit 2012
Fred Davidson
 
2015.10.29--PENC_Presentation_XPSWMM
2015.10.29--PENC_Presentation_XPSWMM2015.10.29--PENC_Presentation_XPSWMM
2015.10.29--PENC_Presentation_XPSWMM
Danee McGee
 
IFS General Presentation 120315
IFS General Presentation 120315IFS General Presentation 120315
IFS General Presentation 120315
Bill Marsh
 
Final Climate Change and Hydraulic Fracturing Proppants
Final Climate Change and  Hydraulic Fracturing ProppantsFinal Climate Change and  Hydraulic Fracturing Proppants
Final Climate Change and Hydraulic Fracturing Proppants
Natalia Nelson
 
ALLENERGY2015_6515
ALLENERGY2015_6515ALLENERGY2015_6515
ALLENERGY2015_6515
Peter Bruce
 

What's hot (20)

Centrigugal pump by GAURAV DHADSE
Centrigugal pump by GAURAV DHADSECentrigugal pump by GAURAV DHADSE
Centrigugal pump by GAURAV DHADSE
 
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
 
Latest technology trends by Prof. Chen
Latest technology trends by Prof. ChenLatest technology trends by Prof. Chen
Latest technology trends by Prof. Chen
 
Fy 19 PPT Public Works and Utilities
Fy 19 PPT Public Works and UtilitiesFy 19 PPT Public Works and Utilities
Fy 19 PPT Public Works and Utilities
 
Wastewater Master Plan Update -- Northgate
Wastewater Master Plan Update -- NorthgateWastewater Master Plan Update -- Northgate
Wastewater Master Plan Update -- Northgate
 
IRJET- Analysis of Reserve Estimation using Volumetric Method on Taq Taq Oil ...
IRJET- Analysis of Reserve Estimation using Volumetric Method on Taq Taq Oil ...IRJET- Analysis of Reserve Estimation using Volumetric Method on Taq Taq Oil ...
IRJET- Analysis of Reserve Estimation using Volumetric Method on Taq Taq Oil ...
 
Piotr Blaut Student Placement
Piotr Blaut Student PlacementPiotr Blaut Student Placement
Piotr Blaut Student Placement
 
Mp surface water
Mp surface waterMp surface water
Mp surface water
 
Cec application form_a
Cec application form_aCec application form_a
Cec application form_a
 
asphalt Pavement rehabilitation through recycling
asphalt Pavement rehabilitation through recyclingasphalt Pavement rehabilitation through recycling
asphalt Pavement rehabilitation through recycling
 
Session 3 - Michael Berna Indiana Logistics Summit 2012
Session 3 - Michael Berna Indiana Logistics Summit 2012Session 3 - Michael Berna Indiana Logistics Summit 2012
Session 3 - Michael Berna Indiana Logistics Summit 2012
 
Mayekawa - Safe use of NH3 in China's cold chain industry
Mayekawa - Safe use of NH3 in China's cold chain industryMayekawa - Safe use of NH3 in China's cold chain industry
Mayekawa - Safe use of NH3 in China's cold chain industry
 
2015.10.29--PENC_Presentation_XPSWMM
2015.10.29--PENC_Presentation_XPSWMM2015.10.29--PENC_Presentation_XPSWMM
2015.10.29--PENC_Presentation_XPSWMM
 
Sgcp14beckmanncp
Sgcp14beckmanncpSgcp14beckmanncp
Sgcp14beckmanncp
 
Two-Lift Paving
Two-Lift PavingTwo-Lift Paving
Two-Lift Paving
 
Cold-in-Place Recycling (CIR) use in Urban Areas
Cold-in-Place Recycling (CIR) use in Urban AreasCold-in-Place Recycling (CIR) use in Urban Areas
Cold-in-Place Recycling (CIR) use in Urban Areas
 
COP19: A Year of Progress
COP19: A Year of ProgressCOP19: A Year of Progress
COP19: A Year of Progress
 
IFS General Presentation 120315
IFS General Presentation 120315IFS General Presentation 120315
IFS General Presentation 120315
 
