Introduction to Project Management           Sanjay Koul           sanjayk@cdac.in
What is a Project? A project is a temporary endeavor undertaken to  produce a unique product or service                  ...
 Management   - Management is the technique of understanding the     problems, needs and controlling the use of resources...
 Process  – A process is part of the project which consists of simple  and routine instructions to achieve a desired resu...
Some experiences-may happen
Project Success Customer Requirements      Completed within   satisfied/exceeded      allocated time frame   Completed wit...
Project Failure                            Poor Requirements       Scope Creep                                Gathering Un...
Project ManagementProject Management is the application of skills, knowledge, tools and techniques to meet the needs and ...
The Project Manager (PM) A project manager is a person who manages the  project. The project manager is responsible to ca...
Role of a Project Manager                                                   PeopleProcess                                 ...
Types of Project Managers• Hands-off versus hands-on managers    Most of the hands-off managers are non-technical manager...
Who will be a Good Software Engineer?People with good problem solving abilities, goodcommunication skills and team spirit ...
How does project management benefit you?You will have goal clarity and measurementYour resources will be coordinatedYou...
Triple Contraint           Time           QualityCost                  Scope
Triple ContraintIncreased Scope = increased time + increased costTight Time = increased costs + reduced scopeTight Budg...
Key Areas of Project ManagementScope ManagementIssue ManagementCost ManagementQuality ManagementCommunications Manage...
Scope Management Primarily it is the definition and control of what IS and  IS NOT included in the project.
Managing the scope of the projectProject scope management constitutes the  processes to ensure that the project includes ...
Planning Activities• Choice of Development life cycle model• Choice of Execution model• Planning of Reviews• Process Audit...
Issue Management Issues are restraints to accomplishing the deliverables of  the project. Typically identified throughou...
Issue Management Issues are restraints to accomplishing the deliverables of  the project. Issues are typically identifie...
Cost Management This process is required to ensure the project is   completed within the approved budget and includes:Res...
Cost Management This process is required to ensure the project is  completed within the approved budget and includes:   ...
Quality Management Quality Management is the process that insure the  project will meet the needs                  “confo...
Communications Management This process is necessary to ensure timely and appropriate  generation, collection, disseminati...
Team Structures• Democratic team or ego-less team• Hierarchical team• Controlled Decentralized team• Single-person army
Democratic team    • Team size is small, less than 10 members.    • All major decisions are arrived at through consensus.•...
Hierarchical team• There will be a Project Manager who willbe responsible for all project activities.• A number of Project...
Controlled Decentralized teamThere will be a project manager who is responsible  for the total project.A number of Project...
One-Person Army• In this team structure, there will be only one       person who will work on the project.  • This person ...
Rules of the Team Game• Software development is a team effort, even if the   individuals are excellent, if they do not wor...
Risk Management Risk identification and mitigation strategy Risk update and tracking Whenif new risks arise            ...
Risk Management Top 10 risk items [Boehm]  • Personnel pitfalls  • Unrealistic schedules and objectives  • Developing wro...
Change Control ManagementDefine how changes to the project scope   will be executedScope Change                          ...
Change Control ManagementDefine how changes to the project scope  will be executed    Formal change control is required ...
Quality Management Quality Management is the process that insure the  project will meet the needs via:    Quality Planni...
The Training Program• The training program has to cover– Rules and regulations of the organization– Client details and sco...
Choice of Execution Model Off-shore development  – Projects with clear requirements and subcontractor  has the capability...
Coding Guidelines• Layout of the code should be in such a way   that it is easy to read and understand.  • Names of files,...
Coding Standards• Every organization should have a set of coding   standards for each programming language used,   indicat...
Project Life Cycle
Initiation Phase Define the need Return on Investment Analysis Make or Buy Decision Budget Development
Definition Phase Determine goals, scope and project constraints Identify members and their roles Define communication c...
Planning Phase Resource Planning Work Breakdown Structure Project Schedule Development Quality Assurance Plan
Implementation Phase Execute project plan and accomplish project goals Training Plan System Build Quality Assurance
Deployment Phase User Training Production Review Start Using
Closing Phase Contractual Closeout Post Production Transition Lessons Learned
Work Breakdown Structure For defining and organizing  the total scope of a project First two levels - define a set  of p...
Project Management Tools PERT Chart- designed to  analyze and represent the  tasks involved in completing a  given projec...
Gantt Chart
PERT Chart
Critical Path Analysis CPA (NetworkAnalysis)Critical Path Analysis (CPA) is a project management tool  that: Sets out all...
Critical Activities                                         Critical activities are activities that cannot run            ...
