Lean Manufacture Systems Approach To Identify & 
Reducing Waste on Metal Casting SMEs 
Sulung rahmawan wira ghani 
Universitas Pesantren Tinggi Darul Ulum 
Summary 
All kind of wastes which happen in small and medium enterprises (SME) are something that must be eliminated to reach effective and efficient business process. Waiting waste in small and medium enterprises (SME) business process is kind of waste which is always faced in production operation process of aluminum casting company. Feeling of having high waiting waste makes this progressive SME must do improvement in business performance process. 
To reduce waiting waste which happens in business process of this SME used Lean Manufacturing approach. Steps which have to be done to reduce waste waiting consists of describing condition of system by using Big Picture Mapping, identifying the most significant waste by using VALSAT, pie diagram, searching the cause of critical waste by using RCA and FMEA, and the last step is determining the best alternative to reduce waste waiting with analyzing the highest risk score of RPN. 
The result which is obtained shows that in production process has high waiting waste. Percentage of VA is 26% and NVA is 74%. This indicates that still many activities don’t add use value in production process of SME. To solve that waste is proposed to use alternative improvement of production activities, giving label on tools and utilization management of production process tools. Those are proposed which are adjusted with problem in business process of SME. 
Key words: SME, VALSAT, waste, VA, NVA, RCA, FMEA, RPN

More Related Content

Viewers also liked

Viewers also liked (12)

Ilmu alamiah dasar bab1
Ilmu alamiah dasar bab1Ilmu alamiah dasar bab1
Ilmu alamiah dasar bab1
 
Pengantar teknik industri, modul 1
Pengantar teknik industri,  modul 1Pengantar teknik industri,  modul 1
Pengantar teknik industri, modul 1
 
Pengantar teknik industri, modul 3
Pengantar teknik industri,  modul 3Pengantar teknik industri,  modul 3
Pengantar teknik industri, modul 3
 
Pti01 pengantar
Pti01 pengantarPti01 pengantar
Pti01 pengantar
 
Pengantar teknik industri, modul 2
Pengantar teknik industri,  modul 2 Pengantar teknik industri,  modul 2
Pengantar teknik industri, modul 2
 
rancangan antropometri kajian teknik industri unhasy
rancangan antropometri kajian teknik industri unhasyrancangan antropometri kajian teknik industri unhasy
rancangan antropometri kajian teknik industri unhasy
 
Jurnal peracangan dan pengembangan produk pigura putar dengan menggunakan met...
Jurnal peracangan dan pengembangan produk pigura putar dengan menggunakan met...Jurnal peracangan dan pengembangan produk pigura putar dengan menggunakan met...
Jurnal peracangan dan pengembangan produk pigura putar dengan menggunakan met...
 
Pengantar teknik industri modul 4
Pengantar teknik industri modul 4Pengantar teknik industri modul 4
Pengantar teknik industri modul 4
 
Aps07 design erd_normalization
Aps07 design erd_normalizationAps07 design erd_normalization
Aps07 design erd_normalization
 
Lean Manufacturing
Lean ManufacturingLean Manufacturing
Lean Manufacturing
 
Lean Manufacturing PowerPoint Presentation Sample
Lean Manufacturing PowerPoint Presentation SampleLean Manufacturing PowerPoint Presentation Sample
Lean Manufacturing PowerPoint Presentation Sample
 
Lean presentation ppt
Lean presentation pptLean presentation ppt
Lean presentation ppt
 

Similar to Lean manufacturing in sme

Evaluating and improving business process
Evaluating and improving business processEvaluating and improving business process
Evaluating and improving business process
dutconsult
 
Introduction To Operational Excellence
Introduction To Operational ExcellenceIntroduction To Operational Excellence
Introduction To Operational Excellence
Ahmed Mansour
 
Lean Six Sigma for Jewellery
Lean Six Sigma for JewelleryLean Six Sigma for Jewellery
Lean Six Sigma for Jewellery
Prem Anand
 
IE7610_REPORT_GROUP_8
IE7610_REPORT_GROUP_8IE7610_REPORT_GROUP_8
IE7610_REPORT_GROUP_8
Parag Kapile
 

Similar to Lean manufacturing in sme (20)

Thesis narulita, riri suci juli 2011-trisakti university jakarta
Thesis narulita, riri suci  juli 2011-trisakti university jakartaThesis narulita, riri suci  juli 2011-trisakti university jakarta
Thesis narulita, riri suci juli 2011-trisakti university jakarta
 