Final Climate Change and Hydraulic Fracturing Proppants
Final Climate Change and  Hydraulic Fracturing ProppantsFinal Climate Change and  Hydraulic Fracturing Proppants
Final Climate Change and Hydraulic Fracturing Proppants
 
ALLENERGY2015_6515
ALLENERGY2015_6515ALLENERGY2015_6515
ALLENERGY2015_6515
 

Viewers also liked

Lydia rama evaluation.ashx
Lydia rama evaluation.ashxLydia rama evaluation.ashx
Lydia rama evaluation.ashx
LydiaRama
 
Lydia Rama - Textual Analysis
Lydia Rama - Textual AnalysisLydia Rama - Textual Analysis
Lydia Rama - Textual Analysis
LydiaRama
 
Storyboard group 3-Eleanor, Lydia, Shannon, Thamina
Storyboard group 3-Eleanor, Lydia, Shannon, Thamina Storyboard group 3-Eleanor, Lydia, Shannon, Thamina
Storyboard group 3-Eleanor, Lydia, Shannon, Thamina
LydiaRama
 
PDXPortland - Dockerize Django
PDXPortland - Dockerize DjangoPDXPortland - Dockerize Django
PDXPortland - Dockerize Django
Hannes Hapke
 

Viewers also liked (15)

Παιδικά Ρούχα - Mandarino collection fall winter 13-14
Παιδικά Ρούχα - Mandarino collection fall winter 13-14Παιδικά Ρούχα - Mandarino collection fall winter 13-14
Παιδικά Ρούχα - Mandarino collection fall winter 13-14
 
hmm
hmmhmm
hmm
 
Dia 1: Olímpiadas de Londres 2012, Mervyn Jones, WRAP_UK
Dia 1: Olímpiadas de Londres 2012, Mervyn Jones, WRAP_UKDia 1: Olímpiadas de Londres 2012, Mervyn Jones, WRAP_UK
Dia 1: Olímpiadas de Londres 2012, Mervyn Jones, WRAP_UK
 
Lydia rama evaluation.ashx
Lydia rama evaluation.ashxLydia rama evaluation.ashx
Lydia rama evaluation.ashx
 
Milk experiment
Milk experimentMilk experiment
Milk experiment
 
Dia 2: Resíduos: abraçando a mudança, Iain Welsh,JCB
Dia 2: Resíduos: abraçando a mudança, Iain Welsh,JCBDia 2: Resíduos: abraçando a mudança, Iain Welsh,JCB
Dia 2: Resíduos: abraçando a mudança, Iain Welsh,JCB
 
Lydia Rama - Textual Analysis
Lydia Rama - Textual AnalysisLydia Rama - Textual Analysis
Lydia Rama - Textual Analysis
 
სვეტოვანი დიაგრამა
სვეტოვანი  დიაგრამასვეტოვანი  დიაგრამა
სვეტოვანი დიაგრამა
 
Dia 2: A extensão e o compartilhamento de responsbilidade: o papel do setor n...
Dia 2: A extensão e o compartilhamento de responsbilidade: o papel do setor n...Dia 2: A extensão e o compartilhamento de responsbilidade: o papel do setor n...
Dia 2: A extensão e o compartilhamento de responsbilidade: o papel do setor n...
 
Nononononono
NonononononoNononononono
Nononononono
 
Dia 2: Passos para implementar um sistema avançado de gestão integrada de res...
Dia 2: Passos para implementar um sistema avançado de gestão integrada de res...Dia 2: Passos para implementar um sistema avançado de gestão integrada de res...
Dia 2: Passos para implementar um sistema avançado de gestão integrada de res...
 
