SlideShare a Scribd company logo
1 of 8
A Not-for-Profit Medical
Research Center
Project Team 1
Sumit Dhavale
Kevin Conroy
Bassam Basheer
Adnan Nazir
MRC Part 2 Project Contents:
 Updated List of activities
 Responsibility Matrix
 Network diagram
 Activity durations
 Earliest/latest start/finish times
 Critical path
MRC Part 3 Project contents:
 Resource Requirements Table
 Table Includes:
- Name of the responsible person
- Activity responsible for
- Working Days for the activity
- Time period for the activity
MRC Part: 2 and 3
Project contents:
 Cost of each Activity
 Total Budgeted cost for the project
 Budgeted cost by period table
 Cumulative budgeted cost by period
MRC Part: 4
MRC Part: 5 Responsibility Matrix
Risk No. Risk Impact Likelihood of
Occurrence
Degree of Impact Action on Trigger Responsibility Response Plan
1
Bad weather on photo shoot days at
hospitals, clinics, or long-term care
facilities
Delay of photo
availibility or no
photos of subject
facility
Medium Low
Check forecast
two days before
scheduled dates
Lakysha
Plan for alternate
indoor shoot
locations at each
facility
2
Vendor delay in printing annual
report
Reports not
available for mailing
on time
Medium High
Vendor equipment
malfunctions or
volume higher
than vendor
accustomed to
delivering
Levi
Add significant
penalties to the
contract for failure to
deliver on time
3
Board requires changes to the
presented plan
Having to modify the
plan would take time
and potentially delay
the entire project
Low High
Board member
personal
preferences that
do not align with
the proposed plan
Alexis
Add resources to
address required
changes as
necessary
4 Full project budget not approved
Make budget cuts
Low Medium
Money not
available to fund
project as planned
Alexis
Get quotes for
various levels of
quality in the printing
(paper type, color vs.
black and white, etc)
and for various
methods of
distribution (first
class mail vs. bulk)
5 Travel delays/cancellations
Delay in getting to
facilities for photo
shoots and client
interviews
Low Low
Check weather
forecast and flight
status
Lakysha
Schedule earlier than
necessary flights to
accommodate
potential airline
delays
6
Lack of client consent for
testimonies
Fewer/no client
testimonies
available for report
Low Low
Clients opt not to
share their stories
Alexis
Use what is available
or leave out client
testimonies entirely
MRC Risk Assessment Matrix
MRC Part: 6
Project contents:
- Actual Cost by Period (sample)
Activity TBC June July August September October (budgeted) November (budgeted)
Annual Report and
Presentation
$ -
Schedule $ 195 235$
Define Major Milestones $ 312 173$
Financial Information
availability Date
$ -
Distribution Date $ -
Budget $ 936 975$
Photography Cost $ 2,186 2,186$
Client Testimony Cost $ 2,186 2,186$
Annual Report Cost $ 1,927 2,045$
Design Cost $ 1,972 1,972$
Printing Cost $ 201,073 201,050$
Distribution Cost $ 50,894 50,894$
Actual Cost by Period for MRC as of September 30
Month
MRC Part: 6 Continued
Cumulative Budgeted and Actual Costs (CBC, CAC) and Earned Value
(CEV):
MRC Part: 6 Continued
Project contents
 In our project, the Cumulated Earned Value (CEV) equals the Cumulative Actual Value
(CAV), as 100% of each activity was completed within the month it was planned
 The Cost Performance Index (CPI), then, is also 100% (1.0), as $1 of earned value was
realized for every $1 expended to-date, and the Cost Variance (CV) is $0.0 as well
 The Forecasted Cost at Completion (FCAC) of the project with a CPI of 1.0 remains at the
total budgeted cost (TBC) of $687,900
Project Team 1
THANK YOU!
Sumit Dhavale
Kevin Conroy
Bassam Basheer
Adnan Nazir

More Related Content

Similar to Team 1 mrc part 6

Dollars and Rands: Budget Planning Pre- and Post-award
Dollars and Rands: Budget Planning Pre- and Post-awardDollars and Rands: Budget Planning Pre- and Post-award
Dollars and Rands: Budget Planning Pre- and Post-awardHopkinsCFAR
 
MS Project 2010 schedule template for large NASA procurements $10-450 million
MS Project 2010 schedule template for large NASA procurements $10-450 millionMS Project 2010 schedule template for large NASA procurements $10-450 million
MS Project 2010 schedule template for large NASA procurements $10-450 millionSelf employed
 
