Schedule - A
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-
731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
1
SCHEDULE-A
(See Clause 10.1)
Site of the PROJECT
1 THE SITE
1.1 Site of the Project Highway shall include the land, buildings, structures and road works as
described in Annex-I of this Schedule-A.
1.2 An inventory of the Site including the land, buildings, structures, road works, trees and any other
immovable property on, or attach to, the Site shall be prepared jointly by the Authority
Representative and the Concessionaire, and such inventory shall form part of the memorandum
referred to in Clause 10.3.1 of the Agreement.
1.3 Additional land required for Toll Plazas, Bus Bays/Shelter, Traffic Aid Posts, Medical Aid Posts and
vehicle rescue posts or for construction of works specified in the Change of Scope Order issued
under Clause 16.2.3 of this Agreement shall be acquired in accordance with the provisions of
Clause 10.3.6 of this Agreement. Upon acquisition, such land shall form part of the Site and vest
in the Authority.
Schedule - A
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-
731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
2
Annex – I
(Schedule-A)
Site for Four Laning
1 Site
The proposed Greenfield alignment commencing from Autarpur Village at km 35.000 in
Pratapgarh District in the State of Uttar Pradesh and ends near Singraur Uparhar Village of
Prayagraj District section NH-731A in the State of Uttar Pradesh at km 49.155.
The start and end chainage coordinates of the package are given below:
Sr. No Easting Northing Remarks
1 562654.556 E 2843498.4942 N Start of Project Road
2 564048.9068 E 2830892.3342 N End of Project Road
The land, carriageway and structures comprising the Site are described below.
The Index Map / location plan of the project highway is given at Appendix A-I of
Schedule-A.
2 Land
The site of the project highway comprises the land (existing right of way) as described below:
Sr. No
Proposed Chainage (km)
Right of Way(m) Remarks
From To
1 35.000 49.155 NIL Greenfield Alignment
3 Carriageway
This Project envisages construction of a 4-lane green field highway with paved shoulder.
4 Major Bridges-
The site includes the following major bridges:
Sr.
No
Existing
Chainage
(km)
Type of Structure No. of Spans
with span
length (m)
Width
(m)
Foundation
Sub-
structure
Super-
structure
NIL
5 Road over-bridges (ROB)/ Road under-bridges (RUB)
The site includes the following ROB (road over railway line)/RUB (road under railway line):
Sr.
No
Existing
Chainage
(km)
Type of Structure No. of Spans
with span
length (m)
Width
(m)
Foundation
Sub-
structure
Super-
structure
NIL
Railway Line / Level Crossings
The Site includes the following Railway Line / Level Crossing:
Schedule - A
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-
731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
3
Sr. No Location (Chainage, km) Remarks
1 43.560 Railway Crossing
6 Grade Separators
The site includes the following Grade Separators:
Sr. No
Existing
Chainage (km)
Type of Structure No. of Spans with span
length (m)
Width(m)
Foundation Superstructure
NIL
7 Minor Bridges
The Site includes the following Minor Bridges:
Sr.
No
Existing
Chainage
(km)
Type of Structure
No. of Spans with
span length (m)
Width
(m)
Foundation
Sub-
structure
Super-
structure
NIL
8 Cross Drainage Structures / Culverts - NIL
The Site includes the following culverts:
Sr.
No
Existing Chainage
(km)
Type of
Culvert
Span/Opening with
span length (m)
Formation Width
(m)
NIL
9 Total Number of Structures
The total number of structures on the site is indicated below:
(a) No. of Major Bridges –NIL
(b) No. of Railway Over Bridges –NIL
(c) No. of Grade Separators –NIL
(d) No. of Minor Bridges –NIL
(e) No. of Culverts – NIL
10 Bus Shelters and Truck lay-byes
10.1 Bus Shelters
The location of existing bus shelters are given below:
Sr. No
Existing Chainage
(km)
Length(m)
Left Hand
Side
Right Hand
Side
NIL
10.2 Truck Lay-byes
The location of existing truck lay byes are given below:
Sr. No Existing Chainage (km) Length(m)
Left Hand
Side
Right Hand
Side
NIL
Schedule - A
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-
731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
4
11 Cross Roads
The details of crossroads are as follows:
Major Cross Road:
Sr. No
Location At
grade
Separated
Category of Cross Road
From km to km NH SH MDR Others
1 47.290
NH-24B/New
NH30
2 48.685
NH-2/New
NH 19
Minor Cross Road:
Sr. No Chainage (Km) Junction Cross Road
1 36+230 + BT
2 37+570 + BT
3 42+070 + BT
4 42+740 + BT
5 44+045 + BT
6 49+125 + BT
12 Permanent Bridge, Bye Pass or Tunnel costing Rs. 50 crore or more
The project is a green field project hence there is no existing structures. The new structures shall
be constructed as per Schedules.
Schedule - A
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid
Annuity Mode (Package – II)
5
13 Details of Existing Utilities
(i) Electrical utilities
The site includes the following electrical utilities: -
Design Chainage (Km)
11KV electrical poles
in nos.
Light Poles in Nos.
132 KV HT
Electric Line
Crossing the
Road
220 KV HT
Electric Line
Crossing the
Road
400 KV HT
Electric Line
Crossing
the Road
800 KV HT
Electric Line
Crossing the
Road
Transformer in nos.
From To LHS RHS LHS RHS LHS RHS
Total 8 14 0 1 1 0 0 0 0 0
35+000 35+500 - - - - - -
35+500 36+000 - - - - - -
36+000 36+500 - - - - - -
36+500 37+000 - - - - - -
37+000 37+500 - - - - - -
37+500 38+000 - - - - - -
38+000 38+500 - - - - - -
38+500 39+000 - - - - - -
39+000 39+500 - - - - - -
39+500 40+000 1 1 - - - -
40+000 40+500 - 1 - - 1 - -
40+500 41+000 - - - - - -
41+000 41+500 - - - - - -
41+500 42+000 - - - - - -
42+000 42+500 - - - - - -
42+500 43+000 - - - - - -
43+000 43+500 - - - - - -
43+500 44+000 1 - - - - -
44+000 44+500 - - - - - -
44+500 45+000 - - - - - -
45+000 45+500 - - - - - -
45+500 46+000 - - - - - -
Schedule - A
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid
Annuity Mode (Package – II)
6
Design Chainage (Km)
11KV electrical poles
in nos.
Light Poles in Nos.
132 KV HT
Electric Line
Crossing the
Road
220 KV HT
Electric Line
Crossing the
Road
400 KV HT
Electric Line
Crossing
the Road
800 KV HT
Electric Line
Crossing the
Road
Transformer in nos.
From To LHS RHS LHS RHS LHS RHS
Total 8 14 0 1 1 0 0 0 0 0
46+000 46+500 - - - - - -
46+500 47+000 - 2 1 - -
47+000 47+500 2 2 - - - -
47+500 48+000 1 3 - - - -
48+000 48+500 - - - - - -
48+500 49+000 3 5 - - - -
49+000 49+155 - - - - - -
(ii) Public Health utilities (Water/Sewage Pipelines) *
The site includes the following Public Health utilities: -
Design Chainage (Km)
Bore Well with Pump
(Nos.)
Tube well/Handpump
(Nos.)
Water Pipe
Line (Nos.)
Well (Nos.)
Water Tank/Over Head
Tank (Nos.)
From To LHS RHS LHS RHS LHS RHS LHS RHS
Total 0 0 0 0 0 0 0 0 0
35+000 35+500 - - - - - - - - -
35+500 36+000 - - - - - - - - -
36+000 36+500 - - - - - - - - -
36+500 37+000 - - - - - - - - -
37+000 37+500 - - - - - - - - -
37+500 38+000 - - - - - - - - -
38+000 38+500 - - - - - - - - -
38+500 39+000 - - - - - - - - -
39+000 39+500 - - - - - - - - -
39+500 40+000 - - - - - - - - -
40+000 40+500 - - - - - - - - -
Schedule - A
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid
Annuity Mode (Package – II)
7
Design Chainage (Km)
Bore Well with Pump
(Nos.)
Tube well/Handpump
(Nos.)
Water Pipe
Line (Nos.)
Well (Nos.)
Water Tank/Over Head
Tank (Nos.)
From To LHS RHS LHS RHS LHS RHS LHS RHS
Total 0 0 0 0 0 0 0 0 0
40+500 41+000 - - - - - - - - -
41+000 41+500 - - - - - - - - -
41+500 42+000 - - - - - - - - -
42+000 42+500 - - - - - - - - -
42+500 43+000 - - - - - - - - -
43+000 43+500 - - - - - - - - -
43+500 44+000 - - - - - - - - -
44+000 44+500 - - - - - - - - -
44+500 45+000 - - - - - - - - -
45+000 45+500 - - - - - - - - -
45+500 46+000 - - - - - - - - -
46+000 46+500 - - - - - - - - -
46+500 47+000 - - - - - - - - -
47+000 47+500 - - - - - - - - -
47+500 48+000 - - - - - - - - -
48+000 48+500 - - - - - - - - -
48+500 49+000 - - - - - - - - -
49+000 49+155 - - - - - - - - -
Schedule - A
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid
Annuity Mode (Package – II)
8
Appendix A-I
(Schedule-A)
INDEX MAP / LOCATION MAP OF PROJECT HIGHWAY
Schedule - A
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
9
Appendix A-II
(Schedule-A)
PROJECT CENTER LINE COORDINATES
The proposed Greenfield alignment commencing from Autarpur Village at km 35.000 in Pratapgarh
District in the State of Uttar Pradesh and ends near Singraur Uparhar village of Prayagraj District section
NH-731A in the State of Uttar Pradesh at km 49.155.
Coordinate System - Universal Transverse Mercator (UTM)-WGS84 (Zone 44R)
Sr. No
Design
Chainage
(km)
Easting Northing
1 35000 562654.6 2843498
2 35020 562639.7 2843485
3 35040 562625 2843472
4 35060 562610.5 2843458
5 35080 562596.7 2843443
6 35100 562583.5 2843428
7 35120 562571.2 2843413
8 35140 562559.8 2843396
9 35160 562549.3 2843379
10 35180 562539.8 2843361
11 35200 562531.3 2843343
12 35220 562523.7 2843325
13 35240 562517.3 2843306
14 35260 562511.9 2843287
15 35280 562507.5 2843267
16 35300 562504.3 2843247
17 35320 562502.1 2843228
18 35340 562500.8 2843208
19 35360 562500.1 2843188
20 35380 562499.7 2843168
21 35400 562499.4 2843148
22 35420 562499.1 2843128
23 35440 562498.8 2843108
24 35460 562498.5 2843088
25 35480 562498.2 2843068
26 35500 562497.8 2843048
27 35520 562497.5 2843028
28 35540 562497.2 2843008
29 35560 562496.9 2842988
30 35580 562496.6 2842968
31 35600 562496.2 2842948
32 35620 562495.9 2842928
Sr. No
Design
Chainage
(km)
Easting Northing
33 35640 562495.6 2842908
34 35660 562495.3 2842888
35 35680 562495 2842868
36 35700 562494.7 2842848
37 35720 562494.3 2842828
38 35740 562494 2842808
39 35760 562493.7 2842788
40 35780 562493.4 2842768
41 35800 562493.1 2842748
42 35820 562492.7 2842728
43 35840 562492.4 2842708
44 35860 562492.1 2842688
45 35880 562491.8 2842668
46 35900 562491.5 2842648
47 35920 562491.1 2842628
48 35940 562490.8 2842608
49 35960 562490.5 2842588
50 35980 562490.2 2842568
51 36000 562489.9 2842548
52 36020 562489.6 2842528
53 36060 562488.9 2842488
54 36080 562488.6 2842468
55 36100 562488.3 2842448
56 36120 562488 2842428
57 36140 562487.7 2842408
58 36160 562487.7 2842388
59 36180 562488.1 2842368
60 36200 562489 2842348
61 36220 562490.6 2842328
62 36240 562492.8 2842308
63 36260 562495.7 2842288
64 36280 562499.3 2842268
Schedule - A
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
10
Sr. No
Design
Chainage
(km)
Easting Northing
65 36300 562503.5 2842249
66 36320 562508.3 2842229
67 36340 562513.4 2842210
68 36360 562518.8 2842191
69 36380 562524.2 2842172
70 36400 562529.7 2842152
71 36420 562535.1 2842133
72 36440 562540.6 2842114
73 36460 562546 2842095
74 36480 562551.4 2842075
75 36500 562556.9 2842056
76 36520 562562.3 2842037
77 36540 562567.7 2842018
78 36560 562573.2 2841998
79 36580 562578.6 2841979
80 36600 562584.1 2841960
81 36620 562589.5 2841941
82 36640 562594.9 2841921
83 36660 562600.4 2841902
84 36680 562605.8 2841883
85 36700 562611.2 2841864
86 36720 562616.7 2841844
87 36740 562622.1 2841825
88 36760 562627.6 2841806
89 36780 562633 2841787
90 36800 562638.4 2841767
91 36820 562643.9 2841748
92 36840 562649.3 2841729
93 36860 562654.8 2841710
94 36880 562660.2 2841690
95 36900 562665.6 2841671
96 36920 562671.1 2841652
97 36940 562676.5 2841633
98 36960 562681.9 2841613
99 36980 562687.4 2841594
100 37000 562692.8 2841575
101 37020 562698.3 2841556
102 37040 562703.7 2841536
103 37060 562709.1 2841517
104 37080 562714.6 2841498
Sr. No
Design
Chainage
(km)
Easting Northing
105 37100 562720 2841479
106 37120 562725.4 2841460
107 37140 562730.9 2841440
108 37160 562736.3 2841421
109 37180 562741.8 2841402
110 37200 562747.2 2841383
111 37220 562752.6 2841363
112 37240 562758.1 2841344
113 37260 562763.5 2841325
114 37280 562769 2841306
115 37300 562774.4 2841286
116 37320 562779.8 2841267
117 37340 562785.3 2841248
118 37360 562790.6 2841229
119 37380 562795.6 2841209
120 37400 562800.1 2841190
121 37420 562804.1 2841170
122 37440 562807.4 2841150
123 37460 562810 2841131
124 37480 562812 2841111
125 37500 562813.4 2841091
126 37520 562814.2 2841071
127 37540 562814.8 2841051
128 37560 562815.1 2841031
129 37580 562815.5 2841011
130 37600 562815.9 2840991
131 37620 562816.2 2840971
132 37640 562816.6 2840951
133 37660 562816.9 2840931
134 37680 562817.3 2840911
135 37700 562817.7 2840891
136 37720 562818 2840871
137 37740 562818.4 2840851
138 37760 562818.7 2840831
139 37780 562819.1 2840811
140 37800 562819.5 2840791
141 37820 562819.8 2840771
142 37840 562820.2 2840751
143 37860 562820.5 2840731
144 37880 562820.9 2840711
Schedule - A
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
11
Sr. No
Design
Chainage
(km)
Easting Northing
145 37900 562821.2 2840691
146 37920 562821.6 2840671
147 37940 562822 2840651
148 37960 562822.3 2840631
149 37980 562822.7 2840611
150 38000 562823 2840591
151 38020 562823.4 2840571
152 38040 562823.8 2840551
153 38060 562824.1 2840531
154 38080 562824.5 2840511
155 38100 562824.8 2840491
156 38120 562825.2 2840471
157 38140 562825.6 2840451
158 38160 562825.9 2840431
159 38180 562826.3 2840411
160 38200 562826.6 2840391
161 38220 562827 2840371
162 38240 562827.4 2840351
163 38260 562827.7 2840331
164 38280 562828.1 2840311
165 38300 562828.4 2840291
166 38320 562828.8 2840271
167 38340 562829.1 2840251
168 38360 562829.5 2840231
169 38380 562829.9 2840211
170 38400 562830.2 2840191
171 38420 562830.6 2840171
172 38440 562830.9 2840151
173 38460 562831.3 2840131
174 38480 562831.7 2840111
175 38500 562832 2840091
176 38520 562832.4 2840071
177 38540 562832.7 2840051
178 38560 562833.1 2840031
179 38580 562833.5 2840011
180 38600 562833.8 2839991
181 38620 562834.2 2839971
182 38640 562834.5 2839951
183 38660 562834.9 2839931
184 38680 562835.3 2839911
Sr. No
Design
Chainage
(km)
Easting Northing
185 38700 562835.6 2839891
186 38720 562836 2839871
187 38740 562836.3 2839851
188 38760 562836.7 2839831
189 38780 562837 2839811
190 38800 562837.4 2839791
191 38820 562837.8 2839771
192 38840 562838.1 2839751
193 38860 562838.5 2839731
194 38880 562838.8 2839711
195 38900 562839.2 2839691
196 38920 562839.6 2839671
197 38940 562839.9 2839651
198 38960 562840.3 2839631
199 38980 562840.6 2839611
200 39000 562841 2839591
201 39020 562841.4 2839571
202 39040 562841.7 2839551
203 39060 562842.1 2839531
204 39080 562842.4 2839511
205 39100 562842.8 2839491
206 39120 562843.1 2839471
207 39140 562843.5 2839451
208 39160 562843.9 2839431
209 39180 562844.3 2839411
210 39200 562844.8 2839391
211 39220 562845.8 2839371
212 39240 562847.2 2839351
213 39260 562849.3 2839331
214 39280 562852.1 2839311
215 39300 562855.5 2839292
216 39320 562859.5 2839272
217 39340 562864.2 2839253
218 39360 562869.5 2839233
219 39380 562875.3 2839214
220 39400 562881.4 2839195
221 39420 562887.6 2839176
222 39440 562893.8 2839157
223 39460 562900 2839138
224 39480 562906.2 2839119
Schedule - A
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
12
Sr. No
Design
Chainage
(km)
Easting Northing
225 39500 562912.4 2839100
226 39520 562918.6 2839081
227 39540 562924.8 2839062
228 39560 562931 2839043
229 39580 562937.2 2839024
230 39600 562943.4 2839005
231 39620 562949.6 2838986
232 39640 562955.8 2838967
233 39660 562962 2838948
234 39680 562968.2 2838929
235 39700 562974.4 2838910
236 39720 562980.6 2838891
237 39740 562986.8 2838872
238 39760 562993 2838853
239 39780 562999.2 2838834
240 39800 563005.4 2838815
241 39820 563011.6 2838796
242 39840 563017.8 2838777
243 39860 563024 2838758
244 39880 563030.2 2838739
245 39900 563036.6 2838720
246 39920 563043.2 2838701
247 39940 563050.3 2838682
248 39960 563057.9 2838664
249 39980 563066.2 2838646
250 40000 563075.1 2838628
251 40020 563084.5 2838610
252 40040 563094.6 2838593
253 40060 563105.2 2838576
254 40080 563116.4 2838559
255 40100 563128.1 2838543
256 40120 563140.3 2838527
257 40140 563153.1 2838512
258 40160 563166.4 2838497
259 40180 563180.1 2838482
260 40200 563194.4 2838468
261 40220 563209.1 2838455
262 40240 563224 2838441
263 40260 563239.2 2838428
264 40280 563254.4 2838415
Sr. No
Design
Chainage
(km)
Easting Northing
265 40300 563269.6 2838402
266 40320 563284.9 2838389
267 40340 563300.1 2838377
268 40360 563315.3 2838364
269 40380 563330.6 2838351
270 40400 563345.8 2838338
271 40420 563361 2838325
272 40440 563376.3 2838312
273 40460 563391.5 2838299
274 40480 563406.7 2838286
275 40500 563422 2838273
276 40520 563437.2 2838260
277 40540 563452.4 2838247
278 40560 563467.7 2838234
279 40580 563482.9 2838221
280 40600 563498.1 2838208
281 40620 563513.4 2838195
282 40640 563528.6 2838182
283 40660 563543.8 2838169
284 40680 563559.1 2838156
285 40700 563574.3 2838143
286 40720 563589.5 2838130
287 40740 563604.8 2838117
288 40760 563620 2838104
289 40780 563635.2 2838091
290 40800 563650.5 2838078
291 40820 563665.7 2838065
292 40840 563680.9 2838053
293 40860 563696.2 2838040
294 40880 563711.4 2838027
295 40900 563726.6 2838014
296 40920 563741.9 2838001
297 40940 563757.1 2837988
298 40960 563772.3 2837975
299 40980 563787.6 2837962
300 41000 563802.8 2837949
301 41020 563818 2837936
302 41040 563833.3 2837923
303 41060 563848.5 2837910
304 41080 563863.7 2837897
Schedule - A
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
13
Sr. No
Design
Chainage
(km)
Easting Northing
305 41100 563879 2837884
306 41120 563894.2 2837871
307 41140 563909.4 2837858
308 41160 563924.7 2837845
309 41180 563939.9 2837832
310 41200 563955.1 2837819
311 41220 563970.4 2837806
312 41240 563985.6 2837793
313 41260 564000.8 2837780
314 41280 564016.1 2837767
315 41300 564031.3 2837754
316 41320 564046.5 2837741
317 41340 564061.4 2837728
318 41360 564076.2 2837715
319 41380 564090.7 2837701
320 41400 564105.1 2837687
321 41420 564119.1 2837673
322 41440 564133 2837658
323 41460 564146.6 2837644
324 41480 564159.9 2837629
325 41500 564173 2837614
326 41520 564185.8 2837598
327 41540 564198.4 2837583
328 41560 564210.7 2837567
329 41580 564222.8 2837551
330 41600 564234.6 2837535
331 41620 564246.1 2837519
332 41640 564257.4 2837502
333 41660 564268.3 2837485
334 41680 564279 2837468
335 41700 564289.4 2837451
336 41720 564299.5 2837434
337 41740 564309.4 2837417
338 41760 564318.9 2837399
339 41780 564328.2 2837381
340 41800 564337.1 2837363
341 41820 564345.8 2837345
342 41840 564354.1 2837327
343 41860 564362.2 2837309
344 41880 564369.9 2837290
Sr. No
Design
Chainage
(km)
Easting Northing
345 41900 564377.3 2837272
346 41920 564384.4 2837253
347 41940 564391.2 2837234
348 41960 564397.7 2837215
349 41980 564403.9 2837196
350 42000 564409.8 2837177
351 42020 564415.3 2837158
352 42040 564420.5 2837139
353 42060 564425.4 2837119
354 42080 564430 2837100
355 42100 564434.2 2837080
356 42120 564438.1 2837061
357 42140 564441.7 2837041
358 42160 564445 2837021
359 42180 564447.9 2837002
360 42200 564450.5 2836982
361 42220 564452.8 2836962
