Document id Title Organisation / Author Date Status
xxx IFC Infra Overall Architecture – Project Plan TUM / AndrÊ Borrmann 29/01/2016 final
1 Project Execution Plan
Having standardized infrastructure asset data available throughout the lifecycle of the facility is an im-
portant key to a higher efficiency in planning, constructing, operating and maintaining our infrastructure.
A comprehensive neutral data model capable to present both semantic as well as geometric aspects is
necessary for enabling data exchange and open data access in the context of planning, realization and
maintenance of road and rail infrastructure.
Recently, a number of national standardization initiatives have emerged which developed proposals for
standardized data exchange schemata. Examples are the Korean IFC-Road project, the Chinese IFC-Rail
project and the IFC-Bridge project led by the French chapter. Due to the overlapping scope of the diverse
national initiatives, partly concurrent data elements have been proposed.
In order to harmonize the diverse proposals and provide a sound foundation for the future international
standardization of Road, Rail, Bridge and Tunnel data exchange formats, this project will provide a
framework which will serve as common basis for all infrastructure activities. The framework includes
commonly used data structures such as the spatial aggregation hierarchy for linear (horizontal) facilities
as well as guidelines regarding the data modeling such as the maximum inheritance level or the use of
enumeration types.
Particular attention is paid to enabling a future integration of GIS and InfraBIM systems by ensuring best
possible compatibility between the proposed IFC-Infra extensions and the InfraGML data model. This is
achieved by developing a joint conceptual model using UML class diagrams.
This project development plan describes the necessary steps to develop the integration framework.
1.1 Objectives
The IFC Infra Integration Framework is set to achieve:
ī‚§ Analysis of the currently available drafts of the IFC infrastructure extension initiatives with respect to
joint / overlapping areas project, including
ī‚§ the IFC-Road project by the Korean chapter (note: the Korean IFC-Road project had already been
analysed and modifications had been suggested by MSG)
ī‚§ the IFC-Rail project by the Chinese chapter
ī‚§ the IFC-Bridge project led by the French chapter
ī‚§ Definition of jointly used data structures as a common basis, including
ī‚§ terrain geometry
ī‚§ earthwork geometries (cut and fill volumes)
ī‚§ subsoil modelling
ī‚§ cant / super elevation
ī‚§ clearance
ī‚§ spatial aggregation hierarchy for linear assets
ī‚§ Provision of modelling guidelines for bSI Infrastructure extension projects
ī‚§ consistent extension of the different class trees for spatial structure, element and element type
structure, element breakdown structure
ī‚§ common criteria for the class inheritance structure (by infrastructure discipline, like IfcBridgeEle-
ment, IfcRoadElement, IfcRailElement, or by common functionality)
Page no. Author
2 AndrÊ Borrmann, Thomas Liebich
ī‚§ common criteria for reusing existing classes from the building domain, like IfcWall, IfcSlab
ī‚§ maximum class inheritance levels
ī‚§ usage of object type libraries
ī‚§ usage of enumerations and property sets
ī‚§ usage of coordinate reference system
ī‚§ usage of alignment and linear references for positioning purposes
ī‚§ preferred geometry description method for identified use cases
ī‚§ Ability to map common infrastructure information between InfraGML (developed by OGC) and en-
hanced version of IFC
ī‚§ A foundation for standardized data exchange during the entire lifecycle, including requirements, de-
sign, construction, operation, maintenance and destruction/recycling
These objectives have to be realized within the current architecture of the IFC schema and shall lead to a
downward compatible extension.
1.2 Deliverables
In order to achieve the objectives the following main deliveries are developed during the project
ī‚§ A clear definition of the scope for common infrastructure information in this standard and references
to other standards covering other scopes relevant for infrastructure information. In order to provide
context to all other descriptions, this includes the definition of a reference process description in the
form of a high level process map containing and defining the most important stages, stakeholders and
exchanges
ī‚§ A clear definition (ontology) of common infrastructure information in the scope of this standard as the
conceptual schema jointly developed by buildingSMART and OGC using UML
ī‚§ The general extension to the buildingSMART IFC4 schema comprising the common infrastructure
model, delivered as a recommendation to enhance the EXPRESS schema in a consistent way
ī‚§ A modelling guideline for the infrastructure domain specific projects on how to consistently extend the
IFC structure
ī‚§ Facilitation of two review panels
ī‚§ From client and domain expert side to state the requirements and assess the solution
ī‚§ From software vendor side to assess the implementability of the solution
1.3 Project execution
The project work is carried out by the project team. At least one member of the project team is member of
buildingSMART Model Support Group (MSG) to carry out the schema extension. The project leader will be
determined and leads the project team.
The work is supervised by the Infrastructure Integration steering committee of the Infrastructure room,
where the stakeholders are adequately represented (see Figure 1).
The steering committee will nominate a representative to be the direct contact person for the project
leader. The project leader reports to the steering committee and will work closely with the steering com-
mittee representative during the execution of the project.
Proposal:
ī‚§ Steering committee representative for the Infrastructure Integration project – Henk Schaap
ī‚§ Project leader – AndrÊ Borrmann, Technical University Munich, Germany
The steering committee (in close collaboration with the project leader) will invite client representatives,
domain experts, and software vendor representatives to participate in the “Expert panel”.
Page no. Author
3 AndrÊ Borrmann, Thomas Liebich
The project team is supported by management support staff for building up the expert panel, workshop
invitations, taking minutes and distributing minutes and materials.
Figure 1 Organisational structure, in accordance with the Infrastructure Room Charter
2 Work Plan
The work plan of the Infra Integration project is based on existing work experience coming from IFC-
Alignment development and preliminary work in buildingSMART, OGC, and other initiatives.
2.1 Existing Work
The project will built upon the significant work by the Korean IFC-Road project, the Chinese IFC-Rail pro-
