SlideShare a Scribd company logo
1 of 14
Download to read offline
Chapter 21: Inventory Models and Safety Stocks
Response to Questions:
1. Material delivery cost is relevant for procurement decisions such as:
“Where to source the supplies from?” For the purchasing manager,
material delivery cost is a ‘controllable’ cost. The number of deliveries, the
distance, and the type of the carrier or mode of transport are important
elements of the procurement cost.
2. Basic EOQ model is a static model and does not take into account the
uncertainties in either the demand or the supply of the item. It assumes a
constant rate of usage and in ‘lumpy’ demand situations this model is not
quite appropriate. The EOQ concept of ‘balancing’ various costs – such as
balancing the procurement costs and carrying costs – is a useful concept.
It could find use despite the model per se not being valid.
3. Changeover from one item to another in a manufacturing facility would
involve the cost of:
a) time spent in changing over,
b) rework, scrap, rejects during the setup and
c) paper work.
Costs (a) & (b) may be different for different sequences.
4. Yes, it would. One has to identify the least cost sequence in the joint
production run.
5. When product-runs are calculated individually, one assumes an ‘average’
set-up time, in an attempt to make the computations independent of the
sequencing decisions. Please note that inventory control calculations are
indeed based on several assumptions.
6. As mentioned in the earlier question, the set-up costs will differ for A, B
and C. The ‘joint cycle’ formula can be used without much difficulty.
7. The activities done before the material is procured and those done before
the material is processed are the cost generators. In manufacturing, the
cost is generated due to waiting of the plant/machinery/manpower. In
purchasing, the cost is generated mainly due to the various paperwork,
phone, fax, receipt and inspection activities. Thus, the components of the
cost are dissimilar. The similarity is that these are pre-manufacturing costs
and can be reduced to a bare minimum.
With proper technical action the manufacturing set-ups could be made
‘single touch’ setups; and with good supplier tie-ups and supply chains,
2
the purchasing order costs could come down drastically. A batch can be
loaded immediately or a material can arrive just in time with minimal
ordering effort.
8. One of the components of carrying costs, viz. the capital cost, is amenable
to be expressed as a fraction of the value of the item. But, the other
components are not. Hence, expressing the carrying cost as a fraction of
the value of the item would not be an accurate way of computing the order
quantities. However, in any case, the ‘cost of capital’ itself is a nebulous
concept; and many simplifications exist in the inventory model itself.
Hence, expressing carrying cost as a fraction of the value of an item offers
much convenience adding only a little more to the existing simplification.
9. When a number of raw materials are procured:
(i) the difficulty is in apportioning order costs to the different
materials (How to divide telephone, follow up charges? How to
apportion effort?);
(ii) there is difficulty in also apportioning the space, materials
handling and insurance costs.
10. Aggregate inventory control can be done by using a Fixed Order Period
model. The carrying cost can also be expressed as a fraction of the value
of inventory.
11. Cost of not being able to fill an order is the shortage cost. However, there
are a number of ways in which a shortage can be met. The items could be
outsourced, borrowed, postponed, or staggered. Hence, computing the
shortage cost becomes difficult.
12. Stock-out can be expressed in terms of
(a) risk level: as done in the chapter, or in terms of
(b) shortage costs (explicit in money terms).
13. Safety stock is there to provide uninterrupted supply to the
production/operations, despite the vagaries in the supplies market and the
changes in the internal production demand.
14. Both R&M are needed simultaneously in order to make the product.
Service levels required = √ 95 / 100
= 0.9747 or 0.975
That is, a service level of 97.5% is required.
3
15.In a fixed order quantity model, the correction (replenishment) takes place
after 1 lead time period. In fixed order period model, the correction takes
place only after a time period of (Lead time + Review period).
16.The fixed order cycle model is preferred when the order for the various
items is to be placed at the same time. This is convenient. However, the
safety stocks required are larger. Hence, the firm may prefer fixed order
quantity model.
17.The time between order and receipt is the ’lead time’. However, lead time
is not just the external (supplier’s) lead time. The internal lead time could
be as big as the external lead time and, hence, needs serious
consideration. How early the need should be communicated is the
question. Internal lead time involves the internal paper-work and other
communication to get the external ordering process started.
18. Inventory Control suggests generalized procedures, whereas Purchasing
and Physical Distribution functions could suggest response to specific
situations in the external market – when there is a dearth or a glut in the
market, when shipments are possible and when they are not. Hence, the
Purchase Manager and Manager of Logistics may want the Inventory
Control to be tempered by the realities of the external environment.
19.Inventory of materials is one type of operations capacity. Inventory could
give the firm the flexibility to respond to sudden demand surges. Hence,
carrying inventory is one of the operations strategies.
However, the other capacity-related strategies could include an ‘inventory’
of manpower, outsourcing and carrying back-orders. Manufacturing
strategies could relate to costs, agility, quality, timeliness, new
technologies etc. Thus, inventory is only a ‘part’ of the manufacturing
strategy.
20.The answer to this question is given in the previous response.
“Optimization of what?“ is the question that one needs to ask. Cost
optimization is not the only objective in front of the management of the
firm. Inventory models express one kind of efficiency and/or effectiveness
that is desired in the organization.
21.Inventory control, Purchasing, Manufacturing, Sales and Physical
Distribution are different aspects of management that need to be
integrated. These different activities need to be coordinated towards the
common organizational set of objectives.
4
22.Here Ku, the understocking cost, is the profit forgone, which is the
difference between sales price per unit and unit cost: (80p – 55p) = 25p.
Ko, the overstocking cost, is the loss in sale on the next day; which is the
difference between the cost per unit and the salvage value per unit: 55p –
40p = 15p.
F(x*) = Ku = 0.25 = 0.625
Ku + Ko 0.25 + 0.15
This is met at x = 700, where the cumulative probability is 0.650 slightly
exceeding the value 0.625.
Assuming that Iyengar makes buns only in 100’s, he should make 700
buns.
23.The service level is defined here in terms of 2 stock-outs in a year. This
necessitates that we know the number of ordering situations in a year.
Therefore, we need to find the EOQ for which the data is available.
EOQ = √ 2ACo
Cc
where A = annual demand = 52 x 1000 units
Co = Rs 200 per order
Cc = Rs 5 per unit
Therefore EOQ = √ 2X52000X200 = 2039.6 units
5
Number of ordering cycles per year A = 52000 = 25.5 = say 26.
Q 2039.6
∴ Service level is 26 -2 = 0.9231
26
This corresponds to a z value of 1.425 (this value is found by referring to
the Normal Distribution table given in Appendix II pg. 21.37)
Since the standard deviation of the usage during a week (which is also the
lead time) is 200 units, the safety stock required is:
(x - µ) = z.σ = 1.425 X 200 = 285 units
5
This is shown in the Figure below.
24.p = 5,000 m/hr, r = 20,000/8 = 2,500 m/hr
A = (20,000 X 365) m/year
CO = 450 per set-up
Cc = 5x0.25 = Rs. 1.25 per m. per year
EBQ =
2 X 450 X (20000 x 365) = 1,02,528 m.
1.25 X (2500 / 5000)
No. of cycles required in a year = 20000 X 365 = 71.2 = 71 approx.
102528
If we make it 73 cycles, then the cycles are taken after every 5 days
(365/73 = 5).
6
25. Solution : Q3opt = 2 x A x C0
s3 x f
where A = 10,000 C0 = Rs 300
f = 0.20 s3 = 9.70
Q3opt = 2 x 10000 x 300 = 1758.6
9.70 x 0.20
This quantity is in the middle price range and not in the range where price
s3 (i.e. Rs 9.70) prevails. Therefore, let us find Q2opt.
Q2opt = 2 x 10000 x 300 = 1745.2
9.85 x 0.20
This falls within its feasible range, because, for this quantity the price s2