362 42240 564454.8 2836942
363 42260 564456.4 2836922
364 42280 564457.6 2836902
365 42300 564458.6 2836882
366 42320 564459.2 2836862
367 42340 564459.5 2836842
368 42360 564459.4 2836822
369 42380 564459 2836802
370 42400 564458.3 2836782
371 42420 564457.3 2836762
372 42440 564455.9 2836742
373 42460 564454.1 2836722
374 42480 564452.1 2836702
375 42500 564449.7 2836683
376 42520 564447 2836663
377 42540 564444 2836643
378 42560 564440.6 2836623
379 42580 564437.1 2836604
380 42600 564433.5 2836584
381 42620 564429.9 2836564
382 42640 564426.3 2836545
383 42660 564422.7 2836525
384 42680 564419.1 2836505
Schedule - A
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
14
Sr. No
Design
Chainage
(km)
Easting Northing
385 42700 564415.6 2836486
386 42720 564412 2836466
387 42740 564408.4 2836446
388 42760 564404.8 2836426
389 42780 564401.2 2836407
390 42800 564397.6 2836387
391 42820 564394.1 2836367
392 42840 564390.5 2836348
393 42860 564386.9 2836328
394 42880 564383.3 2836308
395 42900 564379.7 2836289
396 42920 564376.1 2836269
397 42940 564372.6 2836249
398 42960 564369 2836230
399 42980 564365.4 2836210
400 43000 564361.8 2836190
401 43020 564358.2 2836171
402 43040 564354.6 2836151
403 43060 564351.1 2836131
404 43080 564347.5 2836112
405 43100 564343.9 2836092
406 43120 564340.3 2836072
407 43140 564336.7 2836053
408 43160 564333.1 2836033
409 43180 564329.6 2836013
410 43200 564326 2835994
411 43220 564322.4 2835974
412 43240 564318.8 2835954
413 43260 564315.2 2835935
414 43280 564311.6 2835915
415 43300 564308.1 2835895
416 43320 564304.5 2835876
417 43340 564300.9 2835856
418 43360 564297.3 2835836
419 43380 564293.7 2835817
420 43400 564290.1 2835797
421 43420 564286.6 2835777
422 43440 564283 2835757
423 43460 564279.4 2835738
424 43480 564275.8 2835718
Sr. No
Design
Chainage
(km)
Easting Northing
425 43500 564272.2 2835698
426 43520 564268.6 2835679
427 43540 564265.1 2835659
428 43560 564261.5 2835639
429 43580 564257.9 2835620
430 36060 562488.9 2842488
431 43600 564254.3 2835600
432 43620 564250.7 2835580
433 43640 564247.1 2835561
434 43660 564243.6 2835541
435 43680 564240 2835521
436 43700 564236.4 2835502
437 43720 564232.8 2835482
438 43740 564229.2 2835462
439 43760 564225.6 2835443
440 43780 564222.1 2835423
441 43800 564218.5 2835403
442 43820 564214.9 2835384
443 43840 564211.3 2835364
444 43860 564207.7 2835344
445 43880 564204.2 2835325
446 43900 564200.6 2835305
447 43920 564197 2835285
448 43940 564193.4 2835266
449 43960 564189.8 2835246
450 43980 564186.2 2835226
451 44000 564182.7 2835207
452 44020 564179.1 2835187
453 44040 564175.5 2835167
454 44060 564171.9 2835148
455 44080 564168.3 2835128
456 44100 564164.7 2835108
457 44120 564161.2 2835088
458 44140 564157.6 2835069
459 44160 564154 2835049
460 44180 564150.4 2835029
461 44200 564146.9 2835010
462 44220 564143.5 2834990
463 44240 564140.4 2834970
464 44260 564137.7 2834950
Schedule - A
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
15
Sr. No
Design
Chainage
(km)
Easting Northing
465 44280 564135.4 2834931
466 44300 564133.5 2834911
467 44320 564132.1 2834891
468 44340 564131 2834871
469 44360 564130.3 2834851
470 44380 564130 2834831
471 44400 564130.1 2834811
472 44420 564130.6 2834791
473 44440 564131.6 2834771
474 44460 564132.9 2834751
475 44480 564134.6 2834731
476 44500 564136.7 2834711
477 44520 564139.2 2834691
478 44540 564142.1 2834671
479 44560 564145.4 2834652
480 44580 564149.1 2834632
481 44600 564153.2 2834612
482 44620 564157.7 2834593
483 44640 564162.5 2834574
484 44660 564167.8 2834554
485 44680 564173.4 2834535
486 44700 564179.4 2834516
487 44720 564185.8 2834497
488 44740 564192.6 2834478
489 44760 564199.8 2834460
490 44780 564207.3 2834441
491 44800 564215.2 2834423
492 44820 564223.4 2834404
493 44840 564232.1 2834386
494 44860 564241 2834369
495 44880 564250.4 2834351
496 44900 564260.1 2834333
497 44920 564270.1 2834316
498 44940 564280.5 2834299
499 44960 564291.2 2834282
500 44980 564302.3 2834265
501 45000 564313.6 2834249
502 45020 564325.4 2834233
503 45040 564337.4 2834217
504 45060 564349.7 2834201
Sr. No
Design
Chainage
(km)
Easting Northing
505 45080 564362.4 2834186
506 45100 564375.4 2834170
507 45120 564388.7 2834155
508 45140 564402.2 2834141
509 45160 564416.1 2834126
510 45180 564430.2 2834112
511 45200 564444.7 2834098
512 45220 564459.4 2834085
513 45240 564474.3 2834071
514 45260 564489.6 2834059
515 45280 564505.1 2834046
516 45300 564520.8 2834033
517 45320 564536.6 2834021
518 45340 564552.5 2834009
519 45360 564568.4 2833997
520 45380 564584.3 2833985
521 45400 564600.2 2833973
522 45420 564616 2833961
523 45440 564631.9 2833948
524 45460 564647.8 2833936
525 45480 564663.7 2833924
526 45500 564679.6 2833912
527 45520 564695.5 2833900
528 45540 564711.4 2833888
529 45560 564727.3 2833876
530 45580 564743.2 2833863
531 45600 564759 2833851
532 45620 564774.9 2833839
533 45640 564790.8 2833827
534 45660 564806.7 2833815
535 45680 564822.6 2833803
536 45700 564838.5 2833790
537 45720 564854.4 2833778
538 45740 564870.3 2833766
539 45760 564886.1 2833754
540 45780 564902 2833742
541 45800 564917.9 2833730
542 45820 564933.8 2833718
543 45840 564949.7 2833705
544 45860 564965.6 2833693
Schedule - A
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
16
Sr. No
Design
Chainage
(km)
Easting Northing
545 45880 564981.5 2833681
546 45900 564997.3 2833669
547 45920 565013.1 2833657
548 45940 565028.7 2833644
549 45960 565044 2833631
550 45980 565059 2833618
551 46000 565073.7 2833604
552 46020 565087.9 2833590
553 46040 565101.9 2833576
554 46060 565115.5 2833561
555 46080 565128.7 2833546
556 46100 565141.5 2833531
557 46120 565153.9 2833515
558 46140 565166 2833499
559 46160 565177.6 2833483
560 46180 565188.9 2833467
561 46200 565199.7 2833450
562 46220 565210.1 2833433
563 46240 565220 2833415
564 46260 565229.6 2833398
565 46280 565238.6 2833380
566 46300 565247.3 2833362
567 46320 565255.4 2833344
568 46340 565263.2 2833325
569 46360 565270.4 2833307
570 46380 565277.2 2833288
571 46400 565283.5 2833269
572 46420 565289.4 2833250
573 46440 565294.7 2833230
574 46460 565299.6 2833211
575 46480 565304 2833192
576 46500 565307.9 2833172
577 46520 565311.3 2833152
578 46540 565314.2 2833132
579 46560 565316.6 2833113
580 46580 565318.6 2833093
581 46600 565320 2833073
582 46620 565320.9 2833053
583 46640 565321.3 2833033
584 46660 565321.3 2833013
Sr. No
Design
Chainage
(km)
Easting Northing
585 46680 565320.7 2832993
586 46700 565319.6 2832973
587 46720 565318.1 2832953
588 46740 565316 2832933
589 46760 565313.4 2832913
590 46780 565310.4 2832893
591 46800 565306.8 2832874
592 46820 565302.8 2832854
593 46840 565298.2 2832835
594 46860 565293.2 2832815
595 46880 565287.7 2832796
596 46900 565281.7 2832777
597 46920 565275.3 2832758
598 46940 565268.3 2832739
599 46960 565260.9 2832721
600 46980 565253.1 2832702
601 47000 565244.8 2832684
602 47020 565236 2832666
603 47040 565226.8 2832648
604 47060 565217.1 2832631
605 47080 565207.1 2832614
606 47100 565196.6 2832597
607 47120 565185.8 2832580
608 47140 565174.9 2832563
609 47160 565163.9 2832546
610 47180 565153 2832529
611 47200 565142.1 2832513
612 47220 565131.1 2832496
613 47240 565120.2 2832479
614 47260 565109.3 2832462
615 47280 565098.3 2832446
616 47300 565087.4 2832429
617 47320 565076.5 2832412
618 47340 565065.5 2832395
619 47360 565054.6 2832379
620 47380 565043.6 2832362
621 47400 565032.7 2832345
622 47420 565021.8 2832328
623 47440 565010.8 2832312
624 47460 564999.9 2832295
Schedule - A
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
17
Sr. No
Design
Chainage
(km)
Easting Northing
625 47480 564989 2832278
626 47500 564978 2832261
627 47520 564967.1 2832245
628 47540 564956.2 2832228
629 47560 564945.2 2832211
630 47580 564934.3 2832195
631 47600 564923.3 2832178
632 47620 564912.4 2832161
633 47640 564901.5 2832144
634 47660 564890.5 2832128
635 47680 564879.6 2832111
636 47700 564868.7 2832094
637 47720 564857.7 2832077
638 47740 564846.8 2832061
639 47760 564835.9 2832044
640 47780 564824.9 2832027
641 47800 564814 2832010
642 47820 564803.1 2831994
643 47840 564792.1 2831977
644 47860 564781.2 2831960
645 47880 564770.2 2831943
646 47900 564759.3 2831927
647 47920 564748.4 2831910
648 47940 564737.4 2831893
649 47960 564726.5 2831876
650 47980 564715.6 2831860
651 48000 564704.6 2831843
652 48020 564693.7 2831826
653 48040 564682.8 2831809
654 48060 564671.8 2831793
655 48080 564660.9 2831776
656 48100 564649.9 2831759
657 48120 564639 2831742
658 48140 564628.1 2831726
659 48160 564617.1 2831709
660 48180 564606.2 2831692
661 48200 564595.3 2831675
662 48220 564584.3 2831659
663 48240 564573.4 2831642
664 48260 564562.5 2831625
Sr. No
Design
Chainage
(km)
Easting Northing
665 48280 564551.5 2831608
666 48300 564540.6 2831592
667 48320 564529.7 2831575
668 48340 564518.7 2831558
669 48360 564507.8 2831541
670 48380 564496.8 2831525
671 48400 564485.9 2831508
672 48420 564475 2831491
673 48440 564464 2831474
674 48460 564453 2831458
675 48480 564441.7 2831441
676 48500 564430.2 2831425
677 48520 564418.6 2831409
678 48540 564406.9 2831392
679 48560 564395.3 2831376
680 48580 564383.7 2831360
681 48600 564372 2831344
682 48620 564360.4 2831327
683 48640 564348.7 2831311
684 48660 564337.1 2831295
685 48680 564325.4 2831279
686 48700 564313.8 2831262
687 48720 564302.1 2831246
688 48740 564290.5 2831230
689 48760 564278.9 2831213
690 48780 564267.2 2831197
691 48800 564255.6 2831181
692 48820 564243.9 2831165
693 48840 564232.3 2831148
694 48860 564220.6 2831132
695 48880 564209 2831116
696 48900 564197.4 2831100
697 48920 564185.7 2831083
698 48940 564174.1 2831067
699 48960 564162.4 2831051
700 48980 564150.8 2831035
701 49000 564139.1 2831018
702 49020 564127.5 2831002
703 49040 564115.9 2830986
704 49060 564104.2 2830970
Schedule - A
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
18
Sr. No
Design
Chainage
(km)
Easting Northing
705 49080 564092.6 2830953
706 49100 564080.9 2830937
707 49120 564069.3 2830921
Sr. No
Design
Chainage
(km)
Easting Northing
708 49140 564057.6 2830905
709 49160 564046 2830888
Schedule - B
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
19
SCHEDULE – B
(See Clause 2.1)
DEVELOPMENT OF THE PROJECT HIGHWAY
1 Development of the Project Highway
Development of the Project Highway shall include construction of the Project Highway as
described in this Schedule-B and in Schedule-C.
2 Project Highway (Four Lane)
2.1 Four Laning shall include construction of the Four Lane Project Highway as described in Annex-I
of this Schedule-B and Annex-I of Schedule C.
2.2 The Project Highway shall be designed and constructed in conformity with the specifications and
standards set forth in Annex-I of Schedule-D.
Schedule - B
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
20
ANNEX – I
(Schedule-B)
Description of Four Laning
1. The Project Proposal
1.1 Construction of Four-Lane Greenfield highway with paved shoulders from Chainage Km 35.000
to Km 49.155 of NH-731A shall be undertaken as per Ministry’s Codes & specifications and terms
specified in Schedules.
2. Project Facilities
Project facilities shall be constructed in conformity with Annex-I of Schedule-C.
3. Specifications and Standards
The Project Highways shall be constructed in conformity with the Specifications and Standards
specified in Schedule-D.
4. Other Features of Project Highway
4.1 Geometric Design and General Features
Geometric design and General Features of the Project Highway shall be in conformity with the
Specifications and Standards specified in Schedule-D.
4.2 Design Speed
Design Speed of the Project Highway shall be in conformity with the Specifications and Standards
specified in Schedule-D.
4.3 Vertical Gradient
Vertical Gradient of the Project Highway shall be in conformity with the Specifications and
Standards specified in Schedule-D.
4.4 Right of Way (ROW)
Details of the proposed Right of Way are given below:
Sr. No
Proposed Chainage (km)
Right of Way (m) Remarks
From To
1 35.000 49.155 45/ 60* Green field
*60m RoW is proposed at locations of structures including VUPS/ROB & Interchanges.
4.5 Type of Shoulders
Shoulders on the Project Highway shall be in conformity with the Specifications and Standards
specified in Schedule-D.
4.6 Lateral and Vertical Clearances at Flyovers/Underpasses/Interchanges: As per Schedule D.
4.7 Cross Sections
The Project Highway shall be constructed to Four lane with paved shoulder standards. Typical
cross-sections (TCS) have been as given under Appendix B-II. Schedule of applicable cross-
Schedule - B
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
21
sections are given below. Concessionaire is free to use new/ alternative material & technology in
construction of highway as per Ministry’s circular RW/Nh-33044/18/2020-S&R(P&B) dated
14.12.2020. However, w.r.t TCS-1A Geocell Technology shall be compulsory on pilot basis in the
given section.
Sr.
No
Design
Chainage (Km)
Length (m) TCS
Description
Provision Total
Width
(m)
TCS
From To
1 35000 35963 963 4-lane (2x2)
carriageway +2.5m
paved shoulder+1.5m
earthen shoulder on
either side with
median 5.0m, Fig 2.4
of IRC: SP-84 2019
Road 27 TCS-1 -
2 35963 35988 25 6-lane (3x3) with
10.50m width with
3.0m wide median +
1.5m footpath both
sides, Fig. 7.2A of
IRC: SP-84 2019
Minor
Bridge
28.9 TCS-5 -
3 35988 36220 232 6-lane (3x3)
carriageway 10.5m
width with 3.00m
median along with
Service cum slip road
5.5m wide + 1.5m
footpath cum drain
on both sides,
Approach
to VUP
43.5 TCS-2 -
4 36220 36240 20 6-lane (3x3) 10.50m
carriageway width
with 3.0m median
VUP 25 TCS-3 Deviation to
Fig. 7.8 of
Manual
5 36240 36460 220 6-lane (3x3)
carriageway 10.5m
width with 3.00m
median along with
Service cum slip road
5.5m wide + 1.5m
footpath cum drain
on both sides
Approach
to VUP
43.5 TCS-2 -
6 36460 37265 805 4-lane (2x2)
carriageway +2.5m
paved shoulder+1.5m
earthen shoulder on
either side with
median 5.0m, Fig 2.4
of IRC: SP-84 2019
Road 27 TCS-1 -
7 37265 37560 295 6-lane (3x3)
carriageway 10.5m
width with 3.00m
median along with
Service cum slip road
5.5m wide + 1.5m
footpath cum drain
on both sides
Approach
to VUP
43.5 TCS-2 -
8 37560 37580 20 6-lane (3x3) 10.50m
carriageway width
with 3.0m median
VUP 25 TCS-3 Deviation to
Fig. 7.8 of
Manual
Schedule - B
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
22
Sr.
No
Design
Chainage (Km)
Length (m) TCS
Description
Provision Total
Width
(m)
TCS
From To
9 37580 37870 290 6-lane (3x3)
carriageway 10.5m
width with 3.00m
median along with
Service cum slip road
5.5m wide + 1.5m
footpath cum drain
on both sides
Approach
to VUP
43.5 TCS-2 -
10 37870 38785 915 4-lane (2x2)
carriageway +2.5m
paved shoulder+1.5m
earthen shoulder on
either side with
median 5.0m, Fig 2.4
of IRC: SP-84 2019
Road 27 TCS-1 -
11 38785 38875 90 6-lane (3x3) with
10.50m width with
3.0m wide median +
1.5m footpath both
sides, Fig. 7.2A of
IRC: SP-84 2019
Major
Bridge
28.9 TCS-5 -
12 38875 39648 773 4-lane (2x2)
carriageway +2.5m
paved shoulder+1.5m
earthen shoulder on
either side with
median 5.0m, Fig 2.4
of IRC: SP-84 2019
Road 27 TCS-1 -
13 39648 39673 25 6-lane (3x3) with
10.50m width with
3.0m wide median +
1.5m footpath both
sides, Fig. 7.2A of
IRC: SP-84 2019
Minor
Bridge
28.9 TCS-5 -
14 39673 41840 2167 4-lane (2x2)
carriageway +2.5m
paved shoulder+1.5m
earthen shoulder on
either side with
median 5.0m with
Geocell in sub-base
course, Fig 2.4 of
IRC: SP-84 2019
Road 27 TCS-1A Geocell
Technology
is to be used
compulsory.
15 41840 42060 220 6-lane(3x3)
carriageway 10.5m
width with 3.00m
median along with
Service cum slip road
5.5m wide + 1.5m
footpath cum drain
on both sides
Approach
to VUP
43.5 TCS-2 -
16 42060 42080 20 6-lane (3x3) 10.50m
carriageway width
with 3.0m median
VUP 25 TCS-3 Deviation to
Fig. 7.8 of
Manual
17 42080 42870 790 6-lane(3x3)
carriageway 10.5m
width with 3.00m
Approach
to VUP
43.5 TCS-2 -
Schedule - B
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
23
Sr.
No
Design
Chainage (Km)
Length (m) TCS
Description
Provision Total
Width
(m)
TCS
From To
median along with
Service cum slip road
5.5m wide + 1.5m
footpath cum drain
on both sides
18 42870 42890 20 6-lane (3x3) 10.50m
carriageway width
with 3.0m median
VUP 25 TCS-3 Deviation to
Fig. 7.8 of
Manual
19 42890 43146 256 6-lane(3x3)
carriageway 10.5m
width with 3.00m
median along with
Service cum slip road
5.5m wide + 1.5m
footpath cum drain
on both sides
Approach
to VUP
43.5 TCS-2 -
20 43146 43497 351 9.50m carriageway
width + 1.5m
footpath with 3.0m
median along with
Service cum slip road
5.5m wide + 1.5m
footpath cum drain
on both sides
Approach
to ROB
47.57 TCS-4 -
21 43497 43623 126 As per RDSO 9.50m
carriageway width +
1.5m footpath with
3.0m median
ROB 27 TCS-5A -
22 43623 43840 217 9.50m carriageway
width + 1.5m
footpath with 3.0m
median along with
Service cum slip road
5.5m wide + 1.5m
footpath cum drain
on both sides
Approach
to ROB
47.57 TCS-4 -
23 43840 43850 10 9.50m carriageway
width + 1.5m
footpath with 3.0m
median along with
Service cum slip road
5.5m wide + 1.5m
footpath cum drain
on both sides
Minor
Bridge on
Approach
of ROB
47.57 TCS-4 -
24 43850 43986 136 9.50m carriageway
width + 1.5m
footpath with 3.0m
median along with
Service cum slip road
5.5m wide + 1.5m
footpath cum drain
on both sides
Approach
to ROB
47.57 TCS-4 -
25 43986 44035 49 6-lane(3x3)
carriageway 10.5m
width with 3.00m
median along with
Service cum slip road
Approach
to VUP
43.5 TCS-2 -
Schedule - B
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
24
Sr.
No
Design
Chainage (Km)
Length (m) TCS
Description
Provision Total
Width
(m)
TCS
From To
5.5m wide + 1.5m
footpath cum drain
on both sides
26 44035 44055 20 6-lane (3x3) 10.50m
carriageway width
with 3.0m median
VUP 25 TCS-3 Deviation to
Fig. 7.8 of
Manual
27 44055 44250 195 6-lane(3x3)
carriageway 10.5m
width with 3.00m
median along with
Service cum slip road
5.5m wide + 1.5m
footpath cum drain
on both sides
Approach
to VUP
43.5 TCS-2 -
28 44250 44375 125 4-lane (2x2)
carriageway +2.5m
paved shoulder+1.5m
earthen shoulder on
either side with
median 5.0m, Fig 2.4
of IRC: SP-84 2019
Road 27 TCS-1 -
29 44375 44385 10 6-lane (3x3) with
10.50m width with
3.0m wide median +
1.5m footpath both
sides, Fig. 7.2A of
IRC: SP-84 2019
Minor
Bridge
28.9 TCS-5 -
30 44385 44615 230 4-lane (2x2)
carriageway +2.5m
paved shoulder+1.5m
earthen shoulder on
either side with
median 5.0m, Fig 2.4
of IRC: SP-84 2019
Road 27 TCS-1 -
31 44615 44625 10 6-lane (3x3) with
10.50m width with
3.0m wide median +
1.5m footpath both
sides, Fig. 7.2A of
IRC: SP-84 2019
Minor
Bridge
28.9 TCS-5 -
32 44625 44825 200 4-lane (2x2)
carriageway +2.5m
paved shoulder+1.5m
earthen shoulder on
either side with
median 5.0m, Fig 2.4
of IRC: SP-84 2019
Road 27 TCS-1 -
33 44825 44835 10 6-lane (3x3) with
10.50m width with
3.0m wide median +
1.5m footpath both
sides, Fig. 7.2A of
IRC: SP-84 2019
Minor
Bridge
28.9 TCS-5 -
