SlideShare a Scribd company logo
1 of 7
Download to read offline
CHAPTER 6: Capital Budgeting
Responses to Questions:
1. Operations management involves decisions to invest in plant and
machinery – new plants at new locations and replacement of the old.
These are decisions regarding allocation of available funds i.e. Capital
budgeting.
2. Since ‘sunk cost’ is, by definition, an entity that does not affect present
decisions being made for the future, it does not affect the capital
budgeting process.
3. Depreciation is a notional allocation of capital cost used in tax calculations
and in profit after tax calculations. Therefore while calculating operational
cash flows of a project, depreciation may be used as follows:
Operational cash flow = Profit after tax + Interest on long-term borrowings
(1-tax rate) + Depreciation + Other non-cash charges
(Note: ‘Other non-cash charges’ include amortization of patent cost and
write-off of preliminary expenses)
Operational cash flows are vital figures in the Capital budgeting decisions.
4. These have been mentioned in the chapter.
5. An explicit measure/criterion like NPV would only be relevant. IRR will not
be relevant, as it is only a ‘rate’.
6. IRR is the rate of return on unrecovered balance. This is one
interpretation. Another interpretation is that IRR represents the compound
rate of return or yield earned on initial investment for the life of the project.
The second interpretation of IRR is based on the assumption that the
intermediate inflows can be re-invested at IRR. However, it may not be
possible for a firm to re-invest intermediate funds at IRR. The first
interpretation is more realistic.
7. One incorporates risk into the discount rate, whereas the other reduces
the NPV by using a coefficient. The second method is more flexible; if in
the 10th
year the income is going to be more certain than the income in the
5th
year, the risk equivalence coefficient in the 10th
year will be higher than
that for the 5th
year. The first method classifies projects into different risk
categories, unlike the second method.
Their similarity is that both are only approximations of the risk complexion
of any project and are one-dimensional.
2
8. a) The investment is paid back after 4 years (years have been rounded
off). Payback period = 4 years.
b) NPV = - 10000 + 3000 + 3000 + 3000 + 3000 + 3000
(1+0.1) (1+0.1)2
(1+0.1)3
(1+0.1)4
(1+0.1)5
= -10,000 + 2727 + 2479 + 2254 + 2049 + 1863
= Rs. 1,372
c) To calculate IRR, we equate investment and discounted cash flows for
the five years (life as given):
10000 = 3000 + 3000 + 3000 + 3000 + 3000
(1+ i) (1+i)2
(1+i)3
(1+i)4
(1+i)5
The value of ‘i’ i.e. IRR is 15.2 per cent approximately.
9. (a) Project X: NPV = -700 + 450 + 450
(1+0.1) (1+0.1)2
= -700 + 409 + 372
= 81.
Project Y: NPV = -7,000 + 4,100 + 4,100
(1+0.1) (1+0.1)2
= -7,000 + 3,272 + 3388
= 115.
(b) Project X: IRR = 18.4 % & Project Y: IRR = 11.6 % (approximately).
(c) Under ‘no capital rationing’, select Y between the two mutually
exclusive projects as Y’s NPV is higher than that of Project X.
(d) The selection between the two will, in addition to NPV, depend upon
the budget constraint.
If budget < 7,000 : select X
If budget ≥ 7,000 : select Y
10. We shall compare the NPVs and choose one of the two projects.
Project A : NPV = -100,000 + 30000 + 35000 + 40000 + 45000
(1+0.1) (1+0.1)2
(1+0.1)3
(1+0.1)4
= -100,000 + 27273 + 28926 + 30052 + 30736
= 16,987
3
Project B: = -100,000 + 15000 + 17500 + 20000 + 22500 + 25000
(1.1) (1.1)2
(1.1)3
(1.1)4
(1.1)5
27.500 + 30000 + 32500
(1.1)6
(1.1)7
(1.1)8
= -1,00,000 + 13636 + 14463 + 15026 + 15368 + 15523 +
15523 + 15395 + 15161
= 20,095
Since project B has a larger NPV, we choose project B.
11. With 12 total periods, there are 12 different series of outflows
corresponding to different periods of replacement. Each series can be
considered as a project and these 12 projects could be compared for
their NPV.
However each project has a different life. Therefore, in order to bring in
uniformity, we need to convert the NPVs into uniform annual cash flows
(uniform annual series or UAS as it is known in the literature).
UAS = NPV
PVFA
(where PVFA is Present Value Factor for Annuity. PVFAs are given for
different discount rates and different lives in readily available tables.)
Let us show, as an example, the comparison of two replacement periods
viz. 5 years and 8 years.
NPV5 = -1600 - 50__ - 70___ - 90___ - 120___ - 150
(1.1) (1.1) 2
(1.1) 3
(1.1) 4
(1.1) 5
= -1600 – 45.55 – 57.85 – 67.62 – 81.96 – 93.14
= -1946.02
NPV8
=
-1600 - 50__ - 70___ - 90___ - 120___ - 150 - 190 - 230 - 270_
(1.1) (1.1) 2
(1.1) 3
