SlideShare a Scribd company logo
1 of 21
CASe exAMPle: geneRAl AvIATIOn hAngAR
ReSTORATIOn
I n t ro d u c t i o n
this case example, although for a very small project, illustrates
some interesting features of
planning using critical path analysis. although there are only 17
activities, the precedence
logic is a little complex to draw clearly owing to the number of
crossed links, and we
show how this difficulty is easily overcome by inserting dummy
activities at three of the
crossover points.
our case example demonstrates the application of pert (program
evaluation and
review technique), in which the estimated duration for each
activity can be subjected
to a probabilistic study in an attempt to forecast the most likely
completion time for the
entire project.
finally, this case will demonstrate how a project manager need
not accept the results of
time analysis without question, but can plan to apply extra
effort to expedite critical activities
(usually for additional cost) to bring the planned project
completion date forward
P ro j e c t B a c k g ro u n d
CEN-CONSTRUCT is a medium-sized business located in
Sydney, Australia that is
owned and operated by a family. It is principally a consulting
company that specializes in
aviation civil engineering, having worked on runway
construction and paving projects as
well as several other airport airside projects, most of which
have been for smaller general
airports. Having decided to extend its range of operations, the
company recognized a local
need for a contractor that could carry out aircraft hangar
renovation. In consequence, the
company has now achieved a good level of expertise in the
interior design and renovation
of hangars
the subject of this case example was the renovation of a hangar
for a small client at a
general aviation airport. the client uses the hangar to house his
cessna 310 twin-engine
plane. the hangar was originally built in 1950, since when no
further construction or
renovation work has been carried out. cen-construct had no
previous integrated
project management system or strategy for this type of project,
so the project management
planning steps described here were implemented for them. the
planning exhibits are
slightly simplified for clarity of reproduction.
P ro j e c t D e f i n i t i o n A n d A c t i v i t y L i s t
Because the total number of identified activities was small, a
simple activity list (task
list) sufficed for the WBS. This list, given in Figure 7.11,
defines the project scope. It also
defines the logical work sequence by stating the immediate
predecessor(s) that must be
completed before each new activity can begin. the cost
estimates show that the total
original estimated cost for this project was $46 900.
Readers will note that the table in Figure 7.11 contains four
different duration estimates
for each activity. this is because the project planner decided to
use a probability assessment
method known as pert to this project. this is explained in the
following section.
a v i a t i o n p r o j e c t m a n a g e m e n t� � �
Flouris, T. G., & Lock, D. (2008). Aviation project
management. Retrieved from http://ebookcentral.proquest.com
Created from erau on 2018-09-26 17:31:09.
C
op
yr
ig
ht
©
2
00
8.
R
ou
tle
dg
e.
A
ll
rig
ht
s
re
se
rv
ed
.
A p p l i c a t i o n O f P E RT To T h e H a n g a r R e n o v
a t i o n P ro j e c t
Almost all duration estimates are a matter for subjective
judgement and the actual outcome
for each activity can be quite different from the planner’s
intention. One branch of critical
path analysis recognizes this uncertainty. The method, one of
the earliest critical path
analysis methods, is program evaluation and review technique
(pert). each person who
estimates the duration of an activity is asked to give three
possible values which are:
tm = the most likely estimated time
to = the most optimistic estimated time
tp = the most pessimistic estimated time
the values are inserted in the following formula for each
activity to give the most
probable or expected time, which is based on the standard
deviation from a normal
statistical distribution curve:
te = (to + 4tm + tp)/6.
this method was used for the hangar renovation project, and the
data are given in the
four estimated duration columns of figure 7.11.
Install toilet and shower
Figure 7.11 Activity list for the aircraft hangar
renovation project
c h a p t e r � • p l a n n i n g t h e a v i a t i o n p r o j e c t
t i m e s c a l e � � �
Flouris, T. G., & Lock, D. (2008). Aviation project
management. Retrieved from http://ebookcentral.proquest.com
Created from erau on 2018-09-26 17:31:09.
C
op
yr
ig
ht
©
2
00
8.
R
ou
tle
dg
e.
A
ll
rig
ht
s
re
se
rv
ed
.
T h e N e t w o r k D i a g r a m A n d I t s I n i t i a l Ti m e
A n a l y s i s
the network diagram, using expected duration values, is shown
in figure 7.12. time
