HWE Accessories Website Project Plan, Risk Matrix, and Key Factor.docx
1. HWE Accessories Website: Project Plan, Risk Matrix, and Key
Factors
HWE Accessories Website: Project Plan, Risk Matrix, and Key
Factors
Gregory Hobbs
BSA/515
2/5/18
Anthony Seymour
Start
Tue 2/6/18
2. Finish
Wed 5/9/18
Feb 11, '18
Feb 18, '18
Feb 25, '18
Mar 4, '18
Mar 11, '18
Mar 18, '18
Mar 25, '18
Apr 1, '18
Apr 8, '18
Apr 15, '18
Apr 22, '18
Apr 29, '18
May 6, '18
outline the technical requirements
Wed 2/21/18 - Fri 2/23/18
Gather data
Tue 2/6/18 - Wed 2/7/18
Analyze data
Thu 2/8/18 - Sat 2/10/18
document data
Mon 2/12/18 - Wed 2/14/18
Define and develop the site concept
Fri 2/16/18 - Sat 2/17/18
Define the overall budget
Mon 2/19/18 - Tue 2/20/18
Complete the sitemap
Mon 2/26/18 - Tue 2/27/18
Adress the technical requirements outlined
Wed 2/28/18 - Fri 3/2/18
Begin site's content acquisition
Mon 3/5/18 - Tue 3/6/18
Present the design
Wed 3/7/18 - Thu 3/8/18
3. Set the website's look and feel
Fri 3/9/18 - Tue 3/13/18
content acquisition
Wed 3/14/18 - Thu 3/15/18
design the user interface
Sat 3/17/18 - Tue 3/20/18
Finalize the website design
Wed 3/21/18 - Fri 3/23/18
Programming outline phase
Sat 3/24/18 - Wed 3/28/18
finalize prototype
Fri 3/30/18 - Mon 4/2/18
submit final design
Thu 4/5/18 - Wed 4/11/18
Perform client sign off
Thu 4/12/18 - Fri 4/13/18
perform Usability testing
Wed 4/18/18 - Thu 4/19/18
Carry out cross platform testing
Sat 4/21/18 - Tue 4/24/18
perform browser testing
Wed 4/25/18 - Thu 4/26/18
Make neccesary modifications
Tue 5/1/18 - Wed 5/2/18
Final approval
Thu 5/3/18 - Fri 5/4/18
Launch the website
Sat 5/5/18 - Wed 5/9/18
outline the technical requirements
Wed 2/21/18 - Fri 2/23/18
Gather data
Tue 2/6/18 - Wed 2/7/18
Analyze data
Thu 2/8/18 - Sat 2/10/18
document data
Mon 2/12/18 - Wed 2/14/18
4. Define and develop the site concept
Fri 2/16/18 - Sat 2/17/18
Define the overall budget
Mon 2/19/18 - Tue 2/20/18
Complete the sitemap
Mon 2/26/18 - Tue 2/27/18
Adress the technical requirements outlined
Wed 2/28/18 - Fri 3/2/18
Begin site's content acquisition
Mon 3/5/18 - Tue 3/6/18
Present the design
Wed 3/7/18 - Thu 3/8/18
Set the website's look and feel
Fri 3/9/18 - Tue 3/13/18
content acquisition
Wed 3/14/18 - Thu 3/15/18
design the user interface
Sat 3/17/18 - Tue 3/20/18
Finalize the website design
Wed 3/21/18 - Fri 3/23/18
Programming outline phase
Sat 3/24/18 - Wed 3/28/18
finalize prototype
Fri 3/30/18 - Mon 4/2/18
submit final design
Thu 4/5/18 - Wed 4/11/18
Perform client sign off
Thu 4/12/18 - Fri 4/13/18
perform Usability testing
Wed 4/18/18 - Thu 4/19/18
Carry out cross platform testing
