SlideShare a Scribd company logo
1 of 94
Dr. Imad BreikSupervisor:
Prepared By: Jehad Yahya
Mohammad Shihab
2013-2014
Outlines:
 The objectives of this project .
 Description of Aqraba Electrical Network .
 Making analysis for Aqraba Network by using ETAP software
program :
• Improvement for Max. Case in the (Medium & Low voltage side ) .
• Improvement for Min. Case in the (Medium & Low voltage side ) .
 The economical Study .
 Sag & Tension problem in Overhead lines for Aqraba electrical
network .
 Design a solar energy system to support the network with it .
Objectives
• Increase the voltage level at the consumer terminals ,
decrease the losses in the network and minimize the
penalties by improve the power factor through several
steps:
• Design a solar energy system to support the network
with it .
1. Swing Buses.
2. Transformer Taps.
3. Capacitor Banks (Compensation).
The Problems
Through cooperation with Aqraba municipality,
we were able to know the basic problems in the
network
1. Overload
2. Currents
3. Low voltage at the consumer terminals
5. Penalties because of low power factor
6. Sag & Tension problem in the overhead lines
Description of Aqraba Network
Aqraba Electrical Network is provided by Israel electrical company
(IEC) through an over head transmission line of 33 kV. The max
demand is reached (2MW).
The main supply for Aqraba electrical distribution network in the
Za'tara Street.. And the voltage of the existing distribution networks
are 33 KV only.IEC supplies electricity to the electrified communities
by 33 KV by overhead lines .
Aqraba electrical network consists of 18 (33/0.4 KV) distribution
transformers.
Distribution Transformer for Aqraba Network
The Length of the Transmission Lines
To determine the length for each transmission line, we use a MAP
for Aqraba Village by using AutoCAd software program :
One Line Diagram
Max. Case Improvement
Transformer loading :
Max. Case Improvement
After making analysis for the original Max. Case, the result is shown
below :
 Swing Bus Result :
 Summary of total generation, loading and demand :
Max. Case Improvement
 Increase the swing bus voltage :
Max. Case Improvement
 Swing Bus Result :
 Summary of total generation, loading and demand :
Max. Case Improvement
 Increase the tap ratio of the Transformers to 5 % :
Max. Case Improvement
 Swing Bus Result :
 Summary of total generation, loading and demand :
Max. Case Improvement
 Power Factor Improvement :
How to improve the Power Factor :
Capacitor Bank:
The important of improvement
power factor is by adding shunt
capacitor banks at the buses at
both transmission and distribution
levels and loads and there are more effective to add them in
the low level voltages.
Power Factor Improvement :
The result of load flow after after adding the capacitor banks :
Max. Case Improvement
 Swing Bus Result :
 Summary of total generation, loading and demand :
Max. Case Improvement
After adding the capacitor banks the losses in the network
decrease and the total current decrease
- The losses before= 0.018 MW, and the swing current = 26.42 A.
- The losses after=0.016 MW, and the swing current = 25.4 A.
Max. Case Improvement
 The voltage level improvement :
Max. Case Improvement
 Swing Bus Result :
 Summary of total generation, loading and demand :
Max. Case Improvement
After adding the capacitor banks the losses in the network
decrease and the total current decrease
- The losses before= 0.018 MW, and the swing current = 26.42 A.
- The losses after=0.016 MW, and the swing current = 24.86 A.
Min. Case Improvement
Transformer loading :
Min. Case Improvement
After making analysis for the original Min. Case, the result is shown
below :
 Swing Bus Result :
 Summary of total generation, loading and demand :
Min. Case Improvement
 Increase the tap ratio of the Transformers to 2.5 % :
Min. Case Improvement
 Swing Bus Result :
 Summary of total generation, loading and demand :
Power Factor Improvement :
The result of load flow after after adding the capacitor banks :
Min. Case Improvement
 Swing Bus Result :
 Summary of total generation, loading and demand :
Min. Case Improvement
 The voltage level improvement :
Min. Case Improvement
 Swing Bus Result :
 Summary of total generation, loading and demand :
Min. Case Improvement
After adding the capacitor banks the losses in the network
decrease and the total current decrease
- The losses before= 0.006 MW, and the swing current = 9.91 A.
- The losses after=0.005 MW, and the swing current = 9.57A.
Max. Case Improvement at Low Voltage Side
 Low Voltage Side :
Most of the problems of the electrical networks are located in
the low voltage side ( Low Tension Side ) , and the most
important of these problems are : power losses due to the high
current value in this side, and the drop voltage.
In this chapter and in the next chapter the network in low
voltage will be studied.
We measured the load ( Real Power, Current for each phase,
power factor) for each feeder of each transformer in max. and
min. case.
Max. Case Improvement at Low Voltage Side
The load at each feeder for some trasformers :
After making analysis for the original Max. Case, the result is shown
below :
Max. Case Improvement at Low Voltage Side
 Swing Bus Result :
 Summary of total generation, loading and demand :
Max. Case Improvement at Low Voltage Side
Max. Case Improvement at Low Voltage Side
The main problem in the low level side is the unsymmetrical
loads between phases which cases many problems :
- High neutral current.
- High drop voltage in feeder which cases low voltage in the
consumers.
-High losses in the network
- The losses before adding the low voltage side = 0.017 MW.
- The losses after adding the low voltage side = 0.178 MW.
Max. Case Improvement at Low Voltage Side
 Increase the tap ratio of the Transformers to 5 % :
 Swing Bus Result :
 Summary of total generation, loading and demand :
Max. Case Improvement at Low Voltage Side
After making analysis for the original Max. Case, the result is shown
below :
After changing the taps of the transformers the voltage in the consumers
increased, also the voltage drop in the feeders decrease and the losses in the
network decrease.
Power Factor Improvement :
The result of load flow after after adding the capacitor banks :
 Swing Bus Result :
 Summary of total generation, loading and demand :
Max. Case Improvement at Low Voltage Side
After making analysis for the original Max. Case, the result is shown
below :
After increasing the tap ratio and adding the capacitor banks the losses in the
network decrease :
- The losses before= 0.178 MW.
- The losses after=0.160 MW .
 The voltage level improvement :
Max. Case Improvement at Low Voltage Side
 Swing Bus Result :
 Summary of total generation, loading and demand :
Max. Case Improvement at Low Voltage Side
After adding the capacitor banks the losses in the network decrease :
- The losses in the original case = 0.178 MW.
- The losses after =0.175 MW.
The voltage level in some buses increase.
Min. Case Improvement at Low Voltage Side
The load at each feeder for some trasformers :
After making analysis for the original Min. Case, the result is shown
below :
Min. Case Improvement at Low Voltage Side
 Swing Bus Result :
 Summary of total generation, loading and demand :
Min. Case Improvement at Low Voltage Side
After the analysis : the losses in the network increase more than the losses in the
minimum case at the medium voltage:
- The losses before = 0.006 MW .
- The losses after = 0.53 MW .
Min. Case Improvement at Low Voltage Side
 Increase the tap ratio of the Transformers to 2.5 % :