Postmortem Analysis The 5 angles of postmortem analysis  – Processes  – People  – Technology  – Management  – Money
Need for project managementProject management is necessary because –a) a project requires huge investments which should no...
Upcoming SlideShare
Loading in …5
×

Introduction to-project-management-dabc

503 views

Published on

Published in: Business, Technology
0 Comments
1 Like
Statistics
Notes
  • Be the first to comment

No Downloads
Views
Total views
503
On SlideShare
0
From Embeds
0
Number of Embeds
2
Actions
Shares
0
Downloads
23
Comments
0
Likes
1
Embeds 0
No embeds

No notes for slide
  • Process Responsibilities The project manager normally is responsible for defining and planning the project. This results in the completion of a Project Definition and a project workplan. Once the project starts, the project manager must successfully manage and control the work, including: Identifying, tracking managing and resolving project issues Proactively disseminating project information to all stakeholders Identifying, managing and mitigating project risk Ensuring that the solution is of acceptable quality Proactively managing scope to ensure that only what was agreed to is delivered, unless changes are approved through scope management Defining and collecting metrics to give a sense for how the project is progressing and whether the deliverables produced are acceptable Managing the overall workplan to ensure work is assigned and completed on time and within budget To manage the project management processes, a person should be well organized, have great follow-up skills, be process oriented, be able to multi-task, have a logical thought process, be able to determine root causes, have good analytical ability, be a good estimator and budget manager, and have good self-discipline. People Responsibilities In addition to process skills, a project manager must have good people management skills. This includes: Having the discipline and general management skills to make sure that people follow the standard processes and procedures Establishing leadership skills to get the team to willingly follow your direction. Leadership is about communicating a vision and getting the team to accept it and strive to get there with you. Setting reasonable, challenging and clear expectations for people, and holding them accountable for meeting the expectations. This includes providing good performance feedback to team members Team building skills so that the people work together well, and feel motivated to work hard for the sake of the project and their other team members. The larger your team and the longer the project, the more important it is to have good team-building skills. Proactive verbal and written communicator skills, including good, active listening skills.  Multiple Roles Depending on the size and complexity of the project, the project manager may take on other responsibilities in addition to managing the work. For instance, the project manager may assist with gathering business requirements. Or they may help design a database management system or they may write some of the project documentation. Project management is a particular role that a person fills, even if the person who is the project manager is working in other roles as well. 
  • Like with other things, experience can be a big factor. But just as with young people, if they have the guidance while they are developing their talents they are more likely to progress. In a way we can say that project management can guide people and help them to progress in their profession.
  • SCOPE MANAGEMENT – Ensuring all the appropriate work within the project scope is completed and only the work within scope is being conducted TIME MANAGEMENT – Schedule Management COST MANAGEMENT – How costs are controlled and incurred costs are paid QUALITY MANAGEMENT – Quality Assurance Plan – How quality control is measured and satisfied HUMAN RESOURCE MANAGEMENT – Development of the project team, reporting structure, resource capacity COMMUNICATIONS MANAGEMENT – How project communications will be handled to ensure all project stakeholders are informed RISK MANAGEMENT – Risk Management plan to have all project stakeholders in agreement on how project risks will be handled (aversion, mitigation or assumption) PROCUREMENT MANAGEMENT – Procurement process, contract processes INTEGRATION MANAGEMENT – Integration of all areas of project management to develop a cohesive project plan
  • This component is used to communicate How the scope was defined How the project scope will be managed Who will manage the scope (e.g., PM, QA) Change Control
  • Issues not easily resolved are escalated for resolution. Issues are typically identified throughout the project and logged and tracked through resolution. In this section of the plan the following processes are depicted: Where issues will be maintained and tracked The process for updating issues regularly The escalation process The vehicle by which team members can access documented issues Issue… already impacting the cost, time or quality   Risk… POTENTIAL negative impact to project
  • Issues not easily resolved are escalated for resolution.