ject and the IFC-Bridge project led by the French chapter. All three projects have defined extensive data
models for describing infrastructure assets. However, the projects have developed mostly independent
from each other. In consequence, diverging or even incompatible approaches to modeling commonly used
exist. The proposed project will analyze in detail the proposed data models and incorporate them to the
largest extent possible. The project will also take into consideration the ongoing Infra Asset Management
Requirements project, as well as other relevant activities, such as Japanese developments on Tunnels.
Beside the IFC-related initiatives, there are also other data models. LandXML is a widely adopted quasi
standard for representing roads. However, it has a number of modelling errors and it is no longer actively
maintained. The Finnish infrastructure clients initiated the Finnish Inframodel development1, it docu-
ments and enhances LandXML1.2 for well-defined use cases; this development has also lead to
buildingSMART Recommended Technical Report 2(adopted by InfraRoom in March 2015).
1 See http://cic.vtt.fi/inframodel/
2 See http://cic.vtt.fi/bSI_LandXML12_MVD/
Page no. Author
4 AndrÊ Borrmann, Thomas Liebich
OGC has created a “Land and Infrastructure” working group with the goal to develop InfraGML3.
OKSTRA4 is used for road information systems in Germany. OKSTRA standard is only target for the Ger-
man market, since the complete data model is in German language.
OpenBrIM5 is an XML file format for bridges, however it is only poorly supported by software packages.
In the Singapore bSI Standards Summit Fall 2015, the Infrastructure room concluded the following resolu-
tion: “
The InfraRoom resolves to establish an Overall Architecture Working Group to address the issues of integra-
tion across the evolving Infrastructure standards development. The InfraRoom appreciates the results from
the discussion of issues during the session on Integration.
The InfraRoom acknowledges the work done by national IFC development programs on Roads, Railways,
Bridges and Tunnels, and asks that they provide their conceptual schemas as a resource for the Overall Archi-
tecture.
The InfraRoom acknowledges the urgency of developing the Overall Architecture for Infrastructure Exten-
sions and asks all parties involved to take this into account.”
2.2 Project work package structure
The work packages (WP) of the Infra Integration project are:
WP0 Completion of Project Execution Plan
Based on the project proposal and the Memorandum of Understanding a full project execution plan has to
be developed, showing work packages, deliverables, work schedule, budget plan, project team and the
project organization in terms of responsibilities and reporting lines.
Tasks: T0.1 Development of Project Execution Plan
T0.2 Agreement of Project Execution Plan
Deliverable: Completed Project Execution Plan
Milestone: M0, 31.01.2016
WP 1 Requirement Analysis
Analyze the requirements of existing data exchange processes in infrastructure projects. The require-
ments of a neutral data model capable to present both semantic as well as geometric aspects have to be
determined. Typical user scenarios and use cases have to be captured and documented. Existing data ex-
change standards for infrastructure projects such as the LandXML standard should also be taken into con-
sideration. Methods of the Information Delivery Manual (IDM) are used to create process maps and ex-
change requirements from the user requirements. It has to be documented in detail, who are the users of
the IFC infrastructure extension and for what purpose the data is needed.
The client and domain expert panel will contribute to the requirement analysis and validation. A strong
coordination between the project team and the expert panel will be established.
Tasks: T1.0 Define complete high level bSI infra scope.
T1.1 Select and define scope and use cases for this project (subset of T1.0)
T1.2 Analysis of Rail exchange requirements
T1.3 Analysis of Road exchange requirements
3 See http://geospatial.blogs.com/geospatial/2013/12/a-proposal-to-replace-landxml-with-infragml.html
4 See http://www.okstra.de/
5 See http://openbrim.org/Schema2.aspx
Page no. Author
5 AndrÊ Borrmann, Thomas Liebich
T1.4 Analysis of Bridge exchange requirements
T1.5 Analysis of Tunnel exchange requirements
T1.6 Identification of common exchange requirements
T1.7 Validate common exchange requirements (with WP3).
T1.8 Refinement of scope and use cases
Deliverable: [1] Requirement Analysis, including fine-tuned scope definition
Milestone: [1] M1 30.04.2016
WP2 IFC Schema Extension and Extension Modelling Guidelines
The scope of the model is defined from the outcome of the WP1. A model extension for IFC is defined as a
conceptional schema using the Unified Model Language (UML) as a graphical notation. The corresponding
EXPRESS schema and the XSD schema are derived from the conceptional schema. The schema is docu-
mented using the definitions from the requirement analysis. .
Different stages of the IFC schema will be presented to the domain expert and software expert panels. The
schema extension needs to be incrementally improved with the feedback from these panels.
Tasks: T2.1 Analysis of proposed IFC-Road extension
T2.2 Analysis of proposed IFC-Rail extension
T2.3 Analysis of proposed IFC-Bridge extension
T2.4 Analysis of proposed IFC-Tunnel extension
T2.5 Develop draft conceptual schema
T2.6 Validate draft conceptual schema
T2.7 Develop final IFC4 extension
T2.8 Validate final IFC4 extension (with WP3)
T2.9 Develop modelling guidelines for bSI infrastructure extension projects
Deliverables: [1] Draft IFC4 schema extension
[2] Final IFC4 schema extension
[3] Final IFC4 extension documentation
Milestones: [1] M2 31.07.2016
[2] M3 31.10.2016
[3] M4 15.12.2016
WP3 Facilitate the expert panels
Facilitate the expert panels (both for clients / domain experts and for software experts). Hold regular
meetings with the panels. Inform them via email groups and a development blog and other social media
activities.
Tasks: T3.1 Set-up of expert panels
T3.2 Facilitate reviews with the expert panel
Deliverables: [1] Expert panel discussion at project start - 01.02.2016
[2] Expert panel discussion prior to Milestone 1 – 15.04.2016
[3] Expert panel discussion prior to Milestone 2 – 15.07.2016
[4] Expert panel discussion prior to Milestone 3 – 15.10.2016
[5] Expert panel discussion prior to Milestone 4 – 30.11.2016
WP4 Project management
Manage the technical work of the project, including the reporting to the steering committees according to
Figure 1. Write quarterly reports and inform the stakeholders on progress. Cooperate with the project
Page no. Author
6 AndrÊ Borrmann, Thomas Liebich