34 44835 45294 459 4-lane (2x2)
carriageway +2.5m
paved shoulder+1.5m
earthen shoulder on
Road 27 TCS-1 -
Schedule - B
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
25
Sr.
No
Design
Chainage (Km)
Length (m) TCS
Description
Provision Total
Width
(m)
TCS
From To
either side with
median 5.0m, Fig 2.4
of IRC: SP-84 2019
35 45294 45306 12 6-lane (3x3) with
10.50m width with
3.0m wide median +
1.5m footpath both
sides, Fig. 7.2A of
IRC: SP-84 2019
Minor
Bridge
28.9 TCS-5 -
36 45306 45534 228 4-lane (2x2)
carriageway +2.5m
paved shoulder+1.5m
earthen shoulder on
either side with
median 5.0m, Fig 2.4
of IRC: SP-84 2019
Road 27 TCS-1 -
37 45534 45546 12 6-lane (3x3) with
10.50m width with
3.0m wide median +
1.5m footpath both
sides, Fig. 7.2A of
IRC: SP-84 2019
Minor
Bridge
28.9 TCS-5 -
38 45546 46640 1094 4-lane (2x2)
carriageway +2.5m
paved shoulder+1.5m
earthen shoulder on
either side with
median 5.0m, Fig 2.4
of IRC: SP-84 2019
Road 27 TCS-1 -
39 46640 46660 20 6-lane (3x3) with
10.50m width with
3.0m wide median +
1.5m footpath both
sides, Fig. 7.2A of
IRC: SP-84 2019
Minor
Bridge
28.9 TCS-5 -
40 46660 46920 260 4-lane (2x2)
carriageway +2.5m
paved shoulder+1.5m
earthen shoulder on
either side with
median 5.0m, Fig 2.4
of IRC: SP-84 2019
Road 27 TCS-1 -
41 46920 47260 340 6-lane(3x3)
carriageway 10.5m
width with 3.00m
median along with
Service cum slip road
5.5m wide + 1.5m
footpath cum drain
on both sides
Approach
to Diamond
Interchange
on NH-24B
43.5 TCS-2 -
42 47260 47320 60 6-lane (3x3) 10.50m
carriageway width
with 3.0m median
Flyover 25 TCS-3 Deviation to
Fig. 7.8 of
Manual
43 47320 47645 325 6-lane(3x3)
carriageway 10.5m
width with 3.00m
median along with
Approach
to Diamond
Interchange
of NH-24B
43.5 TCS-2 -
Schedule - B
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
26
Sr.
No
Design
Chainage (Km)
Length (m) TCS
Description
Provision Total
Width
(m)
TCS
From To
Service cum slip road
5.5m wide + 1.5m
footpath cum drain
on both sides
44 47645 48240 595 4-lane (2x2)
carriageway +2.5m
paved shoulder+1.5m
earthen shoulder on
either side with
median 5.0m, Fig 2.4
of IRC: SP-84 2019
Road 27 TCS-1 -
45 48240 48260 20 6-lane (3x3) with
10.50m width with
3.0m wide median +
1.5m footpath both
sides, Fig. 7.2A of
IRC: SP-84 2019
Minor
Bridge
28.9 TCS-5 -
46 48260 48643 383 6-lane(3x3)
carriageway 10.5m
width with 3.00m
median along with
Service cum slip road
5.5m wide + 1.5m
footpath cum drain
on both sides
Approach
to Diamond
Interchange
on NH-19
43.5 TCS-2 -
47 48643 48728 85 6-lane (3x3) 10.50m
carriageway width
with 3.0m median
Flyover 25 TCS-3 Deviation to
Fig. 7.8 of
Manual
48 48728 49115 387 6-lane(3x3)
carriageway 10.5m
width with 3.00m
median along with
Service cum slip road
5.5m wide + 1.5m
footpath cum drain
on both sides
Approach
to Diamond
Interchange
on NH-19
43.5 TCS-2 -
49 49115 49135 20 6-lane (3x3) 10.50m
carriageway width
with 3.0m median
VUP 25 TCS-3 Deviation to
Fig. 7.8 of
Manual
50 49135 49155 20 4-lane (2x2)
carriageway +2.5m
paved shoulder+1.5m
earthen shoulder on
either side with
median 5.0m, Fig 2.4
of IRC: SP-84 2019
Road 27 TCS-1 -
TCS-1 6667
TCS-1A 2167
TCS-2 3982
TCS-3 265
TCS-4 714
TCS-5 234
TCS-5A 126
Total 14155
Schedule - B
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
27
Notes:
(i) Any variation in design length of respective TCS specified in Schedule B shall not constitute a
change of scope, save and except any variations in the design length arising out of a change of
scope expressly undertaken in accordance with the provisions of Article 16.
4.8 Alignment Plan and Longitudinal Section
An alignment Plan and longitudinal section (Plan & Profile) of the project highway are enclosed
at Appendix B-I in soft copy for reference only. Longitudinal profile shall be designed based on
Schedule-D. Finished Road level indicated in the alignment plan is minimum. The Concessionaire
shall design the road profile of the project highway based on site/design requirement specified
in Schedule-D.
5. Bypass and new Realignment
NIL
6 Service cum slip Roads
A. Interchange elements: Ramps/ Loops/ Merged Sections/ Roundabouts
Interchange has been proposed at km 47.290 and km 48.685. A GAD is attached under Appendix-
B-III.
Notes:
(i) Detailed design of all interchange shall be in accordance with Schedule-D.
Service road shall be provided as per para 4.7- Cross-sections of this Schedule.
7. Pavement Design
Design of pavement shall be done for design period of 20 years, in accordance with the Schedule-
D and IRC-37:2018. Concessionaire is free to use new/ alternative material & technology in
construction of highway as per MoRTH circular RW/NH-33044/18/2020-S&R(P&B) dated
14.12.2020
7.1 Design Traffic
Pavement design shall be carried out for the minimum design traffic of 120 MSA for entire project
highway with design life of 20 years as IRC: 37:2018.
7.5 Intersection / Interchanges
Intersection / Interchanges on the Project Highway shall be in conformity with the Specifications
and Standards specified in Schedule-D.
At-Grade Intersections
8.1 Major Junction
S No.
Proposed Chainage
(km) Side(Left/Right) Type of Junction Destination
1 47.290 BHS X- JUNCTION NH – 24B
Schedule - B
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
28
2 48.685 BHS X-JUNCTION NH-2
8.2 Minor Junction
S
No.
Design Chainage
(km)
Side(Left
/ Right)
Type of
Junction
Destination
1 36+230 BHS X-JUNCTION From Burhepur to Bihar
2 37+570 BHS X-JUNCTION From Bihar to Sakardaha
3 42+070 BHS X-JUNCTION Kurha Village Road
4 42+880 BHS X-JUNCTION From Lalgopalganj to Bendhan Gopalpur
5 44+045 BHS X-JUNCTION From Badupur to Barna
6 49+125 BHS X-JUNCTION From Meerjahapur to Sringverpur
9. Underpasses
A) Vehicular Underpasses (VUP)
Sr. No Location (Chainage) Km Type of Structure Span/ opening (m)
1 36+230 VUP 1 x 20
2 37+570 VUP 1 x 20
3 42+070 VUP 1 x 20
4 42+880 VUP 1 x 20
5 44+045 VUP 1 x 20
6 49+125 VUP 1 x 20
Note: Traffic Impact Attenuators shall be provided be provided at all VUPs as per Schedule-D.
10.1 Interchange structures/Grade Separator
Interchange structure/grade separator structure to be provided as per the details below.
Irrespective of span arrangement indicated, all the structures shall provide lateral and vertical
clearances as per Schedule D.
Sr.
No
Location Salient features
Minimum length of
viaduct to be provided
Road to be carried
over/under the
structures
1 47.290 Diamond Interchange 2 x 30 Over the structure
2 48.685 Diamond Interchange 2 x 42.5 Over the structure
Note: (i)GAD attached at Appendix B-III of Schedule-B.
(ii)Noise Barrier shall be provided at both the interchanges as per Schedule-D.
(iii) Traffic Impact Attenuators shall be provided be provided at both the interchanges as per Schedule-D.
10.2 Road Over Bridges (ROB)
The Road Over Bridges (ROB) shall be provided as per the details below:
Sr.
No
Chainage
Road
category
Span Arrangement
Skew
Angle
Structure
Width
Lateral clearance
Schedule - B
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
29
km (m) deg (m)
1 43.560 - 3X36+1X18 21 As per TCS-5A As per GAD Attached
Note: Traffic Impact Attenuators shall be provided at the ROB as per Schedule-D.
10.3 Major Bridges
(A) Widening / Repair / Rehabilitation of Existing Major Bridges
NIL
(B) Reconstruction of Existing Major Bridges
NIL
(C) Construction of New Major Bridges on Main Carriageway (Over River / Streams /Nallah)
Sr.
No
Chainage Category
Span
Arrangement
Skew
Angle
Structure Width
km (m) deg (m)
1 38.830 Canal 3 x 30 0 As per TCS-5
10.4 Minor Bridges
(A) Widening / Repair / Rehabilitation of Existing Minor Bridges
NIL
(B) Reconstruction of Existing Minor Bridges
NIL
(C) Construction of New Minor Bridges on Main Carriageway
Sr. No Chainage Span Arrangement Structure Width
Km (m) (m)
1 35+975 1X25 As per TCS-5
2 39+660 1x25 As per TCS-5
3 43+845 1X10 As per TCS-5
4 44+380 1X10 As per TCS-5
5 44+620 1X10 As per TCS-5
6 44+830 1X10 As per TCS-5
7 45+300 1X12 As per TCS-5
8 45+540 1X12 As per TCS-5
9 46+650 1X20 As per TCS-5
10 48+250 1X20 As per TCS-5
6. Culverts
(A) Widening of Existing Culverts – NIL
(B) Reconstruction of Existing Culverts – NIL
Schedule - B
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
30
(C) Construction of New Culverts
Sr. No
Proposed Chainage
(km)
Type of Culvert Span Arrangement (m)
1 35+380 BOX 1x2
2 35+880 BOX 1x2
3 36+600 BOX 1x2
4 36+990 BOX 1x2
5 37+370 BOX 1x2
6 38+315 BOX 1x2
7 38+555 BOX 1X4
8 39+300 BOX 1X4
9 39+540 BOX 1x2
10 40+100 BOX 1X4
11 40+220 BOX 1x2
12 40+760 BOX 1X4
13 40+975 BOX 1X4
14 41+500 BOX 1X4
15 41+800 BOX 1x2
16 42+400 BOX 1x2
17 43+070 BOX 1x2
18 43+315 BOX 1x4
19 44+800 BOX 1x4
20 45+090 BOX 1x2
21 45+390 BOX 1x4
22 45+720 BOX 1X4
23 46+185 BOX 1X4
24 47+100 BOX 1X4
25 47+800 BOX 1X4
26 48+550 BOX 1X4
7. ROAD SIDE DRAINAGE
Drainage system including surface and subsurface drains for the Project Highway shall
be provided as per the Manual.
Unlined Drain
Sr. No
CHAINAGE (m)
Length (m) Side Total Length (m)
From To
1 35000 35963 963 BHS 1926
2 36460 37265 805 BHS 1610
3 37870 38785 915 BHS 1830
4 38875 39648 773 BHS 1546
5 39673 41840 2167 BHS 4334
6 44250 44375 125 BHS 250
7 44385 44615 230 BHS 460
8 44625 44825 200 BHS 400
9 44835 45294 459 BHS 918
10 45306 45534 228 BHS 456
11 45546 46640 1094 BHS 2188
Schedule - B
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
31
Unlined Drain
Sr. No
CHAINAGE (m)
Length (m) Side Total Length (m)
From To
12 46660 46920 260 BHS 520
13 47645 48240 595 BHS 1190
14 49135 49155 20 BHS 40
TOTAL LENGTH (m) 17668
Lined Drain
Sr.
No
Chainage (m)
Length (m)
Length of Lined Drain
on both side (m)
From To
1 35988 36220 232 464
2 36240 36460 220 440
3 37265 37560 295 590
4 37580 37870 290 580
5 41840 42060 220 440
6 42080 42870 790 1580
7 42890 43146 256 512
8 43146 43506 360 720
9 43614 43840 226 452
10 43850 43986 136 272
11 43986 44035 49 98
12 44055 44250 195 390
13 46920 47260 340 680
14 47320 47645 325 650
15 48260 48643 383 766
16 48728 49115 387 774
TOTAL LENGTH (m) 9408
8. RAINWATER HARVESTING & DRAINAGE
The provision of rainwater harvesting & drainage work shall be executed as per requirement of
IRC: SP: 42-2017 and IRC: SP: 50-2013 & as per Ministry’s circular RW/NH-33044/14/2003-
S&R(R)pt-II dated 03.09.2021.
9. UTILITY SHIFTING
Shifting of obstructing utilities shall be done as per Ministry’s circular RW/NH-33044/29/2015-
S&R(R)pt dated 11.02.2021. The Concessionaire shall be responsible for getting the utilities
shifted as per approval of the concerned utility department. The assistance of the Authority is
limited to giving forwarding letter on the proposal of Concessionaire to utility owning department
whenever asked by the Concessionaire. The decision/approval of utility owning department shall
be binding on the Concessionaire.
Notes:
(a) The supervision charges at the rates/charges applicable of the utility owning department
shall be paid directly by the Authority to the Utility Owning department as and when
Concessionaire furnishes demand of Utility Owning Department along with a copy of
estimated cost given by the latter.
Schedule - B
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
32
(b) The dismantled materials / scrap of the existing utilities to be shifted / dismantled shall
belong to the Concessionaire who would be free to dispose-off the dismantled material as
deemed fit by them unless the concessionaire is required to deposit the dismantled material
to utility owning department as per the norms and practice and, in that case the amount of
credit for dismantled material may be availed by the Concessionaire as per estimates agreed
between them.
(c) The utilities shall be handed over after shifting work is completed to Utility Owning
Department up to their entire satisfaction. The maintenance liability shall rest with the Utility
Owning Department after handing over process is complete as far as utility shifting works are
concerned.
10. CHANGE OF SCOPE
The length of Structures and bridges specified herein above shall be treated as an approximate
assessment. The actual lengths as required on the basis of detailed investigations shall be
determined by the Concessionaire in accordance with the Specifications and Standards. Any
variations in the lengths specified in this Schedule-B shall not constitute a Change of Scope, save
and except any variations in the length arising out of a Change of Scope expressly undertaken in
accordance with the provisions of Article 16.
Schedule - B
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
33
Appendix B-I (Schedule-B)
Alignment Plan and longitudinal Section are enclosed as Appendix B-I (Schedule-B).
Schedule - B
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
34
Appendix B-II (Schedule-B)
Typical Cross Section are enclosed as Appendix B-II (Schedule-B).
Schedule - B
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
35
Appendix B-III (Schedule-B)
Interchange at design chainage km 47.290 (junction with existing NH-24B) and 48.685 (junction with
existing NH-2) are enclosed as Appendix B-III (Schedule-B).
Schedule - C
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
36
Appendix B-IV (Schedule-B)
Traffic Signage Plan of the Project Highway enclosed as Appendix B-IV (Schedule-B).
Schedule - C
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
37
Appendix B-V (Schedule-B)
Drainage Plan of the Project Highway enclosed as Appendix B-V (Schedule-B).
Schedule - C
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
38
Appendix B-VI (Schedule-B)
GAD and Miscellaneous Drawings enclosed as Appendix B-VI (Schedule-B).
Schedule - C
Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of
NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II)
39
SCHEDULE – C
(See Clause 2.1)
PROJECT FACILITIES
1. Project Facilities
The Concessionaire shall construct the Project Facilities in accordance with the provisions of this
Agreement. Such Project Facilities shall include:
(a) Toll plaza
(b) Road side furniture;
(c) Pedestrian facilities;
(d) Tree plantation
(e) Truck lay-byes;
(f) Bus stop and bus shelters;
(g) Rest areas;
(h) Highway Lighting;
(i) Transportation Art.
2 Project Facilities for Project Highway
Project Facilities forming part of Project Highway and to be completed on or before the scheduled
date have been described in Annex‐I of this Schedule‐C.
Annex – I
SCHEDULE – C
(See Clause 2.1)
PROJECT FACILITIES
1. Project Facilities
The Concessionaire shall construct the Project Facilities described in this Annex-1 to form part of
the Four-Lane Project. The project facilities shall include:
(a) Toll plaza
(b) Road side furniture;
(c) Pedestrian facilities;
(d) Tree plantation
(e) Truck lay-byes;
(f) Bus stop and bus shelters;
(g) Rest areas;
(h) Highway Lighting and
(i) Transportation Art.
2. Description of Project Facilities
Each of the project facilities is described below:
(a) Toll Plazas NIL
(b) Roadside Furniture
(i) Traffic Signs and Pavement Markings
Traffic signs and pavement markings shall be provided as per Schedule D.
(a) Overhead Gantry Signs shall be provided at locations mentioned below
Sr. No Chainage
Name of Sign/Road
Marking
Numbers Fig.no as per IRC 67
2012
LHS RHS
1 35+000 Gantry Mounted Sign 1 16.11
2 47+260 Gantry Mounted Sign 1 16.11
3 48+320 Gantry Mounted Sign 1 16.11
4 48+643 Gantry Mounted Sign 1 16.11
5 48+727 Gantry Mounted Sign 1 16.11
Note: The above location is indicative and minimum. The exact location of the overhead gantry
finalized after approval from the Independent Engineer.
ii. Safety Barrier: Thrie beam type steel barrier shall be provided in a minimum length of 19,112 metre
at locations finalized after review by Independent Engineer under clause 9.7 of the Manual referred
in Schedule D.
(c) Pedestrian Facilities
Pedestrian facilities shall be provided as per Schedule-D.
(d) Landscaping & Tree plantation
(j) Minimum of 3000 trees shall be planted as per Schedule-D.
(ii) Landscaping Treatment shall be provided at all grade separators, viaducts, traffic
islands, bus-bays as per Schedule-D.
(e) Truck Lay Bye
Sr. No Design Chainage (Km) LHS/RHS Village name
Nil
(f) Bus Bay – Bus Shelter
Sr.
No
Design Chainage (Km)
LEFT RIGHT
1 36.750 36.850
2 39.100 39.200
3 41.130 41.250
4 44.450 44.550
5 45.430 45.700
6 47.870 48.000
Note: The Bus shelters shall be aesthetically pleasing duly designed by qualified and experienced
Architect.
(g) Rest Areas
Nil
(h) Highway Lighting: Shall be provided as per Schedule-D.
(i) Transportation Art: Shall be provided on all grade-separators, VUPs and ROB to enhance the
overall aesthetics, the graphics/visuals shall be designed by fine arts department of an institute of
repute.
4. Rainwater Harvesting
As per Ministry of Environment and Forests Notification, New Delhi dated 14/01/1997 (as amended on
13/01/1998, 05/01/1999 & 6/11/2000), the construction of Rain water, harvesting structure is mandatory
in and around Water Crisis area, notified by the Central Ground Water Board.
Schedule - D
SCHEDULE – D
(See Clause 2.1)
SPECIFICATIONS AND STANDARDS
1. Four-Laning
The Concessionaire shall comply with the Specifications and Standards set forth in Annex-I of this
Schedule-D for construction of the Four Lane Project Highway.
Schedule - D
Annex - I
(Schedule-D)
SPECIFICATIONS AND STANDARDS
1 Specifications and Standards
All Materials works and construction operations shall conform to the Manual of Specifications
and Standards for Four-Lane Highways (IRC: SP: 84-2019) published by IRC (referred to as
“Manual” in this Schedule) and MORTH Specifications for Road and Bridge Works. Where the
specification for a work is not given, Good Industry Practice shall be adopted to the satisfaction
of the Independent Engineer. Further the specifications & standards shall comply to Ministry’s
specifications & applicable IRC Codes.
2 Deviations from the Specifications and Standards
2.1 Notwithstanding anything to the contrary contained in the aforesaid Manual, the following
Specifications and Standards shall apply to the Four-Lane Project Highway, and for purposes of
this Agreement, the aforesaid Manual shall be deemed to be amended to the extent set forth
below:
Sr.
No
Clause as per
Manual
Provision as per Manual
Deviation/
Modified Provision
1 2.12.2 Service Road
Width of service/slip road
shall be 5.5m at all locations.
No parking Bays are to be
provided.
2 5.4.1 (i) Flexible pavement: design period and strategy
The design period shall be as
specified in Schedule-B.
3 7.1
All bridges and grade separated structures shall
have independent superstructure for each
direction of travel unless specified otherwise in
Schedule ‘B’. Culverts may have single or
independent superstructure.
As per Schedule-B.
4 7.19
Grade Separated Road Structures: Carriageway
width 14.00m.
The Carriageway width shall
be as specified in Schedule-
B; TCS-3.
5 7.21 Structures in Marine Environment Deleted.
6 Nil -
Transportation Art: The
specification and standards
shall be as provided by fine
arts department of an
institute of repute.

