SlideShare a Scribd company logo
1 of 26
KAS-2012 1
TRANSPORTATION OF
CONCRETE
K A Shah
B.Sc.(Civil Engg.) MSc.(Environment Engg.)
Ex-GM-MNC
Guest Faculty- CTE
KAS-2012 2
TRANSPORTATION OF CONCRETE
Precaution in concrete transportation:
 Homogeneity of conc. Mass is maintained
 Movement of hand trolly or truck on rough
road surface makes vibrations
 This results in deposition of heavy
aggregates at bottom of truck
 Water & cement slurry comes on top.
KAS-2012 3
METHODS OF TRANSPORTATION
1. Mortar Pan
2. Wheel barrow
3. Truck Mixer & dumpers
4. Crane, Bucket & rope way
5. Belt conveyors
6. Chutes
7. Skip & hoist
8. Transit Mixer
9. Pump & pipeline
10. Helicopter
KAS-2012 4
MORTAR PAN
 Common method in India
 More labour required
 Segregation of concrete is less
 Greater surface area of concrete is
exposed to sun, concrete dries.
KAS-2012 5
WHEEL BARROW
 When transportation of concrete is at
ground level.
 Movement of wheel on rough road
surface, segregates concrete.
 Some wheel barrows have pneumatic
wheel to reduce vibration
KAS-2012 6
CRANE
 Used for transporting concrete above
ground level.
 For high rise buildings.
 Cranes are fast
 Can move horizontally & vertically
 Concrete in skip discharge from bottom
 In bucket concrete is discharged by tilting.
KAS-2012 7
CONCRETE TRANSPORT BY CRANE-
VIDEO
Pouring Concrete-Cement Truck-Crane-Construction Excavation Site.flv
KAS-2012 8
BUCKET & ROPEWAY
Use for construction in:
 Valley
 Bridge pier in river
 Dam
Advantage:
Concrete is not exposed to sun or air & no
loss of water.
KAS-2012 9
ROPEWAY-VIDEO
Package
KAS-2012 10
Truck Mixer & dumpers
 Used for large concrete works.
 Can travel any part of site.
 Dumpers - 2-3 M3
Capacity
 Trucks – 4 M3
Capacity
 Bottom surface of truck is kept wet
 Top of truck is covered to prevent
evaporation
KAS-2012 11
BELT CONVEYOR-VIDEO
Package
KAS-2012 12
BELT CONVEYORS
 Limited use in construction
Advantages:
 Can transport large volume
 Very quick
 Can go where access is limited
Disadvantages :
 On steep slope concrete segregates.
 Exposed to sun for long time.
KAS-2012 13
CHUTE
 For transporting from ground level to lower
level. (basement etc).
 Used where labour can not reach due to
less space in trench etc.
 Made of metal
 Slope should not be < 1 vertical : 2.5
horizontal.
KAS-2012 14
SKIP & HOIST -VIDEO
Package
KAS-2012 15
SKIP & HOIST
 Labour can go upto 3rd or 4th floors.
 So skip is used for transport vertically up
(in multistory building).
 Skip travels on vertical rail.
 Skip can discharge manually or
automatically.
KAS-2012 16
TRANSIT MIXER
KAS-2012 17
TRANSIT MIXER
 Used for long distance travel in RMC plant.
 Concrete is continuously agitated in truck drum
(2 – 6 rpm).
 Also transported mix in dry condition and water
is added on reaching the destination.
 Wet Mix in truck must reach site in 1- 1.5 hours.
 Pumps are also fitted on truck mixer to
discharge concrete.
KAS-2012 18
PUMPS & PIPELINE
 Most popular method
 Reliable & good quality pumps are used.
 Mostly operated by diesel.
 Concrete is placed in collecting hopper.
 Rotating blades in hopper pushes concrete
towards pipe.
 Vacume in hose pipe (600 mm Hg)
 Rotating rollers in pump chambers squeeze the
concrete in pipe and flow of concrete is started.
 Concrete is discharged from other end of hose
pipe.
 Concrete can be pumped upto 400 m height and
2000 m distance.
KAS-2012 19
SECTION OF PUMP
KAS-2012 20
PIPELINE
Pipeline should :
 Have correct diameter as per pump
pressure. (generally 125 mm)
 Have sufficient thickness
 Good couplings
 Poor pipeline can cause blockage.
KAS-2012 21
PIPELINE
 Thumb rule : For 30 M3
/hr concrete and
200 m length, dia should be 100 mm.
 Length > 500 m then dia = 150 mm.
 Dia = 3 to 4 times the size of aggregate
 Leaky pipe & coupling result in escape of
water /air & finally block the concrete.
 Vertical pipe should good otherwise
difficult to change at height.
 Pump is kept at distance from building
about 15 % of vertical length.
KAS-2012 22
CONCRETE FLOW IN PIPE
KAS-2012 23
PUMPABLE CONCRETE
 Concrete which can be pushed through a pipeline is
called pumpable concrete.
 Friction between pipe wall and concrete is less.
 Concrete flows in the form of plug which is separated
from pipe wall by a thin layer of lubricating cement paste.
 Flow resistant must be < pump pressure.
 If the concrete is more wet then water comes out of mix
which makes more resistance to flow.
 Stiff and also very wet concrete is not pumpable.
KAS-2012 24
Design of pumpable concrete
 Concrete Mix is so designed that all material remain
together.
 Mix must make redial movement of grout to maintain
lubricating paste.
 Mix should be deformed at bends
 Cement & fine particles (0.25 mm size) are important for
good flow.
 350 to 400 Kg/ M3
of fine particles are necessary for flow.
 Slump of pumpable concrete is above 75 mm.
KAS-2012 25
PROBLEMS IN PUMPING
 Blockage in pipe
 Pipe should be cleaned after each day
operation
 Blockage can be cleaned by forward-
backward pumping.
 Tapping pipe with hammer
 Clean pipe with rod or sponge ball pushed
by compressed air.
KAS-2012 26
THANKS