representative. Organize the collaboration with OGC, in particular with the “Land and infrastructure” SWG
for the joint development of the conceptual schema.
Tasks: T4.1 Project management
Deliverables: Quarterly project progress reports
3 Work breakdown (activities per work package)
WP0 Completion of the Project Execution Plan
Activities:
ī‚§ Develop the project execution plan (scope, schedule, budget)
ī‚§ Form the project team
ī‚§ Present the Project Execution Plan to the stakeholders and the Infrastructure steering group
ī‚§ Achieve agreement and initiate the kick-off of the project work
WP 1 Requirement Analysis
Activities:
ī‚§ Define a reference process description in the form of a high level process map containing and defining
the most important stages, stakeholders and exchanges to provide context to all other descriptions
ī‚§ Informally select and document typical user scenarios and use cases of different stakeholders for
ī‚§ Road design, procurement, construction, operation, maintenance and destruction/recycling
ī‚§ Railway design, procurement, construction, operation, maintenance and destruction/recycling
ī‚§ Bridge design, procurement, construction, operation, maintenance and destruction/recycling
Note: Limit scenarios to those relevant for this standard. There might be scenarios that’s more rele-
vant for e. g GIS or ITS standards.
ī‚§ Identify exchange scenarios with highest priority on the basis of the importance for the international
stakeholders
ī‚§ Formally describe which data is required in data exchanges of infrastructure projects (IDM method)
ī‚§ Validate refined scope against use case of the model
ī‚§ Request feedback from users and software expert panel.
These steps need to be repeated and the model scope needs to be incrementally refined.
Risks:
ī‚§ No consensus in expert panel
ī‚§ Requirements can be misunderstood by project team
ī‚§ Some important requirements could be missing in the requirements review
ī‚§ Unimportant requirements that are needed only by one stakeholder could be misleadingly included in
the requirement analysis
Risk Measures:
ī‚§ front end focus on discussion and consensus in order to be able to escalate in time
ī‚§ Make a review with stakeholders to find out if the requirement were correctly determined.
ī‚§ Count the number of stakeholders that needs a certain requirement to find out the importance
Page no. Author
7 AndrÊ Borrmann, Thomas Liebich
WP2 IFC Schema Extension and Extension Modelling Guidelines
Activities:
ī‚§ Develop a conceptual schema comprising all information within the refined scope of WP1
ī‚§ Align this work with the Land & Infrastructure conceptual schema developed in parallel in OGC
ī‚§ Extend the IFC4 schema based on the conceptual schema
ī‚§ Complete the IFC4 extension, and guarantee its syntactical correctness
ī‚§ Complete the overall documentation of the model extension
ī‚§ Develop modelling guidelines to be followed in bSI infrastructure extension projects
Risks:
ī‚§ A common conceptual schema between bSI and OGC cannot be achieved
ī‚§ The extension within the current IFC architecture is too complex
ī‚§ The resulting IFC extension does not capture all requirements defined in WP1
ī‚§ The resulting IFC extension proves too difficult or too ambiguous to be implemented efficiently
Risk Measures:
ī‚§ Involve OGC technical experts in the project
ī‚§ Get involved in OGC “Land and Infrastructure” SWG
ī‚§ Include the domain and the software expert panel in reviewing the conceptual schema
ī‚§ Test the resulting IFC4 extension (and MVD) in WP3
WP3 Facilitate the expert panels
Activities:
ī‚§ Set-up domain expert panel
ī‚§ Set-up software expert panel
ī‚§ Provide intermediate project results to the expert panels (at least before each milestone)
ī‚§ Facilitate online meetings with the expert panels
ī‚§ Integrate the results into the work packages
Risks:
ī‚§ Inadequate representation within expert panels
ī‚§ Inactiveness of some experts (due to voluntary nature of participation)
Risk Measures:
ī‚§ Involve stakeholders and Infrastructure room in selection of expert panels
ī‚§ Show stakeholders’ commitment and realistic goals to experts to get better responses
WP4 Project Management
Activities:
ī‚§ Progress reports, invoicing, representation in bSI, coordination with OGC
WP5 Communication and Dissemination
Page no. Author
8 AndrÊ Borrmann, Thomas Liebich
Activities:
ī‚§ Communication within the project team and within bSI via Infranet
ī‚§ Communication to the general public via project website
ī‚§ Dissemination of the project results
4 Project Team
The technical project team will comprise technical and IFC modeling experts from buildingSMART Inter-
national Model Support Group (MSG), Open Geospatial Consortium (OGC) and a number of research insti-
tutes from around the word.
The following persons are named already:
ī‚§ AndrÊ Borrmann, Project Lead
ī‚§ Thomas Liebich, bSI Model Support Group
ī‚§ Tim Chipman, bSI Model Support Group
ī‚§ Jim Plume, University of New South Wales (UNSW)
ī‚§ Julian Amann, Technical University Munich (TUM)
ī‚§ Dominic Singer, Technical University Munich (TUM)
ī‚§ Juha Hyvärinen, VTT Technical Research Centre of Finland (VTT)
ī‚§ Nobuyoshi Yabuki, Osaka University (OU)
ī‚§ Francois Grobler, bSI IFC Roads and Railways project
ī‚§ Hyunjoo Kim, University of Seoul (UOS)
ī‚§ Yushen Liu, China Railway BIM Alliance (CRBIM)
ī‚§ Hyunseok Moon, Korean Institute of Civil Engineering and Building Technology (KICT)
ī‚§ Christophe Castaing, bSI IFC-Bridge project
ī‚§ Paul Scarponcini, OGC (based on the MoU agreement between bSI and OGC)
ī‚§ Laura Mol, Gobar Adviseurs
The nomination of the domain and software expert panel shall be done in collaboration with the stake-
holders and the Infrastructure room.
5 Cost breakdown
WP0 3.200,00 â‚Ŧ
WP1 48.900,00 â‚Ŧ
WP2 47.400,00 â‚Ŧ
WP3 22.600,00 â‚Ŧ
WP4 14.400,00 â‚Ŧ
WP5 1.200,00 â‚Ŧ
Travel 13.000,00 â‚Ŧ
Total 150.700,00 â‚Ŧ
bSI Overhead 22.605,00 â‚Ŧ
Project Sum 173.305,00 â‚Ŧ
Page no. Author
9 AndrÊ Borrmann, Thomas Liebich
6 Schedule
The project will commence on February 1st, 2016 and will be completed on December 15th, 2016. The pre-
project phase for WP0 “full project execution plan” is from 01.11.2015 till 31.01.2016.
The main milestones are aligned with the buildingSMART International meetings, in March and October
2016.
Detailed schedule:
ID Work Package Start End
2015
MrzJan FebDez SepJun NovOktApr Mai Jul AugNov
1 15.12.201501.11.2015WP0: Completion of the project plan
2 30.04.201601.02.2016WP1: Requirement Analysis
4 15.12.201601.05.2016WP2: IFC Extensions & Guidelines
8 15.12.201601.02.2016WP3: Facilitate the expert panel
9 15.12.201615.12.2015WP4: Project management
30.04.201630.04.2016Milestone 1
2016
3
5 31.07.201631.07.2016Milestone 2
6 31.10.201631.10.2016Milestone 3
7 15.12.201615.12.2016Milestone 4
Dez
Figure 2: Project Gantt chart

