1. Scale of Impact
• Problem Statement:
 At the end of Q3-2014, delivery complaints were the highest
contributor of the ten types of market customers complaints .
 Improve Delivery On Time of 5G HOD was one of the business
priorities to Deliver Volumes OTIF to Support Business
Growth to Delight Our Customers & Consumers .
81.9%
 Delivery complaints were representing 81.9% of total market
complaints during Jan-Oct 2014 with monthly average of 2006
complaints.
September 15, 2014 Project Kick-off Meeting
• Relevant to business:
 The project scope was covering Whole Eastern Area
“population of 4.5 Million” with involvement of HOD
Production, Distribution Staff & Customer Service
Staff noting that NCE is not yet rolled out in SC.
Nestlé Waters –AOA Best of the Best Awards – 2015
• Improvement Quantified:
 80% reduction in non-delivered cases :
61.5% reduction in missed delivery complaints FY-2015 ( From 22,331 to 8,595 )
51% reduction in overall Dammam Consumers Complaints (CCR) FY-2015 ( From 27,625 to 13,528 )
Dammam Factory – Saudi Arabia
Improve Delivery On Time of 5G HOD Through Reduction 20 % of Non-Delivered Cases By March 2015
Nestlé Waters –AOA Best of the Best Awards – 2015
2. Effective use of NCE and problem solving methodologies
Project used NCE problems solving methodologies effectively and efficiently with
Involvement of more than 400 employees from cross-functional team to be aligned with
Green Belt Level . Project was done OTIF with Excellent tollgate score of
98%.
Dammam Factory – Saudi Arabia
Improve Delivery On Time of 5G HOD Through Reduction 20 % of Non-Delivered Cases By March 2015
Nestlé Waters –AOA Best of the Best Awards – 2015
• Impact on NCE Journey
 This GB is supporting NCE Journey through involvement and engagement of SC & Customer
Service beyond of manufacturing team
 We have been awarded Nestlé Quality Global Gold Award -2015 “for the highest factory customers
complaints reduction”.
Dammam Factory – Saudi Arabia
Improve Delivery On Time of 5G HOD Through Reduction 20 % of Non-Delivered Cases By March 2015
Nestlé Waters –AOA Best of the Best Awards – 2015
3. Team work
High level of involvement, engagement &
teamwork enhanced in different cross-
functional together with well experienced
coach and high engagement of the sponsor
were the keys to have the success
achieved .
Brainstorming & Wringing Online Coaching Sponsor-Involvement Helpers & Drivers Coaching
Dammam Factory – Saudi Arabia
Improve Delivery On Time of 5G HOD Through Reduction 20 % of Non-Delivered Cases By March 2015
Nestlé Waters –AOA Best of the Best Awards – 2015
4. Implemented Actions
17 actions were implemented while the main actions with high impact are as hereunder :
1. Weekly & Monthly Meetings with drivers & helpers by distribution management team.
2. Establishment of new coding system for Non-delivered cases.
3. Daily entering & filtering" screening " on all checklists for non-delivered cases.
4. Rerouting Dammam routes to making balancing between it.
5. Create a clear communication plan between production & distribution.
6. Defensive Driving training course was delivered to drivers.
7. Creating SOP’s & SR for several activities.
Dammam Factory – Saudi Arabia
Improve Delivery On Time of 5G HOD Through Reduction 20 % of Non-Delivered Cases By March 2015
 For more information related to project ,please access the full storyboards on I-nexus ID : 133455
Nestlé Waters –AOA Best of the Best Awards – 2015
5. Sustainability
 Solutions were implemented since January -2015, and the results are sustainable till now and
control action plan was created and in place .
Dammam Factory – Saudi Arabia
Improve Delivery On Time of 5G HOD Through Reduction 20 % of Non-Delivered Cases By March 2015
Nestlé Waters –AOA Best of the Best Awards – 2015
6. Creativity & Replication
 “Broken down factory walls by GEMBA & Online Coaching
sessions inside & outside the factory “
 Establishment of a new coding system understandable by all
team members with different skill levels and languages.
 Replication of the project at remaining cities in eastern region
areas in addition to 7 factories in AP Market.
 One of the main future recommendations was using Handheld
devices with barcodes reader to make more improvement.
GEMBA
Online Coaching
DCP
Dammam Factory – Saudi Arabia
Improve Delivery On Time of 5G HOD Through Reduction 20 % of Non-Delivered Cases By March 2015
“ It was an excellent opportunity and first time
involvement in DMAIC & NCE which enhances our
problem solving skills ,also we were able to be in
contact with our customers and knowing their needs
in more detailed to work on improving it .”
Nestlé Waters –AOA Best of the Best Awards – 2015
“The project was impressive, it helps the team to develop and
maintain a realistic and achievable delivery schedule.. The
attitude of the employees to commitment has a great influence
on the quality of outputs for tracking performance, better
delivery efficiency and enhanced customer satisfaction “
I am confident and proud of the successful
achievements of the team great efforts exerted during
this short time. Remarkable results were clear in
reducing non-delivered cases and customer complaints
calls which led to enhancing customer satisfaction.
.
Process Owner
Sponsor
Data Entry & Customer
Service- Females
Dammam Factory – Saudi Arabia
Improve Delivery On Time of 5G HOD Through Reduction 20 % of Non-Delivered Cases By March 2015
 Consumers feedback questionnaire program
was conducted at sample size of 1077 customers
showed an “Excellent "satisfaction.
 Nestle Waters CSI Program was conducted
by Ipsos MENA at sample profile of 402
customers showed satisfaction level of 9 out of
10 “satisfied”
7. VOC “Satisfaction” – Internal & External
Nestlé Waters –AOA Best of the Best Awards – 2015
Team party was organized and certificates of appreciation & rewards awarded for the team
C E L E B R A T I O N ! ! !
Dammam Factory – Saudi Arabia
Improve Delivery On Time of 5G HOD Through Reduction 20 % of Non-Delivered Cases By March 2015
Thank You