Sat 4/21/18 - Tue 4/24/18
perform browser testing
Wed 4/25/18 - Thu 4/26/18
Make neccesary modifications
Tue 5/1/18 - Wed 5/2/18
5. Final approval
Thu 5/3/18 - Fri 5/4/18
Launch the website
Sat 5/5/18 - Wed 5/9/18
Feb 11, '18
Feb 18, '18
Feb 25, '18
Mar 4, '18
Mar 11, '18
Mar 18, '18
Mar 25, '18
Apr 1, '18
Apr 8, '18
Apr 15, '18
Apr 22, '18
Apr 29, '18
May 6, '18
Feb 11, '18
Feb 18, '18
Feb 25, '18
Mar 4, '18
Mar 11, '18
Mar 18, '18
Mar 25, '18
Apr 1, '18
Apr 8, '18
Apr 15, '18
Apr 22, '18
Apr 29, '18
May 6, '18
Feb 11, '18
Feb 18, '18
Feb 25, '18
Mar 4, '18
Mar 11, '18
Mar 18, '18
6. Mar 25, '18
Apr 1, '18
Apr 8, '18
Apr 15, '18
Apr 22, '18
Apr 29, '18
May 6, '18
Feb 11, '18
Feb 18, '18
Feb 25, '18
Mar 4, '18
Mar 11, '18
Mar 18, '18
Mar 25, '18
Apr 1, '18
Apr 8, '18
Apr 15, '18
Apr 22, '18
Apr 29, '18
May 6, '18
Feb 11, '18
Feb 18, '18
Feb 25, '18
Mar 4, '18
Mar 11, '18
Mar 18, '18
Mar 25, '18
Apr 1, '18
Apr 8, '18
Apr 15, '18
Apr 22, '18
Apr 29, '18
May 6, '18
Feb 11, '18
Feb 18, '18
Feb 25, '18
7. Mar 4, '18
Mar 11, '18
Mar 18, '18
Mar 25, '18
Apr 1, '18
Apr 8, '18
Apr 15, '18
Apr 22, '18
Apr 29, '18
May 6, '18
Feb 11, '18
Feb 18, '18
Feb 25, '18
Mar 4, '18
Mar 11, '18
Mar 18, '18
Mar 25, '18
Apr 1, '18
Apr 8, '18
Apr 15, '18
Apr 22, '18
Apr 29, '18
May 6, '18
Feb 11, '18
Feb 18, '18
Feb 25, '18
Mar 4, '18
Mar 11, '18
Mar 18, '18
Mar 25, '18
Apr 1, '18
Apr 8, '18
Apr 15, '18
Apr 22, '18
Apr 29, '18
May 6, '18
8. Feb 11, '18
Feb 18, '18
Feb 25, '18
Mar 4, '18
Mar 11, '18
Mar 18, '18
Mar 25, '18
Apr 1, '18
Apr 8, '18
Apr 15, '18
Apr 22, '18
Apr 29, '18
May 6, '18
Feb 11, '18
Feb 18, '18
Feb 25, '18
Mar 4, '18
Mar 11, '18
Mar 18, '18
Mar 25, '18
Apr 1, '18
Apr 8, '18
Apr 15, '18
Apr 22, '18
Apr 29, '18
May 6, '18
Feb 11, '18
Feb 18, '18
Feb 25, '18
Mar 4, '18
Mar 11, '18
Mar 18, '18
Mar 25, '18
Apr 1, '18
Apr 8, '18
Apr 15, '18
9. Apr 22, '18
Apr 29, '18
May 6, '18
Feb 11, '18
Feb 18, '18
Feb 25, '18
Mar 4, '18
Mar 11, '18
Mar 18, '18
Mar 25, '18
Apr 1, '18
Apr 8, '18
Apr 15, '18
Apr 22, '18
Apr 29, '18
May 6, '18
Feb 11, '18
Feb 18, '18
Feb 25, '18
Mar 4, '18
Mar 11, '18
Mar 18, '18
Mar 25, '18
Apr 1, '18
Apr 8, '18
Apr 15, '18
Apr 22, '18
Apr 29, '18
May 6, '18
Feb 11, '18
Feb 18, '18
Feb 25, '18
Mar 4, '18
Mar 11, '18
Mar 18, '18
Mar 25, '18
10. Apr 1, '18
Apr 8, '18
Apr 15, '18
Apr 22, '18
Apr 29, '18
May 6, '18
Feb 11, '18
Feb 18, '18
Feb 25, '18
Mar 4, '18
Mar 11, '18
Mar 18, '18
Mar 25, '18
Apr 1, '18
Apr 8, '18
Apr 15, '18
Apr 22, '18
Apr 29, '18
May 6, '18
Feb 11, '18
Feb 18, '18
Feb 25, '18
Mar 4, '18
Mar 11, '18
Mar 18, '18
Mar 25, '18
Apr 1, '18
Apr 8, '18
Apr 15, '18
Apr 22, '18
Apr 29, '18