(1.1) 4
(1.1) 5
(1.1) 6
(1.1) 7
(1.1) 8
= -2297.26
PVFA for 5 years = 3.7908 for i = 10 %.
PVFA for 8 years = 5.3349 for i = 10 %.
UAS5 = -1946.02 = - 513.35
3.7908
UAS8 = -2297.26 = - 430.61
5.3349
4
Between these two replacement periods, the period of 8 years is chosen
as it has less negative UAS.
Such comparisons should be made between the 12 different possibilities
of replacement periods. The least negative UAS replacement period
should be the optimal replacement cycle.
Note that the revenues have not been mentioned in this problem. So
essentially we had to compare all negative flows (outflows).
12. We have the following relationship in which ‘i’ (IRR) is to be calculated:
25000 = 20000 + 10000 – 10000 + 15000 + 10000
(1+i) (1+i)2
(1+i)3
(1+i)4
(1+i)5
Let us try i = 0.30. It gives:
25000 = 15384 + 5917 – 4552 + 5252 + 2693
= 246494
This is very close. The IRR could be a little lower; perhaps, we could try
i= 0.29. You may try and verify.
Although there are two changes in sign, there is only one IRR (Reader
may verify). ‘n’ changes in sign is only a necessary, not sufficient,
condition for ‘n’ positive roots (IRRs) to the polynomial.
13. Projects in the social sector may be selected even if they have low
IRR. One is not looking for financial performance in this sector; instead
one is looking for a good ‘economic’ performance, i.e. the social cost
benefit analysis should indicate a clear benefit to the society.
Moreover, many social sector projects have a very long gestation
period. For instance, the work done in the primary and secondary
schooling may show results after nearly a generation.
14. ‘Risk’ in the context of social sector amounts to the long term costs to
the society. Not all cost components can be quantified. Many are in the
qualitative realm. Social sector projects are not entirely amenable to a
mathematical analysis.
5
CHAPTER 6: Capital Budgeting
Objective Questions:
1. Merit of the ‘Pay-back Period’ criterion to appraise projects is:
a. it does not discount the cost and income flows.
b. it assumes the same value of money over the different periods.
√c. it implicitly covers risk.
d. none of the above.
2. The project appraisal method that does not depend on the method of
depreciation used for tax purposes is:
a. NPV
b. IRR
c. PI
√d. none of the above
3. Mutually exclusive projects are best selected based upon:
√a. NPV
b. IRR
c. Capital rationing
d. none of the above
4. An investment that pays a fixed number of Rupees per year for a limited
number of years is called:
a. a good investment
b. an NPV
c. a perpetuity
√ d. an annuity
5. A project involved an initial investment of Rs. 5 crore. If the NPV of the
project is Rs. 10 crore, the Profitability Index is:
√ a. 3.0
b. 2.0
c. 1.0
d. 0.5
6. Different discount rates can be used for different years under:
√ a. NPV
b. IRR
c. Payback period
d. all of the above
6
7. Linear programming is used in project appraisal in cases where:
a. risk is being considered.
b. projects are mutually exclusive
√c. capital is rationed
d. none of the above
8. A bio-tech plant has an initial investment of Rs. 200 crore. The benefits,
before depreciation and taxes, are estimated at Rs. 70 crore per year for
the next 10 years which is the life of the plant. If the depreciation is on a
straight line basis for the life of the plant and if there is no salvage value
for the plant, what is the NPV at a 15 per cent required rate of return?
Assume the taxes to be nil.
a. Rs. 551 crore
√b. Rs. 51 crore
c. Rs. 5.1 crore
d. Rs.140 crore
9. For the above problem, the Payback period is :
a. 2 years
b. 3 years
√ c. 4 years
d. 5 years
10 For the above problem, the Profitability Index is (roughly):
a. 2.5
b. 1.25
c. 0.50
√ d. 0.25
11. Sainath & Co. is considering investment in a new machine costing Rs.
1,00,000, replacing the existing old machine. The old machine was bought
5 years ago for Rs. 40,000 and has a present salvage value of Rs. 20,000.
If Sainath decides to replace the old machine by the new, then at the
required rate of return of 10 per cent the net investment now would be:
a. Rs 32,211
b. Rs 67, 789
c. Rs 75,164
√d. Rs 80,000
7
12. A machine in a factory costs Rs 2 million and lasts for 10 years. What
should be the minimal cost saving per year in order to make the purchase
of the machine worthwhile if the cost of capital is 15 per cent and the tax
rate is 50 per cent?
a. Rs. 0.2 million approximately
b. Rs. 0.4 million approximately
√ c. Rs. 0.8 million approximately
d. Rs. 0.1 million approximately
13. Service sector projects may be appraised by using:
a. NPV criterion
b. IRR criterion
c. PI criterion
√d. all of the above