analysis has revealed the critical path (shown in bold lines) and
indicates a most probable
project duration of 67.9 days.
Two dummy activities, identified as A and B, have been
inserted to clarify the logic
drawing. These dummy activities do not affect the network logic
(work sequence) and as
they both have zero duration they do not affect time analysis. It
is quite usual to add a start
dummy and a finish dummy to network diagrams that otherwise
would have multiple starts
and finishes, but their use within a precedence network, as here,
is less common. However, a
glance at figure 7.13 shows that they can improve the clarity of
a network diagram.
M e a s u re s F o r R e d u c i n g T h e P re d i c t e d Ti m
e s c a l e
It often happens that the predicted timescale for a project is too
long, and that was the case
in this example, with the client specifying that he wanted to fly
in and house his airplane
between days 50 and 55 of this project. clearly the originally
planned completion time
of day 68 would have been far too late. there are two possible
approaches to shortening
the planned timescale of a project. the project manager has a
choice between these two
methods or, to achieve maximum expedition, can use both
methods together.
Fast-tracking using concurrency Network logic often shows
constraints that are not literally
true, and it is known that some activities can be allowed to
overlap or even run concurrently.
one example is in the purchase of long-lead items, where design
engineers are able to release
purchasing information to the buyer before the relevant design
activity has been completed.
the complex constraints given in figure 7.10 showed how the
precedence system will
allow such overlaps to be depicted in a network. However, that
process was not considered
applicable on this aircraft hangar case project and will not be
described further here.
Shortening activity durations by crash action It is often possible
to shorten the duration
of an activity by deploying more resources, using different
processes, or working overtime.
these actions usually add additional cost, and it would thus be
wasteful to crash activities with
large amounts of slack because, to do so, would have no effect
on the total project duration.
Crash action must be considered first, therefore, only on
activities which lie on the
critical path. constructing a table that compares time saved on
an activity with the relevant
additional cost can theoretically produce a factor for each
activity that will reveal the cost
per day saved for that activity.
thus crash action can be even more selective than choosing only
critical activities,
because it can be concentrated on those critical activities which
have the lowest cost per day
saved. However, the exercise becomes complicated in practice
because as one or two critical
activities are crashed and the critical path is shortened, other
paths through the network
become critical. Crash attention must then shift to the newly
created critical activities.
theoretically this process can be reiterated until all activities
and all possible paths through
the network become critical. It could then be claimed that the
network has been optimized,
but that claim needs to be taken with considerable
circumspection because it is based on a
false premise. remember that every duration estimate is only an
estimate, so the perceived
mathematical precision of total network crash optimization is a
myth.
a v i a t i o n p r o j e c t m a n a g e m e n t� � 0
Flouris, T. G., & Lock, D. (2008). Aviation project
management. Retrieved from http://ebookcentral.proquest.com
Created from erau on 2018-09-26 17:31:09.
C
op
yr
ig
ht
©
2
00
8.
R
ou
tle
dg
e.
A
ll
rig
ht
s
re
se
rv
ed
.
10
: T
oi
le
t a
nd
sh
ow
er
Fi
gu
re
7
.1
2
n
et
w
or
k
d
ia
gr
am
f
or
t
h
e
h
an
ga
r
re
n
ov
at
io
n
p
ro
je
ct
b
ef
or
e
cr
as
h
in
g
th
e
ti
m
es
Flouris, T. G., & Lock, D. (2008). Aviation project
management. Retrieved from http://ebookcentral.proquest.com
Created from erau on 2018-09-26 17:31:09.
C
op
yr
ig
ht
©
2
00
8.
R
ou
tle
dg
e.
A
ll
rig
ht
s
re
se
rv
ed
.
Figure 7.13 use of dummy activities in precedence
networks to clarify
multiple links
Install toilet and shower
Figure 7.14 Activity list for the aircraft hangar
renovation project showing
crashed times and extracosts
a v i a t i o n p r o j e c t m a n a g e m e n t� � �
Flouris, T. G., & Lock, D. (2008). Aviation project
management. Retrieved from http://ebookcentral.proquest.com
Created from erau on 2018-09-26 17:31:09.
C
op
yr
ig
ht
©
2
00
8.
R
ou
tle
dg
e.
A
ll
rig
ht
s
re
se
rv
ed
.
there is no slack in a totally crashed network, so that all or most
activities are critical and
that increases the risk of failing to meet the delivery date.
further, the probability results
from the original pert time analysis no longer apply, because
each crashed estimate has