More Related Content

Similar to Architecture project execution plan

design of g building.pdf
design of g building.pdfdesign of g building.pdf
design of g building.pdfNikhilMoviechanger
 
D6.2 Pan European Plan4all Platform
D6.2 Pan European Plan4all PlatformD6.2 Pan European Plan4all Platform
D6.2 Pan European Plan4all Platformplan4all
 
D6.1 deployment of_platforms_on_local_regional_and_national_levels
D6.1 deployment of_platforms_on_local_regional_and_national_levelsD6.1 deployment of_platforms_on_local_regional_and_national_levels
D6.1 deployment of_platforms_on_local_regional_and_national_levelsplan4all
 
Framework for SMART City Deployment V1.0
Framework for SMART City Deployment V1.0Framework for SMART City Deployment V1.0
Framework for SMART City Deployment V1.0Paul Goff
 
4D_BIM_for_Construction_Planning_and_Environmental.pdf
4D_BIM_for_Construction_Planning_and_Environmental.pdf4D_BIM_for_Construction_Planning_and_Environmental.pdf
4D_BIM_for_Construction_Planning_and_Environmental.pdfSemra D.
 
SPOTTED_Francesco Meroddu.pptx
SPOTTED_Francesco Meroddu.pptxSPOTTED_Francesco Meroddu.pptx
SPOTTED_Francesco Meroddu.pptxFIWARE
 
F & A D R E A M I T Baasansuren Burmaa
F &  A  D R E A M  I T  Baasansuren  BurmaaF &  A  D R E A M  I T  Baasansuren  Burmaa
F & A D R E A M I T Baasansuren Burmaapanall2009
 
Application Of Building Information Modeling (BIM) To Civil Engineering Projects
Application Of Building Information Modeling (BIM) To Civil Engineering ProjectsApplication Of Building Information Modeling (BIM) To Civil Engineering Projects
Application Of Building Information Modeling (BIM) To Civil Engineering ProjectsMichele Thomas
 
Whitepaper: How Autodesk Supports Open Data Exchange Standards
Whitepaper: How Autodesk Supports Open Data Exchange Standards Whitepaper: How Autodesk Supports Open Data Exchange Standards
Whitepaper: How Autodesk Supports Open Data Exchange Standards Sander Lijbers
 
IRJET- Application of 4D CAD BIM Technology in Construction Scheduling
IRJET- Application of 4D CAD BIM Technology in Construction SchedulingIRJET- Application of 4D CAD BIM Technology in Construction Scheduling
IRJET- Application of 4D CAD BIM Technology in Construction SchedulingIRJET Journal
 
D2.2 Workflow Guidelines
D2.2  Workflow Guidelines D2.2  Workflow Guidelines
D2.2 Workflow Guidelines Gravitate Project
 
Changes To The Draft Business Plan As Agreed At The Kick Off Meeting On 2010 ...
Changes To The Draft Business Plan As Agreed At The Kick Off Meeting On 2010 ...Changes To The Draft Business Plan As Agreed At The Kick Off Meeting On 2010 ...
Changes To The Draft Business Plan As Agreed At The Kick Off Meeting On 2010 ...Friso de Jong
 
Home page e infracentral egi conference_work shop_20170509 catania
Home page e infracentral egi conference_work shop_20170509 cataniaHome page e infracentral egi conference_work shop_20170509 catania
Home page e infracentral egi conference_work shop_20170509 cataniaGaelle de Meeus d'Argenteuil
 
Advanced infrastructure for pan european collaborative engineering - E-colleg
Advanced infrastructure for pan european collaborative engineering - E-collegAdvanced infrastructure for pan european collaborative engineering - E-colleg
Advanced infrastructure for pan european collaborative engineering - E-collegXavier Warzee
 
Building Information Modeling (BIM) & Industry Foundation Classes (IFC)
Building Information Modeling (BIM)  & Industry Foundation Classes (IFC)Building Information Modeling (BIM)  & Industry Foundation Classes (IFC)
Building Information Modeling (BIM) & Industry Foundation Classes (IFC)metalalp
 