More Related Content

What's hot

Lean six sigma (green belt)new
Lean six sigma (green belt)newLean six sigma (green belt)new
Lean six sigma (green belt)newHakeem-Ur- Rehman
 
Six Sigma and Its Implementation
Six Sigma and Its ImplementationSix Sigma and Its Implementation
Six Sigma and Its ImplementationAnsar Lawi
 
Six sigma vs lean
Six sigma vs leanSix sigma vs lean
Six sigma vs leankiran
 
Six Sigma Session For Production And Project Team By Lt Col Vikram Bakshi
Six Sigma Session For Production And Project Team By Lt Col Vikram BakshiSix Sigma Session For Production And Project Team By Lt Col Vikram Bakshi
Six Sigma Session For Production And Project Team By Lt Col Vikram BakshiLT COLONEL VIKRAM BAKSHI ( RETD)
 
Continuous Improvement using the Toyota Way
Continuous Improvement using the Toyota WayContinuous Improvement using the Toyota Way
Continuous Improvement using the Toyota WayAnita Rao
 
Six Sigma Principles And Concepts PowerPoint Presentation Slides
Six Sigma Principles And Concepts PowerPoint Presentation SlidesSix Sigma Principles And Concepts PowerPoint Presentation Slides
Six Sigma Principles And Concepts PowerPoint Presentation SlidesSlideTeam
 
White Belt DMAIC Project Line G MTTR
White Belt DMAIC Project Line G  MTTRWhite Belt DMAIC Project Line G  MTTR
White Belt DMAIC Project Line G MTTRIrfan Rasheed Rana
 
Joe Moleski, Master Black Belt Lean Sigma Philosophy
Joe Moleski, Master Black Belt Lean Sigma PhilosophyJoe Moleski, Master Black Belt Lean Sigma Philosophy
Joe Moleski, Master Black Belt Lean Sigma Philosophyreelsports
 
Six sigma in automobile Industry
Six sigma in automobile IndustrySix sigma in automobile Industry
Six sigma in automobile IndustryVishnu Rajoriya
 
Yellow belt process improvement training and certification module
Yellow belt process improvement training and certification moduleYellow belt process improvement training and certification module
Yellow belt process improvement training and certification moduleVishy Chandra
 
Six Sigma the best ppt
Six Sigma the best pptSix Sigma the best ppt
Six Sigma the best pptRabia Sgh S
 
Lean Manufacturing Systems WithAdrian
Lean Manufacturing Systems WithAdrianLean Manufacturing Systems WithAdrian
Lean Manufacturing Systems WithAdrianAdrian Beale
 

What's hot (20)

Lean six sigma (green belt)new
Lean six sigma (green belt)newLean six sigma (green belt)new
Lean six sigma (green belt)new
 