been made on a deterministic, not probabilistic basis.
In the aircraft hangar renovation project a realistic approach to
crash action produced
the table shown in Figure 7.14 on the left. When the crashed
times were substituted for the
pert normal duration estimates in the network diagram they
produced a total estimated
project time of 43 days, well within the client’s requirements.
the notes in figure 7.14 show that some activities were less
costly to crash than others
in terms of the dollars budgeted for each day’s time saved.
note that although activity 10 could have been shortened from
5.2 to 3 days, the
additional expenditure of crashing that task was not justified
because Activity 11, running
concurrently, could not be crashed below 6 days. in other
words, activity 10 still had slack
remaining after Activity 11 had been crashed, and there is no
point in wasting money on
crashing non-critical activities, because that process cannot
reduce the project duration.
Summarizing, therefore, the hangar restoration project duration
was originally planned
as 67.9 days at a budget cost of $46 900. crash actions brought
the planned duration down
to 43 days but added $15 000 to the total project budget.
c h a p t e r � • p l a n n i n g t h e a v i a t i o n p r o j e c t
t i m e s c a l e � � �
Flouris, T. G., & Lock, D. (2008). Aviation project
management. Retrieved from http://ebookcentral.proquest.com
Created from erau on 2018-09-26 17:31:09.
C
op
yr
ig
ht
©
2
00
8.
R
ou
tle
dg
e.
A
ll
rig
ht
s
re
se
rv
ed
.
General Aviation Hangar Renovation Group Case Study
Assuming the perspective of your role (Project Manager),
consider how you would address the following case study
questions:
1. What are the key issues surrounding this case?
2. What is the nature of the problems that exist?
3. Identify opportunities that may be involved.
4. In what ways were problems resolved or leveraged?
5. Recommend and justify additional courses of action that are
most likely to be effective.
Student 1 – Project ManagerJob Responsibilities: Accomplishes
project objectives by planning and evaluating project activities..
After reading the case study in the PDF file attached separately,
answer the 5 questions above from a Project Manager
perspective. DON'T JUST GIVE GENERAL ANSWERS TO
THE QUESTIONS. IT HAS TO BE FROM A project manager
POINT OF VIEW. YOUR PERSONAL OPINION AS PROJECT
MANAGER.
DON't list references or citations, as this is supposed to be your
own personal opinion from a project Manager point of view.
AT LEAST 50 Words for each answer.
Copy the questions, then put the answers below each question,
in a Q&A format.
General Aviation Hangar Renovation Group Case
Stud
y
Assum
ing the perspective of your role
(
Project Manager
)
,
consider how
you would address the following case study questions:
1.
What are the key issues surrounding this case?
2.
What is the nature of the problems that exist?
3.
Identify opportunities that may be involved.
4.
In what ways were problems resolved or leveraged?
5.
Recommend and justify additional courses of action that are
most likely to
be effective.
Student 1
–
Project
Manager
Job Responsibilities: Accomplishes project objectives by
planning and evaluating
project activities
.
.
After reading the case study in the PDF file attached
separately, answ
er the 5 questions above from
a
Project Manager
perspective
.
DON'T JUST GIVE GENERAL ANSWERS TO THE
QUESTIONS. IT HAS TO BE FROM
A project manager
POINT OF
VIEW. YOUR
PERSONAL OPINION
AS
PROJECT MANAGER
.
DON't
list references or citations, as this is supposed to be
your own pe
rsonal
opinion from a project
Manager
point of
view.
AT LEAST
50 Words for each answer.
Copy the questions, then put the answer
s
below
each question,
in a Q&A format.
General Aviation Hangar Renovation Group Case
Study
Assuming the perspective of your role (Project Manager),
consider how
you would address the following case study questions:
1. What are the key issues surrounding this case?
2. What is the nature of the problems that exist?
3. Identify opportunities that may be involved.
4. In what ways were problems resolved or leveraged?
5. Recommend and justify additional courses of action that are
most likely to
be effective.
Student 1 – Project Manager
Job Responsibilities: Accomplishes project objectives by
planning and evaluating
project activities..
After reading the case study in the PDF file attached
separately, answer the 5 questions above from a Project
Manager
perspective. DON'T JUST GIVE GENERAL ANSWERS TO
THE
QUESTIONS. IT HAS TO BE FROM A project manager POINT
OF
VIEW. YOUR PERSONAL OPINION AS PROJECT
MANAGER.
DON't list references or citations, as this is supposed to be
your own personal opinion from a project Manager point of
view.
AT LEAST 50 Words for each answer.
Copy the questions, then put the answers
below each question, in a Q&A format.