Similar to Architecture project execution plan (20)

design of g building.pdf
design of g building.pdfdesign of g building.pdf
design of g building.pdf
 
Cora For ITDG
Cora For ITDGCora For ITDG
Cora For ITDG
 
Fabrice Clari - EC-FIA
Fabrice Clari - EC-FIAFabrice Clari - EC-FIA
Fabrice Clari - EC-FIA
 
D6.2 Pan European Plan4all Platform
D6.2 Pan European Plan4all PlatformD6.2 Pan European Plan4all Platform
D6.2 Pan European Plan4all Platform
 
D6.1 deployment of_platforms_on_local_regional_and_national_levels
D6.1 deployment of_platforms_on_local_regional_and_national_levelsD6.1 deployment of_platforms_on_local_regional_and_national_levels
D6.1 deployment of_platforms_on_local_regional_and_national_levels
 
Framework for SMART City Deployment V1.0
Framework for SMART City Deployment V1.0Framework for SMART City Deployment V1.0
Framework for SMART City Deployment V1.0
 
UDMS 2004
UDMS 2004UDMS 2004
UDMS 2004
 
4D_BIM_for_Construction_Planning_and_Environmental.pdf
4D_BIM_for_Construction_Planning_and_Environmental.pdf4D_BIM_for_Construction_Planning_and_Environmental.pdf
4D_BIM_for_Construction_Planning_and_Environmental.pdf
 
SPOTTED_Francesco Meroddu.pptx
SPOTTED_Francesco Meroddu.pptxSPOTTED_Francesco Meroddu.pptx
SPOTTED_Francesco Meroddu.pptx
 
F & A D R E A M I T Baasansuren Burmaa
F &  A  D R E A M  I T  Baasansuren  BurmaaF &  A  D R E A M  I T  Baasansuren  Burmaa
F & A D R E A M I T Baasansuren Burmaa
 
IRW 2004
IRW  2004IRW  2004
IRW 2004
 
Application Of Building Information Modeling (BIM) To Civil Engineering Projects
Application Of Building Information Modeling (BIM) To Civil Engineering ProjectsApplication Of Building Information Modeling (BIM) To Civil Engineering Projects
Application Of Building Information Modeling (BIM) To Civil Engineering Projects
 
Whitepaper: How Autodesk Supports Open Data Exchange Standards
Whitepaper: How Autodesk Supports Open Data Exchange Standards Whitepaper: How Autodesk Supports Open Data Exchange Standards
Whitepaper: How Autodesk Supports Open Data Exchange Standards
 
IRJET- Application of 4D CAD BIM Technology in Construction Scheduling
IRJET- Application of 4D CAD BIM Technology in Construction SchedulingIRJET- Application of 4D CAD BIM Technology in Construction Scheduling
IRJET- Application of 4D CAD BIM Technology in Construction Scheduling
 
D2.2 Workflow Guidelines
D2.2  Workflow Guidelines D2.2  Workflow Guidelines
D2.2 Workflow Guidelines
 
FTA ITS Training
FTA ITS TrainingFTA ITS Training
FTA ITS Training
 
Changes To The Draft Business Plan As Agreed At The Kick Off Meeting On 2010 ...
Changes To The Draft Business Plan As Agreed At The Kick Off Meeting On 2010 ...Changes To The Draft Business Plan As Agreed At The Kick Off Meeting On 2010 ...
Changes To The Draft Business Plan As Agreed At The Kick Off Meeting On 2010 ...
 
Home page e infracentral egi conference_work shop_20170509 catania
Home page e infracentral egi conference_work shop_20170509 cataniaHome page e infracentral egi conference_work shop_20170509 catania
Home page e infracentral egi conference_work shop_20170509 catania
 
Advanced infrastructure for pan european collaborative engineering - E-colleg
Advanced infrastructure for pan european collaborative engineering - E-collegAdvanced infrastructure for pan european collaborative engineering - E-colleg
Advanced infrastructure for pan european collaborative engineering - E-colleg
 
Building Information Modeling (BIM) & Industry Foundation Classes (IFC)
Building Information Modeling (BIM)  & Industry Foundation Classes (IFC)Building Information Modeling (BIM)  & Industry Foundation Classes (IFC)
Building Information Modeling (BIM) & Industry Foundation Classes (IFC)
 

Recently uploaded

Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docxPoojaSen20
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 

Recently uploaded (20)

Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docx
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 

