SlideShare a Scribd company logo
1 of 3
Download to read offline
CHAPTER 14: MAINTENANCE MANAGEMENT ā€“ II
Responses to Questions
1. Spare parts are ā€˜independent demandā€™ items deriving their demand from
the failure characteristics of the components. Statistics of failure is of
much importance in the management of spare parts.
Whereas, most of regular production items are ā€˜dependent demandā€™ items.
Their demand is ultimately derived from customer needs.
Thus, the source of demand and the nature of the source are different for
the spares as against the production items.
2. Poisson distribution is valid when the cause of the failure of the
components is external to them.
3. The number of spares required would depend upon whether it is going to
be total breakdown replacement or partly a preventive replacement ā€“ and
if preventive, what is the preventive replacement type and frequency.
4. Answer is in the text.
5. Yes, I would buy the Insurance spare ā€“ in order to avoid major delay due
to breakdown later.
I would look at the data for similar spares / components on other older
equipment and get failure statistics. These statistics could be used for the
stocking policy of the capital spares.
6. Ī» = 12 items per month Cs = 500 per item
S = 50 Cc = 25 per cent
Lead Time LT = 2 months.
We compute the service level.
Service level = (Cs - S) / Cs = (500 ā€“ 50) / 500 = 0.90
The lead time is 2 months. The mean demand over the lead time is: 12 x 2
= 24 items.
Referring to Poisson distribution table, corresponding to Ī» of 24 and area
underneath the curve of 0.90, the value of x is 30.
Thus we need to maintain a buffer stock of = (30 - 24) = 6 items.
2
CHAPTER 14: Maintenance Management ā€“ II
Objective Questions
1. The following class of spares would have the highest service level:
a. AV
b. AD
c. CD
āˆšd. CV
2. The following class of spares would have the lowest service level:
a. AV
āˆš b. AD
c. CD
d. CV
3. Kodak and Brisch are:
a. systems of classification of spares
āˆšb. systems of codification of spares
c. companies that have almost eliminated the need for spares
d. methods to compute the number of rotable spares
4. Cost of lack of a spare when needed is:
āˆša. downtime cost of the equipment
b. equal to cost of ordering the spare
c. equal to the cost of overstock of one unit
d. none of the above
5. Capital spares are required:
a. as reconditionable spares
b. for frequent breakdown maintenance
c. for group replacement
āˆšd. none of the above.
6. Insurance spare is kept when:
a. reliability of the component is low
b. reliability of the component is very high
c. the equipment is insured
āˆš d. none of the above.
7. Queuing theory is helpful in:
a. computing the number of maintenance personnel required
b. computing the number of ā€˜rotableā€™ spares required
āˆšc. a and b
d. none of the above
3
8. In computing the requirement of maintenance spares one may use:
a. Normal distribution
āˆš b. Normal or Poisson distribution
c. Hyper-exponential distribution
d. None of the above.
9. If an insurance spare costs Rs. 1 lakh and the reliability is estimated to be
0.999, we should buy the spare along with the equipment only if the down-
time costs due to non-availability of the spare are estimated to be:
a. less than or equal to Rs. 10 crore
b. less than or equal to Rs. 1 crore
āˆš c. more than or equal to Rs. 10 crore
d. more than or equal to Rs. 1 crore
10.System reliabilities are the lowest, when redundancies are provided at the
level of the:
āˆš a. equipment
b. module
c. component/part
d. none of the above