Storyboard group 3-Eleanor, Lydia, Shannon, Thamina
Storyboard group 3-Eleanor, Lydia, Shannon, Thamina Storyboard group 3-Eleanor, Lydia, Shannon, Thamina
Storyboard group 3-Eleanor, Lydia, Shannon, Thamina
 
Παιδικά Ρούχα - Sprint collection fall winter 13-14
Παιδικά Ρούχα - Sprint collection fall winter 13-14Παιδικά Ρούχα - Sprint collection fall winter 13-14
Παιδικά Ρούχα - Sprint collection fall winter 13-14
 
Παιδικά Ρούχα - Marasil collection fall winter 13-14
Παιδικά Ρούχα - Marasil collection fall winter 13-14Παιδικά Ρούχα - Marasil collection fall winter 13-14
Παιδικά Ρούχα - Marasil collection fall winter 13-14
 
PDXPortland - Dockerize Django
PDXPortland - Dockerize DjangoPDXPortland - Dockerize Django
PDXPortland - Dockerize Django
 

Similar to Dia 1:Ativando obras no parque olímpico,Jan Hellings, Jan Hellings & Associates Ltd_UK

Basic drilling for we adp 2014 k edit3
Basic drilling for we adp 2014 k edit3Basic drilling for we adp 2014 k edit3
Basic drilling for we adp 2014 k edit3
pakmek
 
LMPP Final Presentation_FINAL1
LMPP Final Presentation_FINAL1LMPP Final Presentation_FINAL1
LMPP Final Presentation_FINAL1
Theodore McNeal
 
Harrison_Simbol_Presentation Peer Review 2012
Harrison_Simbol_Presentation Peer Review 2012Harrison_Simbol_Presentation Peer Review 2012
Harrison_Simbol_Presentation Peer Review 2012
Stephen Harrison
 
19-07-06 Scheme Description details
19-07-06 Scheme Description details19-07-06 Scheme Description details
19-07-06 Scheme Description details
Aonghus Murray
 

Similar to Dia 1:Ativando obras no parque olímpico,Jan Hellings, Jan Hellings & Associates Ltd_UK (20)

Navy Presentation on Site 27 to Moffett RAB July 17, 2008
Navy Presentation on Site 27 to Moffett RAB July 17, 2008Navy Presentation on Site 27 to Moffett RAB July 17, 2008
Navy Presentation on Site 27 to Moffett RAB July 17, 2008
 
Larnaca Port - Energy port
Larnaca Port - Energy portLarnaca Port - Energy port
Larnaca Port - Energy port
 
Soil management at metrolinx
Soil management at metrolinx Soil management at metrolinx
Soil management at metrolinx
 
Stormwater Monitoring - Newington Solid Waste Facility
Stormwater Monitoring - Newington Solid Waste FacilityStormwater Monitoring - Newington Solid Waste Facility
Stormwater Monitoring - Newington Solid Waste Facility
 
Basic drilling for we adp 2014 k edit3
Basic drilling for we adp 2014 k edit3Basic drilling for we adp 2014 k edit3
Basic drilling for we adp 2014 k edit3
 
Premier Oil - Decommissioning Oil Projects In The North Sea Case Study
Premier Oil - Decommissioning Oil Projects In The North Sea Case StudyPremier Oil - Decommissioning Oil Projects In The North Sea Case Study
Premier Oil - Decommissioning Oil Projects In The North Sea Case Study
 
Long Branch & New Alexandria Pump Station Fuel Tank Replacement
Long Branch & New Alexandria Pump Station Fuel Tank ReplacementLong Branch & New Alexandria Pump Station Fuel Tank Replacement
Long Branch & New Alexandria Pump Station Fuel Tank Replacement
 
Prototype Development of an Integrated Mars Atmosphere and Soil Processing Sy...
Prototype Development of an Integrated Mars Atmosphere and Soil Processing Sy...Prototype Development of an Integrated Mars Atmosphere and Soil Processing Sy...
Prototype Development of an Integrated Mars Atmosphere and Soil Processing Sy...
 
Project Management Challenges in an Effluent Treatment Plant Construction
Project Management  Challenges in an Effluent Treatment Plant Construction Project Management  Challenges in an Effluent Treatment Plant Construction
Project Management Challenges in an Effluent Treatment Plant Construction
 
B2 - FIALE GEOTHERMAL EXPLORATION PROJECT Djibouti
B2 - FIALE GEOTHERMAL EXPLORATION PROJECT DjiboutiB2 - FIALE GEOTHERMAL EXPLORATION PROJECT Djibouti
B2 - FIALE GEOTHERMAL EXPLORATION PROJECT Djibouti
 