More Related Content

What's hot

Capital budgeting the basics-2
Capital budgeting the basics-2Capital budgeting the basics-2
Capital budgeting the basics-2Junaid Alam
 
8. Rate of return analysis
8. Rate of return analysis8. Rate of return analysis
8. Rate of return analysisMohsin Siddique
 
Chapter 16 depreciation methods
Chapter 16   depreciation methodsChapter 16   depreciation methods
Chapter 16 depreciation methodsBich Lien Pham
 
Chapter 12 independent projects & budget limitation
Chapter 12   independent projects & budget limitationChapter 12   independent projects & budget limitation
Chapter 12 independent projects & budget limitationBich Lien Pham
 
Chapter 17 after-tax economic analysis
Chapter 17   after-tax economic analysisChapter 17   after-tax economic analysis
Chapter 17 after-tax economic analysisBich Lien Pham
 
Making capital investment decisions
Making capital investment decisionsMaking capital investment decisions
Making capital investment decisionsRahmatia Azzindani
 
4 interest and equivalence
4 interest and equivalence4 interest and equivalence
4 interest and equivalenceMohsin Siddique
 
Chapter 7 ror analysis for a single alternative
Chapter 7   ror analysis for a single alternativeChapter 7   ror analysis for a single alternative
Chapter 7 ror analysis for a single alternativeBich Lien Pham
 
Chapter 10 making choices & marr
Chapter 10   making choices & marrChapter 10   making choices & marr
Chapter 10 making choices & marrBich Lien Pham
 
Chapter 3 combining factors
Chapter 3   combining factorsChapter 3   combining factors
Chapter 3 combining factorsBich Lien Pham
 
Chapter 15 cost estimation
Chapter 15   cost estimationChapter 15   cost estimation
Chapter 15 cost estimationBich Lien Pham
 
Chapter 8 ror analysis for multiple alternatives
Chapter 8   ror analysis for multiple alternativesChapter 8   ror analysis for multiple alternatives
Chapter 8 ror analysis for multiple alternativesBich Lien Pham
 

What's hot (15)

Capital budgeting the basics-2
Capital budgeting the basics-2Capital budgeting the basics-2
Capital budgeting the basics-2
 
8. Rate of return analysis
8. Rate of return analysis8. Rate of return analysis
8. Rate of return analysis
 
Chapter 16 depreciation methods
Chapter 16   depreciation methodsChapter 16   depreciation methods
Chapter 16 depreciation methods
 
Chapter 12 independent projects & budget limitation
Chapter 12   independent projects & budget limitationChapter 12   independent projects & budget limitation
Chapter 12 independent projects & budget limitation
 
Chapter 17 after-tax economic analysis
Chapter 17   after-tax economic analysisChapter 17   after-tax economic analysis
Chapter 17 after-tax economic analysis
 
Assignmen (1)
Assignmen (1)Assignmen (1)
Assignmen (1)
 
Making capital investment decisions
Making capital investment decisionsMaking capital investment decisions
Making capital investment decisions
 
Ch12ppt
Ch12pptCh12ppt
Ch12ppt
 
4 interest and equivalence
4 interest and equivalence4 interest and equivalence
4 interest and equivalence
 
Chapter 7 ror analysis for a single alternative
Chapter 7   ror analysis for a single alternativeChapter 7   ror analysis for a single alternative
Chapter 7 ror analysis for a single alternative
 
Chapter 10 making choices & marr
Chapter 10   making choices & marrChapter 10   making choices & marr
Chapter 10 making choices & marr
 
Unit v depreciation
Unit v depreciationUnit v depreciation
Unit v depreciation
 
Chapter 3 combining factors
Chapter 3   combining factorsChapter 3   combining factors
Chapter 3 combining factors
 
Chapter 15 cost estimation
Chapter 15   cost estimationChapter 15   cost estimation
Chapter 15 cost estimation
 
Chapter 8 ror analysis for multiple alternatives
Chapter 8   ror analysis for multiple alternativesChapter 8   ror analysis for multiple alternatives
Chapter 8 ror analysis for multiple alternatives
 

Viewers also liked

Production & Operation ManagementChapter2[1]
Production & Operation ManagementChapter2[1]Production & Operation ManagementChapter2[1]
Production & Operation ManagementChapter2[1]Hariharan Ponnusamy
 
Spanish phonemes
Spanish phonemesSpanish phonemes
Spanish phonemesleravalera
 
Production & Operation Management Chapter3[1]
Production & Operation Management Chapter3[1]Production & Operation Management Chapter3[1]
Production & Operation Management Chapter3[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter7[1]
Production & Operation Management Chapter7[1]Production & Operation Management Chapter7[1]
Production & Operation Management Chapter7[1]Hariharan Ponnusamy
 
Brain resting-state activity in patients with vision loss due to visual syste...
Brain resting-state activity in patients with vision loss due to visual syste...Brain resting-state activity in patients with vision loss due to visual syste...
Brain resting-state activity in patients with vision loss due to visual syste...Michał Bola
 
Production & Operation Management Chapter12[1]
Production & Operation Management Chapter12[1]Production & Operation Management Chapter12[1]
Production & Operation Management Chapter12[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter1[1]
Production & Operation Management Chapter1[1]Production & Operation Management Chapter1[1]
Production & Operation Management Chapter1[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter27[1]
Production & Operation Management Chapter27[1]Production & Operation Management Chapter27[1]
Production & Operation Management Chapter27[1]Hariharan Ponnusamy
 
Contract and its kinds
Contract and its kindsContract and its kinds
Contract and its kindsMuneeb Ahsan
 
Types of share and share capital
Types of share and share capitalTypes of share and share capital
Types of share and share capitalMuneeb Ahsan
 
Bailment and pledge
Bailment and pledgeBailment and pledge
Bailment and pledgeMuneeb Ahsan
 