More Related Content

Viewers also liked

Production & Operation Management Chapter28[1]
Production & Operation Management Chapter28[1]Production & Operation Management Chapter28[1]
Production & Operation Management Chapter28[1]Hariharan Ponnusamy
Ā 
Production & Operation Management Chapter10[1]
Production & Operation Management Chapter10[1]Production & Operation Management Chapter10[1]
Production & Operation Management Chapter10[1]Hariharan Ponnusamy
Ā 
Production & Operation Management Chapter25[1]
Production & Operation Management Chapter25[1]Production & Operation Management Chapter25[1]
Production & Operation Management Chapter25[1]Hariharan Ponnusamy
Ā 
Production & Operation Management EPILOGUE[1]
Production & Operation Management EPILOGUE[1]Production & Operation Management EPILOGUE[1]
Production & Operation Management EPILOGUE[1]Hariharan Ponnusamy
Ā 
Production & Operation Management Chapter32[1]
Production & Operation Management Chapter32[1]Production & Operation Management Chapter32[1]
Production & Operation Management Chapter32[1]Hariharan Ponnusamy
Ā 
Production & Operation Management Chapter11[1]
Production & Operation Management Chapter11[1]Production & Operation Management Chapter11[1]
Production & Operation Management Chapter11[1]Hariharan Ponnusamy
Ā 
Production & Operation Management Chapter19[1]
Production & Operation Management Chapter19[1]Production & Operation Management Chapter19[1]
Production & Operation Management Chapter19[1]Hariharan Ponnusamy
Ā 
Lsc math course redesign
Lsc math course redesignLsc math course redesign
Lsc math course redesignArthur Garcia
Ā 
Brooks-Keret - Who we are
Brooks-Keret - Who we areBrooks-Keret - Who we are
Brooks-Keret - Who we areLee Shafrir
Ā 
Virtual Reality: Navigating its rapidly evolving landscape
Virtual Reality: Navigating its rapidly evolving landscapeVirtual Reality: Navigating its rapidly evolving landscape
Virtual Reality: Navigating its rapidly evolving landscapeatomworks
Ā 

Viewers also liked (15)

Production & Operation Management Chapter28[1]
Production & Operation Management Chapter28[1]Production & Operation Management Chapter28[1]
Production & Operation Management Chapter28[1]
Ā 
Chapter7[1]
Chapter7[1]Chapter7[1]
Chapter7[1]
Ā 
Production & Operation Management Chapter10[1]
Production & Operation Management Chapter10[1]Production & Operation Management Chapter10[1]
Production & Operation Management Chapter10[1]
Ā 
Production & Operation Management Chapter25[1]
Production & Operation Management Chapter25[1]Production & Operation Management Chapter25[1]
Production & Operation Management Chapter25[1]
Ā 
Chapter4[1]
Chapter4[1]Chapter4[1]
Chapter4[1]
Ā 
Production & Operation Management EPILOGUE[1]
Production & Operation Management EPILOGUE[1]Production & Operation Management EPILOGUE[1]
Production & Operation Management EPILOGUE[1]
Ā 
Chapter8[1]
Chapter8[1]Chapter8[1]
Chapter8[1]
Ā 
Chapter2[1]
Chapter2[1]Chapter2[1]
Chapter2[1]
Ā 
Production & Operation Management Chapter32[1]
Production & Operation Management Chapter32[1]Production & Operation Management Chapter32[1]
Production & Operation Management Chapter32[1]
Ā 
Chapter10[1]
Chapter10[1]Chapter10[1]
Chapter10[1]
Ā 
Production & Operation Management Chapter11[1]
Production & Operation Management Chapter11[1]Production & Operation Management Chapter11[1]
Production & Operation Management Chapter11[1]
Ā 
Production & Operation Management Chapter19[1]
Production & Operation Management Chapter19[1]Production & Operation Management Chapter19[1]
Production & Operation Management Chapter19[1]
Ā 
Lsc math course redesign
Lsc math course redesignLsc math course redesign
Lsc math course redesign
Ā 
Brooks-Keret - Who we are
Brooks-Keret - Who we areBrooks-Keret - Who we are
Brooks-Keret - Who we are
Ā 
Virtual Reality: Navigating its rapidly evolving landscape
Virtual Reality: Navigating its rapidly evolving landscapeVirtual Reality: Navigating its rapidly evolving landscape
Virtual Reality: Navigating its rapidly evolving landscape
Ā 