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
 
LMPP Final Presentation_FINAL1
LMPP Final Presentation_FINAL1LMPP Final Presentation_FINAL1
LMPP Final Presentation_FINAL1
 
Disco Road Biogas Utilization Project
Disco Road Biogas Utilization ProjectDisco Road Biogas Utilization Project
Disco Road Biogas Utilization Project
 
Moffett RAB Site 25 Update
Moffett RAB Site 25 UpdateMoffett RAB Site 25 Update
Moffett RAB Site 25 Update
 
W04 bioremediation of a chlorinated solvents site-turner
W04 bioremediation of a chlorinated solvents site-turnerW04 bioremediation of a chlorinated solvents site-turner
W04 bioremediation of a chlorinated solvents site-turner
 
Harrison_Simbol_Presentation Peer Review 2012
Harrison_Simbol_Presentation Peer Review 2012Harrison_Simbol_Presentation Peer Review 2012
Harrison_Simbol_Presentation Peer Review 2012
 
Marks Sess13 102309
Marks Sess13 102309Marks Sess13 102309
Marks Sess13 102309
 
Logistics 2013: Stephen Carr
Logistics 2013: Stephen Carr Logistics 2013: Stephen Carr
Logistics 2013: Stephen Carr
 
19-07-06 Scheme Description details
19-07-06 Scheme Description details19-07-06 Scheme Description details
19-07-06 Scheme Description details
 
Stormwater Program Update to McLean Citizens Association
Stormwater Program Update to McLean Citizens AssociationStormwater Program Update to McLean Citizens Association
Stormwater Program Update to McLean Citizens Association
 

More from RWM Brasil

More from RWM Brasil (9)

Dia 2: Atendendo as necessidades dos municípios na eliminação de resíduos de ...
Dia 2: Atendendo as necessidades dos municípios na eliminação de resíduos de ...Dia 2: Atendendo as necessidades dos municípios na eliminação de resíduos de ...
Dia 2: Atendendo as necessidades dos municípios na eliminação de resíduos de ...
 
Dia 2: Como a tecnologia de coleta seletiva está ajudando os municípios lidar...
Dia 2: Como a tecnologia de coleta seletiva está ajudando os municípios lidar...Dia 2: Como a tecnologia de coleta seletiva está ajudando os municípios lidar...
Dia 2: Como a tecnologia de coleta seletiva está ajudando os municípios lidar...
 
Dia 2: As contribuições das empresas para a política nacional de resíduos sól...
Dia 2: As contribuições das empresas para a política nacional de resíduos sól...Dia 2: As contribuições das empresas para a política nacional de resíduos sól...
Dia 2: As contribuições das empresas para a política nacional de resíduos sól...
 
Dia 2: Resíduos sólidos quantificados: custo para a implementação da PNRS,Car...
Dia 2: Resíduos sólidos quantificados: custo para a implementação da PNRS,Car...Dia 2: Resíduos sólidos quantificados: custo para a implementação da PNRS,Car...
Dia 2: Resíduos sólidos quantificados: custo para a implementação da PNRS,Car...
 
Dia 2: A valorização energética de resíduos, André Gomes, Lindner Recyclingtech
Dia 2: A valorização energética de resíduos, André Gomes, Lindner RecyclingtechDia 2: A valorização energética de resíduos, André Gomes, Lindner Recyclingtech
Dia 2: A valorização energética de resíduos, André Gomes, Lindner Recyclingtech
 
Dia 1: balanço carnaval 2013, Prefeitura de Recife
Dia 1: balanço carnaval 2013, Prefeitura de RecifeDia 1: balanço carnaval 2013, Prefeitura de Recife
Dia 1: balanço carnaval 2013, Prefeitura de Recife
 
Dia1: Educação ambiental na gestão de resíduos sólidos, Nilo Sergio de Melo D...
Dia1: Educação ambiental na gestão de resíduos sólidos, Nilo Sergio de Melo D...Dia1: Educação ambiental na gestão de resíduos sólidos, Nilo Sergio de Melo D...
Dia1: Educação ambiental na gestão de resíduos sólidos, Nilo Sergio de Melo D...
 