May 6, '18
Feb 11, '18
Feb 18, '18
Feb 25, '18
Mar 4, '18
11. Mar 11, '18
Mar 18, '18
Mar 25, '18
Apr 1, '18
Apr 8, '18
Apr 15, '18
Apr 22, '18
Apr 29, '18
May 6, '18
Feb 11, '18
Feb 18, '18
Feb 25, '18
Mar 4, '18
Mar 11, '18
Mar 18, '18
Mar 25, '18
Apr 1, '18
Apr 8, '18
Apr 15, '18
Apr 22, '18
Apr 29, '18
May 6, '18
Feb 11, '18
Feb 18, '18
Feb 25, '18
Mar 4, '18
Mar 11, '18
Mar 18, '18
Mar 25, '18
Apr 1, '18
Apr 8, '18
Apr 15, '18
Apr 22, '18
Apr 29, '18
May 6, '18
Feb 11, '18
12. Feb 18, '18
Feb 25, '18
Mar 4, '18
Mar 11, '18
Mar 18, '18
Mar 25, '18
Apr 1, '18
Apr 8, '18
Apr 15, '18
Apr 22, '18
Apr 29, '18
May 6, '18
Feb 11, '18
Feb 18, '18
Feb 25, '18
Mar 4, '18
Mar 11, '18
Mar 18, '18
Mar 25, '18
Apr 1, '18
Apr 8, '18
Apr 15, '18
Apr 22, '18
Apr 29, '18
May 6, '18
Feb 11, '18
Feb 18, '18
Feb 25, '18
Mar 4, '18
Mar 11, '18
Mar 18, '18
Mar 25, '18
Apr 1, '18
Apr 8, '18
Apr 15, '18
Apr 22, '18
13. Apr 29, '18
May 6, '18
Feb 11, '18
Feb 18, '18
Feb 25, '18
Mar 4, '18
Mar 11, '18
Mar 18, '18
Mar 25, '18
Apr 1, '18
Apr 8, '18
Apr 15, '18
Apr 22, '18
Apr 29, '18
May 6, '18
Feb 11, '18
Feb 18, '18
Feb 25, '18
Mar 4, '18
Mar 11, '18
Mar 18, '18
Mar 25, '18
Apr 1, '18
Apr 8, '18
Apr 15, '18
Apr 22, '18
Apr 29, '18
May 6, '18
Feb 11, '18
Feb 18, '18
Feb 25, '18
Mar 4, '18
Mar 11, '18
Mar 18, '18
Mar 25, '18
Apr 1, '18
14. Apr 8, '18
Apr 15, '18
Apr 22, '18
Apr 29, '18
May 6, '18
Feb 11, '18
Feb 18, '18
Feb 25, '18
Mar 4, '18
Mar 11, '18
Mar 18, '18
Mar 25, '18
Apr 1, '18
Apr 8, '18
Apr 15, '18
Apr 22, '18
Apr 29, '18
May 6, '18
Feb 11, '18
Feb 18, '18
Feb 25, '18
Mar 4, '18
Mar 11, '18
Mar 18, '18
Mar 25, '18
Apr 1, '18
Apr 8, '18
Apr 15, '18
Apr 22, '18
Apr 29, '18
May 6, '18
Feb 11, '18
Feb 18, '18
Feb 25, '18
Mar 4, '18
Mar 11, '18
15. Mar 18, '18
Mar 25, '18
Apr 1, '18
Apr 8, '18
Apr 15, '18
Apr 22, '18
Apr 29, '18
May 6, '18
Task Mode
Task Name
Duration
Start
Finish
Predecessors
Manually Scheduled
Analysis tasks
8 days
Tue 2/6/18
Thu 2/15/18
Auto Scheduled
Gather data
2 days
Tue 2/6/18
Wed 2/7/18
Auto Scheduled
Analyze data
3 days
Thu 2/8/18
Sat 2/10/18
2
Auto Scheduled
document data
3 days
16. Mon 2/12/18
Wed 2/14/18
3
Manually Scheduled
Outline site design goals
7 days
Fri 2/16/18
Mon 2/26/18
Auto Scheduled
Define and develop the site concept
2 days
Fri 2/16/18
Sat 2/17/18
Auto Scheduled
Define the overall budget
2 days
Mon 2/19/18
Tue 2/20/18
6
Auto Scheduled
outline the technical requirements
3 days
Wed 2/21/18
Fri 2/23/18
7
Manually Scheduled
Define site structure
7 days
Mon 2/26/18
Tue 3/6/18
Auto Scheduled
Complete the sitemap
2 days
17. Mon 2/26/18
Tue 2/27/18
Auto Scheduled
Adress the technical requirements outlined