More Related Content

Similar to CASeexAMPlegeneRAlAvIATIOnhAngARReSTORATIOnI n t r.docx

PERT.pptx
PERT.pptxPERT.pptx
PERT.pptx
Snehal Athawale
 
Overview1) Overview – The continued discussion of .docx
Overview1)             Overview – The continued discussion of .docxOverview1)             Overview – The continued discussion of .docx
Overview1) Overview – The continued discussion of .docx
alfred4lewis58146
 
Overview1) Overview – The continued discussion of project implem.docx
Overview1) Overview – The continued discussion of project implem.docxOverview1) Overview – The continued discussion of project implem.docx
Overview1) Overview – The continued discussion of project implem.docx
alfred4lewis58146
 

Similar to CASeexAMPlegeneRAlAvIATIOnhAngARReSTORATIOnI n t r.docx (20)

project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
 
PERT.pptx
PERT.pptxPERT.pptx
PERT.pptx
 
Overview1) Overview – The continued discussion of .docx
Overview1)             Overview – The continued discussion of .docxOverview1)             Overview – The continued discussion of .docx
Overview1) Overview – The continued discussion of .docx
 
Overview1) Overview – The continued discussion of project implem.docx
Overview1) Overview – The continued discussion of project implem.docxOverview1) Overview – The continued discussion of project implem.docx
Overview1) Overview – The continued discussion of project implem.docx
 
Pert Analysis
Pert AnalysisPert Analysis
Pert Analysis
 
Project-Management.ppt
Project-Management.pptProject-Management.ppt
Project-Management.ppt
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
 
Pert cpm-22-3-21
Pert cpm-22-3-21Pert cpm-22-3-21
Pert cpm-22-3-21
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 ppt
 
A760535773_16727_28_2018_u6.ppt
A760535773_16727_28_2018_u6.pptA760535773_16727_28_2018_u6.ppt
A760535773_16727_28_2018_u6.ppt
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
 
Ii. pert cpm
Ii. pert cpmIi. pert cpm
Ii. pert cpm
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
IGNOU PERT CPM
IGNOU PERT CPMIGNOU PERT CPM
IGNOU PERT CPM
 
Basics CPM&PERT.ppt
Basics CPM&PERT.pptBasics CPM&PERT.ppt
Basics CPM&PERT.ppt
 
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSPLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
Ovi project
Ovi  projectOvi  project
Ovi project
 
Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
 
Cpm module iii reference
Cpm module iii referenceCpm module iii reference
Cpm module iii reference
 

More from troutmanboris

Christian Schussele Men of ProgressOil on canvas, 1862Coope.docx
Christian Schussele  Men of ProgressOil on canvas, 1862Coope.docxChristian Schussele  Men of ProgressOil on canvas, 1862Coope.docx
Christian Schussele Men of ProgressOil on canvas, 1862Coope.docx
troutmanboris
 
Christian EthicsChristian ethics deeply align with absolutism. E.docx
Christian EthicsChristian ethics deeply align with absolutism. E.docxChristian EthicsChristian ethics deeply align with absolutism. E.docx
Christian EthicsChristian ethics deeply align with absolutism. E.docx
troutmanboris
 
Christian Ethics BA 616 Business Ethics Definiti.docx
Christian Ethics BA 616 Business Ethics Definiti.docxChristian Ethics BA 616 Business Ethics Definiti.docx
Christian Ethics BA 616 Business Ethics Definiti.docx
troutmanboris
 
CHPSI think you made a really good point that Howard lacks poli.docx
CHPSI think you made a really good point that Howard lacks poli.docxCHPSI think you made a really good point that Howard lacks poli.docx
CHPSI think you made a really good point that Howard lacks poli.docx
troutmanboris
 
Chose one person to reply to ALBORES 1. Were Manning’s acti.docx
Chose one person to reply to ALBORES 1. Were Manning’s acti.docxChose one person to reply to ALBORES 1. Were Manning’s acti.docx
Chose one person to reply to ALBORES 1. Were Manning’s acti.docx
troutmanboris
 
Choosing your literary essay topic on Disgrace by J. M. Coetzee .docx
Choosing your literary essay topic on Disgrace by J. M. Coetzee .docxChoosing your literary essay topic on Disgrace by J. M. Coetzee .docx
Choosing your literary essay topic on Disgrace by J. M. Coetzee .docx
troutmanboris
 