Dia 1: Governos locais pela sustentabilidade,Florence Laloe, ICLEI
Dia 1: Governos locais pela sustentabilidade,Florence Laloe, ICLEIDia 1: Governos locais pela sustentabilidade,Florence Laloe, ICLEI
Dia 1: Governos locais pela sustentabilidade,Florence Laloe, ICLEI
 
Dia 1: Estação de transferência para resíduos sólidos, Begoña Casanova, Danima
Dia 1: Estação de transferência para resíduos sólidos, Begoña Casanova, DanimaDia 1: Estação de transferência para resíduos sólidos, Begoña Casanova, Danima
Dia 1: Estação de transferência para resíduos sólidos, Begoña Casanova, Danima
 

Recently uploaded

Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
WSO2
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Safe Software
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
?#DUbAI#??##{{(☎️+971_581248768%)**%*]'#abortion pills for sale in dubai@
 

Recently uploaded (20)

Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : Uncertainty
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering Developers
 
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdfRising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
 
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
 
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ..."I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
 
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
 
ICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesICT role in 21st century education and its challenges
ICT role in 21st century education and its challenges
 
FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024
 
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWEREMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
 
MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor Presentation
 
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
 
Six Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal OntologySix Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal Ontology
 
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot ModelMcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 

Dia 1:Ativando obras no parque olímpico,Jan Hellings, Jan Hellings & Associates Ltd_UK