Similar to Production & Operation Management Chapter14[1]

sparepartsmanagment
sparepartsmanagmentsparepartsmanagment
sparepartsmanagmentRAKESH SINGH
Ā 
KEY TO PROFITABILITY: SPARE PART MANAGEMENT
KEY TO PROFITABILITY: SPARE PART MANAGEMENTKEY TO PROFITABILITY: SPARE PART MANAGEMENT
KEY TO PROFITABILITY: SPARE PART MANAGEMENTDr. V.N. Tikku
Ā 
Cost & Management Accounting
Cost & Management AccountingCost & Management Accounting
Cost & Management Accountingamitymbaassignment
Ā 
Accounting for Property, Plant and Equipment
Accounting for Property, Plant and Equipment Accounting for Property, Plant and Equipment
Accounting for Property, Plant and Equipment HelpWithAssignment.com
Ā 
Chap12 mc questions&answers
Chap12 mc questions&answersChap12 mc questions&answers
Chap12 mc questions&answersNarendra Chatterjee
Ā 
Global supply chains and distribution new competitive strategies project peropt
Global supply chains and distribution new competitive strategies project peroptGlobal supply chains and distribution new competitive strategies project peropt
Global supply chains and distribution new competitive strategies project peroptyvwang
Ā 
Om0015 maintenance management..
Om0015   maintenance management..Om0015   maintenance management..
Om0015 maintenance management..smumbahelp
Ā 
Om0015 maintenance management..
Om0015   maintenance management..Om0015   maintenance management..
Om0015 maintenance management..smumbahelp
Ā 
Om0010 operations management
Om0010   operations managementOm0010   operations management
Om0010 operations managementsmumbahelp
Ā 
Basic concept of inventory management
Basic concept of inventory management Basic concept of inventory management
Basic concept of inventory management Molla Morshad
Ā 
Ops 571 final exam
Ops 571 final examOps 571 final exam
Ops 571 final examnbvhgfuyt876
Ā 
Ops 571 final exam
Ops 571 final examOps 571 final exam
Ops 571 final exammn8676766
Ā 
1661351030Unit 4 1056-V1 Equipment Management.pdf
1661351030Unit 4 1056-V1 Equipment Management.pdf1661351030Unit 4 1056-V1 Equipment Management.pdf
1661351030Unit 4 1056-V1 Equipment Management.pdfahsansaeed78
Ā 
05. ACCOUNTING.ppt
05. ACCOUNTING.ppt05. ACCOUNTING.ppt
05. ACCOUNTING.pptalihabsyee
Ā 
Production & Operation Management Chapter21[1]
Production & Operation Management Chapter21[1]Production & Operation Management Chapter21[1]
Production & Operation Management Chapter21[1]Hariharan Ponnusamy
Ā 
MG6863-Unit-4.pdf
MG6863-Unit-4.pdfMG6863-Unit-4.pdf
MG6863-Unit-4.pdfnallak1
Ā 
Operations managementppt
Operations managementpptOperations managementppt
Operations managementpptMaChere Reyes
Ā 

Similar to Production & Operation Management Chapter14[1] (20)

sparepartsmanagment
sparepartsmanagmentsparepartsmanagment
sparepartsmanagment
Ā 
KEY TO PROFITABILITY: SPARE PART MANAGEMENT
KEY TO PROFITABILITY: SPARE PART MANAGEMENTKEY TO PROFITABILITY: SPARE PART MANAGEMENT
KEY TO PROFITABILITY: SPARE PART MANAGEMENT
Ā 
Chapter13[1]
Chapter13[1]Chapter13[1]
Chapter13[1]
Ā 
Cost & Management Accounting
Cost & Management AccountingCost & Management Accounting
Cost & Management Accounting
Ā 
Accounting for Property, Plant and Equipment
Accounting for Property, Plant and Equipment Accounting for Property, Plant and Equipment
Accounting for Property, Plant and Equipment
Ā 
Summarised theory
Summarised theorySummarised theory
Summarised theory
Ā 
Summarised theory
Summarised theorySummarised theory
Summarised theory
Ā 
Chap12 mc questions&answers
Chap12 mc questions&answersChap12 mc questions&answers
Chap12 mc questions&answers
Ā 
Global supply chains and distribution new competitive strategies project peropt
Global supply chains and distribution new competitive strategies project peroptGlobal supply chains and distribution new competitive strategies project peropt
Global supply chains and distribution new competitive strategies project peropt
Ā 
Om0015 maintenance management..
Om0015   maintenance management..Om0015   maintenance management..
Om0015 maintenance management..
Ā 
Om0015 maintenance management..
Om0015   maintenance management..Om0015   maintenance management..
Om0015 maintenance management..
Ā 
Om0010 operations management
Om0010   operations managementOm0010   operations management
Om0010 operations management
Ā 
Basic concept of inventory management
Basic concept of inventory management Basic concept of inventory management
Basic concept of inventory management
Ā 
Ops 571 final exam
Ops 571 final examOps 571 final exam
Ops 571 final exam
Ā 
Ops 571 final exam
Ops 571 final examOps 571 final exam
Ops 571 final exam
Ā 
1661351030Unit 4 1056-V1 Equipment Management.pdf
1661351030Unit 4 1056-V1 Equipment Management.pdf1661351030Unit 4 1056-V1 Equipment Management.pdf
1661351030Unit 4 1056-V1 Equipment Management.pdf
Ā 
05. ACCOUNTING.ppt
05. ACCOUNTING.ppt05. ACCOUNTING.ppt
05. ACCOUNTING.ppt
Ā 
Production & Operation Management Chapter21[1]
Production & Operation Management Chapter21[1]Production & Operation Management Chapter21[1]
Production & Operation Management Chapter21[1]
Ā 
MG6863-Unit-4.pdf
MG6863-Unit-4.pdfMG6863-Unit-4.pdf
MG6863-Unit-4.pdf
Ā 
Operations managementppt
Operations managementpptOperations managementppt
Operations managementppt
Ā 

