1.A program manager is identifying and verifying risks as outlined in
the risk management plan. The results will be recorded in which of the
following?
A.Risk register
B.Risk monitoring and control
C.Risk response planning
D.Risk mitigation strategy
Answer : A
3. Free BICSI RCDDv14 Practice Exam From Passcert for Your Best Preparation
2. A component project manager escalates an issue regarding a key stakeholder
to the program manager. The key stakeholder does not respond to emails or
phone calls and the project manager believes this key stakeholder is exhibiting a
negative attitude toward the work. The key stakeholder has a significant
influence over the component project which could impact other components if
delays occur. The program manager's attempts to reach the stakeholder via email
also fail.
What should the program manager do next?
A.Escalate the issue to the stakeholder's supervisor.
B.Escalate the issue to the program governance board as delays will impact the
program
C.Update the program risk register to reflect a realized risk and execute the
documented risk response
D.Attempt to call the key stakeholder, if unsuccessful, visit their office to identify
potential risks
Answer : D
4. Free BICSI RCDDv14 Practice Exam From Passcert for Your Best Preparation
3.Company A acquires company B. which leads to a two-year
program lo integrate the processes and systems Company B uses a
different project management process, and the company's staff is
unhappy about the acquisition As a result company B's project team
fails to provide status and cost data in a format that conforms to the
program standards.
What should the program manager do first?
A.Inform the stakeholders of this Issue as soon as possible
B.Change the program standards, aligning them with the project
standards
C.Work with the reports provided to extract the required information
D.Remind the project manager of the relevant program standards
Answer : D
5. Free BICSI RCDDv14 Practice Exam From Passcert for Your Best Preparation
4. Program A is dependent upon program B lo complete benefits
sustainment for two benefits Program A is on track to meet program
benefits However program B's program manager has just advised that
program B has been closed.
What should program A's program manager update and review first
with the stakeholders?
A.Benefits sustainment plan
B.Benefits register
C.Benefits management plan
D.Benefits transition plan
Answer : A
6. Free BICSI RCDDv14 Practice Exam From Passcert for Your Best Preparation
5. The program manager defines the program objectives,
requirements and develops a high-level road map. To ensure
program alignment with the enterprise strategic plan the program
manager should work with which of the following?
A.Program governance board
B.Program management office
C.Change control board
D.Project managers on the program
Answer : A
7. Free BICSI RCDDv14 Practice Exam From Passcert for Your Best Preparation
6. A new program component provides an opportunity to enhance
program outcomes. What does the program manager use to document
and monitor the opportunity'?
A.Program risk register
B.Program scope management plan
C.Program risk management plan
D.Component project risk registers
Answer:A
8. Free BICSI RCDDv14 Practice Exam From Passcert for Your Best Preparation
7.A program manager is assigned to a large cross-functional program
trial includes five different technologies and multiple workstreams.
Some potential stakeholders have conflicting program expectations
What should the program manager do next/?
A.Conduct interviews with key stakeholders, and document the results
in the program management plan
B.Update the stakeholder register to document stakeholders' positions
relative to the program
C.Document stakeholder expectations in the program's risk register to
determine their influence
D.Send out satisfaction surveys and document the results in the
program's stakeholder engagement plan.
Answer:C
9. Free BICSI RCDDv14 Practice Exam From Passcert for Your Best Preparation
8. A program manager initiates a developmental program. Significant
resources and funding are required (or early activities until the
program cost and budget estimates are complete
What should the program manager do to understand the financial
environment?
A.Map costs to the expected benefits realization
B.Establish intermediate budget based on historical information
C.Establish program financial framework
D.Obtain intermediate funding from the executive sponsor
Answer:C
10. Free BICSI RCDDv14 Practice Exam From Passcert for Your Best Preparation
9.The program sponsor returns from a board of directors
meeting alter identifying a significant risk to the program
schedule. This may Impact the program's benefits realization
What should the program manager do next?
A.Update the program benefits management plan and risk
register
B.Implement the mitigation plan for the identified risk
C.Adjust the program scope to avoid the risk
D.Document the risk and create a mitigation plan
Answer:D
11. Free BICSI RCDDv14 Practice Exam From Passcert for Your Best Preparation
10.The risk manager completes risk response planning. The risk
manager believes that to effectively address all eventualities, an
additional action is required.
What should the program manager do next?
A.Transfer a percentage of known risks
B.Establish a contingency reserve
C.Avoid known critical project threats.
D.Perform a final review of project scope
Answer:B