Thesis narulita, riri suci juli 2011-trisakti university jakarta
Thesis narulita, riri suci  juli 2011-trisakti university jakartaThesis narulita, riri suci  juli 2011-trisakti university jakarta
Thesis narulita, riri suci juli 2011-trisakti university jakarta
 
Lean manufacturing
Lean manufacturingLean manufacturing
Lean manufacturing
 
The Cost Crisis
The Cost CrisisThe Cost Crisis
The Cost Crisis
 
Lean Six Sigma - Introduction
Lean Six Sigma - IntroductionLean Six Sigma - Introduction
Lean Six Sigma - Introduction
 
Utilize Lean Manufacturing Consulting for Delivering Value to the Customers
Utilize Lean Manufacturing Consulting for Delivering Value to the CustomersUtilize Lean Manufacturing Consulting for Delivering Value to the Customers
Utilize Lean Manufacturing Consulting for Delivering Value to the Customers
 
The Evolving Landscape of Semiconductor Manufacturing to Mitigate Yield Losse...
The Evolving Landscape of Semiconductor Manufacturing to Mitigate Yield Losse...The Evolving Landscape of Semiconductor Manufacturing to Mitigate Yield Losse...
The Evolving Landscape of Semiconductor Manufacturing to Mitigate Yield Losse...
 
Arrelic Services | APM
Arrelic Services | APMArrelic Services | APM
Arrelic Services | APM
 
Evaluating and improving business process
Evaluating and improving business processEvaluating and improving business process
Evaluating and improving business process
 
Introduction To Operational Excellence
Introduction To Operational ExcellenceIntroduction To Operational Excellence
Introduction To Operational Excellence
 
IRJET- Implementing Lean Manufacturing Principle in Fabrication Process- A...
IRJET- 	  Implementing Lean Manufacturing Principle in Fabrication Process- A...IRJET- 	  Implementing Lean Manufacturing Principle in Fabrication Process- A...
IRJET- Implementing Lean Manufacturing Principle in Fabrication Process- A...
 
Lean Six Sigma and Procurement
Lean Six Sigma and ProcurementLean Six Sigma and Procurement
Lean Six Sigma and Procurement
 
Basic overview six sigma
Basic overview six sigmaBasic overview six sigma
Basic overview six sigma
 
Six Sigma Implementation to reduce rejection rate of Pump Casings at local Ma...
Six Sigma Implementation to reduce rejection rate of Pump Casings at local Ma...Six Sigma Implementation to reduce rejection rate of Pump Casings at local Ma...
Six Sigma Implementation to reduce rejection rate of Pump Casings at local Ma...
 
Lean six sigma
Lean six sigmaLean six sigma
Lean six sigma
 
Business process innovation for entrepreneurs
Business process innovation for entrepreneursBusiness process innovation for entrepreneurs
Business process innovation for entrepreneurs
 
Final presentation (1)
Final presentation (1)Final presentation (1)
Final presentation (1)
 
Lean Six Sigma for Jewellery
Lean Six Sigma for JewelleryLean Six Sigma for Jewellery
Lean Six Sigma for Jewellery
 
The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)
 
IE7610_REPORT_GROUP_8
IE7610_REPORT_GROUP_8IE7610_REPORT_GROUP_8
IE7610_REPORT_GROUP_8
 

Recently uploaded

Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
dharasingh5698
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 

Recently uploaded (20)

University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
 
Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 

Lean manufacturing in sme

  • 1. Lean Manufacture Systems Approach To Identify & Reducing Waste on Metal Casting SMEs Sulung rahmawan wira ghani Universitas Pesantren Tinggi Darul Ulum Summary All kind of wastes which happen in small and medium enterprises (SME) are something that must be eliminated to reach effective and efficient business process. Waiting waste in small and medium enterprises (SME) business process is kind of waste which is always faced in production operation process of aluminum casting company. Feeling of having high waiting waste makes this progressive SME must do improvement in business performance process. To reduce waiting waste which happens in business process of this SME used Lean Manufacturing approach. Steps which have to be done to reduce waste waiting consists of describing condition of system by using Big Picture Mapping, identifying the most significant waste by using VALSAT, pie diagram, searching the cause of critical waste by using RCA and FMEA, and the last step is determining the best alternative to reduce waste waiting with analyzing the highest risk score of RPN. The result which is obtained shows that in production process has high waiting waste. Percentage of VA is 26% and NVA is 74%. This indicates that still many activities don’t add use value in production process of SME. To solve that waste is proposed to use alternative improvement of production activities, giving label on tools and utilization management of production process tools. Those are proposed which are adjusted with problem in business process of SME. Key words: SME, VALSAT, waste, VA, NVA, RCA, FMEA, RPN