More Related Content Similar to PROJECT APPRASIAL (20) More from yash nirmale (20) PROJECT APPRASIAL 2. Calculation of cost of capital
Source Amount Weight
share capital 641263247 0.73
loan 232142857 0.27
total 873406104 1
cost of equity hare
beta 1.30
risk free rate 6.39%
market return 11.10%
rf+beta(rm-rf)
capm 13%
interst (1-tax)
interest 15%
tax rate 25%
Cost of loan 11%
WACC 12%
3. PROBABILITY APPROCH
Assumption
The project life cycle for the project after the completion of the project was 5 years so it has
been assumed that the probability of getting will be according to the product life cycle
Year1- 0.1
Year 2 -0.2
year 3 – 0.6
year 4- 0.2
year 5- 0.1
Investment =₹ 87,34,06,104.00
Discounted cashflow= ₹ 31,84,26,533.24
Standard deviation approach
year cashflow X-x (X-x) Calculation
1
₹
28,82,33,500.00
₹
7,69,14,893.6
0
₹
5,91,59,00,85,74,99,32
0
0.
1
₹
59,15,90,08,57,49,932
year profit afte tax depreciation cashflow Probability
Discounting
factor
@12%
Discountedcash
flow
investment
2009
₹
16,94,93,790.00
₹
11,87,39,710.00
₹
28,82,33,500.00 0.1
₹
2,88,23,350.00 0.892857
₹
2,57,35,129.81
2010 ₹ 22,73,14,994.00
₹
12,71,36,969.00
₹
35,44,51,963.00 0.2
₹
7,08,90,392.60 0.797194
₹
5,65,13,395.64
2011 ₹ 25,97,62,498.00
₹
11,78,62,193.00
₹
37,76,24,691.00 0.6
₹
22,65,74,814.60 0.71178
₹
16,12,71,421.54
2012 ₹ 30,20,95,217.00
₹
11,29,67,843.00
₹
41,50,63,060.00 0.2
₹
8,30,12,612.00 0.635518
₹
5,27,56,009.15
2013 ₹ 30,33,39,471.00
₹
8,70,29,283.00
₹
39,03,68,754.00 0.1
₹
3,90,36,875.40 0.567427
₹
2,21,50,577.10
₹
1,82,57,41,968.00
₹
31,84,26,533.24
4. 2
₹
35,44,51,963.00
₹
1,06,96,430.6
0
₹
11,44,13,62,75,80,617
0.
2 ₹ 2,28,82,72,55,16,123
3
₹
37,76,24,691.00
₹ -
1,24,76,297.4
0
₹
15,56,57,99,68,13,246
0.
6 ₹ 9,33,94,79,80,87,948
4
₹
41,50,63,060.00
₹ -
4,99,14,666.4
0
₹
2,49,14,73,92,18,23,29
0
0.
2
₹
49,82,94,78,43,64,658
5
₹
39,03,68,754.00
₹ -
2,52,20,360.4
0
₹
63,60,66,57,87,05,887
0.
1 ₹ 6,36,06,65,78,70,589
₹
1,82,57,41,968.0
0
₹
9,31,35,12,98,24,22,36
0
₹
1,26,97,69,05,15,89,25
0
Conclusion –
If probability is not considered
Under-root of ₹ ₹ 9,31,35,12,98,24,22,360 = ₹9,65,06,543.72
If probability is given
Under-root of ₹ 1,26,97,69,05,15,89,250= ₹ 3,56,33,818.9307
Investment = 87,34,06,104.00
Risk adjusted discount approach
5. RADR = risk free rate of interest + risk premium
6.39+3.91= 10.30
Investment = 87,34,06,104.00 and RADR NPV = ₹4,80,19,003.55
Conclusion – company should go for the project because of positive NPV
Sensitivity
Calculation of cashflows
It has been assumed that the original cashflow is most likely and 30 % increase in weightage
is optimistic and 30 % decrease is pessimistic.