3 days
Wed 2/28/18
Fri 3/2/18
10
Auto Scheduled
Begin site's content acquisition
2 days
Mon 3/5/18
Tue 3/6/18
11
Manually Scheduled
Design user interface
7 days
Wed 3/7/18
Thu 3/15/18
Auto Scheduled
Present the design
2 days
Wed 3/7/18
Thu 3/8/18
Auto Scheduled
Set the website's look and feel
3 days
Fri 3/9/18
Tue 3/13/18
14
Auto Scheduled
content acquisition
2 days
18. Wed 3/14/18
Thu 3/15/18
15
Manually Scheduled
Develop HTML protosite
7 days
Fri 3/16/18
Fri 3/23/18
Auto Scheduled
Coding
1 day
Fri 3/16/18
Fri 3/16/18
Auto Scheduled
design the user interface
3 days
Sat 3/17/18
Tue 3/20/18
18
Auto Scheduled
Finalize the website design
3 days
Wed 3/21/18
Fri 3/23/18
19
Manually Scheduled
Begin HTML production
7 days
Sat 3/24/18
Mon 4/2/18
Auto Scheduled
19. Programming outline phase
4 days
Sat 3/24/18
Wed 3/28/18
Auto Scheduled
incorporate the content and graphics
1 day
Thu 3/29/18
Thu 3/29/18
22
Auto Scheduled
finalize prototype
2 days
Fri 3/30/18
Mon 4/2/18
23
Manually Scheduled
Design tasks
7 days
Tue 4/3/18
Wed 4/11/18
Auto Scheduled
Develop storyboard
1 day
Tue 4/3/18
Tue 4/3/18
Auto Scheduled
Document design
1 day
Wed 4/4/18
Wed 4/4/18
26
Auto Scheduled
20. submit final design
5 days
Thu 4/5/18
Wed 4/11/18
27
Manually Scheduled
Make the website live
7 days
Thu 4/12/18
Thu 4/19/18
Auto Scheduled
Perform client sign off
2 days
Thu 4/12/18
Fri 4/13/18
Auto Scheduled
perform internal unit testing
3 days
Sat 4/14/18
Tue 4/17/18
30
Auto Scheduled
perform Usability testing
2 days
Wed 4/18/18
Thu 4/19/18
31
Manually Scheduled
Move the site to the end server
7 days
Sat 4/21/18
Mon 4/30/18
Auto Scheduled
21. Carry out cross-platform testing
3 days
Sat 4/21/18
Tue 4/24/18
Auto Scheduled
perform browser testing
2 days
Wed 4/25/18
Thu 4/26/18
34
Auto Scheduled
question and answers
2 days
Fri 4/27/18
Mon 4/30/18
35
Manually Scheduled
Further tests
8 days
Tue 5/1/18
Wed 5/9/18
Auto Scheduled
Make necessary modifications
2 days
Tue 5/1/18
Wed 5/2/18
Auto Scheduled
Final approval
2 days
Thu 5/3/18
Fri 5/4/18
38
Auto Scheduled
22. Launch the website
4 days
Sat 5/5/18
Wed 5/9/18
39
The above project plan for the HWE accessories website was
scheduled to run for a period of three months. All the
requirements and planning phase was done in the first week and
the following tasks were allocated a week each. The website’s
main purpose was to revolutionize the company’s transactions
into a more modern online environment thus the developers
employed the company’s prior information and used it in the
project planning. No new information about the functionalities
was collected to save time and resources.
