SlideShare a Scribd company logo
1 of 22
Download to read offline
ADVANCED POWER ANALYTICS LIMITED
Onyx Group - HV installation Test Report
Client - Onyx
Document Prepared by - Ron Richardson (On behalf of Keysource)

Document Date - 02/05/2012
Table Of Contents
!       !   1.0 - Installation Report Overview	     	        	      	       	    	   3
	   	       2.0 - Testing Operation Schedule	       	        	      	       	    	   6-7
	   	       3.0 - HV Testing	
                            	       	        	      	        	      	       	    	   	
	   	       	       3.1 - HV Terminations	
	   	       	             3.1.1 - HV Feed to TX1	   	        	      	       	    	   9
	   	       	             3.1.2 - HV Feed to TX2	   	        	      	       	    	   10
	   	       	             3.1.3 - Scottish Power Incomer Number 1	 	        	    	   11
	   	       	             3.1.4 - Scottish Power Incomer Number 2	 	        	    	   12
	   	       	       3.2 - HV Switchboard
	   	       	             3.2.1 - HV Pressure testing of Busbars & Switchgear	   	   13
	   	       	             3.2.2 - Ductor Testing of HV Busbars 	    	       	    	   14
	   	       	       3.3 - HV Pressure Testing theory
	   	       	           3.3.1 - Pressure testing @ 25KV	     	      	       	    	   15
	   	       	           3.3.2 - Pressure testing @ 18KV	     	      	       	    	   16
	   	       	       3.4 - Transformer Testing
	   	       	           3.4.1 - Transformer No.1	   	        	      	       	    	   17
	   	       	           3.4.2 - Transformer No.2	   	        	      	       	    	   18
	   	       	       4.0 - Recommendations		         	        	      	       	    	   20
1 - HV Report Overview
The following report has been produced to help give clear indication of the testing procedures and the respective results of the tests that were necessary for
the successful implementation of the new HV Substation which has been installed at the Onyx Group data centre (Edinburgh)

Switchgear & Transformer Testing:

Due to the existing configuration (RMU ‘close-coupled’ to the Transformer) in order to carry out the testing of the Transformer it would be necessary to
disconnect the ‘new’ previously installed HV termination at the RMU and then use the switching ‘on’ positions to test through the switches onto the HV
windings of the Transformer. The HV test voltage values and durations would then have to be considered to ensure no possibility of ‘Over-stressing the HV
Equipment. Functional Switching Checks were also carried out to confirm Switching operation reliability.

Secondary protection tests were also carried out to check that the Switchgear would operate under fault conditions as well as Insulation resistance checks for
the Current Transformers

Method Statements and Risk assessments were constructed prior to the work commencing highlighting the Process and Immediate risk(s) in connection with
the tasks.

The equipment tested was subjected to the following electrical tests consisting of :

	       1 - Pre and post Insulation resistance testing @ 5KV

	       2 - Uni-polar HV Testing @ 18 - 25KV (for 1 min & 15min durations)

	       3 - Secondary Injections Currents (0 - 20 amps) for Trip Testing Simulations

	       4 - Ductor testing Currents (50 & 100 amps) for testing the HV Busbars

*Important Notes -

1 - Any recorded values lower than 75 Mega Ohms for Transformer tests will need to be reported to the manufacturer prior to any Energization activity as this
may representative of a potential Failure.

2 - Any HV Cables tests with Insulation resistance values lower than 500 Mega Ohms prior to Energization will be subject to further investigation works as this
may again be representative of imminent or possible near future Failure.
2 - Testing Operation Sheets
3 - HV Testing (Switchgear & Cables)
3.1.1 - HV Cable feed to TX1
3.1.2 - HV Cable feed to TX2
3.1.3 - Scottish Power Incomer No.1
3.1.4 - Scottish Power Incomer No.2
3.2.1 - HV Busbar Testing (Insulation Resistance & Pressure Testing)
3.2.2 - HV Busbar Testing (Ductor Testing)
3.3.1 - HV Pressure Testing Theory (25 KV)




                       System Voltage                                           Peak Value
            This figure is the system voltage, and            This figure is 2x the RMS value and is used
            is the phase to phase value that the             to theoretically simulate some of the 'in rush
            cable/switchgear is subjected to                 currents that are associated at the point of
                                                             energisation.