 Swing Bus Result :
 Summary of total generation, loading and demand :
Min. Case Improvement at Low Voltage Side
After making analysis for the Network, the result is shown below :
After changing the taps of the transformers the voltage in the consumers
increased, also the voltage drop in the feeders decrease and the losses in the
network decrease.
Power Factor Improvement :
The result of load flow after after adding the capacitor banks :
 Swing Bus Result :
 Summary of total generation, loading and demand :
Min. Case Improvement at Low Voltage Side
After making analysis for the Network, the result is shown below :
After increasing the tap ratio and adding the capacitor banks the losses in the
network decrease :
- The losses before= 0.053 MW.
- The losses after=0. 050 MW .
 The voltage level improvement :
Min. Case Improvement at Low Voltage Side
 Swing Bus Result :
 Summary of total generation, loading and demand :
Min. Case Improvement at Low Voltage Side
After adding the capacitor banks the losses in the network decrease :
- The losses in the original case = 0.053 MW.
- The losses after = 0.050 MW.
The voltage level in some buses increase.
The Economical Study
 Saving in Penalties:
The Economical Study
 Saving in Losses:
The Economical Study
 Simple Pay Back Period :
Sag & Tension Problem in the Network
 Calculations of Sag (in general ) :
l = Length of span
Wt = total weight per unit length of conductor
T = Tension in the conductor.
W = weight of conductor per unit length
Wi = weight of ice per unit length
Ww = wind force per unit length
Sag & Tension Problem in the Network
 The Problem :
The problem lies in the poor and an error in the estimation of the
amount of sag when designing and extension for overhead lines in
some areas, where the amount of sag was not enough, and in the last
winter, a large amount of snow and low degrees of temperature led
to a contraction in the tensile strength of the cables, this led to cut in
the cable and destruction of some of the towers as shown in the below
picture:
Sag & Tension Problem in the Network
 The Recommendations for the sag problem :
To avoid the occurrence of the problem that has been raised previously,
there is a mathematical relationship whereby estimate and calculate the
amount of sag in correct form:
This gives the freedom of cable stretch in the summer and contraction in
the winter without affecting on the cable and without leads to a cut in it.
Solar Energy Station Project
 Consumption energy Of the Network :
 Data about consumption of the network :
Solar Energy Station Project
 Calculations of the power for the solar system:
The Energy of the network in year = 5716110 KWH/year.
The Energy of the network in day = The Energy of the network in year / the number of
day in year.
The Energy of the network in day = 5716110/365 = 15660.6 KWH/day.
The average energy produced of 1KW solar cells = 5.4KWH/m^2.day.
We use the penetration factor =20%.
Then the total energy of solar system in day = the penetration factor * The Energy of the
network in day.
The total energy of solar system in day = 15660.6 * 0.2 = 3132.1 KWH/day.
Then we calculate the power of the solar system, that will work on the design.
The power of the solar system(Ppv in KW) = The total energy of solar system in day/ The
average energy produced of 1KW solar cells.
P pv (KW) = 3132.1 () /(5.4KWH/m^2.day) = 580 KW.
Then we will design the pKWH/dayower of solar system = 580KW.
Solar Energy Station Project
 How to determine the optimization of Tilt & Azimuth angle :
To determine the Tilt and Azimuth angle, we use a link on the Internet, as
shown below . (The link:
http://re.jrc.ec.europa.eu/pvgis/apps4/pvest.php?map )
Solar Energy Station Project
 The Result that we obtained from the link :
After we entered all necessary data, the results and calculations of this
program are shown below :
*The optimization tilt angle =26 degree, and the optimum azimuth angle = -6 degree
Ed: Average daily electricity production from
the given system (kWh)
Em: Average monthly electricity production
from the given system (kWh)
Hd: Average daily sum of global irradiation per
square meter received by the modules of the
given system (kWh/m2)
Hm: Average sum of global irradiation per
square meter system (kWh/m2)
Solar Energy Station Project
The average power produced by the solar system per month is shown in the
below figure
Solar Energy Station Project
 The optimal inclination angle & solar irradiation per month :
Optimal inclination angle is:
26 degrees
Annual irradiation deficit
due to shadowing
(horizontal): 0.4 %
Solar Energy Station Project
The table below and picture shows the optimal inclination angle and
irradiation on plane in each month :
H(26): Irradiation on plane at angle: 26deg.
(Wh/m2/day).
Iopt: Optimal inclination (deg.).
Solar Energy Station Project
 The Design of the solar station system :
The Power of this station = 580kw, and we will use two program to design this
station . The first program is PV system .
Solar Energy Station Project
 PV system :
Solar Energy Station Project
 The Result :
After entering all necessary numbers and data and identify options, the program give us the
results as shown in the below curves and tables :
The below curve show us the System output energy for each month :
Solar Energy Station Project
 The design of the solar station by using Aurora program :
By using the Aurora program in this project, we designed the solar system =580KW
,and we distributed it into 10 groups each group equal to 55KW.
 Aurora Designer :
Solar Energy Station Project
In this design that we work on it, we try to achieve the optimum design (the module in
series to achieve the voltage of the inverter , and the parallel string to achieve the power of
the inverter , and the oversize of the inverter that we chosen is between (95%-110%)).
* The number of the module in series =17 module.
* The parallel string =12.
The next figure shown how to enter the series module and parallel string in the Aurora
program:
Solar Energy Station Project
 The Result from the Aurora Program :
System configuration:
Inverter Specifications:
Solar Energy Station Project
PV Module Data:
Array Sizing Parameters:
Solar Energy Station Project
Voltage and Current Parameter Check:
Solar Energy Station Project
*But when the parallel string is equal to (11), the new results are shown
in the below tables ( and this is more acceptable ):
Solar Energy Station Project
 The Result :
New System configuration:
New Voltage and Current Parameter Check:
Solar Energy Station Project
 Calculations to determine the Rating of the set up Transformer:
In this project we distributed the inverter into 10 inverters and the maximum
power for each inverter is equal to 55 KW.
The maximum power for all inverters is equal to 550 KW
The rating of the step up transformer can be calculated by these formulas below
Solar Energy Station Project
 Economical study for the Solar system project :
•The life span period of the solar system = 20 years.
•The price of 1kwh of solar = 0.65 NIC.
•The price of transformer = 30000 NIC.
•The price of each watt =2.2 $ =7.7 NIC. The price of 1 kw =2200$=7700 NIC.
* The average of 1kw produce 1700 kwh/year.
The investment = Price of the transformer + Price of the solar system (580kw)
The investment = 30000 + (580*7700) = 4496000 NIC.
•The average producing of the solar system in year = 1700 * 580 = 986000 kwh
•The saving in the year = 986000 kwh * 0.65 NIC = 640900 NIC/ year.
The simple pay back period = investment / saving in year
S.P.B.P = 4496000 / 640900 = 7 YEARS.
Any Question ?

