SlideShare a Scribd company logo
1 of 16
Resource Scheduling
The Need for Resource Scheduling:
The previous Project Scheduling methods that we have covered have not
considered the constraint of resources. Generally, there are
2 types of projects…..
1. Projects that MUST meet a certain deadline and have ‘unlimited’ resources in
order to meet this. This would use Time Limited Scheduling.
2. Projects that have limited availability of the required resources, however the
project deadline is more flexible. The would use Resource Limited Scheduling.

Note: if a project has both limited time and resources, the project manager must initially
assume that one or the other is flexible. OR, renegotiations will need to take place.
Time Limited Scheduling
Objectives:
▪ Determine exactly what resources the project requires;
▪ Make these resources available for when they are needed;
▪ Use each resource as efficiently as possible
– Resource Smoothing: this defines the act of maximising resources efficiency. Despite having
‘umlimited’ resorurces, it is still necessary to try to keep costs down as much as possible.
The Resources Loading Chart:
Activity

Description

Staff

Duration Earliest Start Time Float Latest Finish Time

A

Prepare offices

2

12

0

0

12

B

Procure equipment

2

8

0

4

12

C

Design tests

1

5

0

17

22

D

Install equiptment

4

10

12

0

22

E

Test system

3

10

22

0

32

F

Train users

1

5

12

15

32

Consider the
adjacent
example which
is adapted from
Field & Keller
‘Project
Management’
1998:
We will build the
previous information
into a ‘Resource
Loading Chart’
Observations:
▪ From the previous slide’s graph we can immediately tell how many
staff are needed at any one time.
▪ For example – in week 10, we can identify that only 2 staff members
are required. Whereas in week 14 there are 5 staff members required.

▪ The method of creating this chart, by positioning one activity at a
time, is called Serial Scheduling.
Note: The bottom row of the graph could also be described as the ‘critical
path’. Each of these items as Float=0. This row can be described as the
Base Line.
Resource Levelling:
▪ As identified in the previous slides, our chart contains
‘extreme peaks’. For example, weeks 1-5.
▪ Resource levelling helps to avoid this.
▪ As we have several activities which contain float, we can try
to move these activities to ‘level’ out the staff distribution:
Obviously this still
isn’t ideal as we still
have a ‘peak’ during
week 13. However we
have levelled s much
as possible, and in
turn we have reduced
costs.
Resource Limited Scheduling
Objectives:
▪ To adjust the project’s time to adapt to fixed level of
resources.
▪ In the previous example, we realised it would take 5 staff to
create the office in 32 weeks.

▪ Now, let’s consider how long it would take if the staff level
were fixed at 4.
Parallel Scheduling:
▪ Definition: Starting at the beginning of a project and
considering all the eligible activities, in a parallel manner.
▪ An eligible activity would be one which could be started if
the resources were available.
Let’s re-consider the example….
Activity

Dependency

Staff

Duration

Latest Start
Time

Float Latest Finish Time

A

N/A

2

12

0

0

12

B

N/A

2

8

4

4

12

C

N/A

1

5

17

17

22

D

A and B

4

10

12

0

22

E

C and D

3

10

22

0

32

F

A and B

1

5

27

15

32

Example
In Excel, Have a
go at plotting
the chart with
the strict
resource limit of
4:
The Result
Sources and Further Reading:
▪ Fiiled, M. and Keller, M. (1998), Croatia: Thomson Learning
– Chapter 3.4

▪ Moder, J., Philips, C. and Davis, E. (1983), Project management with CPM, PERT and
project diagramming, New York: Van Nostrand Reinhold Publishers
▪ Kerzner, H. (2009) Project Management, New Jersey: John Wiley & Sons, 10th edn.
– Chapter 12

More Related Content

What's hot

Introduction to Project Portfolio Management (PPM)
Introduction to Project Portfolio Management (PPM)Introduction to Project Portfolio Management (PPM)
Introduction to Project Portfolio Management (PPM)Kimmy Chen
 