More from Hariharan Ponnusamy

Production & Operation Management Chapter 34, 35[1]
Production & Operation Management Chapter 34, 35[1]Production & Operation Management Chapter 34, 35[1]
Production & Operation Management Chapter 34, 35[1]Hariharan Ponnusamy
Ā 
Production & Operation Management Chapter36[1]
Production & Operation Management Chapter36[1]Production & Operation Management Chapter36[1]
Production & Operation Management Chapter36[1]Hariharan Ponnusamy
Ā 
Production & Operation Management Chapter33[1]
Production & Operation Management Chapter33[1]Production & Operation Management Chapter33[1]
Production & Operation Management Chapter33[1]Hariharan Ponnusamy
Ā 
Production & Operation Management Chapter29[1]
Production & Operation Management Chapter29[1]Production & Operation Management Chapter29[1]
Production & Operation Management Chapter29[1]Hariharan Ponnusamy
Ā 
Production & Operation Management Chapter27[1]
Production & Operation Management Chapter27[1]Production & Operation Management Chapter27[1]
Production & Operation Management Chapter27[1]Hariharan Ponnusamy
Ā 
Production & Operation Management Chapter26[1]
Production & Operation Management Chapter26[1]Production & Operation Management Chapter26[1]
Production & Operation Management Chapter26[1]Hariharan Ponnusamy
Ā 
Production & Operation Management Chapter24[1]
Production & Operation Management Chapter24[1]Production & Operation Management Chapter24[1]
Production & Operation Management Chapter24[1]Hariharan Ponnusamy
Ā 
Production & Operation Management Chapter20[1]
Production & Operation Management Chapter20[1]Production & Operation Management Chapter20[1]
Production & Operation Management Chapter20[1]Hariharan Ponnusamy
Ā 
Production & Operation Management Chapter16[1]
Production & Operation Management Chapter16[1]Production & Operation Management Chapter16[1]
Production & Operation Management Chapter16[1]Hariharan Ponnusamy
Ā 
Production & Operation Management Chapter15[1]
Production & Operation Management Chapter15[1]Production & Operation Management Chapter15[1]
Production & Operation Management Chapter15[1]Hariharan Ponnusamy
Ā 
Production & Operation Management Chapter12[1]
Production & Operation Management Chapter12[1]Production & Operation Management Chapter12[1]
Production & Operation Management Chapter12[1]Hariharan Ponnusamy
Ā 
Production & Operation Management Chapter9[1]
Production & Operation Management Chapter9[1]Production & Operation Management Chapter9[1]
Production & Operation Management Chapter9[1]Hariharan Ponnusamy
Ā 
Production & Operation Management Chapter8[1]
Production & Operation Management Chapter8[1]Production & Operation Management Chapter8[1]
Production & Operation Management Chapter8[1]Hariharan Ponnusamy
Ā 
Production & Operation Management Chapter7[1]
Production & Operation Management Chapter7[1]Production & Operation Management Chapter7[1]
Production & Operation Management Chapter7[1]Hariharan Ponnusamy
Ā 
Production & Operation Management Chapter6[1]
Production & Operation Management Chapter6[1]Production & Operation Management Chapter6[1]
Production & Operation Management Chapter6[1]Hariharan Ponnusamy
Ā 
Production & Operation Management Chapter5[1]
Production & Operation Management Chapter5[1]Production & Operation Management Chapter5[1]
Production & Operation Management Chapter5[1]Hariharan Ponnusamy
Ā 
Production & Operation Management Chapter4[1]
Production & Operation Management Chapter4[1]Production & Operation Management Chapter4[1]
Production & Operation Management Chapter4[1]Hariharan Ponnusamy
Ā 
Production & Operation Management Chapter3[1]
Production & Operation Management Chapter3[1]Production & Operation Management Chapter3[1]
Production & Operation Management Chapter3[1]Hariharan Ponnusamy
Ā 
Production & Operation ManagementChapter2[1]
Production & Operation ManagementChapter2[1]Production & Operation ManagementChapter2[1]
Production & Operation ManagementChapter2[1]Hariharan Ponnusamy
Ā 
Production & Operation Management Chapter1[1]
Production & Operation Management Chapter1[1]Production & Operation Management Chapter1[1]
Production & Operation Management Chapter1[1]Hariharan Ponnusamy
Ā 