                                                                                                            Nominal voltage
                                                                                                    This figure takes is the nominal
                                                    11000 x 1.414 x 2.55 x 1.1                      voltage based on 10% more than
                                                      √3                                            the system voltage (11 KV)


                                      Root 3                                         Transient Voltage                                     Additional notes (For new cables)
                  This figure is used to establish the voltage in           This figure takes into consideration            1 - Insulation resistance test results should be greater than 10
                  any individual 'phase                                    the transient voltage at the peak of           gig ohms when testing each individual core to earth as well as
                  Value = 1.732                                            the sinewave                                   phase to phase testing.
                                                                                                                          2 - Insulation resistance tests that are less than 10 gig Ohms will
                                                                                                                          result in further inspection of the cable installation for any
                                                                                                                          possible causes.
                 11000 x 1.414 x 2.55 x 1.1                                                                               3 - If there is a large variation in core test results when carrying
                                                                                                                          out insulation resistance tests then further investigation will be
                 1.732                                                                                                    required.



                 6351 x 1.414 x 2.55 x 1.1


                                                                          Test value = 25 KV
                           25185 volts
                                                                           (Per Phase - DC Test)
3.3.2 - HV Pressure Testing Theory (18 KV)




            Cable test theory                                                                                                            Additional notes (For new cables)
            Due to the nature of the installation it is deemed that the cable under test is an 'old' cable              1 - Insulation resistance test results should be greater than 10
            because it would have been subjected to factory tests. The test value used in this instance is a            gig ohms when testing each individual core to earth as well as
            value that takes this into consideration as well as the fact that there will be certain impulse             phase to phase testing.
            values which can be 2 or 3 times the Peak value. Each phase of the cable will be tested                     2 - Insulation resistance tests that are less than 10 gig Ohms will
            individually with the other phases earthed for a duration of 1 min. This test will be a DC Test.            result in further inspection of the cable installation for any
                                                                                                                        possible causes.
                                                                                                                        3 - If there is a large variation in core test results when carrying
                                                                                                                        out insulation resistance tests then further investigation will be
                                                                                Peak Value
                       System Voltage                                                                                   required.
                                                             This figure is 2x the RMS value and is used
            This figure is the system voltage, and
                                                             to theoretically simulate some of the 'in rush
            is the phase to phase value that the
                                                             currents that are associated at the point of
            cable/switchgear is subjected to
                                                             energisation.




                                                     11000 x 1.414 x 2
                                                       √3
                                                                                         Peak multiple factor
                                         Root 3                                  This figure takes into consideration
                     This figure is used to establish the voltage in              the peak value which can be 2 or 3 x
                     any individual 'phase                                       the peak value when the cable is
                     Value = 1.732                                               energised



                     11000
                           x 1.414 x 2
                     1.732

                                                                      Test value = 18 KV
                       6351 x 1.414 x 2
                                                                       (Per Phase - DC Test)

                          17960 volts
3.4.1 - Transformer No.1 Testing
3.4.2 - Transformer No.2 Testing
4 - Recommendations
The following items listed below are recommended future works that we feel are necessary to ensure the system resilience for the current and future power
demands the Data centre will be subjected to:

1 - Full HV/LV Protection Study:

It is recommended that a full Protection study including the current and future HV equipment is carried out so that the data centre can run with the maximum
level of safety.

2 - Thermal imaging of new and existing infrastructure:

Thermal imaging will help gauge an understanding of the system performance with respect to system efficiencies and help identify equipment which emit
excessive heat which equate to power losses.

3 - Detailed Power Supply Audit (HV &LV):

APA Ltd can conduct a detailed power audit which differs from the conventional approach in that:

   a) We will identify the losses within the system using multiple approaches.

   b) We will identify how the problems (if any) came into existence.

   c) We will accurately determine what the costs of the inefficiencies are with respect to money.

   d) Provide realistic tangible solutions for the client starting with looking at ways to re-managing the existing power infrastructure.