Risk
Risk Level/impact
Probability of occurrence
Low(L)/Medium(M)/High(H)
Project Size
23. Person Hours
H: Over 20,000
Certainty
Estimated Schedule
H: Over 3 months
Certainty
Team Size
H: Over 15 members
Certainty
Number of Interfaces to Existing Systems Affected
H: Over 3
Certainty
Project Definition
Narrow Knowledge Level of Users
M: Knowledgeable of user area only
Likely
Available documentation clouds establishment of baseline
M: above 75% complete
Likely
Project Scope Creep
L: Scope generally defined and subject to revision
Unlikely
Consultant Project Deliverables unclear
L: Well defined
Unlikely
Vendor Project Deliverables
M: Estimated, not clearly defined
Somewhat likely
Cost Estimates Unrealistic
L: Thoroughly predicted by industry experts using proven
24. practices to 15% margin of error
Unlikely
Timeline Estimates Unrealistic
M: Timeline assumes no derailment
Somewhat likely
Number of Team Members Unknowledgeable of Business
L: Team well versed in business operations impacted by
technology
Unlikely
Project Leadership
Steering Committee existence
L: Identified and enthusiastic
Unlikely
Absence of Commitment Level/Attitude of Management
L: Understands value & supports project
Unlikely
Absence of Commitment Level/Attitude of Users
L: Understands value & supports project
Unlikely
Absence of Mid-Management Commitment
L: Most understand value & support project
Unlikely
Project Staffing
Project Team Availability
M: Distributed team makes availability questionable
Somewhat likely
Physical Location of Team prevents effective management
M: Team is dispersed among several sites
Likely
Project Team’s Shared Work Experience creates poor working
relationship
M: Some have worked together before
25. Somewhat likely
Weak User Participation on Project Team
L: Users are part-time team members
Unlikely
Project Management
Procurement
L: Procurement Methodology familiar to team
Unlikely
Methodology Used foreign to team
Change Management Procedures undefined
L: Well-defined
Unlikely
Quality Management Procedures unclear
L: Well-defined and accepted
Unlikely
Software Vendor
Number of Times Team Has Done Prior Work with Vendor
Creates Foreign Relationship
H: Never
Certainty
Team’s Lack of Knowledge of Package
M: Conceptual understanding
Somewhat likely
Poor Functional Match of website to Initial System
26. Requirements
L: Minimal customization required
Unlikely
The following are the key factors that will help to determine
whether the HWE accessories website project is successful.
1) A standing final contract.
The contract should be a written document that includes all the
agreed upon items with the software provider. Clearly defined
project items goes a long way to assist the project managers
since they now have leverage that they can hold the providers
accountable if any conditions are not met.
2) Project management plan
A proper plan of the project should be created to show how
various issues will be handled, the communication channels to
be used during the project undertaking and a clear statement of
the project schedule. The whole team should review this to
make sure they understand the agreed upon terms and can be
referred to in case of any deviation.
3) Defining the project scope.
This is a document that entails what is and is not in the project.
The steering committee should approve this before the
execution stage of the project begins.
4) Testing.
This is a crucial phase since it helps all users to understand the
application functionality. It helps gauge if the application or
website created is performing as expected or whether further
modifications need to be made before the actual live launch of
the website. Security is also tested thoroughly to ensure people
with malicious intent don’t cause harm or losses to the
company.
5) Verification.
Everyone who was involved in the development of the website
should check and countercheck if everything was completed. All
the deliverables and allocated tasks should be complete as a
single error could lead to the whole project failure. Staff who
27. have deep knowledge of the website’s business operations
should assist users during the first days to ensure they are well
acquainted with the site. Help stations or lines should be set up
to offer any assistance required.
6) Communication and follow up reports.