More Related Content

Similar to Modified_ScheduleABCD.pdf

Special Repair of Roads in Patiala City
Special Repair of Roads in Patiala CitySpecial Repair of Roads in Patiala City
Special Repair of Roads in Patiala CityEmaan Sharma
 
GMLR PPT MC 22-06-15-final
GMLR PPT MC 22-06-15-finalGMLR PPT MC 22-06-15-final
GMLR PPT MC 22-06-15-finalDurgesh Gawde
 
Construction manual for sub stations
Construction manual for sub stationsConstruction manual for sub stations
Construction manual for sub stationsAmit Kumar
 
Use of fly ash in road flyover embankment construction on nh works reg dt on ...
Use of fly ash in road flyover embankment construction on nh works reg dt on ...Use of fly ash in road flyover embankment construction on nh works reg dt on ...
Use of fly ash in road flyover embankment construction on nh works reg dt on ...ssuserbf7f52
 
Doubling presentation
Doubling  presentationDoubling  presentation
Doubling presentationNeha Singh
 
IRJET- Analysis of Construction in Terms of Sustainability in Sagar City Ring...
IRJET- Analysis of Construction in Terms of Sustainability in Sagar City Ring...IRJET- Analysis of Construction in Terms of Sustainability in Sagar City Ring...
IRJET- Analysis of Construction in Terms of Sustainability in Sagar City Ring...IRJET Journal
 
4897-Bridleway Crossing-TN-001-P01 SIGNED.pdf
4897-Bridleway Crossing-TN-001-P01 SIGNED.pdf4897-Bridleway Crossing-TN-001-P01 SIGNED.pdf
4897-Bridleway Crossing-TN-001-P01 SIGNED.pdfnithyanandhan9
 
Constructionmanualforsub stations-130713094651-phpapp02
Constructionmanualforsub stations-130713094651-phpapp02Constructionmanualforsub stations-130713094651-phpapp02
Constructionmanualforsub stations-130713094651-phpapp02Rakesh Sinha
 
TRAINING REPORT A PROJECT ON ROAD WIDENI...
                       TRAINING REPORT              A PROJECT  ON ROAD WIDENI...                       TRAINING REPORT              A PROJECT  ON ROAD WIDENI...
TRAINING REPORT A PROJECT ON ROAD WIDENI...Pradeep Yadav
 
Jirapur susner-mp-rj-border road ppt...7.01.19
Jirapur susner-mp-rj-border road ppt...7.01.19Jirapur susner-mp-rj-border road ppt...7.01.19
Jirapur susner-mp-rj-border road ppt...7.01.19ChandrakantSoni5
 

Similar to Modified_ScheduleABCD.pdf (20)

Detailsh.pdf
Detailsh.pdfDetailsh.pdf
Detailsh.pdf
 
5 (1)
5 (1)5 (1)
5 (1)
 
Special Repair of Roads in Patiala City
Special Repair of Roads in Patiala CitySpecial Repair of Roads in Patiala City
Special Repair of Roads in Patiala City
 
Road
RoadRoad
Road
 
GMLR PPT MC 22-06-15-final
GMLR PPT MC 22-06-15-finalGMLR PPT MC 22-06-15-final
GMLR PPT MC 22-06-15-final
 
Construction manual for sub stations
Construction manual for sub stationsConstruction manual for sub stations
Construction manual for sub stations
 
7251
72517251
7251
 
Use of fly ash in road flyover embankment construction on nh works reg dt on ...
Use of fly ash in road flyover embankment construction on nh works reg dt on ...Use of fly ash in road flyover embankment construction on nh works reg dt on ...
Use of fly ash in road flyover embankment construction on nh works reg dt on ...
 