(i.e. Rs 9.85) prevails. Refer to the following figure:
(TC)
T
o
t
a
l
c
o
s
t
s
Total cost vs Quantity Relationship for the Problem
The cost at Q2optimal = C0 . __A___ + s2 . f. Q2opt + (A . s2)
Q2opt 2
7
= 300 x 10000 + 9.85 x 0.20 x 1745.2 + (10000 x 9.85)
1795.2 2
= 1719 + 1719 + 98,500 = Rs 1,01,938
We should compare the total costs at Q2opt with the total costs at b2 (i.e. second
price-break quantity).
Total costs at b2 = C0 . A + s3 .f. b2 + (A . s3)
b2 2
= 300 x 10000 + 9.70 x 0.20 x 300 + (10000 x 9.70)
3000 2
= 1000 + 2910 + 97000 = Rs 1,00,910
Therefore, TC (b2) < TC (Q2opt)
Thus, economic order quantity = b2 = 3000 units.
26.The problem is to:
Minimize 5 Qisi (1)
∑ 2
i = 1
(Note: Qisi/2 is the average stock value in Rupees for item ‘i’, Qi being the
order quantity, si, the price per unit of item ‘i’, and usage being assumed to
be uniform over time.)
The constraint is:
5 ai ≤ 10 (2)
∑ Qi
i = 1
8
where ai = weekly usage of item ‘i’, in units.
Using λ as the Lagrange Multiplier, we define ‘F’ as:
5 Qisi + λ 5 ai _ 10
F = ∑ 2 ∑ Qi
i = 1 i = 1
Now, Equate ∂ F to zero and ∂ F to zero
∂ Qi ∂ λ
(i = 1, 2, …, 5)
On differentiation with respect to Qi we get, for each ‘i’:
si + λ . ai = 0
2 - Qi
2
Therefore Qi = 2λ . ai (3)
si
Now, 5 ai = 10 since ∂ F = 0
∑ Qi ∂ λ
i = 1
Substituting for Qi from Eq. (3):
5 ai . √si_ = 10 or 5 √ai si = 10
∑ √ (2λ . ai ) ∑ √(2λ)
i = 1 i = 1
Substituting the values of ai and si from the data given in the problem, we have:
1 √160x20 + √50x30 + √20x180 +√250x20 + √10x75 = 10
√(2λ)
Therefore, √λ = 17.92
Substituting the value of λ, now found, in Eq. (3):
Qi = 17.92 x 2ai …i = 1,2, …, 5
si
Thus, Q1 = 17.92 x 2x20 = 8.96 for Bushings
160
Q2 = 17.92 x 2x30 = 19.63 for Spl. Gaskets
50
9
Q3 = 17.92 x 2x180 = 76.03 for Rings
20
Q4 = 17.92 x 2x20 = 7.17 for Seals
250
Q5 = 17.92 x 2x75 = 69.40 for Pins
10
The weekly orders, ni, are:
n1 = a1 = _20 = 2.23
Q1 8.96
n2 = _30 = 1.53
19.63
n3 = _180 = 2.37
76.03
n4 = _20 = 2.79
7.17
n5 = _75 = 1.08
69.40
Rounding off to the nearest possible integer, we have:
n1 = 2 (for Bushings)
n2 = 2 (for Special Gaskets)
n3 = 2 (for Rings)
n4 = 3 (for Seals)
n5 = 1 (for Pins)
∑ni = 10
The above values give the scheme of ordering for VACO.
The order sizes would, therefore, be:
_______________________________________________________
Serial No. Item No. of Orders Order Size (units)
1. Bushings 2 10
2. Spl. Gaskets 2 15
3. Rings 2 90
4. Seals 3 7, 7 and 6
5. Pins 1 75_______
10
Alternative Solution:
A simple intuitive-cum-trial-&-error approach to the solution of the above problem
could also have been attempted. Such an approach may be allowed here, since
in the earlier solution the number of orders was approximated to the nearest
possible integer. Otherwise, the method involving Lagrange multiplier is quite
precise in calculating the optimal quantities.
The simplistic approach is as follows:
1. Compute the weekly usages of the items in Rupee values.
2. Find the total weekly usage of all the five items; compute the average
Rupee value per order, if 10 (maximum allowed) orders were placed.
3. It is intuitively expected that if the number of orders of each item is
calculated on the basis of average Rupee value per order (earlier
computed), the solution would be optimal or near-optimal.
4. The average stock value (in Rs) is calculated for the above solution.
5. Slight changes may be made in the number of orders for the items and
it may be checked as to whether the average stock value goes any
further down.
6. Accordingly the desired trial-&-error changes are made.
7. The minimum (average stock value) gives the optimal solution.
The computations are given below. The following table gives the first intuitive
values for the number of orders.
No. of Orders Average Stock
Sl Price per Weekly Weekly to be placed= Value
No. Item Unit Usage Usage (Weekly Usage) (Rupees)
(Rs) (units) (Rupees) (1205)
1. Bushings 60 20 1200 1 1200 = 600
1 x 2
2. Spl. Gaskets 50 30 1500 1 1500 = 750
1 x 2
3. Rings 20 180 3600 3 3600 = 600
3 x 2
4. Seals 250 20 5000 4 5000 = 633
4 x 2
5. Pins 10 75 750 1 750 = 375
1 x 2
Total = 12,050 Total = 10 Total = 2958
Average per order = 12,050 = 1,205
10
11
The next set of computations try values which are slightly different from the above.
Trial No. 2 Trial No. 3
Sl Weekly No. of Orders Average No. of Orders Average Stock
No. Item Usage per Week Stock Value per Week Value
(Rupees) (Rupees) (Rupees)
1. Bushings 1200 1 600 2 300
2. Spl. Gaskets 1500 2 375 2 375
3. Rings 3600 3 600 2 900
4. Seals 5000 3 833 3 833
5. Pins 750 1 375 1 375
Total = 2783 Total = 2783
It is noted that both the trials give the same average stock value which is lower
than that found in Trial No. 1. We take one of the latter trial values (of the order
sizes) as our solution. It may be noted that trial No. 3 gives the same solution as
found by the use of Lagrange multiplier earlier.
12
CHAPTER 21: Inventory Models and Safety Stocks
Objective Questions
1. Basic EOQ model assumes:
a. Order quantity is fixed
b. Rate of usage of the material is constant
√c. a & b
d. none of the above
2. When usage is varying, the basic EOQ model needs coverage (by means
of a safety stock) over :
√a. one lead time.
b. a period of time computed based upon the desired service level.
c. one standard deviation of the lead time.
d. none of the above.
3. In a ‘two-bin’ system, one of the bins is stocked equal to:
a. normal usage over the review period.
b. normal usage over the review-plus-lead time.
√c. normal usage over the lead time.
d. none of the above.
4. Re-order Point, in the absence of buffer stocks, equals:
√a. normal usage over one lead time.
b. normal usage over a review period.
c. normal usage over one lead time plus one review period.
d. none of the above.
5. For the same normal usage rate and the same lead time, which of the
following is true?
a. Q-system needs more buffer stock than the P-system of inventory
control.
b. Q-system and P-system need the same level of buffer stock.
√c. Q-system needs less buffer stock than the P-system.
d. none of the above.
6. Usage rate is 100 items per day, procurement cost is Rs. 2000 per
procurement order, the lead time is 4 days and the cost of carrying
inventory is 25 per cent. Each item costs Rs. 400. If a month is taken to
have 30 days, the economic order quantity in this case is:
a. 400
b. 800
√c. 1200
d. data inadequate
13
7. For the above question (Question No.6) the safety stock, corresponding to
an enhanced usage level of 200 items per day, is:
√a. 400
b. 800
c. 1200
d. none of the above
8. Guru Provisions buy an item worth Rs.1 lakh. The inventory carrying costs
are 25 per cent and each ordering procedure involves an expenditure of
Rs. 500. How many orders should Guru place in a year?
a. 2 b. 3 c. 4 √d. 5
9. India Soaps Limited (ISL) buys 1000 tons of tallow annually. The cost of
carrying is estimated at 30 per cent and order cost is estimated at Rs.
10,000 per order. Price of tallow in the supply market is Rs. 10,000 per
ton. Allowing for an annual inflation of 20 per cent in the tallow prices,
what should be ISL’s optimal order quantity for tallow?
a. 105.5 tons
b. 122.4 tons
√c. 148.5 tons
d. 81.6 tons
10.Out of 400 orders, the 372 which were met were all for one unit each;
while the 28 which were not met, were all for five units each. The service
level, in this case, may be said to be:
a. 93 per cent
b. 72.7 per cent
c. 65.8 per cent
√d. either 93 per cent or 72.7 per cent depending upon the definition of
service level.
11.When usage rate variation is probabilistic – approximated to a normal
distribution, if the lead time increases from 1 month to 2 months, the
safety stock requirements will increase by:
√a. 41.4 %
b. 50 %
c. 70.7 %
d. 100 %
12.In a P-system of inventory control, the maximum inventory on hand plus
on order is equal to:
a. Buffer stock.
b. Order quantity plus average usage over lead time.
√c. Average usage over a review period-plus-lead time plus buffer
stock.
14
d. Buffer stock plus average usage over a review period.
13.SNC–ZXLQ brand of radial tyres have a procurement lead-time of 2
weeks, a weekly usage rate of 40 units and a weekly standard deviation of
10 units. Assuming a Normal probability distribution, for a 97 per cent
service level what is the reorder point for this tyre?
a. 60
b. 67
c. 80
√d. 107
14. In the inventory model with purchase discount, the optimal quantity is
Q2 optimal (i.e. that corresponding to Price 2) if:
a. Q2 optimal is higher than Q1 optimal
b. Q2 optimal falls in the zone of Price 1
√c. Q2 optimal falls in the zone of Price 2
d. none of the above