More Related Content

What's hot

Admixture of concrete
Admixture of concreteAdmixture of concrete
Admixture of concreteLavanya Singh
 
Quality control of concrete
Quality control of concreteQuality control of concrete
Quality control of concreteGaurang Kakadiya
 
High density concrete, high strength concrete and high performance concrete.
High density concrete, high strength concrete and high performance concrete.High density concrete, high strength concrete and high performance concrete.
High density concrete, high strength concrete and high performance concrete.shebina a
 
type of aggregate
type of aggregatetype of aggregate
type of aggregateAnup Kude
 
Factors affecting the strenght of concrete
Factors affecting the strenght of concreteFactors affecting the strenght of concrete
Factors affecting the strenght of concreteMUBARAKALI111
 
Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)Make Mannan
 
Concrete,batc,mix,trans,copaction etc
Concrete,batc,mix,trans,copaction etcConcrete,batc,mix,trans,copaction etc
Concrete,batc,mix,trans,copaction etcZainul Abideen
 
Manufacturing of concrete
Manufacturing of  concreteManufacturing of  concrete
Manufacturing of concreteBasirat Amir
 
Test on fresh concrete and harden concrete
Test on fresh concrete and harden concreteTest on fresh concrete and harden concrete
Test on fresh concrete and harden concreteMOHAMMED JIRUWALA
 
Workability of Concrete.ppt
Workability of Concrete.pptWorkability of Concrete.ppt
Workability of Concrete.pptRaju S
 

What's hot (20)

Admixture of concrete
Admixture of concreteAdmixture of concrete
Admixture of concrete
 
Curing of concrete
Curing of concreteCuring of concrete
Curing of concrete
 
Introduction to concrete
Introduction to concreteIntroduction to concrete
Introduction to concrete
 
Quality control of concrete
Quality control of concreteQuality control of concrete
Quality control of concrete
 
High density concrete, high strength concrete and high performance concrete.
High density concrete, high strength concrete and high performance concrete.High density concrete, high strength concrete and high performance concrete.
High density concrete, high strength concrete and high performance concrete.
 
type of aggregate
type of aggregatetype of aggregate
type of aggregate
 
Factors affecting the strenght of concrete
Factors affecting the strenght of concreteFactors affecting the strenght of concrete
Factors affecting the strenght of concrete
 