Tqm and six sigma
Tqm and six sigmaTqm and six sigma
Tqm and six sigma
 
Six sigma
Six sigmaSix sigma
Six sigma
 
Six Sigma and Its Implementation
Six Sigma and Its ImplementationSix Sigma and Its Implementation
Six Sigma and Its Implementation
 
Six sigma vs lean
Six sigma vs leanSix sigma vs lean
Six sigma vs lean
 
Six Sigma DMAIC Case Study
Six Sigma DMAIC Case StudySix Sigma DMAIC Case Study
Six Sigma DMAIC Case Study
 
Six Sigma Session For Production And Project Team By Lt Col Vikram Bakshi
Six Sigma Session For Production And Project Team By Lt Col Vikram BakshiSix Sigma Session For Production And Project Team By Lt Col Vikram Bakshi
Six Sigma Session For Production And Project Team By Lt Col Vikram Bakshi
 
Continuous Improvement using the Toyota Way
Continuous Improvement using the Toyota WayContinuous Improvement using the Toyota Way
Continuous Improvement using the Toyota Way
 
Six Sigma Principles And Concepts PowerPoint Presentation Slides
Six Sigma Principles And Concepts PowerPoint Presentation SlidesSix Sigma Principles And Concepts PowerPoint Presentation Slides
Six Sigma Principles And Concepts PowerPoint Presentation Slides
 
White Belt DMAIC Project Line G MTTR
White Belt DMAIC Project Line G  MTTRWhite Belt DMAIC Project Line G  MTTR
White Belt DMAIC Project Line G MTTR
 
Joe Moleski, Master Black Belt Lean Sigma Philosophy
Joe Moleski, Master Black Belt Lean Sigma PhilosophyJoe Moleski, Master Black Belt Lean Sigma Philosophy
Joe Moleski, Master Black Belt Lean Sigma Philosophy
 
Driving Continuous Improvement
Driving Continuous ImprovementDriving Continuous Improvement
Driving Continuous Improvement
 
Six sigma in automobile Industry
Six sigma in automobile IndustrySix sigma in automobile Industry
Six sigma in automobile Industry
 
Lean Manufacturing
Lean ManufacturingLean Manufacturing
Lean Manufacturing
 
Yellow belt process improvement training and certification module
Yellow belt process improvement training and certification moduleYellow belt process improvement training and certification module
Yellow belt process improvement training and certification module
 
Lean 6 sigma
Lean 6 sigmaLean 6 sigma
Lean 6 sigma
 
170 Fundamentals of Lean Thinking 2014 01
170 Fundamentals of Lean Thinking 2014 01170 Fundamentals of Lean Thinking 2014 01
170 Fundamentals of Lean Thinking 2014 01
 
Six Sigma the best ppt
Six Sigma the best pptSix Sigma the best ppt
Six Sigma the best ppt
 
Dmaic
DmaicDmaic
Dmaic
 
Lean Manufacturing Systems WithAdrian
Lean Manufacturing Systems WithAdrianLean Manufacturing Systems WithAdrian
Lean Manufacturing Systems WithAdrian
 

Viewers also liked (7)

Tpm training
Tpm trainingTpm training
Tpm training
 
Tpm Presentation
Tpm PresentationTpm Presentation
Tpm Presentation
 
Nestle Mineral Water-Operation & Production
Nestle Mineral Water-Operation & ProductionNestle Mineral Water-Operation & Production
Nestle Mineral Water-Operation & Production
 
Establish Your Professional Brand
Establish Your Professional BrandEstablish Your Professional Brand
Establish Your Professional Brand
 
Find the Right People
Find the Right PeopleFind the Right People
Find the Right People
 
Build Relationships
Build RelationshipsBuild Relationships
Build Relationships
 
Engage with Insights
Engage with InsightsEngage with Insights
Engage with Insights
 

Similar to Improvement in Delivery Time of 5G HOD

GB-DMAIC One-Pager Summary
GB-DMAIC One-Pager  SummaryGB-DMAIC One-Pager  Summary
GB-DMAIC One-Pager SummaryMo'ath Thwapiah
 
Chelsea apps creds April
Chelsea apps creds AprilChelsea apps creds April
Chelsea apps creds AprilSteve Anderson
 
Nemko Group - Annual performance 2015
Nemko Group - Annual performance 2015Nemko Group - Annual performance 2015
Nemko Group - Annual performance 2015Nemko Italy
 