HIM360 Assignment RubricsAssignment 1 Project Scope and
HIM360 Assignment RubricsAssignment 1 Project Scope and HIM360 Assignment RubricsAssignment 1 Project Scope and
HIM360 Assignment RubricsAssignment 1 Project Scope and SusanaFurman449
 
Project Status Update
Project Status UpdateProject Status Update
Project Status UpdateArifRaihan25
 
Software Project Management: Budget
Software Project Management: BudgetSoftware Project Management: Budget
Software Project Management: BudgetMinhas Kamal
 
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docxRUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docxtoltonkendal
 
CIL: Project planning and infrastructure with notes
CIL: Project planning and infrastructure with notesCIL: Project planning and infrastructure with notes
CIL: Project planning and infrastructure with notesPAS_Team
 
Project Charter - Outreach Events for the Company
Project Charter - Outreach Events for the CompanyProject Charter - Outreach Events for the Company
Project Charter - Outreach Events for the CompanyTimothy Cochran
 
Graded application of project management req
Graded application of project management reqGraded application of project management req
Graded application of project management reqGlen Alleman
 
Mmi entrepreneurship 6
Mmi entrepreneurship 6Mmi entrepreneurship 6
Mmi entrepreneurship 6gatecomro
 
Project Governance Model Powerpoint Presentation Slides
Project Governance Model Powerpoint Presentation SlidesProject Governance Model Powerpoint Presentation Slides
Project Governance Model Powerpoint Presentation SlidesSlideTeam
 
Coursework 5 - IS Project Management Final
Coursework 5 - IS Project Management FinalCoursework 5 - IS Project Management Final
Coursework 5 - IS Project Management FinalTimothy Adrian Lam
 
Project Governance Model PowerPoint Presentation Slides
Project Governance Model PowerPoint Presentation Slides Project Governance Model PowerPoint Presentation Slides
Project Governance Model PowerPoint Presentation Slides SlideTeam
 
USAF 694 Arss Drone
USAF 694 Arss DroneUSAF 694 Arss Drone
USAF 694 Arss Dronetkjohns1
 
Proposed project plan template
Proposed project plan templateProposed project plan template
Proposed project plan templateMichelle Joja
 
Project-Scope-Statement
Project-Scope-StatementProject-Scope-Statement
Project-Scope-StatementJeremy Heady
 
Development project appraisal and sd(L6)1
Development project appraisal and sd(L6)1Development project appraisal and sd(L6)1
Development project appraisal and sd(L6)1Farha Sharmin
 

Similar to Team 1 mrc part 6 (20)

Dollars and Rands: Budget Planning Pre- and Post-award
Dollars and Rands: Budget Planning Pre- and Post-awardDollars and Rands: Budget Planning Pre- and Post-award
Dollars and Rands: Budget Planning Pre- and Post-award
 
MS Project 2010 schedule template for large NASA procurements $10-450 million
MS Project 2010 schedule template for large NASA procurements $10-450 millionMS Project 2010 schedule template for large NASA procurements $10-450 million
MS Project 2010 schedule template for large NASA procurements $10-450 million
 
HIM360 Assignment RubricsAssignment 1 Project Scope and
HIM360 Assignment RubricsAssignment 1 Project Scope and HIM360 Assignment RubricsAssignment 1 Project Scope and
HIM360 Assignment RubricsAssignment 1 Project Scope and
 
Project Status Update
Project Status UpdateProject Status Update
Project Status Update
 
Software Project Management: Budget
Software Project Management: BudgetSoftware Project Management: Budget
Software Project Management: Budget
 
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docxRUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
 
CIL: Project planning and infrastructure with notes
CIL: Project planning and infrastructure with notesCIL: Project planning and infrastructure with notes
CIL: Project planning and infrastructure with notes
 
Project Charter - Outreach Events for the Company
Project Charter - Outreach Events for the CompanyProject Charter - Outreach Events for the Company
Project Charter - Outreach Events for the Company
 
Graded application of project management req
Graded application of project management reqGraded application of project management req
Graded application of project management req
 
Mmi entrepreneurship 6
Mmi entrepreneurship 6Mmi entrepreneurship 6
Mmi entrepreneurship 6
 
Project Governance Model Powerpoint Presentation Slides
Project Governance Model Powerpoint Presentation SlidesProject Governance Model Powerpoint Presentation Slides
Project Governance Model Powerpoint Presentation Slides
 
Coursework 5 - IS Project Management Final
Coursework 5 - IS Project Management FinalCoursework 5 - IS Project Management Final
Coursework 5 - IS Project Management Final
 
Turning your project around
Turning your project aroundTurning your project around
Turning your project around
 
Project Governance Model PowerPoint Presentation Slides
Project Governance Model PowerPoint Presentation Slides Project Governance Model PowerPoint Presentation Slides
Project Governance Model PowerPoint Presentation Slides
 
Kathryn barbe abc inc.
Kathryn barbe  abc inc.Kathryn barbe  abc inc.
Kathryn barbe abc inc.
 