More Related Content

What's hot

Hansen aise im ch14
Hansen aise im ch14Hansen aise im ch14
Hansen aise im ch14Daeng Aiman
 
Inventory management
Inventory managementInventory management
Inventory managementAngelaMaurya
 
Single period inventory ordering
Single period inventory orderingSingle period inventory ordering
Single period inventory orderingFatih Mutlu
 
Cost acc.211.
Cost acc.211.Cost acc.211.
Cost acc.211.Johnykiya
 
3. good inventory-management-edited-ppt
3. good  inventory-management-edited-ppt3. good  inventory-management-edited-ppt
3. good inventory-management-edited-pptshahidch44
 
4. good -inventory-management-ppt
4. good  -inventory-management-ppt4. good  -inventory-management-ppt
4. good -inventory-management-pptshahidch44
 
07 production costs
07 production costs07 production costs
07 production costsNepDevWiki
 

What's hot (12)

Hansen aise im ch14
Hansen aise im ch14Hansen aise im ch14
Hansen aise im ch14
 
Ch14. inventory management
Ch14. inventory managementCh14. inventory management
Ch14. inventory management
 
Inventory management
Inventory managementInventory management
Inventory management
 
Inventory management1
Inventory management1Inventory management1
Inventory management1
 
Single period inventory ordering
Single period inventory orderingSingle period inventory ordering
Single period inventory ordering
 
Cost acc.211.
Cost acc.211.Cost acc.211.
Cost acc.211.
 
3. good inventory-management-edited-ppt
3. good  inventory-management-edited-ppt3. good  inventory-management-edited-ppt
3. good inventory-management-edited-ppt
 
4. good -inventory-management-ppt
4. good  -inventory-management-ppt4. good  -inventory-management-ppt
4. good -inventory-management-ppt
 
Group ii-rtp-dec-2012
Group ii-rtp-dec-2012Group ii-rtp-dec-2012
Group ii-rtp-dec-2012
 
EOQ Ken Homa
EOQ   Ken HomaEOQ   Ken Homa
EOQ Ken Homa
 
07 production costs
07 production costs07 production costs
07 production costs
 
Cost sheet analysis
Cost sheet analysisCost sheet analysis
Cost sheet analysis
 

Viewers also liked

Production & Operation Management Chapter29[1]
Production & Operation Management Chapter29[1]Production & Operation Management Chapter29[1]
Production & Operation Management Chapter29[1]Hariharan Ponnusamy
 
Comenius pathways viktig info
Comenius  pathways viktig infoComenius  pathways viktig info
Comenius pathways viktig infoaned303
 