More from Hariharan Ponnusamy (20)

Production & Operation Management Chapter 34, 35[1]
Production & Operation Management Chapter 34, 35[1]Production & Operation Management Chapter 34, 35[1]
Production & Operation Management Chapter 34, 35[1]
Ā 
Production & Operation Management Chapter36[1]
Production & Operation Management Chapter36[1]Production & Operation Management Chapter36[1]
Production & Operation Management Chapter36[1]
Ā 
Production & Operation Management Chapter33[1]
Production & Operation Management Chapter33[1]Production & Operation Management Chapter33[1]
Production & Operation Management Chapter33[1]
Ā 
Production & Operation Management Chapter29[1]
Production & Operation Management Chapter29[1]Production & Operation Management Chapter29[1]
Production & Operation Management Chapter29[1]
Ā 
Production & Operation Management Chapter27[1]
Production & Operation Management Chapter27[1]Production & Operation Management Chapter27[1]
Production & Operation Management Chapter27[1]
Ā 
Production & Operation Management Chapter26[1]
Production & Operation Management Chapter26[1]Production & Operation Management Chapter26[1]
Production & Operation Management Chapter26[1]
Ā 
Production & Operation Management Chapter24[1]
Production & Operation Management Chapter24[1]Production & Operation Management Chapter24[1]
Production & Operation Management Chapter24[1]
Ā 
Production & Operation Management Chapter20[1]
Production & Operation Management Chapter20[1]Production & Operation Management Chapter20[1]
Production & Operation Management Chapter20[1]
Ā 
Production & Operation Management Chapter16[1]
Production & Operation Management Chapter16[1]Production & Operation Management Chapter16[1]
Production & Operation Management Chapter16[1]
Ā 
Production & Operation Management Chapter15[1]
Production & Operation Management Chapter15[1]Production & Operation Management Chapter15[1]
Production & Operation Management Chapter15[1]
Ā 
Production & Operation Management Chapter12[1]
Production & Operation Management Chapter12[1]Production & Operation Management Chapter12[1]
Production & Operation Management Chapter12[1]
Ā 
Production & Operation Management Chapter9[1]
Production & Operation Management Chapter9[1]Production & Operation Management Chapter9[1]
Production & Operation Management Chapter9[1]
Ā 
Production & Operation Management Chapter8[1]
Production & Operation Management Chapter8[1]Production & Operation Management Chapter8[1]
Production & Operation Management Chapter8[1]
Ā 
Production & Operation Management Chapter7[1]
Production & Operation Management Chapter7[1]Production & Operation Management Chapter7[1]
Production & Operation Management Chapter7[1]
Ā 
Production & Operation Management Chapter6[1]
Production & Operation Management Chapter6[1]Production & Operation Management Chapter6[1]
Production & Operation Management Chapter6[1]
Ā 
Production & Operation Management Chapter5[1]
Production & Operation Management Chapter5[1]Production & Operation Management Chapter5[1]
Production & Operation Management Chapter5[1]
Ā 
Production & Operation Management Chapter4[1]
Production & Operation Management Chapter4[1]Production & Operation Management Chapter4[1]
Production & Operation Management Chapter4[1]
Ā 
Production & Operation Management Chapter3[1]
Production & Operation Management Chapter3[1]Production & Operation Management Chapter3[1]
Production & Operation Management Chapter3[1]
Ā 
Production & Operation ManagementChapter2[1]
Production & Operation ManagementChapter2[1]Production & Operation ManagementChapter2[1]
Production & Operation ManagementChapter2[1]
Ā 
Production & Operation Management Chapter1[1]
Production & Operation Management Chapter1[1]Production & Operation Management Chapter1[1]
Production & Operation Management Chapter1[1]
Ā 