Proposal of Business research
Proposal of Business research Proposal of Business research
Proposal of Business research Muneeb Ahsan
 

Viewers also liked (19)

Production & Operation ManagementChapter2[1]
Production & Operation ManagementChapter2[1]Production & Operation ManagementChapter2[1]
Production & Operation ManagementChapter2[1]
 
Presentation39
Presentation39Presentation39
Presentation39
 
Spanish phonemes
Spanish phonemesSpanish phonemes
Spanish phonemes
 
Production & Operation Management Chapter3[1]
Production & Operation Management Chapter3[1]Production & Operation Management Chapter3[1]
Production & Operation Management Chapter3[1]
 
Production & Operation Management Chapter7[1]
Production & Operation Management Chapter7[1]Production & Operation Management Chapter7[1]
Production & Operation Management Chapter7[1]
 
Brain resting-state activity in patients with vision loss due to visual syste...
Brain resting-state activity in patients with vision loss due to visual syste...Brain resting-state activity in patients with vision loss due to visual syste...
Brain resting-state activity in patients with vision loss due to visual syste...
 
Chapter12[1]
Chapter12[1]Chapter12[1]
Chapter12[1]
 
Chapter6[1]
Chapter6[1]Chapter6[1]
Chapter6[1]
 
Production & Operation Management Chapter12[1]
Production & Operation Management Chapter12[1]Production & Operation Management Chapter12[1]
Production & Operation Management Chapter12[1]
 
Production & Operation Management Chapter1[1]
Production & Operation Management Chapter1[1]Production & Operation Management Chapter1[1]
Production & Operation Management Chapter1[1]
 
Chapter11[1]
Chapter11[1]Chapter11[1]
Chapter11[1]
 
Chapter5[1]
Chapter5[1]Chapter5[1]
Chapter5[1]
 
The nfc technology
The nfc technologyThe nfc technology
The nfc technology
 
Production & Operation Management Chapter27[1]
Production & Operation Management Chapter27[1]Production & Operation Management Chapter27[1]
Production & Operation Management Chapter27[1]
 
Contract and its kinds
Contract and its kindsContract and its kinds
Contract and its kinds
 
Types of share and share capital
Types of share and share capitalTypes of share and share capital
Types of share and share capital
 
Partnership
PartnershipPartnership
Partnership
 
Bailment and pledge
Bailment and pledgeBailment and pledge
Bailment and pledge
 
Proposal of Business research
Proposal of Business research Proposal of Business research
Proposal of Business research
 

Similar to Production & Operation Management Chapter6[1]

Capital Budgeting Rules 04
Capital Budgeting Rules 04Capital Budgeting Rules 04
Capital Budgeting Rules 04rajeevgupta
 
Fin 2732 investment decisions
Fin 2732 investment decisionsFin 2732 investment decisions
Fin 2732 investment decisionsYashGupta744
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgetingyashpal01
 
FN6033-CORP FIN-LECTURE 5A.ppt
FN6033-CORP FIN-LECTURE 5A.pptFN6033-CORP FIN-LECTURE 5A.ppt
FN6033-CORP FIN-LECTURE 5A.ppthass6
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgetingpremarhea
 
Fina521 lecture 3_investment_criteria_2013-10-09-1
Fina521 lecture 3_investment_criteria_2013-10-09-1Fina521 lecture 3_investment_criteria_2013-10-09-1
Fina521 lecture 3_investment_criteria_2013-10-09-1Landry De Chabe
 
Capital Budgeting- Q.pptx
Capital Budgeting- Q.pptxCapital Budgeting- Q.pptx
Capital Budgeting- Q.pptxMohd Sarim
 
A ppt on capital expenditure by corporate for Mba
A ppt on capital expenditure by corporate for MbaA ppt on capital expenditure by corporate for Mba
A ppt on capital expenditure by corporate for MbaVishalMotwani15
 
Capital budgeting complications
Capital budgeting complications Capital budgeting complications
Capital budgeting complications Babasab Patil
 
Capital budgeting complications
Capital budgeting complications Capital budgeting complications
Capital budgeting complications Babasab Patil
 
NPV is net present value of document.ppt
NPV is net present value of document.pptNPV is net present value of document.ppt
NPV is net present value of document.pptSanthoshK757191
 
Presentation on capital budgeting
Presentation on capital budgetingPresentation on capital budgeting
Presentation on capital budgetingAshima Thakur
 
FM-Unit 2_Long Term Investment Decision.pptx
FM-Unit 2_Long Term Investment Decision.pptxFM-Unit 2_Long Term Investment Decision.pptx
FM-Unit 2_Long Term Investment Decision.pptxradha91354
 
present worth analysis.ppt
present worth analysis.pptpresent worth analysis.ppt
present worth analysis.pptashwinigupta38
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgetingAmeen San
 
Capital Budgeting And Investment Decisions In Financial Management 11 Nov.
Capital Budgeting And Investment Decisions  In Financial Management 11 Nov.Capital Budgeting And Investment Decisions  In Financial Management 11 Nov.
Capital Budgeting And Investment Decisions In Financial Management 11 Nov.Dr. Trilok Kumar Jain
 