Vacuum dewatering
Vacuum dewateringVacuum dewatering
Vacuum dewatering
 
Concrete Technology Unit I
Concrete Technology Unit IConcrete Technology Unit I
Concrete Technology Unit I
 
Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)
 
Hydration of cement
Hydration of cementHydration of cement
Hydration of cement
 
Fresh and harden properties of concrete
Fresh and harden properties of concreteFresh and harden properties of concrete
Fresh and harden properties of concrete
 
Foundation ppt
Foundation pptFoundation ppt
Foundation ppt
 
Concrete,batc,mix,trans,copaction etc
Concrete,batc,mix,trans,copaction etcConcrete,batc,mix,trans,copaction etc
Concrete,batc,mix,trans,copaction etc
 
Manufacturing of concrete
Manufacturing of  concreteManufacturing of  concrete
Manufacturing of concrete
 
Mix design-ppt
Mix design-pptMix design-ppt
Mix design-ppt
 
Hydration of cement
Hydration of cementHydration of cement
Hydration of cement
 
Different types of pile
Different types of pile Different types of pile
Different types of pile
 
Test on fresh concrete and harden concrete
Test on fresh concrete and harden concreteTest on fresh concrete and harden concrete
Test on fresh concrete and harden concrete
 
Workability of Concrete.ppt
Workability of Concrete.pptWorkability of Concrete.ppt
Workability of Concrete.ppt
 

Viewers also liked

A presentation of transportation of concrete
A presentation of transportation of concreteA presentation of transportation of concrete
A presentation of transportation of concretePritam Dubey
 
Process of manufacture of concrete
Process of manufacture of  concreteProcess of manufacture of  concrete
Process of manufacture of concreteManpreet Singh
 
A POWERPOINT PRESENTAION ON READY-MIX CONCRETE
A POWERPOINT PRESENTAION ON READY-MIX CONCRETEA POWERPOINT PRESENTAION ON READY-MIX CONCRETE
A POWERPOINT PRESENTAION ON READY-MIX CONCRETEkuntansourav
 
Concrete- Classification,Properties and Testing
Concrete- Classification,Properties and TestingConcrete- Classification,Properties and Testing
Concrete- Classification,Properties and TestingRishabh Lala
 
Detailed ppt on Curing of concrete
Detailed ppt on Curing of concreteDetailed ppt on Curing of concrete
Detailed ppt on Curing of concreteRushabh shah
 
Design of reinforced concrete members lecture notes - er. k m pathan
Design of reinforced concrete members   lecture notes - er. k m pathanDesign of reinforced concrete members   lecture notes - er. k m pathan
Design of reinforced concrete members lecture notes - er. k m pathanSayyad Wajed Ali
 
DIESEL LOCOMOTIVE WORKS, VARANASI, FOR CIVIL ENGG.
DIESEL LOCOMOTIVE WORKS, VARANASI, FOR CIVIL ENGG.DIESEL LOCOMOTIVE WORKS, VARANASI, FOR CIVIL ENGG.
DIESEL LOCOMOTIVE WORKS, VARANASI, FOR CIVIL ENGG.SHASHANK SHEKHAR
 
Anuj sewage treatment plant
Anuj sewage treatment plantAnuj sewage treatment plant
Anuj sewage treatment plantanuj110
 
traffic traffic egg.
 traffic traffic egg. traffic traffic egg.
traffic traffic egg.anuj110
 
curing of concrete
curing of concrete curing of concrete
curing of concrete Rushabh shah
 
Concrete Detail And Commentary
Concrete Detail And CommentaryConcrete Detail And Commentary
Concrete Detail And Commentarylfissel
 
CE 6506 CONSTRUCTION TECHNIQUES EQUIPMENTS & PRACTICE
CE 6506 CONSTRUCTION  TECHNIQUES  EQUIPMENTS  & PRACTICE CE 6506 CONSTRUCTION  TECHNIQUES  EQUIPMENTS  & PRACTICE
CE 6506 CONSTRUCTION TECHNIQUES EQUIPMENTS & PRACTICE Anbarasan Muthaiyah
 