More Related Content

What's hot

Project report soofi
Project report soofiProject report soofi
Project report soofialmsoofi
 
1590053 634881478003587500
1590053 6348814780035875001590053 634881478003587500
1590053 634881478003587500Navyasri Jiguru
 
Automatic Power Factor Corrector Using Arduino report
Automatic Power Factor Corrector Using Arduino reportAutomatic Power Factor Corrector Using Arduino report
Automatic Power Factor Corrector Using Arduino reportSelf-employed
 
Automatic Power Factor Corrector
Automatic Power Factor CorrectorAutomatic Power Factor Corrector
Automatic Power Factor CorrectorSelf-employed
 
Analysis of Power Factor Improvement Techniques in case of Non Linear System ...
Analysis of Power Factor Improvement Techniques in case of Non Linear System ...Analysis of Power Factor Improvement Techniques in case of Non Linear System ...
Analysis of Power Factor Improvement Techniques in case of Non Linear System ...Kaustubh Nande
 
Three phase power factor improvement using Vienna Rectifier
Three phase power factor improvement using Vienna Rectifier Three phase power factor improvement using Vienna Rectifier
Three phase power factor improvement using Vienna Rectifier Mathankumar S
 
Force Energy Saver
Force Energy SaverForce Energy Saver
Force Energy SaverRay Barnes
 
Power Factor: what it is, how to measure it and how to improve it to reduce u...
Power Factor: what it is, how to measure it and how to improve it to reduce u...Power Factor: what it is, how to measure it and how to improve it to reduce u...
Power Factor: what it is, how to measure it and how to improve it to reduce u...Pulse Energy
 
APFC project presentation
APFC project presentationAPFC project presentation
APFC project presentationkartickmp613
 
Automatic Power Factor Correction using Microcontroller 8051
Automatic Power Factor Correction using Microcontroller 8051Automatic Power Factor Correction using Microcontroller 8051
Automatic Power Factor Correction using Microcontroller 8051Neehar NLN
 
Power factor solution,presentation
Power factor solution,presentationPower factor solution,presentation
Power factor solution,presentationAmol Chande
 
Power Factor : Basics and Benefits of Improvement
Power Factor : Basics and  Benefits of ImprovementPower Factor : Basics and  Benefits of Improvement
Power Factor : Basics and Benefits of ImprovementBijadhar Pandey
 
Compensation of harmonic currents utilizing AHC by kingsprime
Compensation of harmonic currents utilizing AHC by kingsprimeCompensation of harmonic currents utilizing AHC by kingsprime
Compensation of harmonic currents utilizing AHC by kingsprimeKalu Kingsley Ekperebuike
 
Kvar Presentation Ppt 8.8.08[1]
Kvar Presentation Ppt 8.8.08[1]Kvar Presentation Ppt 8.8.08[1]
Kvar Presentation Ppt 8.8.08[1]Keystone Clean Air
 
Automatic Power Factor Improvement.Pptx
Automatic Power Factor Improvement.PptxAutomatic Power Factor Improvement.Pptx
Automatic Power Factor Improvement.PptxSveris COE Pandharpur
 
power factor correction soham+niraj
power factor correction soham+nirajpower factor correction soham+niraj
power factor correction soham+nirajsoham patel
 
Automation of capacitor banks based on MVAR Requirement
Automation of capacitor banks based on MVAR RequirementAutomation of capacitor banks based on MVAR Requirement
Automation of capacitor banks based on MVAR RequirementAhmed Aslam
 

What's hot (20)

Project report soofi
Project report soofiProject report soofi
Project report soofi
 
1590053 634881478003587500
1590053 6348814780035875001590053 634881478003587500
1590053 634881478003587500
 
APFC AMTL 30.01.2015
APFC  AMTL  30.01.2015APFC  AMTL  30.01.2015
APFC AMTL 30.01.2015
 
Automatic Power Factor Corrector Using Arduino report
Automatic Power Factor Corrector Using Arduino reportAutomatic Power Factor Corrector Using Arduino report
Automatic Power Factor Corrector Using Arduino report
 
Automatic Power Factor Corrector
Automatic Power Factor CorrectorAutomatic Power Factor Corrector
Automatic Power Factor Corrector
 
Analysis of Power Factor Improvement Techniques in case of Non Linear System ...
Analysis of Power Factor Improvement Techniques in case of Non Linear System ...Analysis of Power Factor Improvement Techniques in case of Non Linear System ...
Analysis of Power Factor Improvement Techniques in case of Non Linear System ...
 
Three phase power factor improvement using Vienna Rectifier
Three phase power factor improvement using Vienna Rectifier Three phase power factor improvement using Vienna Rectifier
Three phase power factor improvement using Vienna Rectifier
 
Force Energy Saver
Force Energy SaverForce Energy Saver
Force Energy Saver
 
Power Factor: what it is, how to measure it and how to improve it to reduce u...
Power Factor: what it is, how to measure it and how to improve it to reduce u...Power Factor: what it is, how to measure it and how to improve it to reduce u...
Power Factor: what it is, how to measure it and how to improve it to reduce u...
 
Apfc final seminar
Apfc final seminarApfc final seminar
Apfc final seminar
 
APFC project presentation
APFC project presentationAPFC project presentation
APFC project presentation
 
Mohsin rana
Mohsin ranaMohsin rana
Mohsin rana
 
Automatic Power Factor Correction using Microcontroller 8051
Automatic Power Factor Correction using Microcontroller 8051Automatic Power Factor Correction using Microcontroller 8051
Automatic Power Factor Correction using Microcontroller 8051
 
Power factor solution,presentation
Power factor solution,presentationPower factor solution,presentation
Power factor solution,presentation
 
Power Factor : Basics and Benefits of Improvement
Power Factor : Basics and  Benefits of ImprovementPower Factor : Basics and  Benefits of Improvement
Power Factor : Basics and Benefits of Improvement
 
Compensation of harmonic currents utilizing AHC by kingsprime
Compensation of harmonic currents utilizing AHC by kingsprimeCompensation of harmonic currents utilizing AHC by kingsprime
Compensation of harmonic currents utilizing AHC by kingsprime
 
Kvar Presentation Ppt 8.8.08[1]
Kvar Presentation Ppt 8.8.08[1]Kvar Presentation Ppt 8.8.08[1]
Kvar Presentation Ppt 8.8.08[1]
 