Cf Capital Budgeting 6
Cf Capital Budgeting 6Cf Capital Budgeting 6
Cf Capital Budgeting 6rajeevgupta
 
Cf Capital Budgeting 6
Cf Capital Budgeting 6Cf Capital Budgeting 6
Cf Capital Budgeting 6rajeevgupta
 

Similar to Production & Operation Management Chapter6[1] (20)

Capital Budgeting Rules 04
Capital Budgeting Rules 04Capital Budgeting Rules 04
Capital Budgeting Rules 04
 
Fin 2732 investment decisions
Fin 2732 investment decisionsFin 2732 investment decisions
Fin 2732 investment decisions
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgeting
 
FN6033-CORP FIN-LECTURE 5A.ppt
FN6033-CORP FIN-LECTURE 5A.pptFN6033-CORP FIN-LECTURE 5A.ppt
FN6033-CORP FIN-LECTURE 5A.ppt
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
Fina521 lecture 3_investment_criteria_2013-10-09-1
Fina521 lecture 3_investment_criteria_2013-10-09-1Fina521 lecture 3_investment_criteria_2013-10-09-1
Fina521 lecture 3_investment_criteria_2013-10-09-1
 
Capital Budgeting- Q.pptx
Capital Budgeting- Q.pptxCapital Budgeting- Q.pptx
Capital Budgeting- Q.pptx
 
A ppt on capital expenditure by corporate for Mba
A ppt on capital expenditure by corporate for MbaA ppt on capital expenditure by corporate for Mba
A ppt on capital expenditure by corporate for Mba
 
Capital budgeting complications
Capital budgeting complications Capital budgeting complications
Capital budgeting complications
 
Capital budgeting complications
Capital budgeting complications Capital budgeting complications
Capital budgeting complications
 
NPV is net present value of document.ppt
NPV is net present value of document.pptNPV is net present value of document.ppt
NPV is net present value of document.ppt
 
Presentation on capital budgeting
Presentation on capital budgetingPresentation on capital budgeting
Presentation on capital budgeting
 
Lecture 3
Lecture 3Lecture 3
Lecture 3
 
FM-Unit 2_Long Term Investment Decision.pptx
FM-Unit 2_Long Term Investment Decision.pptxFM-Unit 2_Long Term Investment Decision.pptx
FM-Unit 2_Long Term Investment Decision.pptx
 
present worth analysis.ppt
present worth analysis.pptpresent worth analysis.ppt
present worth analysis.ppt
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
Capital Budgeting And Investment Decisions In Financial Management 11 Nov.
Capital Budgeting And Investment Decisions  In Financial Management 11 Nov.Capital Budgeting And Investment Decisions  In Financial Management 11 Nov.
Capital Budgeting And Investment Decisions In Financial Management 11 Nov.
 
Fm chapter five
Fm chapter fiveFm chapter five
Fm chapter five
 
Cf Capital Budgeting 6
Cf Capital Budgeting 6Cf Capital Budgeting 6
Cf Capital Budgeting 6
 
Cf Capital Budgeting 6
Cf Capital Budgeting 6Cf Capital Budgeting 6
Cf Capital Budgeting 6
 

More from Hariharan Ponnusamy

Production & Operation Management Chapter 34, 35[1]
Production & Operation Management Chapter 34, 35[1]Production & Operation Management Chapter 34, 35[1]
Production & Operation Management Chapter 34, 35[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter36[1]
Production & Operation Management Chapter36[1]Production & Operation Management Chapter36[1]
Production & Operation Management Chapter36[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter33[1]
Production & Operation Management Chapter33[1]Production & Operation Management Chapter33[1]
Production & Operation Management Chapter33[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter32[1]
Production & Operation Management Chapter32[1]Production & Operation Management Chapter32[1]
Production & Operation Management Chapter32[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter30[1]
Production & Operation Management Chapter30[1]Production & Operation Management Chapter30[1]
Production & Operation Management Chapter30[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter29[1]
Production & Operation Management Chapter29[1]Production & Operation Management Chapter29[1]
Production & Operation Management Chapter29[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter28[1]
Production & Operation Management Chapter28[1]Production & Operation Management Chapter28[1]
Production & Operation Management Chapter28[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter26[1]
Production & Operation Management Chapter26[1]Production & Operation Management Chapter26[1]
Production & Operation Management Chapter26[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter25[1]
Production & Operation Management Chapter25[1]Production & Operation Management Chapter25[1]
Production & Operation Management Chapter25[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter24[1]
Production & Operation Management Chapter24[1]Production & Operation Management Chapter24[1]
Production & Operation Management Chapter24[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter22[1]
Production & Operation Management Chapter22[1]Production & Operation Management Chapter22[1]
Production & Operation Management Chapter22[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter21[1]
Production & Operation Management Chapter21[1]Production & Operation Management Chapter21[1]
Production & Operation Management Chapter21[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter20[1]
Production & Operation Management Chapter20[1]Production & Operation Management Chapter20[1]
Production & Operation Management Chapter20[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter19[1]
Production & Operation Management Chapter19[1]Production & Operation Management Chapter19[1]
Production & Operation Management Chapter19[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter16[1]
Production & Operation Management Chapter16[1]Production & Operation Management Chapter16[1]
Production & Operation Management Chapter16[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter15[1]
Production & Operation Management Chapter15[1]Production & Operation Management Chapter15[1]
Production & Operation Management Chapter15[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter14[1]
Production & Operation Management Chapter14[1]Production & Operation Management Chapter14[1]
Production & Operation Management Chapter14[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter13[1]
Production & Operation Management Chapter13[1]Production & Operation Management Chapter13[1]
Production & Operation Management Chapter13[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter11[1]
Production & Operation Management Chapter11[1]Production & Operation Management Chapter11[1]
Production & Operation Management Chapter11[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter10[1]
Production & Operation Management Chapter10[1]Production & Operation Management Chapter10[1]
Production & Operation Management Chapter10[1]Hariharan Ponnusamy
 