Soil nailing ppt by ankush choudhury
Soil nailing ppt by ankush choudhurySoil nailing ppt by ankush choudhury
Soil nailing ppt by ankush choudhuryAnkush Choudhury
 

Viewers also liked (20)

A presentation of transportation of concrete
A presentation of transportation of concreteA presentation of transportation of concrete
A presentation of transportation of concrete
 
Process of manufacture of concrete
Process of manufacture of  concreteProcess of manufacture of  concrete
Process of manufacture of concrete
 
Batching and mixing
Batching and mixingBatching and mixing
Batching and mixing
 
A POWERPOINT PRESENTAION ON READY-MIX CONCRETE
A POWERPOINT PRESENTAION ON READY-MIX CONCRETEA POWERPOINT PRESENTAION ON READY-MIX CONCRETE
A POWERPOINT PRESENTAION ON READY-MIX CONCRETE
 
Concrete- Classification,Properties and Testing
Concrete- Classification,Properties and TestingConcrete- Classification,Properties and Testing
Concrete- Classification,Properties and Testing
 
Detailed ppt on Curing of concrete
Detailed ppt on Curing of concreteDetailed ppt on Curing of concrete
Detailed ppt on Curing of concrete
 
Concrete technology
Concrete technologyConcrete technology
Concrete technology
 
Concrete Admixtures
 Concrete Admixtures Concrete Admixtures
Concrete Admixtures
 
Concrete
ConcreteConcrete
Concrete
 
IS 10262
IS 10262IS 10262
IS 10262
 
Pumping of concrete
Pumping of concretePumping of concrete
Pumping of concrete
 
Design of reinforced concrete members lecture notes - er. k m pathan
Design of reinforced concrete members   lecture notes - er. k m pathanDesign of reinforced concrete members   lecture notes - er. k m pathan
Design of reinforced concrete members lecture notes - er. k m pathan
 
DIESEL LOCOMOTIVE WORKS, VARANASI, FOR CIVIL ENGG.
DIESEL LOCOMOTIVE WORKS, VARANASI, FOR CIVIL ENGG.DIESEL LOCOMOTIVE WORKS, VARANASI, FOR CIVIL ENGG.
DIESEL LOCOMOTIVE WORKS, VARANASI, FOR CIVIL ENGG.
 
Cement Sectore Report - December 2016
Cement Sectore Report - December 2016Cement Sectore Report - December 2016
Cement Sectore Report - December 2016
 
Anuj sewage treatment plant
Anuj sewage treatment plantAnuj sewage treatment plant
Anuj sewage treatment plant
 
traffic traffic egg.
 traffic traffic egg. traffic traffic egg.
traffic traffic egg.
 
curing of concrete
curing of concrete curing of concrete
curing of concrete
 
Concrete Detail And Commentary
Concrete Detail And CommentaryConcrete Detail And Commentary
Concrete Detail And Commentary
 
CE 6506 CONSTRUCTION TECHNIQUES EQUIPMENTS & PRACTICE
CE 6506 CONSTRUCTION  TECHNIQUES  EQUIPMENTS  & PRACTICE CE 6506 CONSTRUCTION  TECHNIQUES  EQUIPMENTS  & PRACTICE
CE 6506 CONSTRUCTION TECHNIQUES EQUIPMENTS & PRACTICE
 
Soil nailing ppt by ankush choudhury
Soil nailing ppt by ankush choudhurySoil nailing ppt by ankush choudhury
Soil nailing ppt by ankush choudhury
 

Similar to Transportation of Concrete - Notes for Civil engineering Students

Construction management
Construction managementConstruction management
Construction managementTanzil Faraz
 
Highway construction PPT
Highway construction PPTHighway construction PPT
Highway construction PPTVikas Sukhwal
 
Preperation of concrete
Preperation of concretePreperation of concrete
Preperation of concreteRajat Nainwal
 
RIGID PAVEMENT -ANIL GUPTA (P.W.D)
RIGID PAVEMENT -ANIL GUPTA (P.W.D)RIGID PAVEMENT -ANIL GUPTA (P.W.D)
RIGID PAVEMENT -ANIL GUPTA (P.W.D)Anil Gupta
 
CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADGLA University
 
MD NEHAL 8TH SEM PPT- 2pptx.pptx
MD NEHAL 8TH SEM PPT- 2pptx.pptxMD NEHAL 8TH SEM PPT- 2pptx.pptx
MD NEHAL 8TH SEM PPT- 2pptx.pptxnehal103998
 
FOUNDATION ENGINEERING.pptx
FOUNDATION ENGINEERING.pptxFOUNDATION ENGINEERING.pptx
FOUNDATION ENGINEERING.pptxDolanGhosh4
 
foundation and pavement lec 3 Road Construction Methods and Techniques.pptx
foundation and pavement lec 3 Road Construction Methods and Techniques.pptxfoundation and pavement lec 3 Road Construction Methods and Techniques.pptx
foundation and pavement lec 3 Road Construction Methods and Techniques.pptxfazl ullah
 
Manufacturing process of concrete (for civil engineering)
Manufacturing process of concrete (for civil engineering) Manufacturing process of concrete (for civil engineering)
Manufacturing process of concrete (for civil engineering) laxman singh
 
Aryan k tranning file road ppt 07
Aryan k tranning file road ppt 07Aryan k tranning file road ppt 07
Aryan k tranning file road ppt 07aryan kumar
 
ppt on pwd cement concrete road pavement
ppt on pwd cement concrete road pavementppt on pwd cement concrete road pavement
ppt on pwd cement concrete road pavementNIWASHISH VISWAS
 
ROAD CONSTRUCTION METHOD final
ROAD CONSTRUCTION METHOD finalROAD CONSTRUCTION METHOD final
ROAD CONSTRUCTION METHOD finalAvneet Grewall
 
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURESProject:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURESMalay Talaviya
 
Construction of Flexible Pavements Using Plastic Wastes
Construction of Flexible Pavements Using Plastic WastesConstruction of Flexible Pavements Using Plastic Wastes
Construction of Flexible Pavements Using Plastic WastesRaghvendraBajpai3
 
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring MachinesPile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring MachinesPrerak Ka.Patel
 

Similar to Transportation of Concrete - Notes for Civil engineering Students (20)

Construction management
Construction managementConstruction management
Construction management
 
Highway construction PPT
Highway construction PPTHighway construction PPT
Highway construction PPT
 
Preperation of concrete
Preperation of concretePreperation of concrete
Preperation of concrete
 
RIGID PAVEMENT -ANIL GUPTA (P.W.D)
RIGID PAVEMENT -ANIL GUPTA (P.W.D)RIGID PAVEMENT -ANIL GUPTA (P.W.D)
RIGID PAVEMENT -ANIL GUPTA (P.W.D)
 
Anshuman.pptx
Anshuman.pptxAnshuman.pptx
Anshuman.pptx
 
Ready Mix Concrete and Self Compacting concrete by Dr.Vinay Kumar B M
Ready Mix Concrete and Self Compacting concrete by Dr.Vinay Kumar B MReady Mix Concrete and Self Compacting concrete by Dr.Vinay Kumar B M
Ready Mix Concrete and Self Compacting concrete by Dr.Vinay Kumar B M
 
CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROAD
 
MD NEHAL 8TH SEM PPT- 2pptx.pptx
MD NEHAL 8TH SEM PPT- 2pptx.pptxMD NEHAL 8TH SEM PPT- 2pptx.pptx
MD NEHAL 8TH SEM PPT- 2pptx.pptx
 
FOUNDATION ENGINEERING.pptx
FOUNDATION ENGINEERING.pptxFOUNDATION ENGINEERING.pptx
FOUNDATION ENGINEERING.pptx
 
foundation and pavement lec 3 Road Construction Methods and Techniques.pptx
foundation and pavement lec 3 Road Construction Methods and Techniques.pptxfoundation and pavement lec 3 Road Construction Methods and Techniques.pptx
foundation and pavement lec 3 Road Construction Methods and Techniques.pptx
 
Manufacturing process of concrete (for civil engineering)
Manufacturing process of concrete (for civil engineering) Manufacturing process of concrete (for civil engineering)
Manufacturing process of concrete (for civil engineering)
 