Automatic Power Factor Improvement.Pptx
Automatic Power Factor Improvement.PptxAutomatic Power Factor Improvement.Pptx
Automatic Power Factor Improvement.Pptx
 
power factor correction soham+niraj
power factor correction soham+nirajpower factor correction soham+niraj
power factor correction soham+niraj
 
Automation of capacitor banks based on MVAR Requirement
Automation of capacitor banks based on MVAR RequirementAutomation of capacitor banks based on MVAR Requirement
Automation of capacitor banks based on MVAR Requirement
 

Viewers also liked

Analysis optimization and monitoring system
Analysis optimization and monitoring system Analysis optimization and monitoring system
Analysis optimization and monitoring system slmnsvn
 
Optimum design and performance for nablus network
Optimum design and performance for nablus networkOptimum design and performance for nablus network
Optimum design and performance for nablus networkslmnsvn
 
Optimum performances of ramallah
Optimum performances of ramallahOptimum performances of ramallah
Optimum performances of ramallahslmnsvn
 
Optimization of loss minimization using facts in deregulated power systems
Optimization of loss minimization using facts in deregulated power systemsOptimization of loss minimization using facts in deregulated power systems
Optimization of loss minimization using facts in deregulated power systemsAlexander Decker
 
Energy Loss Reduction Initiatives
Energy Loss Reduction InitiativesEnergy Loss Reduction Initiatives
Energy Loss Reduction InitiativesAmit Bhatia
 
Optimization Power FLow At PT PLN Persero Yogyakarta
Optimization Power FLow At PT PLN Persero YogyakartaOptimization Power FLow At PT PLN Persero Yogyakarta
Optimization Power FLow At PT PLN Persero YogyakartaRishal Asri
 
Power factor correction
Power factor correctionPower factor correction
Power factor correctionslmnsvn
 
Three phase-induction-motor(eee499.blospot.com)
Three phase-induction-motor(eee499.blospot.com)Three phase-induction-motor(eee499.blospot.com)
Three phase-induction-motor(eee499.blospot.com)slmnsvn
 
Optimum performance for aqraba electrical network 2
Optimum performance for aqraba electrical network 2Optimum performance for aqraba electrical network 2
Optimum performance for aqraba electrical network 2slmnsvn
 
33/11 KV TRANSMISSION LINE
33/11 KV TRANSMISSION LINE 33/11 KV TRANSMISSION LINE
33/11 KV TRANSMISSION LINE Lalit Kumar
 
Optimum performance for aqraba electrical network
Optimum performance for aqraba electrical networkOptimum performance for aqraba electrical network
Optimum performance for aqraba electrical networkslmnsvn
 
Analysis optimization and monitoring system
Analysis optimization and monitoring system Analysis optimization and monitoring system
Analysis optimization and monitoring system slmnsvn
 
DISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROLDISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROLyohannes feleke
 
Power factor correction
Power factor correctionPower factor correction
Power factor correctionslmnsvn
 
Modeling & Analysis of 31 Bus Power System using Software simulation in PSAT ...
Modeling & Analysis of 31 Bus Power System using Software simulation in PSAT ...Modeling & Analysis of 31 Bus Power System using Software simulation in PSAT ...
Modeling & Analysis of 31 Bus Power System using Software simulation in PSAT ...nikhilkulk21
 
Load flow analysis of 132 kv substation using etap
Load flow analysis of 132 kv substation using etapLoad flow analysis of 132 kv substation using etap
Load flow analysis of 132 kv substation using etapmajeed khan
 
A review on_load_flow_studies_final_2
A review on_load_flow_studies_final_2A review on_load_flow_studies_final_2
A review on_load_flow_studies_final_2yareda6
 
Per unit (pu) quantities|vivasolve.blogspot.com
Per unit (pu) quantities|vivasolve.blogspot.comPer unit (pu) quantities|vivasolve.blogspot.com
Per unit (pu) quantities|vivasolve.blogspot.comboromama
 

Viewers also liked (20)

Analysis optimization and monitoring system
Analysis optimization and monitoring system Analysis optimization and monitoring system
Analysis optimization and monitoring system
 
Optimum design and performance for nablus network
Optimum design and performance for nablus networkOptimum design and performance for nablus network
Optimum design and performance for nablus network
 
Optimum performances of ramallah
Optimum performances of ramallahOptimum performances of ramallah
Optimum performances of ramallah
 
Optimization of loss minimization using facts in deregulated power systems
Optimization of loss minimization using facts in deregulated power systemsOptimization of loss minimization using facts in deregulated power systems
Optimization of loss minimization using facts in deregulated power systems
 
Energy Loss Reduction Initiatives
Energy Loss Reduction InitiativesEnergy Loss Reduction Initiatives
Energy Loss Reduction Initiatives
 
Optimization Power FLow At PT PLN Persero Yogyakarta
Optimization Power FLow At PT PLN Persero YogyakartaOptimization Power FLow At PT PLN Persero Yogyakarta
Optimization Power FLow At PT PLN Persero Yogyakarta
 
Power factor correction
Power factor correctionPower factor correction
Power factor correction
 
Three phase-induction-motor(eee499.blospot.com)
Three phase-induction-motor(eee499.blospot.com)Three phase-induction-motor(eee499.blospot.com)
Three phase-induction-motor(eee499.blospot.com)
 
Loss minimisation in power system
Loss minimisation in power systemLoss minimisation in power system
Loss minimisation in power system
 
Optimum performance for aqraba electrical network 2
Optimum performance for aqraba electrical network 2Optimum performance for aqraba electrical network 2
Optimum performance for aqraba electrical network 2
 
33/11 KV TRANSMISSION LINE
33/11 KV TRANSMISSION LINE 33/11 KV TRANSMISSION LINE
33/11 KV TRANSMISSION LINE
 
Optimum performance for aqraba electrical network
Optimum performance for aqraba electrical networkOptimum performance for aqraba electrical network
Optimum performance for aqraba electrical network
 
Analysis optimization and monitoring system
Analysis optimization and monitoring system Analysis optimization and monitoring system
Analysis optimization and monitoring system
 
DISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROLDISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROL
 
Power factor correction
Power factor correctionPower factor correction
Power factor correction
 
Modeling & Analysis of 31 Bus Power System using Software simulation in PSAT ...
Modeling & Analysis of 31 Bus Power System using Software simulation in PSAT ...Modeling & Analysis of 31 Bus Power System using Software simulation in PSAT ...
Modeling & Analysis of 31 Bus Power System using Software simulation in PSAT ...
 