James Moore CV - 0.7
James Moore CV - 0.7James Moore CV - 0.7
James Moore CV - 0.7James Moore
 
How operational excellence through lean
How operational excellence through lean How operational excellence through lean
How operational excellence through lean globalsevensteps
 
Strengthening it sm es´ productivity, stand out from the crowd v1
Strengthening it sm es´ productivity, stand out from the crowd v1Strengthening it sm es´ productivity, stand out from the crowd v1
Strengthening it sm es´ productivity, stand out from the crowd v1TECNALIA Research & Innovation
 
NQC Best of the best 2014 slide March 22 2015 Final version
NQC Best of the best 2014 slide  March 22 2015 Final versionNQC Best of the best 2014 slide  March 22 2015 Final version
NQC Best of the best 2014 slide March 22 2015 Final versionMo'ath Thwapiah
 
CMD 2015: Increasing profitability through Must-Win implementation
CMD 2015: Increasing profitability through Must-Win implementationCMD 2015: Increasing profitability through Must-Win implementation
CMD 2015: Increasing profitability through Must-Win implementationValmet Oyj
 
Case Study on Automation Capability CT ARROW
Case Study on Automation Capability CT ARROWCase Study on Automation Capability CT ARROW
Case Study on Automation Capability CT ARROWThe Digital Group
 
Vivek M Thayyil - cv
Vivek M Thayyil - cvVivek M Thayyil - cv
Vivek M Thayyil - cvVivekThayyil
 
Welcomm Presentation 2
Welcomm Presentation 2Welcomm Presentation 2
Welcomm Presentation 2Sonal Haja
 
Profile - Shiloh Naidoo 16 October 2015
Profile - Shiloh Naidoo 16 October 2015Profile - Shiloh Naidoo 16 October 2015
Profile - Shiloh Naidoo 16 October 2015Shiloh Naiken
 
Interactions 2015
Interactions 2015Interactions 2015
Interactions 2015Capgemini
 
SWJ TECHNOLOGY Talent Acquisition
SWJ TECHNOLOGY Talent AcquisitionSWJ TECHNOLOGY Talent Acquisition
SWJ TECHNOLOGY Talent AcquisitionAmber Skinner
 
Continuous Delivery: the Strongest Link in Your Value Chain
Continuous Delivery: the Strongest Link in Your Value ChainContinuous Delivery: the Strongest Link in Your Value Chain
Continuous Delivery: the Strongest Link in Your Value ChainCA Technologies
 
oTMS - new market entry
oTMS - new market entryoTMS - new market entry
oTMS - new market entryLi Michelle
 
Mission Possible: You Can Achieve Touchless Invoice Processing
Mission Possible: You Can Achieve Touchless Invoice ProcessingMission Possible: You Can Achieve Touchless Invoice Processing
Mission Possible: You Can Achieve Touchless Invoice ProcessingSAP Ariba
 

Similar to Improvement in Delivery Time of 5G HOD (20)

GB-DMAIC One-Pager Summary
GB-DMAIC One-Pager  SummaryGB-DMAIC One-Pager  Summary
GB-DMAIC One-Pager Summary
 
Chelsea apps creds April
Chelsea apps creds AprilChelsea apps creds April
Chelsea apps creds April
 
Nemko Group - Annual performance 2015
Nemko Group - Annual performance 2015Nemko Group - Annual performance 2015
Nemko Group - Annual performance 2015
 
James Moore CV - 0.7
James Moore CV - 0.7James Moore CV - 0.7
James Moore CV - 0.7
 
How operational excellence through lean
How operational excellence through lean How operational excellence through lean
How operational excellence through lean
 
Strengthening it sm es´ productivity, stand out from the crowd v1
Strengthening it sm es´ productivity, stand out from the crowd v1Strengthening it sm es´ productivity, stand out from the crowd v1
Strengthening it sm es´ productivity, stand out from the crowd v1
 
Magenic - Velocity
Magenic - VelocityMagenic - Velocity
Magenic - Velocity
 
How to Survive and Thrive in Today's and Tomorrow's Manufacturing Environment
How to Survive and Thrive in Today's and Tomorrow's Manufacturing EnvironmentHow to Survive and Thrive in Today's and Tomorrow's Manufacturing Environment
How to Survive and Thrive in Today's and Tomorrow's Manufacturing Environment
 