  • Resource Planning - Full Time Employees, Professional Services, Cost, and Contingency Resource Planning - The physical resources required (people, equipment, materials) and what quantities are necessary for the project Budget Budget estimates Baseline estimates Project Actuals
  • Resource Planning - Full Time Employees, Professional Services, Cost, and Contingency
  • What is Quality - conformance to requirements’ - Crosby ‘ fitness for use’ - Juran ‘ the totality of characteristics of an entity that bear on its ability to satisfy stated and implied need’ - ISO 8402:1994 Customer-Based -> Fitness for use, meeting customer expectations. Manufacturing-Based -> Conforming to design, specifications, or requirements. Having no defects. Product-Based -> The product has something that other similar products do not that adds value. Value-Based -> The product is the best combination of price and features. 5. Transcendent It is not clear what it is, but it is something good... via: Quality Planning, Quality Assurance, and Quality Control Clearly Defined Quality Performance Standards How those Quality and Performance Standards are measured and satisfied How Testing and Quality Assurance Processes will ensure standards are satisfied Continuous ongoing quality control
  • Communications planning: Determining the needs (who needs what information, when they need it, and how it will be delivered) Information Distribution: Defining who and how information will flow to the project stakeholders and the frequency Performance Reporting: Providing project performance updates via status reporting. Communications planning Information Distribution Performance Reporting Define the schedule for the Project Meetings (Team, OSC, ESC), Status Meetings and Issues Meetings to be implemented
  • Formal change control is required for all of the following Scope Change Schedule changes Technical Specification Changes Training Changes All changes require collaboration and buy in via the project sponsor’s signature prior to implementation of the changes
  • What is Quality - conformance to requirements’ - Crosby ‘ fitness for use’ - Juran ‘ the totality of characteristics of an entity that bear on its ability to satisfy stated and implied need’ - ISO 8402:1994 Customer-Based -> Fitness for use, meeting customer expectations. Manufacturing-Based -> Conforming to design, specifications, or requirements. Having no defects. Product-Based -> The product has something that other similar products do not that adds value. Value-Based -> The product is the best combination of price and features. 5. Transcendent It is not clear what it is, but it is something good...
  • Introduction to-project-management-dabc

    1. 1. Introduction to Project Management Sanjay Koul sanjayk@cdac.in
    2. 2. What is a Project? A project is a temporary endeavor undertaken to produce a unique product or service Characteristics of Unique Temporary Projects  Temporary – Definitive beginning and end  Unique – New undertaking, unfamiliar ground  A project is a set of activities which are networked in an order and aimed towards achieving the specific goals . Upon the completion of all the activities the goals of the project would have been achieved.  A project is undertaken to achieve a purpose
    3. 3.  Management - Management is the technique of understanding the problems, needs and controlling the use of resources, such as cost, time, manpower, materials, etc. Project management – It is an art of controlling the cost, time, manpower, and hardware and software resources involved in a project. Project Cycle – A project cycle basically consists of the various activities of operations, resources and the limitations imposed on them.
    4. 4.  Process – A process is part of the project which consists of simple and routine instructions to achieve a desired result of any activity of the project. A process is responsible to bring about the changes in the input fed to the process and gives out desired outputs as results of the process. Resource – It refers to manpower, machinery, money and materials required in the project. Scope – It refers to the various parameters that affect the project in its planning, formulation and executions. Project Cost – It is the budgeted expenditure of the project.
    5. 5. Some experiences-may happen
    6. 6. Project Success Customer Requirements Completed within satisfied/exceeded allocated time frame Completed within Accepted by the customer allocated budget
    7. 7. Project Failure Poor Requirements Scope Creep Gathering Unrealistic planning and Lack of resources scheduling
    8. 8. Project ManagementProject Management is the application of skills, knowledge, tools and techniques to meet the needs and expectations of stakeholders for a project.The purpose of project management is prediction and prevention, NOT recognition and reaction.Relationship with other management disciplines is essential for a project to be successful. Supporting disciplines includes law, strategic planning, logistics, human resource management and domain knowledge
    9. 9. The Project Manager (PM) A project manager is a person who manages the project. The project manager is responsible to carry out all the tasks of a project. Responsibilities of the project manager are: Budgeting and cost control Scheduling tasks Allocating resources Tracking project expenditures Ensuring technical quality Manage relations with the customer and company
    10. 10. Role of a Project Manager PeopleProcess ResponsibilitiesResponsibilities• Project issues• Disseminating project information • Implementing standard processes• Mitigating project risk • Establishing leadership skills• Quality • Setting expectations• Managing scope • Team building• Metrics • Communicator skills• Managing the overall work plan
    11. 11. Types of Project Managers• Hands-off versus hands-on managers  Most of the hands-off managers are non-technical managers who took up software project management.  Only a handful of the managers sit with the engineers and try to debug the software or at least suggest alternative approaches to solve a problem, particularly during the coding phase.• Democratic versus anarchic managers  To develop a congenial atmosphere in which the team members can give vent to their creative abilities, a democratic approach is the most ideal approach. However, one needs to be careful, freedom means responsibility, not carelessness  Proactive versus reactive managers  Reactive managers react to events. When an engineer comes and tells about a problem, he will try to resolve it.  A proactive manager takes the initiative to find the status both informally and formally. Informally, during coffee breaks, lunch breaks or at social gatherings, he gets the different viewpoints of the team members on the status and uses this information to carry out formal reviews.