4 - Asset Maintenance:

We recommend that a planned maintenance program is constructed with respect to the HV supply and Heavy current LV equipment which can be factored in at
the most convenient times suitable to the client.
Advanced Power Analytics Limited
Installation Services:
     HV & LV Cable Jointing up to 33 KV
     HV & LV Construction Up to 33 KV
	    Protection Testing / Grading Surveys 	
     Full HV and LV Commissioning

Maintenance & Analysis (Online & Offline)
	    	
	    HV & LV Maintenance Up to 132 KV
	    Power Quality Analysis / Power Auditing
	    Thermal Imaging	 	
	    Ultrasonic Testing
	    Partial Discharge Testing	


Additional Services:
	        Technical Consultancy	
	        Technical Media Development
	        Asset Management	
	        Project Management	         	     	
	        Training (On site and system specific)




                                                 No.8 Bank Apartments, Marlow, Buckinghamshire, United Kingdom SL7 3DX
                                                                                               Mobile - +44 7515 384458
                                                                                       email - theronrichardson@live.com
Onyx Group   Hv Test Report

More Related Content

What's hot

Original N-CHANNEL Mosfet FQPF10N60 10N60 10A 600V TO-220F New Fairchild
Original N-CHANNEL Mosfet FQPF10N60 10N60 10A 600V TO-220F New FairchildOriginal N-CHANNEL Mosfet FQPF10N60 10N60 10A 600V TO-220F New Fairchild
Original N-CHANNEL Mosfet FQPF10N60 10N60 10A 600V TO-220F New FairchildAUTHELECTRONIC
 
Original Mosfet 4N90C FQP4N90C FQP4N90 900V 4A TO-220 New
Original Mosfet 4N90C FQP4N90C FQP4N90 900V 4A TO-220 NewOriginal Mosfet 4N90C FQP4N90C FQP4N90 900V 4A TO-220 New
Original Mosfet 4N90C FQP4N90C FQP4N90 900V 4A TO-220 NewAUTHELECTRONIC
 
Chapter 5 mukesh gurjar
Chapter 5 mukesh gurjarChapter 5 mukesh gurjar
Chapter 5 mukesh gurjarMukesh gurjar
 
Differential Amplifiers in Bioimpedance Measurement Systems: A Comparison Bas...
Differential Amplifiers in Bioimpedance Measurement Systems: A Comparison Bas...Differential Amplifiers in Bioimpedance Measurement Systems: A Comparison Bas...
Differential Amplifiers in Bioimpedance Measurement Systems: A Comparison Bas...IDES Editor
 
Mitsubishi - substation insulation coordination studies-sparacino
Mitsubishi - substation insulation coordination studies-sparacinoMitsubishi - substation insulation coordination studies-sparacino
Mitsubishi - substation insulation coordination studies-sparacinoGilberto Mejía
 
Original N-Channel Mosfet FQPF2N60C 2N60C 2N60 20A 600V TO-220F New
Original N-Channel Mosfet FQPF2N60C 2N60C 2N60 20A 600V TO-220F NewOriginal N-Channel Mosfet FQPF2N60C 2N60C 2N60 20A 600V TO-220F New
Original N-Channel Mosfet FQPF2N60C 2N60C 2N60 20A 600V TO-220F NewAUTHELECTRONIC
 
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...Thorne & Derrick International
 
A Low Phase Noise CMOS Quadrature Voltage Control Oscillator Using Clock Gate...
A Low Phase Noise CMOS Quadrature Voltage Control Oscillator Using Clock Gate...A Low Phase Noise CMOS Quadrature Voltage Control Oscillator Using Clock Gate...
A Low Phase Noise CMOS Quadrature Voltage Control Oscillator Using Clock Gate...IJERA Editor
 
ECNG 3015 - Overcurrent Protection
ECNG 3015 - Overcurrent ProtectionECNG 3015 - Overcurrent Protection
ECNG 3015 - Overcurrent ProtectionChandrabhan Sharma
 
Fat procedure for lv switchboards
Fat procedure for lv switchboardsFat procedure for lv switchboards
Fat procedure for lv switchboardskhongai
 
Original N-Channel Mosfet FQPF5N50C 5N50C 500V 3A TO-220F New Fairchild
Original N-Channel Mosfet FQPF5N50C 5N50C 500V 3A TO-220F New FairchildOriginal N-Channel Mosfet FQPF5N50C 5N50C 500V 3A TO-220F New Fairchild
Original N-Channel Mosfet FQPF5N50C 5N50C 500V 3A TO-220F New FairchildAUTHELECTRONIC
 
Design and Implementation of Two Stage Operational Amplifier
Design and Implementation of Two Stage Operational AmplifierDesign and Implementation of Two Stage Operational Amplifier
Design and Implementation of Two Stage Operational AmplifierIRJET Journal
 