NQC Best of the best 2014 slide March 22 2015 Final version
NQC Best of the best 2014 slide  March 22 2015 Final versionNQC Best of the best 2014 slide  March 22 2015 Final version
NQC Best of the best 2014 slide March 22 2015 Final version
 
CMD 2015: Increasing profitability through Must-Win implementation
CMD 2015: Increasing profitability through Must-Win implementationCMD 2015: Increasing profitability through Must-Win implementation
CMD 2015: Increasing profitability through Must-Win implementation
 
Case Study on Automation Capability CT ARROW
Case Study on Automation Capability CT ARROWCase Study on Automation Capability CT ARROW
Case Study on Automation Capability CT ARROW
 
Vivek M Thayyil - cv
Vivek M Thayyil - cvVivek M Thayyil - cv
Vivek M Thayyil - cv
 
Welcomm Presentation 2
Welcomm Presentation 2Welcomm Presentation 2
Welcomm Presentation 2
 
Ooredoo CMD 2015 jeremy sell
Ooredoo CMD 2015 jeremy sellOoredoo CMD 2015 jeremy sell
Ooredoo CMD 2015 jeremy sell
 
Profile - Shiloh Naidoo 16 October 2015
Profile - Shiloh Naidoo 16 October 2015Profile - Shiloh Naidoo 16 October 2015
Profile - Shiloh Naidoo 16 October 2015
 
Interactions 2015
Interactions 2015Interactions 2015
Interactions 2015
 
SWJ TECHNOLOGY Talent Acquisition
SWJ TECHNOLOGY Talent AcquisitionSWJ TECHNOLOGY Talent Acquisition
SWJ TECHNOLOGY Talent Acquisition
 
Continuous Delivery: the Strongest Link in Your Value Chain
Continuous Delivery: the Strongest Link in Your Value ChainContinuous Delivery: the Strongest Link in Your Value Chain
Continuous Delivery: the Strongest Link in Your Value Chain
 
oTMS - new market entry
oTMS - new market entryoTMS - new market entry
oTMS - new market entry
 
Mission Possible: You Can Achieve Touchless Invoice Processing
Mission Possible: You Can Achieve Touchless Invoice ProcessingMission Possible: You Can Achieve Touchless Invoice Processing
Mission Possible: You Can Achieve Touchless Invoice Processing
 