Architecture project execution plan

  • 1. Document id Title Organisation / Author Date Status xxx IFC Infra Overall Architecture – Project Plan TUM / AndrÊ Borrmann 29/01/2016 final 1 Project Execution Plan Having standardized infrastructure asset data available throughout the lifecycle of the facility is an im- portant key to a higher efficiency in planning, constructing, operating and maintaining our infrastructure. A comprehensive neutral data model capable to present both semantic as well as geometric aspects is necessary for enabling data exchange and open data access in the context of planning, realization and maintenance of road and rail infrastructure. Recently, a number of national standardization initiatives have emerged which developed proposals for standardized data exchange schemata. Examples are the Korean IFC-Road project, the Chinese IFC-Rail project and the IFC-Bridge project led by the French chapter. Due to the overlapping scope of the diverse national initiatives, partly concurrent data elements have been proposed. In order to harmonize the diverse proposals and provide a sound foundation for the future international standardization of Road, Rail, Bridge and Tunnel data exchange formats, this project will provide a framework which will serve as common basis for all infrastructure activities. The framework includes commonly used data structures such as the spatial aggregation hierarchy for linear (horizontal) facilities as well as guidelines regarding the data modeling such as the maximum inheritance level or the use of enumeration types. Particular attention is paid to enabling a future integration of GIS and InfraBIM systems by ensuring best possible compatibility between the proposed IFC-Infra extensions and the InfraGML data model. This is achieved by developing a joint conceptual model using UML class diagrams. This project development plan describes the necessary steps to develop the integration framework. 1.1 Objectives The IFC Infra Integration Framework is set to achieve: ī‚§ Analysis of the currently available drafts of the IFC infrastructure extension initiatives with respect to joint / overlapping areas project, including ī‚§ the IFC-Road project by the Korean chapter (note: the Korean IFC-Road project had already been analysed and modifications had been suggested by MSG) ī‚§ the IFC-Rail project by the Chinese chapter ī‚§ the IFC-Bridge project led by the French chapter ī‚§ Definition of jointly used data structures as a common basis, including ī‚§ terrain geometry ī‚§ earthwork geometries (cut and fill volumes) ī‚§ subsoil modelling ī‚§ cant / super elevation ī‚§ clearance ī‚§ spatial aggregation hierarchy for linear assets ī‚§ Provision of modelling guidelines for bSI Infrastructure extension projects ī‚§ consistent extension of the different class trees for spatial structure, element and element type structure, element breakdown structure ī‚§ common criteria for the class inheritance structure (by infrastructure discipline, like IfcBridgeEle- ment, IfcRoadElement, IfcRailElement, or by common functionality)
  • 2. Page no. Author 2 AndrÊ Borrmann, Thomas Liebich ī‚§ common criteria for reusing existing classes from the building domain, like IfcWall, IfcSlab ī‚§ maximum class inheritance levels ī‚§ usage of object type libraries ī‚§ usage of enumerations and property sets ī‚§ usage of coordinate reference system ī‚§ usage of alignment and linear references for positioning purposes ī‚§ preferred geometry description method for identified use cases ī‚§ Ability to map common infrastructure information between InfraGML (developed by OGC) and en- hanced version of IFC ī‚§ A foundation for standardized data exchange during the entire lifecycle, including requirements, de- sign, construction, operation, maintenance and destruction/recycling These objectives have to be realized within the current architecture of the IFC schema and shall lead to a downward compatible extension. 1.2 Deliverables In order to achieve the objectives the following main deliveries are developed during the project ī‚§ A clear definition of the scope for common infrastructure information in this standard and references to other standards covering other scopes relevant for infrastructure information. In order to provide context to all other descriptions, this includes the definition of a reference process description in the form of a high level process map containing and defining the most important stages, stakeholders and exchanges ī‚§ A clear definition (ontology) of common infrastructure information in the scope of this standard as the conceptual schema jointly developed by buildingSMART and OGC using UML ī‚§ The general extension to the buildingSMART IFC4 schema comprising the common infrastructure model, delivered as a recommendation to enhance the EXPRESS schema in a consistent way ī‚§ A modelling guideline for the infrastructure domain specific projects on how to consistently extend the IFC structure ī‚§ Facilitation of two review panels ī‚§ From client and domain expert side to state the requirements and assess the solution ī‚§ From software vendor side to assess the implementability of the solution 1.3 Project execution The project work is carried out by the project team. At least one member of the project team is member of buildingSMART Model Support Group (MSG) to carry out the schema extension. The project leader will be determined and leads the project team. The work is supervised by the Infrastructure Integration steering committee of the Infrastructure room, where the stakeholders are adequately represented (see Figure 1). The steering committee will nominate a representative to be the direct contact person for the project leader. The project leader reports to the steering committee and will work closely with the steering com- mittee representative during the execution of the project. Proposal: ī‚§ Steering committee representative for the Infrastructure Integration project – Henk Schaap ī‚§ Project leader – AndrÊ Borrmann, Technical University Munich, Germany The steering committee (in close collaboration with the project leader) will invite client representatives, domain experts, and software vendor representatives to participate in the “Expert panel”.