Original N-Channel Mosfet FQP8N60C 8N60C 8N60 600V 7.5A TO-220F New
Original N-Channel Mosfet FQP8N60C 8N60C 8N60 600V 7.5A TO-220F NewOriginal N-Channel Mosfet FQP8N60C 8N60C 8N60 600V 7.5A TO-220F New
Original N-Channel Mosfet FQP8N60C 8N60C 8N60 600V 7.5A TO-220F NewAUTHELECTRONIC
 
6654882 presentation-on-insulation-co ordination
6654882 presentation-on-insulation-co ordination6654882 presentation-on-insulation-co ordination
6654882 presentation-on-insulation-co ordinationRui Zhang
 

What's hot (18)

Original N-CHANNEL Mosfet FQPF10N60 10N60 10A 600V TO-220F New Fairchild
Original N-CHANNEL Mosfet FQPF10N60 10N60 10A 600V TO-220F New FairchildOriginal N-CHANNEL Mosfet FQPF10N60 10N60 10A 600V TO-220F New Fairchild
Original N-CHANNEL Mosfet FQPF10N60 10N60 10A 600V TO-220F New Fairchild
 
68
6868
68
 
Original Mosfet 4N90C FQP4N90C FQP4N90 900V 4A TO-220 New
Original Mosfet 4N90C FQP4N90C FQP4N90 900V 4A TO-220 NewOriginal Mosfet 4N90C FQP4N90C FQP4N90 900V 4A TO-220 New
Original Mosfet 4N90C FQP4N90C FQP4N90 900V 4A TO-220 New
 
Testing
TestingTesting
Testing
 
Chapter 5 mukesh gurjar
Chapter 5 mukesh gurjarChapter 5 mukesh gurjar
Chapter 5 mukesh gurjar
 
Differential Amplifiers in Bioimpedance Measurement Systems: A Comparison Bas...
Differential Amplifiers in Bioimpedance Measurement Systems: A Comparison Bas...Differential Amplifiers in Bioimpedance Measurement Systems: A Comparison Bas...
Differential Amplifiers in Bioimpedance Measurement Systems: A Comparison Bas...
 
Mitsubishi - substation insulation coordination studies-sparacino
Mitsubishi - substation insulation coordination studies-sparacinoMitsubishi - substation insulation coordination studies-sparacino
Mitsubishi - substation insulation coordination studies-sparacino
 
Lm6171
Lm6171Lm6171
Lm6171
 
Original N-Channel Mosfet FQPF2N60C 2N60C 2N60 20A 600V TO-220F New
Original N-Channel Mosfet FQPF2N60C 2N60C 2N60 20A 600V TO-220F NewOriginal N-Channel Mosfet FQPF2N60C 2N60C 2N60 20A 600V TO-220F New
Original N-Channel Mosfet FQPF2N60C 2N60C 2N60 20A 600V TO-220F New
 
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...
Sheath Fault Location On Power Cables - Sheath Testing, Sheath Fault Location...
 
A Low Phase Noise CMOS Quadrature Voltage Control Oscillator Using Clock Gate...
A Low Phase Noise CMOS Quadrature Voltage Control Oscillator Using Clock Gate...A Low Phase Noise CMOS Quadrature Voltage Control Oscillator Using Clock Gate...
A Low Phase Noise CMOS Quadrature Voltage Control Oscillator Using Clock Gate...
 
Lecture08
Lecture08Lecture08
Lecture08
 
ECNG 3015 - Overcurrent Protection
ECNG 3015 - Overcurrent ProtectionECNG 3015 - Overcurrent Protection
ECNG 3015 - Overcurrent Protection
 
Fat procedure for lv switchboards
Fat procedure for lv switchboardsFat procedure for lv switchboards
Fat procedure for lv switchboards
 
Original N-Channel Mosfet FQPF5N50C 5N50C 500V 3A TO-220F New Fairchild
Original N-Channel Mosfet FQPF5N50C 5N50C 500V 3A TO-220F New FairchildOriginal N-Channel Mosfet FQPF5N50C 5N50C 500V 3A TO-220F New Fairchild
Original N-Channel Mosfet FQPF5N50C 5N50C 500V 3A TO-220F New Fairchild
 