More from Hariharan Ponnusamy (20)

Production & Operation Management Chapter 34, 35[1]
Production & Operation Management Chapter 34, 35[1]Production & Operation Management Chapter 34, 35[1]
Production & Operation Management Chapter 34, 35[1]
 
Production & Operation Management Chapter36[1]
Production & Operation Management Chapter36[1]Production & Operation Management Chapter36[1]
Production & Operation Management Chapter36[1]
 
Production & Operation Management Chapter33[1]
Production & Operation Management Chapter33[1]Production & Operation Management Chapter33[1]
Production & Operation Management Chapter33[1]
 
Production & Operation Management Chapter32[1]
Production & Operation Management Chapter32[1]Production & Operation Management Chapter32[1]
Production & Operation Management Chapter32[1]
 
Production & Operation Management Chapter30[1]
Production & Operation Management Chapter30[1]Production & Operation Management Chapter30[1]
Production & Operation Management Chapter30[1]
 
Production & Operation Management Chapter29[1]
Production & Operation Management Chapter29[1]Production & Operation Management Chapter29[1]
Production & Operation Management Chapter29[1]
 
Production & Operation Management Chapter28[1]
Production & Operation Management Chapter28[1]Production & Operation Management Chapter28[1]
Production & Operation Management Chapter28[1]
 
Production & Operation Management Chapter26[1]
Production & Operation Management Chapter26[1]Production & Operation Management Chapter26[1]
Production & Operation Management Chapter26[1]
 
Production & Operation Management Chapter25[1]
Production & Operation Management Chapter25[1]Production & Operation Management Chapter25[1]
Production & Operation Management Chapter25[1]
 
Production & Operation Management Chapter24[1]
Production & Operation Management Chapter24[1]Production & Operation Management Chapter24[1]
Production & Operation Management Chapter24[1]
 
Production & Operation Management Chapter22[1]
Production & Operation Management Chapter22[1]Production & Operation Management Chapter22[1]
Production & Operation Management Chapter22[1]
 
Production & Operation Management Chapter21[1]
Production & Operation Management Chapter21[1]Production & Operation Management Chapter21[1]
Production & Operation Management Chapter21[1]
 
Production & Operation Management Chapter20[1]
Production & Operation Management Chapter20[1]Production & Operation Management Chapter20[1]
Production & Operation Management Chapter20[1]
 
Production & Operation Management Chapter19[1]
Production & Operation Management Chapter19[1]Production & Operation Management Chapter19[1]
Production & Operation Management Chapter19[1]
 
Production & Operation Management Chapter16[1]
Production & Operation Management Chapter16[1]Production & Operation Management Chapter16[1]
Production & Operation Management Chapter16[1]
 
Production & Operation Management Chapter15[1]
Production & Operation Management Chapter15[1]Production & Operation Management Chapter15[1]
Production & Operation Management Chapter15[1]
 
Production & Operation Management Chapter14[1]
Production & Operation Management Chapter14[1]Production & Operation Management Chapter14[1]
Production & Operation Management Chapter14[1]
 
Production & Operation Management Chapter13[1]
Production & Operation Management Chapter13[1]Production & Operation Management Chapter13[1]
Production & Operation Management Chapter13[1]
 
Production & Operation Management Chapter11[1]
Production & Operation Management Chapter11[1]Production & Operation Management Chapter11[1]
Production & Operation Management Chapter11[1]
 
Production & Operation Management Chapter10[1]
Production & Operation Management Chapter10[1]Production & Operation Management Chapter10[1]
Production & Operation Management Chapter10[1]
 

Recently uploaded

International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdfAlejandromexEspino
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic managementharfimakarim
 
Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field ArtilleryKennethSwanberg
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptxAss.Prof. Dr. Mogeeb Mosleh
 
Independent Escorts Vikaspuri / 9899900591 High Profile Escort Service in Delhi
Independent Escorts Vikaspuri  / 9899900591 High Profile Escort Service in DelhiIndependent Escorts Vikaspuri  / 9899900591 High Profile Escort Service in Delhi
Independent Escorts Vikaspuri / 9899900591 High Profile Escort Service in Delhiguptaswati8536
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentNimot Muili
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxAaron Stannard
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Hedda Bird
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
Strategic Management, Vision Mission, Internal Analsysis
Strategic Management, Vision Mission, Internal AnalsysisStrategic Management, Vision Mission, Internal Analsysis
Strategic Management, Vision Mission, Internal Analsysistanmayarora45
 
Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...Ram V Chary
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxssuserf63bd7
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxalinstan901
 

Recently uploaded (15)

International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdf
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field Artillery
 
Intro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptxIntro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptx
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 
Independent Escorts Vikaspuri / 9899900591 High Profile Escort Service in Delhi
Independent Escorts Vikaspuri  / 9899900591 High Profile Escort Service in DelhiIndependent Escorts Vikaspuri  / 9899900591 High Profile Escort Service in Delhi
Independent Escorts Vikaspuri / 9899900591 High Profile Escort Service in Delhi
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable development
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptx
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
 
Strategic Management, Vision Mission, Internal Analsysis
Strategic Management, Vision Mission, Internal AnalsysisStrategic Management, Vision Mission, Internal Analsysis
Strategic Management, Vision Mission, Internal Analsysis
 
Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docx
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 

Production & Operation Management Chapter6[1]

  • 1. CHAPTER 6: Capital Budgeting Responses to Questions: 1. Operations management involves decisions to invest in plant and machinery – new plants at new locations and replacement of the old. These are decisions regarding allocation of available funds i.e. Capital budgeting. 2. Since ‘sunk cost’ is, by definition, an entity that does not affect present decisions being made for the future, it does not affect the capital budgeting process. 3. Depreciation is a notional allocation of capital cost used in tax calculations and in profit after tax calculations. Therefore while calculating operational cash flows of a project, depreciation may be used as follows: Operational cash flow = Profit after tax + Interest on long-term borrowings (1-tax rate) + Depreciation + Other non-cash charges (Note: ‘Other non-cash charges’ include amortization of patent cost and write-off of preliminary expenses) Operational cash flows are vital figures in the Capital budgeting decisions. 4. These have been mentioned in the chapter. 5. An explicit measure/criterion like NPV would only be relevant. IRR will not be relevant, as it is only a ‘rate’. 6. IRR is the rate of return on unrecovered balance. This is one interpretation. Another interpretation is that IRR represents the compound rate of return or yield earned on initial investment for the life of the project. The second interpretation of IRR is based on the assumption that the intermediate inflows can be re-invested at IRR. However, it may not be possible for a firm to re-invest intermediate funds at IRR. The first interpretation is more realistic. 7. One incorporates risk into the discount rate, whereas the other reduces the NPV by using a coefficient. The second method is more flexible; if in the 10th year the income is going to be more certain than the income in the 5th year, the risk equivalence coefficient in the 10th year will be higher than that for the 5th year. The first method classifies projects into different risk categories, unlike the second method. Their similarity is that both are only approximations of the risk complexion of any project and are one-dimensional.
  • 2. 2 8. a) The investment is paid back after 4 years (years have been rounded off). Payback period = 4 years. b) NPV = - 10000 + 3000 + 3000 + 3000 + 3000 + 3000 (1+0.1) (1+0.1)2 (1+0.1)3 (1+0.1)4 (1+0.1)5 = -10,000 + 2727 + 2479 + 2254 + 2049 + 1863 = Rs. 1,372 c) To calculate IRR, we equate investment and discounted cash flows for the five years (life as given): 10000 = 3000 + 3000 + 3000 + 3000 + 3000 (1+ i) (1+i)2 (1+i)3 (1+i)4 (1+i)5 The value of ‘i’ i.e. IRR is 15.2 per cent approximately. 9. (a) Project X: NPV = -700 + 450 + 450 (1+0.1) (1+0.1)2 = -700 + 409 + 372 = 81. Project Y: NPV = -7,000 + 4,100 + 4,100 (1+0.1) (1+0.1)2 = -7,000 + 3,272 + 3388 = 115. (b) Project X: IRR = 18.4 % & Project Y: IRR = 11.6 % (approximately). (c) Under ‘no capital rationing’, select Y between the two mutually exclusive projects as Y’s NPV is higher than that of Project X. (d) The selection between the two will, in addition to NPV, depend upon the budget constraint. If budget < 7,000 : select X If budget ≥ 7,000 : select Y 10. We shall compare the NPVs and choose one of the two projects. Project A : NPV = -100,000 + 30000 + 35000 + 40000 + 45000 (1+0.1) (1+0.1)2 (1+0.1)3 (1+0.1)4 = -100,000 + 27273 + 28926 + 30052 + 30736 = 16,987