Metro Project
Metro ProjectMetro Project
Metro Project
 
Doubling presentation
Doubling  presentationDoubling  presentation
Doubling presentation
 
IRJET- Analysis of Construction in Terms of Sustainability in Sagar City Ring...
IRJET- Analysis of Construction in Terms of Sustainability in Sagar City Ring...IRJET- Analysis of Construction in Terms of Sustainability in Sagar City Ring...
IRJET- Analysis of Construction in Terms of Sustainability in Sagar City Ring...
 
4897-Bridleway Crossing-TN-001-P01 SIGNED.pdf
4897-Bridleway Crossing-TN-001-P01 SIGNED.pdf4897-Bridleway Crossing-TN-001-P01 SIGNED.pdf
4897-Bridleway Crossing-TN-001-P01 SIGNED.pdf
 
Construction manual for sub stations
Construction manual for sub stationsConstruction manual for sub stations
Construction manual for sub stations
 
Constructionmanualforsub stations-130713094651-phpapp02
Constructionmanualforsub stations-130713094651-phpapp02Constructionmanualforsub stations-130713094651-phpapp02
Constructionmanualforsub stations-130713094651-phpapp02
 
BEST REAL ESTATE COMPANY IN PATNA
BEST REAL ESTATE COMPANY IN PATNABEST REAL ESTATE COMPANY IN PATNA
BEST REAL ESTATE COMPANY IN PATNA
 
New mandovi bridge
New mandovi bridgeNew mandovi bridge
New mandovi bridge
 
Sadab
SadabSadab
Sadab
 
TRAINING REPORT A PROJECT ON ROAD WIDENI...
                       TRAINING REPORT              A PROJECT  ON ROAD WIDENI...                       TRAINING REPORT              A PROJECT  ON ROAD WIDENI...
TRAINING REPORT A PROJECT ON ROAD WIDENI...
 
7242
72427242
7242
 
Jirapur susner-mp-rj-border road ppt...7.01.19
Jirapur susner-mp-rj-border road ppt...7.01.19Jirapur susner-mp-rj-border road ppt...7.01.19
Jirapur susner-mp-rj-border road ppt...7.01.19
 

Recently uploaded

notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLManishPatel169454
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Christo Ananth
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...tanu pandey
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 

Recently uploaded (20)

notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 

Modified_ScheduleABCD.pdf

  • 1. Schedule - A Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH- 731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 1 SCHEDULE-A (See Clause 10.1) Site of the PROJECT 1 THE SITE 1.1 Site of the Project Highway shall include the land, buildings, structures and road works as described in Annex-I of this Schedule-A. 1.2 An inventory of the Site including the land, buildings, structures, road works, trees and any other immovable property on, or attach to, the Site shall be prepared jointly by the Authority Representative and the Concessionaire, and such inventory shall form part of the memorandum referred to in Clause 10.3.1 of the Agreement. 1.3 Additional land required for Toll Plazas, Bus Bays/Shelter, Traffic Aid Posts, Medical Aid Posts and vehicle rescue posts or for construction of works specified in the Change of Scope Order issued under Clause 16.2.3 of this Agreement shall be acquired in accordance with the provisions of Clause 10.3.6 of this Agreement. Upon acquisition, such land shall form part of the Site and vest in the Authority.
  • 2. Schedule - A Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH- 731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 2 Annex – I (Schedule-A) Site for Four Laning 1 Site The proposed Greenfield alignment commencing from Autarpur Village at km 35.000 in Pratapgarh District in the State of Uttar Pradesh and ends near Singraur Uparhar Village of Prayagraj District section NH-731A in the State of Uttar Pradesh at km 49.155. The start and end chainage coordinates of the package are given below: Sr. No Easting Northing Remarks 1 562654.556 E 2843498.4942 N Start of Project Road 2 564048.9068 E 2830892.3342 N End of Project Road The land, carriageway and structures comprising the Site are described below. The Index Map / location plan of the project highway is given at Appendix A-I of Schedule-A. 2 Land The site of the project highway comprises the land (existing right of way) as described below: Sr. No Proposed Chainage (km) Right of Way(m) Remarks From To 1 35.000 49.155 NIL Greenfield Alignment 3 Carriageway This Project envisages construction of a 4-lane green field highway with paved shoulder. 4 Major Bridges- The site includes the following major bridges: Sr. No Existing Chainage (km) Type of Structure No. of Spans with span length (m) Width (m) Foundation Sub- structure Super- structure NIL 5 Road over-bridges (ROB)/ Road under-bridges (RUB) The site includes the following ROB (road over railway line)/RUB (road under railway line): Sr. No Existing Chainage (km) Type of Structure No. of Spans with span length (m) Width (m) Foundation Sub- structure Super- structure NIL Railway Line / Level Crossings The Site includes the following Railway Line / Level Crossing:
  • 3. Schedule - A Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH- 731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 3 Sr. No Location (Chainage, km) Remarks 1 43.560 Railway Crossing 6 Grade Separators The site includes the following Grade Separators: Sr. No Existing Chainage (km) Type of Structure No. of Spans with span length (m) Width(m) Foundation Superstructure NIL 7 Minor Bridges The Site includes the following Minor Bridges: Sr. No Existing Chainage (km) Type of Structure No. of Spans with span length (m) Width (m) Foundation Sub- structure Super- structure NIL 8 Cross Drainage Structures / Culverts - NIL The Site includes the following culverts: Sr. No Existing Chainage (km) Type of Culvert Span/Opening with span length (m) Formation Width (m) NIL 9 Total Number of Structures The total number of structures on the site is indicated below: (a) No. of Major Bridges –NIL (b) No. of Railway Over Bridges –NIL (c) No. of Grade Separators –NIL (d) No. of Minor Bridges –NIL (e) No. of Culverts – NIL 10 Bus Shelters and Truck lay-byes 10.1 Bus Shelters The location of existing bus shelters are given below: Sr. No Existing Chainage (km) Length(m) Left Hand Side Right Hand Side NIL 10.2 Truck Lay-byes The location of existing truck lay byes are given below: Sr. No Existing Chainage (km) Length(m) Left Hand Side Right Hand Side NIL
  • 4. Schedule - A Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH- 731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 4 11 Cross Roads The details of crossroads are as follows: Major Cross Road: Sr. No Location At grade Separated Category of Cross Road From km to km NH SH MDR Others 1 47.290 NH-24B/New NH30 2 48.685 NH-2/New NH 19 Minor Cross Road: Sr. No Chainage (Km) Junction Cross Road 1 36+230 + BT 2 37+570 + BT 3 42+070 + BT 4 42+740 + BT 5 44+045 + BT 6 49+125 + BT 12 Permanent Bridge, Bye Pass or Tunnel costing Rs. 50 crore or more The project is a green field project hence there is no existing structures. The new structures shall be constructed as per Schedules.
  • 5. Schedule - A Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 5 13 Details of Existing Utilities (i) Electrical utilities The site includes the following electrical utilities: - Design Chainage (Km) 11KV electrical poles in nos. Light Poles in Nos. 132 KV HT Electric Line Crossing the Road 220 KV HT Electric Line Crossing the Road 400 KV HT Electric Line Crossing the Road 800 KV HT Electric Line Crossing the Road Transformer in nos. From To LHS RHS LHS RHS LHS RHS Total 8 14 0 1 1 0 0 0 0 0 35+000 35+500 - - - - - - 35+500 36+000 - - - - - - 36+000 36+500 - - - - - - 36+500 37+000 - - - - - - 37+000 37+500 - - - - - - 37+500 38+000 - - - - - - 38+000 38+500 - - - - - - 38+500 39+000 - - - - - - 39+000 39+500 - - - - - - 39+500 40+000 1 1 - - - - 40+000 40+500 - 1 - - 1 - - 40+500 41+000 - - - - - - 41+000 41+500 - - - - - - 41+500 42+000 - - - - - - 42+000 42+500 - - - - - - 42+500 43+000 - - - - - - 43+000 43+500 - - - - - - 43+500 44+000 1 - - - - - 44+000 44+500 - - - - - - 44+500 45+000 - - - - - - 45+000 45+500 - - - - - - 45+500 46+000 - - - - - -
  • 6. Schedule - A Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 6 Design Chainage (Km) 11KV electrical poles in nos. Light Poles in Nos. 132 KV HT Electric Line Crossing the Road 220 KV HT Electric Line Crossing the Road 400 KV HT Electric Line Crossing the Road 800 KV HT Electric Line Crossing the Road Transformer in nos. From To LHS RHS LHS RHS LHS RHS Total 8 14 0 1 1 0 0 0 0 0 46+000 46+500 - - - - - - 46+500 47+000 - 2 1 - - 47+000 47+500 2 2 - - - - 47+500 48+000 1 3 - - - - 48+000 48+500 - - - - - - 48+500 49+000 3 5 - - - - 49+000 49+155 - - - - - - (ii) Public Health utilities (Water/Sewage Pipelines) * The site includes the following Public Health utilities: - Design Chainage (Km) Bore Well with Pump (Nos.) Tube well/Handpump (Nos.) Water Pipe Line (Nos.) Well (Nos.) Water Tank/Over Head Tank (Nos.) From To LHS RHS LHS RHS LHS RHS LHS RHS Total 0 0 0 0 0 0 0 0 0 35+000 35+500 - - - - - - - - - 35+500 36+000 - - - - - - - - - 36+000 36+500 - - - - - - - - - 36+500 37+000 - - - - - - - - - 37+000 37+500 - - - - - - - - - 37+500 38+000 - - - - - - - - - 38+000 38+500 - - - - - - - - - 38+500 39+000 - - - - - - - - - 39+000 39+500 - - - - - - - - - 39+500 40+000 - - - - - - - - - 40+000 40+500 - - - - - - - - -
  • 7. Schedule - A Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 7 Design Chainage (Km) Bore Well with Pump (Nos.) Tube well/Handpump (Nos.) Water Pipe Line (Nos.) Well (Nos.) Water Tank/Over Head Tank (Nos.) From To LHS RHS LHS RHS LHS RHS LHS RHS Total 0 0 0 0 0 0 0 0 0 40+500 41+000 - - - - - - - - - 41+000 41+500 - - - - - - - - - 41+500 42+000 - - - - - - - - - 42+000 42+500 - - - - - - - - - 42+500 43+000 - - - - - - - - - 43+000 43+500 - - - - - - - - - 43+500 44+000 - - - - - - - - - 44+000 44+500 - - - - - - - - - 44+500 45+000 - - - - - - - - - 45+000 45+500 - - - - - - - - - 45+500 46+000 - - - - - - - - - 46+000 46+500 - - - - - - - - - 46+500 47+000 - - - - - - - - - 47+000 47+500 - - - - - - - - - 47+500 48+000 - - - - - - - - - 48+000 48+500 - - - - - - - - - 48+500 49+000 - - - - - - - - - 49+000 49+155 - - - - - - - - -
  • 8. Schedule - A Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 8 Appendix A-I (Schedule-A) INDEX MAP / LOCATION MAP OF PROJECT HIGHWAY
  • 9. Schedule - A Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 9 Appendix A-II (Schedule-A) PROJECT CENTER LINE COORDINATES The proposed Greenfield alignment commencing from Autarpur Village at km 35.000 in Pratapgarh District in the State of Uttar Pradesh and ends near Singraur Uparhar village of Prayagraj District section NH-731A in the State of Uttar Pradesh at km 49.155. Coordinate System - Universal Transverse Mercator (UTM)-WGS84 (Zone 44R) Sr. No Design Chainage (km) Easting Northing 1 35000 562654.6 2843498 2 35020 562639.7 2843485 3 35040 562625 2843472 4 35060 562610.5 2843458 5 35080 562596.7 2843443 6 35100 562583.5 2843428 7 35120 562571.2 2843413 8 35140 562559.8 2843396 9 35160 562549.3 2843379 10 35180 562539.8 2843361 11 35200 562531.3 2843343 12 35220 562523.7 2843325 13 35240 562517.3 2843306 14 35260 562511.9 2843287 15 35280 562507.5 2843267 16 35300 562504.3 2843247 17 35320 562502.1 2843228 18 35340 562500.8 2843208 19 35360 562500.1 2843188 20 35380 562499.7 2843168 21 35400 562499.4 2843148 22 35420 562499.1 2843128 23 35440 562498.8 2843108 24 35460 562498.5 2843088 25 35480 562498.2 2843068 26 35500 562497.8 2843048 27 35520 562497.5 2843028 28 35540 562497.2 2843008 29 35560 562496.9 2842988 30 35580 562496.6 2842968 31 35600 562496.2 2842948 32 35620 562495.9 2842928 Sr. No Design Chainage (km) Easting Northing 33 35640 562495.6 2842908 34 35660 562495.3 2842888 35 35680 562495 2842868 36 35700 562494.7 2842848 37 35720 562494.3 2842828 38 35740 562494 2842808 39 35760 562493.7 2842788 40 35780 562493.4 2842768 41 35800 562493.1 2842748 42 35820 562492.7 2842728 43 35840 562492.4 2842708 44 35860 562492.1 2842688 45 35880 562491.8 2842668 46 35900 562491.5 2842648 47 35920 562491.1 2842628 48 35940 562490.8 2842608 49 35960 562490.5 2842588 50 35980 562490.2 2842568 51 36000 562489.9 2842548 52 36020 562489.6 2842528 53 36060 562488.9 2842488 54 36080 562488.6 2842468 55 36100 562488.3 2842448 56 36120 562488 2842428 57 36140 562487.7 2842408 58 36160 562487.7 2842388 59 36180 562488.1 2842368 60 36200 562489 2842348 61 36220 562490.6 2842328 62 36240 562492.8 2842308 63 36260 562495.7 2842288 64 36280 562499.3 2842268
  • 10. Schedule - A Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 10 Sr. No Design Chainage (km) Easting Northing 65 36300 562503.5 2842249 66 36320 562508.3 2842229 67 36340 562513.4 2842210 68 36360 562518.8 2842191 69 36380 562524.2 2842172 70 36400 562529.7 2842152 71 36420 562535.1 2842133 72 36440 562540.6 2842114 73 36460 562546 2842095 74 36480 562551.4 2842075 75 36500 562556.9 2842056 76 36520 562562.3 2842037 77 36540 562567.7 2842018 78 36560 562573.2 2841998 79 36580 562578.6 2841979 80 36600 562584.1 2841960 81 36620 562589.5 2841941 82 36640 562594.9 2841921 83 36660 562600.4 2841902 84 36680 562605.8 2841883 85 36700 562611.2 2841864 86 36720 562616.7 2841844 87 36740 562622.1 2841825 88 36760 562627.6 2841806 89 36780 562633 2841787 90 36800 562638.4 2841767 91 36820 562643.9 2841748 92 36840 562649.3 2841729 93 36860 562654.8 2841710 94 36880 562660.2 2841690 95 36900 562665.6 2841671 96 36920 562671.1 2841652 97 36940 562676.5 2841633 98 36960 562681.9 2841613 99 36980 562687.4 2841594 100 37000 562692.8 2841575 101 37020 562698.3 2841556 102 37040 562703.7 2841536 103 37060 562709.1 2841517 104 37080 562714.6 2841498 Sr. No Design Chainage (km) Easting Northing 105 37100 562720 2841479 106 37120 562725.4 2841460 107 37140 562730.9 2841440 108 37160 562736.3 2841421 109 37180 562741.8 2841402 110 37200 562747.2 2841383 111 37220 562752.6 2841363 112 37240 562758.1 2841344 113 37260 562763.5 2841325 114 37280 562769 2841306 115 37300 562774.4 2841286 116 37320 562779.8 2841267 117 37340 562785.3 2841248 118 37360 562790.6 2841229 119 37380 562795.6 2841209 120 37400 562800.1 2841190 121 37420 562804.1 2841170 122 37440 562807.4 2841150 123 37460 562810 2841131 124 37480 562812 2841111 125 37500 562813.4 2841091 126 37520 562814.2 2841071 127 37540 562814.8 2841051 128 37560 562815.1 2841031 129 37580 562815.5 2841011 130 37600 562815.9 2840991 131 37620 562816.2 2840971 132 37640 562816.6 2840951 133 37660 562816.9 2840931 134 37680 562817.3 2840911 135 37700 562817.7 2840891 136 37720 562818 2840871 137 37740 562818.4 2840851 138 37760 562818.7 2840831 139 37780 562819.1 2840811 140 37800 562819.5 2840791 141 37820 562819.8 2840771 142 37840 562820.2 2840751 143 37860 562820.5 2840731 144 37880 562820.9 2840711
  • 11. Schedule - A Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 11 Sr. No Design Chainage (km) Easting Northing 145 37900 562821.2 2840691 146 37920 562821.6 2840671 147 37940 562822 2840651 148 37960 562822.3 2840631 149 37980 562822.7 2840611 150 38000 562823 2840591 151 38020 562823.4 2840571 152 38040 562823.8 2840551 153 38060 562824.1 2840531 154 38080 562824.5 2840511 155 38100 562824.8 2840491 156 38120 562825.2 2840471 157 38140 562825.6 2840451 158 38160 562825.9 2840431 159 38180 562826.3 2840411 160 38200 562826.6 2840391 161 38220 562827 2840371 162 38240 562827.4 2840351 163 38260 562827.7 2840331 164 38280 562828.1 2840311 165 38300 562828.4 2840291 166 38320 562828.8 2840271 167 38340 562829.1 2840251 168 38360 562829.5 2840231 169 38380 562829.9 2840211 170 38400 562830.2 2840191 171 38420 562830.6 2840171 172 38440 562830.9 2840151 173 38460 562831.3 2840131 174 38480 562831.7 2840111 175 38500 562832 2840091 176 38520 562832.4 2840071 177 38540 562832.7 2840051 178 38560 562833.1 2840031 179 38580 562833.5 2840011 180 38600 562833.8 2839991 181 38620 562834.2 2839971 182 38640 562834.5 2839951 183 38660 562834.9 2839931 184 38680 562835.3 2839911 Sr. No Design Chainage (km) Easting Northing 185 38700 562835.6 2839891 186 38720 562836 2839871 187 38740 562836.3 2839851 188 38760 562836.7 2839831 189 38780 562837 2839811 190 38800 562837.4 2839791 191 38820 562837.8 2839771 192 38840 562838.1 2839751 193 38860 562838.5 2839731 194 38880 562838.8 2839711 195 38900 562839.2 2839691 196 38920 562839.6 2839671 197 38940 562839.9 2839651 198 38960 562840.3 2839631 199 38980 562840.6 2839611 200 39000 562841 2839591 201 39020 562841.4 2839571 202 39040 562841.7 2839551 203 39060 562842.1 2839531 204 39080 562842.4 2839511 205 39100 562842.8 2839491 206 39120 562843.1 2839471 207 39140 562843.5 2839451 208 39160 562843.9 2839431 209 39180 562844.3 2839411 210 39200 562844.8 2839391 211 39220 562845.8 2839371 212 39240 562847.2 2839351 213 39260 562849.3 2839331 214 39280 562852.1 2839311 215 39300 562855.5 2839292 216 39320 562859.5 2839272 217 39340 562864.2 2839253 218 39360 562869.5 2839233 219 39380 562875.3 2839214 220 39400 562881.4 2839195 221 39420 562887.6 2839176 222 39440 562893.8 2839157 223 39460 562900 2839138 224 39480 562906.2 2839119
  • 12. Schedule - A Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 12 Sr. No Design Chainage (km) Easting Northing 225 39500 562912.4 2839100 226 39520 562918.6 2839081 227 39540 562924.8 2839062 228 39560 562931 2839043 229 39580 562937.2 2839024 230 39600 562943.4 2839005 231 39620 562949.6 2838986 232 39640 562955.8 2838967 233 39660 562962 2838948 234 39680 562968.2 2838929 235 39700 562974.4 2838910 236 39720 562980.6 2838891 237 39740 562986.8 2838872 238 39760 562993 2838853 239 39780 562999.2 2838834 240 39800 563005.4 2838815 241 39820 563011.6 2838796 242 39840 563017.8 2838777 243 39860 563024 2838758 244 39880 563030.2 2838739 245 39900 563036.6 2838720 246 39920 563043.2 2838701 247 39940 563050.3 2838682 248 39960 563057.9 2838664 249 39980 563066.2 2838646 250 40000 563075.1 2838628 251 40020 563084.5 2838610 252 40040 563094.6 2838593 253 40060 563105.2 2838576 254 40080 563116.4 2838559 255 40100 563128.1 2838543 256 40120 563140.3 2838527 257 40140 563153.1 2838512 258 40160 563166.4 2838497 259 40180 563180.1 2838482 260 40200 563194.4 2838468 261 40220 563209.1 2838455 262 40240 563224 2838441 263 40260 563239.2 2838428 264 40280 563254.4 2838415 Sr. No Design Chainage (km) Easting Northing 265 40300 563269.6 2838402 266 40320 563284.9 2838389 267 40340 563300.1 2838377 268 40360 563315.3 2838364 269 40380 563330.6 2838351 270 40400 563345.8 2838338 271 40420 563361 2838325 272 40440 563376.3 2838312 273 40460 563391.5 2838299 274 40480 563406.7 2838286 275 40500 563422 2838273 276 40520 563437.2 2838260 277 40540 563452.4 2838247 278 40560 563467.7 2838234 279 40580 563482.9 2838221 280 40600 563498.1 2838208 281 40620 563513.4 2838195 282 40640 563528.6 2838182 283 40660 563543.8 2838169 284 40680 563559.1 2838156 285 40700 563574.3 2838143 286 40720 563589.5 2838130 287 40740 563604.8 2838117 288 40760 563620 2838104 289 40780 563635.2 2838091 290 40800 563650.5 2838078 291 40820 563665.7 2838065 292 40840 563680.9 2838053 293 40860 563696.2 2838040 294 40880 563711.4 2838027 295 40900 563726.6 2838014 296 40920 563741.9 2838001 297 40940 563757.1 2837988 298 40960 563772.3 2837975 299 40980 563787.6 2837962 300 41000 563802.8 2837949 301 41020 563818 2837936 302 41040 563833.3 2837923 303 41060 563848.5 2837910 304 41080 563863.7 2837897
  • 13. Schedule - A Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 13 Sr. No Design Chainage (km) Easting Northing 305 41100 563879 2837884 306 41120 563894.2 2837871 307 41140 563909.4 2837858 308 41160 563924.7 2837845 309 41180 563939.9 2837832 310 41200 563955.1 2837819 311 41220 563970.4 2837806 312 41240 563985.6 2837793 313 41260 564000.8 2837780 314 41280 564016.1 2837767 315 41300 564031.3 2837754 316 41320 564046.5 2837741 317 41340 564061.4 2837728 318 41360 564076.2 2837715 319 41380 564090.7 2837701 320 41400 564105.1 2837687 321 41420 564119.1 2837673 322 41440 564133 2837658 323 41460 564146.6 2837644 324 41480 564159.9 2837629 325 41500 564173 2837614 326 41520 564185.8 2837598 327 41540 564198.4 2837583 328 41560 564210.7 2837567 329 41580 564222.8 2837551 330 41600 564234.6 2837535 331 41620 564246.1 2837519 332 41640 564257.4 2837502 333 41660 564268.3 2837485 334 41680 564279 2837468 335 41700 564289.4 2837451 336 41720 564299.5 2837434 337 41740 564309.4 2837417 338 41760 564318.9 2837399 339 41780 564328.2 2837381 340 41800 564337.1 2837363 341 41820 564345.8 2837345 342 41840 564354.1 2837327 343 41860 564362.2 2837309 344 41880 564369.9 2837290 Sr. No Design Chainage (km) Easting Northing 345 41900 564377.3 2837272 346 41920 564384.4 2837253 347 41940 564391.2 2837234 348 41960 564397.7 2837215 349 41980 564403.9 2837196 350 42000 564409.8 2837177 351 42020 564415.3 2837158 352 42040 564420.5 2837139 353 42060 564425.4 2837119 354 42080 564430 2837100 355 42100 564434.2 2837080 356 42120 564438.1 2837061 357 42140 564441.7 2837041 358 42160 564445 2837021 359 42180 564447.9 2837002 360 42200 564450.5 2836982 361 42220 564452.8 2836962 362 42240 564454.8 2836942 363 42260 564456.4 2836922 364 42280 564457.6 2836902 365 42300 564458.6 2836882 366 42320 564459.2 2836862 367 42340 564459.5 2836842 368 42360 564459.4 2836822 369 42380 564459 2836802 370 42400 564458.3 2836782 371 42420 564457.3 2836762 372 42440 564455.9 2836742 373 42460 564454.1 2836722 374 42480 564452.1 2836702 375 42500 564449.7 2836683 376 42520 564447 2836663 377 42540 564444 2836643 378 42560 564440.6 2836623 379 42580 564437.1 2836604 380 42600 564433.5 2836584 381 42620 564429.9 2836564 382 42640 564426.3 2836545 383 42660 564422.7 2836525 384 42680 564419.1 2836505