Etap 14
Etap 14Etap 14
Etap 14
 
Load flow analysis of 132 kv substation using etap
Load flow analysis of 132 kv substation using etapLoad flow analysis of 132 kv substation using etap
Load flow analysis of 132 kv substation using etap
 
A review on_load_flow_studies_final_2
A review on_load_flow_studies_final_2A review on_load_flow_studies_final_2
A review on_load_flow_studies_final_2
 
Per unit (pu) quantities|vivasolve.blogspot.com
Per unit (pu) quantities|vivasolve.blogspot.comPer unit (pu) quantities|vivasolve.blogspot.com
Per unit (pu) quantities|vivasolve.blogspot.com
 

Similar to Optimum performance for aqraba electrical network 2

power factor and power factor correction schneider EMERSON EDUARDO RODRIGUES
power factor and power factor correction schneider EMERSON EDUARDO RODRIGUESpower factor and power factor correction schneider EMERSON EDUARDO RODRIGUES
power factor and power factor correction schneider EMERSON EDUARDO RODRIGUESEMERSON EDUARDO RODRIGUES
 
Improvement of Load Power Factor by Using Capacitor
Improvement of Load Power Factor by Using CapacitorImprovement of Load Power Factor by Using Capacitor
Improvement of Load Power Factor by Using CapacitorIOSRJEEE
 
PROBLEM ON THE POWERFACTOR CORRRECTION IN POWER PLANT
PROBLEM ON THE POWERFACTOR CORRRECTION IN POWER PLANTPROBLEM ON THE POWERFACTOR CORRRECTION IN POWER PLANT
PROBLEM ON THE POWERFACTOR CORRRECTION IN POWER PLANTsanjay kumar pediredla
 
IRJET- Harmonics Reduction using Harmonics Injection Method
IRJET- Harmonics Reduction using Harmonics Injection MethodIRJET- Harmonics Reduction using Harmonics Injection Method
IRJET- Harmonics Reduction using Harmonics Injection MethodIRJET Journal
 
Optimum performances of ramallah
Optimum performances of ramallahOptimum performances of ramallah
Optimum performances of ramallahslmnsvn
 
MINOR MODULE 2.pptx
MINOR MODULE 2.pptxMINOR MODULE 2.pptx
MINOR MODULE 2.pptxvikip35
 
Power Factor its Importance and Improvement.pptx
Power Factor its Importance and Improvement.pptxPower Factor its Importance and Improvement.pptx
Power Factor its Importance and Improvement.pptxaafadf1
 
Electrical energy issues presented by arshad khan chiniot power limited
Electrical energy issues presented by arshad khan chiniot  power limitedElectrical energy issues presented by arshad khan chiniot  power limited
Electrical energy issues presented by arshad khan chiniot power limitedarshadkhanmarwat
 
Impacts of Distributed Generation on Power Quality
Impacts of Distributed Generation on Power QualityImpacts of Distributed Generation on Power Quality
Impacts of Distributed Generation on Power QualityParth Patel
 
uppcl training in moradabad report
uppcl training in moradabad reportuppcl training in moradabad report
uppcl training in moradabad reportMONU KUMAR
 
High performance fast charging of electric vehicles
High performance fast charging of electric vehiclesHigh performance fast charging of electric vehicles
High performance fast charging of electric vehiclesstudent
 
IRJET- Automated Energy Monitering System and Power Factor Improvement
IRJET-  	  Automated Energy Monitering System and Power Factor ImprovementIRJET-  	  Automated Energy Monitering System and Power Factor Improvement
IRJET- Automated Energy Monitering System and Power Factor ImprovementIRJET Journal
 

Similar to Optimum performance for aqraba electrical network 2 (20)

power factor and power factor correction schneider EMERSON EDUARDO RODRIGUES
power factor and power factor correction schneider EMERSON EDUARDO RODRIGUESpower factor and power factor correction schneider EMERSON EDUARDO RODRIGUES
power factor and power factor correction schneider EMERSON EDUARDO RODRIGUES
 
Ssfcl
SsfclSsfcl
Ssfcl
 
Power factor
Power factorPower factor
Power factor
 
POWER FACTOR.pptx
POWER FACTOR.pptxPOWER FACTOR.pptx
POWER FACTOR.pptx
 
8925273.ppt
8925273.ppt8925273.ppt
8925273.ppt
 
Improvement of Load Power Factor by Using Capacitor
Improvement of Load Power Factor by Using CapacitorImprovement of Load Power Factor by Using Capacitor
Improvement of Load Power Factor by Using Capacitor
 
1.3
1.31.3
1.3
 
Power factor improvement
Power factor improvement Power factor improvement
Power factor improvement
 
CH1.ppt
CH1.pptCH1.ppt
CH1.ppt
 
PROBLEM ON THE POWERFACTOR CORRRECTION IN POWER PLANT
PROBLEM ON THE POWERFACTOR CORRRECTION IN POWER PLANTPROBLEM ON THE POWERFACTOR CORRRECTION IN POWER PLANT
PROBLEM ON THE POWERFACTOR CORRRECTION IN POWER PLANT
 
IRJET- Harmonics Reduction using Harmonics Injection Method
IRJET- Harmonics Reduction using Harmonics Injection MethodIRJET- Harmonics Reduction using Harmonics Injection Method
IRJET- Harmonics Reduction using Harmonics Injection Method
 
Optimum performances of ramallah
Optimum performances of ramallahOptimum performances of ramallah
Optimum performances of ramallah
 
MINOR MODULE 2.pptx
MINOR MODULE 2.pptxMINOR MODULE 2.pptx
MINOR MODULE 2.pptx
 
Power Factor its Importance and Improvement.pptx
Power Factor its Importance and Improvement.pptxPower Factor its Importance and Improvement.pptx
Power Factor its Importance and Improvement.pptx
 
A010410109
A010410109A010410109
A010410109
 
Electrical energy issues presented by arshad khan chiniot power limited
Electrical energy issues presented by arshad khan chiniot  power limitedElectrical energy issues presented by arshad khan chiniot  power limited
Electrical energy issues presented by arshad khan chiniot power limited
 
Impacts of Distributed Generation on Power Quality
Impacts of Distributed Generation on Power QualityImpacts of Distributed Generation on Power Quality
Impacts of Distributed Generation on Power Quality
 
uppcl training in moradabad report
uppcl training in moradabad reportuppcl training in moradabad report
uppcl training in moradabad report
 
High performance fast charging of electric vehicles
High performance fast charging of electric vehiclesHigh performance fast charging of electric vehicles
High performance fast charging of electric vehicles
 
IRJET- Automated Energy Monitering System and Power Factor Improvement
IRJET-  	  Automated Energy Monitering System and Power Factor ImprovementIRJET-  	  Automated Energy Monitering System and Power Factor Improvement
IRJET- Automated Energy Monitering System and Power Factor Improvement
 