Recently uploaded

Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentationmintusiprd
Ā 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyHafizMuhammadAbdulla5
Ā 
Training Methods and Training Objectives
Training Methods and Training ObjectivesTraining Methods and Training Objectives
Training Methods and Training Objectivesmintusiprd
Ā 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Reviewthomas851723
Ā 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineeringthomas851723
Ā 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentationcraig524401
Ā 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
Ā 
LPC Facility Design And Re-engineering Presentation
LPC Facility Design And Re-engineering PresentationLPC Facility Design And Re-engineering Presentation
LPC Facility Design And Re-engineering Presentationthomas851723
Ā 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girladitipandeya
Ā 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, MumbaiPooja Nehwal
Ā 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sectorthomas851723
Ā 
LPC User Requirements for Automated Storage System Presentation
LPC User Requirements for Automated Storage System PresentationLPC User Requirements for Automated Storage System Presentation
LPC User Requirements for Automated Storage System Presentationthomas851723
Ā 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Nehwal
Ā 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
Ā 
CALL ON āž„8923113531 šŸ”Call Girls Charbagh Lucknow best sexual service
CALL ON āž„8923113531 šŸ”Call Girls Charbagh Lucknow best sexual serviceCALL ON āž„8923113531 šŸ”Call Girls Charbagh Lucknow best sexual service
CALL ON āž„8923113531 šŸ”Call Girls Charbagh Lucknow best sexual serviceanilsa9823
Ā 
VIP Kolkata Call Girl Rajarhat šŸ‘‰ 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat šŸ‘‰ 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat šŸ‘‰ 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat šŸ‘‰ 8250192130 Available With Roomdivyansh0kumar0
Ā 
GENUINE Babe,Call Girls IN Badarpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Badarpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Badarpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Badarpur Delhi | +91-8377087607dollysharma2066
Ā 

Recently uploaded (20)

Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentation
Ā 
Becoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette ThompsonBecoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette Thompson
Ā 
sauth delhi call girls in Defence ColonyšŸ” 9953056974 šŸ” escort Service
sauth delhi call girls in Defence ColonyšŸ” 9953056974 šŸ” escort Servicesauth delhi call girls in Defence ColonyšŸ” 9953056974 šŸ” escort Service
sauth delhi call girls in Defence ColonyšŸ” 9953056974 šŸ” escort Service
Ā 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biography
Ā 
Training Methods and Training Objectives
Training Methods and Training ObjectivesTraining Methods and Training Objectives
Training Methods and Training Objectives
Ā 
Call Girls Service Tilak Nagar @9999965857 Delhi šŸ«¦ No Advance VVIP šŸŽ SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi šŸ«¦ No Advance  VVIP šŸŽ SERVICECall Girls Service Tilak Nagar @9999965857 Delhi šŸ«¦ No Advance  VVIP šŸŽ SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi šŸ«¦ No Advance VVIP šŸŽ SERVICE
Ā 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Review
Ā 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineering
Ā 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentation
Ā 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
Ā 
LPC Facility Design And Re-engineering Presentation
LPC Facility Design And Re-engineering PresentationLPC Facility Design And Re-engineering Presentation
LPC Facility Design And Re-engineering Presentation
Ā 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
Ā 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
Ā 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sector
Ā 
LPC User Requirements for Automated Storage System Presentation
LPC User Requirements for Automated Storage System PresentationLPC User Requirements for Automated Storage System Presentation
LPC User Requirements for Automated Storage System Presentation
Ā 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Ā 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Ā 
CALL ON āž„8923113531 šŸ”Call Girls Charbagh Lucknow best sexual service
CALL ON āž„8923113531 šŸ”Call Girls Charbagh Lucknow best sexual serviceCALL ON āž„8923113531 šŸ”Call Girls Charbagh Lucknow best sexual service
CALL ON āž„8923113531 šŸ”Call Girls Charbagh Lucknow best sexual service
Ā 
VIP Kolkata Call Girl Rajarhat šŸ‘‰ 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat šŸ‘‰ 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat šŸ‘‰ 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat šŸ‘‰ 8250192130 Available With Room
Ā 
GENUINE Babe,Call Girls IN Badarpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Badarpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Badarpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Badarpur Delhi | +91-8377087607
Ā 