Project management life cycle
Project management life cycleProject management life cycle
Project management life cycleAndrei Crăciun
 
What is a Work Breakdown Structure?
What is a Work Breakdown Structure?What is a Work Breakdown Structure?
What is a Work Breakdown Structure?Kenny Hirschmann
 
Work Breakdown Structures (WBS)
Work Breakdown Structures (WBS)Work Breakdown Structures (WBS)
Work Breakdown Structures (WBS)stakeholdermap
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-controlJatindra Malik
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management A Makwana
 
Project management (1)
Project management (1)Project management (1)
Project management (1)Hetal Visaria
 
The role and responsibilities of the project manager
The role and responsibilities of the project manager The role and responsibilities of the project manager
The role and responsibilities of the project manager ProofHub
 
Project controls
Project controlsProject controls
Project controlsAshok Kumar
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource SmoothingDavidMcLachlan1
 

What's hot (20)

Final Project Closing
Final Project ClosingFinal Project Closing
Final Project Closing
 
Project selection
Project selectionProject selection
Project selection
 
Resource allocation and smoothing
Resource allocation and smoothingResource allocation and smoothing
Resource allocation and smoothing
 
Introduction to Project Portfolio Management (PPM)
Introduction to Project Portfolio Management (PPM)Introduction to Project Portfolio Management (PPM)
Introduction to Project Portfolio Management (PPM)
 
Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
 
Project management life cycle
Project management life cycleProject management life cycle
Project management life cycle
 
What is a Work Breakdown Structure?
What is a Work Breakdown Structure?What is a Work Breakdown Structure?
What is a Work Breakdown Structure?
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Work Breakdown Structures (WBS)
Work Breakdown Structures (WBS)Work Breakdown Structures (WBS)
Work Breakdown Structures (WBS)
 
Project portfolio management
Project portfolio managementProject portfolio management
Project portfolio management
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-control
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management
 
Project Budgeting
Project BudgetingProject Budgeting
Project Budgeting
 
crashing of project
crashing of project crashing of project
crashing of project
 
Project management (1)
Project management (1)Project management (1)
Project management (1)
 
The role and responsibilities of the project manager
The role and responsibilities of the project manager The role and responsibilities of the project manager
The role and responsibilities of the project manager
 
Project controls
Project controlsProject controls
Project controls
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing
 
Project cost management-slides
Project cost management-slidesProject cost management-slides
Project cost management-slides
 

Similar to Resource Scheduling

Resource Scheduling
Resource SchedulingResource Scheduling
Resource SchedulingNicola2903
 
Resource Planning
Resource PlanningResource Planning
Resource PlanningWajahat Ali
 
Project-Time-Line.pdf
Project-Time-Line.pdfProject-Time-Line.pdf
Project-Time-Line.pdfNabeel Ahmad
 
PM Session 6
PM Session 6PM Session 6
PM Session 6dmdk12
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Schedulingsslovepk
 
Resource planning and resource allocation
Resource planning and resource allocationResource planning and resource allocation
Resource planning and resource allocationVenu Yemul
 
Project TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docxProject TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docxbriancrawford30935
 
Project management teaching
Project management   teachingProject management   teaching
Project management teachingCHIRANJAN SAHA
 
09 Fine-tuning Assignment Details
09 Fine-tuning Assignment Details09 Fine-tuning Assignment Details
09 Fine-tuning Assignment DetailsSoe Naing Win
 
Part II: Planning Time: Determining When and How Much
Part II: Planning Time: Determining When and How MuchPart II: Planning Time: Determining When and How Much
Part II: Planning Time: Determining When and How MuchMuzo Bacan
 
Resource Allocation In Software Project Management
Resource Allocation In Software Project ManagementResource Allocation In Software Project Management
Resource Allocation In Software Project ManagementSyed Hassan Ali
 