Aryan k tranning file road ppt 07
Aryan k tranning file road ppt 07Aryan k tranning file road ppt 07
Aryan k tranning file road ppt 07
 
ppt on pwd cement concrete road pavement
ppt on pwd cement concrete road pavementppt on pwd cement concrete road pavement
ppt on pwd cement concrete road pavement
 
ROAD CONSTRUCTION METHOD final
ROAD CONSTRUCTION METHOD finalROAD CONSTRUCTION METHOD final
ROAD CONSTRUCTION METHOD final
 
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURESProject:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
 
SACHIN CIVIL.docx
SACHIN CIVIL.docxSACHIN CIVIL.docx
SACHIN CIVIL.docx
 
Construction of Flexible Pavements Using Plastic Wastes
Construction of Flexible Pavements Using Plastic WastesConstruction of Flexible Pavements Using Plastic Wastes
Construction of Flexible Pavements Using Plastic Wastes
 
Highway report
Highway reportHighway report
Highway report
 
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring MachinesPile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
Pile boring/ Driving Equipment, Concrete Batching plant, Tunnel Boring Machines
 
road construction
road constructionroad construction
road construction
 

More from Kezar Ali. Shah

Design & construction of secure waste landfill
Design & construction of secure waste landfillDesign & construction of secure waste landfill
Design & construction of secure waste landfillKezar Ali. Shah
 
Concrete design mix (ss)
Concrete design mix (ss)Concrete design mix (ss)
Concrete design mix (ss)Kezar Ali. Shah
 
Environment Clearance Procedure-India
Environment Clearance Procedure-IndiaEnvironment Clearance Procedure-India
Environment Clearance Procedure-IndiaKezar Ali. Shah
 
Road Safety Awareness (india)
Road Safety Awareness (india)Road Safety Awareness (india)
Road Safety Awareness (india)Kezar Ali. Shah
 

More from Kezar Ali. Shah (6)

Design & construction of secure waste landfill
Design & construction of secure waste landfillDesign & construction of secure waste landfill
Design & construction of secure waste landfill
 
Form Work
Form Work Form Work
Form Work
 
Damp Proof Course
Damp Proof Course Damp Proof Course
Damp Proof Course
 
Concrete design mix (ss)
Concrete design mix (ss)Concrete design mix (ss)
Concrete design mix (ss)
 
Environment Clearance Procedure-India
Environment Clearance Procedure-IndiaEnvironment Clearance Procedure-India
Environment Clearance Procedure-India
 
Road Safety Awareness (india)
Road Safety Awareness (india)Road Safety Awareness (india)
Road Safety Awareness (india)
 

Recently uploaded

chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01KreezheaRecto
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Standamitlee9823
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...tanu pandey
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 

Recently uploaded (20)

chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 

Transportation of Concrete - Notes for Civil engineering Students

  • 1. KAS-2012 1 TRANSPORTATION OF CONCRETE K A Shah B.Sc.(Civil Engg.) MSc.(Environment Engg.) Ex-GM-MNC Guest Faculty- CTE
  • 2. KAS-2012 2 TRANSPORTATION OF CONCRETE Precaution in concrete transportation:  Homogeneity of conc. Mass is maintained  Movement of hand trolly or truck on rough road surface makes vibrations  This results in deposition of heavy aggregates at bottom of truck  Water & cement slurry comes on top.
  • 3. KAS-2012 3 METHODS OF TRANSPORTATION 1. Mortar Pan 2. Wheel barrow 3. Truck Mixer & dumpers 4. Crane, Bucket & rope way 5. Belt conveyors 6. Chutes 7. Skip & hoist 8. Transit Mixer 9. Pump & pipeline 10. Helicopter
  • 4. KAS-2012 4 MORTAR PAN  Common method in India  More labour required  Segregation of concrete is less  Greater surface area of concrete is exposed to sun, concrete dries.
  • 5. KAS-2012 5 WHEEL BARROW  When transportation of concrete is at ground level.  Movement of wheel on rough road surface, segregates concrete.  Some wheel barrows have pneumatic wheel to reduce vibration
  • 6. KAS-2012 6 CRANE  Used for transporting concrete above ground level.  For high rise buildings.  Cranes are fast  Can move horizontally & vertically  Concrete in skip discharge from bottom  In bucket concrete is discharged by tilting.
  • 7. KAS-2012 7 CONCRETE TRANSPORT BY CRANE- VIDEO Pouring Concrete-Cement Truck-Crane-Construction Excavation Site.flv
  • 8. KAS-2012 8 BUCKET & ROPEWAY Use for construction in:  Valley  Bridge pier in river  Dam Advantage: Concrete is not exposed to sun or air & no loss of water.
  • 10. KAS-2012 10 Truck Mixer & dumpers  Used for large concrete works.  Can travel any part of site.  Dumpers - 2-3 M3 Capacity  Trucks – 4 M3 Capacity  Bottom surface of truck is kept wet  Top of truck is covered to prevent evaporation
  • 12. KAS-2012 12 BELT CONVEYORS  Limited use in construction Advantages:  Can transport large volume  Very quick  Can go where access is limited Disadvantages :  On steep slope concrete segregates.  Exposed to sun for long time.
  • 13. KAS-2012 13 CHUTE  For transporting from ground level to lower level. (basement etc).  Used where labour can not reach due to less space in trench etc.  Made of metal  Slope should not be < 1 vertical : 2.5 horizontal.
  • 14. KAS-2012 14 SKIP & HOIST -VIDEO Package
  • 15. KAS-2012 15 SKIP & HOIST  Labour can go upto 3rd or 4th floors.  So skip is used for transport vertically up (in multistory building).  Skip travels on vertical rail.  Skip can discharge manually or automatically.
  • 17. KAS-2012 17 TRANSIT MIXER  Used for long distance travel in RMC plant.  Concrete is continuously agitated in truck drum (2 – 6 rpm).  Also transported mix in dry condition and water is added on reaching the destination.  Wet Mix in truck must reach site in 1- 1.5 hours.  Pumps are also fitted on truck mixer to discharge concrete.
  • 18. KAS-2012 18 PUMPS & PIPELINE  Most popular method  Reliable & good quality pumps are used.  Mostly operated by diesel.  Concrete is placed in collecting hopper.  Rotating blades in hopper pushes concrete towards pipe.  Vacume in hose pipe (600 mm Hg)  Rotating rollers in pump chambers squeeze the concrete in pipe and flow of concrete is started.  Concrete is discharged from other end of hose pipe.  Concrete can be pumped upto 400 m height and 2000 m distance.
  • 20. KAS-2012 20 PIPELINE Pipeline should :  Have correct diameter as per pump pressure. (generally 125 mm)  Have sufficient thickness  Good couplings  Poor pipeline can cause blockage.
  • 21. KAS-2012 21 PIPELINE  Thumb rule : For 30 M3 /hr concrete and 200 m length, dia should be 100 mm.  Length > 500 m then dia = 150 mm.  Dia = 3 to 4 times the size of aggregate  Leaky pipe & coupling result in escape of water /air & finally block the concrete.  Vertical pipe should good otherwise difficult to change at height.  Pump is kept at distance from building about 15 % of vertical length.
  • 23. KAS-2012 23 PUMPABLE CONCRETE  Concrete which can be pushed through a pipeline is called pumpable concrete.  Friction between pipe wall and concrete is less.  Concrete flows in the form of plug which is separated from pipe wall by a thin layer of lubricating cement paste.  Flow resistant must be < pump pressure.  If the concrete is more wet then water comes out of mix which makes more resistance to flow.  Stiff and also very wet concrete is not pumpable.
  • 24. KAS-2012 24 Design of pumpable concrete  Concrete Mix is so designed that all material remain together.  Mix must make redial movement of grout to maintain lubricating paste.  Mix should be deformed at bends  Cement & fine particles (0.25 mm size) are important for good flow.  350 to 400 Kg/ M3 of fine particles are necessary for flow.  Slump of pumpable concrete is above 75 mm.
  • 25. KAS-2012 25 PROBLEMS IN PUMPING  Blockage in pipe  Pipe should be cleaned after each day operation  Blockage can be cleaned by forward- backward pumping.  Tapping pipe with hammer  Clean pipe with rod or sponge ball pushed by compressed air.