Lack of communication is the main problem facing projects that
have been noted to be having problems. The committee should
be informed, and meetings held from time to time to perform
reviews on the website. This also helps to identify the necessary
updates required to keep the site running effectively.
References:
CISA Certification Job Practice. (n.d.). Retrieved from ISACA:
http://www.isaca.org/Certification/CISA-Certified-Information-
Systems-Auditor/Job-Practice-Areas/Pages/CISA-Job-Practice-
Areas.aspx
College of Information Systems and Technology
BSA/515r4 - HWE Website
Contract Plan
Initiating Office:
Project Title:
Requiring Activity:
Estimated Value:
Contract Type:
APPROVALS
Contract Plan is approved.
28. __________________________________
__________________________________
(Requiring Official) (Requiring Official's Supervisor, if needed)
Date: __________________ Date: ___________________
__________________________________
__________________________________
(Insert name), Contracting Officer (Insert name), General
Counsel
Date: __________________ Date: ___________________
__________________________________
Lorraine Allison, Director, Procurement
Support Office
Date: _________________
A. BACKGROUND AND OBJECTIVES
1. Statement of Need.
I intend to create a new interactive website for the HWE
accessories where customers can easily view the updated
accessories and choose on their preferred choice without
necessarily visiting the physical retail shops. Unlike the
existing informational website, the new web page will allow the
users to navigate through it by offering various services for
instance, checking the prices of accessories and making online
purchases. A viable prior alternative contract comprised
29. creating a web page that only allowed customers to order the
commodities online and made physical payments limiting the
online payment option.
2. Applicable Conditions.
The new website will be designed within the desired time scale
and will include text, images and proper graphics. In addition, it
will be developed to work across major browsers, platforms and
on different screen sizes for example computers, mobile phones
and touch pads. The contract however does not guarantee
completely a long-term compatibility across all browsers and
platforms because of the increased likelihood of further
advancements of the updates and upgrades by the respective
vendors. The contract can also not offer full guarantee on
compatibility of the website to old and redundant software.
The contract period will be 12 months and unless under
agreeable terms will the company suppress the period. in case
the HWE company cancels the website agreement after the
design terms have been agreed, the contractor retains the right
to charge the company up to 85% of the total cost depending on
which stage the project has been cancelled even if the website
will not have gone live. The contractor will require a minimum
of one month notice from the company to cancel the web
development project.
3. Costs and Period of Performance. The projected expenditure
for the proposed system is based upon the Independent
Government Cost Estimate (IGCE) and is shown below:
BASE YEAR: 08-02-2018 - 07-02-2019
Contract Budget
Total
$307,468.53
A. Direct labor Hours Rate
Amount
1. Project Manager
720
$119.72
$86,197.07
30. 2. Software Engineer
1440
$99.72
$143,601.91
3. Technical Specialists
720
$74.56
$53,683.54
4. Web Developers
1440
$68.59
$98,775.00
Sub totals
$283,482.53
A) Equipment Purchases
Item Description
Quantity
Unit Price
Total
1. Office Chairs
3
$4,250.00
$12,750.00
2. office table
3. software
1
1
$253.00
$11,001
$235.00
$11,0001
31. SUBTOTAL
$ 12,985.00
4. Capability or performance.
the HWE website will offer capabilities related to hardware and
software constraints. While the hardware constraints include
processor cycles, real storage and network hardware detections,
software constraints will comprise of database design, network
design and use of specific software interfaces and functions.
5. Delivery or performance-period requirements.
The stipulated project time frame of one year is long enough to
cover exceptional cases that may arise during web development.
The allocated time for each task ensures that the project will be
completed on time and the website will be live on or before the
set period is over.