More from slmnsvn

Smart home
Smart homeSmart home
Smart homeslmnsvn
 
Smart fuel theft detector
Smart fuel theft detectorSmart fuel theft detector
Smart fuel theft detectorslmnsvn
 
Smart fuel theft detector
Smart fuel theft detectorSmart fuel theft detector
Smart fuel theft detectorslmnsvn
 
Rfid attendace system
Rfid attendace systemRfid attendace system
Rfid attendace systemslmnsvn
 
Quad pod transformable vehicle
Quad pod transformable vehicleQuad pod transformable vehicle
Quad pod transformable vehicleslmnsvn
 
Quad pod transformable vehicle
Quad pod transformable vehicleQuad pod transformable vehicle
Quad pod transformable vehicleslmnsvn
 
Optimum performance of tulkarim governorate network
Optimum performance of tulkarim governorate networkOptimum performance of tulkarim governorate network
Optimum performance of tulkarim governorate networkslmnsvn
 
Optimum performance of tulkarim governorate network
Optimum performance of tulkarim governorate networkOptimum performance of tulkarim governorate network
Optimum performance of tulkarim governorate networkslmnsvn
 
Multi tone test
Multi tone testMulti tone test
Multi tone testslmnsvn
 
Multi tone test
Multi tone testMulti tone test
Multi tone testslmnsvn
 
Mini scada system for monitoring pv and wind installation in meteorology stat...
Mini scada system for monitoring pv and wind installation in meteorology stat...Mini scada system for monitoring pv and wind installation in meteorology stat...
Mini scada system for monitoring pv and wind installation in meteorology stat...slmnsvn
 
Mini scada system for monitoring pv and wind installation in meteorology stat...
Mini scada system for monitoring pv and wind installation in meteorology stat...Mini scada system for monitoring pv and wind installation in meteorology stat...
Mini scada system for monitoring pv and wind installation in meteorology stat...slmnsvn
 
Investigation effects-of-supplying-power-distrubition
Investigation effects-of-supplying-power-distrubitionInvestigation effects-of-supplying-power-distrubition
Investigation effects-of-supplying-power-distrubitionslmnsvn
 
Investigation of-effects-of-supplying-jenins-power
Investigation of-effects-of-supplying-jenins-powerInvestigation of-effects-of-supplying-jenins-power
Investigation of-effects-of-supplying-jenins-powerslmnsvn
 
Enable talk
Enable talkEnable talk
Enable talkslmnsvn
 
Enable talk
Enable talkEnable talk
Enable talkslmnsvn
 
Cell phone based dtmf controlled
Cell phone based dtmf controlledCell phone based dtmf controlled
Cell phone based dtmf controlledslmnsvn
 
Cell phone based dtmf controlled
Cell phone based dtmf controlledCell phone based dtmf controlled
Cell phone based dtmf controlledslmnsvn
 
Cell phone based dtmf
Cell phone based dtmfCell phone based dtmf
Cell phone based dtmfslmnsvn
 
Cell phone based dtmf
Cell phone based dtmfCell phone based dtmf
Cell phone based dtmfslmnsvn
 

More from slmnsvn (20)

Smart home
Smart homeSmart home
Smart home
 
Smart fuel theft detector
Smart fuel theft detectorSmart fuel theft detector
Smart fuel theft detector
 
Smart fuel theft detector
Smart fuel theft detectorSmart fuel theft detector
Smart fuel theft detector
 
Rfid attendace system
Rfid attendace systemRfid attendace system
Rfid attendace system
 
Quad pod transformable vehicle
Quad pod transformable vehicleQuad pod transformable vehicle
Quad pod transformable vehicle
 
Quad pod transformable vehicle
Quad pod transformable vehicleQuad pod transformable vehicle
Quad pod transformable vehicle
 
Optimum performance of tulkarim governorate network
Optimum performance of tulkarim governorate networkOptimum performance of tulkarim governorate network
Optimum performance of tulkarim governorate network
 
Optimum performance of tulkarim governorate network
Optimum performance of tulkarim governorate networkOptimum performance of tulkarim governorate network
Optimum performance of tulkarim governorate network
 
Multi tone test
Multi tone testMulti tone test
Multi tone test
 
Multi tone test
Multi tone testMulti tone test
Multi tone test
 
Mini scada system for monitoring pv and wind installation in meteorology stat...
Mini scada system for monitoring pv and wind installation in meteorology stat...Mini scada system for monitoring pv and wind installation in meteorology stat...
Mini scada system for monitoring pv and wind installation in meteorology stat...
 
Mini scada system for monitoring pv and wind installation in meteorology stat...
Mini scada system for monitoring pv and wind installation in meteorology stat...Mini scada system for monitoring pv and wind installation in meteorology stat...
Mini scada system for monitoring pv and wind installation in meteorology stat...
 
Investigation effects-of-supplying-power-distrubition
Investigation effects-of-supplying-power-distrubitionInvestigation effects-of-supplying-power-distrubition
Investigation effects-of-supplying-power-distrubition
 
Investigation of-effects-of-supplying-jenins-power
Investigation of-effects-of-supplying-jenins-powerInvestigation of-effects-of-supplying-jenins-power
Investigation of-effects-of-supplying-jenins-power
 
Enable talk
Enable talkEnable talk
Enable talk
 
Enable talk
Enable talkEnable talk
Enable talk
 
Cell phone based dtmf controlled
Cell phone based dtmf controlledCell phone based dtmf controlled
Cell phone based dtmf controlled
 
Cell phone based dtmf controlled
Cell phone based dtmf controlledCell phone based dtmf controlled
Cell phone based dtmf controlled
 
Cell phone based dtmf
Cell phone based dtmfCell phone based dtmf
Cell phone based dtmf
 
Cell phone based dtmf
Cell phone based dtmfCell phone based dtmf
Cell phone based dtmf
 