    12. 12. Who will be a Good Software Engineer?People with good problem solving abilities, goodcommunication skills and team spirit make goodsoftware engineers.Not surprisingly, many organizations recruit peoplebased on an aptitude test (to test the problem solvingabilities) and not based on knowledge of programminglanguages or operating systems.
    13. 13. How does project management benefit you?You will have goal clarity and measurementYour resources will be coordinatedYour risks will be identified and managedYou will increase the possibilities of time savingsYou will increase the possibilities of cost savingsYou will increase the possibilities of achieving the agreed outcomeYou will increase the possibilities to deliver projects successfully
    14. 14. Triple Contraint Time QualityCost Scope
    15. 15. Triple ContraintIncreased Scope = increased time + increased costTight Time = increased costs + reduced scopeTight Budget = increased time + reduced scope.
    16. 16. Key Areas of Project ManagementScope ManagementIssue ManagementCost ManagementQuality ManagementCommunications ManagementRisk ManagementChange Control Management
    17. 17. Scope Management Primarily it is the definition and control of what IS and IS NOT included in the project.
    18. 18. Managing the scope of the projectProject scope management constitutes the processes to ensure that the project includes all of the work required, and only the work required, to complete the project successfully.‘Project scope has several purposes:  It defines what work is needed to complete the project objectives  It determines what is included in the project  It serves as a guide to determine what work is not needed to complete the project objectives  It serves as a point of reference for what is not included in the project
    19. 19. Planning Activities• Choice of Development life cycle model• Choice of Execution model• Planning of Reviews• Process Auditing• Project Planning Document Preparation
    20. 20. Issue Management Issues are restraints to accomplishing the deliverables of the project. Typically identified throughout the project and logged and tracked through resolution. Issue… already impacting the cost, time or quality Rope not thick
    21. 21. Issue Management Issues are restraints to accomplishing the deliverables of the project. Issues are typically identified throughout the project and logged and tracked through resolution. In this section of the plan the following processes are depicted:  Where issues will be maintained and tracked  The process for updating issues regularly  The escalation process  The vehicle by which team members can access documented issues
    22. 22. Cost Management This process is required to ensure the project is completed within the approved budget and includes:Resources Budget people equipment materialsQuantitiesTiming
    23. 23. Cost Management This process is required to ensure the project is completed within the approved budget and includes:  Resource Planning - The physical resources required (people, equipment, materials) and what quantities are necessary for the project  Budget  Budget estimates  Baseline estimates  Project Actuals
    24. 24. Quality Management Quality Management is the process that insure the project will meet the needs “conformance to requirements” - Crosby “fitness for use” - Juran “the totality of characteristics of an entity that bear on its ability to satisfy stated and implied need’ - ISO 8402:1994
    25. 25. Communications Management This process is necessary to ensure timely and appropriate generation, collection, dissemination, and storage of project information using:  Communications planning  Information Distribution  Performance Reporting  for the Project Meetings (Team, OSC, ESDefine the schedule C), Status Meetings and Issues Meetings to be implemented
    26. 26. Team Structures• Democratic team or ego-less team• Hierarchical team• Controlled Decentralized team• Single-person army
    27. 27. Democratic team • Team size is small, less than 10 members. • All major decisions are arrived at through consensus.• Regular interaction amongst all the team members.• The senior-most person acts as the coordinator who will interface with the client for all administrative and managerial work.
    28. 28. Hierarchical team• There will be a Project Manager who willbe responsible for all project activities.• A number of Project Leaders report to the ProjectManager, each Project Leader is responsible for amodule.• A number of engineers report to each Project Leader.The engineers are responsible for sub-modules.
    29. 29. Controlled Decentralized teamThere will be a project manager who is responsible for the total project.A number of Project Leaders report to the Project Manager. Each Project Leader is responsible for a module.A team of engineers act as a democratic team and any decision related to this group is taken collectively. The senior most engineer in the group will act as the Project Leader
    30. 30. One-Person Army• In this team structure, there will be only one person who will work on the project. • This person will report to the project manager periodically. • For prototype development of a high-end creative products, this is a good model. • Many products were initially developed by a single-person armies: UNIX and C being the best example
    31. 31. Rules of the Team Game• Software development is a team effort, even if the individuals are excellent, if they do not work as a cohesive team, the project will not succeed.• The team members should interact with each other regularly.• The team members should communicate with the Project Manager/Leader regularly.• Formal review meetings should be held periodically and all the team members have to openly discuss all the issues.