Network scheduling with limited_resources- revised1
Network scheduling with limited_resources- revised1Network scheduling with limited_resources- revised1
Network scheduling with limited_resources- revised1Ninoto Zhimomi
 

Similar to Resource Scheduling (20)

Resource Scheduling
Resource SchedulingResource Scheduling
Resource Scheduling
 
Module :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levellingModule :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levelling
 
Resource management
Resource managementResource management
Resource management
 
Resource Planning
Resource PlanningResource Planning
Resource Planning
 
Project-Time-Line.pdf
Project-Time-Line.pdfProject-Time-Line.pdf
Project-Time-Line.pdf
 
Ch6 resources
Ch6 resourcesCh6 resources
Ch6 resources
 
Allocating resources
Allocating resourcesAllocating resources
Allocating resources
 
PM Session 6
PM Session 6PM Session 6
PM Session 6
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
 
Resource planning and resource allocation
Resource planning and resource allocationResource planning and resource allocation
Resource planning and resource allocation
 
Chap008.ppt
Chap008.pptChap008.ppt
Chap008.ppt
 
Ch09 (1).pptx
Ch09 (1).pptxCh09 (1).pptx
Ch09 (1).pptx
 
Resource allocation
Resource allocationResource allocation
Resource allocation
 
Project TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docxProject TimeIST4055Chapter 6Now that you have the Sc.docx
Project TimeIST4055Chapter 6Now that you have the Sc.docx
 
Project management teaching
Project management   teachingProject management   teaching
Project management teaching
 
09 Fine-tuning Assignment Details
09 Fine-tuning Assignment Details09 Fine-tuning Assignment Details
09 Fine-tuning Assignment Details
 
Part II: Planning Time: Determining When and How Much
Part II: Planning Time: Determining When and How MuchPart II: Planning Time: Determining When and How Much
Part II: Planning Time: Determining When and How Much
 
Resource Allocation In Software Project Management
Resource Allocation In Software Project ManagementResource Allocation In Software Project Management
Resource Allocation In Software Project Management
 
Spm unit 3
Spm unit 3Spm unit 3
Spm unit 3
 
Network scheduling with limited_resources- revised1
Network scheduling with limited_resources- revised1Network scheduling with limited_resources- revised1
Network scheduling with limited_resources- revised1
 

More from Nicola2903

Network diagrams
Network diagramsNetwork diagrams
Network diagramsNicola2903
 
Critical path method
Critical path methodCritical path method
Critical path methodNicola2903
 
Work breakdown Structure
Work breakdown StructureWork breakdown Structure
Work breakdown StructureNicola2903
 
The gantt Chart
The gantt Chart The gantt Chart
The gantt Chart Nicola2903
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structureNicola2903
 
Network Diagrams
Network DiagramsNetwork Diagrams
Network DiagramsNicola2903
 
Estimating in Project Scheduling
Estimating in Project SchedulingEstimating in Project Scheduling
Estimating in Project SchedulingNicola2903
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path MethodNicola2903
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path MethodNicola2903
 
The Gantt Chart
The Gantt ChartThe Gantt Chart
The Gantt ChartNicola2903
 

More from Nicola2903 (12)

Network diagrams
Network diagramsNetwork diagrams
Network diagrams
 
Estimating
EstimatingEstimating
Estimating
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Work breakdown Structure
Work breakdown StructureWork breakdown Structure
Work breakdown Structure
 
The gantt Chart
The gantt Chart The gantt Chart
The gantt Chart
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 
Network Diagrams
Network DiagramsNetwork Diagrams
Network Diagrams
 
Estimating
EstimatingEstimating
Estimating
 
Estimating in Project Scheduling
Estimating in Project SchedulingEstimating in Project Scheduling
Estimating in Project Scheduling
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path Method
 
The Critical Path Method
The Critical Path MethodThe Critical Path Method
The Critical Path Method
 