USAF 694 Arss Drone
USAF 694 Arss DroneUSAF 694 Arss Drone
USAF 694 Arss Drone
 
Proposed project plan template
Proposed project plan templateProposed project plan template
Proposed project plan template
 
Symons
SymonsSymons
Symons
 
Project-Scope-Statement
Project-Scope-StatementProject-Scope-Statement
Project-Scope-Statement
 
Development project appraisal and sd(L6)1
Development project appraisal and sd(L6)1Development project appraisal and sd(L6)1
Development project appraisal and sd(L6)1
 

Recently uploaded

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 

Recently uploaded (20)

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 

Team 1 mrc part 6

  • 1. A Not-for-Profit Medical Research Center Project Team 1 Sumit Dhavale Kevin Conroy Bassam Basheer Adnan Nazir
  • 2. MRC Part 2 Project Contents:  Updated List of activities  Responsibility Matrix  Network diagram  Activity durations  Earliest/latest start/finish times  Critical path MRC Part 3 Project contents:  Resource Requirements Table  Table Includes: - Name of the responsible person - Activity responsible for - Working Days for the activity - Time period for the activity MRC Part: 2 and 3
  • 3. Project contents:  Cost of each Activity  Total Budgeted cost for the project  Budgeted cost by period table  Cumulative budgeted cost by period MRC Part: 4
  • 4. MRC Part: 5 Responsibility Matrix Risk No. Risk Impact Likelihood of Occurrence Degree of Impact Action on Trigger Responsibility Response Plan 1 Bad weather on photo shoot days at hospitals, clinics, or long-term care facilities Delay of photo availibility or no photos of subject facility Medium Low Check forecast two days before scheduled dates Lakysha Plan for alternate indoor shoot locations at each facility 2 Vendor delay in printing annual report Reports not available for mailing on time Medium High Vendor equipment malfunctions or volume higher than vendor accustomed to delivering Levi Add significant penalties to the contract for failure to deliver on time 3 Board requires changes to the presented plan Having to modify the plan would take time and potentially delay the entire project Low High Board member personal preferences that do not align with the proposed plan Alexis Add resources to address required changes as necessary 4 Full project budget not approved Make budget cuts Low Medium Money not available to fund project as planned Alexis Get quotes for various levels of quality in the printing (paper type, color vs. black and white, etc) and for various methods of distribution (first class mail vs. bulk) 5 Travel delays/cancellations Delay in getting to facilities for photo shoots and client interviews Low Low Check weather forecast and flight status Lakysha Schedule earlier than necessary flights to accommodate potential airline delays 6 Lack of client consent for testimonies Fewer/no client testimonies available for report Low Low Clients opt not to share their stories Alexis Use what is available or leave out client testimonies entirely MRC Risk Assessment Matrix
  • 5. MRC Part: 6 Project contents: - Actual Cost by Period (sample) Activity TBC June July August September October (budgeted) November (budgeted) Annual Report and Presentation $ - Schedule $ 195 235$ Define Major Milestones $ 312 173$ Financial Information availability Date $ - Distribution Date $ - Budget $ 936 975$ Photography Cost $ 2,186 2,186$ Client Testimony Cost $ 2,186 2,186$ Annual Report Cost $ 1,927 2,045$ Design Cost $ 1,972 1,972$ Printing Cost $ 201,073 201,050$ Distribution Cost $ 50,894 50,894$ Actual Cost by Period for MRC as of September 30 Month
  • 6. MRC Part: 6 Continued Cumulative Budgeted and Actual Costs (CBC, CAC) and Earned Value (CEV):
  • 7. MRC Part: 6 Continued Project contents  In our project, the Cumulated Earned Value (CEV) equals the Cumulative Actual Value (CAV), as 100% of each activity was completed within the month it was planned  The Cost Performance Index (CPI), then, is also 100% (1.0), as $1 of earned value was realized for every $1 expended to-date, and the Cost Variance (CV) is $0.0 as well  The Forecasted Cost at Completion (FCAC) of the project with a CPI of 1.0 remains at the total budgeted cost (TBC) of $687,900
  • 8. Project Team 1 THANK YOU! Sumit Dhavale Kevin Conroy Bassam Basheer Adnan Nazir