  • 3. Page no. Author 3 AndrÊ Borrmann, Thomas Liebich The project team is supported by management support staff for building up the expert panel, workshop invitations, taking minutes and distributing minutes and materials. Figure 1 Organisational structure, in accordance with the Infrastructure Room Charter 2 Work Plan The work plan of the Infra Integration project is based on existing work experience coming from IFC- Alignment development and preliminary work in buildingSMART, OGC, and other initiatives. 2.1 Existing Work The project will built upon the significant work by the Korean IFC-Road project, the Chinese IFC-Rail pro- ject and the IFC-Bridge project led by the French chapter. All three projects have defined extensive data models for describing infrastructure assets. However, the projects have developed mostly independent from each other. In consequence, diverging or even incompatible approaches to modeling commonly used exist. The proposed project will analyze in detail the proposed data models and incorporate them to the largest extent possible. The project will also take into consideration the ongoing Infra Asset Management Requirements project, as well as other relevant activities, such as Japanese developments on Tunnels. Beside the IFC-related initiatives, there are also other data models. LandXML is a widely adopted quasi standard for representing roads. However, it has a number of modelling errors and it is no longer actively maintained. The Finnish infrastructure clients initiated the Finnish Inframodel development1, it docu- ments and enhances LandXML1.2 for well-defined use cases; this development has also lead to buildingSMART Recommended Technical Report 2(adopted by InfraRoom in March 2015). 1 See http://cic.vtt.fi/inframodel/ 2 See http://cic.vtt.fi/bSI_LandXML12_MVD/
  • 4. Page no. Author 4 AndrÊ Borrmann, Thomas Liebich OGC has created a “Land and Infrastructure” working group with the goal to develop InfraGML3. OKSTRA4 is used for road information systems in Germany. OKSTRA standard is only target for the Ger- man market, since the complete data model is in German language. OpenBrIM5 is an XML file format for bridges, however it is only poorly supported by software packages. In the Singapore bSI Standards Summit Fall 2015, the Infrastructure room concluded the following resolu- tion: “ The InfraRoom resolves to establish an Overall Architecture Working Group to address the issues of integra- tion across the evolving Infrastructure standards development. The InfraRoom appreciates the results from the discussion of issues during the session on Integration. The InfraRoom acknowledges the work done by national IFC development programs on Roads, Railways, Bridges and Tunnels, and asks that they provide their conceptual schemas as a resource for the Overall Archi- tecture. The InfraRoom acknowledges the urgency of developing the Overall Architecture for Infrastructure Exten- sions and asks all parties involved to take this into account.” 2.2 Project work package structure The work packages (WP) of the Infra Integration project are: WP0 Completion of Project Execution Plan Based on the project proposal and the Memorandum of Understanding a full project execution plan has to be developed, showing work packages, deliverables, work schedule, budget plan, project team and the project organization in terms of responsibilities and reporting lines. Tasks: T0.1 Development of Project Execution Plan T0.2 Agreement of Project Execution Plan Deliverable: Completed Project Execution Plan Milestone: M0, 31.01.2016 WP 1 Requirement Analysis Analyze the requirements of existing data exchange processes in infrastructure projects. The require- ments of a neutral data model capable to present both semantic as well as geometric aspects have to be determined. Typical user scenarios and use cases have to be captured and documented. Existing data ex- change standards for infrastructure projects such as the LandXML standard should also be taken into con- sideration. Methods of the Information Delivery Manual (IDM) are used to create process maps and ex- change requirements from the user requirements. It has to be documented in detail, who are the users of the IFC infrastructure extension and for what purpose the data is needed. The client and domain expert panel will contribute to the requirement analysis and validation. A strong coordination between the project team and the expert panel will be established. Tasks: T1.0 Define complete high level bSI infra scope. T1.1 Select and define scope and use cases for this project (subset of T1.0) T1.2 Analysis of Rail exchange requirements T1.3 Analysis of Road exchange requirements 3 See http://geospatial.blogs.com/geospatial/2013/12/a-proposal-to-replace-landxml-with-infragml.html 4 See http://www.okstra.de/ 5 See http://openbrim.org/Schema2.aspx
  • 5. Page no. Author 5 AndrÊ Borrmann, Thomas Liebich T1.4 Analysis of Bridge exchange requirements T1.5 Analysis of Tunnel exchange requirements T1.6 Identification of common exchange requirements T1.7 Validate common exchange requirements (with WP3). T1.8 Refinement of scope and use cases Deliverable: [1] Requirement Analysis, including fine-tuned scope definition Milestone: [1] M1 30.04.2016 WP2 IFC Schema Extension and Extension Modelling Guidelines The scope of the model is defined from the outcome of the WP1. A model extension for IFC is defined as a conceptional schema using the Unified Model Language (UML) as a graphical notation. The corresponding EXPRESS schema and the XSD schema are derived from the conceptional schema. The schema is docu- mented using the definitions from the requirement analysis. . Different stages of the IFC schema will be presented to the domain expert and software expert panels. The schema extension needs to be incrementally improved with the feedback from these panels. Tasks: T2.1 Analysis of proposed IFC-Road extension T2.2 Analysis of proposed IFC-Rail extension T2.3 Analysis of proposed IFC-Bridge extension T2.4 Analysis of proposed IFC-Tunnel extension T2.5 Develop draft conceptual schema T2.6 Validate draft conceptual schema T2.7 Develop final IFC4 extension T2.8 Validate final IFC4 extension (with WP3) T2.9 Develop modelling guidelines for bSI infrastructure extension projects Deliverables: [1] Draft IFC4 schema extension [2] Final IFC4 schema extension [3] Final IFC4 extension documentation Milestones: [1] M2 31.07.2016 [2] M3 31.10.2016 [3] M4 15.12.2016 WP3 Facilitate the expert panels Facilitate the expert panels (both for clients / domain experts and for software experts). Hold regular meetings with the panels. Inform them via email groups and a development blog and other social media activities. Tasks: T3.1 Set-up of expert panels T3.2 Facilitate reviews with the expert panel Deliverables: [1] Expert panel discussion at project start - 01.02.2016 [2] Expert panel discussion prior to Milestone 1 – 15.04.2016 [3] Expert panel discussion prior to Milestone 2 – 15.07.2016 [4] Expert panel discussion prior to Milestone 3 – 15.10.2016 [5] Expert panel discussion prior to Milestone 4 – 30.11.2016 WP4 Project management Manage the technical work of the project, including the reporting to the steering committees according to Figure 1. Write quarterly reports and inform the stakeholders on progress. Cooperate with the project