Production & Operation Management Chapter14[1]

  • 1. CHAPTER 14: MAINTENANCE MANAGEMENT ā€“ II Responses to Questions 1. Spare parts are ā€˜independent demandā€™ items deriving their demand from the failure characteristics of the components. Statistics of failure is of much importance in the management of spare parts. Whereas, most of regular production items are ā€˜dependent demandā€™ items. Their demand is ultimately derived from customer needs. Thus, the source of demand and the nature of the source are different for the spares as against the production items. 2. Poisson distribution is valid when the cause of the failure of the components is external to them. 3. The number of spares required would depend upon whether it is going to be total breakdown replacement or partly a preventive replacement ā€“ and if preventive, what is the preventive replacement type and frequency. 4. Answer is in the text. 5. Yes, I would buy the Insurance spare ā€“ in order to avoid major delay due to breakdown later. I would look at the data for similar spares / components on other older equipment and get failure statistics. These statistics could be used for the stocking policy of the capital spares. 6. Ī» = 12 items per month Cs = 500 per item S = 50 Cc = 25 per cent Lead Time LT = 2 months. We compute the service level. Service level = (Cs - S) / Cs = (500 ā€“ 50) / 500 = 0.90 The lead time is 2 months. The mean demand over the lead time is: 12 x 2 = 24 items. Referring to Poisson distribution table, corresponding to Ī» of 24 and area underneath the curve of 0.90, the value of x is 30. Thus we need to maintain a buffer stock of = (30 - 24) = 6 items.
  • 2. 2 CHAPTER 14: Maintenance Management ā€“ II Objective Questions 1. The following class of spares would have the highest service level: a. AV b. AD c. CD āˆšd. CV 2. The following class of spares would have the lowest service level: a. AV āˆš b. AD c. CD d. CV 3. Kodak and Brisch are: a. systems of classification of spares āˆšb. systems of codification of spares c. companies that have almost eliminated the need for spares d. methods to compute the number of rotable spares 4. Cost of lack of a spare when needed is: āˆša. downtime cost of the equipment b. equal to cost of ordering the spare c. equal to the cost of overstock of one unit d. none of the above 5. Capital spares are required: a. as reconditionable spares b. for frequent breakdown maintenance c. for group replacement āˆšd. none of the above. 6. Insurance spare is kept when: a. reliability of the component is low b. reliability of the component is very high c. the equipment is insured āˆš d. none of the above. 7. Queuing theory is helpful in: a. computing the number of maintenance personnel required b. computing the number of ā€˜rotableā€™ spares required āˆšc. a and b d. none of the above
  • 3. 3 8. In computing the requirement of maintenance spares one may use: a. Normal distribution āˆš b. Normal or Poisson distribution c. Hyper-exponential distribution d. None of the above. 9. If an insurance spare costs Rs. 1 lakh and the reliability is estimated to be 0.999, we should buy the spare along with the equipment only if the down- time costs due to non-availability of the spare are estimated to be: a. less than or equal to Rs. 10 crore b. less than or equal to Rs. 1 crore āˆš c. more than or equal to Rs. 10 crore d. more than or equal to Rs. 1 crore 10.System reliabilities are the lowest, when redundancies are provided at the level of the: āˆš a. equipment b. module c. component/part d. none of the above