  • 1. Enabling works at the Olympic Park: Effectively delivering the preparation of the construction site for the London 2012 games Dr Jan Hellings Dr Jan Hellings & Associates Ltd Formerly Project Sponsor Olympic Delivery Authority London October 1st 2013
  • 2. SUMMARY OF PRESENTATION • • • • • • • • • Taking possession of the Olympic Park site Site investigation Ground/water considerations Clean-up (Remediation) process Typical contaminants Treatment options Materials movement & management Photos Lessons learned 2 Olympic Delivery Authority
  • 3. LOCATION OF 2012 OLYMPIC VENUES 3 Olympic Delivery Authority
  • 4. OLYMPIC PARK SITE - BEFORE 4 Olympic Delivery Authority
  • 5. TAKING POSSESSION OF THE OLYMPIC PARK SITE • The assembly of a 250 hectare site is one of largest Compulsory Purchase Orders to have taken place in the UK. • 2,200 land ownerships to acquire • Approximately 200 businesses relocated • 98% of the 4,750 jobs secured • Over 140,000 square metres of development space, including three new LDA business parks constructed in areas adjacent to the Park 5 Olympic Delivery Authority
  • 8. Site Investigation Statistics No. of Intrusions Total metres sampled and tested Geotech and contam boreholes 880 30,800 Contam specific boreholes 390 5,850 Window samples (contam specific) 930 5,580 Trial pits (geotech and contam) 600 2,400 2,800 44,630 TOTALS 8 Olympic Delivery Authority
  • 9. Plan of Olympic Park Site Investigation 9 Olympic Delivery Authority
  • 10. Site Preparation Life Cycle Global Remediation Strategy Approvals Site Specific Remediation Strategy Vacant Possession Site Investigation River Walls Utility inputs Invasive Species Construction Roads and Bridges (abutments) Demolition Remediation Method Statements (RMS) Target = 95% re-use Remediation Bulk Earthworks Mechanical Separation Soil Washing 10 Olympic Delivery Authority Bioremediation Stabilisation Target = 85% re-use Handover to Venue Contractor
  • 11. Conceptual Site Model – Risk Driven Remediation 11 Olympic Delivery Authority
  • 13. Treatment Methods Soil Washing North Plant (100 tph) CZ 5b; looking east the fine sands hydraulic separation and output conveyor in foreground Soil Washing Sout); looking at sludge (fines at 15 tph *2) dewatering filter press 13 Olympic Delivery Authority Soil Washing North Plant (100 tph) CZ 5b; looking north to fines separation and beyond to Coarse fraction washing. Soil Washing South (75 tph *3); looking north towards the two soil washing plants in cZ4. Note washed gravel output in left foreground
  • 14. Treatment Methods Mobile Soil Stabilisation Plant set up for Treatment Trials (45t/hr) prior to Main Equipment being Mobilised Bioremediation Pile Cells Aeration, Leachate and irrigation pipe systems being established beneath bio-piles 14 Olympic Delivery Authority Aerial view of site prior to start of projectfiled prior to Bioremediation Pile Cells being Soil Stabilisation Plant in South Treatment Centre (60t/hr) Aeration, Leachate and irrigation systems being established, pipe work still to be connected
  • 15. Treatment Methods Complex Screening Plant setup in North of the Park In-situ Soil Mixer utilising Cement and/or lime to allow geotechnical soil parameter improvement 15 Olympic Delivery Authority Unsorted Landfill Materials at Complex Screening Plant
  • 16. Treatment Centre Locations • Two treatment centres established – one in the north and one in the south • Each treatment centre has several treatment processes available • Flexibility of approach and competition between treatment methods is encouraged • Five soil washing plants at site. • Soil stabilisation • Bioremediation cell pads constructed 16 Olympic Delivery Authority
  • 17. • Materials Total approximately (2.5 Million m3) • Demolition (500,000m3) • Excavated Soil (1.8 Million m3 cut of which 820,000m3 treated ) • Tunnelling soil (approximately 200,000m3) 17 • Beneficial and optimal reuse strategies • General fill (approximately 50% untreated) • Separation layer (approximately 50%) •Base coarse and sub-base •Selected engineering fill Olympic Delivery Authority
  • 18. Materials Balance – Enabling Works Washed Gravels Sludge 18 Olympic Delivery Authority Washed Sands Waste
  • 19. Demolition of Tower Blocks on CZ6b, Clays Lane 19 Olympic Delivery Authority
  • 20. Demolition of warehouse/office building 20 Olympic Delivery Authority
  • 21. Oblique photo looking North 21 Olympic Delivery Authority
  • 22. STADIUM SITE MID 2007 22 Olympic Delivery Authority
  • 23. OLYMPIC PARK LOOKING NORTH – JULY 2008 23 Olympic Delivery Authority
  • 24. OLYMPIC PARK LOOKING NORTH – AUGUST 2008 24 Olympic Delivery Authority
  • 25. OLYMPIC PARK LOOKING NORTH – NOVEMBER 2008 25 Olympic Delivery Authority
  • 26. OLYMPIC PARK LOOKING NORTH – MID 2009 26 Olympic Delivery Authority
  • 27. PARK VIEW LOOKING SOUTH – MID 2008 27 Olympic Delivery Authority
  • 28. PARK VIEW LOOKING SOUTH – November 2008 28 Olympic Delivery Authority
  • 29. PARK VIEW LOOKING SOUTH – MID 2009 29 Olympic Delivery Authority
  • 30. AQUATICS SITE – MID 2008 30 Olympic Delivery Authority
  • 31. AQUATICS SITE – MID 2009 31 Olympic Delivery Authority
  • 32. AQUATICS ROOF – NOV 2009 32 Olympic Delivery Authority
  • 33. LOOKING SOUTH – DEC 2011 33 Olympic Delivery Authority
  • 34. PARK – GAMES MODE 34 Olympic Delivery Authority
  • 36. VILLAGE - LEGACY 36 Olympic Delivery Authority
  • 38. THE QUEEN LEAVES BUCKINGHAM PALACE WITH JAMES BOND FOR THE OPENING CEREMONY 38 Olympic Delivery Authority
  • 39. THE QUEEN PARACHUTES INTO THE STADUIM – OPENING CEREMONY 39 Olympic Delivery Authority
  • 42. THE LEGACY FRAMEWORK FOR THE PARK • • • • • • 42 Olympic Delivery Authority 110 ha open space Development platforms comprising > circa 950,000 sqm development 4,000 new housing units within the village (> 9,000 overall) Major investments in waterways, rims, park edges Venues transformed for legacy Provides strong basis for further development
  • 44. CLOSURE The 2012 London Olympic and Paralympic Games were a great success. We engineers can do the ‘impossible’! Muito obrigado jan@janhellings.com 44 Olympic Delivery Authority