  • 14. Schedule - A Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 14 Sr. No Design Chainage (km) Easting Northing 385 42700 564415.6 2836486 386 42720 564412 2836466 387 42740 564408.4 2836446 388 42760 564404.8 2836426 389 42780 564401.2 2836407 390 42800 564397.6 2836387 391 42820 564394.1 2836367 392 42840 564390.5 2836348 393 42860 564386.9 2836328 394 42880 564383.3 2836308 395 42900 564379.7 2836289 396 42920 564376.1 2836269 397 42940 564372.6 2836249 398 42960 564369 2836230 399 42980 564365.4 2836210 400 43000 564361.8 2836190 401 43020 564358.2 2836171 402 43040 564354.6 2836151 403 43060 564351.1 2836131 404 43080 564347.5 2836112 405 43100 564343.9 2836092 406 43120 564340.3 2836072 407 43140 564336.7 2836053 408 43160 564333.1 2836033 409 43180 564329.6 2836013 410 43200 564326 2835994 411 43220 564322.4 2835974 412 43240 564318.8 2835954 413 43260 564315.2 2835935 414 43280 564311.6 2835915 415 43300 564308.1 2835895 416 43320 564304.5 2835876 417 43340 564300.9 2835856 418 43360 564297.3 2835836 419 43380 564293.7 2835817 420 43400 564290.1 2835797 421 43420 564286.6 2835777 422 43440 564283 2835757 423 43460 564279.4 2835738 424 43480 564275.8 2835718 Sr. No Design Chainage (km) Easting Northing 425 43500 564272.2 2835698 426 43520 564268.6 2835679 427 43540 564265.1 2835659 428 43560 564261.5 2835639 429 43580 564257.9 2835620 430 36060 562488.9 2842488 431 43600 564254.3 2835600 432 43620 564250.7 2835580 433 43640 564247.1 2835561 434 43660 564243.6 2835541 435 43680 564240 2835521 436 43700 564236.4 2835502 437 43720 564232.8 2835482 438 43740 564229.2 2835462 439 43760 564225.6 2835443 440 43780 564222.1 2835423 441 43800 564218.5 2835403 442 43820 564214.9 2835384 443 43840 564211.3 2835364 444 43860 564207.7 2835344 445 43880 564204.2 2835325 446 43900 564200.6 2835305 447 43920 564197 2835285 448 43940 564193.4 2835266 449 43960 564189.8 2835246 450 43980 564186.2 2835226 451 44000 564182.7 2835207 452 44020 564179.1 2835187 453 44040 564175.5 2835167 454 44060 564171.9 2835148 455 44080 564168.3 2835128 456 44100 564164.7 2835108 457 44120 564161.2 2835088 458 44140 564157.6 2835069 459 44160 564154 2835049 460 44180 564150.4 2835029 461 44200 564146.9 2835010 462 44220 564143.5 2834990 463 44240 564140.4 2834970 464 44260 564137.7 2834950
  • 15. Schedule - A Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 15 Sr. No Design Chainage (km) Easting Northing 465 44280 564135.4 2834931 466 44300 564133.5 2834911 467 44320 564132.1 2834891 468 44340 564131 2834871 469 44360 564130.3 2834851 470 44380 564130 2834831 471 44400 564130.1 2834811 472 44420 564130.6 2834791 473 44440 564131.6 2834771 474 44460 564132.9 2834751 475 44480 564134.6 2834731 476 44500 564136.7 2834711 477 44520 564139.2 2834691 478 44540 564142.1 2834671 479 44560 564145.4 2834652 480 44580 564149.1 2834632 481 44600 564153.2 2834612 482 44620 564157.7 2834593 483 44640 564162.5 2834574 484 44660 564167.8 2834554 485 44680 564173.4 2834535 486 44700 564179.4 2834516 487 44720 564185.8 2834497 488 44740 564192.6 2834478 489 44760 564199.8 2834460 490 44780 564207.3 2834441 491 44800 564215.2 2834423 492 44820 564223.4 2834404 493 44840 564232.1 2834386 494 44860 564241 2834369 495 44880 564250.4 2834351 496 44900 564260.1 2834333 497 44920 564270.1 2834316 498 44940 564280.5 2834299 499 44960 564291.2 2834282 500 44980 564302.3 2834265 501 45000 564313.6 2834249 502 45020 564325.4 2834233 503 45040 564337.4 2834217 504 45060 564349.7 2834201 Sr. No Design Chainage (km) Easting Northing 505 45080 564362.4 2834186 506 45100 564375.4 2834170 507 45120 564388.7 2834155 508 45140 564402.2 2834141 509 45160 564416.1 2834126 510 45180 564430.2 2834112 511 45200 564444.7 2834098 512 45220 564459.4 2834085 513 45240 564474.3 2834071 514 45260 564489.6 2834059 515 45280 564505.1 2834046 516 45300 564520.8 2834033 517 45320 564536.6 2834021 518 45340 564552.5 2834009 519 45360 564568.4 2833997 520 45380 564584.3 2833985 521 45400 564600.2 2833973 522 45420 564616 2833961 523 45440 564631.9 2833948 524 45460 564647.8 2833936 525 45480 564663.7 2833924 526 45500 564679.6 2833912 527 45520 564695.5 2833900 528 45540 564711.4 2833888 529 45560 564727.3 2833876 530 45580 564743.2 2833863 531 45600 564759 2833851 532 45620 564774.9 2833839 533 45640 564790.8 2833827 534 45660 564806.7 2833815 535 45680 564822.6 2833803 536 45700 564838.5 2833790 537 45720 564854.4 2833778 538 45740 564870.3 2833766 539 45760 564886.1 2833754 540 45780 564902 2833742 541 45800 564917.9 2833730 542 45820 564933.8 2833718 543 45840 564949.7 2833705 544 45860 564965.6 2833693
  • 16. Schedule - A Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 16 Sr. No Design Chainage (km) Easting Northing 545 45880 564981.5 2833681 546 45900 564997.3 2833669 547 45920 565013.1 2833657 548 45940 565028.7 2833644 549 45960 565044 2833631 550 45980 565059 2833618 551 46000 565073.7 2833604 552 46020 565087.9 2833590 553 46040 565101.9 2833576 554 46060 565115.5 2833561 555 46080 565128.7 2833546 556 46100 565141.5 2833531 557 46120 565153.9 2833515 558 46140 565166 2833499 559 46160 565177.6 2833483 560 46180 565188.9 2833467 561 46200 565199.7 2833450 562 46220 565210.1 2833433 563 46240 565220 2833415 564 46260 565229.6 2833398 565 46280 565238.6 2833380 566 46300 565247.3 2833362 567 46320 565255.4 2833344 568 46340 565263.2 2833325 569 46360 565270.4 2833307 570 46380 565277.2 2833288 571 46400 565283.5 2833269 572 46420 565289.4 2833250 573 46440 565294.7 2833230 574 46460 565299.6 2833211 575 46480 565304 2833192 576 46500 565307.9 2833172 577 46520 565311.3 2833152 578 46540 565314.2 2833132 579 46560 565316.6 2833113 580 46580 565318.6 2833093 581 46600 565320 2833073 582 46620 565320.9 2833053 583 46640 565321.3 2833033 584 46660 565321.3 2833013 Sr. No Design Chainage (km) Easting Northing 585 46680 565320.7 2832993 586 46700 565319.6 2832973 587 46720 565318.1 2832953 588 46740 565316 2832933 589 46760 565313.4 2832913 590 46780 565310.4 2832893 591 46800 565306.8 2832874 592 46820 565302.8 2832854 593 46840 565298.2 2832835 594 46860 565293.2 2832815 595 46880 565287.7 2832796 596 46900 565281.7 2832777 597 46920 565275.3 2832758 598 46940 565268.3 2832739 599 46960 565260.9 2832721 600 46980 565253.1 2832702 601 47000 565244.8 2832684 602 47020 565236 2832666 603 47040 565226.8 2832648 604 47060 565217.1 2832631 605 47080 565207.1 2832614 606 47100 565196.6 2832597 607 47120 565185.8 2832580 608 47140 565174.9 2832563 609 47160 565163.9 2832546 610 47180 565153 2832529 611 47200 565142.1 2832513 612 47220 565131.1 2832496 613 47240 565120.2 2832479 614 47260 565109.3 2832462 615 47280 565098.3 2832446 616 47300 565087.4 2832429 617 47320 565076.5 2832412 618 47340 565065.5 2832395 619 47360 565054.6 2832379 620 47380 565043.6 2832362 621 47400 565032.7 2832345 622 47420 565021.8 2832328 623 47440 565010.8 2832312 624 47460 564999.9 2832295
  • 17. Schedule - A Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 17 Sr. No Design Chainage (km) Easting Northing 625 47480 564989 2832278 626 47500 564978 2832261 627 47520 564967.1 2832245 628 47540 564956.2 2832228 629 47560 564945.2 2832211 630 47580 564934.3 2832195 631 47600 564923.3 2832178 632 47620 564912.4 2832161 633 47640 564901.5 2832144 634 47660 564890.5 2832128 635 47680 564879.6 2832111 636 47700 564868.7 2832094 637 47720 564857.7 2832077 638 47740 564846.8 2832061 639 47760 564835.9 2832044 640 47780 564824.9 2832027 641 47800 564814 2832010 642 47820 564803.1 2831994 643 47840 564792.1 2831977 644 47860 564781.2 2831960 645 47880 564770.2 2831943 646 47900 564759.3 2831927 647 47920 564748.4 2831910 648 47940 564737.4 2831893 649 47960 564726.5 2831876 650 47980 564715.6 2831860 651 48000 564704.6 2831843 652 48020 564693.7 2831826 653 48040 564682.8 2831809 654 48060 564671.8 2831793 655 48080 564660.9 2831776 656 48100 564649.9 2831759 657 48120 564639 2831742 658 48140 564628.1 2831726 659 48160 564617.1 2831709 660 48180 564606.2 2831692 661 48200 564595.3 2831675 662 48220 564584.3 2831659 663 48240 564573.4 2831642 664 48260 564562.5 2831625 Sr. No Design Chainage (km) Easting Northing 665 48280 564551.5 2831608 666 48300 564540.6 2831592 667 48320 564529.7 2831575 668 48340 564518.7 2831558 669 48360 564507.8 2831541 670 48380 564496.8 2831525 671 48400 564485.9 2831508 672 48420 564475 2831491 673 48440 564464 2831474 674 48460 564453 2831458 675 48480 564441.7 2831441 676 48500 564430.2 2831425 677 48520 564418.6 2831409 678 48540 564406.9 2831392 679 48560 564395.3 2831376 680 48580 564383.7 2831360 681 48600 564372 2831344 682 48620 564360.4 2831327 683 48640 564348.7 2831311 684 48660 564337.1 2831295 685 48680 564325.4 2831279 686 48700 564313.8 2831262 687 48720 564302.1 2831246 688 48740 564290.5 2831230 689 48760 564278.9 2831213 690 48780 564267.2 2831197 691 48800 564255.6 2831181 692 48820 564243.9 2831165 693 48840 564232.3 2831148 694 48860 564220.6 2831132 695 48880 564209 2831116 696 48900 564197.4 2831100 697 48920 564185.7 2831083 698 48940 564174.1 2831067 699 48960 564162.4 2831051 700 48980 564150.8 2831035 701 49000 564139.1 2831018 702 49020 564127.5 2831002 703 49040 564115.9 2830986 704 49060 564104.2 2830970
  • 18. Schedule - A Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 18 Sr. No Design Chainage (km) Easting Northing 705 49080 564092.6 2830953 706 49100 564080.9 2830937 707 49120 564069.3 2830921 Sr. No Design Chainage (km) Easting Northing 708 49140 564057.6 2830905 709 49160 564046 2830888
  • 19. Schedule - B Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 19 SCHEDULE – B (See Clause 2.1) DEVELOPMENT OF THE PROJECT HIGHWAY 1 Development of the Project Highway Development of the Project Highway shall include construction of the Project Highway as described in this Schedule-B and in Schedule-C. 2 Project Highway (Four Lane) 2.1 Four Laning shall include construction of the Four Lane Project Highway as described in Annex-I of this Schedule-B and Annex-I of Schedule C. 2.2 The Project Highway shall be designed and constructed in conformity with the specifications and standards set forth in Annex-I of Schedule-D.
  • 20. Schedule - B Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 20 ANNEX – I (Schedule-B) Description of Four Laning 1. The Project Proposal 1.1 Construction of Four-Lane Greenfield highway with paved shoulders from Chainage Km 35.000 to Km 49.155 of NH-731A shall be undertaken as per Ministry’s Codes & specifications and terms specified in Schedules. 2. Project Facilities Project facilities shall be constructed in conformity with Annex-I of Schedule-C. 3. Specifications and Standards The Project Highways shall be constructed in conformity with the Specifications and Standards specified in Schedule-D. 4. Other Features of Project Highway 4.1 Geometric Design and General Features Geometric design and General Features of the Project Highway shall be in conformity with the Specifications and Standards specified in Schedule-D. 4.2 Design Speed Design Speed of the Project Highway shall be in conformity with the Specifications and Standards specified in Schedule-D. 4.3 Vertical Gradient Vertical Gradient of the Project Highway shall be in conformity with the Specifications and Standards specified in Schedule-D. 4.4 Right of Way (ROW) Details of the proposed Right of Way are given below: Sr. No Proposed Chainage (km) Right of Way (m) Remarks From To 1 35.000 49.155 45/ 60* Green field *60m RoW is proposed at locations of structures including VUPS/ROB & Interchanges. 4.5 Type of Shoulders Shoulders on the Project Highway shall be in conformity with the Specifications and Standards specified in Schedule-D. 4.6 Lateral and Vertical Clearances at Flyovers/Underpasses/Interchanges: As per Schedule D. 4.7 Cross Sections The Project Highway shall be constructed to Four lane with paved shoulder standards. Typical cross-sections (TCS) have been as given under Appendix B-II. Schedule of applicable cross-
  • 21. Schedule - B Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 21 sections are given below. Concessionaire is free to use new/ alternative material & technology in construction of highway as per Ministry’s circular RW/Nh-33044/18/2020-S&R(P&B) dated 14.12.2020. However, w.r.t TCS-1A Geocell Technology shall be compulsory on pilot basis in the given section. Sr. No Design Chainage (Km) Length (m) TCS Description Provision Total Width (m) TCS From To 1 35000 35963 963 4-lane (2x2) carriageway +2.5m paved shoulder+1.5m earthen shoulder on either side with median 5.0m, Fig 2.4 of IRC: SP-84 2019 Road 27 TCS-1 - 2 35963 35988 25 6-lane (3x3) with 10.50m width with 3.0m wide median + 1.5m footpath both sides, Fig. 7.2A of IRC: SP-84 2019 Minor Bridge 28.9 TCS-5 - 3 35988 36220 232 6-lane (3x3) carriageway 10.5m width with 3.00m median along with Service cum slip road 5.5m wide + 1.5m footpath cum drain on both sides, Approach to VUP 43.5 TCS-2 - 4 36220 36240 20 6-lane (3x3) 10.50m carriageway width with 3.0m median VUP 25 TCS-3 Deviation to Fig. 7.8 of Manual 5 36240 36460 220 6-lane (3x3) carriageway 10.5m width with 3.00m median along with Service cum slip road 5.5m wide + 1.5m footpath cum drain on both sides Approach to VUP 43.5 TCS-2 - 6 36460 37265 805 4-lane (2x2) carriageway +2.5m paved shoulder+1.5m earthen shoulder on either side with median 5.0m, Fig 2.4 of IRC: SP-84 2019 Road 27 TCS-1 - 7 37265 37560 295 6-lane (3x3) carriageway 10.5m width with 3.00m median along with Service cum slip road 5.5m wide + 1.5m footpath cum drain on both sides Approach to VUP 43.5 TCS-2 - 8 37560 37580 20 6-lane (3x3) 10.50m carriageway width with 3.0m median VUP 25 TCS-3 Deviation to Fig. 7.8 of Manual
  • 22. Schedule - B Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 22 Sr. No Design Chainage (Km) Length (m) TCS Description Provision Total Width (m) TCS From To 9 37580 37870 290 6-lane (3x3) carriageway 10.5m width with 3.00m median along with Service cum slip road 5.5m wide + 1.5m footpath cum drain on both sides Approach to VUP 43.5 TCS-2 - 10 37870 38785 915 4-lane (2x2) carriageway +2.5m paved shoulder+1.5m earthen shoulder on either side with median 5.0m, Fig 2.4 of IRC: SP-84 2019 Road 27 TCS-1 - 11 38785 38875 90 6-lane (3x3) with 10.50m width with 3.0m wide median + 1.5m footpath both sides, Fig. 7.2A of IRC: SP-84 2019 Major Bridge 28.9 TCS-5 - 12 38875 39648 773 4-lane (2x2) carriageway +2.5m paved shoulder+1.5m earthen shoulder on either side with median 5.0m, Fig 2.4 of IRC: SP-84 2019 Road 27 TCS-1 - 13 39648 39673 25 6-lane (3x3) with 10.50m width with 3.0m wide median + 1.5m footpath both sides, Fig. 7.2A of IRC: SP-84 2019 Minor Bridge 28.9 TCS-5 - 14 39673 41840 2167 4-lane (2x2) carriageway +2.5m paved shoulder+1.5m earthen shoulder on either side with median 5.0m with Geocell in sub-base course, Fig 2.4 of IRC: SP-84 2019 Road 27 TCS-1A Geocell Technology is to be used compulsory. 15 41840 42060 220 6-lane(3x3) carriageway 10.5m width with 3.00m median along with Service cum slip road 5.5m wide + 1.5m footpath cum drain on both sides Approach to VUP 43.5 TCS-2 - 16 42060 42080 20 6-lane (3x3) 10.50m carriageway width with 3.0m median VUP 25 TCS-3 Deviation to Fig. 7.8 of Manual 17 42080 42870 790 6-lane(3x3) carriageway 10.5m width with 3.00m Approach to VUP 43.5 TCS-2 -
  • 23. Schedule - B Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 23 Sr. No Design Chainage (Km) Length (m) TCS Description Provision Total Width (m) TCS From To median along with Service cum slip road 5.5m wide + 1.5m footpath cum drain on both sides 18 42870 42890 20 6-lane (3x3) 10.50m carriageway width with 3.0m median VUP 25 TCS-3 Deviation to Fig. 7.8 of Manual 19 42890 43146 256 6-lane(3x3) carriageway 10.5m width with 3.00m median along with Service cum slip road 5.5m wide + 1.5m footpath cum drain on both sides Approach to VUP 43.5 TCS-2 - 20 43146 43497 351 9.50m carriageway width + 1.5m footpath with 3.0m median along with Service cum slip road 5.5m wide + 1.5m footpath cum drain on both sides Approach to ROB 47.57 TCS-4 - 21 43497 43623 126 As per RDSO 9.50m carriageway width + 1.5m footpath with 3.0m median ROB 27 TCS-5A - 22 43623 43840 217 9.50m carriageway width + 1.5m footpath with 3.0m median along with Service cum slip road 5.5m wide + 1.5m footpath cum drain on both sides Approach to ROB 47.57 TCS-4 - 23 43840 43850 10 9.50m carriageway width + 1.5m footpath with 3.0m median along with Service cum slip road 5.5m wide + 1.5m footpath cum drain on both sides Minor Bridge on Approach of ROB 47.57 TCS-4 - 24 43850 43986 136 9.50m carriageway width + 1.5m footpath with 3.0m median along with Service cum slip road 5.5m wide + 1.5m footpath cum drain on both sides Approach to ROB 47.57 TCS-4 - 25 43986 44035 49 6-lane(3x3) carriageway 10.5m width with 3.00m median along with Service cum slip road Approach to VUP 43.5 TCS-2 -
  • 24. Schedule - B Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 24 Sr. No Design Chainage (Km) Length (m) TCS Description Provision Total Width (m) TCS From To 5.5m wide + 1.5m footpath cum drain on both sides 26 44035 44055 20 6-lane (3x3) 10.50m carriageway width with 3.0m median VUP 25 TCS-3 Deviation to Fig. 7.8 of Manual 27 44055 44250 195 6-lane(3x3) carriageway 10.5m width with 3.00m median along with Service cum slip road 5.5m wide + 1.5m footpath cum drain on both sides Approach to VUP 43.5 TCS-2 - 28 44250 44375 125 4-lane (2x2) carriageway +2.5m paved shoulder+1.5m earthen shoulder on either side with median 5.0m, Fig 2.4 of IRC: SP-84 2019 Road 27 TCS-1 - 29 44375 44385 10 6-lane (3x3) with 10.50m width with 3.0m wide median + 1.5m footpath both sides, Fig. 7.2A of IRC: SP-84 2019 Minor Bridge 28.9 TCS-5 - 30 44385 44615 230 4-lane (2x2) carriageway +2.5m paved shoulder+1.5m earthen shoulder on either side with median 5.0m, Fig 2.4 of IRC: SP-84 2019 Road 27 TCS-1 - 31 44615 44625 10 6-lane (3x3) with 10.50m width with 3.0m wide median + 1.5m footpath both sides, Fig. 7.2A of IRC: SP-84 2019 Minor Bridge 28.9 TCS-5 - 32 44625 44825 200 4-lane (2x2) carriageway +2.5m paved shoulder+1.5m earthen shoulder on either side with median 5.0m, Fig 2.4 of IRC: SP-84 2019 Road 27 TCS-1 - 33 44825 44835 10 6-lane (3x3) with 10.50m width with 3.0m wide median + 1.5m footpath both sides, Fig. 7.2A of IRC: SP-84 2019 Minor Bridge 28.9 TCS-5 - 34 44835 45294 459 4-lane (2x2) carriageway +2.5m paved shoulder+1.5m earthen shoulder on Road 27 TCS-1 -