6. Trade-offs.
Some of the expected consequences of the trade- offs may lead
to adjustments of the project scope in terms of durations of the
completion of the project. For instance, the project manager
may consider shortening the project duration by increasing the
number of workers and this will eventually increase the cost and
performance. this will ensure the project manager achieves the
desired goals within the stipulated time
7. Risks.
the technical risks associated with this project involve
discovery of information, technology limits as well as
constraints that render the solution invalid. efforts taken to
reduce this risk comprises of factoring out technical and non-
32. technical risks into launch decisions and planning. An example
of these risks is lack of sufficient knowledge from the
programmers set to design the website. Other technical risks
associated with the project include unavailable test facilities,
lack of a suitable project manager and poor communication
among the stakeholders
Cost risk will occur when the project cost surpasses the
budgeted cost. to reduce this a Work Breakdown Structure
strategy has been employed which organizes project tasks into
phases. failure to do so will leas lead to poor performance due
to reduction of quality and scope of the project. besides, cost
risks are likely to extend the scheduled time frame since there
may be no enough funding to complete the project within the
desired time frame.
schedule risk in the project involves the project completion
taking more time than the scheduled time frame. to avoid this,
Program Evaluation Review Technique (PERT) has been used to
organize the project tasks into a network that represent
dependency of the various tasks. failure to apply the technique
may result into cost risks as well as performance risks. this is
because longer projects will always cost more and may as well
be too late for the project to achieve the intended tasks.
B. PLAN OF ACTION
1. Product or Service Description.
The website will be interactive to users by offering various
options in the web page and on menu driven interfaces that
support Graphical User Interfaces. the website will display
various types of accessories that HWE company offers
alongside their prices and features
2. Potential Sources.
a. Prospective Offerors:
Prospective offers will be identified using evaluation. The first
stage is by establishing the evaluation criteria to the source
selection authority for approval. Secondly, forming the
33. evaluation team and briefing them on their responsibilities.
Lastly conducting the evaluation based on whether the sole
source approach is available
b. Market Research:
Market Research was conducted by the IT personnel using
interviews, surveys and questionnaires on whether the project
was viable and would in any way would lead to improvement in
terms of service delivery. Through the use of statistical analysis
tools on the collected data, it was discovered that the project
was viable and necessary for the HWE Company and would
result in increase of service delivery, sales and entire business
process. The market research was used to develop effective
strategies on the proposed project
3. Competition.
The proposed plan is based on a competitive solicitation with
other upcoming creative web sites due to the continuing
advancements of the web designs. The interactivity of the
website improves customer’s satisfaction which will eventually
promote company’s profit.
4. Source Selection Procedures.
a. Evaluation Procedures.
Explain how offers will be evaluated, the relationship of the
evaluation procedures to the technical factors/standards,
technical evaluation team and solicitation requirements. For
example:
it will be essential to evaluate useful internal tools in order to
establish a good evaluation plan alongside with preparation of
soliciting document. The evaluation plan should be in a position
to have the necessary time frame and responsibilities attributed
to each team member. the proposals in this project should be
evaluated based on the best value procedure with emphasis
made on past performance capabilities and workforce.
b. Evaluation Factors
Some of the evaluation factors in the project include:
i) quality evaluation which may include evaluation of samples
ii) commercial evaluation
34. iii) supplier evaluation
iv) comparative analysis of results
c. Evaluation Factor Standards
first is the utility standards which are aimed at increasing the
extent which stakeholders find evaluation processes and
products essential in meeting their needs.
feasibility standards are aimed at increasing evaluation
efficiencies and effectiveness
propriety standards on the other hand support proper right, just
and legal during evaluation. others include accuracy standards
and evaluation accountability standards.
5. Contracting Considerations
a. Contract Type:
It is an executed contract since the customers/ buyers are in a
position to obtain accessories with ease through the new
webpage just by making logins in the webpage
b. Options:
in case the project is not completed within the stipulated time or
fails to follow the project scope, the project time and budget eill
be extended at the expense of the contractor
c. Special Contract Clauses/Provisions/Deviations:
the project prohibits access and distribution of private
information from being disclosed by third parties and need to do
so would require agreement between the parties involved.
A force majeure clause – in case of a failure to meet the
contractual obligation mainly through unavoidable
circumstances
d. Contracting Method:
the proposed project will use negotiated procedure as a viable
contracting method since it is flexible for use by the
stakeholders and offerors of the project. this contracting method
is essential in providing favorable strategies for competitions
with rival projects.
e. Contract Administration:
the contract project will be administered by HWE project
managers, potential shareholders, CEO and Project sponsors.