Recently uploaded

microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 

Recently uploaded (20)

microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 

Optimum performance for aqraba electrical network 2

  • 1. Dr. Imad BreikSupervisor: Prepared By: Jehad Yahya Mohammad Shihab 2013-2014
  • 2. Outlines:  The objectives of this project .  Description of Aqraba Electrical Network .  Making analysis for Aqraba Network by using ETAP software program : • Improvement for Max. Case in the (Medium & Low voltage side ) . • Improvement for Min. Case in the (Medium & Low voltage side ) .  The economical Study .  Sag & Tension problem in Overhead lines for Aqraba electrical network .  Design a solar energy system to support the network with it .
  • 3. Objectives • Increase the voltage level at the consumer terminals , decrease the losses in the network and minimize the penalties by improve the power factor through several steps: • Design a solar energy system to support the network with it . 1. Swing Buses. 2. Transformer Taps. 3. Capacitor Banks (Compensation).
  • 4. The Problems Through cooperation with Aqraba municipality, we were able to know the basic problems in the network 1. Overload 2. Currents 3. Low voltage at the consumer terminals 5. Penalties because of low power factor 6. Sag & Tension problem in the overhead lines
  • 5. Description of Aqraba Network Aqraba Electrical Network is provided by Israel electrical company (IEC) through an over head transmission line of 33 kV. The max demand is reached (2MW). The main supply for Aqraba electrical distribution network in the Za'tara Street.. And the voltage of the existing distribution networks are 33 KV only.IEC supplies electricity to the electrified communities by 33 KV by overhead lines . Aqraba electrical network consists of 18 (33/0.4 KV) distribution transformers.
  • 7. The Length of the Transmission Lines To determine the length for each transmission line, we use a MAP for Aqraba Village by using AutoCAd software program :
  • 10. Max. Case Improvement After making analysis for the original Max. Case, the result is shown below :  Swing Bus Result :  Summary of total generation, loading and demand :
  • 11.
  • 12. Max. Case Improvement  Increase the swing bus voltage :
  • 13. Max. Case Improvement  Swing Bus Result :  Summary of total generation, loading and demand :
  • 14.
  • 15. Max. Case Improvement  Increase the tap ratio of the Transformers to 5 % :
  • 16. Max. Case Improvement  Swing Bus Result :  Summary of total generation, loading and demand :
  • 17.
  • 18. Max. Case Improvement  Power Factor Improvement : How to improve the Power Factor : Capacitor Bank: The important of improvement power factor is by adding shunt capacitor banks at the buses at both transmission and distribution levels and loads and there are more effective to add them in the low level voltages.
  • 19. Power Factor Improvement : The result of load flow after after adding the capacitor banks :
  • 20. Max. Case Improvement  Swing Bus Result :  Summary of total generation, loading and demand :
  • 21. Max. Case Improvement After adding the capacitor banks the losses in the network decrease and the total current decrease - The losses before= 0.018 MW, and the swing current = 26.42 A. - The losses after=0.016 MW, and the swing current = 25.4 A.
  • 22.
  • 23. Max. Case Improvement  The voltage level improvement :
  • 24. Max. Case Improvement  Swing Bus Result :  Summary of total generation, loading and demand :
  • 25.
  • 26. Max. Case Improvement After adding the capacitor banks the losses in the network decrease and the total current decrease - The losses before= 0.018 MW, and the swing current = 26.42 A. - The losses after=0.016 MW, and the swing current = 24.86 A.
  • 28. Min. Case Improvement After making analysis for the original Min. Case, the result is shown below :  Swing Bus Result :  Summary of total generation, loading and demand :
  • 29.
  • 30. Min. Case Improvement  Increase the tap ratio of the Transformers to 2.5 % :
  • 31. Min. Case Improvement  Swing Bus Result :  Summary of total generation, loading and demand :
  • 32.
  • 33. Power Factor Improvement : The result of load flow after after adding the capacitor banks :
  • 34. Min. Case Improvement  Swing Bus Result :  Summary of total generation, loading and demand :
  • 35.
  • 36. Min. Case Improvement  The voltage level improvement :
  • 37. Min. Case Improvement  Swing Bus Result :  Summary of total generation, loading and demand :
  • 38.
  • 39. Min. Case Improvement After adding the capacitor banks the losses in the network decrease and the total current decrease - The losses before= 0.006 MW, and the swing current = 9.91 A. - The losses after=0.005 MW, and the swing current = 9.57A.
  • 40. Max. Case Improvement at Low Voltage Side  Low Voltage Side : Most of the problems of the electrical networks are located in the low voltage side ( Low Tension Side ) , and the most important of these problems are : power losses due to the high current value in this side, and the drop voltage. In this chapter and in the next chapter the network in low voltage will be studied. We measured the load ( Real Power, Current for each phase, power factor) for each feeder of each transformer in max. and min. case.
  • 41. Max. Case Improvement at Low Voltage Side The load at each feeder for some trasformers :
  • 42. After making analysis for the original Max. Case, the result is shown below : Max. Case Improvement at Low Voltage Side
  • 43.  Swing Bus Result :  Summary of total generation, loading and demand : Max. Case Improvement at Low Voltage Side
  • 44.
  • 45. Max. Case Improvement at Low Voltage Side The main problem in the low level side is the unsymmetrical loads between phases which cases many problems : - High neutral current. - High drop voltage in feeder which cases low voltage in the consumers. -High losses in the network - The losses before adding the low voltage side = 0.017 MW. - The losses after adding the low voltage side = 0.178 MW.
  • 46. Max. Case Improvement at Low Voltage Side  Increase the tap ratio of the Transformers to 5 % :
  • 47.  Swing Bus Result :  Summary of total generation, loading and demand : Max. Case Improvement at Low Voltage Side After making analysis for the original Max. Case, the result is shown below :
  • 48. After changing the taps of the transformers the voltage in the consumers increased, also the voltage drop in the feeders decrease and the losses in the network decrease.
  • 49. Power Factor Improvement : The result of load flow after after adding the capacitor banks :
  • 50.  Swing Bus Result :  Summary of total generation, loading and demand : Max. Case Improvement at Low Voltage Side After making analysis for the original Max. Case, the result is shown below :
  • 51. After increasing the tap ratio and adding the capacitor banks the losses in the network decrease : - The losses before= 0.178 MW. - The losses after=0.160 MW .
  • 52.  The voltage level improvement : Max. Case Improvement at Low Voltage Side
  • 53.  Swing Bus Result :  Summary of total generation, loading and demand : Max. Case Improvement at Low Voltage Side
  • 54. After adding the capacitor banks the losses in the network decrease : - The losses in the original case = 0.178 MW. - The losses after =0.175 MW. The voltage level in some buses increase.
  • 55. Min. Case Improvement at Low Voltage Side The load at each feeder for some trasformers :
  • 56. After making analysis for the original Min. Case, the result is shown below : Min. Case Improvement at Low Voltage Side
  • 57.  Swing Bus Result :  Summary of total generation, loading and demand : Min. Case Improvement at Low Voltage Side
  • 58. After the analysis : the losses in the network increase more than the losses in the minimum case at the medium voltage: - The losses before = 0.006 MW . - The losses after = 0.53 MW .