  • 3. 3 Project B: = -100,000 + 15000 + 17500 + 20000 + 22500 + 25000 (1.1) (1.1)2 (1.1)3 (1.1)4 (1.1)5 27.500 + 30000 + 32500 (1.1)6 (1.1)7 (1.1)8 = -1,00,000 + 13636 + 14463 + 15026 + 15368 + 15523 + 15523 + 15395 + 15161 = 20,095 Since project B has a larger NPV, we choose project B. 11. With 12 total periods, there are 12 different series of outflows corresponding to different periods of replacement. Each series can be considered as a project and these 12 projects could be compared for their NPV. However each project has a different life. Therefore, in order to bring in uniformity, we need to convert the NPVs into uniform annual cash flows (uniform annual series or UAS as it is known in the literature). UAS = NPV PVFA (where PVFA is Present Value Factor for Annuity. PVFAs are given for different discount rates and different lives in readily available tables.) Let us show, as an example, the comparison of two replacement periods viz. 5 years and 8 years. NPV5 = -1600 - 50__ - 70___ - 90___ - 120___ - 150 (1.1) (1.1) 2 (1.1) 3 (1.1) 4 (1.1) 5 = -1600 – 45.55 – 57.85 – 67.62 – 81.96 – 93.14 = -1946.02 NPV8 = -1600 - 50__ - 70___ - 90___ - 120___ - 150 - 190 - 230 - 270_ (1.1) (1.1) 2 (1.1) 3 (1.1) 4 (1.1) 5 (1.1) 6 (1.1) 7 (1.1) 8 = -2297.26 PVFA for 5 years = 3.7908 for i = 10 %. PVFA for 8 years = 5.3349 for i = 10 %. UAS5 = -1946.02 = - 513.35 3.7908 UAS8 = -2297.26 = - 430.61 5.3349
  • 4. 4 Between these two replacement periods, the period of 8 years is chosen as it has less negative UAS. Such comparisons should be made between the 12 different possibilities of replacement periods. The least negative UAS replacement period should be the optimal replacement cycle. Note that the revenues have not been mentioned in this problem. So essentially we had to compare all negative flows (outflows). 12. We have the following relationship in which ‘i’ (IRR) is to be calculated: 25000 = 20000 + 10000 – 10000 + 15000 + 10000 (1+i) (1+i)2 (1+i)3 (1+i)4 (1+i)5 Let us try i = 0.30. It gives: 25000 = 15384 + 5917 – 4552 + 5252 + 2693 = 246494 This is very close. The IRR could be a little lower; perhaps, we could try i= 0.29. You may try and verify. Although there are two changes in sign, there is only one IRR (Reader may verify). ‘n’ changes in sign is only a necessary, not sufficient, condition for ‘n’ positive roots (IRRs) to the polynomial. 13. Projects in the social sector may be selected even if they have low IRR. One is not looking for financial performance in this sector; instead one is looking for a good ‘economic’ performance, i.e. the social cost benefit analysis should indicate a clear benefit to the society. Moreover, many social sector projects have a very long gestation period. For instance, the work done in the primary and secondary schooling may show results after nearly a generation. 14. ‘Risk’ in the context of social sector amounts to the long term costs to the society. Not all cost components can be quantified. Many are in the qualitative realm. Social sector projects are not entirely amenable to a mathematical analysis.
  • 5. 5 CHAPTER 6: Capital Budgeting Objective Questions: 1. Merit of the ‘Pay-back Period’ criterion to appraise projects is: a. it does not discount the cost and income flows. b. it assumes the same value of money over the different periods. √c. it implicitly covers risk. d. none of the above. 2. The project appraisal method that does not depend on the method of depreciation used for tax purposes is: a. NPV b. IRR c. PI √d. none of the above 3. Mutually exclusive projects are best selected based upon: √a. NPV b. IRR c. Capital rationing d. none of the above 4. An investment that pays a fixed number of Rupees per year for a limited number of years is called: a. a good investment b. an NPV c. a perpetuity √ d. an annuity 5. A project involved an initial investment of Rs. 5 crore. If the NPV of the project is Rs. 10 crore, the Profitability Index is: √ a. 3.0 b. 2.0 c. 1.0 d. 0.5 6. Different discount rates can be used for different years under: √ a. NPV b. IRR c. Payback period d. all of the above
  • 6. 6 7. Linear programming is used in project appraisal in cases where: a. risk is being considered. b. projects are mutually exclusive √c. capital is rationed d. none of the above 8. A bio-tech plant has an initial investment of Rs. 200 crore. The benefits, before depreciation and taxes, are estimated at Rs. 70 crore per year for the next 10 years which is the life of the plant. If the depreciation is on a straight line basis for the life of the plant and if there is no salvage value for the plant, what is the NPV at a 15 per cent required rate of return? Assume the taxes to be nil. a. Rs. 551 crore √b. Rs. 51 crore c. Rs. 5.1 crore d. Rs.140 crore 9. For the above problem, the Payback period is : a. 2 years b. 3 years √ c. 4 years d. 5 years 10 For the above problem, the Profitability Index is (roughly): a. 2.5 b. 1.25 c. 0.50 √ d. 0.25 11. Sainath & Co. is considering investment in a new machine costing Rs. 1,00,000, replacing the existing old machine. The old machine was bought 5 years ago for Rs. 40,000 and has a present salvage value of Rs. 20,000. If Sainath decides to replace the old machine by the new, then at the required rate of return of 10 per cent the net investment now would be: a. Rs 32,211 b. Rs 67, 789 c. Rs 75,164 √d. Rs 80,000
  • 7. 7 12. A machine in a factory costs Rs 2 million and lasts for 10 years. What should be the minimal cost saving per year in order to make the purchase of the machine worthwhile if the cost of capital is 15 per cent and the tax rate is 50 per cent? a. Rs. 0.2 million approximately b. Rs. 0.4 million approximately √ c. Rs. 0.8 million approximately d. Rs. 0.1 million approximately 13. Service sector projects may be appraised by using: a. NPV criterion b. IRR criterion c. PI criterion √d. all of the above