Production & Operation Management Chapter24[1]
Production & Operation Management Chapter24[1]Production & Operation Management Chapter24[1]
Production & Operation Management Chapter24[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter4[1]
Production & Operation Management Chapter4[1]Production & Operation Management Chapter4[1]
Production & Operation Management Chapter4[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter9[1]
Production & Operation Management Chapter9[1]Production & Operation Management Chapter9[1]
Production & Operation Management Chapter9[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter 34, 35[1]
Production & Operation Management Chapter 34, 35[1]Production & Operation Management Chapter 34, 35[1]
Production & Operation Management Chapter 34, 35[1]Hariharan Ponnusamy
 
Swedish finale product
Swedish finale productSwedish finale product
Swedish finale productaned303
 
Production & Operation Management Chapter8[1]
Production & Operation Management Chapter8[1]Production & Operation Management Chapter8[1]
Production & Operation Management Chapter8[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter16[1]
Production & Operation Management Chapter16[1]Production & Operation Management Chapter16[1]
Production & Operation Management Chapter16[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter26[1]
Production & Operation Management Chapter26[1]Production & Operation Management Chapter26[1]
Production & Operation Management Chapter26[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter33[1]
Production & Operation Management Chapter33[1]Production & Operation Management Chapter33[1]
Production & Operation Management Chapter33[1]Hariharan Ponnusamy
 

Viewers also liked (16)

Chapter13[1]
Chapter13[1]Chapter13[1]
Chapter13[1]
 
Chapter3[1]
Chapter3[1]Chapter3[1]
Chapter3[1]
 
Production & Operation Management Chapter29[1]
Production & Operation Management Chapter29[1]Production & Operation Management Chapter29[1]
Production & Operation Management Chapter29[1]
 
Comenius pathways viktig info
Comenius  pathways viktig infoComenius  pathways viktig info
Comenius pathways viktig info
 
Production & Operation Management Chapter24[1]
Production & Operation Management Chapter24[1]Production & Operation Management Chapter24[1]
Production & Operation Management Chapter24[1]
 
Production & Operation Management Chapter4[1]
Production & Operation Management Chapter4[1]Production & Operation Management Chapter4[1]
Production & Operation Management Chapter4[1]
 
Production & Operation Management Chapter9[1]
Production & Operation Management Chapter9[1]Production & Operation Management Chapter9[1]
Production & Operation Management Chapter9[1]
 
Chapter9[1]
Chapter9[1]Chapter9[1]
Chapter9[1]
 
Production & Operation Management Chapter 34, 35[1]
Production & Operation Management Chapter 34, 35[1]Production & Operation Management Chapter 34, 35[1]
Production & Operation Management Chapter 34, 35[1]
 
Swedish finale product
Swedish finale productSwedish finale product
Swedish finale product
 
Chapter1[1]
Chapter1[1]Chapter1[1]
Chapter1[1]
 
A
AA
A
 
Production & Operation Management Chapter8[1]
Production & Operation Management Chapter8[1]Production & Operation Management Chapter8[1]
Production & Operation Management Chapter8[1]
 
Production & Operation Management Chapter16[1]
Production & Operation Management Chapter16[1]Production & Operation Management Chapter16[1]
Production & Operation Management Chapter16[1]
 
Production & Operation Management Chapter26[1]
Production & Operation Management Chapter26[1]Production & Operation Management Chapter26[1]
Production & Operation Management Chapter26[1]
 
Production & Operation Management Chapter33[1]
Production & Operation Management Chapter33[1]Production & Operation Management Chapter33[1]
Production & Operation Management Chapter33[1]
 

Similar to Production & Operation Management Chapter21[1]

Ch10 Managerial accounting aiou mba mcom 8508
Ch10 Managerial accounting aiou mba mcom 8508Ch10 Managerial accounting aiou mba mcom 8508
Ch10 Managerial accounting aiou mba mcom 8508Ali Imran Awan MBA (IT)
 
Spare parts inventory optimization for auto mobile sector
Spare parts inventory optimization for auto mobile sectorSpare parts inventory optimization for auto mobile sector
Spare parts inventory optimization for auto mobile sectorAlexander Decker
 
UNIT 1 JOB COSTING (1).pptx
UNIT 1 JOB COSTING (1).pptxUNIT 1 JOB COSTING (1).pptx
UNIT 1 JOB COSTING (1).pptxENOCK13
 
Improved Inventory Management System for a Jute Mill - A Case Study.
Improved Inventory Management System for a Jute Mill - A Case Study.Improved Inventory Management System for a Jute Mill - A Case Study.
Improved Inventory Management System for a Jute Mill - A Case Study.IOSR Journals
 
Production & Operation Management Chapter20[1]
Production & Operation Management Chapter20[1]Production & Operation Management Chapter20[1]
Production & Operation Management Chapter20[1]Hariharan Ponnusamy
 
Ch19 Managerial accounting aiou mba mcom 8508
Ch19 Managerial accounting aiou mba mcom 8508Ch19 Managerial accounting aiou mba mcom 8508
Ch19 Managerial accounting aiou mba mcom 8508Ali Imran Awan MBA (IT)
 
Management AccountingActivity Based Costing vs Absorption Cost.docx
Management AccountingActivity Based Costing vs Absorption Cost.docxManagement AccountingActivity Based Costing vs Absorption Cost.docx
Management AccountingActivity Based Costing vs Absorption Cost.docxinfantsuk
 
Inventory management
Inventory managementInventory management
Inventory managementNilesh Ahuja
 
1. Suppose a firm decides to minimize its holdings of current asse.docx
1. Suppose a firm decides to minimize its holdings of current asse.docx1. Suppose a firm decides to minimize its holdings of current asse.docx
1. Suppose a firm decides to minimize its holdings of current asse.docxjackiewalcutt
 
Basic EOQ Model, Quantity Discount, Economic Lot Size
Basic EOQ Model, Quantity Discount, Economic Lot SizeBasic EOQ Model, Quantity Discount, Economic Lot Size
Basic EOQ Model, Quantity Discount, Economic Lot SizePhillip Leonard Petate
 
Marginal-Costing_7dmZZc0.pdf
Marginal-Costing_7dmZZc0.pdfMarginal-Costing_7dmZZc0.pdf
Marginal-Costing_7dmZZc0.pdfMonishAswani1
 
Chapter 4 Activity Based Product Costing
Chapter 4 Activity Based Product CostingChapter 4 Activity Based Product Costing
Chapter 4 Activity Based Product CostingYesica Adicondro
 

Similar to Production & Operation Management Chapter21[1] (20)

Ch10 Managerial accounting aiou mba mcom 8508
Ch10 Managerial accounting aiou mba mcom 8508Ch10 Managerial accounting aiou mba mcom 8508
Ch10 Managerial accounting aiou mba mcom 8508
 
Inventory notes
Inventory notesInventory notes
Inventory notes
 
Inventory 1.1
Inventory 1.1Inventory 1.1
Inventory 1.1
 
Ch-7_Order Quantities.ppt
Ch-7_Order Quantities.pptCh-7_Order Quantities.ppt
Ch-7_Order Quantities.ppt
 