Design and Implementation of Two Stage Operational Amplifier
Design and Implementation of Two Stage Operational AmplifierDesign and Implementation of Two Stage Operational Amplifier
Design and Implementation of Two Stage Operational Amplifier
 
Original N-Channel Mosfet FQP8N60C 8N60C 8N60 600V 7.5A TO-220F New
Original N-Channel Mosfet FQP8N60C 8N60C 8N60 600V 7.5A TO-220F NewOriginal N-Channel Mosfet FQP8N60C 8N60C 8N60 600V 7.5A TO-220F New
Original N-Channel Mosfet FQP8N60C 8N60C 8N60 600V 7.5A TO-220F New
 
6654882 presentation-on-insulation-co ordination
6654882 presentation-on-insulation-co ordination6654882 presentation-on-insulation-co ordination
6654882 presentation-on-insulation-co ordination
 

Similar to Onyx Group Hv Test Report

Distribution Transformer testing, West Bengal, India
Distribution Transformer testing,  West Bengal, IndiaDistribution Transformer testing,  West Bengal, India
Distribution Transformer testing, West Bengal, IndiaRajuMondal18
 
Testing of transformer.pptx
Testing of transformer.pptxTesting of transformer.pptx
Testing of transformer.pptxNoorulAmin67
 
Introduction of transfromer
Introduction of transfromerIntroduction of transfromer
Introduction of transfromerpretty gurna
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformervikasgupta1965
 
Isolator and bushing
Isolator and bushingIsolator and bushing
Isolator and bushingNovia Putri
 
Testing of Transformers.
Testing of Transformers.Testing of Transformers.
Testing of Transformers.Geetesh Verma
 
Testing of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalTesting of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalNihal Shiroya
 
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuitsModule 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuitsAsha Anu Kurian
 
Presentation OutDoorSwithGear(AIS) .pptx
Presentation OutDoorSwithGear(AIS) .pptxPresentation OutDoorSwithGear(AIS) .pptx
Presentation OutDoorSwithGear(AIS) .pptxRAJKIRANR3
 
Electrical disturbances from conduction and coupling.pptx
Electrical disturbances from conduction and coupling.pptxElectrical disturbances from conduction and coupling.pptx
Electrical disturbances from conduction and coupling.pptxPritishPachhapure1
 
The value of power factor testing
The value of power factor testingThe value of power factor testing
The value of power factor testingAbi finni
 
REPORT -VALLUR THERMAL POWER PLANT
REPORT -VALLUR THERMAL POWER PLANTREPORT -VALLUR THERMAL POWER PLANT
REPORT -VALLUR THERMAL POWER PLANTRAJPRASAD RS
 
Quality control (training course)
Quality control (training course)Quality control (training course)
Quality control (training course)fikireyesus
 

Similar to Onyx Group Hv Test Report (20)

Distribution Transformer testing, West Bengal, India
Distribution Transformer testing,  West Bengal, IndiaDistribution Transformer testing,  West Bengal, India
Distribution Transformer testing, West Bengal, India
 
Testing of transformer.pptx
Testing of transformer.pptxTesting of transformer.pptx
Testing of transformer.pptx
 
Module 6part1
Module 6part1Module 6part1
Module 6part1
 
Introduction of transfromer
Introduction of transfromerIntroduction of transfromer
Introduction of transfromer
 
High potential test
High potential testHigh potential test
High potential test
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
Isolator and bushing
Isolator and bushingIsolator and bushing
Isolator and bushing
 
Electrical testing
Electrical testingElectrical testing
Electrical testing
 
Testing of Transformers.
Testing of Transformers.Testing of Transformers.
Testing of Transformers.
 
Testing of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihalTesting of c.b.(hk & hr) nihal
Testing of c.b.(hk & hr) nihal
 
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuitsModule 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
Module 2 ee369 KTU syllabus-high voltage ac generation,resonant circuits
 
tcee-161003100321.pptx
tcee-161003100321.pptxtcee-161003100321.pptx
tcee-161003100321.pptx
 
16950
1695016950
16950
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
Presentation OutDoorSwithGear(AIS) .pptx
Presentation OutDoorSwithGear(AIS) .pptxPresentation OutDoorSwithGear(AIS) .pptx
Presentation OutDoorSwithGear(AIS) .pptx
 