Choosing your Philosophical Question The Final Project is an opp.docx
Choosing your Philosophical Question The Final Project is an opp.docxChoosing your Philosophical Question The Final Project is an opp.docx
Choosing your Philosophical Question The Final Project is an opp.docx
troutmanboris
 
Choosing Your Research Method in a NutshellBy James Rice and.docx
Choosing Your Research Method in a NutshellBy James Rice and.docxChoosing Your Research Method in a NutshellBy James Rice and.docx
Choosing Your Research Method in a NutshellBy James Rice and.docx
troutmanboris
 

More from troutmanboris (20)

Christian Schussele Men of ProgressOil on canvas, 1862Coope.docx
Christian Schussele  Men of ProgressOil on canvas, 1862Coope.docxChristian Schussele  Men of ProgressOil on canvas, 1862Coope.docx
Christian Schussele Men of ProgressOil on canvas, 1862Coope.docx
 
Christian EthicsChristian ethics deeply align with absolutism. E.docx
Christian EthicsChristian ethics deeply align with absolutism. E.docxChristian EthicsChristian ethics deeply align with absolutism. E.docx
Christian EthicsChristian ethics deeply align with absolutism. E.docx
 
Christian Ethics BA 616 Business Ethics Definiti.docx
Christian Ethics BA 616 Business Ethics Definiti.docxChristian Ethics BA 616 Business Ethics Definiti.docx
Christian Ethics BA 616 Business Ethics Definiti.docx
 
CHPSI think you made a really good point that Howard lacks poli.docx
CHPSI think you made a really good point that Howard lacks poli.docxCHPSI think you made a really good point that Howard lacks poli.docx
CHPSI think you made a really good point that Howard lacks poli.docx
 
Chrétien de Troyes, Lancelot, 1Chrétien de Troyes, Lancelo.docx
Chrétien de Troyes, Lancelot, 1Chrétien de Troyes, Lancelo.docxChrétien de Troyes, Lancelot, 1Chrétien de Troyes, Lancelo.docx
Chrétien de Troyes, Lancelot, 1Chrétien de Troyes, Lancelo.docx
 
Chosen brand CHANELStudents are required to research a fash.docx
Chosen brand CHANELStudents are required to research a fash.docxChosen brand CHANELStudents are required to research a fash.docx
Chosen brand CHANELStudents are required to research a fash.docx
 
Chose one person to reply to ALBORES 1. Were Manning’s acti.docx
Chose one person to reply to ALBORES 1. Were Manning’s acti.docxChose one person to reply to ALBORES 1. Were Manning’s acti.docx
Chose one person to reply to ALBORES 1. Were Manning’s acti.docx
 
Choosing your literary essay topic on Disgrace by J. M. Coetzee .docx
Choosing your literary essay topic on Disgrace by J. M. Coetzee .docxChoosing your literary essay topic on Disgrace by J. M. Coetzee .docx
Choosing your literary essay topic on Disgrace by J. M. Coetzee .docx
 
Choosing your Philosophical Question The Final Project is an opp.docx
Choosing your Philosophical Question The Final Project is an opp.docxChoosing your Philosophical Question The Final Project is an opp.docx
Choosing your Philosophical Question The Final Project is an opp.docx
 
Choosing Your Research Method in a NutshellBy James Rice and.docx
Choosing Your Research Method in a NutshellBy James Rice and.docxChoosing Your Research Method in a NutshellBy James Rice and.docx
Choosing Your Research Method in a NutshellBy James Rice and.docx
 
Choose two of the systems (education, work, the military, and im.docx
Choose two of the systems (education, work, the military, and im.docxChoose two of the systems (education, work, the military, and im.docx
Choose two of the systems (education, work, the military, and im.docx
 
Choose two disorders from the categories presented this week.C.docx
Choose two disorders from the categories presented this week.C.docxChoose two disorders from the categories presented this week.C.docx
Choose two disorders from the categories presented this week.C.docx
 
Choose ONE of the following topics Length 750-900 words, .docx
Choose ONE of the following topics Length 750-900 words, .docxChoose ONE of the following topics Length 750-900 words, .docx
Choose ONE of the following topics Length 750-900 words, .docx
 
Choose one of the following topicsAmerica A Narrative.docx
Choose one of the following topicsAmerica A Narrative.docxChoose one of the following topicsAmerica A Narrative.docx
Choose one of the following topicsAmerica A Narrative.docx
 
Choose one of the following topics below. Comparecont.docx
Choose one of the following topics below. Comparecont.docxChoose one of the following topics below. Comparecont.docx
Choose one of the following topics below. Comparecont.docx
 