Assumption -
Calculation in different situations when cost of capital is 12%
year cashflow
RADR discount
factor discounted cashflow
1
₹
28,82,33,500.00 0.906618314
₹
26,13,17,769.72
2
₹
35,44,51,963.00 0.821956767
₹
29,13,44,189.46
3
₹
37,76,24,691.00 0.745201058
₹
28,14,06,319.17
4
₹
41,50,63,060.00 0.675612926
₹
28,04,21,968.59
5
₹
39,03,68,754.00 0.612523052
₹
23,91,09,860.60
₹
1,35,36,00,107.55
year
cashflowmost
likely Weights
optimistic (+30%
weights)
pessimistic (-
30%weights)
1
₹
28,82,33,500.00 0.84212802 1.09 315548358.5 0.589489614
₹
16,99,10,654.60
2
₹
35,44,51,963.00 0.805858676 1.05 371329646.5 0.564101073
₹
19,99,46,732.72
3
₹
37,76,24,691.00 0.793166451 1.03 389375006.7 0.555216516
₹
20,96,63,465.15
4
₹
41,50,63,060.00 0.772660613 1.00 416913741.8 0.540862429
₹
22,44,92,014.83
5
₹
39,03,68,754.00 0.786186241 1.02 398973306.1 0.550330368
₹
21,48,31,780.19
6. year
cashflowmost
likely
discounted
cashflow
cash flow
optimistic
discounted
cashflow
cash flow
pessimistic
discounted
cashflow
1
₹
28,82,33,500.00
₹
25,73,51,339.29
₹
31,55,48,358.54
₹
28,17,39,605.84
₹
16,99,10,654.60
₹
15,17,05,941.60
2
₹
35,44,51,963.00
₹
28,25,66,934.79
₹
37,13,29,646.48
₹
29,60,21,720.73
₹
19,99,46,732.72
₹
15,93,96,311.16
3
₹
37,76,24,691.00
₹
26,87,85,796.14
₹
38,93,75,006.71
₹
27,71,49,438.77
₹
20,96,63,465.15
₹
14,92,34,313.18
4
₹
41,50,63,060.00
₹
26,37,80,078.31
₹
41,69,13,741.83
₹
26,49,56,220.07
₹
22,44,92,014.83
₹
14,26,68,733.88
5
₹
39,03,68,754.00
₹
22,15,05,714.65
₹
39,89,73,306.07
₹
22,63,88,168.58
₹
21,48,31,780.19
₹
12,19,01,321.54
₹
1,29,39,89,863.18 ₹ 1,34,62,55,153.98
₹
72,49,06,621.37
NPV for the following events are
Most-likely-₹ 1,29,39,89,863.18 -₹ 87,34,06,104.00=₹ 42,05,83,759.18
Optimistic ₹ 1,34,62,55,153.98-₹ 87,34,06,104.00=₹ 47,28,49,049.98
Pessimistic ₹ 72,49,06,621.37 -₹ 87,34,06,104.00=₹ -14,84,99,482.63
Certainty equilantent approach
cashflow
Discount
factor 2
Discount
factor2
risky cash
flow
risk free
cash flow
1 288233500 0.90662 0.94073 261317769.8 271150987.8
2 354451963 0.82196 0.88498 291344189.6 313682909
3 377624691 0.7452 0.83253 281406319.3 314384111.5
4 415063060 0.67561 0.78319 280421968.4 325073094.5
5 390368754 0.61252 0.73677 239109860.6 287613141.6
1825741968 1353600108 1511904244
CEC 1.116950446
Conclusion – company should go for the project because it has CEC factor greater then one
7. Decision tree
Three case are considered
Case 1 – In this case the addition capital is invested in 6th year for the expansion which and it
involved an investment of ₹ 3,79,00,00,000.00 and which will provide then additional cash
flow for 7 years
Case 2 – in this case no expansion is done was opted
Case 3- in this case project was not taken into.
particular Year Case-1 Case-2
Case-
3
initial
investment
₹
87,34,06,104.00
₹
87,34,06,104.00
₹
-
additional
investment
₹
3,79,00,00,000.00
₹
-
₹
-
cashflows
1.00
₹
28,82,33,500.00
₹
25,73,51,339.29
₹
28,82,33,500.00
₹
25,73,51,339.29 0
2.00
₹
35,44,51,963.00
₹
28,25,66,934.79
₹
35,44,51,963.00
₹
28,25,66,934.79 0
3.00
₹
37,76,24,691.00
₹
26,87,85,796.14
₹
37,76,24,691.00
₹
26,87,85,796.14 0
4.00
₹
41,50,63,060.00
₹
26,37,80,078.31
₹
41,50,63,060.00
₹
26,37,80,078.31 0
5.00
₹
39,03,68,754.00
₹
22,15,05,714.65
₹
39,03,68,754.00
₹
22,15,05,714.65 0
Additional
cashflows
1.00 6.00
₹
51,88,20,300.00
₹
46,32,32,410.71
₹
1,92,01,31,949.26
0
2.00 7.00
₹
63,80,13,533.40
₹
50,86,20,482.62 0
3.00 8.00
₹
67,97,24,443.80
₹
48,38,14,433.05 0
4.00 9.00
₹
74,71,13,508.00
₹
47,48,04,140.95 0
5.00 10.00
₹
70,26,63,757.20
₹
39,87,10,286.38 0
6.00 11.00
₹
93,38,76,540.00
₹
47,31,30,918.50 0
7.00 12.00
₹
1,14,84,24,360.12
₹
51,94,88,858.17 0
NPV
₹
1,82,22,53,340.31 ₹
1,29,39,89,863.18
8. NPV in different cases are
1. ₹ 1,82,22,53,340.31
2. ₹ 1,29,39,89,863.18
3. 0
Conclusion – the company should go for the expansion project because it has a greater NPV
from the other cases