Inventory control
Inventory controlInventory control
Inventory control
 
Ops5
Ops5Ops5
Ops5
 
Spare parts inventory optimization for auto mobile sector
Spare parts inventory optimization for auto mobile sectorSpare parts inventory optimization for auto mobile sector
Spare parts inventory optimization for auto mobile sector
 
UNIT 1 JOB COSTING (1).pptx
UNIT 1 JOB COSTING (1).pptxUNIT 1 JOB COSTING (1).pptx
UNIT 1 JOB COSTING (1).pptx
 
chap014.ppt
chap014.pptchap014.ppt
chap014.ppt
 
Inventory models
Inventory  modelsInventory  models
Inventory models
 
COST ACCOUNTING.pptx
COST ACCOUNTING.pptxCOST ACCOUNTING.pptx
COST ACCOUNTING.pptx
 
Improved Inventory Management System for a Jute Mill - A Case Study.
Improved Inventory Management System for a Jute Mill - A Case Study.Improved Inventory Management System for a Jute Mill - A Case Study.
Improved Inventory Management System for a Jute Mill - A Case Study.
 
Production & Operation Management Chapter20[1]
Production & Operation Management Chapter20[1]Production & Operation Management Chapter20[1]
Production & Operation Management Chapter20[1]
 
Ch19 Managerial accounting aiou mba mcom 8508
Ch19 Managerial accounting aiou mba mcom 8508Ch19 Managerial accounting aiou mba mcom 8508
Ch19 Managerial accounting aiou mba mcom 8508
 
Management AccountingActivity Based Costing vs Absorption Cost.docx
Management AccountingActivity Based Costing vs Absorption Cost.docxManagement AccountingActivity Based Costing vs Absorption Cost.docx
Management AccountingActivity Based Costing vs Absorption Cost.docx
 
Inventory management
Inventory managementInventory management
Inventory management
 
1. Suppose a firm decides to minimize its holdings of current asse.docx
1. Suppose a firm decides to minimize its holdings of current asse.docx1. Suppose a firm decides to minimize its holdings of current asse.docx
1. Suppose a firm decides to minimize its holdings of current asse.docx
 
Basic EOQ Model, Quantity Discount, Economic Lot Size
Basic EOQ Model, Quantity Discount, Economic Lot SizeBasic EOQ Model, Quantity Discount, Economic Lot Size
Basic EOQ Model, Quantity Discount, Economic Lot Size
 
Marginal-Costing_7dmZZc0.pdf
Marginal-Costing_7dmZZc0.pdfMarginal-Costing_7dmZZc0.pdf
Marginal-Costing_7dmZZc0.pdf
 
Chapter 4 Activity Based Product Costing
Chapter 4 Activity Based Product CostingChapter 4 Activity Based Product Costing
Chapter 4 Activity Based Product Costing
 

More from Hariharan Ponnusamy

Production & Operation Management Chapter36[1]
Production & Operation Management Chapter36[1]Production & Operation Management Chapter36[1]
Production & Operation Management Chapter36[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter32[1]
Production & Operation Management Chapter32[1]Production & Operation Management Chapter32[1]
Production & Operation Management Chapter32[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter30[1]
Production & Operation Management Chapter30[1]Production & Operation Management Chapter30[1]
Production & Operation Management Chapter30[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter28[1]
Production & Operation Management Chapter28[1]Production & Operation Management Chapter28[1]
Production & Operation Management Chapter28[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter27[1]
Production & Operation Management Chapter27[1]Production & Operation Management Chapter27[1]
Production & Operation Management Chapter27[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter25[1]
Production & Operation Management Chapter25[1]Production & Operation Management Chapter25[1]
Production & Operation Management Chapter25[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter22[1]
Production & Operation Management Chapter22[1]Production & Operation Management Chapter22[1]
Production & Operation Management Chapter22[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter19[1]
Production & Operation Management Chapter19[1]Production & Operation Management Chapter19[1]
Production & Operation Management Chapter19[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter15[1]
Production & Operation Management Chapter15[1]Production & Operation Management Chapter15[1]
Production & Operation Management Chapter15[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter14[1]
Production & Operation Management Chapter14[1]Production & Operation Management Chapter14[1]
Production & Operation Management Chapter14[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter13[1]
Production & Operation Management Chapter13[1]Production & Operation Management Chapter13[1]
Production & Operation Management Chapter13[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter12[1]
Production & Operation Management Chapter12[1]Production & Operation Management Chapter12[1]
Production & Operation Management Chapter12[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter11[1]
Production & Operation Management Chapter11[1]Production & Operation Management Chapter11[1]
Production & Operation Management Chapter11[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter10[1]
Production & Operation Management Chapter10[1]Production & Operation Management Chapter10[1]
Production & Operation Management Chapter10[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter7[1]
Production & Operation Management Chapter7[1]Production & Operation Management Chapter7[1]
Production & Operation Management Chapter7[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter6[1]
Production & Operation Management Chapter6[1]Production & Operation Management Chapter6[1]
Production & Operation Management Chapter6[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter5[1]
Production & Operation Management Chapter5[1]Production & Operation Management Chapter5[1]
Production & Operation Management Chapter5[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter3[1]
Production & Operation Management Chapter3[1]Production & Operation Management Chapter3[1]
Production & Operation Management Chapter3[1]Hariharan Ponnusamy
 
Production & Operation ManagementChapter2[1]
Production & Operation ManagementChapter2[1]Production & Operation ManagementChapter2[1]
Production & Operation ManagementChapter2[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter1[1]
Production & Operation Management Chapter1[1]Production & Operation Management Chapter1[1]
Production & Operation Management Chapter1[1]Hariharan Ponnusamy
 

More from Hariharan Ponnusamy (20)

Production & Operation Management Chapter36[1]
Production & Operation Management Chapter36[1]Production & Operation Management Chapter36[1]
Production & Operation Management Chapter36[1]
 
Production & Operation Management Chapter32[1]
Production & Operation Management Chapter32[1]Production & Operation Management Chapter32[1]
Production & Operation Management Chapter32[1]
 
Production & Operation Management Chapter30[1]
Production & Operation Management Chapter30[1]Production & Operation Management Chapter30[1]
Production & Operation Management Chapter30[1]
 
Production & Operation Management Chapter28[1]
Production & Operation Management Chapter28[1]Production & Operation Management Chapter28[1]
Production & Operation Management Chapter28[1]
 
Production & Operation Management Chapter27[1]
Production & Operation Management Chapter27[1]Production & Operation Management Chapter27[1]
Production & Operation Management Chapter27[1]
 
Production & Operation Management Chapter25[1]
Production & Operation Management Chapter25[1]Production & Operation Management Chapter25[1]
Production & Operation Management Chapter25[1]
 