Electrical disturbances from conduction and coupling.pptx
Electrical disturbances from conduction and coupling.pptxElectrical disturbances from conduction and coupling.pptx
Electrical disturbances from conduction and coupling.pptx
 
The value of power factor testing
The value of power factor testingThe value of power factor testing
The value of power factor testing
 
Wapda Engineering Acadmy Report
Wapda Engineering Acadmy ReportWapda Engineering Acadmy Report
Wapda Engineering Acadmy Report
 
REPORT -VALLUR THERMAL POWER PLANT
REPORT -VALLUR THERMAL POWER PLANTREPORT -VALLUR THERMAL POWER PLANT
REPORT -VALLUR THERMAL POWER PLANT
 
Quality control (training course)
Quality control (training course)Quality control (training course)
Quality control (training course)
 

Onyx Group Hv Test Report

  • 1. ADVANCED POWER ANALYTICS LIMITED Onyx Group - HV installation Test Report Client - Onyx Document Prepared by - Ron Richardson (On behalf of Keysource) Document Date - 02/05/2012
  • 2. Table Of Contents ! ! 1.0 - Installation Report Overview 3 2.0 - Testing Operation Schedule 6-7 3.0 - HV Testing 3.1 - HV Terminations 3.1.1 - HV Feed to TX1 9 3.1.2 - HV Feed to TX2 10 3.1.3 - Scottish Power Incomer Number 1 11 3.1.4 - Scottish Power Incomer Number 2 12 3.2 - HV Switchboard 3.2.1 - HV Pressure testing of Busbars & Switchgear 13 3.2.2 - Ductor Testing of HV Busbars 14 3.3 - HV Pressure Testing theory 3.3.1 - Pressure testing @ 25KV 15 3.3.2 - Pressure testing @ 18KV 16 3.4 - Transformer Testing 3.4.1 - Transformer No.1 17 3.4.2 - Transformer No.2 18 4.0 - Recommendations 20
  • 3. 1 - HV Report Overview
  • 4. The following report has been produced to help give clear indication of the testing procedures and the respective results of the tests that were necessary for the successful implementation of the new HV Substation which has been installed at the Onyx Group data centre (Edinburgh) Switchgear & Transformer Testing: Due to the existing configuration (RMU ‘close-coupled’ to the Transformer) in order to carry out the testing of the Transformer it would be necessary to disconnect the ‘new’ previously installed HV termination at the RMU and then use the switching ‘on’ positions to test through the switches onto the HV windings of the Transformer. The HV test voltage values and durations would then have to be considered to ensure no possibility of ‘Over-stressing the HV Equipment. Functional Switching Checks were also carried out to confirm Switching operation reliability. Secondary protection tests were also carried out to check that the Switchgear would operate under fault conditions as well as Insulation resistance checks for the Current Transformers Method Statements and Risk assessments were constructed prior to the work commencing highlighting the Process and Immediate risk(s) in connection with the tasks. The equipment tested was subjected to the following electrical tests consisting of : 1 - Pre and post Insulation resistance testing @ 5KV 2 - Uni-polar HV Testing @ 18 - 25KV (for 1 min & 15min durations) 3 - Secondary Injections Currents (0 - 20 amps) for Trip Testing Simulations 4 - Ductor testing Currents (50 & 100 amps) for testing the HV Busbars *Important Notes - 1 - Any recorded values lower than 75 Mega Ohms for Transformer tests will need to be reported to the manufacturer prior to any Energization activity as this may representative of a potential Failure. 2 - Any HV Cables tests with Insulation resistance values lower than 500 Mega Ohms prior to Energization will be subject to further investigation works as this may again be representative of imminent or possible near future Failure.
  • 5. 2 - Testing Operation Sheets
  • 6.
  • 7.
  • 8. 3 - HV Testing (Switchgear & Cables)
  • 9. 3.1.1 - HV Cable feed to TX1
  • 10. 3.1.2 - HV Cable feed to TX2
  • 11. 3.1.3 - Scottish Power Incomer No.1
  • 12. 3.1.4 - Scottish Power Incomer No.2
  • 13. 3.2.1 - HV Busbar Testing (Insulation Resistance & Pressure Testing)
  • 14. 3.2.2 - HV Busbar Testing (Ductor Testing)