  • 6. Page no. Author 6 AndrÊ Borrmann, Thomas Liebich representative. Organize the collaboration with OGC, in particular with the “Land and infrastructure” SWG for the joint development of the conceptual schema. Tasks: T4.1 Project management Deliverables: Quarterly project progress reports 3 Work breakdown (activities per work package) WP0 Completion of the Project Execution Plan Activities: ī‚§ Develop the project execution plan (scope, schedule, budget) ī‚§ Form the project team ī‚§ Present the Project Execution Plan to the stakeholders and the Infrastructure steering group ī‚§ Achieve agreement and initiate the kick-off of the project work WP 1 Requirement Analysis Activities: ī‚§ Define a reference process description in the form of a high level process map containing and defining the most important stages, stakeholders and exchanges to provide context to all other descriptions ī‚§ Informally select and document typical user scenarios and use cases of different stakeholders for ī‚§ Road design, procurement, construction, operation, maintenance and destruction/recycling ī‚§ Railway design, procurement, construction, operation, maintenance and destruction/recycling ī‚§ Bridge design, procurement, construction, operation, maintenance and destruction/recycling Note: Limit scenarios to those relevant for this standard. There might be scenarios that’s more rele- vant for e. g GIS or ITS standards. ī‚§ Identify exchange scenarios with highest priority on the basis of the importance for the international stakeholders ī‚§ Formally describe which data is required in data exchanges of infrastructure projects (IDM method) ī‚§ Validate refined scope against use case of the model ī‚§ Request feedback from users and software expert panel. These steps need to be repeated and the model scope needs to be incrementally refined. Risks: ī‚§ No consensus in expert panel ī‚§ Requirements can be misunderstood by project team ī‚§ Some important requirements could be missing in the requirements review ī‚§ Unimportant requirements that are needed only by one stakeholder could be misleadingly included in the requirement analysis Risk Measures: ī‚§ front end focus on discussion and consensus in order to be able to escalate in time ī‚§ Make a review with stakeholders to find out if the requirement were correctly determined. ī‚§ Count the number of stakeholders that needs a certain requirement to find out the importance
  • 7. Page no. Author 7 AndrÊ Borrmann, Thomas Liebich WP2 IFC Schema Extension and Extension Modelling Guidelines Activities: ī‚§ Develop a conceptual schema comprising all information within the refined scope of WP1 ī‚§ Align this work with the Land & Infrastructure conceptual schema developed in parallel in OGC ī‚§ Extend the IFC4 schema based on the conceptual schema ī‚§ Complete the IFC4 extension, and guarantee its syntactical correctness ī‚§ Complete the overall documentation of the model extension ī‚§ Develop modelling guidelines to be followed in bSI infrastructure extension projects Risks: ī‚§ A common conceptual schema between bSI and OGC cannot be achieved ī‚§ The extension within the current IFC architecture is too complex ī‚§ The resulting IFC extension does not capture all requirements defined in WP1 ī‚§ The resulting IFC extension proves too difficult or too ambiguous to be implemented efficiently Risk Measures: ī‚§ Involve OGC technical experts in the project ī‚§ Get involved in OGC “Land and Infrastructure” SWG ī‚§ Include the domain and the software expert panel in reviewing the conceptual schema ī‚§ Test the resulting IFC4 extension (and MVD) in WP3 WP3 Facilitate the expert panels Activities: ī‚§ Set-up domain expert panel ī‚§ Set-up software expert panel ī‚§ Provide intermediate project results to the expert panels (at least before each milestone) ī‚§ Facilitate online meetings with the expert panels ī‚§ Integrate the results into the work packages Risks: ī‚§ Inadequate representation within expert panels ī‚§ Inactiveness of some experts (due to voluntary nature of participation) Risk Measures: ī‚§ Involve stakeholders and Infrastructure room in selection of expert panels ī‚§ Show stakeholders’ commitment and realistic goals to experts to get better responses WP4 Project Management Activities: ī‚§ Progress reports, invoicing, representation in bSI, coordination with OGC WP5 Communication and Dissemination
  • 8. Page no. Author 8 AndrÊ Borrmann, Thomas Liebich Activities: ī‚§ Communication within the project team and within bSI via Infranet ī‚§ Communication to the general public via project website ī‚§ Dissemination of the project results 4 Project Team The technical project team will comprise technical and IFC modeling experts from buildingSMART Inter- national Model Support Group (MSG), Open Geospatial Consortium (OGC) and a number of research insti- tutes from around the word. The following persons are named already: ī‚§ AndrÊ Borrmann, Project Lead ī‚§ Thomas Liebich, bSI Model Support Group ī‚§ Tim Chipman, bSI Model Support Group ī‚§ Jim Plume, University of New South Wales (UNSW) ī‚§ Julian Amann, Technical University Munich (TUM) ī‚§ Dominic Singer, Technical University Munich (TUM) ī‚§ Juha Hyvärinen, VTT Technical Research Centre of Finland (VTT) ī‚§ Nobuyoshi Yabuki, Osaka University (OU) ī‚§ Francois Grobler, bSI IFC Roads and Railways project ī‚§ Hyunjoo Kim, University of Seoul (UOS) ī‚§ Yushen Liu, China Railway BIM Alliance (CRBIM) ī‚§ Hyunseok Moon, Korean Institute of Civil Engineering and Building Technology (KICT) ī‚§ Christophe Castaing, bSI IFC-Bridge project ī‚§ Paul Scarponcini, OGC (based on the MoU agreement between bSI and OGC) ī‚§ Laura Mol, Gobar Adviseurs The nomination of the domain and software expert panel shall be done in collaboration with the stake- holders and the Infrastructure room. 5 Cost breakdown WP0 3.200,00 â‚Ŧ WP1 48.900,00 â‚Ŧ WP2 47.400,00 â‚Ŧ WP3 22.600,00 â‚Ŧ WP4 14.400,00 â‚Ŧ WP5 1.200,00 â‚Ŧ Travel 13.000,00 â‚Ŧ Total 150.700,00 â‚Ŧ bSI Overhead 22.605,00 â‚Ŧ Project Sum 173.305,00 â‚Ŧ
  • 9. Page no. Author 9 AndrÊ Borrmann, Thomas Liebich 6 Schedule The project will commence on February 1st, 2016 and will be completed on December 15th, 2016. The pre- project phase for WP0 “full project execution plan” is from 01.11.2015 till 31.01.2016. The main milestones are aligned with the buildingSMART International meetings, in March and October 2016. Detailed schedule: ID Work Package Start End 2015 MrzJan FebDez SepJun NovOktApr Mai Jul AugNov 1 15.12.201501.11.2015WP0: Completion of the project plan 2 30.04.201601.02.2016WP1: Requirement Analysis 4 15.12.201601.05.2016WP2: IFC Extensions & Guidelines 8 15.12.201601.02.2016WP3: Facilitate the expert panel 9 15.12.201615.12.2015WP4: Project management 30.04.201630.04.2016Milestone 1 2016 3 5 31.07.201631.07.2016Milestone 2 6 31.10.201631.10.2016Milestone 3 7 15.12.201615.12.2016Milestone 4 Dez Figure 2: Project Gantt chart