The Gantt Chart
The Gantt ChartThe Gantt Chart
The Gantt Chart
 

Recently uploaded

Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...lizamodels9
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxMarkAnthonyAurellano
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...lizamodels9
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfJos Voskuil
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchirictsugar
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyotictsugar
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadAyesha Khan
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...lizamodels9
 

Recently uploaded (20)

Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdf
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchir
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyot
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
Corporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information TechnologyCorporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information Technology
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
 

Resource Scheduling

  • 2. The Need for Resource Scheduling: The previous Project Scheduling methods that we have covered have not considered the constraint of resources. Generally, there are 2 types of projects….. 1. Projects that MUST meet a certain deadline and have ‘unlimited’ resources in order to meet this. This would use Time Limited Scheduling. 2. Projects that have limited availability of the required resources, however the project deadline is more flexible. The would use Resource Limited Scheduling. Note: if a project has both limited time and resources, the project manager must initially assume that one or the other is flexible. OR, renegotiations will need to take place.
  • 4. Objectives: ▪ Determine exactly what resources the project requires; ▪ Make these resources available for when they are needed; ▪ Use each resource as efficiently as possible – Resource Smoothing: this defines the act of maximising resources efficiency. Despite having ‘umlimited’ resorurces, it is still necessary to try to keep costs down as much as possible.
  • 5. The Resources Loading Chart: Activity Description Staff Duration Earliest Start Time Float Latest Finish Time A Prepare offices 2 12 0 0 12 B Procure equipment 2 8 0 4 12 C Design tests 1 5 0 17 22 D Install equiptment 4 10 12 0 22 E Test system 3 10 22 0 32 F Train users 1 5 12 15 32 Consider the adjacent example which is adapted from Field & Keller ‘Project Management’ 1998:
  • 6. We will build the previous information into a ‘Resource Loading Chart’
  • 7. Observations: ▪ From the previous slide’s graph we can immediately tell how many staff are needed at any one time. ▪ For example – in week 10, we can identify that only 2 staff members are required. Whereas in week 14 there are 5 staff members required. ▪ The method of creating this chart, by positioning one activity at a time, is called Serial Scheduling. Note: The bottom row of the graph could also be described as the ‘critical path’. Each of these items as Float=0. This row can be described as the Base Line.
  • 8. Resource Levelling: ▪ As identified in the previous slides, our chart contains ‘extreme peaks’. For example, weeks 1-5. ▪ Resource levelling helps to avoid this. ▪ As we have several activities which contain float, we can try to move these activities to ‘level’ out the staff distribution:
  • 9. Obviously this still isn’t ideal as we still have a ‘peak’ during week 13. However we have levelled s much as possible, and in turn we have reduced costs.
  • 11. Objectives: ▪ To adjust the project’s time to adapt to fixed level of resources. ▪ In the previous example, we realised it would take 5 staff to create the office in 32 weeks. ▪ Now, let’s consider how long it would take if the staff level were fixed at 4.
  • 12. Parallel Scheduling: ▪ Definition: Starting at the beginning of a project and considering all the eligible activities, in a parallel manner. ▪ An eligible activity would be one which could be started if the resources were available. Let’s re-consider the example….
  • 13. Activity Dependency Staff Duration Latest Start Time Float Latest Finish Time A N/A 2 12 0 0 12 B N/A 2 8 4 4 12 C N/A 1 5 17 17 22 D A and B 4 10 12 0 22 E C and D 3 10 22 0 32 F A and B 1 5 27 15 32 Example
  • 14. In Excel, Have a go at plotting the chart with the strict resource limit of 4:
  • 16. Sources and Further Reading: ▪ Fiiled, M. and Keller, M. (1998), Croatia: Thomson Learning – Chapter 3.4 ▪ Moder, J., Philips, C. and Davis, E. (1983), Project management with CPM, PERT and project diagramming, New York: Van Nostrand Reinhold Publishers ▪ Kerzner, H. (2009) Project Management, New Jersey: John Wiley & Sons, 10th edn. – Chapter 12