  • 15. 3.3.1 - HV Pressure Testing Theory (25 KV) System Voltage Peak Value This figure is the system voltage, and This figure is 2x the RMS value and is used is the phase to phase value that the to theoretically simulate some of the 'in rush cable/switchgear is subjected to currents that are associated at the point of energisation. Nominal voltage This figure takes is the nominal 11000 x 1.414 x 2.55 x 1.1 voltage based on 10% more than √3 the system voltage (11 KV) Root 3 Transient Voltage Additional notes (For new cables) This figure is used to establish the voltage in This figure takes into consideration 1 - Insulation resistance test results should be greater than 10 any individual 'phase the transient voltage at the peak of gig ohms when testing each individual core to earth as well as Value = 1.732 the sinewave phase to phase testing. 2 - Insulation resistance tests that are less than 10 gig Ohms will result in further inspection of the cable installation for any possible causes. 11000 x 1.414 x 2.55 x 1.1 3 - If there is a large variation in core test results when carrying out insulation resistance tests then further investigation will be 1.732 required. 6351 x 1.414 x 2.55 x 1.1 Test value = 25 KV 25185 volts (Per Phase - DC Test)
  • 16. 3.3.2 - HV Pressure Testing Theory (18 KV) Cable test theory Additional notes (For new cables) Due to the nature of the installation it is deemed that the cable under test is an 'old' cable 1 - Insulation resistance test results should be greater than 10 because it would have been subjected to factory tests. The test value used in this instance is a gig ohms when testing each individual core to earth as well as value that takes this into consideration as well as the fact that there will be certain impulse phase to phase testing. values which can be 2 or 3 times the Peak value. Each phase of the cable will be tested 2 - Insulation resistance tests that are less than 10 gig Ohms will individually with the other phases earthed for a duration of 1 min. This test will be a DC Test. result in further inspection of the cable installation for any possible causes. 3 - If there is a large variation in core test results when carrying out insulation resistance tests then further investigation will be Peak Value System Voltage required. This figure is 2x the RMS value and is used This figure is the system voltage, and to theoretically simulate some of the 'in rush is the phase to phase value that the currents that are associated at the point of cable/switchgear is subjected to energisation. 11000 x 1.414 x 2 √3 Peak multiple factor Root 3 This figure takes into consideration This figure is used to establish the voltage in the peak value which can be 2 or 3 x any individual 'phase the peak value when the cable is Value = 1.732 energised 11000 x 1.414 x 2 1.732 Test value = 18 KV 6351 x 1.414 x 2 (Per Phase - DC Test) 17960 volts
  • 17. 3.4.1 - Transformer No.1 Testing
  • 18. 3.4.2 - Transformer No.2 Testing
  • 20. The following items listed below are recommended future works that we feel are necessary to ensure the system resilience for the current and future power demands the Data centre will be subjected to: 1 - Full HV/LV Protection Study: It is recommended that a full Protection study including the current and future HV equipment is carried out so that the data centre can run with the maximum level of safety. 2 - Thermal imaging of new and existing infrastructure: Thermal imaging will help gauge an understanding of the system performance with respect to system efficiencies and help identify equipment which emit excessive heat which equate to power losses. 3 - Detailed Power Supply Audit (HV &LV): APA Ltd can conduct a detailed power audit which differs from the conventional approach in that: a) We will identify the losses within the system using multiple approaches. b) We will identify how the problems (if any) came into existence. c) We will accurately determine what the costs of the inefficiencies are with respect to money. d) Provide realistic tangible solutions for the client starting with looking at ways to re-managing the existing power infrastructure. 4 - Asset Maintenance: We recommend that a planned maintenance program is constructed with respect to the HV supply and Heavy current LV equipment which can be factored in at the most convenient times suitable to the client.
  • 21. Advanced Power Analytics Limited Installation Services: HV & LV Cable Jointing up to 33 KV HV & LV Construction Up to 33 KV Protection Testing / Grading Surveys Full HV and LV Commissioning Maintenance & Analysis (Online & Offline) HV & LV Maintenance Up to 132 KV Power Quality Analysis / Power Auditing Thermal Imaging Ultrasonic Testing Partial Discharge Testing Additional Services: Technical Consultancy Technical Media Development Asset Management Project Management Training (On site and system specific) No.8 Bank Apartments, Marlow, Buckinghamshire, United Kingdom SL7 3DX Mobile - +44 7515 384458 email - theronrichardson@live.com