35. 6. Budgeting and Funding.
a. Derivation of Budgeting Estimates:
a detailed estimate for all the project costs was first compiled
and thereafter adding it to the budget plan. the strategy makes it
possible for contractor to track the project according to the
budget provided while the work is still ongoing.
b. Funding Availability:
The projections from the previous final years shows that the
contracted business is in a position to meet the required
financial capabilities
c. Currency Used: U.S. Dollar
7. Management Information Requirements.
The Quality Assurance Surveillance plan will be used to
continually monitor the progress of the project by giving
periodic feedbacks.
8. Logistics considerations.
For a project to run smoothly, certain aspects have to be
implemented before commencing on the project. Hardware,
software and hiring of new workers must be properly addressed
before any attempts of starting a project are made. the key
aspects include transfer of knowledge which requires the
contractor to train the staff so as to acquire the necessary skills
in addition, detailed schedules for implementation must be put
in place since it is illogical to implement the whole project all
at once. besides, risk identification factors must be strategized
because of the possibility of a new risk factor arising when the
project is taking place.
9. Business-Furnished Equipment.
the contractors will be provided with the necessary hardware
and software that will aid in website designing and will include
computers and printers. this hardware should be available
throughout the project implementation. office tables and chairs
are as well necessary before, during and after project
implementation
10. Business-Furnished Information.
Maps and drawings depicting the schedule, time frame and
37. 1
HWE Accessories Website: Business Case
4
This study is a project plan overview of HWE Accessories
Company. This is a company that primarily deals with the
production of accessories for cell phones such as screen covers
and cases. The company conducts most of their sales through
retail stores and their current website is reserved for only
information. The company is relatively young and small and
therefore lacks an internal department of information
technology. This study will carry out an unequivocal analysis
on the problem statement analysis of the situation, a cost-
benefit analysis, preliminary feasibility studies, the total cost of
ownership, the return on investments and culminate with an
analysis on the solution options recommendation.
The company is faced with the problem of not having an in-
depth website which can improve its market and reduce its
reliance on retail stores. The company is in dire need of a
website which can enable their customers to browse inventory.
In addition, it is also in need of a website where it customers
can compare items and consequently make their purchases. This
will go a long way in reducing their reliance on retail stores and
consequently improve their market base by making it easier for
the customers to reach them and also purchase their products.
One of the most profound ways of ensuring that the customers
are able to access the inventory of the company is by ensuring
that all of their products are available on their website in a way
that is easy for the customers to access the products in an easy
way. In addition, it is also important to ensure that the
customers are updated regarding the old stock and also the new
38. stock in a way that will make it easier for them to access the
products they desire. In addition, the website should also be
structured in a way that denotes the prices of all the products.
This will make it easier for the customers to know the price of
the products prior to requesting for them. In addition, it also
enables the customers to compare the products based on their
prices and consequently make their purchases according to their
purchase capabilities. In addition, the opportunity to view the
prices and to compare the prices will also enable the customers
to make informed budgets on some of the items that they would
wish to purchase in the near and distant future. A comparison of
the items will also reveal their uniqueness and also their quality
and consequently enable the customers to make prudent
decisions when purchasing the items.
In terms of the cost-benefit analysis, it is evident that the
benefits that will be accrued out of the development and
improvement of their website will be significant. One of the
main benefits will be the fact that the market share will
ultimately increase. Secondly, the company will attract a
constant clientele. Thirdly, the company will be able to get a
prompt feedback from the customers and consequently improve
on their products’ features and also on their services. The
preliminary feasibility study will be conducted on the website
and also through the various social media sites. The total cost of
ownership will be conducted by assessing both the direct and
indirect costs that have been incurred out of the development of
the website. The return on investment on the other hand will be
calculated based on the returns from the website relative to the
costs incurred out of the same. The solutions options
recommendation would be to go ahead and implement the
website since the benefits will far outweigh the costs.
39. References
Hallam, S. (2017, January 10). Amazon's Business Strategy: 6
examples of latest trends in ecommerce | Hallam Internet.
Retrieved from https://www.hallaminternet.com/amazons-
business-strategy-new-developments/
Kumar, V. (2017). Data security in cloud computing. Stevenage:
The Institution of Engineering and Technology.