  • 59. Min. Case Improvement at Low Voltage Side  Increase the tap ratio of the Transformers to 2.5 % :
  • 60.  Swing Bus Result :  Summary of total generation, loading and demand : Min. Case Improvement at Low Voltage Side After making analysis for the Network, the result is shown below :
  • 61. After changing the taps of the transformers the voltage in the consumers increased, also the voltage drop in the feeders decrease and the losses in the network decrease.
  • 62. Power Factor Improvement : The result of load flow after after adding the capacitor banks :
  • 63.  Swing Bus Result :  Summary of total generation, loading and demand : Min. Case Improvement at Low Voltage Side After making analysis for the Network, the result is shown below :
  • 64. After increasing the tap ratio and adding the capacitor banks the losses in the network decrease : - The losses before= 0.053 MW. - The losses after=0. 050 MW .
  • 65.  The voltage level improvement : Min. Case Improvement at Low Voltage Side
  • 66.  Swing Bus Result :  Summary of total generation, loading and demand : Min. Case Improvement at Low Voltage Side
  • 67. After adding the capacitor banks the losses in the network decrease : - The losses in the original case = 0.053 MW. - The losses after = 0.050 MW. The voltage level in some buses increase.
  • 68. The Economical Study  Saving in Penalties:
  • 69. The Economical Study  Saving in Losses:
  • 70. The Economical Study  Simple Pay Back Period :
  • 71. Sag & Tension Problem in the Network  Calculations of Sag (in general ) : l = Length of span Wt = total weight per unit length of conductor T = Tension in the conductor. W = weight of conductor per unit length Wi = weight of ice per unit length Ww = wind force per unit length
  • 72. Sag & Tension Problem in the Network  The Problem : The problem lies in the poor and an error in the estimation of the amount of sag when designing and extension for overhead lines in some areas, where the amount of sag was not enough, and in the last winter, a large amount of snow and low degrees of temperature led to a contraction in the tensile strength of the cables, this led to cut in the cable and destruction of some of the towers as shown in the below picture:
  • 73. Sag & Tension Problem in the Network  The Recommendations for the sag problem : To avoid the occurrence of the problem that has been raised previously, there is a mathematical relationship whereby estimate and calculate the amount of sag in correct form: This gives the freedom of cable stretch in the summer and contraction in the winter without affecting on the cable and without leads to a cut in it.
  • 74. Solar Energy Station Project  Consumption energy Of the Network :  Data about consumption of the network :
  • 75. Solar Energy Station Project  Calculations of the power for the solar system: The Energy of the network in year = 5716110 KWH/year. The Energy of the network in day = The Energy of the network in year / the number of day in year. The Energy of the network in day = 5716110/365 = 15660.6 KWH/day. The average energy produced of 1KW solar cells = 5.4KWH/m^2.day. We use the penetration factor =20%. Then the total energy of solar system in day = the penetration factor * The Energy of the network in day. The total energy of solar system in day = 15660.6 * 0.2 = 3132.1 KWH/day. Then we calculate the power of the solar system, that will work on the design. The power of the solar system(Ppv in KW) = The total energy of solar system in day/ The average energy produced of 1KW solar cells. P pv (KW) = 3132.1 () /(5.4KWH/m^2.day) = 580 KW. Then we will design the pKWH/dayower of solar system = 580KW.
  • 76. Solar Energy Station Project  How to determine the optimization of Tilt & Azimuth angle : To determine the Tilt and Azimuth angle, we use a link on the Internet, as shown below . (The link: http://re.jrc.ec.europa.eu/pvgis/apps4/pvest.php?map )
  • 77. Solar Energy Station Project  The Result that we obtained from the link : After we entered all necessary data, the results and calculations of this program are shown below : *The optimization tilt angle =26 degree, and the optimum azimuth angle = -6 degree Ed: Average daily electricity production from the given system (kWh) Em: Average monthly electricity production from the given system (kWh) Hd: Average daily sum of global irradiation per square meter received by the modules of the given system (kWh/m2) Hm: Average sum of global irradiation per square meter system (kWh/m2)
  • 78. Solar Energy Station Project The average power produced by the solar system per month is shown in the below figure
  • 79. Solar Energy Station Project  The optimal inclination angle & solar irradiation per month : Optimal inclination angle is: 26 degrees Annual irradiation deficit due to shadowing (horizontal): 0.4 %
  • 80. Solar Energy Station Project The table below and picture shows the optimal inclination angle and irradiation on plane in each month : H(26): Irradiation on plane at angle: 26deg. (Wh/m2/day). Iopt: Optimal inclination (deg.).
  • 81. Solar Energy Station Project  The Design of the solar station system : The Power of this station = 580kw, and we will use two program to design this station . The first program is PV system .
  • 82. Solar Energy Station Project  PV system :
  • 83. Solar Energy Station Project  The Result : After entering all necessary numbers and data and identify options, the program give us the results as shown in the below curves and tables : The below curve show us the System output energy for each month :
  • 84. Solar Energy Station Project  The design of the solar station by using Aurora program : By using the Aurora program in this project, we designed the solar system =580KW ,and we distributed it into 10 groups each group equal to 55KW.  Aurora Designer :
  • 85. Solar Energy Station Project In this design that we work on it, we try to achieve the optimum design (the module in series to achieve the voltage of the inverter , and the parallel string to achieve the power of the inverter , and the oversize of the inverter that we chosen is between (95%-110%)). * The number of the module in series =17 module. * The parallel string =12. The next figure shown how to enter the series module and parallel string in the Aurora program:
  • 86. Solar Energy Station Project  The Result from the Aurora Program : System configuration: Inverter Specifications:
  • 87. Solar Energy Station Project PV Module Data: Array Sizing Parameters:
  • 88. Solar Energy Station Project Voltage and Current Parameter Check:
  • 89. Solar Energy Station Project *But when the parallel string is equal to (11), the new results are shown in the below tables ( and this is more acceptable ):
  • 90. Solar Energy Station Project  The Result : New System configuration: New Voltage and Current Parameter Check:
  • 91. Solar Energy Station Project  Calculations to determine the Rating of the set up Transformer: In this project we distributed the inverter into 10 inverters and the maximum power for each inverter is equal to 55 KW. The maximum power for all inverters is equal to 550 KW The rating of the step up transformer can be calculated by these formulas below
  • 92. Solar Energy Station Project  Economical study for the Solar system project : •The life span period of the solar system = 20 years. •The price of 1kwh of solar = 0.65 NIC. •The price of transformer = 30000 NIC. •The price of each watt =2.2 $ =7.7 NIC. The price of 1 kw =2200$=7700 NIC. * The average of 1kw produce 1700 kwh/year. The investment = Price of the transformer + Price of the solar system (580kw) The investment = 30000 + (580*7700) = 4496000 NIC. •The average producing of the solar system in year = 1700 * 580 = 986000 kwh •The saving in the year = 986000 kwh * 0.65 NIC = 640900 NIC/ year. The simple pay back period = investment / saving in year S.P.B.P = 4496000 / 640900 = 7 YEARS.
  • 93.