    32. 32. Risk Management Risk identification and mitigation strategy Risk update and tracking Whenif new risks arise Risk… POTENTIAL negative impact to projectTree – location, accessibility, Weather ownership
    33. 33. Risk Management Top 10 risk items [Boehm] • Personnel pitfalls • Unrealistic schedules and objectives • Developing wrong interface functions • Wrong user interface • Gold plating • Continuous stream of requirements changes • Shortfalls in externally furnished/purchased components • Shortfalls in externally performed tasks • Real time performance • Straining computer science capabilities
    34. 34. Change Control ManagementDefine how changes to the project scope will be executedScope Change Technical Specification Changes Schedule changesAll changes require collaboration and buy in via the project sponsor’s signatureprior to implementation of the changes
    35. 35. Change Control ManagementDefine how changes to the project scope will be executed  Formal change control is required for all of the following 1. Scope Change 2. Schedule changes 3. Technical Specification Changes 4. Training Changes All changes require collaboration and buy in via the project sponsor’s signature prior to implementation of the changes
    36. 36. Quality Management Quality Management is the process that insure the project will meet the needs via:  Quality Planning, Quality Assurance, and Quality Control  ClearlyDefined Quality Performance Standards  How those Quality and Performance Standards are measured and satisfied  How Testing and Quality Assurance Processes will ensure standards are satisfied  Continuous ongoing quality control
    37. 37. The Training Program• The training program has to cover– Rules and regulations of the organization– Client details and scope of the project– Communication skills– Team work– Software Development tools– Application domain– Software Engineering Principles– Quality standards to be followed
    38. 38. Choice of Execution Model Off-shore development – Projects with clear requirements and subcontractor has the capability in the specific area; maintenance projects • On-site development – Projects without clear requirements/changing requirements; and constant interaction with client is required. • On-site cum off-shore development – If the project can be partly done using off-shore execution model.
    39. 39. Coding Guidelines• Layout of the code should be in such a way that it is easy to read and understand. • Names of files, classes, functions, variables etc. should be meaningful. • Exceptions should be handled. • Internal (on-line) documentation should be embedded in the code. • Function size to be limited to 40/50 lines
    40. 40. Coding Standards• Every organization should have a set of coding standards for each programming language used, indicating: – Backup mechanism – Naming conventions – Internal documentation to be included.
    41. 41. Project Life Cycle
    42. 42. Initiation Phase Define the need Return on Investment Analysis Make or Buy Decision Budget Development
    43. 43. Definition Phase Determine goals, scope and project constraints Identify members and their roles Define communication channels, methods, frequency and content Risk management planning
    44. 44. Planning Phase Resource Planning Work Breakdown Structure Project Schedule Development Quality Assurance Plan
    45. 45. Implementation Phase Execute project plan and accomplish project goals Training Plan System Build Quality Assurance
    46. 46. Deployment Phase User Training Production Review Start Using
    47. 47. Closing Phase Contractual Closeout Post Production Transition Lessons Learned
    48. 48. Work Breakdown Structure For defining and organizing the total scope of a project First two levels - define a set of planned outcomes that collectively and exclusively represent 100% of the project scope. Subsequent levels - represent 100% of the scope of their parent node
    49. 49. Project Management Tools PERT Chart- designed to analyze and represent the tasks involved in completing a given project  Gantt Chart - popular type of bar chart that illustrates a project schedule
    50. 50. Gantt Chart
    51. 51. PERT Chart
    52. 52. Critical Path Analysis CPA (NetworkAnalysis)Critical Path Analysis (CPA) is a project management tool that: Sets out all the individual activities that make up a larger project. Shows the order in which activities have to be undertaken. Shows which activities can only taken place once other activities have been completed. Shows which activities can be undertaken simultaneously, thereby reducing the overall time taken to complete the whole project. Shows when certain resources will be needed – for example, a crane to be hired for a building sit
    53. 53. Critical Activities Critical activities are activities that cannot run late. For critical activities: Latest finish — Earliest start = length of activity 2 3 4 A(3) B(8) 1 1 42 42 D(12) 1 3 2 2 5 E(10) 0 0 C(7) F(20) 4 22 22The green arrows mark the critical activities,which form the critical path. The critical path(s)must form a continuous route from the start nodeto the finish node.
    54. 54. Postmortem Analysis The 5 angles of postmortem analysis – Processes – People – Technology – Management – Money
    55. 55. Need for project managementProject management is necessary because –a) a project requires huge investments which should not go wasteb) a loss in any project would have direct or indirect impact on the societyc) prevent failures in projectsd) scope of the project activity may undergo a changee) technology used may change during the course of project executionf) consequences of negativity in project related problems could be very seriousg) changes in economic conditions may affect a project

    ×