Production & Operation Management Chapter22[1]
Production & Operation Management Chapter22[1]Production & Operation Management Chapter22[1]
Production & Operation Management Chapter22[1]
 
Production & Operation Management Chapter19[1]
Production & Operation Management Chapter19[1]Production & Operation Management Chapter19[1]
Production & Operation Management Chapter19[1]
 
Production & Operation Management Chapter15[1]
Production & Operation Management Chapter15[1]Production & Operation Management Chapter15[1]
Production & Operation Management Chapter15[1]
 
Production & Operation Management Chapter14[1]
Production & Operation Management Chapter14[1]Production & Operation Management Chapter14[1]
Production & Operation Management Chapter14[1]
 
Production & Operation Management Chapter13[1]
Production & Operation Management Chapter13[1]Production & Operation Management Chapter13[1]
Production & Operation Management Chapter13[1]
 
Production & Operation Management Chapter12[1]
Production & Operation Management Chapter12[1]Production & Operation Management Chapter12[1]
Production & Operation Management Chapter12[1]
 
Production & Operation Management Chapter11[1]
Production & Operation Management Chapter11[1]Production & Operation Management Chapter11[1]
Production & Operation Management Chapter11[1]
 
Production & Operation Management Chapter10[1]
Production & Operation Management Chapter10[1]Production & Operation Management Chapter10[1]
Production & Operation Management Chapter10[1]
 
Production & Operation Management Chapter7[1]
Production & Operation Management Chapter7[1]Production & Operation Management Chapter7[1]
Production & Operation Management Chapter7[1]
 
Production & Operation Management Chapter6[1]
Production & Operation Management Chapter6[1]Production & Operation Management Chapter6[1]
Production & Operation Management Chapter6[1]
 
Production & Operation Management Chapter5[1]
Production & Operation Management Chapter5[1]Production & Operation Management Chapter5[1]
Production & Operation Management Chapter5[1]
 
Production & Operation Management Chapter3[1]
Production & Operation Management Chapter3[1]Production & Operation Management Chapter3[1]
Production & Operation Management Chapter3[1]
 
Production & Operation ManagementChapter2[1]
Production & Operation ManagementChapter2[1]Production & Operation ManagementChapter2[1]
Production & Operation ManagementChapter2[1]
 
Production & Operation Management Chapter1[1]
Production & Operation Management Chapter1[1]Production & Operation Management Chapter1[1]
Production & Operation Management Chapter1[1]
 

Recently uploaded

Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Nehwal
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceanilsa9823
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic managementharfimakarim
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementTulsiDhidhi1
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girladitipandeya
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607dollysharma2066
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Roomdivyansh0kumar0
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, MumbaiPooja Nehwal
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyHafizMuhammadAbdulla5
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
 

Recently uploaded (20)

Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
 
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 
Disrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdfDisrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdf
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote SpeakerLeadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing management
 
Discover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdfDiscover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdf
 
Becoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette ThompsonBecoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette Thompson
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
 
Empowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdfEmpowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdf
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
 
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdfImagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
 
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg PartnershipUnlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
 
Peak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian DugmorePeak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian Dugmore
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biography
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 

Production & Operation Management Chapter21[1]