Improvement in Delivery Time of 5G HOD

  • 1. Nestlé Waters –AOA Best of the Best Awards – 2015 GB-DMAIC : Improve Delivery On Time of 5G HOD Through Reduction 20 % of Non-Delivered Cases By March 2015 Dammam-KSA
  • 2. Nestlé Waters –AOA Best of the Best Awards – 2015 Dammam Factory – Saudi Arabia Improve Delivery On Time of 5G HOD Through Reduction 20 % of Non-Delivered Cases By March 2015 1. Scale of Impact • Problem Statement:  At the end of Q3-2014, delivery complaints were the highest contributor of the ten types of market customers complaints .  Improve Delivery On Time of 5G HOD was one of the business priorities to Deliver Volumes OTIF to Support Business Growth to Delight Our Customers & Consumers . 81.9%  Delivery complaints were representing 81.9% of total market complaints during Jan-Oct 2014 with monthly average of 2006 complaints. September 15, 2014 Project Kick-off Meeting • Relevant to business:  The project scope was covering Whole Eastern Area “population of 4.5 Million” with involvement of HOD Production, Distribution Staff & Customer Service Staff noting that NCE is not yet rolled out in SC.
  • 3. Nestlé Waters –AOA Best of the Best Awards – 2015 • Improvement Quantified:  80% reduction in non-delivered cases : 61.5% reduction in missed delivery complaints FY-2015 ( From 22,331 to 8,595 ) 51% reduction in overall Dammam Consumers Complaints (CCR) FY-2015 ( From 27,625 to 13,528 ) Dammam Factory – Saudi Arabia Improve Delivery On Time of 5G HOD Through Reduction 20 % of Non-Delivered Cases By March 2015
  • 4. Nestlé Waters –AOA Best of the Best Awards – 2015 2. Effective use of NCE and problem solving methodologies Project used NCE problems solving methodologies effectively and efficiently with Involvement of more than 400 employees from cross-functional team to be aligned with Green Belt Level . Project was done OTIF with Excellent tollgate score of 98%. Dammam Factory – Saudi Arabia Improve Delivery On Time of 5G HOD Through Reduction 20 % of Non-Delivered Cases By March 2015
  • 5. Nestlé Waters –AOA Best of the Best Awards – 2015 • Impact on NCE Journey  This GB is supporting NCE Journey through involvement and engagement of SC & Customer Service beyond of manufacturing team  We have been awarded Nestlé Quality Global Gold Award -2015 “for the highest factory customers complaints reduction”. Dammam Factory – Saudi Arabia Improve Delivery On Time of 5G HOD Through Reduction 20 % of Non-Delivered Cases By March 2015
  • 6. Nestlé Waters –AOA Best of the Best Awards – 2015 3. Team work High level of involvement, engagement & teamwork enhanced in different cross- functional together with well experienced coach and high engagement of the sponsor were the keys to have the success achieved . Brainstorming & Wringing Online Coaching Sponsor-Involvement Helpers & Drivers Coaching Dammam Factory – Saudi Arabia Improve Delivery On Time of 5G HOD Through Reduction 20 % of Non-Delivered Cases By March 2015
  • 7. Nestlé Waters –AOA Best of the Best Awards – 2015 4. Implemented Actions 17 actions were implemented while the main actions with high impact are as hereunder : 1. Weekly & Monthly Meetings with drivers & helpers by distribution management team. 2. Establishment of new coding system for Non-delivered cases. 3. Daily entering & filtering" screening " on all checklists for non-delivered cases. 4. Rerouting Dammam routes to making balancing between it. 5. Create a clear communication plan between production & distribution. 6. Defensive Driving training course was delivered to drivers. 7. Creating SOP’s & SR for several activities. Dammam Factory – Saudi Arabia Improve Delivery On Time of 5G HOD Through Reduction 20 % of Non-Delivered Cases By March 2015  For more information related to project ,please access the full storyboards on I-nexus ID : 133455
  • 8. Nestlé Waters –AOA Best of the Best Awards – 2015 5. Sustainability  Solutions were implemented since January -2015, and the results are sustainable till now and control action plan was created and in place . Dammam Factory – Saudi Arabia Improve Delivery On Time of 5G HOD Through Reduction 20 % of Non-Delivered Cases By March 2015
  • 9. Nestlé Waters –AOA Best of the Best Awards – 2015 6. Creativity & Replication  “Broken down factory walls by GEMBA & Online Coaching sessions inside & outside the factory “  Establishment of a new coding system understandable by all team members with different skill levels and languages.  Replication of the project at remaining cities in eastern region areas in addition to 7 factories in AP Market.  One of the main future recommendations was using Handheld devices with barcodes reader to make more improvement. GEMBA Online Coaching DCP Dammam Factory – Saudi Arabia Improve Delivery On Time of 5G HOD Through Reduction 20 % of Non-Delivered Cases By March 2015
  • 10. “ It was an excellent opportunity and first time involvement in DMAIC & NCE which enhances our problem solving skills ,also we were able to be in contact with our customers and knowing their needs in more detailed to work on improving it .” Nestlé Waters –AOA Best of the Best Awards – 2015 “The project was impressive, it helps the team to develop and maintain a realistic and achievable delivery schedule.. The attitude of the employees to commitment has a great influence on the quality of outputs for tracking performance, better delivery efficiency and enhanced customer satisfaction “ I am confident and proud of the successful achievements of the team great efforts exerted during this short time. Remarkable results were clear in reducing non-delivered cases and customer complaints calls which led to enhancing customer satisfaction. . Process Owner Sponsor Data Entry & Customer Service- Females Dammam Factory – Saudi Arabia Improve Delivery On Time of 5G HOD Through Reduction 20 % of Non-Delivered Cases By March 2015  Consumers feedback questionnaire program was conducted at sample size of 1077 customers showed an “Excellent "satisfaction.  Nestle Waters CSI Program was conducted by Ipsos MENA at sample profile of 402 customers showed satisfaction level of 9 out of 10 “satisfied” 7. VOC “Satisfaction” – Internal & External
  • 11. Nestlé Waters –AOA Best of the Best Awards – 2015 Team party was organized and certificates of appreciation & rewards awarded for the team C E L E B R A T I O N ! ! ! Dammam Factory – Saudi Arabia Improve Delivery On Time of 5G HOD Through Reduction 20 % of Non-Delivered Cases By March 2015