Choose one of the following topics below. Comparecon.docx
Choose one of the following topics below. Comparecon.docxChoose one of the following topics below. Comparecon.docx
Choose one of the following topics below. Comparecon.docx
 
Choose one of the states of RacialCultural Identity Development.docx
Choose one of the states of RacialCultural Identity Development.docxChoose one of the states of RacialCultural Identity Development.docx
Choose one of the states of RacialCultural Identity Development.docx
 
Choose one of the following topicsNative AmericansWomenEnvi.docx
Choose one of the following topicsNative AmericansWomenEnvi.docxChoose one of the following topicsNative AmericansWomenEnvi.docx
Choose one of the following topicsNative AmericansWomenEnvi.docx
 
Choose one of the following films for review (with faculty’s appro.docx
Choose one of the following films for review (with faculty’s appro.docxChoose one of the following films for review (with faculty’s appro.docx
Choose one of the following films for review (with faculty’s appro.docx
 
Choose and complete one of the two assignment options.docx
Choose and complete one of the two assignment options.docxChoose and complete one of the two assignment options.docx
Choose and complete one of the two assignment options.docx
 

Recently uploaded

Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
PECB
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
QucHHunhnh
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
ciinovamais
 

Recently uploaded (20)

Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docx
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 

CASeexAMPlegeneRAlAvIATIOnhAngARReSTORATIOnI n t r.docx

  • 1. CASe exAMPle: geneRAl AvIATIOn hAngAR ReSTORATIOn I n t ro d u c t i o n this case example, although for a very small project, illustrates some interesting features of planning using critical path analysis. although there are only 17 activities, the precedence logic is a little complex to draw clearly owing to the number of crossed links, and we show how this difficulty is easily overcome by inserting dummy activities at three of the crossover points. our case example demonstrates the application of pert (program evaluation and review technique), in which the estimated duration for each activity can be subjected to a probabilistic study in an attempt to forecast the most likely completion time for the entire project. finally, this case will demonstrate how a project manager need not accept the results of time analysis without question, but can plan to apply extra effort to expedite critical activities (usually for additional cost) to bring the planned project completion date forward P ro j e c t B a c k g ro u n d
  • 2. CEN-CONSTRUCT is a medium-sized business located in Sydney, Australia that is owned and operated by a family. It is principally a consulting company that specializes in aviation civil engineering, having worked on runway construction and paving projects as well as several other airport airside projects, most of which have been for smaller general airports. Having decided to extend its range of operations, the company recognized a local need for a contractor that could carry out aircraft hangar renovation. In consequence, the company has now achieved a good level of expertise in the interior design and renovation of hangars the subject of this case example was the renovation of a hangar for a small client at a general aviation airport. the client uses the hangar to house his cessna 310 twin-engine plane. the hangar was originally built in 1950, since when no further construction or renovation work has been carried out. cen-construct had no previous integrated project management system or strategy for this type of project, so the project management planning steps described here were implemented for them. the planning exhibits are slightly simplified for clarity of reproduction. P ro j e c t D e f i n i t i o n A n d A c t i v i t y L i s t Because the total number of identified activities was small, a simple activity list (task list) sufficed for the WBS. This list, given in Figure 7.11, defines the project scope. It also
  • 3. defines the logical work sequence by stating the immediate predecessor(s) that must be completed before each new activity can begin. the cost estimates show that the total original estimated cost for this project was $46 900. Readers will note that the table in Figure 7.11 contains four different duration estimates for each activity. this is because the project planner decided to use a probability assessment method known as pert to this project. this is explained in the following section. a v i a t i o n p r o j e c t m a n a g e m e n t� � � Flouris, T. G., & Lock, D. (2008). Aviation project management. Retrieved from http://ebookcentral.proquest.com Created from erau on 2018-09-26 17:31:09. C op yr ig ht © 2 00 8. R ou tle
  • 4. dg e. A ll rig ht s re se rv ed . A p p l i c a t i o n O f P E RT To T h e H a n g a r R e n o v a t i o n P ro j e c t Almost all duration estimates are a matter for subjective judgement and the actual outcome for each activity can be quite different from the planner’s intention. One branch of critical path analysis recognizes this uncertainty. The method, one of the earliest critical path analysis methods, is program evaluation and review technique (pert). each person who estimates the duration of an activity is asked to give three possible values which are: tm = the most likely estimated time