  • 1. Chapter 21: Inventory Models and Safety Stocks Response to Questions: 1. Material delivery cost is relevant for procurement decisions such as: “Where to source the supplies from?” For the purchasing manager, material delivery cost is a ‘controllable’ cost. The number of deliveries, the distance, and the type of the carrier or mode of transport are important elements of the procurement cost. 2. Basic EOQ model is a static model and does not take into account the uncertainties in either the demand or the supply of the item. It assumes a constant rate of usage and in ‘lumpy’ demand situations this model is not quite appropriate. The EOQ concept of ‘balancing’ various costs – such as balancing the procurement costs and carrying costs – is a useful concept. It could find use despite the model per se not being valid. 3. Changeover from one item to another in a manufacturing facility would involve the cost of: a) time spent in changing over, b) rework, scrap, rejects during the setup and c) paper work. Costs (a) & (b) may be different for different sequences. 4. Yes, it would. One has to identify the least cost sequence in the joint production run. 5. When product-runs are calculated individually, one assumes an ‘average’ set-up time, in an attempt to make the computations independent of the sequencing decisions. Please note that inventory control calculations are indeed based on several assumptions. 6. As mentioned in the earlier question, the set-up costs will differ for A, B and C. The ‘joint cycle’ formula can be used without much difficulty. 7. The activities done before the material is procured and those done before the material is processed are the cost generators. In manufacturing, the cost is generated due to waiting of the plant/machinery/manpower. In purchasing, the cost is generated mainly due to the various paperwork, phone, fax, receipt and inspection activities. Thus, the components of the cost are dissimilar. The similarity is that these are pre-manufacturing costs and can be reduced to a bare minimum. With proper technical action the manufacturing set-ups could be made ‘single touch’ setups; and with good supplier tie-ups and supply chains,
  • 2. 2 the purchasing order costs could come down drastically. A batch can be loaded immediately or a material can arrive just in time with minimal ordering effort. 8. One of the components of carrying costs, viz. the capital cost, is amenable to be expressed as a fraction of the value of the item. But, the other components are not. Hence, expressing the carrying cost as a fraction of the value of the item would not be an accurate way of computing the order quantities. However, in any case, the ‘cost of capital’ itself is a nebulous concept; and many simplifications exist in the inventory model itself. Hence, expressing carrying cost as a fraction of the value of an item offers much convenience adding only a little more to the existing simplification. 9. When a number of raw materials are procured: (i) the difficulty is in apportioning order costs to the different materials (How to divide telephone, follow up charges? How to apportion effort?); (ii) there is difficulty in also apportioning the space, materials handling and insurance costs. 10. Aggregate inventory control can be done by using a Fixed Order Period model. The carrying cost can also be expressed as a fraction of the value of inventory. 11. Cost of not being able to fill an order is the shortage cost. However, there are a number of ways in which a shortage can be met. The items could be outsourced, borrowed, postponed, or staggered. Hence, computing the shortage cost becomes difficult. 12. Stock-out can be expressed in terms of (a) risk level: as done in the chapter, or in terms of (b) shortage costs (explicit in money terms). 13. Safety stock is there to provide uninterrupted supply to the production/operations, despite the vagaries in the supplies market and the changes in the internal production demand. 14. Both R&M are needed simultaneously in order to make the product. Service levels required = √ 95 / 100 = 0.9747 or 0.975 That is, a service level of 97.5% is required.
  • 3. 3 15.In a fixed order quantity model, the correction (replenishment) takes place after 1 lead time period. In fixed order period model, the correction takes place only after a time period of (Lead time + Review period). 16.The fixed order cycle model is preferred when the order for the various items is to be placed at the same time. This is convenient. However, the safety stocks required are larger. Hence, the firm may prefer fixed order quantity model. 17.The time between order and receipt is the ’lead time’. However, lead time is not just the external (supplier’s) lead time. The internal lead time could be as big as the external lead time and, hence, needs serious consideration. How early the need should be communicated is the question. Internal lead time involves the internal paper-work and other communication to get the external ordering process started. 18. Inventory Control suggests generalized procedures, whereas Purchasing and Physical Distribution functions could suggest response to specific situations in the external market – when there is a dearth or a glut in the market, when shipments are possible and when they are not. Hence, the Purchase Manager and Manager of Logistics may want the Inventory Control to be tempered by the realities of the external environment. 19.Inventory of materials is one type of operations capacity. Inventory could give the firm the flexibility to respond to sudden demand surges. Hence, carrying inventory is one of the operations strategies. However, the other capacity-related strategies could include an ‘inventory’ of manpower, outsourcing and carrying back-orders. Manufacturing strategies could relate to costs, agility, quality, timeliness, new technologies etc. Thus, inventory is only a ‘part’ of the manufacturing strategy. 20.The answer to this question is given in the previous response. “Optimization of what?“ is the question that one needs to ask. Cost optimization is not the only objective in front of the management of the firm. Inventory models express one kind of efficiency and/or effectiveness that is desired in the organization. 21.Inventory control, Purchasing, Manufacturing, Sales and Physical Distribution are different aspects of management that need to be integrated. These different activities need to be coordinated towards the common organizational set of objectives.
  • 4. 4 22.Here Ku, the understocking cost, is the profit forgone, which is the difference between sales price per unit and unit cost: (80p – 55p) = 25p. Ko, the overstocking cost, is the loss in sale on the next day; which is the difference between the cost per unit and the salvage value per unit: 55p – 40p = 15p. F(x*) = Ku = 0.25 = 0.625 Ku + Ko 0.25 + 0.15 This is met at x = 700, where the cumulative probability is 0.650 slightly exceeding the value 0.625. Assuming that Iyengar makes buns only in 100’s, he should make 700 buns. 23.The service level is defined here in terms of 2 stock-outs in a year. This necessitates that we know the number of ordering situations in a year. Therefore, we need to find the EOQ for which the data is available. EOQ = √ 2ACo Cc where A = annual demand = 52 x 1000 units Co = Rs 200 per order Cc = Rs 5 per unit Therefore EOQ = √ 2X52000X200 = 2039.6 units 5 Number of ordering cycles per year A = 52000 = 25.5 = say 26. Q 2039.6 ∴ Service level is 26 -2 = 0.9231 26 This corresponds to a z value of 1.425 (this value is found by referring to the Normal Distribution table given in Appendix II pg. 21.37) Since the standard deviation of the usage during a week (which is also the lead time) is 200 units, the safety stock required is: (x - µ) = z.σ = 1.425 X 200 = 285 units
  • 5. 5 This is shown in the Figure below. 24.p = 5,000 m/hr, r = 20,000/8 = 2,500 m/hr A = (20,000 X 365) m/year CO = 450 per set-up Cc = 5x0.25 = Rs. 1.25 per m. per year EBQ = 2 X 450 X (20000 x 365) = 1,02,528 m. 1.25 X (2500 / 5000) No. of cycles required in a year = 20000 X 365 = 71.2 = 71 approx. 102528 If we make it 73 cycles, then the cycles are taken after every 5 days (365/73 = 5).
  • 6. 6 25. Solution : Q3opt = 2 x A x C0 s3 x f where A = 10,000 C0 = Rs 300 f = 0.20 s3 = 9.70 Q3opt = 2 x 10000 x 300 = 1758.6 9.70 x 0.20 This quantity is in the middle price range and not in the range where price s3 (i.e. Rs 9.70) prevails. Therefore, let us find Q2opt. Q2opt = 2 x 10000 x 300 = 1745.2 9.85 x 0.20 This falls within its feasible range, because, for this quantity the price s2 (i.e. Rs 9.85) prevails. Refer to the following figure: (TC) T o t a l c o s t s Total cost vs Quantity Relationship for the Problem The cost at Q2optimal = C0 . __A___ + s2 . f. Q2opt + (A . s2) Q2opt 2