  • 25. Schedule - B Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 25 Sr. No Design Chainage (Km) Length (m) TCS Description Provision Total Width (m) TCS From To either side with median 5.0m, Fig 2.4 of IRC: SP-84 2019 35 45294 45306 12 6-lane (3x3) with 10.50m width with 3.0m wide median + 1.5m footpath both sides, Fig. 7.2A of IRC: SP-84 2019 Minor Bridge 28.9 TCS-5 - 36 45306 45534 228 4-lane (2x2) carriageway +2.5m paved shoulder+1.5m earthen shoulder on either side with median 5.0m, Fig 2.4 of IRC: SP-84 2019 Road 27 TCS-1 - 37 45534 45546 12 6-lane (3x3) with 10.50m width with 3.0m wide median + 1.5m footpath both sides, Fig. 7.2A of IRC: SP-84 2019 Minor Bridge 28.9 TCS-5 - 38 45546 46640 1094 4-lane (2x2) carriageway +2.5m paved shoulder+1.5m earthen shoulder on either side with median 5.0m, Fig 2.4 of IRC: SP-84 2019 Road 27 TCS-1 - 39 46640 46660 20 6-lane (3x3) with 10.50m width with 3.0m wide median + 1.5m footpath both sides, Fig. 7.2A of IRC: SP-84 2019 Minor Bridge 28.9 TCS-5 - 40 46660 46920 260 4-lane (2x2) carriageway +2.5m paved shoulder+1.5m earthen shoulder on either side with median 5.0m, Fig 2.4 of IRC: SP-84 2019 Road 27 TCS-1 - 41 46920 47260 340 6-lane(3x3) carriageway 10.5m width with 3.00m median along with Service cum slip road 5.5m wide + 1.5m footpath cum drain on both sides Approach to Diamond Interchange on NH-24B 43.5 TCS-2 - 42 47260 47320 60 6-lane (3x3) 10.50m carriageway width with 3.0m median Flyover 25 TCS-3 Deviation to Fig. 7.8 of Manual 43 47320 47645 325 6-lane(3x3) carriageway 10.5m width with 3.00m median along with Approach to Diamond Interchange of NH-24B 43.5 TCS-2 -
  • 26. Schedule - B Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 26 Sr. No Design Chainage (Km) Length (m) TCS Description Provision Total Width (m) TCS From To Service cum slip road 5.5m wide + 1.5m footpath cum drain on both sides 44 47645 48240 595 4-lane (2x2) carriageway +2.5m paved shoulder+1.5m earthen shoulder on either side with median 5.0m, Fig 2.4 of IRC: SP-84 2019 Road 27 TCS-1 - 45 48240 48260 20 6-lane (3x3) with 10.50m width with 3.0m wide median + 1.5m footpath both sides, Fig. 7.2A of IRC: SP-84 2019 Minor Bridge 28.9 TCS-5 - 46 48260 48643 383 6-lane(3x3) carriageway 10.5m width with 3.00m median along with Service cum slip road 5.5m wide + 1.5m footpath cum drain on both sides Approach to Diamond Interchange on NH-19 43.5 TCS-2 - 47 48643 48728 85 6-lane (3x3) 10.50m carriageway width with 3.0m median Flyover 25 TCS-3 Deviation to Fig. 7.8 of Manual 48 48728 49115 387 6-lane(3x3) carriageway 10.5m width with 3.00m median along with Service cum slip road 5.5m wide + 1.5m footpath cum drain on both sides Approach to Diamond Interchange on NH-19 43.5 TCS-2 - 49 49115 49135 20 6-lane (3x3) 10.50m carriageway width with 3.0m median VUP 25 TCS-3 Deviation to Fig. 7.8 of Manual 50 49135 49155 20 4-lane (2x2) carriageway +2.5m paved shoulder+1.5m earthen shoulder on either side with median 5.0m, Fig 2.4 of IRC: SP-84 2019 Road 27 TCS-1 - TCS-1 6667 TCS-1A 2167 TCS-2 3982 TCS-3 265 TCS-4 714 TCS-5 234 TCS-5A 126 Total 14155
  • 27. Schedule - B Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 27 Notes: (i) Any variation in design length of respective TCS specified in Schedule B shall not constitute a change of scope, save and except any variations in the design length arising out of a change of scope expressly undertaken in accordance with the provisions of Article 16. 4.8 Alignment Plan and Longitudinal Section An alignment Plan and longitudinal section (Plan & Profile) of the project highway are enclosed at Appendix B-I in soft copy for reference only. Longitudinal profile shall be designed based on Schedule-D. Finished Road level indicated in the alignment plan is minimum. The Concessionaire shall design the road profile of the project highway based on site/design requirement specified in Schedule-D. 5. Bypass and new Realignment NIL 6 Service cum slip Roads A. Interchange elements: Ramps/ Loops/ Merged Sections/ Roundabouts Interchange has been proposed at km 47.290 and km 48.685. A GAD is attached under Appendix- B-III. Notes: (i) Detailed design of all interchange shall be in accordance with Schedule-D. Service road shall be provided as per para 4.7- Cross-sections of this Schedule. 7. Pavement Design Design of pavement shall be done for design period of 20 years, in accordance with the Schedule- D and IRC-37:2018. Concessionaire is free to use new/ alternative material & technology in construction of highway as per MoRTH circular RW/NH-33044/18/2020-S&R(P&B) dated 14.12.2020 7.1 Design Traffic Pavement design shall be carried out for the minimum design traffic of 120 MSA for entire project highway with design life of 20 years as IRC: 37:2018. 7.5 Intersection / Interchanges Intersection / Interchanges on the Project Highway shall be in conformity with the Specifications and Standards specified in Schedule-D. At-Grade Intersections 8.1 Major Junction S No. Proposed Chainage (km) Side(Left/Right) Type of Junction Destination 1 47.290 BHS X- JUNCTION NH – 24B
  • 28. Schedule - B Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 28 2 48.685 BHS X-JUNCTION NH-2 8.2 Minor Junction S No. Design Chainage (km) Side(Left / Right) Type of Junction Destination 1 36+230 BHS X-JUNCTION From Burhepur to Bihar 2 37+570 BHS X-JUNCTION From Bihar to Sakardaha 3 42+070 BHS X-JUNCTION Kurha Village Road 4 42+880 BHS X-JUNCTION From Lalgopalganj to Bendhan Gopalpur 5 44+045 BHS X-JUNCTION From Badupur to Barna 6 49+125 BHS X-JUNCTION From Meerjahapur to Sringverpur 9. Underpasses A) Vehicular Underpasses (VUP) Sr. No Location (Chainage) Km Type of Structure Span/ opening (m) 1 36+230 VUP 1 x 20 2 37+570 VUP 1 x 20 3 42+070 VUP 1 x 20 4 42+880 VUP 1 x 20 5 44+045 VUP 1 x 20 6 49+125 VUP 1 x 20 Note: Traffic Impact Attenuators shall be provided be provided at all VUPs as per Schedule-D. 10.1 Interchange structures/Grade Separator Interchange structure/grade separator structure to be provided as per the details below. Irrespective of span arrangement indicated, all the structures shall provide lateral and vertical clearances as per Schedule D. Sr. No Location Salient features Minimum length of viaduct to be provided Road to be carried over/under the structures 1 47.290 Diamond Interchange 2 x 30 Over the structure 2 48.685 Diamond Interchange 2 x 42.5 Over the structure Note: (i)GAD attached at Appendix B-III of Schedule-B. (ii)Noise Barrier shall be provided at both the interchanges as per Schedule-D. (iii) Traffic Impact Attenuators shall be provided be provided at both the interchanges as per Schedule-D. 10.2 Road Over Bridges (ROB) The Road Over Bridges (ROB) shall be provided as per the details below: Sr. No Chainage Road category Span Arrangement Skew Angle Structure Width Lateral clearance
  • 29. Schedule - B Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 29 km (m) deg (m) 1 43.560 - 3X36+1X18 21 As per TCS-5A As per GAD Attached Note: Traffic Impact Attenuators shall be provided at the ROB as per Schedule-D. 10.3 Major Bridges (A) Widening / Repair / Rehabilitation of Existing Major Bridges NIL (B) Reconstruction of Existing Major Bridges NIL (C) Construction of New Major Bridges on Main Carriageway (Over River / Streams /Nallah) Sr. No Chainage Category Span Arrangement Skew Angle Structure Width km (m) deg (m) 1 38.830 Canal 3 x 30 0 As per TCS-5 10.4 Minor Bridges (A) Widening / Repair / Rehabilitation of Existing Minor Bridges NIL (B) Reconstruction of Existing Minor Bridges NIL (C) Construction of New Minor Bridges on Main Carriageway Sr. No Chainage Span Arrangement Structure Width Km (m) (m) 1 35+975 1X25 As per TCS-5 2 39+660 1x25 As per TCS-5 3 43+845 1X10 As per TCS-5 4 44+380 1X10 As per TCS-5 5 44+620 1X10 As per TCS-5 6 44+830 1X10 As per TCS-5 7 45+300 1X12 As per TCS-5 8 45+540 1X12 As per TCS-5 9 46+650 1X20 As per TCS-5 10 48+250 1X20 As per TCS-5 6. Culverts (A) Widening of Existing Culverts – NIL (B) Reconstruction of Existing Culverts – NIL
  • 30. Schedule - B Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 30 (C) Construction of New Culverts Sr. No Proposed Chainage (km) Type of Culvert Span Arrangement (m) 1 35+380 BOX 1x2 2 35+880 BOX 1x2 3 36+600 BOX 1x2 4 36+990 BOX 1x2 5 37+370 BOX 1x2 6 38+315 BOX 1x2 7 38+555 BOX 1X4 8 39+300 BOX 1X4 9 39+540 BOX 1x2 10 40+100 BOX 1X4 11 40+220 BOX 1x2 12 40+760 BOX 1X4 13 40+975 BOX 1X4 14 41+500 BOX 1X4 15 41+800 BOX 1x2 16 42+400 BOX 1x2 17 43+070 BOX 1x2 18 43+315 BOX 1x4 19 44+800 BOX 1x4 20 45+090 BOX 1x2 21 45+390 BOX 1x4 22 45+720 BOX 1X4 23 46+185 BOX 1X4 24 47+100 BOX 1X4 25 47+800 BOX 1X4 26 48+550 BOX 1X4 7. ROAD SIDE DRAINAGE Drainage system including surface and subsurface drains for the Project Highway shall be provided as per the Manual. Unlined Drain Sr. No CHAINAGE (m) Length (m) Side Total Length (m) From To 1 35000 35963 963 BHS 1926 2 36460 37265 805 BHS 1610 3 37870 38785 915 BHS 1830 4 38875 39648 773 BHS 1546 5 39673 41840 2167 BHS 4334 6 44250 44375 125 BHS 250 7 44385 44615 230 BHS 460 8 44625 44825 200 BHS 400 9 44835 45294 459 BHS 918 10 45306 45534 228 BHS 456 11 45546 46640 1094 BHS 2188
  • 31. Schedule - B Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 31 Unlined Drain Sr. No CHAINAGE (m) Length (m) Side Total Length (m) From To 12 46660 46920 260 BHS 520 13 47645 48240 595 BHS 1190 14 49135 49155 20 BHS 40 TOTAL LENGTH (m) 17668 Lined Drain Sr. No Chainage (m) Length (m) Length of Lined Drain on both side (m) From To 1 35988 36220 232 464 2 36240 36460 220 440 3 37265 37560 295 590 4 37580 37870 290 580 5 41840 42060 220 440 6 42080 42870 790 1580 7 42890 43146 256 512 8 43146 43506 360 720 9 43614 43840 226 452 10 43850 43986 136 272 11 43986 44035 49 98 12 44055 44250 195 390 13 46920 47260 340 680 14 47320 47645 325 650 15 48260 48643 383 766 16 48728 49115 387 774 TOTAL LENGTH (m) 9408 8. RAINWATER HARVESTING & DRAINAGE The provision of rainwater harvesting & drainage work shall be executed as per requirement of IRC: SP: 42-2017 and IRC: SP: 50-2013 & as per Ministry’s circular RW/NH-33044/14/2003- S&R(R)pt-II dated 03.09.2021. 9. UTILITY SHIFTING Shifting of obstructing utilities shall be done as per Ministry’s circular RW/NH-33044/29/2015- S&R(R)pt dated 11.02.2021. The Concessionaire shall be responsible for getting the utilities shifted as per approval of the concerned utility department. The assistance of the Authority is limited to giving forwarding letter on the proposal of Concessionaire to utility owning department whenever asked by the Concessionaire. The decision/approval of utility owning department shall be binding on the Concessionaire. Notes: (a) The supervision charges at the rates/charges applicable of the utility owning department shall be paid directly by the Authority to the Utility Owning department as and when Concessionaire furnishes demand of Utility Owning Department along with a copy of estimated cost given by the latter.
  • 32. Schedule - B Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 32 (b) The dismantled materials / scrap of the existing utilities to be shifted / dismantled shall belong to the Concessionaire who would be free to dispose-off the dismantled material as deemed fit by them unless the concessionaire is required to deposit the dismantled material to utility owning department as per the norms and practice and, in that case the amount of credit for dismantled material may be availed by the Concessionaire as per estimates agreed between them. (c) The utilities shall be handed over after shifting work is completed to Utility Owning Department up to their entire satisfaction. The maintenance liability shall rest with the Utility Owning Department after handing over process is complete as far as utility shifting works are concerned. 10. CHANGE OF SCOPE The length of Structures and bridges specified herein above shall be treated as an approximate assessment. The actual lengths as required on the basis of detailed investigations shall be determined by the Concessionaire in accordance with the Specifications and Standards. Any variations in the lengths specified in this Schedule-B shall not constitute a Change of Scope, save and except any variations in the length arising out of a Change of Scope expressly undertaken in accordance with the provisions of Article 16.
  • 33. Schedule - B Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 33 Appendix B-I (Schedule-B) Alignment Plan and longitudinal Section are enclosed as Appendix B-I (Schedule-B).
  • 34. Schedule - B Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 34 Appendix B-II (Schedule-B) Typical Cross Section are enclosed as Appendix B-II (Schedule-B).
  • 35. Schedule - B Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 35 Appendix B-III (Schedule-B) Interchange at design chainage km 47.290 (junction with existing NH-24B) and 48.685 (junction with existing NH-2) are enclosed as Appendix B-III (Schedule-B).
  • 36. Schedule - C Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 36 Appendix B-IV (Schedule-B) Traffic Signage Plan of the Project Highway enclosed as Appendix B-IV (Schedule-B).
  • 37. Schedule - C Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 37 Appendix B-V (Schedule-B) Drainage Plan of the Project Highway enclosed as Appendix B-V (Schedule-B).
  • 38. Schedule - C Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 38 Appendix B-VI (Schedule-B) GAD and Miscellaneous Drawings enclosed as Appendix B-VI (Schedule-B).
  • 39. Schedule - C Construction of 4-lane green field highway from Km 35.000 to Km 49.155 (Autarpur to Singraur Uparhar) of NH-731A with paved shoulders in the state of Uttar Pradesh on Hybrid Annuity Mode (Package – II) 39 SCHEDULE – C (See Clause 2.1) PROJECT FACILITIES 1. Project Facilities The Concessionaire shall construct the Project Facilities in accordance with the provisions of this Agreement. Such Project Facilities shall include: (a) Toll plaza (b) Road side furniture; (c) Pedestrian facilities; (d) Tree plantation (e) Truck lay-byes; (f) Bus stop and bus shelters; (g) Rest areas; (h) Highway Lighting; (i) Transportation Art. 2 Project Facilities for Project Highway Project Facilities forming part of Project Highway and to be completed on or before the scheduled date have been described in Annex‐I of this Schedule‐C.
  • 40. Annex – I SCHEDULE – C (See Clause 2.1) PROJECT FACILITIES 1. Project Facilities The Concessionaire shall construct the Project Facilities described in this Annex-1 to form part of the Four-Lane Project. The project facilities shall include: (a) Toll plaza (b) Road side furniture; (c) Pedestrian facilities; (d) Tree plantation (e) Truck lay-byes; (f) Bus stop and bus shelters; (g) Rest areas; (h) Highway Lighting and (i) Transportation Art. 2. Description of Project Facilities Each of the project facilities is described below: (a) Toll Plazas NIL (b) Roadside Furniture (i) Traffic Signs and Pavement Markings Traffic signs and pavement markings shall be provided as per Schedule D. (a) Overhead Gantry Signs shall be provided at locations mentioned below Sr. No Chainage Name of Sign/Road Marking Numbers Fig.no as per IRC 67 2012 LHS RHS 1 35+000 Gantry Mounted Sign 1 16.11 2 47+260 Gantry Mounted Sign 1 16.11 3 48+320 Gantry Mounted Sign 1 16.11 4 48+643 Gantry Mounted Sign 1 16.11 5 48+727 Gantry Mounted Sign 1 16.11 Note: The above location is indicative and minimum. The exact location of the overhead gantry finalized after approval from the Independent Engineer. ii. Safety Barrier: Thrie beam type steel barrier shall be provided in a minimum length of 19,112 metre at locations finalized after review by Independent Engineer under clause 9.7 of the Manual referred in Schedule D. (c) Pedestrian Facilities Pedestrian facilities shall be provided as per Schedule-D.
  • 41. (d) Landscaping & Tree plantation (j) Minimum of 3000 trees shall be planted as per Schedule-D. (ii) Landscaping Treatment shall be provided at all grade separators, viaducts, traffic islands, bus-bays as per Schedule-D. (e) Truck Lay Bye Sr. No Design Chainage (Km) LHS/RHS Village name Nil (f) Bus Bay – Bus Shelter Sr. No Design Chainage (Km) LEFT RIGHT 1 36.750 36.850 2 39.100 39.200 3 41.130 41.250 4 44.450 44.550 5 45.430 45.700 6 47.870 48.000 Note: The Bus shelters shall be aesthetically pleasing duly designed by qualified and experienced Architect. (g) Rest Areas Nil (h) Highway Lighting: Shall be provided as per Schedule-D. (i) Transportation Art: Shall be provided on all grade-separators, VUPs and ROB to enhance the overall aesthetics, the graphics/visuals shall be designed by fine arts department of an institute of repute. 4. Rainwater Harvesting As per Ministry of Environment and Forests Notification, New Delhi dated 14/01/1997 (as amended on 13/01/1998, 05/01/1999 & 6/11/2000), the construction of Rain water, harvesting structure is mandatory in and around Water Crisis area, notified by the Central Ground Water Board.
  • 42. Schedule - D SCHEDULE – D (See Clause 2.1) SPECIFICATIONS AND STANDARDS 1. Four-Laning The Concessionaire shall comply with the Specifications and Standards set forth in Annex-I of this Schedule-D for construction of the Four Lane Project Highway.
  • 43. Schedule - D Annex - I (Schedule-D) SPECIFICATIONS AND STANDARDS 1 Specifications and Standards All Materials works and construction operations shall conform to the Manual of Specifications and Standards for Four-Lane Highways (IRC: SP: 84-2019) published by IRC (referred to as “Manual” in this Schedule) and MORTH Specifications for Road and Bridge Works. Where the specification for a work is not given, Good Industry Practice shall be adopted to the satisfaction of the Independent Engineer. Further the specifications & standards shall comply to Ministry’s specifications & applicable IRC Codes. 2 Deviations from the Specifications and Standards 2.1 Notwithstanding anything to the contrary contained in the aforesaid Manual, the following Specifications and Standards shall apply to the Four-Lane Project Highway, and for purposes of this Agreement, the aforesaid Manual shall be deemed to be amended to the extent set forth below: Sr. No Clause as per Manual Provision as per Manual Deviation/ Modified Provision 1 2.12.2 Service Road Width of service/slip road shall be 5.5m at all locations. No parking Bays are to be provided. 2 5.4.1 (i) Flexible pavement: design period and strategy The design period shall be as specified in Schedule-B. 3 7.1 All bridges and grade separated structures shall have independent superstructure for each direction of travel unless specified otherwise in Schedule ‘B’. Culverts may have single or independent superstructure. As per Schedule-B. 4 7.19 Grade Separated Road Structures: Carriageway width 14.00m. The Carriageway width shall be as specified in Schedule- B; TCS-3. 5 7.21 Structures in Marine Environment Deleted. 6 Nil - Transportation Art: The specification and standards shall be as provided by fine arts department of an institute of repute.