  • 5. to = the most optimistic estimated time tp = the most pessimistic estimated time the values are inserted in the following formula for each activity to give the most probable or expected time, which is based on the standard deviation from a normal statistical distribution curve: te = (to + 4tm + tp)/6. this method was used for the hangar renovation project, and the data are given in the four estimated duration columns of figure 7.11. Install toilet and shower Figure 7.11 Activity list for the aircraft hangar renovation project c h a p t e r � • p l a n n i n g t h e a v i a t i o n p r o j e c t t i m e s c a l e � � � Flouris, T. G., & Lock, D. (2008). Aviation project management. Retrieved from http://ebookcentral.proquest.com Created from erau on 2018-09-26 17:31:09. C op yr ig ht ©
  • 6. 2 00 8. R ou tle dg e. A ll rig ht s re se rv ed . T h e N e t w o r k D i a g r a m A n d I t s I n i t i a l Ti m e A n a l y s i s the network diagram, using expected duration values, is shown in figure 7.12. time analysis has revealed the critical path (shown in bold lines) and indicates a most probable
  • 7. project duration of 67.9 days. Two dummy activities, identified as A and B, have been inserted to clarify the logic drawing. These dummy activities do not affect the network logic (work sequence) and as they both have zero duration they do not affect time analysis. It is quite usual to add a start dummy and a finish dummy to network diagrams that otherwise would have multiple starts and finishes, but their use within a precedence network, as here, is less common. However, a glance at figure 7.13 shows that they can improve the clarity of a network diagram. M e a s u re s F o r R e d u c i n g T h e P re d i c t e d Ti m e s c a l e It often happens that the predicted timescale for a project is too long, and that was the case in this example, with the client specifying that he wanted to fly in and house his airplane between days 50 and 55 of this project. clearly the originally planned completion time of day 68 would have been far too late. there are two possible approaches to shortening the planned timescale of a project. the project manager has a choice between these two methods or, to achieve maximum expedition, can use both methods together. Fast-tracking using concurrency Network logic often shows constraints that are not literally true, and it is known that some activities can be allowed to overlap or even run concurrently. one example is in the purchase of long-lead items, where design
  • 8. engineers are able to release purchasing information to the buyer before the relevant design activity has been completed. the complex constraints given in figure 7.10 showed how the precedence system will allow such overlaps to be depicted in a network. However, that process was not considered applicable on this aircraft hangar case project and will not be described further here. Shortening activity durations by crash action It is often possible to shorten the duration of an activity by deploying more resources, using different processes, or working overtime. these actions usually add additional cost, and it would thus be wasteful to crash activities with large amounts of slack because, to do so, would have no effect on the total project duration. Crash action must be considered first, therefore, only on activities which lie on the critical path. constructing a table that compares time saved on an activity with the relevant additional cost can theoretically produce a factor for each activity that will reveal the cost per day saved for that activity. thus crash action can be even more selective than choosing only critical activities, because it can be concentrated on those critical activities which have the lowest cost per day saved. However, the exercise becomes complicated in practice because as one or two critical activities are crashed and the critical path is shortened, other paths through the network become critical. Crash attention must then shift to the newly
  • 9. created critical activities. theoretically this process can be reiterated until all activities and all possible paths through the network become critical. It could then be claimed that the network has been optimized, but that claim needs to be taken with considerable circumspection because it is based on a false premise. remember that every duration estimate is only an estimate, so the perceived mathematical precision of total network crash optimization is a myth. a v i a t i o n p r o j e c t m a n a g e m e n t� � 0 Flouris, T. G., & Lock, D. (2008). Aviation project management. Retrieved from http://ebookcentral.proquest.com Created from erau on 2018-09-26 17:31:09. C op yr ig ht © 2 00 8. R ou tle
  • 12. or e cr as h in g th e ti m es Flouris, T. G., & Lock, D. (2008). Aviation project management. Retrieved from http://ebookcentral.proquest.com Created from erau on 2018-09-26 17:31:09. C op yr ig ht © 2 00 8. R ou tle dg
  • 13. e. A ll rig ht s re se rv ed . Figure 7.13 use of dummy activities in precedence networks to clarify multiple links Install toilet and shower Figure 7.14 Activity list for the aircraft hangar renovation project showing crashed times and extracosts a v i a t i o n p r o j e c t m a n a g e m e n t� � � Flouris, T. G., & Lock, D. (2008). Aviation project management. Retrieved from http://ebookcentral.proquest.com Created from erau on 2018-09-26 17:31:09. C