  • 7. 7 = 300 x 10000 + 9.85 x 0.20 x 1745.2 + (10000 x 9.85) 1795.2 2 = 1719 + 1719 + 98,500 = Rs 1,01,938 We should compare the total costs at Q2opt with the total costs at b2 (i.e. second price-break quantity). Total costs at b2 = C0 . A + s3 .f. b2 + (A . s3) b2 2 = 300 x 10000 + 9.70 x 0.20 x 300 + (10000 x 9.70) 3000 2 = 1000 + 2910 + 97000 = Rs 1,00,910 Therefore, TC (b2) < TC (Q2opt) Thus, economic order quantity = b2 = 3000 units. 26.The problem is to: Minimize 5 Qisi (1) ∑ 2 i = 1 (Note: Qisi/2 is the average stock value in Rupees for item ‘i’, Qi being the order quantity, si, the price per unit of item ‘i’, and usage being assumed to be uniform over time.) The constraint is: 5 ai ≤ 10 (2) ∑ Qi i = 1
  • 8. 8 where ai = weekly usage of item ‘i’, in units. Using λ as the Lagrange Multiplier, we define ‘F’ as: 5 Qisi + λ 5 ai _ 10 F = ∑ 2 ∑ Qi i = 1 i = 1 Now, Equate ∂ F to zero and ∂ F to zero ∂ Qi ∂ λ (i = 1, 2, …, 5) On differentiation with respect to Qi we get, for each ‘i’: si + λ . ai = 0 2 - Qi 2 Therefore Qi = 2λ . ai (3) si Now, 5 ai = 10 since ∂ F = 0 ∑ Qi ∂ λ i = 1 Substituting for Qi from Eq. (3): 5 ai . √si_ = 10 or 5 √ai si = 10 ∑ √ (2λ . ai ) ∑ √(2λ) i = 1 i = 1 Substituting the values of ai and si from the data given in the problem, we have: 1 √160x20 + √50x30 + √20x180 +√250x20 + √10x75 = 10 √(2λ) Therefore, √λ = 17.92 Substituting the value of λ, now found, in Eq. (3): Qi = 17.92 x 2ai …i = 1,2, …, 5 si Thus, Q1 = 17.92 x 2x20 = 8.96 for Bushings 160 Q2 = 17.92 x 2x30 = 19.63 for Spl. Gaskets 50
  • 9. 9 Q3 = 17.92 x 2x180 = 76.03 for Rings 20 Q4 = 17.92 x 2x20 = 7.17 for Seals 250 Q5 = 17.92 x 2x75 = 69.40 for Pins 10 The weekly orders, ni, are: n1 = a1 = _20 = 2.23 Q1 8.96 n2 = _30 = 1.53 19.63 n3 = _180 = 2.37 76.03 n4 = _20 = 2.79 7.17 n5 = _75 = 1.08 69.40 Rounding off to the nearest possible integer, we have: n1 = 2 (for Bushings) n2 = 2 (for Special Gaskets) n3 = 2 (for Rings) n4 = 3 (for Seals) n5 = 1 (for Pins) ∑ni = 10 The above values give the scheme of ordering for VACO. The order sizes would, therefore, be: _______________________________________________________ Serial No. Item No. of Orders Order Size (units) 1. Bushings 2 10 2. Spl. Gaskets 2 15 3. Rings 2 90 4. Seals 3 7, 7 and 6 5. Pins 1 75_______
  • 10. 10 Alternative Solution: A simple intuitive-cum-trial-&-error approach to the solution of the above problem could also have been attempted. Such an approach may be allowed here, since in the earlier solution the number of orders was approximated to the nearest possible integer. Otherwise, the method involving Lagrange multiplier is quite precise in calculating the optimal quantities. The simplistic approach is as follows: 1. Compute the weekly usages of the items in Rupee values. 2. Find the total weekly usage of all the five items; compute the average Rupee value per order, if 10 (maximum allowed) orders were placed. 3. It is intuitively expected that if the number of orders of each item is calculated on the basis of average Rupee value per order (earlier computed), the solution would be optimal or near-optimal. 4. The average stock value (in Rs) is calculated for the above solution. 5. Slight changes may be made in the number of orders for the items and it may be checked as to whether the average stock value goes any further down. 6. Accordingly the desired trial-&-error changes are made. 7. The minimum (average stock value) gives the optimal solution. The computations are given below. The following table gives the first intuitive values for the number of orders. No. of Orders Average Stock Sl Price per Weekly Weekly to be placed= Value No. Item Unit Usage Usage (Weekly Usage) (Rupees) (Rs) (units) (Rupees) (1205) 1. Bushings 60 20 1200 1 1200 = 600 1 x 2 2. Spl. Gaskets 50 30 1500 1 1500 = 750 1 x 2 3. Rings 20 180 3600 3 3600 = 600 3 x 2 4. Seals 250 20 5000 4 5000 = 633 4 x 2 5. Pins 10 75 750 1 750 = 375 1 x 2 Total = 12,050 Total = 10 Total = 2958 Average per order = 12,050 = 1,205 10
  • 11. 11 The next set of computations try values which are slightly different from the above. Trial No. 2 Trial No. 3 Sl Weekly No. of Orders Average No. of Orders Average Stock No. Item Usage per Week Stock Value per Week Value (Rupees) (Rupees) (Rupees) 1. Bushings 1200 1 600 2 300 2. Spl. Gaskets 1500 2 375 2 375 3. Rings 3600 3 600 2 900 4. Seals 5000 3 833 3 833 5. Pins 750 1 375 1 375 Total = 2783 Total = 2783 It is noted that both the trials give the same average stock value which is lower than that found in Trial No. 1. We take one of the latter trial values (of the order sizes) as our solution. It may be noted that trial No. 3 gives the same solution as found by the use of Lagrange multiplier earlier.
  • 12. 12 CHAPTER 21: Inventory Models and Safety Stocks Objective Questions 1. Basic EOQ model assumes: a. Order quantity is fixed b. Rate of usage of the material is constant √c. a & b d. none of the above 2. When usage is varying, the basic EOQ model needs coverage (by means of a safety stock) over : √a. one lead time. b. a period of time computed based upon the desired service level. c. one standard deviation of the lead time. d. none of the above. 3. In a ‘two-bin’ system, one of the bins is stocked equal to: a. normal usage over the review period. b. normal usage over the review-plus-lead time. √c. normal usage over the lead time. d. none of the above. 4. Re-order Point, in the absence of buffer stocks, equals: √a. normal usage over one lead time. b. normal usage over a review period. c. normal usage over one lead time plus one review period. d. none of the above. 5. For the same normal usage rate and the same lead time, which of the following is true? a. Q-system needs more buffer stock than the P-system of inventory control. b. Q-system and P-system need the same level of buffer stock. √c. Q-system needs less buffer stock than the P-system. d. none of the above. 6. Usage rate is 100 items per day, procurement cost is Rs. 2000 per procurement order, the lead time is 4 days and the cost of carrying inventory is 25 per cent. Each item costs Rs. 400. If a month is taken to have 30 days, the economic order quantity in this case is: a. 400 b. 800 √c. 1200 d. data inadequate
  • 13. 13 7. For the above question (Question No.6) the safety stock, corresponding to an enhanced usage level of 200 items per day, is: √a. 400 b. 800 c. 1200 d. none of the above 8. Guru Provisions buy an item worth Rs.1 lakh. The inventory carrying costs are 25 per cent and each ordering procedure involves an expenditure of Rs. 500. How many orders should Guru place in a year? a. 2 b. 3 c. 4 √d. 5 9. India Soaps Limited (ISL) buys 1000 tons of tallow annually. The cost of carrying is estimated at 30 per cent and order cost is estimated at Rs. 10,000 per order. Price of tallow in the supply market is Rs. 10,000 per ton. Allowing for an annual inflation of 20 per cent in the tallow prices, what should be ISL’s optimal order quantity for tallow? a. 105.5 tons b. 122.4 tons √c. 148.5 tons d. 81.6 tons 10.Out of 400 orders, the 372 which were met were all for one unit each; while the 28 which were not met, were all for five units each. The service level, in this case, may be said to be: a. 93 per cent b. 72.7 per cent c. 65.8 per cent √d. either 93 per cent or 72.7 per cent depending upon the definition of service level. 11.When usage rate variation is probabilistic – approximated to a normal distribution, if the lead time increases from 1 month to 2 months, the safety stock requirements will increase by: √a. 41.4 % b. 50 % c. 70.7 % d. 100 % 12.In a P-system of inventory control, the maximum inventory on hand plus on order is equal to: a. Buffer stock. b. Order quantity plus average usage over lead time. √c. Average usage over a review period-plus-lead time plus buffer stock.
  • 14. 14 d. Buffer stock plus average usage over a review period. 13.SNC–ZXLQ brand of radial tyres have a procurement lead-time of 2 weeks, a weekly usage rate of 40 units and a weekly standard deviation of 10 units. Assuming a Normal probability distribution, for a 97 per cent service level what is the reorder point for this tyre? a. 60 b. 67 c. 80 √d. 107 14. In the inventory model with purchase discount, the optimal quantity is Q2 optimal (i.e. that corresponding to Price 2) if: a. Q2 optimal is higher than Q1 optimal b. Q2 optimal falls in the zone of Price 1 √c. Q2 optimal falls in the zone of Price 2 d. none of the above