  • 15. there is no slack in a totally crashed network, so that all or most activities are critical and that increases the risk of failing to meet the delivery date. further, the probability results from the original pert time analysis no longer apply, because each crashed estimate has been made on a deterministic, not probabilistic basis. In the aircraft hangar renovation project a realistic approach to crash action produced the table shown in Figure 7.14 on the left. When the crashed times were substituted for the pert normal duration estimates in the network diagram they produced a total estimated project time of 43 days, well within the client’s requirements. the notes in figure 7.14 show that some activities were less costly to crash than others in terms of the dollars budgeted for each day’s time saved. note that although activity 10 could have been shortened from 5.2 to 3 days, the additional expenditure of crashing that task was not justified because Activity 11, running concurrently, could not be crashed below 6 days. in other words, activity 10 still had slack remaining after Activity 11 had been crashed, and there is no point in wasting money on crashing non-critical activities, because that process cannot reduce the project duration. Summarizing, therefore, the hangar restoration project duration was originally planned as 67.9 days at a budget cost of $46 900. crash actions brought the planned duration down
  • 16. to 43 days but added $15 000 to the total project budget. c h a p t e r � • p l a n n i n g t h e a v i a t i o n p r o j e c t t i m e s c a l e � � � Flouris, T. G., & Lock, D. (2008). Aviation project management. Retrieved from http://ebookcentral.proquest.com Created from erau on 2018-09-26 17:31:09. C op yr ig ht © 2 00 8. R ou tle dg e. A ll rig ht
  • 17. s re se rv ed . General Aviation Hangar Renovation Group Case Study Assuming the perspective of your role (Project Manager), consider how you would address the following case study questions: 1. What are the key issues surrounding this case? 2. What is the nature of the problems that exist? 3. Identify opportunities that may be involved. 4. In what ways were problems resolved or leveraged? 5. Recommend and justify additional courses of action that are most likely to be effective. Student 1 – Project ManagerJob Responsibilities: Accomplishes project objectives by planning and evaluating project activities.. After reading the case study in the PDF file attached separately, answer the 5 questions above from a Project Manager perspective. DON'T JUST GIVE GENERAL ANSWERS TO THE QUESTIONS. IT HAS TO BE FROM A project manager POINT OF VIEW. YOUR PERSONAL OPINION AS PROJECT MANAGER. DON't list references or citations, as this is supposed to be your own personal opinion from a project Manager point of view. AT LEAST 50 Words for each answer. Copy the questions, then put the answers below each question, in a Q&A format. General Aviation Hangar Renovation Group Case
  • 18. Stud y Assum ing the perspective of your role ( Project Manager ) , consider how you would address the following case study questions: 1. What are the key issues surrounding this case? 2. What is the nature of the problems that exist? 3. Identify opportunities that may be involved. 4. In what ways were problems resolved or leveraged? 5. Recommend and justify additional courses of action that are most likely to be effective. Student 1 –
  • 19. Project Manager Job Responsibilities: Accomplishes project objectives by planning and evaluating project activities . . After reading the case study in the PDF file attached separately, answ er the 5 questions above from a Project Manager perspective . DON'T JUST GIVE GENERAL ANSWERS TO THE QUESTIONS. IT HAS TO BE FROM A project manager POINT OF VIEW. YOUR PERSONAL OPINION AS PROJECT MANAGER . DON't list references or citations, as this is supposed to be your own pe rsonal opinion from a project
  • 20. Manager point of view. AT LEAST 50 Words for each answer. Copy the questions, then put the answer s below each question, in a Q&A format. General Aviation Hangar Renovation Group Case Study Assuming the perspective of your role (Project Manager), consider how you would address the following case study questions: 1. What are the key issues surrounding this case? 2. What is the nature of the problems that exist? 3. Identify opportunities that may be involved. 4. In what ways were problems resolved or leveraged? 5. Recommend and justify additional courses of action that are most likely to be effective. Student 1 – Project Manager Job Responsibilities: Accomplishes project objectives by planning and evaluating project activities.. After reading the case study in the PDF file attached separately, answer the 5 questions above from a Project
  • 21. Manager perspective. DON'T JUST GIVE GENERAL ANSWERS TO THE QUESTIONS. IT HAS TO BE FROM A project manager POINT OF VIEW. YOUR PERSONAL OPINION AS PROJECT MANAGER. DON't list references or citations, as this is supposed to be your own personal opinion from a project Manager point of view. AT LEAST 50 Words for each answer. Copy the questions, then put the answers below each question, in a Q&A format.